JPH0128200B2 - - Google Patents
Info
- Publication number
- JPH0128200B2 JPH0128200B2 JP56112809A JP11280981A JPH0128200B2 JP H0128200 B2 JPH0128200 B2 JP H0128200B2 JP 56112809 A JP56112809 A JP 56112809A JP 11280981 A JP11280981 A JP 11280981A JP H0128200 B2 JPH0128200 B2 JP H0128200B2
- Authority
- JP
- Japan
- Prior art keywords
- steel girder
- steel
- track
- girder
- horizontal hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired
Links
- 229910000831 Steel Inorganic materials 0.000 claims description 44
- 239000010959 steel Substances 0.000 claims description 44
- 239000000463 material Substances 0.000 claims description 11
- 238000000034 method Methods 0.000 claims description 9
- 238000005553 drilling Methods 0.000 claims description 3
- 230000000149 penetrating effect Effects 0.000 claims description 3
- 238000009412 basement excavation Methods 0.000 description 6
- 238000010276 construction Methods 0.000 description 5
- 241001669679 Eleotris Species 0.000 description 4
- 238000007796 conventional method Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 239000011810 insulating material Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 238000012856 packing Methods 0.000 description 1
- 239000002023 wood Substances 0.000 description 1
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Description
【発明の詳細な説明】
本発明は軌道下に該軌道を横断する地下道等の
地下構造物を構築するのに必要な横孔を掘削する
方法に関するものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to a method for excavating a lateral hole under a track necessary for constructing an underground structure such as an underground passage that crosses the track.
踏切事故や道路交通渋滞の対策として、鉄道と
道路とを立体交差にすべき要望が高く、そのため
に、最近では第1,2図に示すような施工が行わ
れている。 As a countermeasure against railroad crossing accidents and road traffic congestion, there is a strong desire to create grade-separated intersections between railways and roads, and to this end, construction projects such as those shown in Figures 1 and 2 have recently been carried out.
即ち、軌道Aを挾んだ計画地下構造物の両側に
立坑B,B′を掘削し、軌道A下の適宜深さの地
盤内に、軌道Aに対して略々直角方向に多数本の
鋼管パイプCを互いに密接状態で並列させて水平
に圧入することによりパイプルーフ防護工を施工
したのち、一方の立坑から他方の立坑に向かつて
側部の土留と鋼管パイプとを支持する支保工Dを
架設しながらトンネルを掘削する方法が実施され
ている。 In other words, vertical shafts B and B' are excavated on both sides of the planned underground structure sandwiching track A, and a large number of steel pipes are installed in the ground at an appropriate depth under track A in a direction approximately perpendicular to track A. After constructing pipe roof protection by horizontally press-fitting pipes C in close parallel to each other, shoring D is installed to support the earth retaining and steel pipes on the side from one shaft to the other. A method is being implemented in which the tunnel is excavated while the tunnel is being constructed.
しかしながら、この方法によれば、鋼管パイプ
を地中に埋設するので、軌条と鋼管パイプ間に一
定以上の土被Eが必要となり、その分だけ地下構
造物を深く構築しなければならず、従つて、該構
造物への進入スロープFは急勾配になるかスロー
プ部が長くなり、又、鋼管パイプは撤去できない
ために建設費が高くなる欠点があつた。 However, according to this method, since the steel pipe is buried underground, a certain amount of earth cover E is required between the rail and the steel pipe, and the underground structure must be built that much deeper. As a result, the slope F for entering the structure becomes steep or the slope portion becomes long, and the construction cost increases because the steel pipes cannot be removed.
本発明はこのような欠点をなくすために、パイ
プルーフ防護工を形成することなく、軌道の下面
を複数本の鋼製桁材で支持させ、この鋼製桁材の
下面側地盤に横孔を掘削することを特長とする土
被りを必要としない軌道下における横孔掘削法を
提供するものである。 In order to eliminate such drawbacks, the present invention supports the lower surface of the track with a plurality of steel girder members without forming a pipe roof protection work, and horizontal holes are formed in the ground on the lower surface side of the steel girder members. The present invention provides a method for excavating a horizontal hole under a track that does not require earth covering.
本発明の実施例を図面について説明すると、軌
条1と該軌条1,1を支持する枕木2,2とから
なる軌道下の道床バラスト3を各枕木2,2間に
おいて軌条1に対し直角方向に掘削して第9図に
示すように、道床バラスト3の両側面間に貫通す
る複数条の溝aを軌道の所定長さ部分に設ける。 To explain an embodiment of the present invention with reference to the drawings, a track bed ballast 3 under the track consisting of a rail 1 and sleepers 2, 2 supporting the rails 1, 1 is placed between each sleeper 2, 2 in a direction perpendicular to the rail 1. As shown in FIG. 9, a plurality of grooves a penetrating between both sides of the track bed ballast 3 are formed in a predetermined length portion of the track by excavation.
この際、必要に応じて路盤4をも掘削してもよ
い。次いで、この掘削溝底面にモルタル5を敷均
したのち、各溝aに溝aの深さよりもやゝ低いH
型鋼製桁材6を路盤4の全幅に亘つて挿入、敷設
し、さらに、この鋼製桁材6の上面と軌条1の下
面間の隙間部7に鋼製桁材6の上面に沿わせて木
製等の絶縁材料からなる絶縁部材8を挿入し、軌
条1と絶縁部材8とを適宜な締結材9で繋合、固
着すると共に絶縁部材8と鋼製桁材6とをボルト
22等で固定することによつて列車荷重を軌条
1、締結材9、絶縁部材8及び鋼製桁材6を介し
て路盤4に支持させる。 At this time, the roadbed 4 may also be excavated if necessary. Next, after spreading mortar 5 evenly on the bottom of this excavated groove, each groove a has a depth of H that is slightly lower than the depth of groove a.
Insert and lay the shaped steel girder 6 over the entire width of the roadbed 4, and then place it along the upper surface of the steel girder 6 in the gap 7 between the upper surface of the steel girder 6 and the lower surface of the rail 1. Then insert the insulating member 8 made of an insulating material such as wood, connect and secure the rail 1 and the insulating member 8 with a suitable fastener 9, and connect the insulating member 8 and the steel girder 6 with bolts 22 or the like. By fixing, the train load is supported by the roadbed 4 via the rail 1, the fastening material 9, the insulating member 8, and the steel girder 6.
このようにして構築すべき構造物の掘削底面1
1の両端から引いた地盤の崩壊仮想線12,12
の領域内に複数本の並列した鋼製桁材6,6…6
からなるかんざし桁10を構成したのち、鋼製桁
材6の上面適所に軌条1と平行して継ぎ材13を
架設し、この継ぎ材13によつて並列した鋼製桁
材6,6…6を連結して軌道の安定を図る。枕木
2はこの時点で撤去する。 Excavation bottom surface 1 of the structure to be constructed in this way
Hypothetical ground collapse line drawn from both ends of 1 12, 12
A plurality of parallel steel girder members 6, 6...6 in the area of
After constructing the hairpin girder 10, a splice material 13 is constructed in a suitable place on the upper surface of the steel girder material 6 in parallel with the rail 1, and the steel girder materials 6, 6...6 are arranged in parallel by the splice material 13. to stabilize the orbit. Sleeper 2 will be removed at this point.
次に、鋼製桁材群からなるかんざし桁10の両
端側、即ち軌道の両側方の地盤に第5図に示すよ
うに立坑23,23′を築造し、一方の立坑23
から他方の立坑23′に向かつて構造物の断面形
状を有する自走式掘削機14によりかんざし桁1
0の鋼製桁材6と側部土圧を支持しながら路盤4
を掘削する。 Next, vertical shafts 23 and 23' are constructed in the ground on both ends of the hairpin girder 10 made of steel girder groups, that is, on both sides of the track, as shown in FIG.
A self-propelled excavator 14 having the cross-sectional shape of the structure is used to move the hairpin girder 1 toward the other shaft 23'.
0 steel girders 6 and the roadbed 4 while supporting the side earth pressure.
excavate.
自走式掘削機14は第8図に示すように、正面
方形状に組んだ支持枠15を前後方向に配設して
連結してなる移動枠の両側面に複数枚の鋼矢板1
6,16…16を前後摺動自在に取付け、これら
の鋼矢板16に作用する土圧との摩擦力を推進反
力として鋼矢板16と移動支保枠15とを交互に
推進させながら横孔を掘削するものである。 As shown in FIG. 8, the self-propelled excavator 14 has a plurality of steel sheet piles 1 on both sides of a movable frame, which is made up of a support frame 15 assembled in a frontal shape and connected in the front-rear direction.
6, 16...16 are attached so as to be slidable back and forth, and the horizontal hole is drilled while alternately propelling the steel sheet piles 16 and the movable support frame 15 using the frictional force with the earth pressure acting on these steel sheet piles 16 as a propulsion reaction force. It is something to be excavated.
この掘削機14が掘進するに従つて該掘削機1
4の後方横孔部に、第7図に示すように上桁18
と下桁19及び土留柱20,20とからなる支保
工17を組立て、この支保工17によつて鋼製桁
材6と側部土圧とを支持させる。この時、道床バ
ラスト3も同時に除去する。さらに、支保工17
の外側面を、隣接する土留柱20,20の外側部
間に土留矢板21を掛け渡し、係止させることに
より被覆する。 As this excavator 14 digs, the excavator 1
As shown in Fig. 7, the upper girder 18 is inserted into the rear horizontal hole of No.
A shoring 17 consisting of a lower girder 19 and earth retaining columns 20, 20 is assembled, and this shoring 17 supports the steel girder 6 and the lateral earth pressure. At this time, the track bed ballast 3 is also removed at the same time. In addition, shoring 17
The outer surface of the earth retaining sheet pile 21 is spanned between the outer parts of the adjacent earth retaining columns 20, 20, and is locked therewith to cover the outer surface of the earth retaining column.
こうして、掘削機14による路盤4の掘削と支
保工17の架設とを順次行いながら他方の立坑2
3′にまで掘削して軌道下に横孔24を掘削する。 In this way, while the excavator 14 excavates the roadbed 4 and erects the shoring 17 in sequence, the other vertical shaft 2
3' and drill a horizontal hole 24 under the track.
しかるのち、通常の手段により該横孔24内に
通路となる地下構造物を構築し、又、鋼製桁材
6,6間に道床バラストを投入しつつ枕木を敷設
すると共に鋼製桁材6を引き抜いて元の状態にす
る。 Thereafter, an underground structure that will serve as a passage is constructed within the horizontal hole 24 by normal means, and sleepers are laid while placing bed ballast between the steel girders 6 and 6. Pull it out and restore it to its original state.
又、鋼製桁材6の下面が凹凸面となつている場
合には、上桁18と鋼製桁材との間にパツキンを
介在させてその凹凸面を吸収させるようにすれば
よい。 Furthermore, if the lower surface of the steel girder 6 is uneven, a packing may be interposed between the upper girder 18 and the steel girder to absorb the uneven surface.
次に、地下構造物の幅が相当広くてこのような
構造物を構築する横孔を一度に掘削するには大型
の掘削機を要し、その費用が嵩むので、第11図
に示すように前記実施例で述べた掘削方法を横方
向に分割して実施することにより適宜間隔を存し
た横孔24a,24bを立孔間に掘削し、これら
の横孔24a,24bで挾まれた残りの地盤26
をシヨベル等の通常の掘削機で掘削しながら横孔
24a,24bに架設した上桁18a,18bの
対向端部に継ぎ上桁27の両端を接続し、又、横
孔24a,24bの下桁19a,19b間も同様
に下桁28で接続して支保工17a,17bを架
設する。 Next, since the width of the underground structure is quite wide, a large excavator is required to excavate the horizontal holes for constructing such a structure at once, which increases the cost. By performing the excavation method described in the above embodiment by dividing it in the horizontal direction, horizontal holes 24a and 24b with an appropriate interval are excavated between the vertical holes, and the remaining holes sandwiched between these horizontal holes 24a and 24b are ground 26
While excavating with a normal excavator such as a shovel, connect both ends of the upper girder 27 to the opposite ends of the upper girders 18a and 18b built in the horizontal holes 24a and 24b, and connect the lower girders of the horizontal holes 24a and 24b. 19a and 19b are similarly connected by a lower girder 28, and shoring structures 17a and 17b are erected.
この場合、鋼製桁材6,6…6は上桁18a,
18bと継ぎ桁27によつて支持されることにな
り、土留柱20a,20bは上桁18a,18b
と継ぎ桁27の中間支柱となる。 In this case, the steel girders 6, 6...6 are the upper girder 18a,
18b and the joint girder 27, and the earth retaining columns 20a, 20b are supported by the upper girder 18a, 18b.
This becomes the intermediate support of the joint girder 27.
その後は前記実施例と同様にして軌道を元の状
態に復元する。 Thereafter, the trajectory is restored to its original state in the same manner as in the previous embodiment.
以上のように本発明は、掘削すべき横孔の上方
部における軌道に敷設している軌条を支持した各
枕木間の道床バラストに軌道に直交する溝を掘削
し、これらの溝に鋼製桁材を敷設すると共に軌条
下面と鋼製桁材の上面間に絶縁部材を介在させて
軌条を鋼製桁材で支持させ、次いで枕木を撤去し
たのち鋼製桁材の一端側から他端側に向かつて鋼
製桁材の下部地盤に横孔を掘進し、該掘削中の横
孔に孔側壁面の土留矢板と前記鋼製桁材及び側方
土圧を支持するための支保工を架設しながら軌道
下の地盤に横孔を掘削、貫通させることを特徴と
する軌道下における横孔掘削法に係るものである
から、軌条を受止する鋼製桁材は、各枕木間の道
床バラストを掘削することにより形成される溝内
に敷設されるので、その敷設作業は地中に打ち込
む方法に比べて簡単且つ正確に行うことができる
と共に該鋼製桁材の上面に絶縁部材を介して軌条
を直接受止させることができるものであり、この
ように軌条を直接受止した鋼製桁材には土被りが
なく、この鋼製桁材の下面に沿うようにして横孔
を掘削するので、軌条にできるだけ接近させた横
孔を地盤中に掘削することができ、従つて、横孔
に構築する地下構道物への進入スロープを短かく
することができると共にその勾配も緩やかに形成
でき、さらに列車の運行を停止させることなく能
率的に横孔の掘削が可能となつて夜間作業を行う
必要をなくすることができると共にその掘削期間
が短かくてすむので列車の除行期間も短縮できる
ものである。 As described above, the present invention involves excavating grooves perpendicular to the track in the track bed ballast between the sleepers supporting the rail laid on the track above the horizontal hole to be excavated, and inserting steel girders into these grooves. At the same time, an insulating member is interposed between the lower surface of the rail and the upper surface of the steel girder material, and the rail is supported by the steel girder material.Then, after removing the sleepers, the steel girder material is installed from one end to the other. Before proceeding, a horizontal hole is dug in the ground below the steel girder material, and in the horizontal hole being excavated, earth retaining sheet piles on the side wall of the hole and shoring to support the steel girder material and lateral earth pressure are erected. However, since this relates to the method of excavating horizontal holes under the tracks, which is characterized by drilling and penetrating horizontal holes in the ground under the tracks, the steel girders that receive the rails are designed to hold the trackbed ballast between each sleeper. Since it is installed in a trench formed by excavation, the installation work can be done more easily and accurately than the method of driving it into the ground. The steel girder that directly supports the rail in this way has no earth cover, and the horizontal hole is drilled along the bottom surface of the steel girder. , it is possible to drill a horizontal hole into the ground as close as possible to the rail, and therefore it is possible to shorten the approach slope to the underground structure constructed in the horizontal hole, and also to create a gentle slope. In addition, it is possible to efficiently excavate side holes without stopping train operations, eliminating the need for night work, and the excavation period is shortened, which also shortens the running period of trains. It is possible.
又、軌条を受止する鋼製桁材は横孔掘削後に撤
去できるから建設費が安価になり、経済的である
等の特長を有するものである。 Furthermore, since the steel girders that receive the rails can be removed after the horizontal hole is excavated, the construction cost is low and the system is economical.
第1図は従来方法の施工図、第2図はその簡略
縦断正面図、第3図乃至第11図は本発明の実施
例を示すもので、第3図〜第6図はその施工工程
図、第7図は支保工を組立てた状態の簡略縦断正
面図、第8図は自走式掘削機で掘削中の簡略縦断
正面図、第9図は軌条を受止した鋼製桁材部分の
拡大縦断正面図、第10図はその側面図、第11
図は本発明の別な実施例を示す簡略縦断正面図で
ある。
1…軌条、2…枕木、3…道床バラスト、4…
路盤、6…鋼製桁材、8…絶縁部材、14…掘削
機、17…支保工、23,23′…立坑、24…
横孔、25…地下構造物。
Fig. 1 is a construction drawing of the conventional method, Fig. 2 is a simplified longitudinal sectional front view thereof, Figs. 3 to 11 show an embodiment of the present invention, and Figs. 3 to 6 are construction process diagrams. , Figure 7 is a simplified vertical front view of the assembled shoring, Figure 8 is a simplified vertical front view of the excavation being performed with a self-propelled excavator, and Figure 9 is a simplified vertical front view of the steel girder section that receives the rail. Enlarged vertical front view, Fig. 10 is a side view, Fig. 11
The figure is a simplified longitudinal sectional front view showing another embodiment of the present invention. 1...rail, 2...sleeper, 3...trackbed ballast, 4...
Roadbed, 6... Steel girder, 8... Insulating member, 14... Excavator, 17... Shoring, 23, 23'... Vertical shaft, 24...
Horizontal hole, 25...underground structure.
Claims (1)
している軌条を支持した各枕木間の道床バラスト
に軌条に直交する溝を掘削し、これらの溝に鋼製
桁材を敷設すると共に軌条下面と鋼製桁材の上面
間に絶縁部材を介在させて軌条を鋼製桁材で支持
させ、次いで枕木を撤去したのち、鋼製桁材の一
端から他端側に向かつて鋼製桁材の下部地盤に横
孔を掘進し、該掘削中の横孔に孔側壁面の土留矢
板と前記鋼製桁材及び側方土圧を支持するための
支保工を架設しながら軌道下の地盤に横孔を掘
削、貫通させることを特徴とする軌道下における
横孔掘削法。1. In the upper part of the horizontal hole to be excavated, grooves perpendicular to the rails are excavated in the bed ballast between the sleepers that support the rails laid on the track, and steel girders are laid in these grooves, and the bottom surface of the rails is The rail is supported by the steel girder by interposing an insulating member between the upper surface of the steel girder and the steel girder, and after removing the sleepers, the steel girder is moved from one end of the steel girder to the other. A horizontal hole is excavated in the lower ground, and while the earth retaining sheet pile on the side wall of the hole, the steel girder material, and a support to support the lateral earth pressure are erected in the horizontal hole being excavated, the horizontal hole is laid in the ground under the track. A horizontal hole drilling method under the track, which is characterized by drilling and penetrating a hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11280981A JPS5813897A (en) | 1981-07-17 | 1981-07-17 | Drilling of horizontal hole under track |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP11280981A JPS5813897A (en) | 1981-07-17 | 1981-07-17 | Drilling of horizontal hole under track |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS5813897A JPS5813897A (en) | 1983-01-26 |
JPH0128200B2 true JPH0128200B2 (en) | 1989-06-01 |
Family
ID=14596067
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP11280981A Granted JPS5813897A (en) | 1981-07-17 | 1981-07-17 | Drilling of horizontal hole under track |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5813897A (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6016698A (en) * | 1983-07-05 | 1985-01-28 | 日本国有鉄道 | Pipe parallelly arranging method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4919637A (en) * | 1972-06-14 | 1974-02-21 | ||
JPS54160023A (en) * | 1978-06-09 | 1979-12-18 | Uemura Koichi | Tunnel structure and its constructing method |
JPS5617515A (en) * | 1979-07-23 | 1981-02-19 | Nec Corp | Flip-flop circuit |
-
1981
- 1981-07-17 JP JP11280981A patent/JPS5813897A/en active Granted
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS4919637A (en) * | 1972-06-14 | 1974-02-21 | ||
JPS54160023A (en) * | 1978-06-09 | 1979-12-18 | Uemura Koichi | Tunnel structure and its constructing method |
JPS5617515A (en) * | 1979-07-23 | 1981-02-19 | Nec Corp | Flip-flop circuit |
Also Published As
Publication number | Publication date |
---|---|
JPS5813897A (en) | 1983-01-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4009579A (en) | Method for constructing a tunnel or underpass | |
KR20080025478A (en) | None open cut tunnelling method and tunnel | |
KR20130014160A (en) | The tunel execution method | |
KR100509707B1 (en) | None open cut tunnelling of arch type with hume pipe and con'c rib | |
KR20210078779A (en) | Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same | |
JPH0128200B2 (en) | ||
JPH06105025B2 (en) | Reconstruction method for existing underground structures | |
JPH0135160B2 (en) | ||
JPS622116B2 (en) | ||
CN108979641B (en) | Construction method for underground structure | |
JPS584094A (en) | Method of constructing low road cross | |
JP3116098B2 (en) | Construction method for underground structures | |
JP3146333B2 (en) | Tunnel construction method | |
KR100443819B1 (en) | Underway Tunneling Methods of arch typed Triangle Elementary pipe-roof | |
JPS6317999B2 (en) | ||
JP2860751B2 (en) | Construction method of underpass introduction section | |
KR20110101289A (en) | Gradual progress drive tunnel digging method and that component | |
JP4926093B2 (en) | How to build a box structure | |
JP5167578B2 (en) | Construction method for underground structures | |
KR200331521Y1 (en) | None open cut tunnelling of arch type with with hume pipe and con'c rib | |
CZ1392A3 (en) | Method of foundation engineering along a traffic road, for instance soundproof walls | |
JPS6145034B2 (en) | ||
JP4014182B2 (en) | Interconnection element and element construction method | |
JPS6237497A (en) | Pipe beam structure | |
JPH06220872A (en) | Underground beam construction method |