JPH0213609A - Steel sheet pile and work method of steel sheet pile wall using it - Google Patents

Steel sheet pile and work method of steel sheet pile wall using it

Info

Publication number
JPH0213609A
JPH0213609A JP16021188A JP16021188A JPH0213609A JP H0213609 A JPH0213609 A JP H0213609A JP 16021188 A JP16021188 A JP 16021188A JP 16021188 A JP16021188 A JP 16021188A JP H0213609 A JPH0213609 A JP H0213609A
Authority
JP
Japan
Prior art keywords
steel sheet
sheet pile
grip
resistance
supporting ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP16021188A
Other languages
Japanese (ja)
Inventor
Shinji Kondo
近藤 伸治
Hiroo Nakagawa
中川 宏夫
Satoshi Matsunaga
聡 松永
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Steel Corp
Original Assignee
Kawasaki Steel Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kawasaki Steel Corp filed Critical Kawasaki Steel Corp
Priority to JP16021188A priority Critical patent/JPH0213609A/en
Publication of JPH0213609A publication Critical patent/JPH0213609A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To decrease grip resistance at the time of driving in and a necessary hanging capacity of a crane without disturbing sheeting and water-stopping capacity, by eliminating a grip on the side which is fit to a preceding steel sheet pile from the bottom end within a range of driving-in length to supporting ground layer. CONSTITUTION:Among grips 4a, 4b arranged on both sides of a steel sheet pile 3, the grip 4a on the side which is fit to a preceding steel sheet pile is eliminated from the bottom end along a specified measure 5 within a range of driving-in of the steel sheet pile 3 to a supporting ground layer. Hanging capacity of a crane can be smaller by an amount corresponding to this specified measure 5. And a length which has to be driven in against grip resistance within a supporting ground where the biggest resistance exists can be reduced by the specified measure 5. In upper ground layer than the supporting ground, grips are fit together and necessary sheeting and water-stopping are performed.

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、河川護岸1港湾岸壁工事等に広く利用され
ている鋼矢板とこれを用いた鋼矢板壁の施工法に関する
DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a steel sheet pile widely used in river revetment and port quay wall construction, and a method of constructing a steel sheet pile wall using the same.

「従来の技術」 周知の通り鋼矢板は第4図a、bに示される如く、両側
端にジヨイント用グリップ2,2を有し、当該グリップ
2.2同志を嵌合させてガイドさせつつ、先行打設の鋼
矢板1に対して後行の同型鋼矢機工を隣接させて打設し
ていき、土留め、止水壁を構築していくものである。
``Prior Art'' As is well known, a steel sheet pile has joint grips 2, 2 at both ends, as shown in FIGS. Steel sheet piles 1 of the same type are placed next to the steel sheet piles 1 that are placed in advance, and earth retaining and water-stop walls are constructed.

叙上のグリップ2.2は止水壁の継目となるので、密嵌
し得るように設計されており、打込み時の抵抗は極めて
大となる。
Since the grip 2.2 mentioned above forms a joint between the water-stop walls, it is designed to fit tightly, and the resistance during driving is extremely large.

ちなみに、鋼矢板打込み時の総抵抗R0の内訳は下記の
如くである。
Incidentally, the breakdown of the total resistance R0 when driving steel sheet piles is as follows.

RO=RG+Rア+R,(長尺矢板の比率)R,ニゲリ
ップ抵抗   平均70% RT:先端抵抗      〃 5% RP:周辺摩擦抵抗    〃15% グリップ抵抗R0がいかに大きなウェイトを占めている
かが判る。
RO = RG + R + R, (ratio of long sheet piles) R, average lip resistance 70% RT: tip resistance 〃 5% RP: peripheral friction resistance 〃 15% It can be seen how much weight the grip resistance R0 occupies.

叙上グリップ抵抗R6については、次記の事項が判明し
ている。
Regarding the grip resistance R6 mentioned above, the following matters have been found.

すなわち、図に於いて、すでに打込まれた通常のU型グ
リップ2,2を有する鋼矢板1に隣接してグリップ同志
を嵌合させて同型鋼矢板1”を打設する場合、打設中の
打込力Pと根入深さhとの関係は、根太深さhがおよそ
6mから非常に大きな打込み力Pを必要とする。
In other words, in the figure, when a steel sheet pile 1'' of the same type is placed adjacent to a steel sheet pile 1 having already driven normal U-shaped grips 2, 2 by fitting the grips together, The relationship between the driving force P and the rooting depth h requires a very large driving force P when the joist depth h is about 6 m.

この理由は、既設鋼矢板1のグリップ内では深さに応じ
て高い密度の土砂が詰まっており、次の鋼矢板1゛を先
の鋼矢板1に嵌合させて打込むと、最初はグリップ内の
土砂密度は小さいので、一部の土砂は鋼矢板1のグリッ
プ開口部より排除され、残りの土砂は嵌合した鋼矢板1
′が侵入するにつれてそのグリップ先端によって下方に
圧縮される。
The reason for this is that the grip of the existing steel sheet pile 1 is filled with earth and sand with a high density depending on the depth, and when the next steel sheet pile 1 is fitted into the previous steel sheet pile 1 and driven in, the grip initially Since the soil density inside the steel sheet pile 1 is small, some of the soil is removed from the grip opening of the steel sheet pile 1, and the remaining soil is removed from the fitted steel sheet pile 1.
As it penetrates, it is compressed downward by its grip tip.

さらに打込みを続けるとグリップ内の土砂は脱水され空
隙がほとんどなくなり、真比重に近くなるほどの圧縮を
受ける。この状態となる位置は、土質、打込み条件等に
よって異なるが、鋼矢板1゛の先端が6mを通過した時
点から打込み力Pが大きくなることから鋼矢板1゛の先
端下にある鋼矢板1のグリップ内土砂密度は相当高くな
っている。
As driving continues, the soil within the grip becomes dehydrated, leaving almost no voids, and is compressed to the point that it approaches its true specific gravity. The position at which this state occurs varies depending on the soil quality, driving conditions, etc., but since the driving force P increases from the point when the tip of the steel sheet pile 1'' passes 6 m, the position where the steel sheet pile 1 below the tip of the steel sheet pile 1'' increases. The sediment density inside the grip is quite high.

しかして、後行の鋼矢板1゛は先行の鋼矢板1のグリッ
プ内に閉じ込められた高密度土砂中を押し進まねばなら
ず、大なる抵抗を占めるものとなっている。
Therefore, the trailing steel sheet pile 1' has to push through the high-density earth and sand trapped in the grip of the leading steel sheet pile 1, which creates a large amount of resistance.

畝上の高抵抗については、グリップが脆弱であると、嵌
合状態にあるべき鋼矢板のグリップが開口し、連結が外
れて、土砂の流出を生じるので、従来より、例えば特開
昭63−83313号の如く、グリップの強度を高める
提案が種々なされているのが実情である。
Regarding high resistance on ridges, if the grip is weak, the grip of the steel sheet pile that should be in the fitted state will open, the connection will come off, and earth and sand will flow out. The reality is that various proposals have been made to increase the strength of the grip, such as No. 83313.

「発明が解決しようとする課題j しかし、鋼矢板の打込み時の高抵抗についての対策とし
てグリップの強度を高めるという従来の仕方は、実際の
施工事情からして、合理的ではない。
``Problem to be solved by the inventionj'' However, the conventional method of increasing the strength of the grip as a countermeasure to the high resistance when driving steel sheet piles is not rational in view of the actual construction situation.

つまり、既述の如く鋼矢板l”の先端下Qこある鋼矢v
i1のグリップ内土砂密度が相当高くなるが、この傾向
は鋼矢板が貫入しなければならない支持地盤層では一層
顕著になるはずであるが、当該支持地盤層では、土留め
能も止水能も側段必要とされることがなく、土留め、上
水は鋼矢板が根入れされる支持地盤層上層の軟弱、透水
地盤層にて必要とされる事項であり、畝上従来手段にあ
っては、支持地盤層に於いて不必要な困難を何ら解消し
ていないからである。
In other words, as mentioned above, there is a steel arrow v below the tip of the steel sheet pile l''.
The soil density in the grip of i1 becomes considerably high, and this tendency should be even more pronounced in the supporting ground layer where the steel sheet pile must penetrate, but the supporting ground layer has neither earth retaining ability nor water stopping ability. There is no need for side berms, and earth retaining and water supply are necessary due to the soft upper layer of the supporting ground layer in which the steel sheet piles are embedded, and the permeable ground layer, and are not possible with conventional methods on ridges. This is because no unnecessary difficulties have been resolved in the supporting ground layer.

抵抗解消がなされない結果、鋼矢板の長尺化に伴い、グ
リップ抵抗が増大し、共下り等の施工トラプルが頻発し
ている。
As a result of unresolved resistance, grip resistance increases as steel sheet piles become longer, resulting in frequent construction problems such as when descending.

尚、鋼矢板の長尺化については、後行鋼矢板の嵌合にあ
たり、クレーンに、吊り込み能力の大きさ(背の高い)
が要求されることとなる結果、能力不足による転倒事故
が多発している。
In addition, regarding the lengthening of steel sheet piles, when fitting the trailing steel sheet piles, the size of the crane's lifting capacity (tall)
As a result, there are many falls accidents due to lack of ability.

本発明は、畝上の事情に鑑み、最も過酷な打込み抵抗が
発現する支持地盤層部に於ける抵抗を激減させるも所望
の土留め、止水能は確保することができる鋼矢板及びこ
れを用いた鋼矢板壁の施工法を提供することを目的とし
ている。
In view of the situation on ridges, the present invention has developed a steel sheet pile that can drastically reduce the resistance in the supporting ground layer where the most severe driving resistance occurs, yet still maintain the desired soil retaining and water-stopping ability. The purpose of this study is to provide a construction method for steel sheet pile walls.

「課題を解決するための手段」 上記目的を達成するために、本発明の鋼矢板においては
、先行の鋼矢板に嵌合する側のグリップを、下端より支
持地盤層根入れの範囲内にて削除するものとしたもので
ある。
"Means for Solving the Problem" In order to achieve the above object, in the steel sheet pile of the present invention, the grip on the side to be fitted to the preceding steel sheet pile is moved from the lower end within the range of penetration of the supporting ground layer. It has been decided that it will be deleted.

また、かかる鋼矢板を用いて、先行鋼矢板に対して下端
を削除した後行鋼矢板のグリップを嵌合させていき、鋼
矢板壁を施工するとしたものである。
Further, using such steel sheet piles, a grip of a trailing steel sheet pile whose lower end has been removed is fitted to the leading steel sheet pile to construct a steel sheet pile wall.

「作用」 上記のように構成された鋼矢板では、グリップが削除さ
れた支持地盤層ではグリップ間の嵌合がないので、グリ
ップ抵抗が発現しない。
"Operation" In the steel sheet pile configured as described above, since there is no fitting between the grips in the supporting ground layer where the grips have been removed, grip resistance does not occur.

しかし、当該支持地盤より上層の地層にあっては、グリ
ップ間の嵌合がなされであるので、所定の土留め、止水
は果たされる。
However, in the strata above the supporting ground, the grips are only fitted, so that the specified earth retention and water stoppage can be achieved.

また、後行の鋼矢板を嵌合させるに際してはグリップ削
除分、嵌合位置が下がるので、クレーンについて要求さ
れる吊り込み能力は小さくなる。
Furthermore, when fitting the trailing steel sheet pile, the fitting position is lowered by the amount of grip removed, so the lifting capacity required of the crane becomes smaller.

「実施例」 実施例について図面を参照して説明すると、第1回は断
面U形の鋼矢板3に於ける本発明の実施態様を示し、両
側に設けられたグリップ4a、 4bのうち、先行の鋼
矢板に嵌合する側のグリップ4aは下端より所定寸法5
にわたって削除されている。
"Example" To explain an example with reference to the drawings, the first part shows an embodiment of the present invention in a steel sheet pile 3 having a U-shaped cross section, and the grips 4a and 4b provided on both sides are The grip 4a on the side that fits into the steel sheet pile has a predetermined size 5 from the lower end.
has been deleted over the years.

当該所定寸法5は鋼矢板3の支持地盤層根入れ範囲内に
設定される。
The predetermined dimension 5 is set within the support ground layer penetration range of the steel sheet pile 3.

第2図は、かかる鋼矢板3を用いての鋼矢板壁6の施工
態様を示す。図示の如く、後行の鋼矢板3′は先行の鋼
矢板3に組付くが、この際のグリップの嵌合は、該所定
寸法5分上方よりなされるので、この分クレーンの吊り
込み能力は小さくてよい。
FIG. 2 shows a construction mode of a steel sheet pile wall 6 using such a steel sheet pile 3. As shown in the figure, the trailing steel sheet pile 3' is assembled to the preceding steel sheet pile 3, but at this time the grip is fitted from above the predetermined distance by 5 minutes, so the lifting capacity of the crane is reduced accordingly. Small is good.

グリップ間の嵌合がなされると、既述の通り、ガイドさ
せつつ打ち込みされ、支持地盤7に根入れされる。
Once the grips are fitted, they are driven into the supporting ground 7 while being guided, as described above.

当該支持地盤7に於いては、所定寸法5分グリップ間嵌
合部の打ち込みが不要上なる。
In the supporting ground 7, it is unnecessary to drive the fitting portion between the grips by a predetermined size of 5 minutes.

つまり、最も高抵抗の支持地盤7中での打ち込みに於い
て、グリップ抵抗のもとて先端を侵入させねばならぬ丈
は所定寸法5だけ少なくて済む。
That is, when driving into the support ground 7 with the highest resistance, the length that the tip must penetrate due to grip resistance can be reduced by the predetermined dimension 5.

かくして、形成された鋼矢壁6は、各鋼矢板の下端部は
支持地盤7に根入れして、しっかりと支持されていると
共に、支持地盤7の上層の軟弱地盤層8にあってはグリ
ップ間の嵌合のもとに連結されて所定の土留め、止水能
を発揮している。
In this way, the formed steel sheet piles 6 are firmly supported by the lower end of each steel sheet pile being embedded in the supporting ground 7, and the soft ground layer 8 above the supporting ground 7 has a grip. They are connected by fitting between them and exhibit a certain earth retaining and water stopping ability.

第3図a −dはU形、Z形、H形、ボックス形各種の
鋼矢板による鋼矢板壁の平面図で、いずれの場合も本発
明を実施することが出来る。
FIGS. 3a to 3d are plan views of steel sheet pile walls made of various U-shaped, Z-shaped, H-shaped, and box-shaped steel sheet piles, and the present invention can be practiced in any of these cases.

「発明の効果」 本発明は、以上説明したように構成されているので、以
下に記載されるような効果を奏する。
"Effects of the Invention" Since the present invention is configured as described above, it produces the effects described below.

グリップ抵抗を発現させる嵌合部の長さが短かくなる結
果、グリップ抵抗が著しく減少し、打込み速度、施工性
が高まる。
As the length of the fitting portion that produces grip resistance is shortened, grip resistance is significantly reduced and driving speed and workability are increased.

さらに、最も抵抗の高い支持地盤層に於ける貫入が無い
ため、打込み容易化は顕著なものとなる。
Furthermore, since there is no penetration into the supporting soil layer, which has the highest resistance, the ease of driving is significant.

打込みに際してのグリップ間嵌合の位置が下がる結果、
クレーンの吊込み能を低くすることが出来、鋼矢板の長
尺化に伴いクレーンの吊り込み能をアップしなければな
らない不便から逸れる。
As a result of lowering the position of the fitting between the grips during driving,
The lifting capacity of the crane can be lowered, thereby avoiding the inconvenience of having to increase the lifting capacity of the crane as steel sheet piles become longer.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図は本発明の鋼矢板の全体図、第2図は本発明鋼矢
板壁の施工態様説明図、第3図a −dは、各種形状の
鋼矢板に於ける本発明実施態様図、第4図a、bは、鋼
矢板の打ち継ぎ説明図である。 1.1”・・・鋼矢板、 2・・・グリップ、 3,3
゛・・・鋼矢板、 4a、 4b・・・グリップ、 5
・・・所定寸法、 6・・・鋼矢板壁、 7・・・支持
地盤、 8・・・軟弱地盤層。 ブゾリA6 a、             b。 C1d。
Figure 1 is an overall view of the steel sheet pile of the present invention, Figure 2 is an explanatory diagram of the construction mode of the steel sheet pile wall of the present invention, Figures 3 a - d are diagrams of embodiments of the present invention in steel sheet piles of various shapes, FIGS. 4a and 4b are explanatory views of the pouring of steel sheet piles. 1.1”...Steel sheet pile, 2...Grip, 3,3
゛...Steel sheet pile, 4a, 4b...Grip, 5
...Predetermined dimensions, 6. Steel sheet pile wall, 7. Supporting ground, 8. Soft ground layer. Busoli A6 a, b. C1d.

Claims (2)

【特許請求の範囲】[Claims] (1)先行の鋼矢板に嵌合する側のグリップを、下端よ
り支持地盤層根入れの範囲内にて削除してなることを特
徴とする鋼矢板。
(1) A steel sheet pile characterized in that the grip on the side that fits into the preceding steel sheet pile is removed from the lower end within the range of penetration of the supporting ground layer.
(2)請求項1記載の鋼矢板に於ける下端を削除したグ
リップを先行鋼矢板のグリップに対して嵌合させて打ち
込みしていくとしたことを特徴とする鋼矢板壁の施工法
(2) A method of constructing a steel sheet pile wall, characterized in that the grip of the steel sheet pile according to claim 1 with its lower end removed is fitted into the grip of the preceding steel sheet pile and driven into the grip.
JP16021188A 1988-06-28 1988-06-28 Steel sheet pile and work method of steel sheet pile wall using it Pending JPH0213609A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16021188A JPH0213609A (en) 1988-06-28 1988-06-28 Steel sheet pile and work method of steel sheet pile wall using it

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16021188A JPH0213609A (en) 1988-06-28 1988-06-28 Steel sheet pile and work method of steel sheet pile wall using it

Publications (1)

Publication Number Publication Date
JPH0213609A true JPH0213609A (en) 1990-01-18

Family

ID=15710153

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16021188A Pending JPH0213609A (en) 1988-06-28 1988-06-28 Steel sheet pile and work method of steel sheet pile wall using it

Country Status (1)

Country Link
JP (1) JPH0213609A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013204273A (en) * 2012-03-28 2013-10-07 Nippon Steel & Sumitomo Metal Construction method of steel sheet pile foundation and steel sheet pile foundation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2013204273A (en) * 2012-03-28 2013-10-07 Nippon Steel & Sumitomo Metal Construction method of steel sheet pile foundation and steel sheet pile foundation

Similar Documents

Publication Publication Date Title
KR100221211B1 (en) Building construction methods and materials
CN102653945A (en) Foundation reinforcing and replacing structure and construction method thereof
CN105672250B (en) A kind of diaphram wall and underwater concrete tongue and groove bindiny mechanism and construction method
CN206721870U (en) A kind of long auger guncreting pile steel reinforcement cage
CN108978635A (en) Synchronous grouting steel sheet pile and using method
JP3658296B2 (en) Ground improvement structure and construction method to control surrounding ground displacement
CN108118689B (en) Prefabricated underground diaphragm wall capable of being partially recycled, lifting appliance and construction method
CN108775009A (en) A kind of measure method preventing grooving spillage and leak
CN102619215A (en) Lock catch type steel pipe pile structure and construction method thereof
JPH0213609A (en) Steel sheet pile and work method of steel sheet pile wall using it
CN109736295A (en) A kind of building structure vertical supporting system and its construction method
CN108221955B (en) Prefabricated underground diaphragm wall capable of being recycled integrally, lifting appliance and construction method
CN110725717A (en) Water plugging structure for ore body roadway
CN215210984U (en) Ride partial reverse construction method underground continuous wall of striding sewage pipe
CN209652911U (en) A kind of building structure vertical supporting system
WO1997034053A1 (en) Pre-cast concrete panel wall
CN207003366U (en) A kind of flood-control wall ruggedized construction
CN109137887A (en) A kind of continuous underground wall structure passing through solution cavity, construction method and suspension device
CN1245849A (en) Dry construction composite filling pile
JPS6128624A (en) Slope-stabilizing construction
CN217923603U (en) Multi-pile combined driving type pile wall supporting structure system
CN218090818U (en) PHC tubular pile with special pile shoe
CN214994003U (en) Small foundation pile adopting steel pipe post grouting
JP2524579B2 (en) Reinforcement method of existing retaining wall under water surface
CN101338559A (en) Underground continuous wall bottom slag removal grouting apparatus and method