JP4911823B2 - Anchor frame anchoring structure - Google Patents

Anchor frame anchoring structure Download PDF

Info

Publication number
JP4911823B2
JP4911823B2 JP2001041498A JP2001041498A JP4911823B2 JP 4911823 B2 JP4911823 B2 JP 4911823B2 JP 2001041498 A JP2001041498 A JP 2001041498A JP 2001041498 A JP2001041498 A JP 2001041498A JP 4911823 B2 JP4911823 B2 JP 4911823B2
Authority
JP
Japan
Prior art keywords
anchor frame
bolt
anchor
horizontal piece
fixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2001041498A
Other languages
Japanese (ja)
Other versions
JP2002242203A (en
Inventor
泰則 三瀬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Asahi Kasei Construction Materials Corp
Original Assignee
Asahi Kasei Construction Materials Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Asahi Kasei Construction Materials Corp filed Critical Asahi Kasei Construction Materials Corp
Priority to JP2001041498A priority Critical patent/JP4911823B2/en
Publication of JP2002242203A publication Critical patent/JP2002242203A/en
Application granted granted Critical
Publication of JP4911823B2 publication Critical patent/JP4911823B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)
  • Joining Of Building Structures In Genera (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は柱脚用アンカーフレームの定着構造に係り、特にアンカーフレームの高さを簡単かつ自在に微調整することが出来ると共に、該アンカーフレームを杭頭の周りに施された捨コンクリート上に安定した状態で設置固定し得るアンカーフレーム定着構造に関するものである。
【0002】
【従来の技術】
従来、杭頭の周りに打設された捨コンクリートの上に柱脚用のアンカーボルト等を取付固定するための柱脚用アンカーフレームを設置して定着させるに当っては、アングル材で現場に於て構成した架台の下部を捨コンクリートの中に埋設して固定し、この架台の上にアンカーフレームを固定することによって定着させることが一般的に実施されていた。
【0003】
しかるに前述のように架台を使用する場合には、構造が複雑になる上に、架台の下部を捨コンクリートの中に埋設したり、或はライナーを使用して隙間を埋めながらアンカーフレームの水平レベルを出したりしなければならないので、作業が極めて繁雑でコスト高になる問題があった。かつ、前述のように架台やアンカーフレームを捨コンクリートに設置する場合に、これ等が杭頭と接触する際には、アンカーフレーム等の一部を切欠かなければならない問題があった。
【0004】
また、前述の従来のアンカーフレームの固定方法を改善するために、例えば公開平成2-120534号公報或は図4に示す如きコンクリート杭上に施設するアンカーボルトの定着装置が開発されている。
【0005】
この定着装置は、図4に示す如く、アンカーボルト51を固定手段52を介して支持する堅杆53が、取付固定されるアンカーフレーム54をZ型支持脚55を介して、杭頭56の周りに打設された捨コンクリート57に設置していた。図中58はテンプレート、59はナットである。
【0006】
【発明が解決しようとする課題】
前述の図4に示す装置のように、Z型支持脚55を用いてアンカーフレーム54を捨コンクリート57に設置する場合には、前述の従来の架台やライナー等を不要とし、かつ架台の下部を捨コンクリートの中に埋設する必要がないので、作業が簡単である等の点に於て大きな作用効果を有している。
【0007】
しかし、この図4に示す装置に於ては、一定の高さを有するZ型支持脚55を使用するので、高さ調整が出来ず、従ってアンカーフレーム54の水平レベル出しが困難である問題があった。
【0008】
本発明に係るアンカーフレームの定着構造は、前述の従来の多くの問題点に鑑み開発された全く新しい技術であって、特に下端にプレートが一体的に固着されたアジャストボルトの上部をアンカーフレームの水平片に穿設されたボルト穴に挿通し、該アジャストボルトの上部にナットを螺合して構成するようにし、アジャストボルトによってアンカーフレームの高さを自在に微調整するようにした全く新しい技術を提供するものである。
【0009】
【課題を解決するための手段】
本発明に係るアンカーフレームの定着構造は、柱脚用のアンカーボルト等を取付固定し得る柱脚用アンカーフレームを杭頭の周りに施された捨コンクリート上に設置して定着させる構造に於て、水平片及び垂直片よりなる複数のアングル材を前記垂直片の下端に配置された前記水平片が前記垂直片よりも外側になるように配置しつつ互いに溶接で固着することで形成されるアンカーフレームと、下端にプレートが一体的に溶着されかつほぼ全周面にネジが設けられたアジャストボルトと、を有し、前記アジャストボルトの上部を前記水平片に穿設されたボルト穴に挿通し、さらに該アジャストボルトの上部にナットを螺合して構成したことを特徴としたアンカーフレーム定着構造である。
【0010】
前述の本発明のアンカーフレームの定着構造に於ては、アジャストボルトの下端にプレートを一体的に固着したので、このプレートを捨コンクリートの表面に安定した状態で載置することが出来る。前記プレートとしては平のものが望ましいが、アングル、C型綱などの型鋼を使用することも出来る。また、このプレートを固着する手段としては、(1)事前にプレートに穴を開けておき、その穴部より捨コンアンカーにて固着する。(2)プレートを捨コンクリートに埋め込まれた金物などに溶接して固着する。(3)プレートをコンクリート等で固着する、等の手段がある。
【0011】
前記アジャストボルトは、その外周面のほぼ全周面にネジが設けられており、かつアンカーフレームの水平片に穿設されたボルト穴にアジャストボルトの上部が挿通されると共に、その上部にナットが螺合されているので、ナットを固動することによってアンカーフレームの高さを自在に微調整することが出来る。従って、アンカーフレームの水平レベルを簡単かつ正確に出すことが出来る。
【0012】
【発明の実施の形態】
図により本発明に係るアンカーフレームの定着構造の一実地例を具体的に説明すると、図1は本発明の定着構造の要部の簡略説明図、図2は図1の定着構造の一部の斜視説明図、図3は本発明の定着構造を現場で具体的に実施した状態の斜視図である。
【0013】
図1乃至図3に於いて、1は柱脚用のアンカーフレームであって、水平片2a及び垂直片2bよりなるアングル材2より形成されている。3はこのアンカーフレーム1に取付け固定された堅杆であって、固定手段4を介してアンカーボルト5を保持している。6はテンプレートであって、複数のアンカーボルト5の上部にナット7を介して取付けられている。
【0014】
8は地中に埋設された杭の杭頭であって、この杭頭8の周りには捨コンクリート9が打設されている。10はアジャストボルトであって、そのほぼ全周にはネジが設けられている。このアジャストボルト10の下端にはプレートとして平プレート11が一体的に溶着されている。
【0015】
前記アジャストボルト10の上部は、アンカーフレーム1の水平片2aの所定位置に設けられたボルト穴に挿通され、かつその上部には水平片2aを挟んで2個のナット12が螺合されている。従って、ナット12を固動することによって、アジャストボルト10に沿ってアンカーボルト51を自在に昇降することが出来るように構成されている。
【0016】
本発明に係るアンカーフレームの定着構造の実施に当っては、特に図3或は図1に示す如く、複数のアングル材2で形成されたアンカーボルト51を用意し、そのアンカーフレーム1のほぼ四隅に対応する水平片2aの所定位置に穿設されたボルト穴に、アジャストボルト10の上部を挿通し、かつこのアジャストボルト10上部所定位置に、予め螺合されていたナット7を、水平片2aの下面に当接する。次に別のナット7をアジャストボルト10の上部に螺合し、上下のナット7で水平片2aを上下方面より挟持する。
【0017】
このように、アンカーフレーム1の四隅の水平片2aにアジャストボルト10を取付けた状態で、アンカーフレーム1を杭頭8の周りに配置し、アジャストボルト10の下端に取付けられている平プレート11を杭頭8の周りに打設されている捨コンクリート9の表面に載置する。
【0018】
このように杭頭8の周りにアジャストボルト10を介して所定の高さに配置されたアンカーフレーム1は、そのアンカーフレーム1の四隅に設けられたアジャストボルト10に螺合されたナット7を固動することによって、アンカーフレーム1の高さを自由に微調整することが出来、これによってアンカーフレーム1の水平レベル出しを正確に実施することが出来る。
【0019】
【発明の効果】
前述の本発明のアンカーフレームの定着構造に於ては、アジャストボルトの下端に平プレートを一体的に溶着したので、このプレートを捨コンクリートの表面に安定した状態で載置することが出来る。かつ該捨コンクリートの上に更にコンクリートを打設した場合に、このプレートをコンクリート内に完全に埋設して安定した状態で固着することが出来る等の多大な効果を有している。
【0020】
前記アジャストボルトは、その外周面のほぼ全周面にネジが設けられており、また、かつアンカーフレームの水平片に穿設されたボルト穴にアジャストボルトの上部が挿通されると共に、その上部にナットが螺合されているので、ナットを固動することによってアンカーフレームの高さを自在に微調整することが出来る。従って、アンカーフレームの水平レベルを簡単かつ正確に出すことが出来る等の効果も有している。
【図面の簡単な説明】
【図1】本発明の定着構造の要部の簡略説明図である。
【図2】図1の定着構造の一部の斜視説明図である。
【図3】本発明の定着構造を現場で具体的に実施した状態の斜視図である。
【図4】従来例のアンカーフレームの定着構造を示す簡略説明図である。
【符号の説明】
1 …アンカーフレーム
2 …アングル材
2a …水平片
2b …垂直片
3 …堅杆
5 …アンカーボルト
6 …テンプレート
8 …杭頭
9 …捨コンクリート
10 …アジャストボルト
11 …平プレート
12 …ナット
13 …捨コンアンカー
51 …アンカーボルト
53 …堅杆
54 …アンカーフレーム
55 …Z型支持脚
56 …杭頭
57 …捨コンクリート
58 …テンプレート
59 …ナット
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a fixing structure for an anchor frame for a column base, and in particular, the height of the anchor frame can be easily and freely finely adjusted, and the anchor frame can be stably placed on a concrete disposed around a pile head. The present invention relates to an anchor frame fixing structure that can be installed and fixed in the above state.
[0002]
[Prior art]
Conventionally, when installing and fixing a column base anchor frame for mounting and fixing a column base anchor bolt, etc., on the scraped concrete placed around the pile head, it is necessary to use an angle material on the site. It has been generally practiced that the lower part of the gantry constructed in the above is fixed by being buried in discarded concrete, and an anchor frame is secured on the gantry.
[0003]
However, when using a gantry as described above, the structure is complicated, and the lower part of the gantry is buried in scraped concrete, or a liner is used to fill the gap and the horizontal level of the anchor frame. There is a problem that the work is extremely complicated and expensive. In addition, when the gantry and the anchor frame are installed on the discarded concrete as described above, there is a problem that a part of the anchor frame or the like has to be cut off when they come into contact with the pile head.
[0004]
In order to improve the above-described conventional anchor frame fixing method, for example, a fixing device for anchor bolts installed on a concrete pile as shown in Japanese Patent Laid-Open No. Hei 2-120534 or FIG. 4 has been developed.
[0005]
In this fixing device, as shown in FIG. 4, the anchor frame 53 that supports the anchor bolt 51 via the fixing means 52 is attached to the anchor frame 54 around the pile head 56 via the Z-type support leg 55. It was installed on the discarded concrete 57 placed in In the figure, 58 is a template and 59 is a nut.
[0006]
[Problems to be solved by the invention]
When the anchor frame 54 is installed on the waste concrete 57 using the Z-type support leg 55 as in the apparatus shown in FIG. 4, the above-described conventional frame or liner is not required, and the lower part of the frame is Since there is no need to embed it in discarded concrete, it has a great effect in that it is easy to work.
[0007]
However, in the apparatus shown in FIG. 4, since the Z-type support leg 55 having a certain height is used, the height cannot be adjusted, so that the horizontal level of the anchor frame 54 is difficult. there were.
[0008]
The anchor frame fixing structure according to the present invention is a completely new technology developed in view of the above-mentioned conventional problems, and in particular, the upper portion of the adjustment bolt having the plate integrally fixed to the lower end is attached to the anchor frame. A completely new technology in which a bolt hole drilled in a horizontal piece is inserted and a nut is screwed onto the top of the adjustment bolt, and the height of the anchor frame can be finely adjusted freely with the adjustment bolt. Is to provide.
[0009]
[Means for Solving the Problems]
The anchor frame fixing structure according to the present invention is a structure in which a column base anchor frame capable of mounting and fixing a column base anchor bolt or the like is installed and fixed on waste concrete provided around a pile head. An anchor formed by welding a plurality of angle members composed of a horizontal piece and a vertical piece so that the horizontal piece arranged at the lower end of the vertical piece is positioned outside the vertical piece and welded to each other. A frame, and an adjustment bolt having a plate integrally welded to the lower end and a screw provided on substantially the entire peripheral surface, and the upper portion of the adjustment bolt is inserted into a bolt hole drilled in the horizontal piece Furthermore, the anchor frame fixing structure is characterized in that a nut is screwed onto an upper portion of the adjusting bolt.
[0010]
In the anchor frame fixing structure of the present invention described above, since the plate is integrally fixed to the lower end of the adjusting bolt, the plate can be placed on the surface of the discarded concrete in a stable state. The plate is preferably a flat plate, but it is also possible to use a steel plate such as an angle or a C-shaped rope. Further, as means for fixing the plate, (1) a hole is made in the plate in advance, and the plate is fixed by a discard anchor from the hole. (2) The plate is welded and fixed to a metal object embedded in discarded concrete. (3) There are means such as fixing the plate with concrete or the like.
[0011]
The adjustment bolt is provided with a screw on substantially the entire outer peripheral surface thereof, and the upper part of the adjustment bolt is inserted into a bolt hole drilled in a horizontal piece of the anchor frame, and a nut is provided on the upper part thereof. Since it is screwed, the height of the anchor frame can be finely adjusted freely by moving the nut. Accordingly, the horizontal level of the anchor frame can be obtained easily and accurately.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
A practical example of the anchor frame fixing structure according to the present invention will be described in detail with reference to the drawings. FIG. 1 is a simplified explanatory view of the main part of the fixing structure of the present invention, and FIG. 2 is a part of the fixing structure of FIG. FIG. 3 is a perspective view illustrating a state in which the fixing structure of the present invention is specifically implemented on site.
[0013]
1 to 3, reference numeral 1 denotes an anchor frame for a column base, which is formed of an angle member 2 composed of a horizontal piece 2a and a vertical piece 2b. Reference numeral 3 denotes a rigid member fixedly attached to the anchor frame 1 and holds an anchor bolt 5 via a fixing means 4. Reference numeral 6 denotes a template, which is attached to the upper portions of a plurality of anchor bolts 5 via nuts 7.
[0014]
Reference numeral 8 denotes a pile head embedded in the ground, and a discarded concrete 9 is placed around the pile head 8. Reference numeral 10 denotes an adjusting bolt, and a screw is provided on almost the entire circumference thereof. A flat plate 11 is integrally welded to the lower end of the adjusting bolt 10 as a plate.
[0015]
The upper part of the adjustment bolt 10 is inserted into a bolt hole provided at a predetermined position of the horizontal piece 2a of the anchor frame 1, and two nuts 12 are screwed to the upper part with the horizontal piece 2a interposed therebetween. . Accordingly, the anchor bolt 51 can be moved up and down freely along the adjustment bolt 10 by fixing the nut 12.
[0016]
In implementing the anchor frame fixing structure according to the present invention, in particular, as shown in FIG. 3 or FIG. 1, anchor bolts 51 formed of a plurality of angle members 2 are prepared, and the anchor frame 1 has almost four corners. The upper part of the adjusting bolt 10 is inserted into a bolt hole drilled at a predetermined position of the horizontal piece 2a corresponding to the nut, and a nut 7 screwed in advance at a predetermined position of the upper part of the adjusting bolt 10 is attached to the horizontal piece 2a. It contacts the lower surface of the. Next, another nut 7 is screwed onto the upper portion of the adjusting bolt 10, and the horizontal piece 2 a is sandwiched from the upper and lower surfaces by the upper and lower nuts 7.
[0017]
In this way, with the adjustment bolts 10 attached to the horizontal pieces 2 a at the four corners of the anchor frame 1, the anchor frame 1 is arranged around the pile head 8 and the flat plate 11 attached to the lower end of the adjustment bolt 10 is attached. It is placed on the surface of the waste concrete 9 that is placed around the pile head 8.
[0018]
In this way, the anchor frame 1 arranged at a predetermined height around the pile head 8 via the adjusting bolt 10 is fixed with nuts 7 screwed into the adjusting bolts 10 provided at the four corners of the anchor frame 1. By moving, the height of the anchor frame 1 can be finely adjusted freely, whereby the horizontal leveling of the anchor frame 1 can be accurately performed.
[0019]
【Effect of the invention】
In the anchor frame fixing structure of the present invention described above, since the flat plate is integrally welded to the lower end of the adjusting bolt, the plate can be placed on the surface of the discarded concrete in a stable state. In addition, when concrete is further placed on the discarded concrete, the plate is completely embedded in the concrete and can be fixed in a stable state.
[0020]
The adjustment bolt is provided with a screw on almost the entire outer peripheral surface thereof, and the upper part of the adjustment bolt is inserted into a bolt hole drilled in a horizontal piece of the anchor frame. Since the nut is screwed, the height of the anchor frame can be finely adjusted freely by moving the nut. Therefore, the horizontal level of the anchor frame can be obtained easily and accurately.
[Brief description of the drawings]
FIG. 1 is a simplified explanatory diagram of a main part of a fixing structure of the present invention.
FIG. 2 is a perspective view of a part of the fixing structure of FIG.
FIG. 3 is a perspective view of a state in which the fixing structure of the present invention is specifically implemented on site.
FIG. 4 is a simplified explanatory view showing a fixing structure of an anchor frame of a conventional example.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1 ... Anchor frame 2 ... Angle material 2a ... Horizontal piece 2b ... Vertical piece 3 ... Solid 5 ... Anchor bolt 6 ... Template 8 ... Pile head 9 ... Discrete concrete 10 ... Adjust bolt 11 ... Flat plate 12 ... Nut 13 ... Disc Anchor 51 ... Anchor bolt 53 ... Solid 54 ... Anchor frame 55 ... Z-type support leg 56 ... Pile head 57 ... Waste concrete 58 ... Template 59 ... Nut

Claims (1)

柱脚用のアンカーボルト等を取付固定し得る柱脚用アンカーフレームを杭頭の周りに施された捨コンクリート上に設置して定着させる構造に於て、
水平片及び垂直片よりなる複数のアングル材を前記垂直片の下端に配置された前記水平片が前記垂直片よりも外側になるように配置しつつ互いに溶接で固着することで形成されるアンカーフレームと、
下端にプレートが一体的に溶着されかつほぼ全周面にネジが設けられたアジャストボルトと、を有し、
前記アジャストボルトの上部を前記水平片に穿設されたボルト穴に挿通し、さらに該アジャストボルトの上部にナットを螺合して構成したことを特徴としたアンカーフレーム定着構造。
In the structure where the anchor frame for the column base that can fix and fix the anchor bolt for the column base, etc. is installed and fixed on the rubbing concrete provided around the pile head,
An anchor frame formed by fixing a plurality of angle members composed of a horizontal piece and a vertical piece by welding while arranging the horizontal piece arranged at the lower end of the vertical piece outside the vertical piece. When,
An adjustment bolt having a plate integrally welded to the lower end and a screw provided on substantially the entire circumferential surface;
An anchor frame fixing structure characterized in that an upper portion of the adjusting bolt is inserted into a bolt hole drilled in the horizontal piece, and a nut is screwed onto the upper portion of the adjusting bolt.
JP2001041498A 2001-02-19 2001-02-19 Anchor frame anchoring structure Expired - Lifetime JP4911823B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2001041498A JP4911823B2 (en) 2001-02-19 2001-02-19 Anchor frame anchoring structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2001041498A JP4911823B2 (en) 2001-02-19 2001-02-19 Anchor frame anchoring structure

Publications (2)

Publication Number Publication Date
JP2002242203A JP2002242203A (en) 2002-08-28
JP4911823B2 true JP4911823B2 (en) 2012-04-04

Family

ID=18903933

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2001041498A Expired - Lifetime JP4911823B2 (en) 2001-02-19 2001-02-19 Anchor frame anchoring structure

Country Status (1)

Country Link
JP (1) JP4911823B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5563409B2 (en) * 2010-09-03 2014-07-30 株式会社住金システム建築 Anchor bolt installation jig and pile foundation construction method using the installation jig
CN103334496B (en) * 2013-07-19 2018-03-16 中建八局第一建设有限公司 Pre-embedded steel slab leveling bolt and application method under shock isolating pedestal
JP7366714B2 (en) 2019-11-29 2023-10-23 岡部株式会社 Base frame height adjustment bracket

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0713416B2 (en) * 1992-03-30 1995-02-15 大和ハウス工業株式会社 Anchor frame positioning tool
JP2932893B2 (en) * 1993-06-29 1999-08-09 株式会社ダイフク Structural support lower end support device
JPH08134926A (en) * 1994-11-14 1996-05-28 Komatsu Forklift Co Ltd Column base mounting structure for automatic warehouse
JP2694431B2 (en) * 1996-03-08 1997-12-24 岡部株式会社 Construction method of anchor bolt

Also Published As

Publication number Publication date
JP2002242203A (en) 2002-08-28

Similar Documents

Publication Publication Date Title
KR101912800B1 (en) Bridge lifting apparatus and bridge lifting method therefor
JPH04247160A (en) Method and device for installing double floor and support therefor
JP2012102601A (en) Height-adjustable bearing device for structure and height adjustment method of bearing device for structure
JP4911823B2 (en) Anchor frame anchoring structure
JPH05214731A (en) Column base fixing device
CN108708297A (en) Punching stick anchor ear support device
JP3362809B2 (en) Pillar support device
JP3787971B2 (en) How to install seismic isolation devices
JPH062313A (en) Level adjustment of bearing part
JPS6315415B2 (en)
JP2001348952A (en) Position adjustment device for steel-frame column
JP3659766B2 (en) Surface plate construction method and apparatus for building pillars
JP6604979B2 (en) Elastic ballast track laying apparatus and elastic ballast track laying method
JP4410522B2 (en) Platform door device and platform door device installation method
JP4756750B2 (en) Anchor frame fixing method
JPH063878Y2 (en) Anchor frame level adjustment structure
CN214996176U (en) Municipal administration public facilities built-in fitting mounting tool
CN220132756U (en) Bridge jacking heightening supporting device and support structure
JP3252318B2 (en) Concrete block adjuster
JP2589046Y2 (en) Rail frame bearing device
JPH06272219A (en) Support device of buffer stop support
CN216202305U (en) Lateral fixing device
JP7049961B2 (en) How to add equipment mount
JP2006299587A (en) Construction method and positioning device of column base foundation
JPH10168899A (en) Installing jig of precast reinforced concrete foundation block

Legal Events

Date Code Title Description
RD02 Notification of acceptance of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7422

Effective date: 20080131

A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080206

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100526

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110308

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110420

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20111108

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20111222

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20120117

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20120117

R150 Certificate of patent or registration of utility model

Ref document number: 4911823

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20150127

Year of fee payment: 3

EXPY Cancellation because of completion of term