JP6999170B2 - Formwork for pit construction and pit construction method - Google Patents

Formwork for pit construction and pit construction method Download PDF

Info

Publication number
JP6999170B2
JP6999170B2 JP2018054581A JP2018054581A JP6999170B2 JP 6999170 B2 JP6999170 B2 JP 6999170B2 JP 2018054581 A JP2018054581 A JP 2018054581A JP 2018054581 A JP2018054581 A JP 2018054581A JP 6999170 B2 JP6999170 B2 JP 6999170B2
Authority
JP
Japan
Prior art keywords
formwork
pit
concrete
formwork body
pit construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018054581A
Other languages
Japanese (ja)
Other versions
JP2019167697A (en
Inventor
一郎 妹川
Original Assignee
妹川建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 妹川建設株式会社 filed Critical 妹川建設株式会社
Priority to JP2018054581A priority Critical patent/JP6999170B2/en
Publication of JP2019167697A publication Critical patent/JP2019167697A/en
Application granted granted Critical
Publication of JP6999170B2 publication Critical patent/JP6999170B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

本発明は、掘削穴に設置された型枠本体が打設されたコンクリート硬化後に埋殺しされるピット構築用型枠およびピット構築方法に関するものである。 The present invention relates to a pit-building formwork and a pit-building method in which a formwork body installed in an excavation hole is buried after the concrete is placed and hardened.

車両の整備工場では、車両の底面部分を整備・修理するために、車両を床面から上昇させるリフト装置や、車両の重量を測定する重量計、ブレーキ、速度計などの検査を行うための試験機などの各種機器が、床面から掘り下げたピットに設置される。
これらの機器を設置するときには、床面から掘り下げた掘削穴に、ピットの空間を確保するための枠をコンクリートにより形成し、枠と掘削穴の周壁との間にコンクリートを打設してピットを形成する。
このようなピットの構築に関連する技術として、給油装置を設置するものではあるが、特許文献1に記載されたものが知られている。
At a vehicle maintenance shop, tests are conducted to inspect lift devices that raise the vehicle from the floor, weight scales that measure the weight of the vehicle, brakes, speedometers, etc. in order to maintain and repair the bottom part of the vehicle. Various equipment such as machines will be installed in the pit dug down from the floor.
When installing these devices, a frame for securing space for the pit is formed from concrete in the excavation hole dug down from the floor, and concrete is placed between the frame and the peripheral wall of the excavation hole to form the pit. Form.
As a technique related to the construction of such a pit, although a refueling device is installed, the one described in Patent Document 1 is known.

特許文献1に記載の給油装置は、鋼製の矩形枠による鋼製ピットの上端が顕出するように、アイランド内に埋設する転倒防止部材としての鋼製ピットをアンカーボルトでベットに締結し、ベットとハウジング本体とはボルトで締結することで、ハウジング本体をベットを介してアイランド上に設置するようにとしたものである。 In the refueling device described in Patent Document 1, a steel pit as a fall prevention member to be buried in the island is fastened to the bed with anchor bolts so that the upper end of the steel pit by the steel rectangular frame is exposed. By fastening the bed and the housing body with bolts, the housing body is installed on the island via the bed.

特許文献1に記載の給油装置では、アイランド内にピットを形成するのに、鋼製の矩形枠による鋼製ピットを型枠として使用し、コンクリート硬化後に鋼製ピットがそのまま埋め殺しされ、その上端が顕出するようにアイランド内に埋設される、と記載されている。 In the refueling device described in Patent Document 1, a steel pit made of a rectangular steel frame is used as a formwork to form a pit in the island, and the steel pit is buried as it is after the concrete is hardened, and the upper end thereof is filled. It is stated that it will be buried in the island so that it will be exposed.

特許第3975687号公報Japanese Patent No. 3975678

ここで、ピットに機器が設置される従来のピット構築方法を図面に基づいて説明する。
図5(A)に示すように、掘削穴Dの底面D1に鉄筋Rを配筋し、コンクリートを打設して、図5(B)に示すように、底盤P1を形成して平坦面を形成する。
次に、図5(C)に示すように、底盤P1上に木製の板材などでピットの周壁を形成するための周壁用型枠Fを形成し、この周壁用型枠Fにコンクリートを打設する。このとき、ピットとなる周壁用型枠Fの縁部にアングルと称されるL字状金具Aを設置しておく。
そして、図5(D)に示すように、掘削穴Dの周壁D2と周壁用型枠Fとの間にコンクリートを打設することで、コンクリートが囲う、機器が設置されるピットPが形成される。
Here, a conventional pit construction method in which equipment is installed in the pit will be described with reference to the drawings.
As shown in FIG. 5 (A), a reinforcing bar R is arranged on the bottom surface D1 of the excavation hole D, concrete is poured, and as shown in FIG. 5 (B), a bottom plate P1 is formed to form a flat surface. Form.
Next, as shown in FIG. 5C, a peripheral wall formwork F for forming a peripheral wall of the pit is formed on the batholith P1 with a wooden plate or the like, and concrete is poured into the peripheral wall formwork F. do. At this time, an L-shaped metal fitting A called an angle is installed at the edge of the peripheral wall formwork F which is a pit.
Then, as shown in FIG. 5 (D), by placing concrete between the peripheral wall D2 of the excavation hole D and the peripheral wall formwork F, a pit P in which the concrete is surrounded and the equipment is installed is formed. The concrete.

しかし、この従来のピット構築方法では、2回のコンクリートの打設が必要である。図5に示す例では、同図(B)の底盤P1のためのコンクリートを打設すると、その硬化を待たなければ、同図(C)の打設用型枠Fの設置ができないため、かなりの時間を要する。 However, this conventional pit construction method requires two concrete placements. In the example shown in FIG. 5, when the concrete for the batholith P1 in the figure (B) is placed, the casting formwork F in the figure (C) cannot be installed without waiting for the hardening. It takes time.

そこで本発明は、工期の短縮を図ることができるピット構築用型枠およびピット構築方法を提供することを目的とする。 Therefore, an object of the present invention is to provide a pit construction formwork and a pit construction method capable of shortening the construction period.

本発明のピット構築用型枠は、床面の掘削穴に設置され、機器が設置されるピットを囲む枠部材により形成された型枠本体が、打設されたコンクリート硬化後に埋殺しされるものであり、前記型枠本体に、前記型枠本体と前記掘削穴の底面との間に隙間を空けるための高さ位置決め部材が設けられていることを特徴とする。 The formwork for pit construction of the present invention is installed in an excavation hole on the floor surface, and the formwork body formed by the frame member surrounding the pit in which the equipment is installed is buried after the cast concrete is hardened. The formwork body is provided with a height positioning member for opening a gap between the formwork body and the bottom surface of the excavation hole.

本発明のピット構築方法は、床面の掘削穴に設置され、機器が設置されるピットを囲む枠部材により形成された型枠本体が、打設されたコンクリート硬化後に埋殺しされるピット構築用型枠を用いた方法において、前記型枠本体の下方に隙間を空けるための高さ位置決め部材が設けられた前記ピット構築用型枠を、掘削穴に配置する工程と、前記型枠本体と前記掘削穴の周壁との間に、前記床面までの高さのコンクリートを打設すると共に、前記型枠本体の内側に前記掘削穴の底盤となる厚みのコンクリートを打設する工程と、
前記コンクリートを硬化させる工程とを含むことを特徴とする。
The pit construction method of the present invention is for pit construction in which a formwork body formed by a frame member that is installed in a drilling hole on a floor surface and surrounds a pit in which equipment is installed is buried after the placed concrete is hardened. In the method using a formwork, a step of arranging the pit construction formwork provided with a height positioning member below the formwork body in a drilling hole, and the formwork body and the above. A step of placing concrete up to the floor surface between the peripheral wall of the drilling hole and a step of placing concrete having a thickness to be the bottom of the drilling hole inside the formwork body.
It is characterized by including a step of hardening the concrete.

本発明によれば、型枠本体と掘削穴の底面との間に隙間を空けるための高さ位置決め部材が、型枠本体に設けられているため、掘削穴に型枠本体を設置してコンクリートを打設するだけで、型枠本体の下方に底盤の厚みの層ができるため、硬化すると底盤が形成できる。また、型枠本体の外側にコンクリートが打設されることで、型枠本体の周囲部に床面を形成することができる。従って、一度の打設工程にてコンクリートの打設を完了することができる。 According to the present invention, since the formwork body is provided with a height positioning member for opening a gap between the formwork body and the bottom surface of the excavation hole, the formwork body is installed in the excavation hole and concrete. Since a layer with the thickness of the bottom plate is formed under the formwork body just by placing the bottom plate, the bottom plate can be formed when it is hardened. Further, by placing concrete on the outside of the formwork body, a floor surface can be formed around the formwork body. Therefore, the concrete casting can be completed in one casting process.

前記高さ位置決め部材を、前記型枠本体の下端に設けられた足部とすることができる。足部により掘削穴の底面からの型枠本体の位置決めすることで、ピットの底盤の厚みを容易に調整することができる。 The height positioning member can be a foot portion provided at the lower end of the formwork body. By positioning the formwork body from the bottom of the excavation hole with the foot, the thickness of the bottom of the pit can be easily adjusted.

前記高さ位置決め部材を、前記型枠本体の上端に連結して前記掘削穴に前記型枠本体を吊り下げる吊り下げ部とすることができる。型枠本体を掘削穴に吊り下げるだけで、掘削穴の底面の状態に関係なく型枠本体の高さの位置決めを行うことができる。 The height positioning member can be connected to the upper end of the formwork body to form a hanging portion for suspending the formwork body in the excavation hole. By simply suspending the formwork body from the excavation hole, the height of the formwork body can be positioned regardless of the state of the bottom surface of the excavation hole.

前記型枠本体の上端および下端のいずれか一方、または両方には、外向きのフランジ部が形成されていると、コンクリートがフランジ部の間に入り込み、しっかりと保持されるため、型枠本体をコンクリートに強固に固定することができる。また、型枠本体の上端にフランジ部が形成されていれば、ピットの開口縁部を補強することができる。 If an outward flange portion is formed on either one or both of the upper end and the lower end of the formwork body, concrete enters between the flange portions and is firmly held, so that the formwork body is held firmly. Can be firmly fixed to concrete. Further, if the flange portion is formed at the upper end of the form body, the opening edge portion of the pit can be reinforced.

前記型枠本体の外壁との間に隙間を空けた状態でフランジ部同士を接続する補強部が形成されていると、型枠本体の枠部材単体の曲がりや捩れを抑止すると共に、コンクリートがフランジ部の間に入り込む際に、外壁と補強部との間にコンクリートが入り込むため、型枠本体を更にコンクリートに強固に固定することができる。 If a reinforcing portion for connecting the flange portions is formed with a gap between the outer wall of the formwork body and the outer wall of the formwork body, the frame member of the formwork body is prevented from bending or twisting, and the concrete is flanged. Since concrete enters between the outer wall and the reinforcing portion when entering between the portions, the formwork body can be further firmly fixed to the concrete.

前記フランジ部は、外向き部分と、前記外向き部分の先端に形成され、前記型枠本体の上端であれば下方に向かう下向き部分、前記型枠本体の下端であれば上方に向かう上向き部分とを備えることができる。
コンクリートを打設したときに、コンクリートがフランジ部の内側に抱き込まれるように入り込むため、フランジ部をより強固にコンクリートと固着させることができる。
The flange portion is formed at the outward portion and the tip of the outward portion, and is a downward portion facing downward at the upper end of the formwork body and an upward facing portion at the lower end of the formwork body. Can be provided.
When the concrete is placed, the concrete enters the inside of the flange portion so as to be embraced, so that the flange portion can be more firmly fixed to the concrete.

本発明によれば、型枠本体の外側にコンクリートが打設されることで、型枠本体の周囲部に床面を形成することができるので、一度の打設工程にてコンクリートの打設を完了することができる。従って、工期の短縮を図ることができる。 According to the present invention, since concrete is placed on the outside of the formwork body, a floor surface can be formed around the formwork body, so that the concrete can be placed in one casting process. Can be completed. Therefore, the construction period can be shortened.

本発明の実施の形態1に係るピット構築用型枠を示す斜視図である。It is a perspective view which shows the formwork for pit construction which concerns on Embodiment 1 of this invention. (A)から(D)は、図1に示すピット構築用型枠を用いたピット構築方法の各工程を説明するための図である。(A) to (D) are diagrams for explaining each process of the pit construction method using the pit construction form shown in FIG. 1. 本発明の実施の形態1に係るピット構築用型枠の変形例を説明するための図であり、型枠本体の枠部材の断面図である。It is a figure for demonstrating the modification of the formwork for pit construction which concerns on Embodiment 1 of this invention, and is sectional drawing of the frame member of the formwork body. 本発明の実施の形態2に係るピット構築用型枠を示す図である。It is a figure which shows the formwork for pit construction which concerns on Embodiment 2 of this invention. (A)から(E)は、従来のピット構築方法の各工程を説明するための図である。(A) to (E) are diagrams for explaining each process of the conventional pit construction method.

(実施の形態1)
本発明の実施の形態1に係るピット構築用型枠を図面に基づいて説明する。
図1に示すようにピット構築用型枠10は、床面の掘削穴に設置され、打設されたコンクリート硬化後に埋殺しされ、機器が設置されるピットを構築するための型枠である。ピット構築用型枠10は、機器が設置されるピットを囲む板状部材により形成された鋼製の型枠本体20を有している。
(Embodiment 1)
The pit construction formwork according to the first embodiment of the present invention will be described with reference to the drawings.
As shown in FIG. 1, the pit construction formwork 10 is a formwork for constructing a pit that is installed in an excavation hole on a floor surface, is buried after the cast concrete is hardened, and equipment is installed. The pit construction formwork 10 has a steel formwork body 20 formed of a plate-shaped member surrounding the pit in which the equipment is installed.

型枠本体20は、本実施の形態1では平面視矩形状に形成されている。型枠本体20は、各辺に対応する板状部材により形成された枠部材20p同士がナットとボルトにより連結されている。
枠部材20pの上下方向の長さは、後述するアジャスターボルトを掘削穴に立設したときに、型枠本体20の上端20tが掘削穴の開口位置である床面と同じ位置となる長さに形成されている。
In the first embodiment, the formwork body 20 is formed in a rectangular shape in a plan view. In the formwork body 20, frame members 20p formed of plate-shaped members corresponding to each side are connected to each other by nuts and bolts.
The vertical length of the frame member 20p is such that when the adjuster bolt described later is erected in the excavation hole, the upper end 20t of the form body 20 is at the same position as the floor surface where the excavation hole is opened. It is formed.

型枠本体20(枠部材20p)の上端20tには、外向きのフランジ部22が形成されている。また、型枠本体20の下端20bにも、外向きのフランジ部23が形成されている。
フランジ部22とフランジ部23との間には、矩形板材による補強部24が、フランジ部22とフランジ部23とに両端部を接続し、型枠本体20の外壁21との間に隙間を空けた状態で形成されている。
型枠本体20の隣接する双方の枠部材20pには、筋交い部25がボルトとナットとにより連結されている。従って、外側から枠部材20pおよび筋交い部25を挿通するボルトから、ボルトにねじ込まれた内側のナットを取り外すことで、この筋交い部25が取り外し可能である。
An outward flange portion 22 is formed at the upper end 20t of the form main body 20 (frame member 20p). Further, an outward flange portion 23 is also formed on the lower end 20b of the formwork main body 20.
Between the flange portion 22 and the flange portion 23, a reinforcing portion 24 made of a rectangular plate material connects both ends to the flange portion 22 and the flange portion 23, and leaves a gap between the flange portion 22 and the outer wall 21 of the formwork body 20. It is formed in a state of being.
The brace portion 25 is connected to both adjacent frame members 20p of the form body 20 by bolts and nuts. Therefore, the brace portion 25 can be removed by removing the inner nut screwed into the bolt from the bolt through which the frame member 20p and the brace portion 25 are inserted from the outside.

型枠本体20の下端20bに、高さ位置決め部材として機能する足部となるアジャスターボルト30が設けられている。このアジャスターボルト30は、型枠本体20を、少なくとも底盤の厚み以上の高さに位置させる長さを有する。 An adjuster bolt 30 that serves as a foot portion that functions as a height positioning member is provided at the lower end 20b of the formwork body 20. The adjuster bolt 30 has a length that positions the formwork body 20 at a height equal to or higher than the thickness of the batholith.

以上のように構成された本発明の実施の形態1に係るピット構築用型枠を用いたピット構築方法を図面に基づいて説明する。
まず、作業者は、型枠本体20の枠部材20pを分解した状態で車両に搭載して、設置場所まで運搬する。そして、作業者は、設置場所にて枠部材20pをナットとボルトにより連結して型枠本体20を組み立てる。型枠本体20は分解できるため運搬が容易である。
次に、図2(A)に示すように、配筋工程にて、床面から掘り下げた掘削穴Dの底面D1に、底盤およびピットの周囲部を補強する鉄筋Rを配筋する。
A pit construction method using the pit construction formwork according to the first embodiment of the present invention configured as described above will be described with reference to the drawings.
First, the worker mounts the frame member 20p of the formwork body 20 in a disassembled state on the vehicle and transports it to the installation location. Then, the worker assembles the formwork body 20 by connecting the frame member 20p with nuts and bolts at the installation location. Since the formwork body 20 can be disassembled, it is easy to transport.
Next, as shown in FIG. 2A, in the reinforcing bar arrangement step, reinforcing bars R for reinforcing the bottom plate and the peripheral portion of the pit are arranged on the bottom surface D1 of the excavation hole D dug down from the floor surface.

次に、図2(B)に示すように、設置工程にて、図1に示すピット構築用型枠10が掘削穴Dに配置される。このときのアジャスターボルト30は、型枠本体20の下端20bの位置が定盤の高さ位置となるように調整される。 Next, as shown in FIG. 2B, the pit construction formwork 10 shown in FIG. 1 is arranged in the excavation hole D in the installation process. At this time, the adjuster bolt 30 is adjusted so that the position of the lower end 20b of the formwork body 20 is the height position of the surface plate.

次に、打設工程にて、型枠本体20の外側20o(外壁21と掘削穴Dの周壁D2との間)にコンクリートを打設する。型枠本体20はアジャスターボルト30により下方に隙間ができる。そのため、型枠本体20の外側20oから、型枠本体20の下方を通過させて内側20iにコンクリートを流し込ませることができる。
また、型枠本体20の外側20oからの流し込みで内側20iのコンクリートが不足するときには、型枠本体20の上方から枠内に直接コンクリートを投入して内側20iにコンクリートを打設してもよい。
型枠本体20の内側のコンクリートは、型枠本体20の下端20bの厚みまでとする。外側20oのコンクリートは、掘削穴Dの開口部までの高さとする。
Next, in the placing step, concrete is placed on the outer side 20o of the formwork body 20 (between the outer wall 21 and the peripheral wall D2 of the excavation hole D). The formwork body 20 has a downward gap due to the adjuster bolt 30. Therefore, concrete can be poured from the outer side 20o of the formwork body 20 to the inner side 20i by passing under the formwork body 20.
Further, when the concrete on the inner side 20i is insufficient due to the pouring from the outer side 20o of the formwork main body 20, concrete may be directly poured into the frame from above the formwork main body 20 and the concrete may be poured on the inner side 20i.
The concrete inside the formwork body 20 is up to the thickness of the lower end 20b of the formwork body 20. The concrete on the outer side 20o has a height up to the opening of the excavation hole D.

これにより、コンクリートは、内側20iでは下端20bの厚みまで打設され、外側20oでは、それ以上の高さに打設される。しかし、コンクリートの粘性が高く、掘削穴Dの深さが機器を設置する程度の深さである。そのため、コンクリートの厚みによる圧力が外側20oから下方を通じて内側20iに掛かっても、外側20oに打設されたコンクリートが、型枠本体20の下方に回り込み、内側20iへ流れ込むことは無く、内側20iのコンクリートの高さは上昇しない。 As a result, the concrete is cast to the thickness of the lower end 20b on the inner side 20i and higher than that on the outer side 20o. However, the viscosity of concrete is high, and the depth of the excavation hole D is such that the equipment is installed. Therefore, even if the pressure due to the thickness of the concrete is applied from the outer side 20o to the inner side 20i through the lower part, the concrete placed on the outer side 20o does not wrap around the lower part of the formwork main body 20 and flow into the inner side 20i, and the inner side 20i The height of concrete does not rise.

従って、図2(C)に示すように、ピット構築用型枠10の下端20bの厚みまでコンクリートが打設されることで、型枠本体20の下方に底盤P1の厚みの層ができるため、硬化すると底盤P1が形成できる。また、図2(D)に示すように、型枠本体20の外側20oにコンクリートが打設されることで、型枠本体20の周囲部に床面FLを形成することができる。 Therefore, as shown in FIG. 2C, concrete is poured to the thickness of the lower end 20b of the pit construction formwork 10, so that a layer having the thickness of the batholith P1 is formed below the formwork body 20. When cured, the batholith P1 can be formed. Further, as shown in FIG. 2D, concrete is cast on the outer side 20o of the formwork body 20, so that a floor surface FL can be formed around the formwork body 20.

次に、図1に示す筋交い部25を枠部材20pに連結していたナットを外して、筋交い部25を取り外す。後は、コンクリートが硬化すれば、ピット構築用型枠10に囲まれたピットP(図2(D)参照)に、機器設置の作業者による機器の設置ができるため、ピット構築用型枠10を設置する作業者は、コンクリートの硬化を待つこと無く、作業を終えることができる。 Next, the nut connecting the brace portion 25 shown in FIG. 1 to the frame member 20p is removed, and the brace portion 25 is removed. After that, once the concrete is hardened, the equipment can be installed by the equipment installation worker in the pit P (see FIG. 2D) surrounded by the pit construction formwork 10, so that the pit construction formwork 10 can be installed. The worker who installs the formwork can finish the work without waiting for the concrete to harden.

このように本実施の形態1に係るピット構築用型枠を用いたピット構築方法によれば、1度のコンクリートの打設工程にてピットPが構築できるため、工期を短縮することができる。 As described above, according to the pit construction method using the pit construction formwork according to the first embodiment, the pit P can be constructed in one concrete placing step, so that the construction period can be shortened.

図2(B)および同図(C)に示すようにアジャスターボルト30により掘削穴Dの底面D1からの型枠本体20の位置決めすることで、ピットPの底盤P1の厚みを容易に調整することができる。
図1に示す型枠本体20の上端20tに外向きのフランジ部22が形成されていることで、ピットPの周縁部を補強するL字状金具の設置を省略することができる。
As shown in FIGS. 2B and 2C, the thickness of the bottom plate P1 of the pit P can be easily adjusted by positioning the formwork body 20 from the bottom surface D1 of the excavation hole D by the adjuster bolt 30. Can be done.
Since the outward flange portion 22 is formed at the upper end 20t of the formwork main body 20 shown in FIG. 1, it is possible to omit the installation of the L-shaped metal fitting that reinforces the peripheral edge portion of the pit P.

また、型枠本体20の上端20tと下端20bとに、フランジ部22,23が形成されていることで、コンクリートがフランジ部22,23の間に入り込み、しっかりと保持されるため、型枠本体20をコンクリートに強固に固定することができる。 Further, since the flange portions 22 and 23 are formed on the upper end 20t and the lower end 20b of the formwork main body 20, concrete enters between the flange portions 22 and 23 and is firmly held, so that the formwork main body is held firmly. 20 can be firmly fixed to concrete.

フランジ部22,23との間に補強部24が形成されているため、型枠本体20の枠部材20p単体の曲がりや捩れを抑止すると共に、コンクリートがフランジ部22,23の間に入り込む際に、外壁21と補強部24との間にコンクリートが入り込むため、型枠本体20を更にコンクリートに強固に固定することができる。 Since the reinforcing portion 24 is formed between the flange portions 22 and 23, bending and twisting of the frame member 20p of the formwork body 20 alone is suppressed, and when concrete enters between the flange portions 22 and 23. Since concrete enters between the outer wall 21 and the reinforcing portion 24, the formwork body 20 can be further firmly fixed to the concrete.

筋交い部25が枠部材20pに連結しているため、コンクリートが硬化するまでの型枠本体20の変形を抑止することができ、コンクリート硬化後には簡単に取り外すことができ、機器を設置するスペースを確保することができる。 Since the brace portion 25 is connected to the frame member 20p, deformation of the formwork body 20 until the concrete is hardened can be suppressed, and it can be easily removed after the concrete is hardened, providing a space for installing the equipment. Can be secured.

本実施の形態1では、高さ位置決め部材となる足部として、アジャスターボルト30が設けられていたが、図2(B)に示すように型枠本体20と掘削穴Dの底面D1との間に隙間を空けることができ、図2(C)に示す底盤P1が形成できればよいので、単なる棒状部材でもよい。 In the first embodiment, the adjuster bolt 30 is provided as a foot portion serving as a height positioning member, but as shown in FIG. 2B, between the formwork main body 20 and the bottom surface D1 of the excavation hole D. As long as a gap can be left in the space and the bottom plate P1 shown in FIG. 2C can be formed, a simple rod-shaped member may be used.

(実施の形態1の変形例)
本発明の実施の形態の形態1の変形例に係るピット構築用型枠を図面に基づいて説明する。なお、図3においては、図1と同じ構成のものは同符号を付して説明を省略する。
図3に示すピット構築用型枠11は、型枠本体の枠部材20qの断面図である。
型枠本体20xは、上端20tと下端20bとに、外向きのフランジ部221,231が形成されている。
(Modified Example of Embodiment 1)
The pit construction formwork according to the modified example of the first embodiment of the present invention will be described with reference to the drawings. In FIG. 3, the same components as those in FIG. 1 are designated by the same reference numerals and the description thereof will be omitted.
The pit construction formwork 11 shown in FIG. 3 is a cross-sectional view of a frame member 20q of the formwork body.
In the formwork body 20x, outward flange portions 221,231 are formed at the upper end 20t and the lower end 20b.

型枠本体20xの上端20tに形成されたフランジ部221は、外向き部分221aと、外向き部分221aの先端に形成され、下方に向かう下向き部分221bとから形成されている。
型枠本体20xの下端20bに形成されたフランジ部231は、外向き部分231aと、外向き部分231aの先端に形成され、上方に向かう上向き部分231bとから形成されている。
The flange portion 221 formed at the upper end 20t of the formwork body 20x is formed of an outward facing portion 221a and a downward facing portion 221b formed at the tip of the outward facing portion 221a.
The flange portion 231 formed at the lower end 20b of the formwork body 20x is formed of an outward facing portion 231a and an upward facing portion 231b formed at the tip of the outward facing portion 231a.

このようにフランジ部221,231が外向き部分221a,231aだけでなく、下向き部分221bまたは/および上向き部分231bが形成されているため、コンクリートを打設したときに、コンクリートがフランジ部221,231の内側に抱き込まれるように入り込むため、フランジ部221,231をより強固にコンクリートと固着させることができる。 In this way, the flange portions 221 and 231 are formed not only with the outward portions 221a and 231a but also with the downward portions 221b and / and the upward portions 231b. Since it is embraced inside the concrete, the flange portions 221,231 can be more firmly fixed to the concrete.

なお、本実施の形態では、型枠本体20xの上端20tおよび下端20bの両方にフランジ部221,231が形成されていたが、いずれか一方でもよい。その場合には、フランジ部221またはフランジ部231を省略してもよいし、図1に示すフランジ部22,23としてもよい。
しかし、ピットP(図5参照)の開口縁部を補強する上でも、少なくとも、上端20tには、フランジ部22,221が形成されていることが望ましい。
In the present embodiment, the flange portions 221,231 are formed on both the upper end 20t and the lower end 20b of the formwork main body 20x, but either one may be used. In that case, the flange portion 221 or the flange portion 231 may be omitted, or the flange portions 22 and 23 shown in FIG. 1 may be used.
However, in order to reinforce the opening edge portion of the pit P (see FIG. 5), it is desirable that the flange portions 22 and 221 are formed at least at the upper end 20t.

(実施の形態2)
本発明の実施の形態2に係るピット構築用型枠を図面に基づいて説明する。
なお、図4においては、図1と同じ構成のものは同符号を付して説明を省略する。
図4に示すピット構築用型枠12は、型枠本体20に、型枠本体20と掘削穴Dの底面D1との間に隙間を空けるための高さ位置決め部材が設けられてい。
本実施の形態2では、この高さ位置決め部材を、型枠本体20の上端に連結して掘削穴Dに型枠本体20を吊り下げる吊り下げ部40としている。
(Embodiment 2)
The pit construction formwork according to the second embodiment of the present invention will be described with reference to the drawings.
In FIG. 4, the same components as those in FIG. 1 are designated by the same reference numerals and the description thereof will be omitted.
In the formwork 12 for pit construction shown in FIG. 4, the formwork body 20 is provided with a height positioning member for opening a gap between the formwork body 20 and the bottom surface D1 of the excavation hole D.
In the second embodiment, the height positioning member is connected to the upper end of the formwork body 20 to form a hanging portion 40 for suspending the formwork body 20 in the excavation hole D.

吊り下げ部40は、掘削穴Dの両側の周囲部D2に懸架される棒状部材41を備えている。
この棒状部材41は、フランジ部22の下面に取り付けられたナット42aに、棒状部材41を挿通した状態のボルト42bがねじ込まれることで、型枠本体20と固定されている。
また、棒状部材41は、掘削穴Dの両側の周囲部D2に打ち込まれたコンクリートアンカー43aに、棒状部材41を挿通した状態のボルト43bがねじ込まれることで、周囲部D2と固定されている。
The hanging portion 40 includes a rod-shaped member 41 suspended from peripheral portions D2 on both sides of the excavation hole D.
The rod-shaped member 41 is fixed to the formwork body 20 by screwing a bolt 42b in a state where the rod-shaped member 41 is inserted into a nut 42a attached to the lower surface of the flange portion 22.
Further, the rod-shaped member 41 is fixed to the peripheral portion D2 by screwing bolts 43b in a state where the rod-shaped member 41 is inserted into the concrete anchors 43a driven into the peripheral portions D2 on both sides of the excavation hole D.

このとき、掘削穴Dの周囲部が不陸であると、棒状部材41が傾斜した状態となる。その場合には、棒状部材41の下に薄板44をスペーサーとして挿入したり、ボルト43bの高さを調整したりして、棒状部材41が水平となるように調整する。 At this time, if the peripheral portion of the excavation hole D is uneven, the rod-shaped member 41 is in an inclined state. In that case, the thin plate 44 is inserted as a spacer under the rod-shaped member 41, or the height of the bolt 43b is adjusted so that the rod-shaped member 41 is horizontal.

この吊り下げ部40により吊り下げられた型枠本体20は、掘削穴Dの下方に底盤の厚みの隙間ができる。
従って、このような状態でコンクリートを打設することで、底盤と、型枠本体20の周囲部の床面とを同時に形成することができる。
コンクリートを打設し、コンクリートが硬化した後に、ボルト42b,43bを取り外せば、棒状部材41を取り除くことができる。
The formwork body 20 suspended by the suspension portion 40 has a gap of the thickness of the batholith below the excavation hole D.
Therefore, by placing concrete in such a state, the bottom board and the floor surface around the peripheral portion of the formwork main body 20 can be formed at the same time.
The rod-shaped member 41 can be removed by placing the concrete and removing the bolts 42b and 43b after the concrete has hardened.

このように、高さ位置決め部材を、型枠本体20の上端に連結して掘削穴Dに型枠本体20を吊り下げる吊り下げ部40とすることにより、型枠本体20を掘削穴D1に吊り下げるだけで、掘削穴Dの底面D1の状態に関係なく型枠本体の高さの位置決めを行うことができる。 In this way, the formwork body 20 is suspended in the excavation hole D1 by connecting the height positioning member to the upper end of the formwork body 20 to form a hanging portion 40 for suspending the formwork body 20 in the excavation hole D. By simply lowering it, the height of the formwork body can be positioned regardless of the state of the bottom surface D1 of the excavation hole D.

以上、本発明の実施の形態1,2に係るピット構築用型枠を説明した。
図1に示すピット構築用型枠10では平面視矩形状に形成されているが、型枠本体はピット形状に応じて変形が可能である。
The pit construction formwork according to the first and second embodiments of the present invention has been described above.
Although the pit construction formwork 10 shown in FIG. 1 is formed in a rectangular shape in a plan view, the formwork body can be deformed according to the pit shape.

本発明は、床面から掘り下げた掘削穴に形成され、機器が設置されるピットの構築に好適である。 The present invention is suitable for constructing a pit formed in a drilling hole dug down from a floor surface and in which equipment is installed.

10,11,12 ピット構築用型枠
20,20x 型枠本体
20t 上端
20b 下端
20i 内側
20o 外側
20p,20q 枠部材
21 外壁
22,23,221,231 フランジ部
221a,231a 外向き部分
221b 下向き部分
231b 上向き部分
24 補強部
25 筋交い部
30 アジャスターボルト
40 吊り下げ部
41 棒状部材
42a ナット
42b ボルト
43a コンクリートアンカー
43b ボルト
44 薄板
D 掘削穴
D1 底面
D2 周壁
R 鉄筋
P ピット
P1 底盤
FL 床面
10,11,12 Formwork for pit construction 20,20x Formwork body 20t Upper end 20b Lower end 20i Inner 20o Outer 20p, 20q Frame member 21 Outer wall 22,23,221,231 Flange part 221a, 231a Outward part 221b Downward part 231b Upward part 24 Reinforcement part 25 Brace part 30 Adjuster bolt 40 Suspension part 41 Rod-shaped member 42a Nut 42b Bolt 43a Concrete anchor 43b Bolt 44 Thin plate D Drilling hole D1 Bottom D2 Peripheral wall R Reinforcing bar P Pit P1 Bottom

Claims (7)

床面の掘削穴に設置され、機器が設置されるピットを囲む枠部材により形成された型枠本体が、打設されたコンクリート硬化後に埋殺しされるピット構築用型枠において、
前記型枠本体に、前記型枠本体と前記掘削穴の底面との間に隙間を空けるための高さ位置決め部材が設けられているピット構築用型枠。
In the formwork for pit construction, the formwork body formed by the frame member that is installed in the excavation hole on the floor and surrounds the pit where the equipment is installed is buried after the cast concrete is hardened.
A pit construction formwork provided with a height positioning member in the formwork body for allowing a gap between the formwork body and the bottom surface of the excavation hole.
前記高さ位置決め部材は、前記型枠本体の下端に設けられた足部である請求項1記載のピット構築用型枠。 The pit construction formwork according to claim 1, wherein the height positioning member is a foot portion provided at the lower end of the formwork body. 前記高さ位置決め部材は、前記型枠本体の上端に連結して前記掘削穴に前記型枠本体を吊り下げる吊り下げ部である請求項1記載のピット構築用型枠。 The pit construction formwork according to claim 1, wherein the height positioning member is a hanging portion that is connected to the upper end of the formwork body and suspends the formwork body in the excavation hole. 前記型枠本体の上端および下端のいずれか一方、または両方には、外向きのフランジ部が形成された請求項1から3のいずれか項に記載のピット構築用型枠。 The pit-building formwork according to any one of claims 1 to 3, wherein an outward flange portion is formed on one or both of the upper end and the lower end of the form body. 前記型枠本体の外壁との間に隙間を空けた状態でフランジ部同士を接続する補強部が形成された請求項4記載のピット構築用型枠。 The pit construction formwork according to claim 4, wherein a reinforcing portion for connecting the flange portions is formed with a gap between the formwork and the outer wall of the formwork body. 前記フランジ部は、外向き部分と、前記外向き部分の先端に形成され、前記型枠本体の上端であれば下方に向かう下向き部分、前記型枠本体の下端であれば上方に向かう上向き部分とを備えた請求項4または5記載のピット構築用型枠。 The flange portion is formed at the outward portion and the tip of the outward portion, and is a downward portion facing downward at the upper end of the formwork body and an upward facing portion at the lower end of the formwork body. The pit construction formwork according to claim 4 or 5. 床面の掘削穴に設置され、機器が設置されるピットを囲む枠部材により形成された型枠本体が、打設されたコンクリート硬化後に埋殺しされるピット構築用型枠を用いたピット構築方法において、
前記型枠本体の下方の隙間であり、前記型枠本体と前記掘削穴の底面との間に隙間を空けるための高さ位置決め部材が設けられた前記ピット構築用型枠を、掘削穴に配置する工程と、
前記型枠本体と前記掘削穴の周壁との間に、前記床面までの高さのコンクリートを打設すると共に、前記型枠本体の内側に前記掘削穴の底盤となる厚みのコンクリートを打設する工程と、
前記コンクリートを硬化させる工程とを含むピット構築方法。
A pit construction method using a pit construction formwork in which the formwork body formed by the frame member that is installed in the excavation hole on the floor and surrounds the pit where the equipment is installed is buried after the cast concrete is hardened. In
The pit construction formwork, which is a gap below the formwork body and is provided with a height positioning member for opening a gap between the formwork body and the bottom surface of the excavation hole, is arranged in the excavation hole. And the process to do
A concrete having a height up to the floor is placed between the formwork body and the peripheral wall of the excavation hole, and concrete having a thickness that serves as the bottom of the excavation hole is placed inside the formwork body. And the process to do
A pit construction method including a step of hardening the concrete.
JP2018054581A 2018-03-22 2018-03-22 Formwork for pit construction and pit construction method Active JP6999170B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018054581A JP6999170B2 (en) 2018-03-22 2018-03-22 Formwork for pit construction and pit construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018054581A JP6999170B2 (en) 2018-03-22 2018-03-22 Formwork for pit construction and pit construction method

Publications (2)

Publication Number Publication Date
JP2019167697A JP2019167697A (en) 2019-10-03
JP6999170B2 true JP6999170B2 (en) 2022-01-18

Family

ID=68107711

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018054581A Active JP6999170B2 (en) 2018-03-22 2018-03-22 Formwork for pit construction and pit construction method

Country Status (1)

Country Link
JP (1) JP6999170B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343060B (en) * 2020-11-30 2024-06-21 江西基业科技集团有限公司 Clockwise and anticlockwise composite construction method for cylindrical foundation pit structure
CN114991479B (en) * 2022-07-04 2023-10-13 新疆富昌建设工程有限公司 Intelligent construction method for building decoration
CN116122190B (en) * 2023-04-13 2023-06-27 山西建投建筑产业有限公司 Construction structure and construction process for assembled integral multi-cabin drainage box culvert

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000087354A (en) 1998-09-11 2000-03-28 Tokyo Koatsu Kk Pit and construction method thereof
JP2000291028A (en) 1999-04-09 2000-10-17 Nabco System Kk Parking lot installation underground pit structure and its construction method
JP2002308397A (en) 2001-04-11 2002-10-23 Tatsuno Corp Oiling device
JP2009097274A (en) 2007-10-18 2009-05-07 Ohbayashi Corp Column construction method and column form unit

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000087354A (en) 1998-09-11 2000-03-28 Tokyo Koatsu Kk Pit and construction method thereof
JP2000291028A (en) 1999-04-09 2000-10-17 Nabco System Kk Parking lot installation underground pit structure and its construction method
JP2002308397A (en) 2001-04-11 2002-10-23 Tatsuno Corp Oiling device
JP2009097274A (en) 2007-10-18 2009-05-07 Ohbayashi Corp Column construction method and column form unit

Also Published As

Publication number Publication date
JP2019167697A (en) 2019-10-03

Similar Documents

Publication Publication Date Title
JP6999170B2 (en) Formwork for pit construction and pit construction method
JP4738886B2 (en) Equipment foundation
US10837173B2 (en) Beam-column connection structure and method of making the same
JP3899366B1 (en) Boxing formwork and boxing method using the same
JP4641328B1 (en) Seismic isolation device mounting method and mounting structure
JP2012158912A (en) Base isolation structure and construction method for the same
JP5183606B2 (en) Unit structure of anchor bolt used for foundation construction of equipment and foundation construction method of equipment using it
JP6632290B2 (en) Steel column leg structure and steel column leg construction method
JP7194531B2 (en) Seismic isolation upper foundation structure and manufacturing method thereof, footing structure, and seismic isolation foundation construction method
JP2008255724A (en) Jig for execution of work of foundation structure with anchor bolt
JP6485830B2 (en) Plate for slope protection
JP4563879B2 (en) Anchor bolt support device
JP7476044B2 (en) Temporary opening formwork
JP2018100488A (en) Base-isolation construction, base plate and method for construction of lower foundation member
JP6654918B2 (en) Fixing method and joint structure of joint steel frame in composite structure
JP4928142B2 (en) Seismic isolation structure construction method
KR101894411B1 (en) Reinforcement structure for pillar and pillar reinforcing process to intall the same
JP4095953B2 (en) Anchor device and method of using the anchor device
KR101157588B1 (en) Slab form bracket and method for constructing slab of an iron architect using thereof
JP2016153559A (en) Construction method of wooden building and foundation member used for construction method
JP6425584B2 (en) Horizontal movement restraint method
JP7149744B2 (en) Seismic isolation upper foundation structure, its fabrication method, and seismic isolation foundation construction method
JP4758803B2 (en) Foundation structure with anchor bolt and its construction method
JP2014173343A (en) Upper concrete placing formwork of marine structure and upper concrete forming method using the formwork
JP5470195B2 (en) How to install the structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200917

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210820

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210901

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20211007

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211207

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211215

R150 Certificate of patent or registration of utility model

Ref document number: 6999170

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150