JP5300549B2 - Construction method of earth structure - Google Patents

Construction method of earth structure Download PDF

Info

Publication number
JP5300549B2
JP5300549B2 JP2009069814A JP2009069814A JP5300549B2 JP 5300549 B2 JP5300549 B2 JP 5300549B2 JP 2009069814 A JP2009069814 A JP 2009069814A JP 2009069814 A JP2009069814 A JP 2009069814A JP 5300549 B2 JP5300549 B2 JP 5300549B2
Authority
JP
Japan
Prior art keywords
embankment
slope
water shielding
water
shielding material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2009069814A
Other languages
Japanese (ja)
Other versions
JP2009257074A (en
Inventor
彰宣 安藤
Original Assignee
旭化成ジオテック株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 旭化成ジオテック株式会社 filed Critical 旭化成ジオテック株式会社
Priority to JP2009069814A priority Critical patent/JP5300549B2/en
Publication of JP2009257074A publication Critical patent/JP2009257074A/en
Application granted granted Critical
Publication of JP5300549B2 publication Critical patent/JP5300549B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method of an earth structure advantageous in shutting off water from a face of slope having a vertical or almost vertical steep gradient. <P>SOLUTION: The construction method of the earth structure includes laying an impervious material 3 along the face of slope B and fixing it into mounded soil 13 in a stage where the mounded soil 13 reaches a height corresponding to the length of the impervious material 3 before reaching a target completion height by repeating laying of a banking reinforcing material 1, banking 13 and rolling compaction, and then repeating the above process to construct the impervious earth structure with the target completion height. <P>COPYRIGHT: (C)2010,JPO&amp;INPIT

Description

本発明は、廃棄物処分場や貯水構造物等に適用される遮水性を有する法面を構築する際に有利な土構造物の構築方法に関するものである。   The present invention relates to a method for constructing a soil structure that is advantageous when constructing a slope having water-impervious properties applied to a waste disposal site or a water storage structure.

廃棄物処分場や貯水構造物においては、水が土壌中に浸透することがないように底面及び法面を遮水することが行われる。最近の廃棄物処分場では、遮水性を有する法面を鉛直又は急勾配で構築することにより限られた用地で最大限の容積を確保することが求められている。   In a waste disposal site and a water storage structure, the bottom and slope are shielded so that water does not penetrate into the soil. In a recent waste disposal site, it is required to secure a maximum volume on a limited site by constructing a slope with water impermeability vertically or steeply.

このような要求を満足するために、種々の遮水性能を有する法面の構築方法が提案されている。例えば、特許文献1に記載された技術は、急勾配の遮水法面を有する廃棄物処分場などの造成に利用される補強土工法であり、崖地から離れた位置に基礎を設け、この基礎に擁壁を順次構築し、擁壁と崖地との間に遮水性盛土を施工し、これに補強材を埋設して先端を擁壁に連結し、その後、擁壁と盛土との間に間詰材を埋め戻すものである。この技術では、鉛直又は鉛直に近い急勾配の法面の補強土工法を実現することができる。   In order to satisfy such requirements, methods for constructing slopes having various water shielding performances have been proposed. For example, the technique described in Patent Document 1 is a reinforced earth method used for the construction of a waste disposal site having a steep water impervious slope, and a foundation is provided at a position away from a cliff. Build a retaining wall on the foundation in sequence, construct a water-impervious embankment between the retaining wall and the cliff, embed a reinforcing material in this, connect the tip to the retaining wall, and then between the retaining wall and the embankment The backfilling material is backfilled. With this technology, it is possible to realize a reinforced earth construction method with a steep slope close to vertical or near vertical.

また、特許文献2に記載された技術は、複数の遮水シートを敷設する作業を簡易に行うようにしたものであり、法面に敷設される複数の遮水シートを、各遮水シートの傾斜方向上流側の接続部分に於いて、傾斜方向上流側の遮水シートの下端部分を傾斜方向下流側の遮水シートの上面に重ねて配置するものである。   In addition, the technique described in Patent Document 2 is intended to easily perform the work of laying a plurality of water-impervious sheets, and a plurality of water-impervious sheets laid on a slope are attached to each of the water-impervious sheets. In the connecting portion on the upstream side in the tilt direction, the lower end portion of the water-impervious sheet on the upstream side in the tilt direction is arranged so as to overlap the upper surface of the water-impervious sheet on the downstream side in the tilt direction.

特開2004−232232号公報JP 2004-232232 A 特開平8−323318号公報JP-A-8-323318

特許文献1の技術は、補強材を埋設することにより補強したセメント安定材からなる遮水性盛土を構築することで、鉛直又は鉛直に近い急勾配の遮水性壁面を構築するものである。しかし、工事内容が煩雑であり、施工、養生にかかる期間が長い等の問題がある。   The technology of Patent Document 1 is to construct a vertical or vertical steep water-impervious wall surface by constructing a water-impervious embankment made of a cement stabilizing material reinforced by embedding a reinforcing material. However, there are problems such as complicated construction contents and a long period of time for construction and curing.

また特許文献2の技術は、法面上に複数の遮水シートを敷設する際の技術であるが、法面に対し遮水シートを固定する際に、固定釘を用いている。このため、引張力がかかった時に、固定釘の部分に応力が集中して、シートが引裂かれる虞がある。   Moreover, although the technique of patent document 2 is a technique at the time of laying a some water impervious sheet | seat on a slope, when fixing a water impervious sheet with respect to a slope, a fixing nail is used. For this reason, when a tensile force is applied, stress concentrates on the fixed nail portion and the sheet may be torn.

本発明の目的は、鉛直又は鉛直に近い急勾配を持った法面を遮水する際に有利な土構造物の構築方法を提供することにある。   An object of the present invention is to provide a method for constructing an earth structure that is advantageous when shielding a slope having a vertical or steep slope close to vertical.

上記課題を解決するために本発明に係る土構造物の構築方法は、盛土補強材の敷設、盛土、転圧を繰り返して目的の完成高さに到達する以前に、該盛土が遮水材の長さに対応する高さになった段階で、遮水材を法面に沿って敷設すると共に予め連結用シートが設けられた摩擦固定材に該連結用シートを介して連結することによって盛土内に固定し、その後、前記工程を繰り返して目的の完成高さを持った遮水性を持った土構造物を構築することを特徴とするものである。 In order to solve the above problems, the method for constructing a soil structure according to the present invention repeats the laying, embankment, and rolling of the embankment reinforcing material, and before the embankment reaches the desired finished height, In the embankment, when the height corresponding to the length is reached, a water-impervious material is laid along the slope and connected to a friction fixing material provided with a connecting sheet in advance via the connecting sheet . Then, the above-described process is repeated to construct a soil structure having a desired height and having a water barrier property.

また上記何れかの土構造物の構築方法に於いて、法面に敷設した遮水材同士を接続することにより一体化することを特徴とするものである。   In any one of the above-described methods for constructing a soil structure, the structure is integrated by connecting the water shielding materials laid on the slope.

また上記何れかの土構造物の構築方法に於いて、前記遮水材が、遮水シートと保護マット又は排水材を重ね合せ、一体化したものであることを特徴とするものである。   In any one of the above-described methods for constructing a soil structure, the water shielding material is a laminate of a water shielding sheet and a protective mat or drainage material, which are integrated.

本発明に係る土構造物の構築方法では、法面に遮水材を敷設する際に、構築中の盛土の上端から遮水材を法面に沿って敷設する作業を行うことができる。このため、鉛直又は鉛直に近い急勾配の法面に対する遮水材を施工する際にも、安全に且つ容易に作業を行うことができる。   In the construction method of the earth structure according to the present invention, when the water shielding material is laid on the slope, the work of laying the water shielding material along the slope from the upper end of the embankment under construction can be performed. For this reason, even when constructing a water shielding material for a vertical or steep slope close to vertical, the work can be performed safely and easily.

即ち、盛土補強材の敷設、盛土、転圧を繰り返しながら、該盛土が遮水材の長さに対応する高さになった段階で、遮水材を構築中の盛土の上端から法肩を経て法面にかけて敷設し、更にその上に盛土を構築することにより盛土内に固定するので、法面に対する遮水材の敷設作業を構築中の盛土の上端から行って、急勾配の法面であっても安全に且つ容易に作業を進めることができる。   That is, while repeating embankment reinforcement, embankment, and rolling, when the embankment reaches a height corresponding to the length of the impermeable material, the shoulder from the upper end of the embankment that is constructing the impermeable material After that, laying over the slope, and then fixing it in the embankment by constructing the embankment on it, perform the work of laying a water shielding material on the slope from the top of the embankment under construction, with a steep slope Even if it exists, the work can proceed safely and easily.

また、遮水材を摩擦固定材に連結することによって盛土内に固定するようにした場合には、比較的容易な作業により、信頼性の高い固定が可能である。   In addition, when the water shielding material is connected to the friction fixing material to be fixed in the embankment, it can be fixed with high reliability by a relatively easy operation.

また、法面に敷設した遮水材同士を接続することにより一体化するようにした場合には、法面に沿って敷設された遮水材どうしが一体化することにより、水が盛土内に浸透するのを防止できる。   In addition, when the water shielding materials laid on the slope are connected together, the water shielding materials laid along the slope are integrated, so that the water enters the embankment. Infiltration can be prevented.

また、摩擦固定材が、遮水材との連結用シートが予め設けられたものである場合には、遮水材を摩擦固定材介して盛土に固定する作業を容易に行うことができる。このため、遮水材を法面に沿って敷設する作業を容易に進行することができ、例えばコンクリート固定工の場合に必要な養生時間等が不要であり、工期の短縮が可能である。   Moreover, when the friction fixing material is provided with a sheet for connecting with the water shielding material in advance, the work of fixing the water shielding material to the embankment through the friction fixing material can be easily performed. For this reason, it is possible to easily proceed with the work of laying the water shielding material along the slope, and, for example, the curing time required in the case of concrete fixing work is unnecessary, and the construction period can be shortened.

土構造物の第一の構築方法の構成を説明する図である。It is a figure explaining the structure of the 1st construction method of a soil structure. 遮水材の構成を説明する断面図である。It is sectional drawing explaining the structure of a water shielding material. 摩擦固定材の構成を説明する図である。It is a figure explaining the structure of a friction fixing material. 比較例に係る土構造物の構築方法に用いる摩擦固定部分を有する遮水材の構成を説明する図である。It is a figure explaining the structure of the water shielding material which has a friction fixed part used for the construction method of the earth structure which concerns on a comparative example . 土構造物を構築する手順を説明する図であり、一連の工程の最初の工程を実施する際の状態を説明する図である。It is a figure explaining the procedure which builds an earth structure, and is a figure explaining the state at the time of implementing the first process of a series of processes. 土構造物を構築する手順を説明する図であり図5に連続した工程を示すものである。It is a figure explaining the procedure which builds a soil structure, and shows the process continued in FIG. 土構造物を構築する手順を説明する図であり図5に連続した工程を示すものである。It is a figure explaining the procedure which builds a soil structure, and shows the process continued in FIG. 法面に沿って遮水材を敷設すると共に該遮水材を盛土内に固定する手順を説明する図である。It is a figure explaining the procedure of laying a water shielding material along a slope and fixing the water shielding material in the embankment. 法面に沿って遮水材を敷設すると共に該遮水材を盛土内に固定する手順を説明する図である。It is a figure explaining the procedure of laying a water shielding material along a slope and fixing the water shielding material in the embankment. 法面に沿って遮水材を敷設すると共に該遮水材を盛土内に固定する手順を説明する図である。It is a figure explaining the procedure of laying a water shielding material along a slope and fixing the water shielding material in the embankment. 法面に沿って遮水材を敷設すると共に該遮水材を盛土内に固定する手順を説明する図である。It is a figure explaining the procedure of laying a water shielding material along a slope and fixing the water shielding material in the embankment. 法面に沿って遮水材を敷設すると共に該遮水材を盛土内に固定する手順を説明する図である。It is a figure explaining the procedure of laying a water shielding material along a slope and fixing the water shielding material in the embankment. 第一の構築方法による土構造物の完成した状態を説明する図である。It is a figure explaining the completed state of the earth structure by the 1st construction method. 土構造物の構築方法の比較例を説明する図である。It is a diagram illustrating a comparative example of the building process of the soil structure. 法面に沿って摩擦固定部分を有する遮水材を敷設すると共に該遮水材を盛土内に固定する手順を説明する図である。It is a figure explaining the procedure of laying the water shielding material which has a friction fixed part along a slope, and fixing this water shielding material in embankment. 法面に沿って摩擦固定部分を有する遮水材を敷設すると共に該遮水材を盛土内に固定する手順を説明する図である。It is a figure explaining the procedure of laying the water shielding material which has a friction fixed part along a slope, and fixing this water shielding material in embankment. 第二の構築方法による土構造物の完成した状態を説明する図である。It is a figure explaining the completed state of the earth structure by the 2nd construction method.

以下、本発明に係る土構造物の構築方法の好ましい実施の形態について説明する。   Hereinafter, a preferred embodiment of a method for constructing a soil structure according to the present invention will be described.

本発明の土構造物の構築方法は、予め設定された目的の完成高さを持った土構造物を構築する際に、盛土補強材の敷設、盛土、転圧を繰り返すことで、前記完成高さよりも低い中間土構造物を構築し、この中間土構造物の高さが遮水材の長さに対応する高さになった段階で、遮水材の端部を盛土上に固定すると共に、遮水材を法面に沿って敷設することで、中間土構造物の法面に遮水性を持たせ、更に、前記した各工程を繰り返して目的の完成高さを持った土構造物を構築するものである。   The method for constructing a soil structure according to the present invention repeats laying, embankment, and rolling of the embankment reinforcing material when constructing an earth structure having a preset finished height. When an intermediate soil structure lower than the height of the intermediate soil structure is constructed and the height of the intermediate soil structure reaches a height corresponding to the length of the water shielding material, the end of the water shielding material is fixed on the embankment. By laying a water shielding material along the slope, the slope of the intermediate soil structure is made water-tight, and each of the above steps is repeated to create a soil structure with the desired finished height. To build.

土構造物の構築方法の手順を説明するのに先立って構築に用いる材料について説明する。   Prior to explaining the procedure of the construction method of the earth structure, materials used for construction will be explained.

盛土補強材1は、盛土内に敷設され、盛土全体の安定に寄与する。盛土補強材1としては、例えば、盛土補強用として一般的に用いられている、ジオグリッド、ジオテキスタイル等の面状補強材を利用することが可能である。   The embankment reinforcement 1 is laid in the embankment and contributes to the stability of the entire embankment. As the embankment reinforcing material 1, for example, a planar reinforcement material such as a geogrid or a geotextile that is generally used for embankment reinforcement can be used.

法面材2は、盛土補強材1に連結(土のうの場合は巻き込みによる固定)され、法面の土留めの役割りを担う。法面材2としては、鋼製枠、コンクリートブロック、土のう等が用いられる。   The slope material 2 is connected to the embankment reinforcing material 1 (in the case of a sandbag, fixed by entrainment) and plays a role of retaining the slope. As the slope member 2, a steel frame, a concrete block, a sandbag, or the like is used.

法面に敷設される遮水材3は、遮水シートとそれを保護する保護マットもしくは排水材により構成される。遮水シートとそれを保護する保護マットもしくは排水材は個別でもよいが、施工性、施工の手間を考えると、一体化された方が望ましい。   The water shielding material 3 laid on the slope is composed of a water shielding sheet and a protective mat or drainage material that protects it. Although the water shielding sheet and the protective mat or drainage material for protecting the water shielding sheet may be individually provided, it is desirable that they are integrated in consideration of the workability and the labor of construction.

このため、本実施例では、図2に示すように構成した遮水材3を用いている。この遮水材3は、表面側に遮水性を有する遮水シート3aを配置すると共に裏面側に保護マットまたは排水材3bを配置し、両者を一体化して構成されている。そして、法面に敷設する際には、保護マット又は排水材3bを法面に接触させて遮水シート3aを法面の表面となるように配置される。このため、盛土に対し遮水シート3aを直接接触させることがなく、該遮水シート3aの保護をはかることが可能である。   For this reason, in this embodiment, a water shielding material 3 configured as shown in FIG. 2 is used. This water-impervious material 3 is configured by disposing a water-impervious sheet 3a having water-impervious properties on the front surface side and a protective mat or drainage material 3b on the rear surface side, and integrating both. Then, when laying on the slope, the protective mat or drainage material 3b is brought into contact with the slope, and the water shielding sheet 3a is disposed on the slope. For this reason, the water-impervious sheet 3a can be protected without directly contacting the water-impervious sheet 3a to the embankment.

保護マット又は排水材3bは、遮水シート3aと法面との間に介在して該遮水シート3aを法面を構成する材に直接接触することを防ぐものである。このため、保護マットまたは排水材3bとしてはこの機能を発揮し得るものであれば良く、素材を限定するものではない。保護マットとしては、例えば、不織布を用いることができる。排水材としては、例えば3次元網状構造体、ストリップドレーン等を用いることができる。本実施例では、3bとして3次元網状構造体の両面に不織布を積層した排水材を用いている。   The protective mat or drainage material 3b is interposed between the water shielding sheet 3a and the slope to prevent the water shielding sheet 3a from directly contacting the material constituting the slope. Therefore, the protective mat or the drainage material 3b may be any material that can exhibit this function, and the material is not limited. As the protective mat, for example, a nonwoven fabric can be used. As the drainage material, for example, a three-dimensional network structure, a strip drain, or the like can be used. In this embodiment, a drainage material in which nonwoven fabrics are laminated on both surfaces of a three-dimensional network structure is used as 3b.

通常、保護マットとして不織布を用いた場合には、水分を含むと重量が大きくなり過大な引張力が働く。そのため透水性の高い、例えば3次元網状体を有する排水材を用いれば、重量軽減にも寄与できる。   Usually, when a non-woven fabric is used as a protective mat, when moisture is contained, the weight increases and an excessive tensile force acts. Therefore, if drainage material having a high water permeability, for example, a three-dimensional network is used, it can contribute to weight reduction.

摩擦固定材4は、遮水材3の重量と廃棄物埋立時の引張力に抵抗するものである。摩擦固定材4は、図3に示すように、遮水シート4aと、土との摩擦抵抗がより高い、ジオグリッド、ジオテキスタイル等の面状材料4bから構成され、熱融着、接着もしくは機械的な方法で一体化されている。土との摩擦抵抗がより高い面状材料4bとして、本実施例では、ジオグリッドが用いられている。そして、遮水シート4aが遮水材3との連結用シートとしての機能を有する。   The friction fixing material 4 resists the weight of the water shielding material 3 and the tensile force at the time of waste landfill. As shown in FIG. 3, the friction fixing material 4 is composed of a water shielding sheet 4 a and a planar material 4 b such as geogrid or geotextile that has a higher frictional resistance with soil, and is heat-sealed, bonded, or mechanically. Are integrated in a simple manner. In this embodiment, a geogrid is used as the planar material 4b having a higher frictional resistance with the soil. And the water-impervious sheet 4a has a function as a sheet for connection with the water-impervious material 3.

摩擦固定材4は、遮水材3に盛土内で熱融着、接着材もしくは機械的な方法で横接合6され、遮水材3に働く引張力を伝達する。ただし、充分な摩擦抵抗が得られれば、摩擦固定材4を用いることなく、遮水材3をそのまま盛土内に延長して敷設しても構わない。   The frictional fixing material 4 is heat-bonded to the water shielding material 3 in the embankment, laterally bonded 6 by an adhesive or a mechanical method, and transmits the tensile force acting on the water shielding material 3. However, if sufficient frictional resistance is obtained, the water shielding material 3 may be extended and laid in the embankment without using the friction fixing material 4.

また、図4に示される摩擦固定部分を有する遮水材8は本発明の比較例に係る土構造の構築方法を実施する際に用いるものであり、その遮水シート部分を法面に敷設し、摩擦固定部分であるジオグリッドを盛土中に敷設することにより、遮水シートの盛土法面への固定を容易な作業で実現するものである。 Further, the water shielding material 8 having the friction fixed portion shown in FIG. 4 is used when the soil structure construction method according to the comparative example of the present invention is carried out, and the water shielding sheet portion is laid on the slope. By laying the geogrid, which is a friction fixing part, in the embankment, the water impervious sheet can be secured to the embankment slope by an easy operation.

摩擦固定部分を有する遮水材8は、上記の遮水材3に更にジオグリッド、不織布等、盛土との摩擦力の強い材料を連結したものである。   The water shielding material 8 having a friction fixed portion is formed by connecting a material having a strong frictional force with the embankment such as a geogrid or a nonwoven fabric to the water shielding material 3 described above.

図4では、ジオグリッド8bと遮水シート8aとはホットメルト接着剤によって連結されている。即ち、遮水シート8aの端部に、ホットメルト接着剤をアプリケーターで溶融し、ノズルを通してビード状に塗布してホットメルト接着材8dとし、これにジオグリッド8bの端部を重ね合わせることにより両者を接着している。また、遮水シート8aには、保護マットまたは排水材8cが配置されホットメルト接着材8dを利用して接着されている。   In FIG. 4, the geogrid 8b and the water shielding sheet 8a are connected by a hot melt adhesive. That is, a hot melt adhesive is melted with an applicator at the end of the water shielding sheet 8a, applied in a bead shape through a nozzle to form a hot melt adhesive 8d, and both ends of the geogrid 8b are overlapped with this. Is glued. Further, a protective mat or drainage material 8c is disposed on the water shielding sheet 8a and is bonded using a hot melt adhesive material 8d.

なお、ホットメルト接着剤による連結の方法としては、上記の他にも、ジオグリット8bまたは遮水シート8aの一方または両方に、ホットメルトアプリケーターで加熱、溶融したホットメルト接着剤を、ノズルやスリットを通して、点状、ビード状、らせん状、面状に塗布した後、接着剤が溶融した状態で両方を重ねて貼り合わせる等の方法で実施することができ、塗布した後に接着剤を一旦固化させ、貼り合わせる際に再度加熱して溶融させることもできる。この場合、再加熱の方法としては、熱板、熱風、赤外線等で接着剤又は材料を加熱する方法や、電磁波誘導加熱等で接着剤又は材料を発熱させる方法等を用いることができる。   In addition to the above, as a method of connection with a hot melt adhesive, in addition to the above, hot melt adhesive heated and melted with a hot melt applicator is applied to one or both of the geogrid 8b and the water shielding sheet 8a through a nozzle or a slit. After being applied in a dotted, beaded, spiral, or planar shape, it can be carried out by a method such as laminating and laminating both in a state where the adhesive is melted, once the adhesive is solidified, It can also be heated and melted again at the time of bonding. In this case, as a reheating method, a method of heating the adhesive or the material with a hot plate, hot air, infrared rays, or the like, a method of heating the adhesive or the material with electromagnetic induction heating, or the like can be used.

ホットメルト接着剤としては、本実施例では、ポリオレフィン系ホットメルト接着剤を用いているが、このほかにも、ポリウレタン系、エチレン−酢酸ビニル共重合体系、ポリアミド系、ポリエステル系、熱可塑性エラストマー系、スチレン−ブタジエン共重合体系、スチレン−イソプレン共重合体系などの樹脂を成分としたものを単独で用いられても併用されてもよい。   As the hot melt adhesive, in this embodiment, a polyolefin hot melt adhesive is used, but in addition to this, a polyurethane system, an ethylene-vinyl acetate copolymer system, a polyamide system, a polyester system, and a thermoplastic elastomer system are used. , A styrene-butadiene copolymer system, a styrene-isoprene copolymer system, or the like as a component may be used alone or in combination.

ホットメルト接着剤以外にも、例えば、ポリ酢酸ビニル系接着剤、ポリアクリル酸エステル系接着剤、シアノアクリレ−ト系接着剤、エチレン共重合体系接着剤、ポリオレフィン系接着剤、セルロ−ス系接着剤、ポリエステル系接着剤、ポリアミド系接着剤、ポリイミド系接着剤、フェノ−ル樹脂系接着剤、エポキシ系接着剤、ポリウレタン系接着剤、反応型(メタ)アクリル系接着剤等の溶剤型、エマルジョン型、無溶剤型等の接着剤を用いることもできる。   In addition to hot melt adhesives, for example, polyvinyl acetate adhesives, polyacrylate ester adhesives, cyanoacrylate adhesives, ethylene copolymer adhesives, polyolefin adhesives, cellulose adhesives , Polyester adhesive, polyamide adhesive, polyimide adhesive, phenolic resin adhesive, epoxy adhesive, polyurethane adhesive, solvent type such as reactive (meth) acrylic adhesive, emulsion type An adhesive such as a solventless type can also be used.

接着の安定性、コスト、作業工程等を考慮すると、ホットメルト接着剤による接着が最も好ましく用いられる。   In consideration of adhesion stability, cost, work process, etc., adhesion by a hot melt adhesive is most preferably used.

次に、土構造物の構築方法について説明する。先ず、本実施例に係る土構造物の第一の構築方法について図5〜図13により説明する。   Next, the construction method of the earth structure will be described. First, the first construction method of the earth structure according to the present embodiment will be described with reference to FIGS.

本実施例に係る土構造物の第一の構築方法は、先ず、図5に示すように、底面Aに目的の法面Bに沿って複数の法面材2を並べて配置し、夫々の法面材2に盛土補強材1を接続し、敷設する。   The first construction method of the earth structure according to the present embodiment is as follows. First, as shown in FIG. 5, a plurality of slope members 2 are arranged side by side along the target slope B on the bottom face A. The embankment reinforcing material 1 is connected to the face material 2 and laid.

そして、図6に示すように、底面A上に盛土13を施したとき、この盛土13の法面B側は法面材2によって規定される。次いで図7に示すように、盛土13の上面を転圧機14によって転圧し、土砂を転圧して平坦な転圧面を形成する。   Then, as shown in FIG. 6, when the bank 13 is applied on the bottom surface A, the slope B side of the bank 13 is defined by the slope material 2. Next, as shown in FIG. 7, the upper surface of the embankment 13 is rolled by a rolling machine 14 to roll the earth and sand to form a flat rolling surface.

上記の如くして法面材2の設置、盛土補強材1による地盤面或いは転圧面の補強、盛土、転圧、からなる一連の工程を経た後、この転圧面の上面であって法面B側に法面材2を設置し、転圧面の上面に盛土補強材1を設置して該転圧面を補強し、盛土13し、転圧機14による転圧からなる一連の工程を繰り返す。   After passing through a series of steps consisting of the installation of the slope material 2 as described above, the reinforcement of the ground surface or the rolling surface by the embankment reinforcing material 1, the embankment, and the rolling, the upper surface of this rolling surface is the slope B. The slope material 2 is installed on the side, the embankment reinforcing material 1 is installed on the upper surface of the compaction surface, the compaction surface is reinforced, the embankment 13 is formed, and a series of steps consisting of compaction by the compactor 14 is repeated.

上記工程を繰り返すことによって盛土13を構築し、目的の完成高さに到達する以前の段階で、且つ遮水材3の長さに対応する高さになったとき、次の手順により、遮水材の敷設を行う。   The embankment 13 is constructed by repeating the above steps, and when the height reaches the target completed height and reaches the height corresponding to the length of the water shielding material 3, the water shielding is performed by the following procedure. Laying wood.

ここで、遮水材3の長さに対応する高さとは、遮水材3の長さと高さとが一致するという意味ではなく、遮水材3の摩擦固定材4と連結された側を盛土13の法面材2に接近させた位置上に配置して法面Bに沿って敷設したとき、他端(自由端)が下方にある遮水材3に重ね合わさるような高さであることをいうものとする。   Here, the height corresponding to the length of the water shielding material 3 does not mean that the length and height of the water shielding material 3 coincide with each other, but the side of the water shielding material 3 connected to the friction fixing material 4 is embanked. The height is such that the other end (free end) is superimposed on the water shielding material 3 below when placed along the slope B and placed on a position close to the 13 slope material 2. It shall be said.

先ず、図8に示すように、立ち上げた盛土の天端スペースに、遮水材3と摩擦固定材4を準備する。   First, as shown in FIG. 8, a water shielding material 3 and a friction fixing material 4 are prepared in the top edge space of the raised bank.

次いで図9に示すように、遮水材3の展開を行う。そして、展開完了後に遮水材3同士の縦接合5および遮水材3と摩擦固定材4の横接合6を行う。縦接合5及び横接合6の接合方法は熱溶着、機械的接続、接着剤による接合等を選択することにより行う。この時、遮水材3の落下防止のために、例えばアンカー等を用いた落下防止装置7を摩擦固定材4に設置しておく。   Next, as shown in FIG. 9, the water shielding material 3 is developed. Then, after the expansion is completed, the vertical joining 5 between the water shielding materials 3 and the horizontal joining 6 between the water shielding material 3 and the friction fixing material 4 are performed. The joining method of the longitudinal joining 5 and the transverse joining 6 is performed by selecting thermal welding, mechanical connection, joining with an adhesive, or the like. At this time, in order to prevent the water shielding material 3 from falling, for example, a fall prevention device 7 using an anchor or the like is installed on the friction fixing material 4.

次いで、図10に示すように、遮水材3を盛土法面に所定の位置まで下ろす。特に、既に盛土法面に敷設済みの遮水材3との横接合6aは風等によるまくれ上がりがないように面ファスナー等で接合しておく。このとき、水の漏れを防止するため、遮水材3どうしは、瓦状に充分に重ね合わせを行う。また縦接合5aはガスケットのような付属品を用いて接合することも可能である。   Next, as shown in FIG. 10, the water shielding material 3 is lowered to a predetermined position on the embankment slope. In particular, the lateral joint 6a with the water shielding material 3 already laid on the embankment slope is joined with a hook-and-loop fastener or the like so as not to be turned up by wind or the like. At this time, in order to prevent water leakage, the water shielding materials 3 are sufficiently overlapped in a tile shape. The vertical joint 5a can be joined using an accessory such as a gasket.

次いで、図11に示すように、盛土上に、摩擦固定材4を敷設する。   Next, as shown in FIG. 11, the friction fixing material 4 is laid on the embankment.

上記の如くして盛土上に摩擦固定材4を敷設した後、図12に示すように、法面材2を設置し、盛土補強材1を敷設する。所定数の法面材2を設置した後、盛土、転圧を行う。   After laying the frictional fixing material 4 on the embankment as described above, as shown in FIG. 12, the slope material 2 is installed and the embankment reinforcement 1 is laid. After the predetermined number of slope members 2 are installed, embankment and rolling are performed.

これにより、遮水材3は、摩擦固定材4を介して盛土13内に固定される。更に、上記工程を繰り返すことで、盛土13を構築してゆく。   Thereby, the water shielding material 3 is fixed in the embankment 13 through the friction fixing material 4. Furthermore, the embankment 13 is constructed by repeating the above steps.

その後、再度前述した法面材2の設置、盛土補強材1による盛土13の補強、盛土13、転圧、遮水材3及び摩擦固定材4の敷設、からなる一連の工程を進行させ、盛土13の転圧面が目的の完成高さに到達したとき、目的の土構造物が構築される。   Thereafter, a series of steps including the installation of the slope material 2 described above, the reinforcement of the embankment 13 with the embankment reinforcing material 1, the embankment 13, rolling, the water shielding material 3 and the friction fixing material 4 is advanced, and the embankment is advanced. When the thirteen rolling surfaces reach the target completion height, the target soil structure is constructed.

図13に示すように、盛土13が目的の完成高さに到達したときにも前述と同様の手順によって法面Bに遮水材3が敷設され、遮水材3は、摩擦固定材4を介して盛土内に固定される。   As shown in FIG. 13, when the embankment 13 reaches a target completed height, the water shielding material 3 is laid on the slope B by the same procedure as described above, and the water shielding material 3 includes the friction fixing material 4. Fixed in the embankment.

なお、最上部には、管理用道路等アスファルト、コンクリート舗装がなされたり、他の構造物を構築するために、盛土13以外の材料が積上げられる場合があり、遮水材3の盛土13中への固定方法としては、摩擦固定材4を用いる方法、遮水材3を盛土補強材1に直接連結する方法、遮水材3を土の中に埋め込む方法等を用いることができ、中間高さの場合と同じ方法でも異なった方法でもよい。   In addition, asphalt such as a management road, concrete pavement, etc. may be made on the top, and materials other than the embankment 13 may be stacked in order to construct other structures, and into the embankment 13 of the water shielding material 3 As a fixing method, a method using the friction fixing material 4, a method of directly connecting the water shielding material 3 to the embankment reinforcing material 1, a method of embedding the water shielding material 3 in the soil, and the like can be used. The same method as in the case of or a different method may be used.

次いで、比較例に係る土構造物の構築方法について図14〜図17により説明する。尚、前述の第一の構築方法と同一の工程又は類似した工程については参考として前述した図を参照して説明する。 Next, it will be described with reference to FIGS. 14 to 17 for building method of soil structure according to the comparative example. Note that the same or similar steps as those in the first construction method described above will be described with reference to the above-described drawings for reference.

比較例に係る土構造物の構築方法は、先ず、図5に示すように、底面Aに目的の法面Bに沿って複数の法面材2を並べて配置し、夫々の法面材2に盛土補強材1を接続し、敷設する。 Build process of soil structure according to the comparative example, first, as shown in FIG. 5, along the slope B of the object to the bottom surface A are arranged side by side a plurality of slope members 2, each of the slopes material 2 The embankment reinforcement 1 is connected to and laid.

そして、図6に示すように、底面A上に盛土13を施したとき、この盛土13の法面B側は法面材2によって規定される。次いで図7に示すように、盛土13の上面を転圧機14によって転圧し、土砂を転圧して平坦な転圧面を形成する。   Then, as shown in FIG. 6, when the bank 13 is applied on the bottom surface A, the slope B side of the bank 13 is defined by the slope material 2. Next, as shown in FIG. 7, the upper surface of the embankment 13 is rolled by a rolling machine 14 to roll the earth and sand to form a flat rolling surface.

上記の如くして法面材2の設置、盛土補強材1による地盤面或いは転圧面の補強、盛土、転圧、からなる一連の工程を経た後、この転圧面の上面であって法面B側に法面材2を設置し、転圧面の上面に盛土補強材1を設置して該転圧面を補強し、盛土13し、転圧機14による転圧からなる一連の工程を繰り返す。   After passing through a series of steps consisting of the installation of the slope material 2 as described above, the reinforcement of the ground surface or the rolling surface by the embankment reinforcing material 1, the embankment, and the rolling, the upper surface of this rolling surface is the slope B. The slope material 2 is installed on the side, the embankment reinforcing material 1 is installed on the upper surface of the compaction surface, the compaction surface is reinforced, the embankment 13 is formed, and a series of steps consisting of compaction by the compactor 14 is repeated.

上記工程を繰り返すことによって盛土13を構築し、目的の完成高さに到達する以前の段階で、且つ遮水シート部分8aの長さに対応する高さになったとき、次の手順により、図4に示される摩擦固定部分を有する遮水材8の敷設を行う。   When the embankment 13 is constructed by repeating the above steps, and reaches the height corresponding to the length of the water-impervious sheet portion 8a at the stage before reaching the target completed height, The water shielding material 8 having the friction fixed portion shown in 4 is laid.

ここで、遮水シート部分8aの長さに対応する高さとは、遮水シート部分8aの長さと高さとが一致するという意味ではなく、遮水シート部分8aの摩擦固定部分8b側を盛土13の法面材2に接近させた位置上に配置して法面Bに沿って敷設したとき、他端(自由端)が下方にある遮水シート部分8aに重ね合わさるような高さであることをいうものとする。   Here, the height corresponding to the length of the water-impervious sheet portion 8a does not mean that the length and height of the water-impervious sheet portion 8a coincide with each other. When placed on a position close to the slope material 2 and laid along the slope B, the other end (free end) should be high enough to overlap the water shielding sheet portion 8a below. It shall be said.

先ず、図15に示すように、立ち上げた盛土の天端スペースに、摩擦固定部分を有する遮水材8を準備する。   First, as shown in FIG. 15, a water shielding material 8 having a friction fixing portion is prepared in the top edge space of the raised bank.

次いで図16に示すように、摩擦固定部分を有する遮水材8の展開を行う。そして、展開完了後に遮水シート部分8a同士の縦接合5を行う。縦接合5の接合方法は熱溶着、機械的接続、接着剤による接合等を選択することにより行う。この時、摩擦固定部分を有する遮水材8の落下防止のために、例えばアンカー等を用いた落下防止装置7を摩擦固定部分8bに設置しておく。   Next, as shown in FIG. 16, the water shielding material 8 having the friction fixed portion is developed. And the vertical joining 5 of the water-shielding sheet | seat parts 8a is performed after completion | finish of expansion | deployment. The joining method of the longitudinal joining 5 is performed by selecting thermal welding, mechanical connection, joining with an adhesive, or the like. At this time, in order to prevent the water shielding material 8 having the friction fixing portion from falling, for example, a fall prevention device 7 using an anchor or the like is installed in the friction fixing portion 8b.

次いで、摩擦固定部分を有する遮水材8を盛土法面に所定の位置まで下ろす(図10参照)。特に、既に盛土法面に敷設済みの摩擦固定部分を有する遮水材8との横接合(6a)は風等によるまくれ上がりがないように面ファスナー等で接合しておく。このとき、水の漏れを防止するため、摩擦固定部分を有する遮水材8どうしは、瓦状に充分に重ね合わせを行う。また縦接合(5a)はガスケットのような付属品を用いて接合することも可能である。   Next, the water shielding material 8 having a friction fixed portion is lowered to a predetermined position on the embankment slope (see FIG. 10). In particular, the lateral joining (6a) with the water shielding material 8 having the friction fixed portion already laid on the embankment slope is joined with a hook-and-loop fastener or the like so as not to be rolled up by wind or the like. At this time, in order to prevent water leakage, the water shielding materials 8 having the friction fixed portions are sufficiently overlapped in a tile shape. Further, the longitudinal joining (5a) can be joined using an accessory such as a gasket.

次いで、盛土上に、摩擦固定部分であるジオグリッド8bを敷設する(図11参照)。   Next, a geogrid 8b, which is a friction fixed portion, is laid on the embankment (see FIG. 11).

上記の如くして盛土上に摩擦固定部分であるジオグリッド8bを敷設した後、法面材2を設置し、盛土補強材1を敷設する。所定数の法面材2を設置した後、盛土、転圧を行う(図12参照)。   After laying the geogrid 8b which is a friction fixed part on the embankment as described above, the slope material 2 is installed, and the embankment reinforcement 1 is laid. After the predetermined number of slope members 2 are installed, embankment and rolling are performed (see FIG. 12).

なお、摩擦固定部分を有する遮水材8は、補強材1と接して敷設こともできるが、図14に示すように、摩擦固定部分を有する遮水材8と補強材1の間に盛土の層を介在させることも可能である。   Although the water shielding material 8 having the friction fixed portion can be laid in contact with the reinforcing material 1, as shown in FIG. 14, the embankment is interposed between the water shielding material 8 having the friction fixed portion and the reinforcing material 1. It is also possible to intervene layers.

これにより、遮水シート部分8aは、摩擦固定部分8bを介して盛土13内に固定される。更に、上記工程を繰り返すことで、盛土13を構築してゆく。   Thereby, the water-impervious sheet portion 8a is fixed in the embankment 13 through the friction fixing portion 8b. Furthermore, the embankment 13 is constructed by repeating the above steps.

その後、再度前述した法面材2の設置、盛土補強材1による盛土13の補強、盛土13、転圧、摩擦固定部分を有する遮水材8の敷設、からなる一連の工程を進行させ、盛土13の転圧面が目的の完成高さに到達したとき、目的の土構造物が構築される。   Thereafter, a series of steps including the installation of the slope material 2 described above, the reinforcement of the embankment 13 with the embankment reinforcing material 1, the embankment 13, the rolling pressure, and the laying of the water shielding material 8 having a friction fixing portion are advanced to the embankment. When the thirteen rolling surfaces reach the target completion height, the target soil structure is constructed.

図17に示すように、盛土13が目的の完成高さに到達したときにも前述と同様の手順によって法面Bに遮水シート部分8aが敷設され、摩擦固定部分8bを介して盛土内に固定される。   As shown in FIG. 17, when the embankment 13 reaches the target completed height, the water shielding sheet portion 8a is laid on the slope B by the same procedure as described above, and the embankment 13 is inserted into the embankment via the friction fixing portion 8b. Fixed.

なお、最上部には、管理用道路等アスファルト、コンクリート舗装がなされたり、他の構造物を構築するために、盛土13以外の材料が積上げられる場合があり、摩擦固定部分を有する遮水材8の盛土13中への固定方法としては、摩擦固定部分8bを用いる方法、遮水材3を盛土補強材1に直接連結する方法等、を用いることができ、中間高さの場合と同じ方法でも異なった方法でもよい。   In addition, in order to construct asphalt such as a management road, concrete pavement, or to construct other structures, the material other than the embankment 13 may be stacked on the top, and the water shielding material 8 having a friction fixing portion 8 As a method for fixing the material into the embankment 13, a method using the friction fixing portion 8b, a method of directly connecting the water shielding material 3 to the embankment reinforcing material 1, and the like can be used. Different methods are possible.

なお、前述した第一の構築方法と比較例に係る構築方法を併用して盛土を構築することもできる。 The embankment can also be constructed by using the first construction method described above and the construction method according to the comparative example in combination.

以下、本実施例の第一の構築方法および比較例に係る構築方法に共通する、法面に敷設された遮水材同士の接合について説明する。 Hereinafter, the joint of the water shielding materials laid on the slope, which is common to the first construction method of the present embodiment and the construction method according to the comparative example, will be described.

法面に敷設された遮水材同士の接合については、各中間高さの盛土に遮水材を敷設した後、次ぎの盛土を構築する前に実施するのが、安全上好ましい方法である。   About joining of the water shielding materials laid on the slope, it is preferable from the viewpoint of safety that the water shielding material is laid on each intermediate height bank before the next bank is constructed.

既に盛土法面の下方に敷設済みの遮水材3、8が存在するとき、この遮水材3、8との横接合については、この連結部位のレベルが貯留水水位よりも下方であるときには熱溶着によって連結することが好ましい。また連結部位のレベルが貯留水水位よりも上方であるときには熱溶着、接着剤、重ね合わせ、ガスケットを用いた連結等を用いることができるが、敷設済みの遮水材3、8の上に充分重ね合せをとって、瓦状に重ね合わせるのが好ましい方法であり、この方法によれば、熱溶着をしなくても水漏れを防止することができる。   When the water shielding materials 3 and 8 that have already been laid below the embankment slope are present, the lateral connection with the water shielding materials 3 and 8 is when the level of this connection part is below the stored water level. It is preferable to connect by thermal welding. Further, when the level of the connection portion is higher than the stored water level, it is possible to use heat welding, adhesive, overlapping, connection using a gasket, etc., but it is sufficient on the laid water shielding materials 3 and 8. It is preferable to superimpose and overlap the tiles. According to this method, water leakage can be prevented without performing heat welding.

急傾斜な法面での、遮水シートの熱溶着作業は危険を伴うが、本発明において、貯留水水位よりも上方での熱溶着作業を瓦状の重ね合わせで行うことにより、安全に作業することができる。更に、本発明では、法面が急傾斜であるため、瓦状の重ね合せによる水漏れ防止効果が大きいという特徴を有する。なお、瓦状の重ね合わせの場合において、風などによるめくれを防ぐため、面ファスナー等で遮水材同士を固定することが好ましい。   Although heat welding work of a water shielding sheet on a steep slope is dangerous, in the present invention, work can be performed safely by performing heat welding work above the stored water level by tile-like superposition. can do. Furthermore, in the present invention, since the slope is steeply inclined, it has a feature that the effect of preventing water leakage by the tile-like overlapping is great. In addition, in the case of tile-like superposition, it is preferable to fix the water shielding materials with a hook-and-loop fastener or the like in order to prevent turning up by wind or the like.

一方、並行して敷設される遮水材3、8同士の、縦接合については、熱溶着、接着剤、ガスケットを用いた連結等を用いることができる。   On the other hand, for vertical joining of the water shielding materials 3 and 8 laid in parallel, thermal welding, bonding using an adhesive, a gasket, or the like can be used.

なお、遮水材同士の接合については、上記したように、各中間高さの盛土に遮水材を敷設した後、次ぎの盛土を構築する前以外に、行うこともできる。例えば、下方の接合は、盛土構築時に行い、上方の接合については、廃棄物を埋立てを開始した後、所定の高さまで廃棄物埋立てが進んだ時点で、廃棄物自体を足場として適切な接合作業を行うことも可能である。   In addition, as mentioned above, after joining a water-shielding material to each intermediate height embankment, it can also perform joining of water-shielding materials other than before constructing the next banking. For example, the lower joint is performed at the time of embankment construction, and the upper joint is suitable as a foothold when the waste landfill is advanced to a predetermined height after the landfill is started. It is also possible to perform a joining operation.

尚、上記実施例では遮水材3を固定するために摩擦固定材4の連結用シート4aに連結したが、遮水材3の固定方式はこの実施例に限定するものではなく、例えば、遮水材3の端部3cを直接アンカーによって盛土13に固定することも可能である。この場合、アンカーとしては、釘状に形成されたもの、コンクリートの塊状に形成されたもの、等を採用することが可能である。   In the above embodiment, the water blocking material 3 is connected to the connecting sheet 4a of the friction fixing material 4 in order to fix the water blocking material 3. However, the fixing method of the water blocking material 3 is not limited to this embodiment. It is also possible to fix the end 3c of the water material 3 to the embankment 13 directly by an anchor. In this case, an anchor formed in a nail shape, a concrete lump shape, or the like can be used.

本発明の土構造物の構築方法は、廃棄物処理場や貯水構造物のように、遮水性を持った法面を有する土構造物を構築する際に利用して有利である。   The method for constructing a soil structure of the present invention is advantageous when used for constructing a soil structure having a slope with water barrier properties, such as a waste disposal site or a water storage structure.

A 地盤面
B 法面
1 盛土補強材
2 法面材
3 遮水材
3a 遮水シート
3b 保護マット
3c 端部
4 摩擦固定材
4a 遮水シート、連結用シート
4b 面状材料
5、5a 縦接合
6、6a 横接合
7 落下防止装置
8 摩擦固定部分を有する遮水材
8b ジオグリッド
8a 遮水シート
8d ホットメルト接着材
8c 保護マットまたは排水材
13 盛土
14 転圧機
A Ground surface B Slope 1 Embankment reinforcement 2 Slope material 3 Water shielding material 3a Water shielding sheet 3b Protective mat 3c End 4 Friction fixing material 4a Water shielding sheet, connecting sheet 4b Planar material 5, 5a Vertical joint 6 , 6a Lateral joining 7 Fall prevention device 8 Water shielding material having friction fixed portion 8b Geogrid 8a Water shielding sheet 8d Hot melt adhesive 8c Protective mat or drainage material 13 Embankment 14 Rolling press

Claims (3)

盛土補強材の敷設、盛土、転圧を繰り返して目的の完成高さに到達する以前に、該盛土が遮水材の長さに対応する高さになった段階で、遮水材を法面に沿って敷設すると共に予め連結用シートが設けられた摩擦固定材に該連結用シートを介して連結することによって盛土内に固定し、その後、前記工程を繰り返して目的の完成高さを持った遮水性を持った土構造物を構築することを特徴とする土構造物の構築方法。 Before reaching the desired finished height by repeatedly laying, embanking and rolling the embankment reinforcement, the embankment is sloped when the embankment reaches a height corresponding to the length of the impermeable material. And fixed in the embankment by connecting to the friction fixing material provided with a connecting sheet in advance through the connecting sheet , and then repeating the above steps to have the desired finished height. A method for constructing a soil structure, characterized by constructing a soil structure having water impermeability. 法面に敷設した遮水材同士を接続することにより一体化することを特徴とする請求項1の土構造物の構築方法。   The method for constructing a soil structure according to claim 1, wherein the water shielding materials laid on the slope are integrated by connecting each other. 前記遮水材が、遮水シートと保護マット又は排水材を重ね合せ、一体化したものであることを特徴とする請求項1又は2の土構造物の構築方法。   The method for constructing a soil structure according to claim 1 or 2, wherein the water shielding material is formed by superimposing a water shielding sheet and a protective mat or drainage material.
JP2009069814A 2008-03-24 2009-03-23 Construction method of earth structure Active JP5300549B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009069814A JP5300549B2 (en) 2008-03-24 2009-03-23 Construction method of earth structure

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
JP2008075005 2008-03-24
JP2008075005 2008-03-24
JP2009069814A JP5300549B2 (en) 2008-03-24 2009-03-23 Construction method of earth structure

Publications (2)

Publication Number Publication Date
JP2009257074A JP2009257074A (en) 2009-11-05
JP5300549B2 true JP5300549B2 (en) 2013-09-25

Family

ID=41384823

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009069814A Active JP5300549B2 (en) 2008-03-24 2009-03-23 Construction method of earth structure

Country Status (1)

Country Link
JP (1) JP5300549B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100966512B1 (en) 2010-03-12 2010-07-01 (주) 화랑건설엔지니어링 Vegetion earths retaining wall and construction method of the same
ES2524691T3 (en) * 2012-02-21 2014-12-11 Terre Armée Internationale A cladding element for a reinforced floor structure
JP5380627B1 (en) * 2013-05-14 2014-01-08 株式会社フジコーポレーション Simple vertical wall structure at final disposal site
JP5320519B1 (en) * 2013-05-14 2013-10-23 株式会社フジコーポレーション Vertical wall structure of waste storage facility
KR102341469B1 (en) * 2021-01-08 2021-12-21 윤영근 Method for preventing sliding of cutting side by concrete structures
JP7352605B2 (en) * 2021-05-21 2023-09-28 三ツ星ベルト株式会社 Construction method of civil engineering or architectural sheet and method of fixing civil engineering or architectural sheet

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61130514A (en) * 1984-11-27 1986-06-18 Fujita Corp Cut-off work for fill-dam
JPH0557032U (en) * 1991-12-27 1993-07-30 三菱油化産資株式会社 Embankment reinforcement
JP3740341B2 (en) * 1999-12-24 2006-02-01 天龍工業株式会社 Protective greening structure on slopes, walls, shores, etc.

Also Published As

Publication number Publication date
JP2009257074A (en) 2009-11-05

Similar Documents

Publication Publication Date Title
JP5300549B2 (en) Construction method of earth structure
US10227750B2 (en) Device and method for foundation drainage
JP6403502B2 (en) Tunnel water stop structure and construction method
US8029376B2 (en) Shock absorbing athletic field and method of constructing same
JP5921857B2 (en) Slope protection structure in which honeycomb-shaped three-dimensional solid cell structures are stacked vertically
JP5388646B2 (en) Civil engineering complex and construction method of earth structure
JP5171792B2 (en) Water shielding facilities at waste disposal sites and construction methods
RU139821U1 (en) MULTILAYER WATERPROOFING OF UNDERGROUND STRUCTURE
CN107354920B (en) Combination against seepage structure and its construction method for culverts and water gates
RU2539456C2 (en) Multi-layer hydraulic insulation of underground structure (device by p.b. yurkevich)
JP7405363B2 (en) Water-shielding structure of managed seawall and water-shielding structure at the end of the water-shielding sheet.
KR20140053485A (en) Paramat and waterproofing method using it
JP6676463B2 (en) Embankment reinforcement method
JP7182451B2 (en) Water-shielding structure of the landfill area of the sea surface disposal site
JP2010090534A (en) Reinforcement structure of paved road
JP3698969B2 (en) Underwater impermeable method
JPH0270814A (en) Water-shield structure and sheet for reclamation
JP2021188291A (en) Rainwater storage facility and construction method of rainwater storage facility
KR20200034927A (en) 3-layer structure of unity with the guide sewing lines
JP5918436B1 (en) Bottom plate / side wall structure and bottom plate / side wall construction method
JP2001062420A (en) Fixing structure for protective mat
JP3971917B2 (en) Method for confirming water tightness of impermeable sheet used for surface impermeable work on wall surface
JP2017057593A (en) Waterproof sheet for tunnel
CN220225362U (en) Domatic solidification structure
KR101525827B1 (en) Panel Module for Constructing Retaining Wall

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120319

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20130228

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130402

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130603

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130618

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130618

R150 Certificate of patent or registration of utility model

Ref document number: 5300549

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350