JP4573964B2 - Retaining wall construction method using blocks - Google Patents
Retaining wall construction method using blocks Download PDFInfo
- Publication number
- JP4573964B2 JP4573964B2 JP2000241134A JP2000241134A JP4573964B2 JP 4573964 B2 JP4573964 B2 JP 4573964B2 JP 2000241134 A JP2000241134 A JP 2000241134A JP 2000241134 A JP2000241134 A JP 2000241134A JP 4573964 B2 JP4573964 B2 JP 4573964B2
- Authority
- JP
- Japan
- Prior art keywords
- block
- slope
- retaining wall
- blocks
- excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Retaining Walls (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、通常の積み方式とは逆の上方から下方へコンクリートブロック(以下ブロックと略記)を配置して法面に擁壁を構築する方法に関する。
【0002】
【従来の技術】
法面に擁壁を構築する場合、従来は土台の上にブロックを積む施工方法が一般的であった。しかし、下から順に上へブロックを積む通常の擁壁施工法の場合、地山を大幅に掘削する必要があり、過堀りの問題と施工中に足場が必要であるという難点を有している。また、施工中に土砂の崩壊事故といった危険が伴う。
【0003】
法面の上方から下方へブロックを用いて擁壁を構築する方法の従来例として、図11に示すように、切り土法面1の補強にプレキャスト板2を配置する場合において、上段のプレキャスト板を地山に向けて打ち込んだ補強材(鋼棒、長尺ボルト等)3により固定した後、その下方を掘削し(a)、掘削された部分に下段のプレキャスト板を配置し(b)、下段のプレキャスト板を地山へ向けて打ち込んだ補強材3により固定する一連の工程によって、上方から下方へ擁壁を構築していく方法がある(例えば特開平7-34464号)。この施工法は余分な切り土や埋め戻しを必要としないので、土工量が低減でき、また、大幅に掘削土量が削減できるので地山を傷めず、森林維持と自然環境の保護が可能となる等の特徴がある。
【0004】
しかし、従来のこの施工方法は上段のプレキャスト板を配置した後に、下段の掘削に先だって上段のプレキャスト板を地山の有効部へ長尺の補強材3で固定する必要がある。図11(a)〜(f)によっても明らかであるが、この作業は大変であるし、危険が伴う。そのうえ、図11(e)にみられるように、補強材3頭部をトルクレンチ等により定着し、その後に補強材3頭部を隠すキャップを装着して仕上げる煩雑な作業が必要となる。そのため、全体の工費も一般工法に比べ割高となり、工法普及の妨げにもなっている。
【0005】
【発明が解決しようとする課題】
そこで、擁壁を構築する際に、地山の保護が可能であり、足場の構築の必要性もない、高能率に施工できるブロックを用いる擁壁構築方法を検討した。
【0006】
【課題を解決するための手段】
上記課題を検討した結果、法面に擁壁を構築するに際し、法面上部から法面の横方向に掘削法面と未掘削地山が交互になるよう掘削法面を段状に形成し、上段で掘削法面にブロックが配置された部位の下方は未掘削地山として、この未掘削地山の上面で施工途中の擁壁荷重を支持しながら上方から下方へ擁壁を連結構築することを特徴とするブロックを用いる擁壁構築方法を開発した。
【0007】
具体的には、法面に擁壁を構築するに際し、先ず、(a)天端法面において横方向に掘削法面を形成して、該掘削法面に天端コンクリート及びブロックを下方が地山に支持されるように配置し、次に、(b)前記(a)で配置されたブロックの下方に対して横方向に前記ブロックの縦サイズと同じだけ掘削した掘削法面と未掘削法面を交互に形成し、この掘削法面部分にブロックを下方が地山に支持されるように配置するとともにブロック上部を前記(a)で配置されたブロックに係合させ、(c)前記(b)で間欠的に残された未掘削地山を前記ブロックの縦方向幅の倍以上に掘削して掘削法面とし、この掘削法面部分にブロックを下方が地山に支持されるように配置するとともにブロック上部を前記(b)で配置されたブロックに係合させ、この一連の工程を土台まで交互に繰り返し、最下段においては未掘削地山を土台までの必要幅掘削して最下段ブロックを配置し、その下方に土台が設けられることを特徴とするブロックを用いる擁壁構築方法とした。
【0008】
前記ブロックは、使用態様によってはその控えに縦方向に連通する配筋孔又は砕石充填穴を設ける。更に、ブロックの上下左右に隣接するブロック間との継手を設ける。これにより土圧、上部荷重等の外圧を分散できる。
【0009】
更に、前記ブロックの背面の縦又は横サイズをブロック正面の縦又は横サイズよりも小さくすることにより、縦又は横方向のカーブにも対応させることができるようにした。
【0010】
【発明の実施の形態】
以下図面に基づき本発明を更に詳細に説明する。図1〜図6は本発明の擁壁構築方法で施工している過程の正面図であり、図7は完成時の正面図、図8は完成時の中央縦断面図である。図9はこの施工に用いられるブロックの斜視図であり、図10は他の構造例ブロックの斜視図である。
【0011】
図1にみられるように、擁壁を構築するに際し、先ず、天端法面において横方向に掘削法面を形成して、該掘削法面にブロックC1群を下方が地山に支持されるように配置し、その上に、天端コンクリート(天端ブロックでもよい)TCを上部が法面へ載るように打設配置している。ブロックC1群の下方から地山Bが支持しているからブロックC1や天端コンクリートが法面の下方に落ちることはない。
【0012】
次工程で未掘削地山B1を前記ブロックC1の縦サイズと同じだけ掘削して掘削法面とする。この掘削した法面にブロックC2群を配置する(図2)。ブロックC2群の下方から地山が支持しているからブロックC2が法面を下方に落ちることはない。また、図9にみられるように用いられるブロックCには上下左右に継手11a,11b,12a,12bを有するのでこれらの係合によって全体が一体となり、ブロックC2群の下方から地山が支持しているので、ブロックC1群の下方の次工程掘削対象地B2の部分を掘削してもブロックC1群は安定している。
【0013】
図2にみられるように、次工程掘削対象地B2部分を掘削するときは、間欠的に残された未掘削地山を前記ブロックの縦方向幅の倍以上に掘削して掘削法面とする。同様にして次工程掘削対象地B3〜次工程掘削対象地B5を順次繰り返す。
上段で掘削法面にブロックが配置された部位の下方は下段では未掘削地山として、未掘削地山で施工途中の擁壁荷重を支持しながら、上方から下方へ擁壁を構築することができるのである(図3〜図5)。
【0014】
このブロックを用いる擁壁構築方法において、これら一連の工程を土台Dまで交互に繰り返し、図6に示す最下段においては未掘削地山B6を土台までの必要幅だけ掘削して最下段ブロックを配置し、その下方に土台Dが最後に形成されている。
【0015】
各ブロックCの控えには配筋孔15が縦方向に上下のブロック間で連通して設けられている。これに上部の天端コンクリート(天端ブロックでもよい)に設けた配筋孔13から鉄筋14を配筋して土台Dに固定する。また、最上段は天端コンクリートとブロックC1を一体化した形状のL状の天端ブロックを使用してもよく、その上部に設けられた配筋孔から下方へ鉄筋を配筋してせん断抵抗を強化することが可能である。
【0016】
更に各ブロックCの控えに砕石充填穴16を設けている。この砕石充填穴16も上下のブロック間で連通して設けられている。このため、擁壁の背面へ裏込砕石を必要としない。
【0017】
図9(a)にみられる例では上方が突出した形状で、下方が凹溝の継手11a,11bに加えて、左右に突出した継手(あり継手)12a,12aを設けている。そこで全面が連結された構造とするには、図9(b)にみられるように、上方が突出した形状で、下方が凹溝の継手11a,11bに加えて、横に隣接するブロックには左右に凹溝(あり溝)継手12b,12bを有する構造のブロックを用いる必要がある。
【0018】
図10の例は、継手を図面上方と右方は突出した継手(あり継手)11a,12bとし、下方と左方の継ぎ手は凹溝(あり溝)継手11b,12aとしている。しかも、これらは前面の面(つら)から少し控えて設けているため、施工後の外観が目地のみ見えて良好である。特に、前面に擬石模様等の模様を形成すると環境に配慮したものとなる。また、1種類のブロックで施工が可能である。
【0019】
なお、図示することを省略するが、ブロックの背面の横(施工現場によっては縦)のサイズをブロック正面の横(又は縦)のサイズよりも小さくすることによって、横(又は縦)方向の曲面施工が可能となった。
【0020】
【発明の効果】
本発明は以上詳述したような擁壁構築方法であり、下記の特徴がある。
(1)掘削法面の過掘を最小限にすることができる。
(2)桁方向には鋼棒及びモルタルを配することで一体化及びずれ止め防止が可能である。
(3)ブロックの上下左右を連結することで外圧を分散することができる。
(4)切土と並行して施工できるため、安全施工が可能である。
(5)ブロック内に排水用の砕石を含む構造であるため、裏込砕石を必要としない。
(6)曲面(カーブ)に対しても良好な施工が可能である。
【図面の簡単な説明】
【図1】本発明の擁壁構築方法で施工している過程の正面図である。
【図2】同施工している過程の正面図である。
【図3】同施工している過程の正面図である。
【図4】同施工している過程の正面図である。
【図5】同施工している過程の正面図である。
【図6】同施工している過程の正面図である。
【図7】完成時の擁壁の正面図である。
【図8】完成時の同擁壁の中央縦断面側面図である。
【図9】 (a)、(b)共に施工に用いられたブロックの斜視図である。
【図10】他の構造例ブロックの斜視図である。
【図11】 (a)〜(f)は法面の上方から下方へブロックを用いて擁壁を構築する従来例の側面図である。
【符号の説明】
1 切り土法面
2 プレキャスト板
3 補強材(鋼棒、長尺ボルト等)
11a,11b 継手
12a,12b 継手
13 配筋孔
14 鉄筋
15 配筋孔
16 砕石充填穴
B 未掘削地山
C ブロック
D 土台
TC 天端コンクリート[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method for constructing a retaining wall on a slope by arranging concrete blocks (hereinafter abbreviated as blocks) from the upper side to the lower side, which is the reverse of the normal stacking method.
[0002]
[Prior art]
When building a retaining wall on the slope, a construction method in which blocks are stacked on the foundation has been common. However, in the case of the usual retaining wall construction method in which blocks are piled up in order from the bottom, it is necessary to excavate a large amount of ground, and there is a problem that a scaffold is necessary during construction and overdrilling problems. Yes. In addition, there is a risk of a sediment collapse accident during construction.
[0003]
As a conventional example of a method for constructing a retaining wall using blocks from the upper side to the lower side of the slope, as shown in FIG. 11, when the
[0004]
However, in this conventional construction method, it is necessary to fix the upper precast plate to the effective portion of the natural ground with the long reinforcing
[0005]
[Problems to be solved by the invention]
Therefore, when building a retaining wall, we examined a retaining wall construction method using blocks that can protect the natural ground and do not require the construction of a scaffold, and can be constructed efficiently.
[0006]
[Means for Solving the Problems]
As a result of examining the above problems, when building a retaining wall on the slope, the excavation slope is formed in steps so that the excavation slope and the unexcavated ground are alternated from the upper part of the slope to the lateral direction of the slope , The lower part of the part where the block is located on the excavation slope in the upper stage is an unexcavated ground, and the upper wall of this unexcavated ground is connected to the retaining wall from above while supporting the retaining wall load during construction. A retaining wall construction method using characteristic blocks was developed.
[0007]
Specifically, when constructing a retaining wall to slope, first, (a) at the top end slopes to form a drilling slopes laterally, the Tentan concrete and block the excavation slopes is below ground Placed to be supported by a mountain, then (b) a drilling slope and an unexcavated method excavated as much as the vertical size of the block laterally with respect to the lower side of the block placed in (a) forming a surface alternately engage the block to the excavation slopes portion blocks arranged block top in said (a) with downwardly arranged to be supported in the natural ground, (c) the ( The unexcavated ground pile left intermittently in b) is excavated to a depth of more than double the longitudinal width of the block, and the lower part of the block is supported by the natural ground on this excavation slope portion. the block upper with placing engaged with blocks arranged in the (b), until the base of this series of steps Each other repeatedly, in the bottom and required width drilling non excavating natural ground to the base to place the bottom block, and a retaining wall construction method using a block, characterized in that the base is provided therebelow.
[0008]
Depending on the mode of use, the block is provided with a reinforcing hole or a crushed stone filling hole that communicates in the longitudinal direction. Furthermore, joints between adjacent blocks on the top, bottom, left and right of the block are provided. Thereby, external pressures such as earth pressure and upper load can be dispersed.
[0009]
Furthermore, by making the vertical or horizontal size of the back of the block smaller than the vertical or horizontal size of the block front, it is possible to cope with a curve in the vertical or horizontal direction.
[0010]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, the present invention will be described in more detail with reference to the drawings. FIGS. 1-6 is a front view of the process of constructing by the retaining wall construction method of the present invention, FIG. 7 is a front view at the time of completion, and FIG. 8 is a central longitudinal sectional view at the time of completion. FIG. 9 is a perspective view of a block used for this construction, and FIG. 10 is a perspective view of another structural example block.
[0011]
As shown in FIG. 1, when constructing the retaining wall, first, a excavation slope is formed in the lateral direction at the top slope, and the block C 1 group is supported by the natural ground below the excavation slope. The top end concrete (or a top end block) TC is placed on the slope so that the upper part rests on the slope. Since the natural ground B supports from below the block C 1 group, the block C 1 and the top concrete do not fall below the slope.
[0012]
In the next step by drilling non excavating natural ground B 1 as much as the vertical size of the block C 1 and excavation slopes. A block C 2 group is placed on the excavated slope (FIG. 2). Since the natural ground is supported from below the block C 2 group, the block C 2 does not fall down the slope. Further, the joint 11a vertically and horizontally in block C to be used as seen in FIG. 9, 11b, 12a, generally by these engagement because it has a 12b come together, natural ground is supported from below of the block C 2 group since it is, and the block C 1 group be drilled portion of the subsequent step excavation target area B 2 of the lower block C 1 group is stable.
[0013]
As shown in FIG. 2, when excavating the area B 2 to be excavated in the next process, the unexcavated ground that has been left intermittently is excavated more than double the vertical width of the block, To do. Similarly, the next process excavation target area B 3 to the next process excavation target area B 5 are sequentially repeated.
The lower part of the area where the block is placed on the excavation slope in the upper stage is an unexcavated ground in the lower stage, and the retaining wall can be constructed from above to below while supporting the retaining wall load during construction on the unexcavated ground. It can be done (FIGS. 3 to 5).
[0014]
In retaining wall construction method using this block are alternately repeated series of steps up to the base D, and the bottom block by drilling the non-drilling natural ground B 6 only required widths up base in the bottom of FIG. 6 The base D is finally formed below it.
[0015]
In the block of each block C, a
[0016]
Further, a crushed
[0017]
In the example shown in FIG. 9 (a), in addition to the joints 11a and 11b having an upward projecting shape and a recessed groove on the lower side, joints 12a and 12a projecting to the left and right are provided. Therefore, in order to obtain a structure in which the entire surface is connected, as shown in FIG. 9 (b), in addition to the joints 11a and 11b having a protruding top and a concave groove on the bottom, It is necessary to use a block having a structure having concave groove (groove) joints 12b, 12b on the left and right.
[0018]
In the example of FIG. 10, the joints (protruded joints) 11a and 12b protrude from the upper and right sides of the drawing, and the concave and concave joints (recessed groove) joints 11b and 12a are provided at the lower and left joints. In addition, since these are provided a little from the front surface (icicle), the appearance after construction is good because only the joints can be seen. In particular, when a pattern such as a pseudo stone pattern is formed on the front surface, the environment is considered. Moreover, construction is possible with one type of block.
[0019]
Although not shown in the figure, the horizontal (or vertical) curved surface is made smaller by making the horizontal (or vertical) size of the back of the block smaller than the horizontal (or vertical) size of the front of the block. Construction is now possible.
[0020]
【The invention's effect】
The present invention is a retaining wall construction method as detailed above, and has the following features.
(1) Excessive excavation of the slope can be minimized.
(2) Integration and prevention of slippage are possible by arranging steel bars and mortar in the girder direction.
(3) The external pressure can be dispersed by connecting the top, bottom, left and right of the block.
(4) Since it can be constructed in parallel with the cut, safe construction is possible.
(5) Since the block contains crushed stone for drainage, no back crushed crushed stone is required.
(6) Good construction is possible even for curved surfaces (curves).
[Brief description of the drawings]
FIG. 1 is a front view of a process in which a retaining wall construction method according to the present invention is applied.
FIG. 2 is a front view of the construction process.
FIG. 3 is a front view of the construction process.
FIG. 4 is a front view of the construction process.
FIG. 5 is a front view of the construction process.
FIG. 6 is a front view of the construction process.
FIG. 7 is a front view of the retaining wall when completed.
FIG. 8 is a central longitudinal cross-sectional side view of the retaining wall when completed.
FIGS. 9A and 9B are perspective views of blocks used for construction.
FIG. 10 is a perspective view of another structural example block;
FIGS. 11A to 11F are side views of a conventional example in which a retaining wall is constructed using blocks from the upper side to the lower side of the slope.
[Explanation of symbols]
1 Cut
11a, 11b fitting
12a, 12b fitting
13 Reinforcing bar
14 Rebar
15 Reinforcing bar
16 Crushed stone filling hole B Unexcavated ground C Block D Foundation
TC top concrete
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000241134A JP4573964B2 (en) | 2000-08-09 | 2000-08-09 | Retaining wall construction method using blocks |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2000241134A JP4573964B2 (en) | 2000-08-09 | 2000-08-09 | Retaining wall construction method using blocks |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2002054159A JP2002054159A (en) | 2002-02-20 |
JP4573964B2 true JP4573964B2 (en) | 2010-11-04 |
Family
ID=18732367
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2000241134A Expired - Fee Related JP4573964B2 (en) | 2000-08-09 | 2000-08-09 | Retaining wall construction method using blocks |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4573964B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6074342B2 (en) * | 2013-09-14 | 2017-02-01 | 岡本 俊仁 | Stabilization method of natural slope |
JP7194850B1 (en) | 2022-02-15 | 2022-12-22 | 株式会社エスイー | Auxiliary support device for retaining wall panels |
JP7234438B1 (en) | 2022-03-25 | 2023-03-07 | 株式会社エスイー | How to construct a slope-stabilizing retaining wall |
JP7194853B1 (en) | 2022-05-25 | 2022-12-22 | 株式会社エスイー | Support structure for retaining wall panel in slope-stabilized retaining wall |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62276123A (en) * | 1986-05-26 | 1987-12-01 | Makoto Kaneuji | Slope cutting work |
-
2000
- 2000-08-09 JP JP2000241134A patent/JP4573964B2/en not_active Expired - Fee Related
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS62276123A (en) * | 1986-05-26 | 1987-12-01 | Makoto Kaneuji | Slope cutting work |
Also Published As
Publication number | Publication date |
---|---|
JP2002054159A (en) | 2002-02-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6299386B1 (en) | Method and apparatus for a shoring wall | |
KR101051965B1 (en) | Panel joint for underground continuous wall construction and underground continuous wall construction method | |
KR20060103309A (en) | Gradual bottom-up slice and gradual infilling method for removing underground retaining wall | |
KR102195504B1 (en) | Construction method for Eearth self-retaining wall using reinforcing member and CIP construction method | |
CN105525627A (en) | Two-way anchorage plate retaining wall and construction method thereof | |
KR100831332B1 (en) | Underground retaining wall for public works and method for constructing the same | |
KR102195510B1 (en) | Construction method for earth self-retaining wall using reinforcing member and PHC pile | |
KR100289256B1 (en) | Tunnel construction method in shallow toffee area | |
JP4573964B2 (en) | Retaining wall construction method using blocks | |
US20190003142A1 (en) | Block Retaining Wall with Micro-Pile Soldier Piles | |
KR20090057708A (en) | Bracing structure to use two rows pile | |
JP3893056B2 (en) | Construction method of underground structure | |
KR100562686B1 (en) | The underground structure and it's construction method is using sheet pile and cast in a place concrete | |
KR102345291B1 (en) | Tunnel construction method and tunnel supporting structure | |
JP3955763B2 (en) | Retaining wall block and retaining wall construction method using the same | |
JPH11190024A (en) | Earth retaining work | |
KR20030086233A (en) | execution method of landscape architecture for cutting ground using blasting stone and structure of landscape architecture for the same | |
JP4529631B2 (en) | Underground structure and construction method of underground structure | |
JP2899668B2 (en) | Simple underground construction | |
JPS6018769B2 (en) | Construction method of underground structure | |
JPS6015774B2 (en) | like wall | |
KR102194388B1 (en) | Construction method for earth self-retaining wall using reinforcing member and Soil retaining plate construction method | |
JPS60192030A (en) | Terraced block for reinforced concrete retaining wall | |
JP4337561B2 (en) | Cut reinforcement earthwork and its construction method | |
KR100500648B1 (en) | Structure for temporary retaining wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20070802 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20090428 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090507 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090623 |
|
RD03 | Notification of appointment of power of attorney |
Free format text: JAPANESE INTERMEDIATE CODE: A7423 Effective date: 20090623 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20090721 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20090910 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20100720 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20100818 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130827 Year of fee payment: 3 |
|
LAPS | Cancellation because of no payment of annual fees |