JP7049961B2 - How to add equipment mount - Google Patents

How to add equipment mount Download PDF

Info

Publication number
JP7049961B2
JP7049961B2 JP2018148740A JP2018148740A JP7049961B2 JP 7049961 B2 JP7049961 B2 JP 7049961B2 JP 2018148740 A JP2018148740 A JP 2018148740A JP 2018148740 A JP2018148740 A JP 2018148740A JP 7049961 B2 JP7049961 B2 JP 7049961B2
Authority
JP
Japan
Prior art keywords
waterproof layer
support column
presser concrete
support
base plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2018148740A
Other languages
Japanese (ja)
Other versions
JP2020023826A (en
Inventor
哲也 枡井
和雄 青木
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2018148740A priority Critical patent/JP7049961B2/en
Publication of JP2020023826A publication Critical patent/JP2020023826A/en
Application granted granted Critical
Publication of JP7049961B2 publication Critical patent/JP7049961B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は、防水層が敷設された床構造のスラブに設備架台の支柱を設置して、当該支柱の周囲に新規の防水層を設ける設備架台の増設方法に関する。 The present invention relates to a method of adding a facility pedestal in which a support for an equipment pedestal is installed on a slab having a floor structure in which a waterproof layer is laid and a new waterproof layer is provided around the support.

防水層が敷設された床構造のスラブ上に対し、設備架台の支柱を設置して、当該支柱の周囲に新規の防水層を設ける従来の設備架台の増設方法は、一般的に、スラブ上における支柱の設置箇所の防水層を撤去し、当該防水層が撤去されたスラブ上に対して支柱の下端部にあるベースプレートを間に調整モルタルを介在させた状態で載置し、スラブに打ち込んだ複数のアンカーにより当該ベースプレートを固定して行われる。
しかし、このような設備架台の増設方法では、防水層の撤去作業が必要となるため、工期の長期化や高コスト化の要因となる上に、作業中の漏水リスクが生じるという問題がある。そこで、従来の方法として、防水層を撤去することなく、防水層の上に基礎部材を設置し、その上に屋外設備の一部を載置すると共に、その周囲に新規の防水層を設ける設備架台の増設方法が提案されている(例えば、特許文献1を参照。)。
The conventional method of adding a facility pedestal on a slab having a floor structure in which a waterproof layer is laid is generally performed on a slab by installing a support for the equipment pedestal and providing a new waterproof layer around the support. Multiple layers were driven into the slab by removing the waterproof layer at the location where the support was installed, placing the base plate at the lower end of the support on the slab from which the waterproof layer was removed, with an adjustment mortar in between. This is done by fixing the base plate with the anchor of.
However, in such a method of adding an equipment frame, it is necessary to remove the waterproof layer, which causes a problem that the construction period is lengthened and the cost is increased, and that there is a risk of water leakage during the work. Therefore, as a conventional method, a foundation member is installed on the waterproof layer without removing the waterproof layer, a part of the outdoor equipment is placed on the foundation member, and a new waterproof layer is provided around the foundation member. A method for adding a gantry has been proposed (see, for example, Patent Document 1).

特開2011-231481号公報Japanese Unexamined Patent Publication No. 2011-231481

しかしながら、上記特許文献1に記載の方法では、防水層の上に基礎部材を設置するため、当該防水層が破損する可能性があり、更には、基礎部材の水平度やレベルを調整するための煩雑な作業が必要となる。 However, in the method described in Patent Document 1, since the foundation member is installed on the waterproof layer, the waterproof layer may be damaged, and further, for adjusting the levelness and level of the foundation member. Complicated work is required.

この実情に鑑み、本発明の主たる課題は、作業中の漏水リスクを軽減しながら、短工期且つ高精度に屋上等の床構造に対して設備架台を増設することができる技術を提供する点にある。 In view of this situation, a main problem of the present invention is to provide a technique capable of adding an equipment stand to a floor structure such as a rooftop with a short construction period and high accuracy while reducing the risk of water leakage during work. be.

本発明の第1特徴構成は、防水層が敷設され当該防水層の上に押えコンクリートを敷設して構成された床構造のスラブに設備架台の支柱を設置して、当該支柱の周囲に新規の防水層を設ける設備架台の増設方法であって、
前記スラブにおける前記支柱の設置箇所及びその周囲における前記押えコンクリートの部分を、前記防水層を残した状態で撤去する押えコンクリート撤去工程と、
前記押えコンクリート撤去工程を実行して前記押えコンクリートが撤去された前記スラブにおける前記支柱の設置箇所に対し、前記防水層を撤去することなく当該防水層を貫通させて複数のアンカーを打ち込むアンカー打ち込み工程と、
前記アンカー打ち込み工程で打ち込んだ複数のアンカーに対してのみに前記支柱の下端部にあるベースプレートを固定して、当該ベースプレートを前記複数のアンカー以外全ての部分において前記防水層から浮かせた状態する支柱固定工程と、
前記支柱固定工程で固定した前記支柱の周囲に前記新規の防水層を敷設する新規防水層敷設工程と、
前記押えコンクリート撤去工程で撤去した前記支柱の設置箇所の周囲における前記押えコンクリートの部分を復旧させる押えコンクリート復旧工程と、を行う点にある。
The first characteristic configuration of the present invention is to install a support for an equipment pedestal on a slab of a floor structure in which a waterproof layer is laid and presser concrete is laid on the waterproof layer, and a new support is provided around the support. It is a method of adding a facility stand that provides a waterproof layer.
In the presser concrete removing step of removing the place where the support column is installed in the slab and the part of the presser concrete around it with the waterproof layer left.
Anchor driving step of executing the presser concrete removing step to penetrate the waterproof layer and driving a plurality of anchors into the installation location of the support column in the slab from which the presser concrete has been removed without removing the waterproof layer. When,
A support column in which a base plate at the lower end of the support column is fixed only to a plurality of anchors driven in the anchor driving step so that the base plate is floated from the waterproof layer in all parts other than the plurality of anchors. Fixing process and
A new waterproof layer laying step of laying the new waterproof layer around the support fixed in the support fixing step, and a new waterproof layer laying step.
The point is to perform a presser concrete restoration step of restoring a portion of the presser concrete around the installation location of the support column removed in the presser concrete removal step .

本構成によれば、既存の防水層を撤去することなくスラブに打ち込んだ複数のアンカーに対して支柱を固定するので、防水層の撤去作業を省略して工期の短期化及び低コスト化を実現することができる上に、作業中の漏水リスクを低減することができる。
更に、スラブに打ち込んだ複数のアンカーに対して、支柱の下端部にあるベースプレートを浮かせた状態で当該支柱を固定するので、スラブに敷設された防水層の破損を防止しながら、スラブやそれに敷設された防水層に影響を受けることなく、支柱のベースプレートの水平度やレベルの調整を簡単に行うことができる。
従って、本発明により、作業中の漏水リスクを軽減しながら、短工期且つ高精度に屋上等の床構造に対して設備架台を増設することができる設備架台の増設方法を提供することができる。
更に、本構成によれば、支柱の設置箇所及びその周囲の押えコンクリートの部分が撤去された状態で、既存の防水層を撤去することなくスラブに打ち込まれたアンカーに対して固定された支柱の周囲に新規の防水層が敷設され、その後、撤去された支柱の設置箇所の周囲における押えコンクリートの部分が復旧されることになる。すると、支柱の周囲では、復旧された押えコンクリートにより保護された状態で、既存の防水層の上に新規の防水層が重なった状態となるので、それらの境界部分での漏水を確実に防止することができる。
According to this configuration, the columns are fixed to multiple anchors driven into the slab without removing the existing waterproof layer, so the work of removing the waterproof layer is omitted and the construction period is shortened and the cost is reduced. In addition to being able to reduce the risk of water leakage during work.
Furthermore, since the support is fixed to the multiple anchors driven into the slab with the base plate at the lower end of the support floating, the slab and the slab are laid while preventing damage to the waterproof layer laid on the slab. The levelness and level of the base plate of the column can be easily adjusted without being affected by the waterproof layer.
Therefore, according to the present invention, it is possible to provide a method for adding an equipment pedestal that can add an equipment pedestal to a floor structure such as a rooftop in a short construction period and with high accuracy while reducing the risk of water leakage during work.
Further, according to this configuration, the support is fixed to the anchor driven into the slab without removing the existing waterproof layer in a state where the installation location of the support and the part of the presser concrete around the support are removed. A new waterproof layer will be laid around it, after which the part of the presser concrete around the location of the removed columns will be restored. Then, around the pillars, a new waterproof layer is layered on top of the existing waterproof layer while being protected by the restored presser concrete, so that water leakage at the boundary between them is surely prevented. be able to.

本発明の第2特徴構成は、前記支柱固定工程において、前記複数のアンカーに前記防水層から浮かせた状態で下ナットを螺合させ、当該下ナットの上に前記ベースプレートを設置する点にある。 The second characteristic configuration of the present invention is that in the support column fixing step, the lower nut is screwed into the plurality of anchors while floating from the waterproof layer, and the base plate is installed on the lower nut.

本構成によれば、支柱固定工程において、スラブに打ち込んだ複数のアンカーに当該スラブ上の防水層から浮かせた状態で下ナットを螺合させ、その下ナットの上に支柱のベースプレートを設置するという構成を採用することで、スラブに打ち込んだ複数のアンカーに対してスラブ上の防水層から浮かせた状態で支柱のベースプレートを固定することができる。この場合、複数のアンカーに螺合された夫々の下ナットのレベルを各別に調整するだけで、その上に設置された支柱のベースプレートの水平度やレベルを簡単に調整することができる。 According to this configuration, in the strut fixing process, the lower nut is screwed into a plurality of anchors driven into the slab while floating from the waterproof layer on the slab, and the base plate of the strut is installed on the lower nut. By adopting the configuration, it is possible to fix the base plate of the column to a plurality of anchors driven into the slab while floating from the waterproof layer on the slab. In this case, the levelness and level of the base plate of the support column installed on the lower nuts can be easily adjusted by simply adjusting the level of each lower nut screwed into the plurality of anchors.

本発明の第3特徴構成は、前記アンカー打ち込み工程において、前記防水層に対する前記アンカーの貫通部周囲に対して防水処理を施す点にある。 The third characteristic configuration of the present invention is that in the anchor driving step, a waterproof treatment is applied to the periphery of the penetration portion of the anchor with respect to the waterproof layer .

設備架台の増設方法の流れを示すフロー図Flow diagram showing the flow of how to add equipment mounts 押えコンクリート撤去工程後の支柱設置箇所の状態を表す図The figure which shows the state of the support post installation place after the presser concrete removal process アンカー打ち込み工程後の支柱設置箇所の状態を表す図Diagram showing the state of the support column installation location after the anchor driving process 支柱固定工程後の支柱設置箇所の状態を表す図The figure which shows the state of the support post installation place after the support support fixing process モルタル充填工程後の支柱設置箇所の状態を表す図The figure which shows the state of the support post installation place after the mortar filling process 新規防水層敷設工程後の支柱設置箇所の状態を表す図Diagram showing the state of the column installation location after the new waterproof layer laying process 押えコンクリート復旧工程後の支柱設置箇所の状態を表す図Diagram showing the state of the column installation location after the presser concrete restoration process 設備架台の設置状態を示す図The figure which shows the installation state of the equipment pedestal 支柱のベースプレートの平面図Top view of the base plate of the column

本発明の実施形態について図面に基づいて説明する。
本実施形態の設備架台の増設方法(以下「本架台増設方法」と呼ぶ。)は、図8に示すように、屋上等の床構造1に重量機械等を設置するための設備架台20を増設する方法として構成されている。
ここで、設備架台20は、重量機械等が載置される枠体20Bと、当該枠体の少なくとも四隅から下方に延びる支柱20Aとを有して構成されている。尚、この支柱20Aは、図7及び図9にも示すように、上下方向に延びるH形鋼からなる柱部22と、その下端部に接合された平板状のベースプレート21とを有して構成されている。尚、本実施形態では、柱部22の下端面のベースプレート21の上面を当接させた状態で、柱部22の下端部にベースプレート21が接合されている。しかし、このベースプレート21の形態や支柱20Aの下端部への接続状態等については適宜変更することができ、例えば柱部22の下端部の側面にベースプレート21を外方に延出させる形態で接合しても構わない。
An embodiment of the present invention will be described with reference to the drawings.
As shown in FIG. 8, the method of adding the equipment pedestal of the present embodiment (hereinafter referred to as “the method of adding the main pedestal”) is to add the equipment pedestal 20 for installing a heavy machine or the like on the floor structure 1 of the rooftop or the like. It is configured as a way to do it.
Here, the equipment pedestal 20 is configured to have a frame body 20B on which a heavy machine or the like is placed, and columns 20A extending downward from at least four corners of the frame body. As shown in FIGS. 7 and 9, the pillar 20A includes a pillar portion 22 made of H-shaped steel extending in the vertical direction and a flat plate-shaped base plate 21 joined to the lower end portion thereof. Has been done. In this embodiment, the base plate 21 is joined to the lower end of the pillar 22 in a state where the upper surface of the base plate 21 on the lower end of the pillar 22 is in contact with the lower end of the pillar 22. However, the form of the base plate 21 and the connection state to the lower end of the column 20A can be appropriately changed. For example, the base plate 21 is joined to the side surface of the lower end of the column 22 so as to extend outward. It doesn't matter.

本架台増設方法は、詳細については後述するが、図7及び図8に示すように、防水層3が敷設された床構造1のスラブ2に設備架台20の支柱20Aを設置して、当該支柱20Aの周囲に新規の防水層33を設ける方法として構成されており、本架台増設方法では、図1に示すように、押えコンクリート撤去工程(ステップ#1)と、アンカー打ち込み工程(ステップ#2)と、支柱固定工程(ステップ#3)と、モルタル充填工程(ステップ#4)と、新規防水層敷設工程(ステップ#5)と、押えコンクリート復旧工程(ステップ#6)とが、記載の順に実行される。
以下、各工程の詳細について順に説明する。
The method for adding the main gantry will be described in detail later, but as shown in FIGS. 7 and 8, the stanchion 20A of the equipment gantry 20 is installed on the slab 2 of the floor structure 1 in which the waterproof layer 3 is laid, and the stanchion is concerned. It is configured as a method of providing a new waterproof layer 33 around the 20A, and in the method of adding the gantry, as shown in FIG. 1, a presser concrete removing step (step # 1) and an anchor driving step (step # 2). , The column fixing step (step # 3), the mortar filling step (step # 4), the new waterproof layer laying step (step # 5), and the presser concrete restoration step (step # 6) are executed in the order described. Will be done.
Hereinafter, the details of each step will be described in order.

(押えコンクリート撤去工程)
本架台増設方法の実行前の床構造1は、図2に示すように、コンクリート製のスラブ2の表面に防水層3が敷設されている。更に、この防水層3の表面には、押えコンクリート4が敷設されており、また、この押えコンクリート4の表面には適宜仕上材5が敷設されている。
そして、本架台増設方法では、先ずは押えコンクリート撤去工程(図1のステップ#1)が実行される。この押えコンクリート撤去工程では、支柱20A(図8等参照)の設置箇所X及びその周囲における押えコンクリート4の部分4a更には仕上材5の部分5aが、防水層3を残した状態で撤去される。このとき、押えコンクリート4及び仕上材5における撤去対象の部分4a,5aの広さは、支柱20Aよりも若干大きいものとされる。
(Presser concrete removal process)
As shown in FIG. 2, in the floor structure 1 before the execution of the method for adding the main frame, the waterproof layer 3 is laid on the surface of the concrete slab 2. Further, a presser concrete 4 is laid on the surface of the waterproof layer 3, and a finishing material 5 is appropriately laid on the surface of the presser concrete 4.
Then, in the method of adding the main stand, first, the presser concrete removing step (step # 1 in FIG. 1) is executed. In this presser concrete removing step, the part 4a of the presser concrete 4 and the part 5a of the finishing material 5 around the installation location X of the support column 20A (see FIG. 8 and the like) are removed with the waterproof layer 3 left. .. At this time, the area of the parts 4a and 5a to be removed in the presser concrete 4 and the finishing material 5 is slightly larger than that of the support column 20A.

(アンカー打ち込み工程)
上記押えコンクリート撤去工程(図1のステップ#1)の実行後には、アンカー打ち込み工程(図1のステップ#2)が実行される。このアンカー打ち込み工程では、図3に示すように、スラブ2における支柱20Aの設置箇所Xに対し、防水層3を撤去することなく当該防水層3を貫通させて複数のアンカー25が打ち込まれる。尚、本実施形態では、設置箇所X毎に一の支柱20A(図8等を参照)を固定するための4本のアンカー25が打ち込まれる。また、防水層3におけるアンカー25の貫通部周囲については、シール剤等により簡易な方法でアンカー打ち込み作業中の仮設的な防水処理が施される。
(Anchor driving process)
After the pressing concrete removing step (step # 1 in FIG. 1) is executed, the anchor driving step (step # 2 in FIG. 1) is executed. In this anchor driving step, as shown in FIG. 3, a plurality of anchors 25 are driven into the installation location X of the support column 20A in the slab 2 by penetrating the waterproof layer 3 without removing the waterproof layer 3. In this embodiment, four anchors 25 for fixing one support column 20A (see FIG. 8 and the like) are driven into each installation location X. Further, the area around the penetrating portion of the anchor 25 in the waterproof layer 3 is temporarily waterproofed during the anchor driving operation by a simple method such as a sealing agent.

(支柱固定工程)
上記アンカー打ち込み工程(図1のステップ#2)の実行後には、支柱固定工程(図1のステップ#3)が実行される。この支柱固定工程では、図4に示すように、アンカー打ち込み工程で打ち込んだ複数のアンカー25に対し、防水層3から支柱20Aの下端部にあるベースプレート21を浮かせた状態で、支柱20Aが固定される。
具体的に、この支柱固定工程では、複数のアンカー25に防水層3から浮かせた状態で下ナット26が螺合され、当該下ナット26の上にベースプレート21が設置される。その状態で、複数のアンカー25の夫々に螺合された下ナット26の高さ位置を調整することで、ベースプレート21の水平度やレベル等が調整される。そして、その調整が完了した段階で、複数のアンカー25の夫々に座金28及び上ナット27が螺合され、当該上ナット27が締め付けられる。すると、下ナット26と上ナット27との間にベースプレート21を挟み込む形態で、当該ベースプレート21がアンカー25に固定されることになる。
(Strut fixing process)
After the anchor driving step (step # 2 in FIG. 1) is executed, the support column fixing step (step # 3 in FIG. 1) is executed. In this support column fixing step, as shown in FIG. 4, the support column 20A is fixed to the plurality of anchors 25 driven in the anchor driving step in a state where the base plate 21 at the lower end of the support column 20A is floated from the waterproof layer 3. To.
Specifically, in this support column fixing step, the lower nut 26 is screwed onto the plurality of anchors 25 in a state of being floated from the waterproof layer 3, and the base plate 21 is installed on the lower nut 26. In that state, the levelness and level of the base plate 21 are adjusted by adjusting the height position of the lower nut 26 screwed into each of the plurality of anchors 25. Then, when the adjustment is completed, the washer 28 and the upper nut 27 are screwed into each of the plurality of anchors 25, and the upper nut 27 is tightened. Then, the base plate 21 is fixed to the anchor 25 by sandwiching the base plate 21 between the lower nut 26 and the upper nut 27.

即ち、本架台増設工程では、アンカー打ち込み工程において、図3に示すように既存の防水層3が撤去されることなくスラブ2に複数のアンカー25が打ち込まれ、次の支柱固定工程において、図4に示すように複数のアンカー25に対して支柱20Aが固定される。即ち、既存の防水層3の撤去作業が省略されているので、工期の短期化及び低コスト化が実現されている。更に、既存の防水層3が残ることで、作業中の漏水リスクが低減されている。 That is, in the main pedestal expansion step, a plurality of anchors 25 are driven into the slab 2 without removing the existing waterproof layer 3 as shown in FIG. 3 in the anchor driving step, and in the next column fixing step, FIG. 4 As shown in the above, the support column 20A is fixed to the plurality of anchors 25. That is, since the work of removing the existing waterproof layer 3 is omitted, the construction period can be shortened and the cost can be reduced. Further, the existing waterproof layer 3 remains, so that the risk of water leakage during work is reduced.

(モルタル充填工程)
上記支柱固定工程(図1のステップ#3)の実行後には、モルタル充填工程(図1のステップ#4)が実行される。このモルタル充填工程では、図5に示すように、スラブ2上に敷設された既存の防水層3と、その防水層3から上方に浮かせた状態でアンカー25に固定されたベースプレート21との間の隙間に無収縮モルタル30が充填される。ここで、無収縮モルタル30が充填される隙間の周囲は仮設の型枠35により塞がれており、その型枠35は、無収縮モルタル30の固化後に撤去される。尚、本架台増設方法では、支柱20Aのベースプレート21から伝達される荷重は下ナット26を通じてアンカー25により支持されるので、このモルタル充填工程を省略して防水層3とベースプレート21との間の隙間をそのまま空間として残すようにしても構わない。この場合、アンカー25はスラブ2から突出した構造となるため、地震時に設備架台20から伝達されるせん断力によって生じる曲げモーメントに対して必要な耐力を有するようにアンカー25等の設計を行うことが望ましい。
(Mortar filling process)
After the execution of the support column fixing step (step # 3 in FIG. 1), the mortar filling step (step # 4 in FIG. 1) is executed. In this mortar filling step, as shown in FIG. 5, between the existing waterproof layer 3 laid on the slab 2 and the base plate 21 fixed to the anchor 25 while floating upward from the waterproof layer 3. The gap is filled with the non-shrink mortar 30. Here, the periphery of the gap filled with the non-shrink mortar 30 is closed by a temporary mold 35, and the mold 35 is removed after the non-shrink mortar 30 is solidified. In the method of adding the gantry, the load transmitted from the base plate 21 of the support column 20A is supported by the anchor 25 through the lower nut 26. Therefore, this mortar filling step is omitted and the gap between the waterproof layer 3 and the base plate 21 is omitted. May be left as it is as a space. In this case, since the anchor 25 has a structure protruding from the slab 2, the anchor 25 and the like can be designed so as to have a necessary yield strength against the bending moment generated by the shearing force transmitted from the equipment frame 20 at the time of an earthquake. desirable.

(新規防水層敷設工程)
上記モルタル充填工程(図1のステップ#4)の実行後には、新規防水層敷設工程(図1のステップ#5)が実行される。この新規防水層敷設工程では、図6に示すように、上述の支柱固定工程で固定した支柱20Aの周囲に新規の防水層33が敷設される。
かかる新規の防水層33は、支柱20Aの周囲において既存の防水層3の上面に敷設される環状の平面部33bと、当該平面部33bの中央部から支柱20Aの外周部に沿って立ち上げられる立上部33aとで構成される。
(New waterproof layer laying process)
After the execution of the mortar filling step (step # 4 in FIG. 1), a new waterproof layer laying step (step # 5 in FIG. 1) is executed. In this new waterproof layer laying step, as shown in FIG. 6, a new waterproof layer 33 is laid around the support column 20A fixed in the above-mentioned column fixing step.
The new waterproof layer 33 is erected from an annular flat surface portion 33b laid on the upper surface of the existing waterproof layer 3 around the support column 20A and from the central portion of the flat surface portion 33b along the outer peripheral portion of the support column 20A. It is composed of a rising portion 33a.

(押えコンクリート復旧工程)
上記新規防水層敷設工程(図1にステップ#5)の実行後には、押えコンクリート復旧工程(図1のステップ#6)が実行される。この押えコンクリート復旧工程では、図7に示すように、例えば、支柱20Aの設置箇所Xの周囲における新規の防水層33の平面部33b上に押えコンクリート4の部分4bを打設し、その上に仕上材5の部分5bを敷設する形態で、上述の押えコンクリート撤去工程(図1のステップ#1)で撤去した押えコンクリート4の部分4b更には仕上材5の部分5bが復旧される。
(Presser concrete restoration process)
After the execution of the new waterproof layer laying step (step # 5 in FIG. 1), the presser concrete restoration step (step # 6 in FIG. 1) is executed. In this presser concrete restoration step, as shown in FIG. 7, for example, a portion 4b of the presser concrete 4 is placed on the flat surface portion 33b of the new waterproof layer 33 around the installation location X of the support column 20A, and the portion 4b of the presser concrete 4 is placed on the flat portion 33b. In the form of laying the part 5b of the finishing material 5, the part 4b of the presser concrete 4 removed in the above-mentioned step of removing the presser concrete (step # 1 in FIG. 1) and further the part 5b of the finishing material 5 are restored.

そして、支柱20Aの設置箇所Xの周囲では、押えコンクリート復旧工程で復旧される押えコンクリート4の部分4b等により保護された状態で、既存の防水層3の上に新規の防水層33の平面部33bが重なった状態で存在することになる。よって、それら既存の防水層3と新規の防水層33との境界部分での漏水が確実に防止されることになる。 Then, around the installation location X of the support column 20A, the flat surface portion of the new waterproof layer 33 is placed on the existing waterproof layer 3 in a state of being protected by the portion 4b of the presser concrete 4 restored in the presser concrete restoration step. 33b will exist in an overlapping state. Therefore, water leakage at the boundary between the existing waterproof layer 3 and the new waterproof layer 33 is surely prevented.

〔別実施形態〕
本発明の他の実施形態について説明する。尚、以下に説明する各実施形態の構成は、それぞれ単独で適用することに限らず、他の実施形態の構成と組み合わせて適用することも可能である。
[Another Embodiment]
Other embodiments of the present invention will be described. It should be noted that the configurations of the respective embodiments described below are not limited to being applied independently, but can also be applied in combination with the configurations of other embodiments.

(1)上記実施形態では、支柱固定工程(図4参照)において、複数のアンカー25に螺合させた下ナット26の上に支柱20Aのベースプレート21を設置することで、複数のアンカー25に対してスラブ2上の防水層3から浮かせた状態で支柱20Aのベースプレート21を固定するように構成したが、当該複数のアンカー25に対するベースプレート21の固定方法については適宜改変しても構わない。 (1) In the above embodiment, in the support column fixing step (see FIG. 4), by installing the base plate 21 of the support column 20A on the lower nuts 26 screwed into the plurality of anchors 25, the base plate 21 of the support column 20A is attached to the plurality of anchors 25. The base plate 21 of the support column 20A is fixed in a state of being floated from the waterproof layer 3 on the slab 2, but the method of fixing the base plate 21 to the plurality of anchors 25 may be appropriately modified.

(2)上記実施形態では、アンカー打ち込み工程(図3参照)の実行前に押えコンクリート撤去工程(図2参照)を行い、新規防水層敷設工程(図6参照)の実行後に押えコンクリート復旧工程(図7参照)を行うように構成したが、既存の防水層3の上に押えコンクリートが存在しない場合等においては、これら押えコンクリート撤去工程及び押えコンクリート復旧工程を適宜省略しても構わない。 (2) In the above embodiment, the presser concrete removing step (see FIG. 2) is performed before the anchor driving step (see FIG. 3) is executed, and the presser concrete restoration step (see FIG. 6) is performed after the execution of the new waterproof layer laying step (see FIG. 6). Although it is configured to perform (see FIG. 7), if the presser concrete does not exist on the existing waterproof layer 3, the presser concrete removal step and the presser concrete restoration step may be omitted as appropriate.

1 床構造
2 スラブ
3 防水層
4 押えコンクリート
4a,4b 押えコンクリートの部分
20 設備架台
20A 支柱
21 ベースプレート
25 アンカー
26 下ナット
33 防水層
X 設置箇所
1 Floor structure 2 Slab 3 Waterproof layer 4 Presser concrete 4a, 4b Presser concrete part 20 Equipment stand 20A Support 21 Base plate 25 Anchor 26 Lower nut 33 Waterproof layer X Installation location

Claims (3)

防水層が敷設され当該防水層の上に押えコンクリートを敷設して構成された床構造のスラブに設備架台の支柱を設置して、当該支柱の周囲に新規の防水層を設ける設備架台の増設方法であって、
前記スラブにおける前記支柱の設置箇所及びその周囲における前記押えコンクリートの部分を、前記防水層を残した状態で撤去する押えコンクリート撤去工程と、
前記押えコンクリート撤去工程を実行して前記押えコンクリートが撤去された前記スラブにおける前記支柱の設置箇所に対し、前記防水層を撤去することなく当該防水層を貫通させて複数のアンカーを打ち込むアンカー打ち込み工程と、
前記アンカー打ち込み工程で打ち込んだ複数のアンカーに対してのみに前記支柱の下端部にあるベースプレートを固定して、当該ベースプレートを前記複数のアンカー以外全ての部分において前記防水層から浮かせた状態する支柱固定工程と、
前記支柱固定工程で固定した前記支柱の周囲に前記新規の防水層を敷設する新規防水層敷設工程と、
前記押えコンクリート撤去工程で撤去した前記支柱の設置箇所の周囲における前記押えコンクリートの部分を復旧させる押えコンクリート復旧工程と、を行う設備架台の増設方法。
A method of adding a facility pedestal in which a support for an equipment pedestal is installed on a slab having a floor structure in which a waterproof layer is laid and presser concrete is laid on the waterproof layer, and a new waterproof layer is provided around the support. And
In the presser concrete removing step of removing the place where the support column is installed in the slab and the part of the presser concrete around it with the waterproof layer left.
Anchor driving step of executing the presser concrete removing step to penetrate the waterproof layer and driving a plurality of anchors into the installation location of the support column in the slab from which the presser concrete has been removed without removing the waterproof layer. When,
A support column in which a base plate at the lower end of the support column is fixed only to a plurality of anchors driven in the anchor driving step so that the base plate is floated from the waterproof layer in all parts other than the plurality of anchors. Fixing process and
A new waterproof layer laying step of laying the new waterproof layer around the support fixed in the support fixing step, and a new waterproof layer laying step.
A method for adding a facility pedestal to perform a presser concrete restoration step of restoring a part of the presser concrete around the installation location of the support column removed in the presser concrete removal step .
前記支柱固定工程において、前記複数のアンカーに前記防水層から浮かせた状態で下ナットを螺合させ、当該下ナットの上に前記ベースプレートを設置する請求項1に記載の設備架台の増設方法。 The method for adding an equipment stand according to claim 1, wherein in the support column fixing step, a lower nut is screwed onto the plurality of anchors while floating from the waterproof layer, and the base plate is installed on the lower nut. 前記アンカー打ち込み工程において、前記防水層に対する前記アンカーの貫通部周囲に対して防水処理を施す請求項1又は2に記載の設備架台の増設方法。 The method for adding an equipment frame according to claim 1 or 2 , wherein in the anchor driving step, waterproofing treatment is performed on the periphery of the penetration portion of the anchor with respect to the waterproof layer .
JP2018148740A 2018-08-07 2018-08-07 How to add equipment mount Active JP7049961B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018148740A JP7049961B2 (en) 2018-08-07 2018-08-07 How to add equipment mount

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018148740A JP7049961B2 (en) 2018-08-07 2018-08-07 How to add equipment mount

Publications (2)

Publication Number Publication Date
JP2020023826A JP2020023826A (en) 2020-02-13
JP7049961B2 true JP7049961B2 (en) 2022-04-07

Family

ID=69618399

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018148740A Active JP7049961B2 (en) 2018-08-07 2018-08-07 How to add equipment mount

Country Status (1)

Country Link
JP (1) JP7049961B2 (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1997040244A1 (en) 1996-04-23 1997-10-30 MAMMINA, Jean-François Process for making anchoring points and installation of a structure on a terraced roof, and adapted structures
JP2003138699A (en) 2001-10-30 2003-05-14 Airec Engineering Corp Method for installing new equipment and foundation member
JP2009167754A (en) 2008-01-18 2009-07-30 Cosmo System Kk Base frame for setting facility equipment and method of setting the base frame
JP3161082U (en) 2010-04-02 2010-07-22 渡邊 心治 Panel mounting structure
JP2011231481A (en) 2010-04-26 2011-11-17 Sunkensetsu Co Ltd Foundation member for installing outdoor facilities and backing fixing method for foundation member
JP2013213350A (en) 2012-04-02 2013-10-17 Sharp Corp Supporting member attachment structure, construction method for support structure, and photovoltaic power generation system using supporting member attachment structure

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS608285Y2 (en) * 1980-02-29 1985-03-23 松下電工株式会社 Solar water heater mounting device

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1997040244A1 (en) 1996-04-23 1997-10-30 MAMMINA, Jean-François Process for making anchoring points and installation of a structure on a terraced roof, and adapted structures
JP2003138699A (en) 2001-10-30 2003-05-14 Airec Engineering Corp Method for installing new equipment and foundation member
JP2009167754A (en) 2008-01-18 2009-07-30 Cosmo System Kk Base frame for setting facility equipment and method of setting the base frame
JP3161082U (en) 2010-04-02 2010-07-22 渡邊 心治 Panel mounting structure
JP2011231481A (en) 2010-04-26 2011-11-17 Sunkensetsu Co Ltd Foundation member for installing outdoor facilities and backing fixing method for foundation member
JP2013213350A (en) 2012-04-02 2013-10-17 Sharp Corp Supporting member attachment structure, construction method for support structure, and photovoltaic power generation system using supporting member attachment structure

Also Published As

Publication number Publication date
JP2020023826A (en) 2020-02-13

Similar Documents

Publication Publication Date Title
CA2741013C (en) Construction frame shear lug
CN102433935A (en) Mounting and positioning rack for shock isolation supporting seat
JP2012102601A (en) Height-adjustable bearing device for structure and height adjustment method of bearing device for structure
JP2010048054A (en) Placing method and joint structure
JP7049961B2 (en) How to add equipment mount
JP3787971B2 (en) How to install seismic isolation devices
JPH10121576A (en) Fixing structure of pedestal
JP6964999B2 (en) Base plate fixing device and fixing method
JP4634829B2 (en) Base structure of base-isolated building
CN202370098U (en) Positioning frame for mounting shock-insulation support
JP4154472B2 (en) Deformation suppression device
JP5693372B2 (en) Seismic isolation structure and its construction method
JP3031253B2 (en) Adjustable column base
JP5181279B2 (en) Lower foundation structure of seismic isolation members
JP3858337B2 (en) Bridge girder erection method, support and bridge girder used therein, and bridge erected by the method
JP3829458B2 (en) Attaching the vibration control device to the building
JP5749606B2 (en) Seismic isolation method for existing buildings
JP7290940B2 (en) Seismic isolation device installation member, seismic isolation device stand structure, and construction method for seismic isolation device stand
JP2007284969A (en) Base isolation structure of building and its construction method
JP7192153B1 (en) Anchor bolt construction method and level adjustment member
JP6302778B2 (en) How to install seismic isolation devices
JP7421886B2 (en) How to construct a seismically isolated building
JP6368839B2 (en) How to install the seismic isolation device
JP2003293315A (en) Bearing position adjusting method and its adjusting jig
JP2022139045A (en) Seismic isolation construction method and seismic isolation structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201210

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211005

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20211013

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20211129

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220316

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220328

R150 Certificate of patent or registration of utility model

Ref document number: 7049961

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150