JP5789489B2 - Temporary deadline structure of dam body - Google Patents

Temporary deadline structure of dam body Download PDF

Info

Publication number
JP5789489B2
JP5789489B2 JP2011247783A JP2011247783A JP5789489B2 JP 5789489 B2 JP5789489 B2 JP 5789489B2 JP 2011247783 A JP2011247783 A JP 2011247783A JP 2011247783 A JP2011247783 A JP 2011247783A JP 5789489 B2 JP5789489 B2 JP 5789489B2
Authority
JP
Japan
Prior art keywords
dam
anchor
dome
water
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2011247783A
Other languages
Japanese (ja)
Other versions
JP2013104203A (en
Inventor
武夫 土橋
武夫 土橋
宗一 藤原
宗一 藤原
知仁 鎌田
知仁 鎌田
誠 金井
誠 金井
篤 徳永
篤 徳永
和弥 重井
和弥 重井
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Hokoku Kogyo Co Ltd
Original Assignee
Obayashi Corp
Hokoku Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp, Hokoku Kogyo Co Ltd filed Critical Obayashi Corp
Priority to JP2011247783A priority Critical patent/JP5789489B2/en
Publication of JP2013104203A publication Critical patent/JP2013104203A/en
Application granted granted Critical
Publication of JP5789489B2 publication Critical patent/JP5789489B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Description

本発明は、ダム堤体の仮締切構造に関するものであり、具体的には、施工時に作用する浮力に確実に対処可能である仮締切構造の技術に関する。   The present invention relates to a temporary closing structure of a dam dam body, and specifically relates to a technique of a temporary closing structure that can reliably cope with buoyancy acting during construction.

ダム堤体上流側における堆積土砂の排砂経路、洪水調節容量増加を目的とした新たな放水経路、或いは、小水力発電機の設置領域などを確保する目的で、既存ダムの堤体に貫通穴を構築するケースが増えている。従来、既存のダム堤体に貫通穴を構築する場合、ダム堤体の上流側に水底まで達する大規模な仮設の締切工を実施し、締切構造内側をドライアップして貫通穴掘削を行っていた。しかし、こうした方法では仮設の締切構造が大がかりになり、施工期間及び施工費が増大するという問題点があった。そこで、小規模・低コストでダム水域の仮締切を可能とする技術として、例えば、ダム堤体の水域側の面に球面状止水壁を取り付けた仮締切構造(特許文献1)などが提案されている。   Through holes in the dam body of the existing dam for the purpose of securing a sediment discharge path on the upstream side of the dam body, a new water discharge path for the purpose of increasing flood control capacity, or a small hydroelectric generator installation area The number of cases of building is increasing. Conventionally, when constructing a through-hole in an existing dam body, a large-scale temporary cut-off work has been carried out to reach the bottom of the water upstream of the dam body, and the inside of the cut-off structure has been dried up to drill the through-hole. It was. However, such a method has a problem that the temporary deadline structure becomes large and the construction period and construction cost increase. Therefore, as a technology that enables temporary closing of dam water areas at a small scale and low cost, for example, a temporary closing structure (Patent Document 1) in which a spherical water blocking wall is attached to the surface of the dam dam body is proposed. Has been.

特開2004−263380号公報JP 2004-263380 A

上記従来の仮締切構造の技術においては、水中の半球状止水壁が水圧によりダム堤体に押圧されることで両者の間に摩擦力が発生し、これによりダム堤体への半球状止水壁の固定が図られるとの前提に立っている。一方、そうした従来の仮締切構造を実際の施工に採用した場合、内部を排水した半球状止水壁には自身の空中重量に比べて遥かに大きな浮力がかかるとの知見が、発明者らにおいて得られている。しかもこの浮力は、上述の摩擦力が十分発揮される前の、半球状止水壁の内部を排水する際に発生するものであるため、上記摩擦力により浮力に対抗することを期待するのは危険である。
他方、仮締切構造の周縁部を、貫通穴外周のダム堤体にアンカーを打設することで固定する場合、上述したような大きな浮力が仮締切構造にかかると、この浮力を受けたアンカーによる反力で、貫通穴周囲のダム堤体が損傷する懸念もある。
つまり、従来技術においては、施工に際し仮締切構造にかかる浮力について、その対策が十分考慮されていなかったのである。
In the above-described conventional temporary cutoff structure technology, the underwater hemispherical water blocking wall is pressed against the dam dam body by water pressure, and a frictional force is generated between them. It is based on the premise that the water wall will be fixed. On the other hand, when such a conventional temporary closing structure is adopted in actual construction, the inventors have found that a hemispherical water blocking wall drained from inside has a much larger buoyancy than its own aerial weight. Has been obtained. Moreover, since this buoyancy is generated when draining the inside of the hemispherical water blocking wall before the above-mentioned friction force is sufficiently exerted, it is expected that the buoyancy is countered by the friction force. It is a danger.
On the other hand, when the peripheral part of the temporary closing structure is fixed by driving an anchor to the dam dam body around the through hole, when the large buoyancy as described above is applied to the temporary closing structure, the anchor receiving the buoyancy There is also a concern that the dam dam around the through hole may be damaged by the reaction force.
That is, in the prior art, countermeasures have not been sufficiently taken into account for buoyancy applied to the temporary closing structure during construction.

そこで本発明では、施工時に作用する浮力に確実に対処可能である仮締切構造の技術を提供することを目的とする。   In view of this, an object of the present invention is to provide a technique of a temporary closing structure that can reliably cope with buoyancy acting during construction.

上記課題を解決する本発明のダム堤体の仮締切構造は、既存ダム堤体での貫通穴構築に際し用いる仮締切構造であり、前記貫通穴の開口予定位置を囲むようにダム堤体上流面に開口が当接するドーム体と、ダム堤体上流側の水底部に打設され、前記ドーム体と連結されたアンカーとからなることを特徴とする。   The temporary closing structure of the dam dam body of the present invention that solves the above-mentioned problem is a temporary closing structure used when constructing a through hole in an existing dam dam body, and the upstream surface of the dam dam body so as to surround the planned opening position of the through hole The dome body is in contact with the dome body, and the anchor is connected to the dome body.

こうした仮締切構造によれば、ドーム体内空の水を排水する際に生じる浮力に対し、打設済みのアンカーに反力をとってドーム体の浮き上がりを抑止することが出来る。ドーム体と連結されているアンカーは、ダム堤体上流側の水底部に打設されているものとする。この水底部としては、ダム堤体上流側の水底地盤の他、ダム堤体上流側における堤体の底部など、アンカーの打設が可能な所定構造物も含まれるものとする。   According to such a temporary closing structure, the dome body can be prevented from being lifted against the buoyancy generated when the water in the dome body is drained by reacting with the anchor that has been placed. The anchor connected to the dome body is assumed to be driven at the bottom of the water on the upstream side of the dam body. As the water bottom, in addition to the water bottom ground on the upstream side of the dam dam body, a predetermined structure capable of placing an anchor such as the bottom of the dam body upstream side of the dam dam body is included.

上記構造の場合、アンカーから延びるワイヤーの先端に備わるフック等の連結具を、ドーム体外周に備わる連結受入治具(例:フッキング用のリングや孔)に連結させ、ドーム体とアンカーとを連結させる。本発明によれば、施工時に作用する浮力に確実に対処可能である仮締切構造を提供できる。   In the case of the above structure, a hook or other connecting tool provided at the tip of the wire extending from the anchor is connected to a connection receiving jig (eg, hooking ring or hole) provided on the outer periphery of the dome body, and the dome body and the anchor are connected. Let ADVANTAGE OF THE INVENTION According to this invention, the temporary closing structure which can respond reliably to the buoyancy which acts at the time of construction can be provided.

本発明によれば、施工時に作用する浮力に確実に対処可能である仮締切構造を提供できる。   ADVANTAGE OF THE INVENTION According to this invention, the temporary closing structure which can respond reliably to the buoyancy which acts at the time of construction can be provided.

本実施形態における仮締切構造の構造例を示す全体図である。It is a general view which shows the structural example of the temporary closing structure in this embodiment. 本実施形態における仮締切構造の施工手順1を示す図である。It is a figure which shows the construction procedure 1 of the temporary closing structure in this embodiment. 本実施形態における仮締切構造の施工手順2を示す図である。It is a figure which shows the construction procedure 2 of the temporary closing structure in this embodiment. 本実施形態における仮締切構造の施工手順3を示す図である。It is a figure which shows the construction procedure 3 of the temporary closing structure in this embodiment. 本実施形態における仮締切構造の施工手順4を示す図である。It is a figure which shows the construction procedure 4 of the temporary closing structure in this embodiment. 本実施形態における仮締切構造の施工手順5を示す図である。It is a figure which shows the construction procedure 5 of the temporary closing structure in this embodiment. 本実施形態における仮締切構造の施工手順6を示す図である。It is a figure which shows the construction procedure 6 of the temporary closing structure in this embodiment. 本実施形態における仮締切構造の施工手順7を示す図である。It is a figure which shows the construction procedure 7 of the temporary closing structure in this embodiment.

以下に本発明の実施形態について図面を用いて詳細に説明する。図1は、本実施形態におけるダム堤体の仮締切構造の構造例を示す全体図である。本実施形態における仮締切構造100は、既存ダムの堤体1での、排砂坑などの貫通穴2の構築に際し用いる、堤体上流側の仮締切構造である。本実施形態の仮締切構造100は、図1で示すように、断面がダム堤体上流側に凸である半楕円状の構造をなすドーム体10と、このドーム体10と水底部5たる水底地盤(以下、水底地盤5とする)とを結ぶアンカー60とで構成されている。   Embodiments of the present invention will be described below in detail with reference to the drawings. FIG. 1 is an overall view showing a structural example of a temporary closing structure of a dam dam body in the present embodiment. The temporary closing structure 100 in the present embodiment is a temporary closing structure on the upstream side of the dam body used in the construction of the through hole 2 such as a sand pit in the dam body 1 of the existing dam. As shown in FIG. 1, the provisional deadline structure 100 of the present embodiment includes a dome body 10 having a semi-elliptical structure whose cross section is convex on the upstream side of the dam dam body, and a water bottom that is the dome body 10 and the water bottom 5. It is comprised with the anchor 60 which connects the ground (henceforth the water bottom ground 5).

ドーム体10は、その開口21がダム堤体上流面3に止水材7を介して当接し、貫通穴2の開口予定位置4aを囲むものである。このドーム体10の外周上部には、給気バルブ27とマンホール28が、また外周下部には排水バルブ29がそれぞれ備わっている。   The dome body 10 has an opening 21 that abuts the dam dam body upstream surface 3 via a water blocking material 7 and surrounds the planned opening position 4 a of the through hole 2. An air supply valve 27 and a manhole 28 are provided at the upper outer periphery of the dome body 10, and a drain valve 29 is provided at the lower outer periphery.

給気バルブ27は、堤体2上の給気装置と適宜な給気経路を介して結ばれ、ドーム体10すなわち仮締切構造100の内空25に空気を導くためのバルブである。また、マンホール28は、仮締切構造100の内空25で作業を行う作業員の出入口となる開閉口である。このマンホール28は図示しないバルブを備えており、内空25とマンホール外との間の開閉が可能となっている。また、排水バルブ29は仮締切構造100の内空25から水を外部に排水するためのバルブである。   The air supply valve 27 is connected to an air supply device on the bank body 2 through an appropriate air supply path, and is a valve for guiding air to the inner space 25 of the dome body 10, that is, the temporary cutoff structure 100. The manhole 28 is an opening / closing port serving as an entrance / exit of a worker who performs work in the inner space 25 of the temporary closing structure 100. The manhole 28 includes a valve (not shown), and can be opened and closed between the inner space 25 and the outside of the manhole. The drain valve 29 is a valve for draining water from the inner space 25 of the temporary closing structure 100 to the outside.

こうしたドーム体10の外周面24には、リング状のリブ材30が備わっている。このリブ材30はドーム体10の補剛材である。こうしたリブ材30を設けることにより、ドーム体10自体の肉厚を(リブ材30の取り付け前より)薄くし、ドーム体10の軽量化を図ることが出来る。軽量化したドーム体10は運搬や設置が容易となり、その為のコストや手間も軽減される。   A ring-shaped rib member 30 is provided on the outer peripheral surface 24 of the dome body 10. This rib member 30 is a stiffener for the dome body 10. By providing such a rib member 30, the thickness of the dome body 10 itself can be reduced (before the rib member 30 is attached), and the dome body 10 can be reduced in weight. The weight-reduced dome body 10 can be easily transported and installed, and the cost and labor for that purpose can be reduced.

このリブ材30の下端は、ダム堤体上流側における水底地盤5に打設したアンカー60との連結構造31を有している。本実施形態で例示する連結構造31は、リブ材30の下端を下方に延長したスカート状のプレート32と、このプレート32に設けられたフッキング用孔33からなっている。この場合、水底地盤5中に打設されているアンカー60(から延びるワイヤー)の先端に備わるフック61を、上述の連結構造31に備わるフッキング用孔33にフッキングさせ、連結構造31を介して、リブ材30ひいてはドーム体10とアンカー60とを連結させることができる。このような連結構造31を採用すれば、仮締切構造内空の水を排水する際に生じる浮力に対し、水底地盤5中のアンカー60に反力をとって仮締切構造100の浮き上がりを抑止することが出来る。   The lower end of the rib member 30 has a connection structure 31 with an anchor 60 placed on the water bottom ground 5 on the upstream side of the dam dam body. The connection structure 31 exemplified in this embodiment includes a skirt-like plate 32 in which the lower end of the rib member 30 extends downward, and a hooking hole 33 provided in the plate 32. In this case, the hook 61 provided at the tip of the anchor 60 (wire extending from) placed in the water bottom ground 5 is hooked into the hooking hole 33 provided in the connection structure 31 described above, The rib member 30 and thus the dome body 10 and the anchor 60 can be connected. If such a connection structure 31 is adopted, the buoyancy generated when draining the water in the temporary cutoff structure is counteracted by the anchor 60 in the water bottom ground 5 to suppress the floating of the temporary cutoff structure 100. I can do it.

上記のアンカー60は、水底地盤5に設けた孔6に鋼材等を挿入、定着させた構造となっており、アンカー体120、引張り部130、アンカー頭部140から構成されている。このうちアンカー体120は、アンカー60にかかる引張り力を水底地盤5に直接伝達するもので、孔6へのグラウト注入によって形成される。また、引張り部130は、アンカー頭部140からの引張り力をアンカー体120に伝達する部分で、PC鋼棒、PC鋼より線、多重PC鋼より線、連続繊維補強材などを材料としたテンドン131と、テンドン131の防食と摩擦損失を防ぐ機能を担うシース132から構成されている。アンカー頭部140は、テンドン131の定着具141と、これを支えて荷重を水底地盤5に伝達する支圧板142からなっている。   The anchor 60 has a structure in which a steel material or the like is inserted and fixed in a hole 6 provided in the water bottom ground 5, and includes an anchor body 120, a tension portion 130, and an anchor head 140. Among them, the anchor body 120 directly transmits the tensile force applied to the anchor 60 to the water bottom ground 5 and is formed by injecting grout into the hole 6. The tension portion 130 is a portion that transmits the tensile force from the anchor head 140 to the anchor body 120, and is a tendon made of a PC steel rod, a PC steel strand, a multiplex PC steel strand, a continuous fiber reinforcement, or the like. 131 and a sheath 132 having a function of preventing corrosion of the tendon 131 and preventing friction loss. The anchor head 140 includes a fixing tool 141 of the tendon 131 and a support plate 142 that supports the fixing tool 141 and transmits the load to the water bottom ground 5.

なお、本実施形態では、アンカー60の打設先であるダム堤体上流側の水底部として水底地盤5を例示しているが、この水底部としては、ダム堤体上流側における堤体1の底部など、アンカー60の打設が可能な所定構造物も含まれるものとする。   In addition, in this embodiment, although the water bottom ground 5 is illustrated as a water bottom part of the dam dam body upstream side which is the placement destination of the anchor 60, as this water bottom part, the dam body 1 upstream of the dam dam body is illustrated. It is assumed that a predetermined structure such as a bottom portion on which the anchor 60 can be driven is also included.

貫通穴2の施工に当たっては、ドーム体10を貫通穴2における上流側の開口4の位置(開口予定位置4a)に予め設置してアンカー60と連結の上、ドーム体10の内空25に存在する水を排水することにより、ドーム体10をダム堤体上流面3に押しつけ、作業空間を確保する。   In constructing the through hole 2, the dome body 10 is installed in advance at the position of the upstream opening 4 in the through hole 2 (expected opening position 4 a) and connected to the anchor 60, and is present in the inner space 25 of the dome body 10. By draining the water to be used, the dome body 10 is pressed against the upstream surface 3 of the dam dam body, and a work space is secured.

次に、本実施形態の仮締切構造100の施工手順について詳細に説明する。図2〜8は本実施形態における仮締切構造の各施工手順1〜7をそれぞれ示す図である。まず、図2に示すように、ドーム体10を、クレーン80で堤体上部より吊り下げて、堤体上流面3における放流管48の呑口位置となる場所(水中の仮設構台上)まで沈める(手順1)。なお、ドーム体10の内空25には放流管呑口の閉鎖ゲート扉体49(図8)等を予め載置しておくが、これらは、ともに寸法、重量ともに大きく、現地まで一体で搬入することは不可能である。よってこれらは、工場での検査終了後、施工現地まで分割して輸送し、ダム堤体近傍で組立作業を行うこととする(不図示)。また、堤体上流側の水底地盤5における、ドーム体10の設置位置には、予め潜水作業等にてアンカー60を設置しておく。   Next, the construction procedure of the temporary closing structure 100 of this embodiment will be described in detail. 2-8 is a figure which shows each construction procedure 1-7 of the temporary closing structure in this embodiment, respectively. First, as shown in FIG. 2, the dome body 10 is suspended from the upper part of the dam body by a crane 80 and submerged to a place (on the temporary gantry in water) where the discharge pipe 48 is located at the upstream side 3 of the dam body ( Procedure 1). In addition, a closed gate door body 49 (FIG. 8) or the like of a discharge pipe mouth is placed in advance in the inner space 25 of the dome body 10, both of which are large in size and weight, and are carried into the site integrally. It is impossible. Therefore, after completion of the inspection at the factory, these are divided and transported to the construction site and assembled near the dam body (not shown). In addition, an anchor 60 is installed in advance at the installation position of the dome body 10 in the water bottom ground 5 on the upstream side of the bank body by diving work or the like.

なお、アンカー60の打設は以下のような手順で行われる。まず、アンカー挿入用の所定径の孔6をボーリングマシンで削孔し、形成した孔6にテンドン131およびシース132を挿入する。テンドン131およびシース132の挿入後、アンカー体120としてグラウトを孔6に注入し、注入後のグラウトが所定強度に達した後、引張部130への緊張付加を行う。また、引張部130の上端に支圧板142を挿通させた上で定着具141により引張部130とアンカー頭部140を一体となし、アンカー60の打設が完了する。   The anchor 60 is placed in the following procedure. First, a hole 6 having a predetermined diameter for anchor insertion is drilled by a boring machine, and the tendon 131 and the sheath 132 are inserted into the formed hole 6. After insertion of the tendon 131 and the sheath 132, a grout is injected into the hole 6 as the anchor body 120. After the injected grout reaches a predetermined strength, tension is applied to the tension portion 130. In addition, the support plate 142 is inserted through the upper end of the tension portion 130, and then the tension portion 130 and the anchor head 140 are integrally formed by the fixing tool 141, and the anchor 60 is completely driven.

手順1に続き、図3に示すように、仮締切構造100におけるドーム体10の開口21と堤体上流面3との間を止水材で挟み込んで固定するなどの水密加工を実施する(手順2)。また、上述のように予め打設してあるアンカー60を、ドーム体10の下部に備わる連結構造31に連結し、この連結構造31を介してドーム体10とアンカー60とを連結させておく。これらの作業は潜水夫による水中作業と共同して行う。   Following the procedure 1, as shown in FIG. 3, a watertight process such as sandwiching and fixing the opening 21 of the dome body 10 and the upstream surface 3 of the dam body with a water-stopping material in the temporary closing structure 100 is performed (procedure) 2). In addition, the anchor 60 that has been placed in advance as described above is connected to the connection structure 31 provided in the lower portion of the dome body 10, and the dome body 10 and the anchor 60 are connected via the connection structure 31. These operations are carried out in cooperation with underwater work by divers.

続いて、図4に示すように、マンホール管8をクレーン81で堤体上より吊り下げて、ドーム体10のマンホール28に接続し、マンホール28に接続したマンホール管8の上端に他のマンホール管8を順次接続していく(手順3)。このマンホール管8の設置に当たっては、堤体上流側の水域に作業台船40を浮かべて作業員を配置し、クレーン81で吊下したマンホール管8の位置決め、マンホール28とマンホール管8の連結、およびマンホール管8同士の連結といった作業に当たらせる。また、マンホール管8は堤体上流面3に対し、鋼棒など適宜な転倒防止材9で一時的に固定される。   Subsequently, as shown in FIG. 4, the manhole pipe 8 is suspended from the dam body by a crane 81 and connected to the manhole 28 of the dome body 10, and another manhole pipe is connected to the upper end of the manhole pipe 8 connected to the manhole 28. 8 are sequentially connected (procedure 3). In installing the manhole tube 8, a work table ship 40 is floated in the water area upstream of the dam body, an operator is placed, the manhole tube 8 suspended by the crane 81 is positioned, the manhole 28 and the manhole tube 8 are connected, In addition, the manhole tube 8 is connected to each other. The manhole pipe 8 is temporarily fixed to the dam body upstream surface 3 with an appropriate tipping prevention material 9 such as a steel bar.

次に、図5に示すように、作業台船40上に設置したポンプ41より、給気ホース42を伸ばしてドーム体10の給気バルブ27に接続し、ドーム体10の内空25への圧力空気の給気を開始する(手順4)。また、それとともに、ドーム体10の排水バルブ29を開き、ドーム体10の内空25に存在する水を、上述の給気による空気充填に伴って排出し、内空25をドライ状態とする。上述の圧力空気の給気に際し、ドーム体10の排水バルブ29から空気泡が噴出し始めたら、内空25において完全に排水がなされたことを意味するから、排水バルブ29および給気バルブ27を閉じ、マンホール28のバルブを開放して圧力空気を徐々に逃がし、内空25を大気圧とする。こうして内空25は大気圧となって、ドーム体10は水圧によって堤体上流面3に押圧されることになり、アンカー60と連結構造31の連結によって水中位置に留められる。   Next, as shown in FIG. 5, the air supply hose 42 is extended from the pump 41 installed on the work table ship 40 and connected to the air supply valve 27 of the dome body 10, and the dome body 10 is connected to the inner space 25. Supply of pressurized air is started (procedure 4). At the same time, the drain valve 29 of the dome body 10 is opened, and the water present in the inner space 25 of the dome body 10 is discharged along with the air filling by the above-mentioned supply air, thereby making the inner space 25 dry. When air bubbles start to be ejected from the drain valve 29 of the dome body 10 during the above-mentioned supply of pressurized air, it means that the drainage valve 29 and the air supply valve 27 are completely discharged. Then, the valve of the manhole 28 is opened and the pressure air is gradually released, and the inner space 25 is set to atmospheric pressure. Thus, the inner space 25 becomes atmospheric pressure, and the dome body 10 is pressed against the upstream surface 3 of the dam body by water pressure, and is held at the underwater position by the connection of the anchor 60 and the connection structure 31.

なお、内空25の水を排水するにあたっては、内空25に予めセットしておいた水中ポンプを、上述の給気バルブ27および排水バルブ29を閉じた状態で稼働させ、マンホール管8の上端から排水を行う方法を採用しても良い。   When draining the water in the inner space 25, a submersible pump set in advance in the inner space 25 is operated with the above-described air supply valve 27 and drain valve 29 closed, and the upper end of the manhole pipe 8 is operated. Alternatively, a method of draining water may be employed.

なお、ドーム体10の内空25の排水を行った際に発生する浮力は、ドーム体10の空中重量に比べて遥かに大きくなる。例えば、水深17mの位置に直径10000mmの開口を備えたドーム体10を設置しようとした場合、凡そ18000kNの浮力がドーム体10の空中重量に勝るという知見を発明者らは得ている。一方、水圧によってドーム体10がダム堤体上流面3に押圧されていれば、堤体上流面3とドーム体10との間に摩擦力が発生して浮力を減らすことが出来るが、この浮力は、前述の摩擦力が十分発揮される前の、内空25の水を排出する際に発生するため、上述の摩擦力により浮力に対抗することを期待するのは危険である。よって、アンカー60に関して想定する荷重は、ドーム体10にかかる全浮力分以上の大きさとする。また、この浮力対策が必要な期間はドーム体10の内空25での作業員による作業時だけであるから、仮設のアンカーとして設計する。こうしたアンカー60にはPC鋼より線を採用できる。   Note that the buoyancy generated when draining the inner space 25 of the dome body 10 is much larger than the weight of the dome body 10 in the air. For example, the inventors have found that when a dome body 10 having an opening with a diameter of 10000 mm is installed at a water depth of 17 m, the buoyancy of about 18000 kN exceeds the air weight of the dome body 10. On the other hand, if the dome body 10 is pressed against the dam dam body upstream surface 3 by water pressure, a frictional force is generated between the dam body upstream surface 3 and the dome body 10 to reduce buoyancy. Is generated when the water in the inner space 25 is discharged before the above-described frictional force is sufficiently exerted, and therefore it is dangerous to expect to resist buoyancy by the above-described frictional force. Therefore, the load assumed for the anchor 60 is set to be equal to or larger than the total buoyancy applied to the dome body 10. Further, since the period during which this buoyancy countermeasure is required is only during work by the worker in the inner space 25 of the dome body 10, it is designed as a temporary anchor. Such an anchor 60 can employ a stranded wire of PC steel.

続いて、図6に示すように、連結したマンホール管8のうち最上部のマンホール管8の上部に、管理歩廊43を設け、堤体1の上部より移動してきた作業員がこの管理歩廊43、マンホール管8、およびマンホール28を通ってドーム体10の内空25に入る(手順5)。内空25に入った作業員は、内空25が排水完了状態である事を確認する。一方で、堤体下流側からは、ローダー85など適宜な掘削機が貫通穴2を掘削しているものとする。内空25の排水完了状態の確認の後、ローダー85は、ドーム体10の内空25と掘削済みの貫通穴2との間に残された部位の掘削を実行する。   Subsequently, as shown in FIG. 6, a management corridor 43 is provided above the uppermost manhole pipe 8 among the connected manhole pipes 8. It enters the inner space 25 of the dome body 10 through the manhole tube 8 and the manhole 28 (procedure 5). The worker who enters the inner space 25 confirms that the inner space 25 is in a drained state. On the other hand, it is assumed that an appropriate excavator such as a loader 85 excavates the through hole 2 from the downstream side of the bank body. After confirming the drainage completion state of the inner air 25, the loader 85 performs excavation of a portion left between the inner air 25 of the dome body 10 and the drilled through hole 2.

この掘削が完了し、ドーム体10の内空25と貫通穴2とが貫通したならば、図7に示すように、閉鎖ゲート扉体用戸当り47およびベルマウス46の据え付けと空気管45の設置を行う(手順6)。この場合、ドーム体10の内空25に予め載置しておいた閉鎖ゲート扉体用戸当り47およびベルマウス46を堤体1に据え付け、また、貫通穴2において堤体下流から放流管48を搬入し、この放流管48を閉鎖ゲート扉体49およびベルマウス46と接続する。更に、閉鎖ゲート扉体49を閉鎖ゲート扉体用戸当り47およびベルマウス46に接続する。   When this excavation is completed and the inner space 25 and the through hole 2 of the dome body 10 penetrate, the installation of the closed gate door body door 47 and the bell mouth 46 and the installation of the air pipe 45 are performed as shown in FIG. Installation is performed (procedure 6). In this case, the door 47 for the closed gate door body and the bell mouth 46 previously placed in the inner space 25 of the dome body 10 are installed on the bank body 1, and the discharge pipe 48 from the downstream side of the bank body in the through hole 2. The discharge pipe 48 is connected to the closed gate door body 49 and the bell mouth 46. Further, the closed gate door body 49 is connected to the door 47 for the closed gate door body and the bell mouth 46.

この接続の完了後、放流管48と貫通穴2の内壁との間の空隙など所定領域にコンクリートを打設しておく。また、ドーム体10の内空25で作業を行っていた作業員を、マンホール管8を介して水上の作業台船40上又は管理歩廊43上に退出させる。   After this connection is completed, concrete is placed in a predetermined region such as a gap between the discharge pipe 48 and the inner wall of the through hole 2. In addition, the worker who has been working in the inner space 25 of the dome body 10 is made to leave on the work table boat 40 on the water or the management corridor 43 through the manhole pipe 8.

続いて、給気バルブ27、排水バルブ29を開き、ドーム体10の内空25への充水を行う。また、図8に示すように、マンホール28に連結させていたマンホール管8を順次撤去し、仮締切構造100におけるドーム体10とアンカー60との連結を解除して、ドーム体10もクレーン80によって吊り上げて撤去する(手順7)。   Subsequently, the air supply valve 27 and the drain valve 29 are opened, and the inner space 25 of the dome body 10 is filled with water. Further, as shown in FIG. 8, the manhole tube 8 connected to the manhole 28 is sequentially removed, the connection between the dome body 10 and the anchor 60 in the temporary closing structure 100 is released, and the dome body 10 is also moved by the crane 80. Lift and remove (Procedure 7).

このように本実施形態によれば、施工時に作用する浮力に確実に対処可能である仮締切構造を提供できる。   Thus, according to the present embodiment, it is possible to provide a temporary closing structure that can reliably cope with buoyancy acting during construction.

本発明の実施の形態について、その実施の形態に基づき具体的に説明したが、これに限定されるものではなく、その要旨を逸脱しない範囲で種々変更可能である。   Although the embodiment of the present invention has been specifically described based on the embodiment, the present invention is not limited to this, and various modifications can be made without departing from the scope of the invention.

1 堤体
2 貫通穴
3 ダム堤体上流面
4 開口
4a 貫通穴の開口予定位置
5 水底地盤(水底部)
6 孔
7 止水材
10 ドーム体
21 開口
24 外周面
25 内空
27 給気バルブ
28 マンホール
29 排水バルブ
30 リブ材
31 連結構造
32 プレート
33 フッキング用孔
45 空気管
46 ベルマウス
47 閉鎖ゲート扉体用戸当り
48 放流管
49 閉鎖ゲート扉体
60 アンカー
61 フック
100 仮締切構造
120 アンカー体
130 引張り部
131 テンドン
132 シース
140 アンカー頭部
141 定着具
142 支圧板
DESCRIPTION OF SYMBOLS 1 Bank body 2 Through-hole 3 Dam dam body upstream surface 4 Opening 4a Planned opening position of through-hole 5 Water bottom ground (water bottom)
6 hole 7 water stop material 10 dome body 21 opening 24 outer peripheral surface 25 inner air 27 air supply valve 28 manhole 29 drainage valve 30 rib material 31 connection structure 32 plate 33 hooking hole 45 air pipe 46 bell mouth 47 for closed gate door body 48 per door 48 discharge pipe 49 closed gate door body 60 anchor 61 hook 100 temporary closing structure 120 anchor body 130 tension part 131 tendon 132 sheath 140 anchor head 141 fixing tool 142 bearing plate

Claims (1)

既存ダム堤体での貫通穴構築に際し用いる仮締切構造であり、
前記貫通穴の開口予定位置を囲むようにダム堤体上流面に開口が当接するドーム体と、
ダム堤体上流側の水底部に打設され、前記ドーム体と連結されたアンカーと、
からなることを特徴とするダム堤体の仮締切構造。
It is a temporary deadline structure used when constructing a through hole in an existing dam body.
A dome body in which the opening contacts the upstream surface of the dam dam body so as to surround the planned opening position of the through hole;
An anchor placed on the bottom of the dam body upstream and connected to the dome body;
A temporary closing structure of a dam body characterized by comprising
JP2011247783A 2011-11-11 2011-11-11 Temporary deadline structure of dam body Active JP5789489B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2011247783A JP5789489B2 (en) 2011-11-11 2011-11-11 Temporary deadline structure of dam body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2011247783A JP5789489B2 (en) 2011-11-11 2011-11-11 Temporary deadline structure of dam body

Publications (2)

Publication Number Publication Date
JP2013104203A JP2013104203A (en) 2013-05-30
JP5789489B2 true JP5789489B2 (en) 2015-10-07

Family

ID=48623970

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2011247783A Active JP5789489B2 (en) 2011-11-11 2011-11-11 Temporary deadline structure of dam body

Country Status (1)

Country Link
JP (1) JP5789489B2 (en)

Also Published As

Publication number Publication date
JP2013104203A (en) 2013-05-30

Similar Documents

Publication Publication Date Title
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN103507109B (en) Underwater dry type cutting cabin and application method thereof
JP4910200B2 (en) Sectional repair method for concrete structures
CN107059857A (en) Steel pile casting follow-up method under the conditions of deep water inclined scar
CN107142954B (en) Steel hanging box lifting system for integral lifting and lifting method thereof
JP5903877B2 (en) Temporary deadline construction method for dam body
CN205224036U (en) Device is abolished to bridge pile foundation pile head
JP2008208533A (en) Caisson and its construction method
CN106968252B (en) Pile pulling recharging method and pile pulling recharging system
JP5789489B2 (en) Temporary deadline structure of dam body
CN209066508U (en) Cross the existing electric power piping lane protection structure of tunnel foundation pit
JP5898915B2 (en) Temporary deadline structure of dam body
KR100422216B1 (en) The method of construction prevening a waterflow of cassion basis for a bridge
KR100880367B1 (en) Process for constructing diffuser in the water
CN206554106U (en) Conehead muscle body posttension pile foundation
KR20200043719A (en) Supporting apparatus for marine structure
CN210797531U (en) Ground is wall anchor muscle protection architecture even
CN113431081A (en) Integral ship-leaning anti-collision structure of offshore wind power multi-pile foundation and construction method
CN203527525U (en) Underwater dry type cutting cabin
JP6214808B1 (en) Submarine pipeline landing method
JP5853646B2 (en) Temporary deadline structure of dam body
TW200417661A (en) Method for constituting a vertical well in water﹑vertical well in water﹑method for connection of a vertical well and a harizontal well﹑and construction of a well
JP2011084923A (en) Water sealing structure of steel pipe pile foundation, and method for constructing steel pipe pile foundation
CN112095748A (en) Rapid construction method for non-stop butt joint of newly-built sewage pipeline and operation pipeline
JPH09209361A (en) Pilingh method in pit structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20141020

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20150622

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20150707

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20150803

R150 Certificate of patent or registration of utility model

Ref document number: 5789489

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250