JP5371791B2 - Pile holder trolley and pile driving method - Google Patents

Pile holder trolley and pile driving method Download PDF

Info

Publication number
JP5371791B2
JP5371791B2 JP2010000576A JP2010000576A JP5371791B2 JP 5371791 B2 JP5371791 B2 JP 5371791B2 JP 2010000576 A JP2010000576 A JP 2010000576A JP 2010000576 A JP2010000576 A JP 2010000576A JP 5371791 B2 JP5371791 B2 JP 5371791B2
Authority
JP
Japan
Prior art keywords
pile
pile holder
ship
crane
holder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2010000576A
Other languages
Japanese (ja)
Other versions
JP2011140754A (en
Inventor
宏 飯田
琢 斉藤
康裕 仲
彌太郎 中村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toa Corp
Original Assignee
Toa Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toa Corp filed Critical Toa Corp
Priority to JP2010000576A priority Critical patent/JP5371791B2/en
Publication of JP2011140754A publication Critical patent/JP2011140754A/en
Application granted granted Critical
Publication of JP5371791B2 publication Critical patent/JP5371791B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a pile holder barge which enables pile driving even for a normal crane barge, and a pile driving method using the pile holder barge. <P>SOLUTION: The non-self-navigation type pile holder barge 1, on which a pile holder 2 is installed, is lifted by a crane of the crane barge 10; and a barge-side fitting member 8, which is fixed to the barge edge of the pile holder barge 1, is fitted in a vertically sliding manner to a work barge-side fitting member 13 which is fixed to a barge edge of the crane barge 10. Thus, the pile holder barge 1 is secured to the barge edge of the crane barge 10; and a pile 14a, which is held in a vertically movable manner by the pile holder 2 installed on the pile holder barge 1, is driven into underwater ground by means of a hammer device 12 suspended by the crane. <P>COPYRIGHT: (C)2011,JPO&amp;INPIT

Description

本発明は、パイルホルダー台船および杭の打設方法に関し、さらに詳しくは、通常のクレーン船であっても杭の打設を行なえるようにするパイルホルダー台船およびこのパイルホルダー台船を用いた杭の打設方法に関するものである。   TECHNICAL FIELD The present invention relates to a pile holder trolley and a pile driving method, and more particularly, to a pile holder trolley that enables a pile to be driven even with an ordinary crane ship, and the pile holder trolley. This is related to the method of placing the pile.

海等の水底に杭を打設するには、杭を打ち込むハンマー装置を吊り上げるクレーンを備えた杭打ち船が用いられている。この杭打ち船には、打設する杭を保持するパイルホルダー(杭保持機構)が艤装されている(例えば、特許文献1、2参照)。水底地盤に立てた状態の杭を、パイルホルダーによって所定位置で所定方向に保持することにより、予め計画したどおりの位置および向きで精度よく水底に打設することが可能になる。   In order to drive a pile to the bottom of the sea or the like, a pile driving ship equipped with a crane that lifts a hammer device for driving the pile is used. This pile driving ship is equipped with a pile holder (pile holding mechanism) for holding a pile to be placed (for example, see Patent Documents 1 and 2). By holding the pile standing on the bottom of the water bottom in a predetermined direction at a predetermined position by a pile holder, it is possible to place the pile on the bottom of the water with high accuracy in the position and orientation as planned in advance.

このようにパイルホルダーは杭の打設には不可欠な機構なので、パイルホルダーを艤装した杭打ち船が必要であり、或いは、杭を打設するためにクレーン船にパイルホルダーを艤装する必要があり、コスト負担が大きくなるという問題があった。また、例えば、現場の都合で早急に杭の打設を行なう必要が生じた場合、パイルホルダーを艤装した杭打ち船の手配が間に合わないことや杭打ち船の数が足りないことがあり、現場の要求に迅速に対応できないことがあった。   In this way, the pile holder is an indispensable mechanism for driving piles, so a pile driving ship equipped with a pile holder is necessary, or a pile holder needs to be installed on a crane ship to drive piles. There was a problem that the cost burden increased. In addition, for example, if it is necessary to drive piles immediately due to circumstances at the site, arrangements for pile driving boats equipped with pile holders may not be in time, or the number of pile driving boats may be insufficient. In some cases, it was impossible to respond quickly to the request.

特開昭61−113926号公報JP 61-1113926 A 特開2003−119783号公報JP 2003-119784 A

本発明の目的は、通常のクレーン船であっても杭の打設を行なえるようにするパイルホルダー台船およびこのパイルホルダー台船を用いた杭の打設方法を提供することにある。   An object of the present invention is to provide a pile holder trolley capable of driving piles even with an ordinary crane ship, and a pile driving method using the pile holder trolley.

上記目的を達成するためパイルホルダー台船は、クレーンを備えた作業船の船縁に固結する固結手段を有し、船上にパイルホルダーを設置した非自航式であることを特徴とするものである。   In order to achieve the above-mentioned object, the pile holder trolley is a non-self-propelled type having a consolidation means to be consolidated to the rim of a work ship equipped with a crane and having a pile holder installed on the ship. It is.

ここで、前記固結手段が、パイルホルダー台船の船縁に固定された台船側嵌合部材であり、この台船側嵌合部材を、前記クレーンを備えた作業船の船縁に固定された作業船側嵌合部材に対して上下スライドさせて嵌合する構成にすることもできる。前記パイルホルダーを台船上に移動可能、かつ旋回可能に設置するともに、鉛直に対して所定の角度範囲内で任意の角度で傾斜可能な構成にすることもできる。前記パイルホルダーの支柱に、打設する杭を保持する保持アームを上下方向に間隔をあけて複数設け、上下の保持アームと保持アームの間で、前記支柱を折り曲げ可能な構成にすることもできる。例えば、前記保持アームの数が3つ以上にして、支柱を折り曲げる位置よりも上方側に複数の保持アームを設けることもできる。   Here, the consolidation means is a base ship side fitting member fixed to a ship edge of a pile holder base ship, and the base ship side fitting member is fixed to a ship edge of a work ship equipped with the crane. It can also be set as the structure which slides up and down with respect to a fitting member, and is fitted. The pile holder can be installed on the carriage so as to be movable and turnable, and the pile holder can be tilted at an arbitrary angle within a predetermined angle range with respect to the vertical. A plurality of holding arms for holding piles to be placed can be provided on the pile holder column at intervals in the vertical direction, and the column can be bent between the upper and lower holding arms. . For example, the number of the holding arms may be three or more, and a plurality of holding arms may be provided above the position where the support column is bent.

本発明の杭の打設方法は、クレーンを備えた作業船の船縁に、パイルホルダーを設置した非自航式のパイルホルダー台船を固結し、前記クレーンに吊ったハンマー装置を用いて、前記パイルホルダー台船に設置したパイルホルダーによって保持している杭を水中地盤に打設することを特徴とするものである。   In the pile driving method of the present invention, a non-self-propelled pile holder base ship having a pile holder is fixed to the rim of a work ship equipped with a crane, and a hammer device suspended on the crane is used. A pile held by a pile holder installed on the pile holder trolley is driven on the underwater ground.

ここで、前記パイルホルダー台船を前記作業船のクレーンにより吊り上げて、パイルホルダー台船の船縁に固定された台船側嵌合部材を、前記作業船の船縁に固定された作業船側嵌合部材に対して上下にスライドさせて嵌合することにより、パイルホルダー台船を作業船の船縁に固結することもできる。   Here, the pile holder base ship is lifted by the crane of the work ship, and the base ship side fitting member fixed to the ship edge of the pile holder base ship is changed to the work ship side fitting member fixed to the ship edge of the work ship. On the other hand, the pile holder carriage can be fixed to the rim of the work ship by sliding it up and down.

本発明によれば、クレーンを備えた作業船の船縁に、パイルホルダーを船上に配置した非自航式のパイルホルダー台船を、固結手段を用いて固結することで、この作業船がパイルホルダーを艤装した杭打ち船と同様の仕様になる。これにより、作業船のクレーンで吊ったハンマー装置を用いて、パイルホルダー台船に設置したパイルホルダーによって保持している杭を水中地盤に打設することが可能になる。このように、パイルホルダーを艤装していない通常のクレーン船であっても、パイルホルダー台船を固結することで、現場の要求に迅速に対応して杭の打設を行なうことも可能になる。   According to the present invention, a non-self-propelled pile holder base ship in which a pile holder is arranged on the ship's edge is consolidated to the edge of a work ship equipped with a crane by using a consolidation means. The specifications are the same as a pile driving ship equipped with a pile holder. Thereby, it becomes possible to drive the pile currently hold | maintained by the pile holder installed in the pile holder base boat to the underwater ground using the hammer apparatus hung with the crane of the work ship. In this way, even a normal crane ship that is not equipped with pile holders can be piled up quickly in response to on-site requirements by caulking the pile holder carrier. Become.

クレーン船の船縁に固結されている本発明のパイルホルダー台船を例示する平面図である。It is a top view which illustrates the pile holder trolley of the present invention fixed to the ship's edge of a crane ship. 図1のパイルホルダー台船を例示する平面図である。It is a top view which illustrates the pile holder trolley of FIG. パイルホルダー台船をクレーン船の船縁に固結する工程を例示する側面図である。It is a side view which illustrates the process of solidifying a pile holder trolley to the edge of a crane ship. クレーン船の側面図である。It is a side view of a crane ship. 杭を保持しているパイルホルダーを例示する平面図である。It is a top view which illustrates the pile holder holding the pile. 図5の側面図である。FIG. 6 is a side view of FIG. 5. 杭を斜めに保持しているパイルホルダー台船を例示する側面図である。It is a side view which illustrates the pile holder trolley holding the pile diagonally. 杭を斜めに打設している状態を例示する側面図である。It is a side view which illustrates the state which has piled up diagonally. 支柱を折り曲げた状態のパイルホルダーを例示する側面図である。It is a side view which illustrates the pile holder of the state which bent the support | pillar. 継打ちする杭を保持しているパイルホルダー台船を例示する側面図である。It is a side view which illustrates the pile holder trolley holding the pile to be spliced. 杭を継打ちする工程を例示する側面図である。It is a side view which illustrates the process of splicing a pile.

以下、本発明のパイルホルダー台船および杭の打設方法を図に示した実施形態に基づいて説明する。   Hereinafter, a pile holder trolley and a pile placing method of the present invention will be described based on the embodiments shown in the drawings.

図1、図2に例示するように、本発明のパイルホルダー台船1は推進機構が備わっていない非自航式の台船であり、その船縁には台船側嵌合部材8が固定されている。クレーン船10の船縁には作業船側嵌合部材13が固定されている。台船側嵌合部材8を作業船側嵌合部材13に嵌合することにより、パイルホルダー台船1がクレーン船10の船縁に強固に連結(剛結合)される構造になっている。このように台船側嵌合部材8は、パイルホルダー台船1をクレーン船10の船縁に固結する固結手段として機能する。   As illustrated in FIGS. 1 and 2, the pile holder carrier 1 according to the present invention is a non-self-propelled carrier with no propulsion mechanism, and a carrier-side fitting member 8 is fixed to the ship edge. Yes. A work ship side fitting member 13 is fixed to the rim of the crane ship 10. By fitting the carrier side fitting member 8 to the work vessel side fitting member 13, the pile holder carrier 1 is firmly connected (rigidly coupled) to the rim of the crane vessel 10. In this way, the carrier-side fitting member 8 functions as a consolidation means for solidifying the pile holder carrier 1 to the edge of the crane ship 10.

この実施形態では、台船側嵌合部材8はC字状の金属フレームで構成されている。作業船側嵌合部材13は、台船側嵌合部材8に嵌り込むT字状の金属体で構成されている。したがって、台船側嵌合部材8を作業船側嵌合部材13に対して上下スライドさせることで両者が嵌合するようになっている。台船側嵌合部材8と作業船側嵌合部材13とを互いに反対の形状にしてもよい。固結手段はこの実施形態の構造に限定されず、パイルホルダー台船1とクレーン船10を固結できる種々の構造を採用することができる。   In this embodiment, the carrier side fitting member 8 is formed of a C-shaped metal frame. The work ship side fitting member 13 is configured by a T-shaped metal body that is fitted into the trolley side fitting member 8. Accordingly, the base boat side fitting member 8 is slid up and down with respect to the work boat side fitting member 13 so as to be fitted together. The base boat side fitting member 8 and the work boat side fitting member 13 may have opposite shapes. The consolidation means is not limited to the structure of this embodiment, and various structures that can solidify the pile holder carrier 1 and the crane ship 10 can be adopted.

パイルホルダー台船1をクレーン船10の船縁に固結する場合は、図3に例示するようにクレーン11を用いてパイルホルダー台船1を吊り上げて所定位置(嵌合させる作業船側嵌合部材13の位置)まで移動させる。次いで、その位置でパイルホルダー台船1を下方移動させて台船側嵌合部材8を作業船側嵌合部材13に対して上下にスライドさせて嵌合する。これにより、パイルホルダー台船1がクレーン船10の船縁に固結される。   When solidifying the pile holder trolley 1 to the rim of the crane ship 10, the pile holder trolley 1 is lifted by using the crane 11 as illustrated in FIG. To the position). Next, the pile holder base boat 1 is moved downward at that position, and the base boat side fitting member 8 is slid up and down with respect to the work boat side fitting member 13 to be fitted. As a result, the pile holder carrier 1 is consolidated to the rim of the crane ship 10.

パイルホルダー台船1が固結されるクレーン船10は、クレーン11を備えているがパイルホルダーを儀装していない通常のクレーン船10である。 尚、クレーン船10とは、クレーン11を備えた作業船であり、船上に予めクレーン10が固設されている作業船や移動式のクレーン車両を載置した作業船である。   The crane ship 10 to which the pile holder carrier 1 is consolidated is a normal crane ship 10 having a crane 11 but not equipped with a pile holder. The crane ship 10 is a work ship provided with a crane 11, and is a work ship in which a crane 10 is fixed in advance or a mobile crane vehicle.

図2、図5、図6に例示するようにパイルホルダー台船1の船上にパイルホルダー2が設置されている。パイルホルダー2の具体的な構成は以下のとおりである。   As illustrated in FIGS. 2, 5, and 6, the pile holder 2 is installed on the pile holder carrier 1. The specific configuration of the pile holder 2 is as follows.

パイルホルダー台船1の上にはレール6bが台船の前後方向に延設されており、このレール6bに上にローラ6aを介してベース7aが載置されている。ベース7aは油圧シリンダ6cのロッドの進退によってレール6bに沿って台船の前後方向に移動可能に設置されている。   A rail 6b extends on the pile holder carrier 1 in the longitudinal direction of the carrier, and a base 7a is placed on the rail 6b via a roller 6a. The base 7a is installed so as to be movable in the front-rear direction of the carriage along the rail 6b as the rod of the hydraulic cylinder 6c advances and retreats.

ベース7aの上にはスライドベース7bが台船の幅方向に移動可能に設置されている。スライドベース7bには旋回台5が設置されている。旋回台5の上にはケーシング9aが固定され、旋回可能なケーシング9aにはスライド部材9bが内設されている。スライド部材9bは、その後端部に接続された油圧シリンダ9cのロッドの進退によって、ケーシング9aの長手方向に移動して、ケーシング9aの先端から突出するように構成されている。   A slide base 7b is installed on the base 7a so as to be movable in the width direction of the carriage. A swivel base 5 is installed on the slide base 7b. A casing 9a is fixed on the turntable 5, and a slide member 9b is provided in the turnable casing 9a. The slide member 9b is configured to move in the longitudinal direction of the casing 9a and protrude from the front end of the casing 9a as the rod of the hydraulic cylinder 9c connected to the rear end thereof moves forward and backward.

スライド部材9bの先端部には回転軸3aを介して支柱3が立設するように取り付けられている。この支柱3には、スライド部材9bの上に後端部が回転可能に固定された油圧シリンダ9dの先端部が回転可能に固定されている。したがって、油圧シリンダ9dのロッドの進退によって、支柱3は回転軸3aを中心にして前後方向に回転するようになっている。   The support column 3 is attached to the front end portion of the slide member 9b through the rotating shaft 3a. A front end portion of a hydraulic cylinder 9d, whose rear end portion is rotatably fixed on the slide member 9b, is rotatably fixed to the column 3. Therefore, as the rod of the hydraulic cylinder 9d advances and retreats, the column 3 rotates in the front-rear direction about the rotation shaft 3a.

支柱3には、打設する杭14aを保持する3つの保持アーム4A、4B、4Cが上下方向に間隔をあけて設けられている。保持アーム4A、4B、4Cの数は複数であればよく、3つに限定されるものではない。   The support column 3 is provided with three holding arms 4A, 4B, and 4C that hold a pile 14a to be placed at intervals in the vertical direction. The number of holding arms 4A, 4B, and 4C may be plural, and is not limited to three.

それぞれの保持アーム4A、4B、4Cはすべて同じ構造であり、一対の円弧状のアーム部4m、4mを有している。一対のアーム部4m、4mは支軸を中心に回動して図2に例示するように開いた状態から図5に例示するように閉じた状態になる。   Each holding arm 4A, 4B, 4C has the same structure and has a pair of arc-shaped arm portions 4m, 4m. The pair of arm portions 4m and 4m are rotated about the support shaft to be in a closed state as illustrated in FIG. 5 from an open state as illustrated in FIG.

それぞれのアーム部4m、4mの内周面には保持ローラ4r、4rが設けられている。それぞれの保持ローラ4rは、アーム部4mの内周面からの突出量を変更できるように移動可能に設けられている。   Holding rollers 4r and 4r are provided on the inner peripheral surfaces of the respective arm portions 4m and 4m. Each holding roller 4r is movably provided so that the amount of protrusion from the inner peripheral surface of the arm portion 4m can be changed.

一対のアーム部4m、4mを閉じ、保持ローラ4rを杭14aの外周面に当接させることにより、杭14aが保持アーム4A、4B、4C(パイルホルダー2)によって上下方向に移動可能に保持される。ここで、それぞれの保持ローラ4rは杭14aの半径方向に移動できるので、保持ローラ4rの移動範囲内で外径の異なる杭14aを保持アーム4A、4B、4Cにより保持することができる。   By closing the pair of arm portions 4m and 4m and bringing the holding roller 4r into contact with the outer peripheral surface of the pile 14a, the pile 14a is held movably in the vertical direction by the holding arms 4A, 4B and 4C (pile holder 2). The Here, since each holding roller 4r can move in the radial direction of the pile 14a, the piles 14a having different outer diameters can be held by the holding arms 4A, 4B, and 4C within the moving range of the holding roller 4r.

また、この実施形態では、上下の保持アーム4Bと保持アーム4Cの間で、支柱3が折り曲げ可能な構成になっている。   In this embodiment, the support column 3 can be bent between the upper and lower holding arms 4B and 4C.

パイルホルダー2は上記のように構成されているので、パイルホルダー台船1上で任意の位置に移動可能で、かつ旋回可能に設置されている。また、パイルホルダー2を構成する支柱3は鉛直に対して所定の角度範囲内で任意の角度で傾斜可能に構成されている。   Since the pile holder 2 is configured as described above, the pile holder 2 can be moved to an arbitrary position on the pile holder carrier 1 and can be turned. Moreover, the support | pillar 3 which comprises the pile holder 2 is comprised so that it can incline at arbitrary angles within the predetermined angle range with respect to the perpendicular | vertical.

次に、パイルホルダー台船1を用いて杭を水中地盤に打設する方法を説明する。   Next, a method for placing a pile on the underwater ground using the pile holder carrier 1 will be described.

まず、施工現場にて、パイルホルダー台船1を上記した手順により、クレーン船10の所定の位置の船縁に固結手段を用いて固結させる。パイルホルダー台船1は、施工現場までクレーン船10や他の船で曳航することもできるが、クレーン船10に搭載して施工現場まで搬送することもできる。   First, at the construction site, the pile holder trolley 1 is consolidated to a ship edge at a predetermined position of the crane ship 10 by using the above-described procedure. The pile holder carrier 1 can be towed to the construction site by the crane ship 10 or another ship, but can also be carried on the crane ship 10 and transported to the construction site.

次いで、それぞれの保持アーム4A、4B、4Cを構成する一対のアーム部4m、4mを開いた状態にする。ここで、打設する杭14aをクレーン11のワイヤ11aにより吊って、開いた状態の一対のアーム部4m、4mの内部に配置する。次いで、一対のアーム部4m、4mを閉じた状態にして保持アーム4A、4B、4Cにより、杭14aを上下移動可能に保持する。次いで、パイルホルダー2(杭14a)を、その位置および向き(傾斜)を所望の設定にする。   Next, the pair of arm portions 4m and 4m constituting the holding arms 4A, 4B and 4C are opened. Here, the pile 14a to be laid is suspended by the wire 11a of the crane 11 and disposed inside the pair of arm portions 4m and 4m in an open state. Next, the piles 14a are held so as to be vertically movable by the holding arms 4A, 4B, and 4C with the pair of arm portions 4m and 4m being closed. Next, the pile holder 2 (pile 14a) is set to a desired position and orientation (tilt).

その後、図4に例示するようにクレーン11のワイヤ11aによってハンマー装置12が吊られる。ハンマー装置12の下端にはガイドスリーブ12aが設けられる。そして、図6に例示するようにパイルホルダー2によって保持されている杭14aの上端にガイドスリーブ12aが取り付けられる。このようにして、クレーン11によって吊下げられたハンマー装置12によって杭14aが水中地盤に打ち込まれる。   Thereafter, the hammer device 12 is suspended by the wire 11a of the crane 11 as illustrated in FIG. A guide sleeve 12 a is provided at the lower end of the hammer device 12. And the guide sleeve 12a is attached to the upper end of the pile 14a currently hold | maintained by the pile holder 2 so that it may illustrate in FIG. In this way, the pile 14a is driven into the underwater ground by the hammer device 12 suspended by the crane 11.

杭14aの打ち込みが進むに連れて、ガイドスリーブ12aが保持アーム4A、4Bに近づいてくる。そこで、順次、保持アーム4A、4Bのアーム部4m、4mを開いた状態にして保持アーム4A、4Bとガイドスリーブ12aとの干渉を回避して杭14aの打ち込みを進める。   As the pile 14a is driven, the guide sleeve 12a approaches the holding arms 4A and 4B. Therefore, the arm portions 4m and 4m of the holding arms 4A and 4B are sequentially opened to avoid interference between the holding arms 4A and 4B and the guide sleeve 12a, and the driving of the pile 14a is advanced.

このようにパイルホルダー2を艤装していない通常のクレーン船10であっても、パイルホルダー台船1を船縁に固結することで杭14aの打設を行なうことができるようになる。それ故、現場の要求に迅速に対応して杭14aの打設を行なうことも可能になる。   Thus, even if it is the normal crane ship 10 which does not equip the pile holder 2, the pile 14a can be driven by solidifying the pile holder carrier 1 to the ship's edge. Therefore, it is also possible to drive the pile 14a in response to a request from the site quickly.

また、パイルホルダー台船1を固結する位置を変更するだけで、他の位置にも杭14aを打設することも可能になる。従来のように、クレーン船10を移動させて杭14aの打設位置を変更しようとすると、クレーン船10のアンカーを引き揚げて再度新たな場所にアンカーを投錨する必要があるので、非常に時間と手間を要する。ところが本発明によれば、クレーン船10を移動させることなく、パイルホルダー台船1を固結する位置を変更するだけで他の位置での杭14aの打設が行なえるので、クレーン船10の移動頻度を抑えることができ、作業効率の向上にも有利になる。   Moreover, it is also possible to place piles 14a at other positions simply by changing the position at which the pile holder carrier 1 is consolidated. When the crane ship 10 is moved and the driving position of the pile 14a is changed as in the prior art, it is necessary to lift the anchor of the crane ship 10 and throw the anchor again at a new location. It takes time and effort. However, according to the present invention, it is possible to place the pile 14a at another position by simply changing the position where the pile holder carrier 1 is consolidated without moving the crane ship 10. The frequency of movement can be suppressed, which is advantageous for improving work efficiency.

支柱3は回転軸3aを中心にして回転して、鉛直に対して所定の角度範囲内で任意の角度で傾斜可能に構成されているので、図6に例示するように杭14aを鉛直に打設するだけでなく、図7に例示するように傾斜させて打設することもできる。杭14aが打ち込まれるに連れて、ガイドスリーブ12aが保持アーム4A、4Bに近づいてくるので、保持アーム4A、4Bとガイドスリーブ12aとの干渉を回避するため、図8に例示するように、順次保持アーム4A、4Bを開いた状態にして杭14aの打ち込みを進める。   The column 3 rotates around the rotation axis 3a and can be tilted at an arbitrary angle within a predetermined angle range with respect to the vertical, so that the pile 14a is hit vertically as illustrated in FIG. In addition to providing, it is possible to place it in an inclined manner as illustrated in FIG. As the pile 14a is driven, the guide sleeve 12a approaches the holding arms 4A and 4B. Therefore, in order to avoid interference between the holding arms 4A and 4B and the guide sleeve 12a, as illustrated in FIG. Driving the pile 14a is advanced with the holding arms 4A and 4B opened.

図8に例示するように、杭14aをパイルホルダー台船1の下方に入り込むように打設する場合は、打ち込みが進むに連れてハンマー装置12を吊っているワイヤ11aが支柱3と干渉し易くなる。そこで、図9に例示するように支柱3を長手方向中途(保持アーム4Bと4Cの間)で折り曲げて、折り曲げ位置よりも上方側の支柱3の部分をワイヤ11aから離れる方向に回動させる。このように上下の保持アーム4Bと4Cの間で、支柱3を折り曲げ可能な構成にすることにより、ワイヤ11aと支柱3とが干渉することなく、杭14aの打設を進めることができる。   As illustrated in FIG. 8, when the pile 14 a is driven so as to enter the lower part of the pile holder carriage 1, the wire 11 a hanging the hammer device 12 easily interferes with the column 3 as the driving proceeds. Become. Therefore, as shown in FIG. 9, the support column 3 is bent halfway in the longitudinal direction (between the holding arms 4B and 4C), and the portion of the support column 3 above the bending position is rotated away from the wire 11a. In this way, by placing the support column 3 between the upper and lower holding arms 4B and 4C, the pile 14a can be driven without interfering with the wire 11a and the support column 3.

既に水中地盤に打設した杭14aに対して新たな杭14bを継打ちする場合は、図10に例示するように回動させて鉛直に立設させた状態の支柱3の部分の保持アーム4A、4Bに対して、クレーン11のワイヤ11aによって吊った新たな杭14bを近づける。そして、それぞれの保持アーム4A、4Bの開いた状態の一対のアーム部4m、4mの内部に杭14bを配置する。次いで、一対のアーム部4m、4mを閉じた状態にして保持アーム4A、4Bにより、杭14bを保持した状態にする。   When a new pile 14b is spliced to a pile 14a that has already been placed on the underwater ground, as shown in FIG. 10, the holding arm 4A of the portion of the column 3 that has been rotated and erected vertically is illustrated. The new pile 14b suspended by the wire 11a of the crane 11 is brought close to 4B. And the pile 14b is arrange | positioned inside a pair of arm part 4m and 4m in the state where each holding arm 4A and 4B was opened. Next, the pair of arm portions 4m and 4m are closed, and the pile 14b is held by the holding arms 4A and 4B.

次いで、新たな杭14bをワイヤ11aで吊りつつ、鉛直に立設させた状態の支柱3の部分を傾斜させて、折り曲げ位置よりも上側の支柱3の部分と、折り曲げ位置よりも下側の支柱3の部分との傾斜を一致させる。これにより、新たな杭14bは既に打設された杭14aと同じ傾斜で直結した状態にセッティングされる。   Next, while hanging a new pile 14b with the wire 11a, the portion of the column 3 in a vertically standing state is tilted, and the portion of the column 3 above the folding position and the column below the folding position The inclination with the portion 3 is matched. Thereby, the new pile 14b is set to the state directly connected with the same inclination as the already piled pile 14a.

次いで、図11に例示するように新たな杭14bの上端にガイドスリーブ12aを介してハンマー装置12を取り付けて杭14bの打設を行なう。この実施形態では、支柱3に3つの保持アーム4A、4B、4Cを設け、支柱3を折り曲げる位置よりも上方側に2つの保持アーム4A、4Bを設けるように構成しているので、継打ちする新たな杭14bを2つの保持アーム4A、4Bにより安定して保持することができ、また、既に打設された杭14aと同じ傾斜になるようにセッティングする作業も容易になる。このように支柱3に3つ以上の保持アーム4A、4B、4Cを設け、支柱3を折り曲げる位置よりも上方側に複数の保持アーム4A、4Bを設けるように構成すると、新たな杭14bの継打ちを精度よく効率的に行なうには有利になる。   Next, as illustrated in FIG. 11, the hammer device 12 is attached to the upper end of the new pile 14b via the guide sleeve 12a, and the pile 14b is driven. In this embodiment, the support column 3 is provided with three holding arms 4A, 4B, and 4C, and the two holding arms 4A and 4B are provided above the position where the support column 3 is bent. The new pile 14b can be stably held by the two holding arms 4A and 4B, and the setting operation so as to have the same inclination as the pile 14a already placed is facilitated. In this way, when three or more holding arms 4A, 4B, and 4C are provided on the column 3 and a plurality of holding arms 4A and 4B are provided above the position where the column 3 is bent, a new pile 14b is joined. It is advantageous to perform hitting accurately and efficiently.

また、このパイルホルダー台船1は、クレーン船10とは別の独立した油圧系統を備えている。パイルホルダー台船1に備わった油圧シリンダ6c、9c、9d等の油圧機器を作動させるために、これら油圧機器をクレーン船10の油圧系統(油圧ポンプ等)と油圧ホースで連結した構造にすることもできるが、油圧ホースが破損等した場合、作動油が漏洩して水中に拡散する危険性がある。そこで、この実施形態のようにパイルホルダー台船1に、自己の油圧機器を作動させる油圧系統を備えることで、このような作動油による水質汚染を防止することが可能になる。   Further, the pile holder trolley 1 includes an independent hydraulic system different from the crane ship 10. In order to operate hydraulic equipment such as the hydraulic cylinders 6c, 9c, 9d provided in the pile holder carrier 1, these hydraulic equipments are connected to the hydraulic system (such as a hydraulic pump) of the crane ship 10 by a hydraulic hose. However, if the hydraulic hose is damaged, there is a risk that the hydraulic oil will leak and diffuse into the water. Therefore, by providing the pile holder carrier 1 with a hydraulic system that operates its own hydraulic equipment as in this embodiment, it is possible to prevent water contamination due to such hydraulic oil.

1 パイルホルダー台船
2 パイルホルダー
3 支柱
3a 回転軸
4A、4B、4C 保持アーム
4m アーム部
4r 保持ローラ
5 旋回台
6a ローラ
6b レール
6c 油圧シリンダ
7a ベース
7b スライドベース
8 台船側嵌合部材
9a ケーシング
9b スライド部材
9c、9d 油圧シリンダ
10 クレーン船
11 クレーン
11a ワイヤ
12 ハンマー装置
12a ガイドスリーブ
13 作業船側嵌合部材
14a、14b 杭
DESCRIPTION OF SYMBOLS 1 Pile holder base ship 2 Pile holder 3 Post 3a Rotating shaft 4A, 4B, 4C Holding arm 4m Arm part 4r Holding roller 5 Swivel base 6a Roller 6b Rail 6c Hydraulic cylinder 7a Base 7b Slide base 8 Standing side fitting member 9a Casing 9b Slide member 9c, 9d Hydraulic cylinder 10 Crane ship 11 Crane 11a Wire 12 Hammer device 12a Guide sleeve 13 Work ship side fitting member 14a, 14b Pile

Claims (7)

クレーンを備えた作業船の船縁に固結する固結手段を有し、船上にパイルホルダーを設置した非自航式であるパイルホルダー台船。   A non-self-propelled pile holder trolley that has consolidation means to be consolidated to the edge of a work ship equipped with a crane, and has a pile holder installed on the ship. 前記固結手段が、パイルホルダー台船の船縁に固定された台船側嵌合部材であり、この台船側嵌合部材を、前記クレーンを備えた作業船の船縁に固定された作業船側嵌合部材に対して上下スライドさせて嵌合する構成にした請求項1に記載のパイルホルダー台船。   The consolidation means is a base ship side fitting member fixed to a ship edge of a pile holder base ship, and this base ship side fitting member is fixed to a ship edge of a work ship equipped with the crane. The pile holder carrier according to claim 1, wherein the pile holder is configured to be slid up and down with respect to the fitting. 前記パイルホルダーを台船上に移動可能、かつ旋回可能に設置するともに、鉛直に対して所定の角度範囲内で任意の角度で傾斜可能な構成にした請求項1または2に記載のパイルホルダー台船。   3. The pile holder trolley according to claim 1, wherein the pile holder is configured to be movable and turnable on the trolley and to be inclined at an arbitrary angle within a predetermined angle range with respect to the vertical. . 前記パイルホルダーの支柱に、打設する杭を保持する保持アームを上下方向に間隔をあけて複数設け、上下の保持アームと保持アームの間で、前記支柱を折り曲げ可能な構成にした請求項3に記載のパイルホルダー台船。   4. A plurality of holding arms for holding piles to be placed are provided at intervals in the vertical direction on the pillar of the pile holder, and the pillar can be bent between the upper and lower holding arms. Pile holder trolley as described in. 前記保持アームの数が3つ以上であり、支柱を折り曲げる位置よりも上方側に複数の保持アームを設けた請求項4に記載のパイルホルダー台船。   The pile holder trolley according to claim 4, wherein the number of the holding arms is three or more, and a plurality of holding arms are provided above a position where the support column is bent. クレーンを備えた作業船の船縁に、パイルホルダーを設置した非自航式のパイルホルダー台船を固結し、前記クレーンで吊ったハンマー装置を用いて、前記パイルホルダー台船に設置したパイルホルダーによって保持している杭を水中地盤に打設する杭の打設方法。   A pile holder installed on the pile holder trolley using a hammer device, which is a non-self-propelled pile holder trolley with a pile holder attached to the rim of a work ship equipped with a crane, and suspended by the crane. A pile placing method in which a pile held by a stake is placed on the underwater ground. 前記パイルホルダー台船を前記作業船のクレーンにより吊り上げて、パイルホルダー台船の船縁に固定された台船側嵌合部材を、前記作業船の船縁に固定された作業船側嵌合部材に対して上下にスライドさせて嵌合することにより、パイルホルダー台船を作業船の船縁に固結する請求項6に記載の杭の打設方法。   The pile holder trolley is lifted by the crane of the work ship, and the pedestal side fitting member fixed to the ship rim of the pile holder trolley is vertically moved with respect to the work ship side fitting member fixed to the ship rim of the work ship. The pile placing method according to claim 6, wherein the pile holder carrier is consolidated to the rim of the work ship by sliding and fitting.
JP2010000576A 2010-01-05 2010-01-05 Pile holder trolley and pile driving method Active JP5371791B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010000576A JP5371791B2 (en) 2010-01-05 2010-01-05 Pile holder trolley and pile driving method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010000576A JP5371791B2 (en) 2010-01-05 2010-01-05 Pile holder trolley and pile driving method

Publications (2)

Publication Number Publication Date
JP2011140754A JP2011140754A (en) 2011-07-21
JP5371791B2 true JP5371791B2 (en) 2013-12-18

Family

ID=44456788

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010000576A Active JP5371791B2 (en) 2010-01-05 2010-01-05 Pile holder trolley and pile driving method

Country Status (1)

Country Link
JP (1) JP5371791B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196028A (en) * 2014-09-15 2014-12-10 中联重科股份有限公司 Piling equipment
JP6074017B1 (en) * 2015-11-30 2017-02-01 東亜建設工業株式会社 Pile driving system
CN109778839A (en) * 2019-03-18 2019-05-21 中铁四局集团有限公司 Construction system and construction method for the closely knit cobble coating steel-pipe pile of deep water

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392450A (en) * 2011-10-14 2012-03-28 江苏海上龙源风力发电有限公司 Special device for offshore wind power sunk pile righting guide frame
KR101382967B1 (en) 2012-01-12 2014-04-09 엄광수 pipe guide device for incline casing
JP5767131B2 (en) * 2012-02-08 2015-08-19 東亜建設工業株式会社 Pile driving construction management system
KR101230946B1 (en) * 2012-08-01 2013-02-07 주식회사 금호메카텍 Pipe guide device for incline casing
CN103334435B (en) * 2013-06-26 2015-05-20 上海振华重工(集团)股份有限公司 Multi-pile pile-embracing machine
CN105464117B (en) * 2015-12-25 2017-07-25 天津港航工程有限公司 Rotary marine piling saddle and multi-column pier foundation piling technique waterborne
NL2018066B1 (en) * 2016-12-23 2018-07-02 Itrec Bv A method for installation of a pile adapted to support an offshore wind turbine, wave-induced motion compensated pile holding system, vessel, and pile holder.
CN107152025A (en) * 2017-07-12 2017-09-12 赵魁 A kind of shallow sea piling frame net boat
CN107882028B (en) * 2017-11-18 2019-10-29 东台市巨力机械制造有限公司 A kind of caterpillar telescopic arm piling machine
NL2020536B1 (en) 2018-03-06 2019-09-13 Itrec Bv Pile holding system, vessel and pile installation method
KR102136144B1 (en) * 2017-12-26 2020-07-21 주식회사 포스코 Apparatus for installing plie of offshore structure
US11313096B2 (en) 2018-03-06 2022-04-26 Itrec B.V. Adjustable pile holding system, vessel and pile installation method
CN108867646B (en) * 2018-05-31 2021-08-10 武汉船用机械有限责任公司 Pile gripper
CN111994239B (en) * 2020-09-01 2022-02-08 覃晓军 Underwater component detection device for road and bridge of civil engineering and application method
CN112323801A (en) * 2020-09-30 2021-02-05 中船华南船舶机械有限公司 Control method of pile embracing machine
CN116605352B (en) * 2023-05-18 2023-12-19 建湖宝迪工程机械有限公司 Piling ship convenient to multidirectional adjustment
CN116605378B (en) * 2023-07-20 2023-09-22 中交一航局第一工程有限公司 Fuel oil monitoring system of large pile driving ship and large pile driving ship

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0412541U (en) * 1990-05-18 1992-01-31
JPH07197461A (en) * 1993-12-29 1995-08-01 Takenaka Komuten Co Ltd Pile driver, transferable base frame of pile driver and preventive device of diffusion of turbid water resulting from the pile drive and piling method thereof
JP3612267B2 (en) * 2000-07-26 2005-01-19 倉本鐵工株式会社 Split assembly work trolley

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104196028A (en) * 2014-09-15 2014-12-10 中联重科股份有限公司 Piling equipment
JP6074017B1 (en) * 2015-11-30 2017-02-01 東亜建設工業株式会社 Pile driving system
JP2017101413A (en) * 2015-11-30 2017-06-08 東亜建設工業株式会社 Pile driving system
CN109778839A (en) * 2019-03-18 2019-05-21 中铁四局集团有限公司 Construction system and construction method for the closely knit cobble coating steel-pipe pile of deep water

Also Published As

Publication number Publication date
JP2011140754A (en) 2011-07-21

Similar Documents

Publication Publication Date Title
JP5371791B2 (en) Pile holder trolley and pile driving method
JP7295862B2 (en) pile retention system
CN112088234B (en) Adjustable pile holding system, vessel and pile installation method
JP6074017B1 (en) Pile driving system
CN202828024U (en) Hoisting pile driving barge
EP2492402B1 (en) Device for manufacturing a foundation for a mass located at height, associated method and assembly of the device and a jack-up platform
JP5767131B2 (en) Pile driving construction management system
KR20160119125A (en) Pipe laying machine and pipe laying method
JP2017103995A (en) Supporting device for work vehicle
JP2009275395A (en) Pile construction apparatus
JPH07197461A (en) Pile driver, transferable base frame of pile driver and preventive device of diffusion of turbid water resulting from the pile drive and piling method thereof
JP6499789B1 (en) Electric pole former hole rebuilding device, electric pole former hole rebuilding vehicle and utility pole former hole rebuilding method
KR20160076084A (en) Barge for pile construction and pile construction method
JP4406375B2 (en) Pile placement method, trolley and placement guide used for this
JP2004027548A (en) Pile driving guide and pile driving method
JPS5925049B2 (en) Static load type pile driver
JP2521236B2 (en) Pile driving device for driving piles on the seabed
JP2006063684A (en) Pile driving boat and pile driving method
CN207108366U (en) A kind of car lift structure
JP4855067B2 (en) Welding device suspension
JP2003328322A (en) Erection method and erection apparatus for floor slab
JP2006132118A (en) Pile driver
JP6738779B2 (en) Pile driver and method of changing the posture of the pile driver
CN218779485U (en) Pile stabilizing system for offshore wind power pile foundation construction
JP2020090797A (en) Pile press-in machine

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20121109

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130821

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130827

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130917

R150 Certificate of patent or registration of utility model

Ref document number: 5371791

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250