JP7276308B2 - 搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 - Google Patents
搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 Download PDFInfo
- Publication number
- JP7276308B2 JP7276308B2 JP2020216027A JP2020216027A JP7276308B2 JP 7276308 B2 JP7276308 B2 JP 7276308B2 JP 2020216027 A JP2020216027 A JP 2020216027A JP 2020216027 A JP2020216027 A JP 2020216027A JP 7276308 B2 JP7276308 B2 JP 7276308B2
- Authority
- JP
- Japan
- Prior art keywords
- container allocation
- molten steel
- allocation
- transport
- evaluation criteria
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- General Factory Administration (AREA)
- Treatment Of Steel In Its Molten State (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Description
図1は、製鋼工場における溶鋼処理の流れを説明するための模式図である。なお、図1では、説明を簡略化するために、製鋼工場100で実施される主要な工程のみを図示している。
図2は、引当計画作成装置の構成例を模式的に示すブロック図である。本実施形態の引当計画作成装置10は、製鋼工場100の溶鋼処理に溶鋼鍋3を効率よく引き当てることが可能な引当計画(搬送容器引当計画)を作成する装置である。図2に示すように、引当計画作成装置10は、ワークステーション等の情報処理装置によって構成され、製鋼データベース(製鋼DB)11と、端末インターフェイス12と、演算部13とを備えている。
ここで、出鋼チャージに溶鋼鍋3を引き当てる際の制約条件について説明する。なお、制約条件は、以下に列記する4つに限定されない。また、引当計画作成装置10が引当計画を作成する際にこれら制約条件が考慮される。
まず、「溶鋼鍋は受鋼した出鋼チャージの鋳造処理後、引当可能時刻まで、次の出鋼チャージを受鋼することができない」という制約条件が挙げられる。引当可能時刻は、上述した次引当可能時刻と同義である。
次に、「特定の出鋼チャージには、一定時間、空の状態で冷えた溶鋼鍋(冷鍋という)を使えない」という制約条件が挙げられる。特定の出鋼チャージであるか否かは、二次精錬設備110の通過処理工程(通過工程コード)および二次精錬での目標成分に基づいて判断される。また、溶鋼鍋が空の状態で冷えたか否か(冷鍋であるか否か)は、その溶鋼鍋について空の状態が続いた時間が閾値を超えたか否かを判定することにより判断される。なお、この閾値は予め定められた所定値でもよい。
また、「特定の出鋼チャージを受鋼した溶鋼鍋は、溶鋼成分の関係上、次に受鋼できる出鋼チャージが限られる」という制約条件が挙げられる。
さらに、「溶鋼鍋の整備時間は交換される部品によって異なる」という制約条件が挙げられる。ポーラス使用回数、ノズル使用回数、プレート使用回数の増加数は、出鋼チャージの通過工程コード毎に異なり、その分が加算される。そして、使用回数が所定回数に達したタイミングで溶鋼鍋が整備(部品交換)され、その整備内容に応じた整備の時間を要する。交換に必要な時間は部品毎に異なるため、整備時間は交換される部品に応じて変化する。例えば、整備時間は、演算部13が製鋼DB11の交換時間データ(図5に示す)を参照して設定される。
また、制約ではないが、考慮することが望ましい条件(評価基準)がある。評価基準としては、鍋センター130で先に整備を終えた溶鋼鍋3から順に極力引き当てたいという評価基準(第1評価基準)や、オペレータの整備作業負荷の一部期間への集中を避けたいという評価基準(第2評価基準)などが挙げられる。オペレータの整備作業負荷には、鍋センター130でオペレータが溶鋼鍋3の部品交換を行う作業負荷が含まれる。つまり、鍋センター130において、ある特定の時間に部品交換の作業が集中すると、オペレータの整備作業負荷が増大するということが考慮される。
図9は、引当計画作成処理手順を示すフローチャートである。なお、図9に示す引当計画作成処理は引当計画作成装置10によって実施される。
2 溶鋼
3 溶鋼鍋
5 プレート
6 ノズル
7 ポーラス
10 引当計画作成装置
11 製鋼データベース(製鋼DB)
13 演算部
21 端末装置
100 製鋼工場
110 二次精錬設備
111 真空脱ガス設備(RH)
112 取鍋精錬設備(LF)
120 連続鋳造設備
130 鍋センター
Claims (11)
- バッチプロセスの処理単位ごとの生成物を搬送する搬送容器を、該処理単位ごとに引き当てる搬送容器引当計画作成方法において、
搬送容器毎にバッチプロセスの処理単位に引き当てるか否かを表した搬送容器引当ルートを作成するとともに、各搬送容器単独で考慮可能な制約を充足する前記搬送容器引当ルートを搬送容器毎に列挙する搬送容器引当ルート作成ステップと、
少なくとも、使用する搬送容器数の評価値および複数の搬送容器間で考慮が必要な評価基準を含む目的関数と、複数の搬送容器間で考慮が必要な制約と、を含む数理モデルを作成する搬送容器引当モデル作成ステップと、
前記数理モデルの値が小さくなる前記搬送容器引当ルートを搬送容器毎に選択するとともに、当該選択された前記搬送容器引当ルートを解とする複数の解を出力する搬送容器引当最適化計算ステップと、
前記出力された複数の解について、定量化された最終評価基準に基づき、当該最終評価基準が最良に近づく前記解を最終解として出力する最終解出力ステップと
を含むことを特徴とする搬送容器引当計画作成方法。 - 前記搬送容器引当最適化計算ステップにより選択された複数の解について、複数の評価基準を定量的に評価する評価基準確認ステップ、をさらに含み、
前記最終解出力ステップは、前記搬送容器引当最適化計算ステップにより選択された複数の解について、前記評価基準確認ステップにて評価される各評価基準が定量化されたものを組み合わせることにより求まる前記最終評価基準に基づき、前記最終解を出力する
ことを特徴とする請求項1に記載の搬送容器引当計画作成方法。 - 前記搬送容器引当モデル作成ステップは、前記評価基準に前記搬送容器の整備時間を少なくとも含み、前記整備時間の分布を考慮して前記複数の搬送容器間での前記整備時間の重複を評価する
ことを特徴とする請求項2に記載の搬送容器引当計画作成方法。 - 前記搬送容器引当モデル作成ステップは、前記数理モデルをイジングモデルもしくはQUBOに則り作成し、
前記搬送容器引当最適化計算ステップは、アニーリングマシンによって前記複数の解を出力する
ことを特徴とする請求項1から3のいずれか1項に記載の搬送容器引当計画作成方法。 - 前記バッチプロセスは、精錬であり、
前記処理単位は、出鋼チャージであり、
前記生成物は、溶鋼であり、
前記搬送容器は、溶鋼鍋である
ことを特徴とする請求項1から4のいずれか1項に記載の搬送容器引当計画作成方法。 - バッチプロセスの処理単位ごとの生成物を搬送する搬送容器を、該処理単位ごとに引き当てる搬送容器引当計画作成装置において、
搬送容器毎にバッチプロセスの処理単位に引き当てるか否かを表した搬送容器引当ルートを作成するとともに、各搬送容器単独で考慮可能な制約を充足する前記搬送容器引当ルートを搬送容器毎に列挙する搬送容器引当ルート作成手段と、
少なくとも、使用する搬送容器数の評価値および複数の搬送容器間で考慮が必要な評価基準を含む目的関数と、複数の搬送容器間で考慮が必要な制約と、を含む数理モデルを作成する搬送容器引当モデル作成手段と、
前記数理モデルの値が小さくなる前記搬送容器引当ルートを搬送容器毎に選択するとともに、当該選択された前記搬送容器引当ルートを解とする複数の解を出力する搬送容器引当最適化計算手段と、
前記出力された複数の解について、定量化された最終評価基準に基づき、当該最終評価基準が最良に近づく前記解を最終解として出力する最終解出力手段と
を有することを特徴とする搬送容器引当計画作成装置。 - 前記搬送容器引当最適化計算手段により選択された複数の解について、複数の評価基準を定量的に評価する評価基準確認手段、をさらに含み、
前記最終解出力手段は、前記搬送容器引当最適化計算手段により選択された複数の解について、前記評価基準確認手段にて評価される各評価基準が定量化されたものを組み合わせることにより求まる前記最終評価基準に基づき、前記最終解を出力する
ことを特徴とする請求項6に記載の搬送容器引当計画作成装置。 - 前記搬送容器引当モデル作成手段は、前記評価基準に前記搬送容器の整備時間を少なくとも含み、前記整備時間の分布を考慮して前記複数の搬送容器間での前記整備時間の重複を評価する
ことを特徴とする請求項7に記載の搬送容器引当計画作成装置。 - 前記搬送容器引当モデル作成手段は、前記数理モデルをイジングモデルもしくはQUBOに則り作成し、
前記搬送容器引当最適化計算手段は、アニーリングマシンによって前記複数の解を出力する
ことを特徴とする請求項6から8のいずれか1項に記載の搬送容器引当計画作成装置。 - 前記バッチプロセスは、精錬であり、
前記処理単位は、出鋼チャージであり、
前記生成物は、溶鋼であり、
前記搬送容器は、溶鋼鍋である
ことを特徴とする請求項6から9のいずれか1項に記載の搬送容器引当計画作成装置。 - 請求項1から5のいずれか1項に記載の搬送容器引当計画作成方法により作成された搬送容器引当計画を用いて製鉄所の操業を行うことを特徴とする製鉄所の操業方法。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2020216027A JP7276308B2 (ja) | 2020-12-25 | 2020-12-25 | 搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2020216027A JP7276308B2 (ja) | 2020-12-25 | 2020-12-25 | 搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2022101762A JP2022101762A (ja) | 2022-07-07 |
JP7276308B2 true JP7276308B2 (ja) | 2023-05-18 |
Family
ID=82273109
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2020216027A Active JP7276308B2 (ja) | 2020-12-25 | 2020-12-25 | 搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP7276308B2 (ja) |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012123772A (ja) | 2010-11-15 | 2012-06-28 | Jfe Steel Corp | 溶鋼鍋の出鋼引当て方法及び溶鋼鍋の出鋼引当て装置 |
WO2015115467A1 (ja) | 2014-02-03 | 2015-08-06 | Jfeスチール株式会社 | 溶鋼鍋の出鋼引当て方法、製鋼工場の操業方法、及び溶鋼鍋の出鋼引当て装置 |
JP2018190312A (ja) | 2017-05-11 | 2018-11-29 | Jfeスチール株式会社 | 搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 |
JP2020181575A (ja) | 2019-04-23 | 2020-11-05 | 日本製鉄株式会社 | 最適化支援装置、最適化支援方法、プログラムおよび最適化システム |
-
2020
- 2020-12-25 JP JP2020216027A patent/JP7276308B2/ja active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2012123772A (ja) | 2010-11-15 | 2012-06-28 | Jfe Steel Corp | 溶鋼鍋の出鋼引当て方法及び溶鋼鍋の出鋼引当て装置 |
WO2015115467A1 (ja) | 2014-02-03 | 2015-08-06 | Jfeスチール株式会社 | 溶鋼鍋の出鋼引当て方法、製鋼工場の操業方法、及び溶鋼鍋の出鋼引当て装置 |
JP2018190312A (ja) | 2017-05-11 | 2018-11-29 | Jfeスチール株式会社 | 搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 |
JP6724858B2 (ja) | 2017-05-11 | 2020-07-15 | Jfeスチール株式会社 | 搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 |
JP2020181575A (ja) | 2019-04-23 | 2020-11-05 | 日本製鉄株式会社 | 最適化支援装置、最適化支援方法、プログラムおよび最適化システム |
Also Published As
Publication number | Publication date |
---|---|
JP2022101762A (ja) | 2022-07-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2017088674A1 (zh) | 一种面向全流程生产的炼钢组批与排产方法 | |
US20110258087A1 (en) | Analytics for setting up strategic inventory systems to handle small lot orders in the steel industry | |
JP6724858B2 (ja) | 搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 | |
JP5786724B2 (ja) | 製鋼プロセスの操業スケジュール作成方法、製鋼プロセスの操業スケジュール作成システム、製鋼プロセスの操業方法、及び鋼材の製造方法 | |
JP7276308B2 (ja) | 搬送容器引当計画作成方法、搬送容器引当計画作成装置、および製鉄所の操業方法 | |
JP5867662B2 (ja) | 溶鋼鍋の出鋼引当て方法、製鋼工場の操業方法、及び溶鋼鍋の出鋼引当て装置 | |
Han et al. | Energy-efficient integration optimization of production scheduling and ladle dispatching in steelmaking plants | |
JP2017211834A (ja) | 計画作成装置、計画作成方法、およびプログラム | |
JP5652069B2 (ja) | 最適チャ−ジ編成装置及び最適チャージ編成方法 | |
JP6070766B2 (ja) | 溶鋼鍋の引当計画作成方法及び引当計画作成装置 | |
JP3391261B2 (ja) | 生産計画方法及び装置 | |
JPS62164811A (ja) | 出鋼・鋳造の操業計画策定方法 | |
JPH10143567A (ja) | スケジュ−リング装置 | |
JP6904157B2 (ja) | 操業スケジュール作成方法、装置及びプログラム | |
CN112926828B (zh) | 一种面向中厚板产线的炼钢生产数据解析与优化排程方法 | |
JP4473467B2 (ja) | 生産計画立案装置 | |
JP4373275B2 (ja) | 払出計画管理装置及び払出計画管理方法、並びにプログラム | |
JP3705009B2 (ja) | 生産計画作成方法 | |
Welgama et al. | Evaluating options to increase production of a copper smelter aisle: A simulation approach | |
JPS6296611A (ja) | 精錬計画の策定方法 | |
JP3360638B2 (ja) | 鋳造の操業計画策定方法 | |
Xu et al. | A subpopulation-based differential evolution algorithm for scheduling with batching decisions in steelmaking-continuous casting production | |
JP2008156740A (ja) | 溶銑の割り付け方法及びその装置 | |
JP5556028B2 (ja) | 溶銑割り付け方法及びその装置並びに溶銑在庫推移の推定装置 | |
JP3933109B2 (ja) | 製鋼炉の操業方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20220725 |
|
TRDD | Decision of grant or rejection written | ||
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20230331 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20230404 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20230417 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 7276308 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |