JP3955763B2 - Retaining wall block and retaining wall construction method using the same - Google Patents

Retaining wall block and retaining wall construction method using the same Download PDF

Info

Publication number
JP3955763B2
JP3955763B2 JP2002030098A JP2002030098A JP3955763B2 JP 3955763 B2 JP3955763 B2 JP 3955763B2 JP 2002030098 A JP2002030098 A JP 2002030098A JP 2002030098 A JP2002030098 A JP 2002030098A JP 3955763 B2 JP3955763 B2 JP 3955763B2
Authority
JP
Japan
Prior art keywords
retaining wall
wall block
front plate
concrete
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002030098A
Other languages
Japanese (ja)
Other versions
JP2003232047A (en
Inventor
隆行 大月
修司 小野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Landes Co Ltd
Original Assignee
Landes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Landes Co Ltd filed Critical Landes Co Ltd
Priority to JP2002030098A priority Critical patent/JP3955763B2/en
Publication of JP2003232047A publication Critical patent/JP2003232047A/en
Application granted granted Critical
Publication of JP3955763B2 publication Critical patent/JP3955763B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Retaining Walls (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、通常の積み方式とは逆に上方から下方へ配置して法面に擁壁を構築するに適し た擁壁ブロックと、前記擁壁ブロックを用いた擁壁構築方法とに関する。
【0002】
【従来の技術】
法面に擁壁を構築する場合、従来は土台の上に擁壁ブロックを積む施工方法が一般的であった。しかし、下から順に上へ擁壁ブロックを積む通常の擁壁施工法の場合、地山を大幅に掘削する必要があり、過堀りの問題があることと、施工中に足場が必要であるという難点を有している。また、施工中に土砂の崩壊事故を生起するといった危険を伴う。
【0003】
この欠点を補うために、法面の上方から下方へコンクリート板を用いて擁壁を構築する方法として、図21に示す工法がある。この工法は、切り土法面21の補強にコンクリート板22を配置する場合に、上段のコンクリート板を地山に向けて打ち込んだ補強材(鋼棒、長尺ボルト等)23により固定した後、その下方を掘削し(a)、掘削された部分に下段のコンクリート板を配置し(b)、下段のコンクリート板を地山へ向けて打ち込んだ補強材23により固定する一連の工程によって、上方から下方へ擁壁を構築していく方法である(例えば特開平07-34464号)。この施工法は余分な切り土や埋め戻しを必要としないので、土工量が低減でき、また、大幅に掘削土量が削減できるので地山を傷めず、森林維持と自然環境の保護が可能となる等の特徴がある。
【0004】
しかし、従来のこの施工方法は上段のプレキャスト板を配置した後に、下段の掘削に先だって上段のプレキャスト板を地山の有効部へ長尺の補強材23で固定する必要がある。図21(a)〜(f)によっても明らかであるが、この作業は大変であるし、危険を伴う。そのうえ、図21(e)にみられるように、補強材23の頭部をトルクレンチ等により定着し、その後に補強材23の頭部を隠すキャップを装着して仕上げる煩雑な作業が必要となる。そのため、全体の工費も一般工法に比べ割高となり、工法普及の妨げにもなっている。
【0005】
【発明が解決しようとする課題】
そこで、擁壁ブロックを用いて擁壁を構築する際に、掘削土量を削減して地山の保護が可能であり、足場の構築の必要性もなく、かつ高能率、安価に施工できる擁壁構築方法を検討した。更に、構築された擁壁の耐久性についても検討し、この施工法に適した擁壁ブロックを提供することとしたのである。
【0006】
【課題を解決するための手段】
上記課題について、本発明は、前面版と、梁部を介して前記前面版に対して傾斜して設けた控版とにより上方にコンクリート打設口を有するコンクリート打設間隙を形成すると共に控版背部に設けた背面梁部と前記控版とにより上方を開口した胴込部を形成してなる擁壁ブロックを開発した。よりしくは、部前面版と、上部前面版下部へ屈曲状態で形成され、梁部を介して前記前面版に対して傾斜して設けた控版とにより、上方にコンクリート打設口を有するコンクリート打設間隙を形成すると共に、上部前面版又は控版の背部に設けた背面梁部と前記控版とにより上方を開口した胴込部を形成してなる擁壁ブロックである。上部前面版は擁壁勾配に略平行とし、控版は上部前面版と逆勾配でくの字状屈曲状態で形成し、下部前版が略垂直状態に形成してなる構造が好適である。この擁壁ブロックには吊り作業を容易にするために、吊り環を設けたり、吊り環を螺着するためのねじ穴を擁壁ブロック上部に設ける等の吊り手段を設けると好ましい。上部前面版の上部に重合突縁を形成すると、上段の擁壁ブロックとの隙間を覆うことができる。
【0007】
また、コンクリート打設間隙に設けられた前後方向の梁部に対して水抜き孔を設けると、擁壁背面の水を排水して擁壁にかかる背面圧を減少させ得る。前面版と下方が広くなるよう傾斜させて設けた控版間が、強度的に問題を生じる場合には、前面版の上部又は底部から控版に向けて補強版(底版)をコンクリート打設が可能な程度の通過穴を形成した状態で設けることもできる。
【0008】
上段の擁壁ブロックと下段の擁壁ブロックとは、上記コンクリート打設間隙と胴込部とに打設一体化されたコンクリートによって高強度に維持される。通常使用されるコンクリート以外に、軽量コンクリート、合成樹脂、合成樹脂発泡体等の擁壁全体の一体固化を図ることができる材料を用いることも可能である。これらはコンクリート打設口からの打設量を加減することにより控版と下部前面版間の上方一部に植栽土の充填室を形成して緑化を可能にすることもできる。その際に根腐れを防止するために、植栽土の充填室下方に保水剤や排水可能な多孔質コンクリート等の使用、又は下部前面版に排水孔を設けるとよい。
【0009】
本発明は他の一態様として、擁壁ブロックの上部又は底部に上段の擁壁ブロックと下段の擁壁ブロック間の係合手段を設けることも考えられる。係合手段としては、上段の擁壁ブロックに下段の擁壁ブロックを吊る鈎状フック金具等がある。鈎状フック金具の場合、上段の擁壁ブロックに対して下段の擁壁ブロックを垂直方向へ回動させながら、かつ水平方向へ調整して配置することもできる。また、下段の擁壁ブロックの下方の地山を更に掘削する作業における安全性を確保することができる。
【0010】
また、上部前面版又は控版の背部に設けた背面梁部の上方にはコンクリートの横方向への流出防止版を形成すると共に、その流出防止版の下段のものが擁壁ブロックを積んだ時に下部前面版下方に嵌まる嵌合い溝を設けるとよい。更に、上部前面版又は下部前面版の上部又は下部に型枠板挿入用切欠を設けて、挿入した型枠板によりコンクリートの横方向への流出防止を可能にしてもよい。更に、擁壁ブロックの縦方向に配筋を設けたり、施工時に擁壁ブロック縦方向に配筋を施すことも、擁壁強度を高めるのに好ましいので、必要に応じて実施することができる。
【0011】
更に、本発明は、上記いずれかの擁壁ブロックを用い、法面上部の横方向に上段の擁壁ブロックを配置連結し、その下方一部の地山を掘削して掘削法面部分に形成し、前記掘削法面部分に下段の擁壁ブロックを配置し、上段の擁壁ブロックのコンクリート打設間隙と下段の擁壁ブロックの胴込部とに打設するコンクリートによって一体化する擁壁構築方法を開発した。詳しくは、コンクリート打設間隙と胴込部とを形成した擁壁ブロックを用い、法面上部の横方向に連結した上段の擁壁ブロック群間の下方一部の地山を掘削して掘削法面部分と未掘削地山部分とし、前記掘削法面部分に下ブロック群を配置して、前記上段の擁壁ブロック群のコンクリート打設間隙と前記下段の擁壁ブロック群の胴込部とに打設するコンクリートによって、下段の擁壁ブロック群と上段の擁壁ブロック群の一部とを上下に一体化させ、次に下段の擁壁ブロック群の横方向で上段の擁壁ブロック群の下方に残る未掘削地山部分を掘削して形成した掘削法面部分へ他の下段の擁壁ブロック群を配置し上下及び左右を一体化する一連の工程を上下方向と左右方向に複数回繰り返しながら擁壁を上方から下方へと構築する擁壁構築方法である。
【0012】
この擁壁構築方法において、最上段の擁壁ブロックは天端コンクリートで仕上げされた後、又は同時に一体施工するのが好ましい。未掘削地山部分による支持力を利用して天端構造物を構築することができる。また、最下段の擁壁ブロックの下方には擁壁全体を安定に支持するための土台を現場打ちにより形成するとか、基礎ブロックを使用することができる。
【0013】
この擁壁構築方法によると、上段の擁壁ブロック下方の一部の未掘削地山部分を掘削して掘削法面部分を形成する際に、掘削法面部分上の宙吊り上段の擁壁ブロックが地山で支持された擁壁ブロック群により形成された横梁により支持されることとなる。そのためには、擁壁ブロック間のコンクリートによる一体化も好ましいが、法面の横方向に連結する擁壁ブロック間に配筋を施すとより効果的である。擁壁ブロック間に連なる配筋を有するように個々の擁壁ブロックへ配筋を施したものも好適である。
【0014】
更に地山と擁壁ブロック背部との間には必要に応じて排水材とか、隙間処理材を用いるとよい。排水材は擁壁背面の水を排水して背面圧を減少させる機能を有するものであればよく、例えば、多孔質(ポーラス)コンクリート等の多孔質無機粒子や、不織布、織布、金網等の水が浸透する素材の中から選択して使用することができる。隙間処理材は擁壁ブロックを設計された勾配に合致させる際に掘削後の法面との間に生じる隙間を埋めるためのもので、強度と耐久性を備えたものであれば、無機粒体(例えば砂利、砕石等)、有機粒体を問わず使用することができる。
【0015】
擁壁ブロックの地盤支持を均等にするためや破損防止、配置や位置決めを容易にするため、更には、安定性、安全等を期すために、掘削法面部分に配置する擁壁ブロックの底面へ緩衝材、滑材、滑り防止材又は楔材を用いるとよい。緩衝材としては、無機又は有機繊維不織布、織布、金網やその他多孔質部材を使用することができる。滑材は上段の擁壁ブロックの下方へ下段の擁壁ブロックを配置する際に滑り抵抗を減少させて移動を容易にすることができ、金属板、プラスチック板、平行な複数の棒体、コロ等を適宜使用する。配置や位置決めの正確さを期すために楔材の使用もよい。更に、配置した擁壁ブロックの移動を防止したり、擁壁完成までの安全を確保するために擁壁ブロックの底面と地山との間、又は完成された擁壁の安定性を確保するために擁壁ブロック背面と地山との間に滑り防止材を使用するのも好適である。
【0016】
【発明の実施の形態】
図1〜図6に本発明の擁壁構築方法の施工の様子を示している。図7は完成された擁壁例の正面図である。図1〜図5において(a)は施工断面図であり、(b)は正面図である。この施工は、まず、1)図1にみられるように天端部分となる地山を掘削する。2)次に、図2に示すように、法面の横方向に最上段(天端)の上段の擁壁ブロック1aが地山2へ支持されるように順次配置する。3)次いで、図3に示すように、上段の擁壁ブロック1aの背面部3にコンクリートを充填して天端コンクリート4を形成する。施工場所によっては、天端コンクリート4が上段の擁壁ブロック1aの上部に予め一体化された構造であってもよい。また、上段の擁壁ブロック1aの側面に継手を設けてもよい。
【0017】
4)次に、天端コンクリート4を形成した後に、図4に示すように上段の擁壁ブロック1aの下部地山2を掘削法面部分2aと未掘削地山部分2bが交互になるように掘削する。コンクリートで一体化された上段の擁壁ブロック群が未掘削地山部分に支持されて横梁をなすので下部地山を掘削しても落下しない。5)次いで、図5に示すように掘削法面部分2aへ下段の擁壁ブロック1bが地山へ支持されるように配置する。6)更に、図6に示すように、上段の擁壁ブロック1a前方の開口部であるコンクリート打設口5よりコンクリートを充填することで、下段の擁壁ブロック1bと一体化する。各擁壁ブロック背面と掘削法面6間には必要時に隙間処理材や排水材を使用する。
【0018】
これで、前記4)〜6)を下方向と横方向に複数回繰り返しながら擁壁を上方から下方へと構築すると、いわゆる逆巻きブロック工法で、図7に一例を示すように擁壁を構築することができる。最下段の擁壁ブロック1nの前方のコンクリート打設口5よりコンクリートを充填して擁壁全体を安定に支持するための土台24を形成している。台形断面の基礎ブロックの使用も可能である。この例では、いも目地となるように下段の擁壁ブロックが配置されているが、食い違いの目地(破り目地)を有するように下段の擁壁ブロックを配置することもできる。また、目地の形状も谷切り、2面切り、亀甲切り等任意なものにすることができる。
【0019】
この擁壁構築方法に用いる擁壁ブロックの実施例を図8、図9に示す。この擁壁ブロック1は、擁壁勾配に略平行に形成されている上部前面版7の下部へ控版8を形成し、上方を開口した胴込部10を形成している。また、上部前面版7の下部で控版8の前面へ下部前面版9によりコンクリート打設間隙11を形成している。更に、控版8と下部前面版9間の上方を開口してコンクリート打設口5とした構造である。控版8と下部前面版9間のコンクリート打設間隙11の中間に前後方向に梁部12を形成して躯体をなしており、かつ、梁部12の両側に打設されるコンクリートが左右に隣り合う擁壁ブロック及び下段の擁壁ブロックとの一体化を可能にして擁壁の剛性を高める。胴込部10の中間にも前後方向に背面梁部13を形成して補強している。この例では背面梁部13に横方向の貫通孔14を形成しており、法面の横方向に連結する擁壁ブロック間に配筋を施すとか、吊り作業に使用する。吊り作業を容易にするためには、吊り環を設けたり、吊り環を螺着するためのねじ穴等の適当な吊り手段を適当な位置に設けてもよい。
【0020】
上部前面版7の上部には前方への重合突縁15を形成しており、上段の擁壁ブロックとの隙間を覆うようにしている。また、梁部の前後方向に対して水抜き孔16を設けることによって、図10に施工後の要部断面を示すように、擁壁背面の水を排水して擁壁にかかる背面圧を減少させるようにしている。なお、図11は正面図であり、図12は平面図である。背面梁部13が掘削法面と接する部分には排水材17を使用し、隙間がある部分には隙間処理材18を用いた。排水材17は擁壁背面の水を排水して背面圧を減少させる機能を有するもので、この例では多孔質(ポーラス)コンクリートを使用した。例えば、不織布、織布等の中から選択使用することができる。隙間処理材18は擁壁ブロックを設計された勾配に合致させる際に掘削後の法面との間に生じる隙間を埋めるもので、強度と耐久性を備えた鉱物を熱処理して得られた無機連続気泡体を使用した。
【0021】
掘削法面部分で上段の擁壁ブロック1aの下へ下段の擁壁ブロック1bを配置する方法は、図13にみられるように、下段の擁壁ブロック1bを水平方向に移動させて所定の位置へ吊りながら適所に配置するのも一つの方法である。下段の擁壁ブロック1bを水平方向に移動させるとき、滑り抵抗を減少させて移動を容易にするために、金属板の移動抵抗減少材を一時使用している。配置や位置決めの正確を期すために楔材の使用等の使用も適宜行う。更に、配置した擁壁ブロックの移動を防止したり、擁壁完成までの安全を確保するために擁壁ブロックの底面と地山との間、又は完成された擁壁の安定性を確保するために擁壁ブロック背面と地山との間に滑り防止材を使用するのも好適である。
【0022】
図14〜図17は背面梁部13の上方から横方向へコンクリートが流出するのを防止する手段を設けた本発明の実施例である。図14〜図16は背面梁部13の上方へ横方向流出防止版25を形成すると共に、下部前面版9の下方に嵌合い溝26を設けている。下段の擁壁ブロックの横方向流出防止版25が擁壁ブロックを積んだ時に上段の擁壁ブロックの嵌合い溝26に嵌まるようにして密な構造としている。また、図17のように、上部前面版7と下部前面版9のそれぞれに型枠板挿入用切欠27、28を設けて、挿入した型枠板によりコンクリートの横方向への流出防止を可能にしてもよい。型枠板挿入用切欠は上部前面版7又は下部前面版9のいずれか一方に設けるだけでもよい。
【0023】
これまで例示した擁壁ブロックの構造を簡略化して、本発明の擁壁構築方法に用いることもできる擁壁ブロックの他の構造例を図18に示す。この擁壁ブロックは、前面版29と前記前面版へ梁部12を介して下方が広くなるよう傾斜させて設けた控版8とにより、上方にコンクリート打設口5のある下方が広いコンクリート打設間隙11を形成すると同時に控版の背部に下方を狭くした胴込部10を形成した構造である。控版の背部に背面梁部13を形成している。
【0024】
本発明の擁壁構築方法の他の態様として、図19にみられるような、下段の擁壁ブロックを回動させながら配置することも考えられる。そのために、上段の擁壁ブロック1aと下段の擁壁ブロック1bとの間に係合手段19を設けている。係合手段19として、上段の擁壁ブロック1aの底部前方に下段の擁壁ブロック1bを吊ることができる鈎状フック金具19aを垂直方向へ回動可能に軸支して設け、下段の擁壁ブロック1bの上部前方へ前記フック金具19aを掛止可能に受け環19bを設けている。この場合、係合手段19の鈎状フック金具19aと受け環19bを係合させた後、上段の擁壁ブロック1aに対して下段の擁壁ブロック1bを垂直方向へ回動させながら、かつ水平方向へ調整して配置することができる。下段の擁壁ブロックの下方の地山を更に掘削する作業の間の安全を確保する特徴もある。
【0025】
図20は本発明の擁壁構築方法によって構築する擁壁を植生可能な多自然型とした例であって、前記のように上方から下方へと配置される上段の擁壁ブロック1aと下段の擁壁ブロック1bとをコンクリート打設間隙11と胴込部10とにコンクリート打設によって一体化するに際し、コンクリート打設口5からの打設量を加減することにより控版8と下部前面版9間の上方一部に空間を残して、植栽土等の充填室20を形成し緑化を可能にしている。植物の根腐れを防止するために、植栽土の充填室20底部下方にポーラスコンクリートを使用すると共に下部前面版9に水抜き孔を設けている。
【0026】
【発明の効果】
本発明の擁壁ブロックは、この擁壁構築方法における擁壁の上方から下方へと配置される上段の擁壁ブロックと下段の擁壁ブロックとをコンクリート打設によって一体化するのに適しており、また、コンクリート打設で一体化された上段の擁壁ブロック群が未掘削地山部分に支持されて横梁をなすので下部地山を掘削しても落下しない。更に、掘削法面部分へ下段の擁壁ブロックを配置した後に、後の工程で更に下段の擁壁ブロックの下方を掘削しても落ちない一体化構造が可能である。加えて、上部前面版も下部前面版も自然石や擬石模様を付すことができるので、前面のコンクリート打設口からの打設構造でありながら、自然石や擬石模様の擁壁とすることができる。
【0027】
また、本発明の擁壁ブロックを用いた擁壁構築方法によって、擁壁の下方向と横方向に擁壁ブロックを複数回繰り返しながら配置して、擁壁を上方から下方へと構築する、いわゆる逆巻きブロック工法を実施可能にした。従来の擁壁構築方法に比べて掘削土量を削減し、地山の保護が可能であり、足場の構築の必要性もない。高能率、安価に施工できる擁壁構築方法となっている。更に、施工中の安全が確保され、しかも、構築された擁壁の耐久性も良好となっている。
【図面の簡単な説明】
【図1】本発明の擁壁構築方法における部分掘削の様子を示す、(a)は施工断面図であり、(b)は正面図である。
【図2】上部より一段目の擁壁ブロックを配置した様子を示す、(a)は施工断面図であり、(b)は正面図である。
【図3】天端コンクリートを形成した様子を示す、(a)は施工断面図であり、(b)は正面図である。
【図4】擁壁ブロックの下部地山を掘削法面部分と未掘削地山部分が交互になるように掘削した様子を示す、(a)は施工断面図であり、(b)は正面図である。
【図5】掘削法面部分へ下段の擁壁ブロックを配置した様子を示す、(a)は施工断面図であり、(b)は正面図である。
【図6】上段の擁壁ブロック前方のコンクリート打設口よりコンクリートを充填することで、下段の擁壁ブロックと一体化した様子を示す施工断面図である。
【図7】本発明の擁壁構築方法の施工の結果完成された擁壁例の正面図である。
【図8】本発明の擁壁構築方法に用いる擁壁ブロック例の正面斜視図である。
【図9】同擁壁ブロックの背面斜視図である。
【図10】同擁壁ブロックを用いて施工後の要部断面図である。
【図11】同要部正面図である。
【図12】同要部平面図である。
【図13】下段の擁壁ブロックを水平に移動させて配置する様子を示す施工断面図である。
【図14】背面梁部の上方へ横方向流出防止版を形成した例の平面図である。
【図15】同正面図である。
【図16】図14、図15中A−A断面図である。
【図17】型枠板挿入用切欠を設けた例の正面斜視図である。
【図18】簡略化した擁壁ブロックの背面斜視図である。
【図19】下段の擁壁ブロックを回動させながら配置する様子を示す施工断面図である。
【図20】本発明の擁壁構築方法によって構築する擁壁を植生可能な多自然型とした例の要部断面図である。
【図21】上方から下方へ擁壁を構築していく従来法の施工断面図である。
【符号の説明】
1 擁壁ブロック
1a 上段の擁壁ブロック
1b 下段の擁壁ブロック
1n 最下段の擁壁ブロック
2 地山
2a 掘削法面部分
2b 未掘削地山部分
擁壁ブロックの背面部
4 天端コンクリート
5 コンクリート打設口
6 掘削法面
7 上部前面版
8 控版
9 下部前面版
10 胴込部
11 コンクリート打設間隙
12 梁部
13 背面梁部
14 貫通孔
15 重合突縁
16 水抜き孔
17 排水材
18 隙間処理材
19 係合手段
19a 鈎状フック金具
19b 受け環
20 植栽土等の充填室
24 土台
25 横方向流出防止版
26 嵌合い溝
27 型枠板挿入用切欠
28 型枠板挿入用切欠
29 前面版
[0001]
BACKGROUND OF THE INVENTION
The present invention includes a retaining wall block the normal loading scheme suitable for building a retaining wall to slope and placed from above in the reverse downward, and to a retaining wall construction method using the retaining wall blocks.
[0002]
[Prior art]
When constructing a retaining wall on a slope , a construction method in which retaining wall blocks are stacked on a base has been common. However, in the case of the usual retaining wall construction method, in which the retaining wall blocks are stacked in order from the bottom, it is necessary to excavate the natural ground drastically, and there is a problem of overexcavation, and a scaffold is necessary during construction. Has the disadvantages. In addition, there is a risk of causing a sediment collapse accident during construction.
[0003]
In order to make up for this drawback, there is a method shown in FIG. 21 as a method for constructing a retaining wall using a concrete plate from the upper side to the lower side of the slope. In this method, when the concrete plate 22 is arranged to reinforce the cut slope 21, the upper concrete plate is fixed with a reinforcing material (steel bar, long bolt, etc.) 23 that is driven toward the ground, The lower part is excavated (a), the lower concrete plate is arranged in the excavated part (b), and the lower concrete board is fixed by the reinforcing material 23 driven into the natural ground from above, from above. This is a method of constructing a retaining wall downward (for example, Japanese Patent Application Laid-Open No. 07-34464). Since this construction method does not require extra cutting or backfilling, the amount of earthwork can be reduced, and the amount of excavated soil can be greatly reduced, so that it is possible to maintain the forest and protect the natural environment without damaging the ground. There are features such as.
[0004]
However, in this conventional construction method, it is necessary to fix the upper precast plate to the effective part of the natural ground with the long reinforcing material 23 prior to the lower excavation after the upper precast plate is arranged. As is apparent from FIGS. 21A to 21F, this work is difficult and dangerous. In addition, as shown in FIG. 21 (e), the head of the reinforcing member 23 is fixed with a torque wrench or the like, and then a complicated work is required to finish by attaching a cap that hides the head of the reinforcing member 23. . For this reason, the overall construction cost is higher than that of the general construction method, which hinders the spread of the construction method.
[0005]
[Problems to be solved by the invention]
Therefore, when constructing a retaining wall using retaining wall blocks, it is possible to reduce the amount of excavated soil and protect the natural ground, and there is no need to construct a scaffold, and it is possible to construct a retaining wall with high efficiency and low cost. The wall construction method was examined. Furthermore, the durability of the constructed retaining wall was also examined, and a retaining wall block suitable for this construction method was provided.
[0006]
[Means for Solving the Problems]
For above-mentioned problems, the present onset Ming, a front plate, to form the concreting gap with concrete設口upward by a copy plate provided to be inclined with respect to the front plate through the beam portion, the rear beam portion provided on the back of the copy version and said copy version developed a retaining wall block which is formed by forming a Dokomi portion that opens upward. More good details, the lower portion front plate, are formed at the bottom to the flexion of the upper front plate, by a copy plate provided to be inclined with respect to the front plate through the beam portion, concrete設口upward to form the concrete設間gap having a top front plates or Receipt Version back to retaining wall blocks formed by forming an opening was Dokomi unit upward by a rear beam portion and the copy version provided for. A structure in which the upper front plate is substantially parallel to the gradient of the retaining wall, the holding plate is formed in a dogleg-shaped bent state opposite to the upper front plate, and the lower front plate is formed in a substantially vertical state is preferable. To facilitate the work hanging in the retaining wall block, preferably hanging or provided ring, provided hanging means such as providing a screw hole for screwing the hanging ring on top of the retaining wall blocks. If a superposed protrusion is formed on the upper part of the upper front plate, the gap with the upper retaining wall block can be covered.
[0007]
Moreover, if a drainage hole is provided in the beam portion in the front-rear direction provided in the concrete placing gap, the back pressure applied to the retaining wall can be reduced by draining the water on the rear surface of the retaining wall. If there is a problem in strength between the front plate and the plate that is tilted so that the lower part is wide, concrete reinforcement is placed from the top or bottom of the front plate toward the plate. It can also be provided in a state where a possible passage hole is formed.
[0008]
The upper retaining wall blocks and the lower retaining wall blocks, is maintained at a high strength by Da設integrated concrete and the concreting gap and Dokomi portion. In addition to the commonly used concrete, it is also possible to use a material that can achieve solidification of the entire retaining wall, such as lightweight concrete, synthetic resin, and synthetic resin foam. These can be made green by adjusting the amount of placement from the concrete placement opening to form a planting soil filling chamber in the upper part between the plate and the lower front plate. In this case, in order to prevent root rot, it is preferable to use a water retaining agent or porous concrete that can be drained below the filling chamber of the planting soil, or to provide a drain hole in the lower front plate.
[0009]
The present invention as another aspect, it is conceivable to the top or bottom of the retaining wall block provided engagement means between the upper retaining wall blocks and the lower retaining wall blocks. Examples of the engaging means include a hook-shaped hook metal fitting that suspends the lower retaining wall block from the upper retaining wall block. In the case of the hook-shaped hook metal fitting, the lower retaining wall block can be arranged in the horizontal direction while being rotated in the vertical direction with respect to the upper retaining wall block. Moreover, the safety | security in the operation | work which excavates the natural ground below the lower retaining wall block further can be ensured.
[0010]
In addition, a concrete spill prevention plate is formed above the rear beam on the back of the upper front plate or holding plate, and the lower plate of the spill prevention plate is loaded with retaining wall blocks. A fitting groove that fits below the lower front plate may be provided. Moreover, also the upper portion of the upper front plate or the lower front plate provided with a notch for mold plates inserted at the bottom, the inserted mold plate may allow outflow prevention in the lateral direction of the concrete. Additionally, or provided Haisuji in the longitudinal direction of the retaining wall blocks, also be subjected to Haisuji in the longitudinal direction of the retaining wall blocks during construction, since preferred for increasing the retaining wall strength can be implemented if necessary .
[0011]
Furthermore, the present invention uses any one of the above retaining wall blocks, and arranges and connects the upper retaining wall block in the lateral direction above the slope surface, and excavates a part of the ground below it to form the excavation slope surface portion. retaining wall construction and, the place lower retaining wall blocks drilling method surface section, integrated with the concrete to Da設to the Dokomi of concrete設間gap and lower retaining wall blocks of the upper retaining wall blocks Developed a method. Specifically, using a retaining wall block formed with a concrete placement gap and a trunk portion, excavation method is performed by excavating a part of the lower ground between the upper retaining wall blocks connected laterally above the slope. and the surface portion and the non-excavating natural ground portion, by placing the blocks of the lower stage to the excavation slopes portion, Dokomi portion of retaining wall blocks of said lower and concrete設間gap retaining wall blocks of the upper The lower retaining wall block group and a part of the upper retaining wall block group are vertically integrated by the concrete placed on the upper side, and then the upper retaining wall block group in the lateral direction of the lower retaining wall block group. Place a group of other lower retaining wall blocks on the excavation slope part formed by excavating the unexcavated ground part remaining below, and perform a series of processes to integrate the vertical and horizontal sides in the vertical and horizontal directions. Retaining wall structure that builds the retaining wall from top to bottom while repeating It is a method.
[0012]
In this retaining wall construction method, it is preferable that the uppermost retaining wall block is integrally constructed after finishing with top-end concrete or simultaneously. The top end structure can be constructed using the bearing force of the unexcavated ground. In addition, a foundation for stably supporting the entire retaining wall can be formed below the lowermost retaining wall block by spotting, or a foundation block can be used.
[0013]
According to this retaining wall construction method, when a part of the unexcavated ground part below the upper retaining wall block is excavated to form the excavation slope part, the upper suspended wall block suspended above the excavation slope part is It will be supported by the cross beam formed by the retaining wall block group supported by the natural ground. For that purpose, the integration of the retaining wall blocks with concrete is also preferable, but it is more effective if reinforcement is provided between the retaining wall blocks connected in the lateral direction of the slope. Also suitable that has been subjected to Haisuji to individual retaining wall blocks to have a reinforcement continuous between retaining wall blocks.
[0014]
Further, a drainage material or a clearance treatment material may be used between the natural ground and the back of the retaining wall block as necessary. The drainage material only needs to have a function of draining the water behind the retaining wall and reducing the backside pressure. For example, porous inorganic particles such as porous concrete, nonwoven fabric, woven fabric, wire mesh, etc. It can be selected from materials that allow water to penetrate. The gap treatment material is for filling the gap between the sloped wall and the slope after excavation when matching the retaining wall block with the designed slope, and if it has strength and durability, inorganic particles (For example, gravel, crushed stone, etc.) and organic particles can be used.
[0015]
And prevent damage to equalize the ground supporting the retaining wall blocks, in order to facilitate placement and positioning, furthermore, stability, for the sake of safety and the like, to the bottom surface of the retaining wall blocks to place excavation slopes portion A cushioning material, a sliding material, an anti-slip material, or a wedge material may be used. As the buffer material, inorganic or organic fiber nonwoven fabric, woven fabric, wire mesh, and other porous members can be used. When the lower retaining wall block is placed below the upper retaining wall block, the sliding material can reduce sliding resistance and facilitate movement, and can be moved by metal plates, plastic plates, parallel bars, rollers Etc. are used as appropriate. A wedge material may also be used to ensure placement and positioning accuracy. Furthermore, in order to prevent the movement of the retaining wall block placed, and to ensure the safety until the retaining wall is completed, between the bottom surface of the retaining wall block and the natural ground, or to ensure the stability of the completed retaining wall. It is also preferable to use an anti-slip material between the back of the retaining wall block and the natural ground.
[0016]
DETAILED DESCRIPTION OF THE INVENTION
1 to 6 show the construction of the retaining wall construction method of the present invention. FIG. 7 is a front view of a completed retaining wall example. 1 to 5, (a) is a construction sectional view, and (b) is a front view. In this construction, first, as shown in FIG. 1, a natural mountain that becomes a top end portion is excavated. 2) Next, as shown in FIG. 2, the upper retaining wall block 1 a at the uppermost stage (top edge) is sequentially arranged in the lateral direction of the slope so that it is supported by the natural ground 2. 3) Next, as shown in FIG. 3, concrete is filled in the back surface portion 3 of the upper retaining wall block 1 a to form the top concrete 4. Depending on the construction site, the top end concrete 4 may be integrated in advance with the upper part of the upper retaining wall block 1a. Further, a joint may be provided on the side surface of the upper retaining wall block 1a.
[0017]
4) Next, after the top concrete 4 is formed, as shown in FIG. 4, the lower ground 2 of the upper retaining wall block 1a is alternated between the excavation slope portion 2a and the unexcavated ground portion 2b. Excavate. The upper retaining wall block group integrated with concrete is supported by the unexcavated ground part and forms a horizontal beam, so it does not fall even if the lower ground part is excavated. 5) Next, as shown in FIG. 5, the lower retaining wall block 1b is disposed on the excavation slope portion 2a so as to be supported by the natural ground. 6) Furthermore, as shown in FIG. 6, it is integrated with the lower retaining wall block 1b by filling the concrete from the concrete placement port 5 which is an opening in front of the upper retaining wall block 1a. Between the rear surface of each retaining wall block and the excavation slope 6, clearance treatment materials and drainage materials are used when necessary.
[0018]
When the retaining wall is constructed from above to below while repeating the above 4) to 6) multiple times in the downward and lateral directions, the retaining wall is constructed as shown in FIG. 7 by the so-called reverse winding block method. be able to. A base 24 is formed to fill the concrete from the concrete placing port 5 in front of the lowermost retaining wall block 1n and stably support the entire retaining wall. It is also possible to use a trapezoidal cross section foundation block. In this example, the lower retaining wall blocks are arranged such that the potato joints, can also be placed lower retaining wall blocks to have discrepancies joint (breaking joint). Moreover, the shape of the joint can also be made arbitrary, such as a valley cut, a double cut, and a turtle shell cut.
[0019]
Examples of retaining wall blocks used in this retaining wall construction method are shown in FIGS. This retaining wall block 1 forms a holding plate 8 at the lower part of the upper front plate 7 formed substantially parallel to the retaining wall gradient, and forms a body portion 10 that opens upward. Further, a concrete placing gap 11 is formed by the lower front plate 9 at the lower part of the upper front plate 7 and in front of the holding plate 8. Further, the upper part between the holding plate 8 and the lower front plate 9 is opened to form a concrete placing port 5. A beam 12 is formed in the front-rear direction in the middle of the concrete placing gap 11 between the holding plate 8 and the lower front plate 9 to form a frame, and the concrete placed on both sides of the beam 12 is left and right. It is possible to integrate the adjacent retaining wall block and the lower retaining wall block to increase the rigidity of the retaining wall. A back beam portion 13 is also formed in the middle of the trunk portion 10 in the front-rear direction and is reinforced. In this example, a lateral through-hole 14 is formed in the back beam portion 13, and reinforcement is provided between retaining wall blocks connected in the lateral direction of the slope or used for a suspension operation. In order to facilitate the suspension work, a suspension ring may be provided or an appropriate suspension means such as a screw hole for screwing the suspension ring may be provided at an appropriate position.
[0020]
A front overlapping projection 15 is formed on the upper portion of the upper front plate 7 so as to cover a gap with the upper retaining wall block. In addition, by providing drain holes 16 in the longitudinal direction of the beam part, the water behind the retaining wall is drained to reduce the back pressure on the retaining wall, as shown in the cross section of the main part after construction. I try to let them. FIG. 11 is a front view, and FIG. 12 is a plan view. The drainage material 17 was used for the portion where the back beam portion 13 was in contact with the excavation slope, and the clearance treatment material 18 was used for the portion where there was a gap. The drainage material 17 has a function of draining the water behind the retaining wall to reduce the backside pressure. In this example, porous (porous) concrete was used. For example, it can be selected and used from nonwoven fabrics, woven fabrics, and the like. Crevice treatment material 18 fills the gap that occurs between the slope and the slope after excavation when matching the retaining wall block with the designed gradient, and it is an inorganic material obtained by heat-treating mineral with strength and durability. An open cell was used.
[0021]
How to place the lower retaining wall block 1b to below the upper retaining wall blocks 1a drilling slope face portions, as seen in FIG. 13, a predetermined position by moving the lower retaining wall block 1b in the horizontal direction One way is to place it in the right place while hanging it. When the lower retaining wall block 1b is moved in the horizontal direction, a metal plate movement resistance reducing material is temporarily used to reduce sliding resistance and facilitate movement. Use of a wedge material or the like is also performed as appropriate in order to ensure accurate placement and positioning. Furthermore, in order to prevent the movement of the retaining wall block placed, and to ensure the safety until the retaining wall is completed, between the bottom surface of the retaining wall block and the natural ground, or to ensure the stability of the completed retaining wall. It is also preferable to use an anti-slip material between the back of the retaining wall block and the natural ground.
[0022]
14 to 17 show an embodiment of the present invention in which means for preventing the concrete from flowing out in the lateral direction from above the back beam portion 13 is provided. 14 to 16, a lateral outflow prevention plate 25 is formed above the back beam portion 13, and a fitting groove 26 is provided below the lower front plate 9. The lateral retaining plate 25 of the lower retaining wall block has a dense structure so that it fits into the fitting groove 26 of the upper retaining wall block when the retaining wall block is stacked. In addition, as shown in FIG. 17, the upper front plate 7 and the lower front plate 9 are provided with notches 27 and 28 for inserting the form plate, respectively, and the inserted form plate can prevent the concrete from flowing out in the lateral direction. May be. The notch for inserting the mold plate may be provided only in either the upper front plate 7 or the lower front plate 9.
[0023]
FIG. 18 shows another structural example of the retaining wall block that can be used in the retaining wall construction method of the present invention by simplifying the structure of the retaining wall block exemplified so far. The retaining wall block, by a copy plate 8 provided in an inclined so that the lower widened via the beam portion 12 and the front plate 29 to the front plate, concrete設口5 of some lower wide concrete upward In this structure, the gap portion 11 is formed, and at the same time, the body portion 10 having a narrowed bottom is formed on the back portion of the plate. A back beam 13 is formed on the back of the plate.
[0024]
As another aspect of the retaining wall construction method of the present invention, it is also conceivable that the lower retaining wall block as shown in FIG. 19 is arranged while being rotated. For this purpose, the engaging means 19 is provided between the upper retaining wall block 1a and the lower retaining wall block 1b. As the engagement means 19, a hook-shaped hook metal fitting 19a capable of hanging the lower retaining wall block 1b in front of the bottom of the upper retaining wall block 1a is pivotally supported so as to be pivotable in the vertical direction, and the lower retaining wall is provided. A receiving ring 19b is provided in front of the upper portion of the block 1b so that the hook metal piece 19a can be hooked. In this case, after engaging the hook-shaped hook metal fitting 19a of the engaging means 19 and the receiving ring 19b, the lower retaining wall block 1b is rotated in the vertical direction with respect to the upper retaining wall block 1a, and horizontally. Adjustable to the direction. There is also a feature to ensure safety during the work of further excavating the natural ground below the lower retaining wall block.
[0025]
Figure 20 is a retaining wall constructed by retaining walls construction method of the present invention there is provided a case in which the vegetation can multi natural type, the upper retaining wall blocks 1a and the lower disposed from above downward as When the retaining wall block 1b is integrated with the concrete placement gap 11 and the trunk portion 10 by concrete placement, the amount of placement from the concrete placement opening 5 is adjusted to adjust the holding plate 8 and the lower front plate 9 A space 20 is left in the upper part of the space, and a filling room 20 for planting soil or the like is formed to enable greening. In order to prevent root rot of the plant, porous concrete is used below the bottom of the planting soil filling chamber 20 and a drain hole is provided in the lower front plate 9.
[0026]
【The invention's effect】
The retaining wall block of the present invention is suitable for integrating the upper retaining wall block and the lower retaining wall block, which are arranged from the upper side to the lower side of the retaining wall in this retaining wall construction method, by concrete placement. In addition, the upper retaining wall block group integrated by the concrete placement is supported by the unexcavated natural ground portion and forms a horizontal beam, so it does not fall even if the lower natural ground is excavated. Furthermore, after placing the lower retaining wall blocks to excavation slopes portion, by drilling a lower further lower retaining wall blocks in the subsequent step it is possible integral structure which does not fall even. In addition, because both the upper front plate and the lower front plate can be given natural stones or pseudo stone patterns, they can be natural stones or pseudo stone pattern retaining walls, even though they are cast from the front concrete placement port. it can.
[0027]
In addition, by the retaining wall construction method using the retaining wall block of the present invention, the retaining wall block is arranged in a downward direction and a lateral direction while repeating the retaining wall block a plurality of times, so that the retaining wall is constructed from the top to the bottom. The reverse winding block method was made possible. Compared with the conventional retaining wall construction method, the amount of excavated soil can be reduced, the ground can be protected, and there is no need to construct a scaffold. Retaining wall construction method that can be constructed at high efficiency and at low cost. Furthermore, safety during construction is ensured, and the durability of the constructed retaining wall is also good.
[Brief description of the drawings]
1A and 1B show a state of partial excavation in the retaining wall construction method of the present invention, in which FIG. 1A is a sectional view of construction and FIG. 1B is a front view;
FIGS. 2A and 2B show a state where a first-stage retaining wall block is arranged from the top, FIG. 2A is a sectional view of construction, and FIG. 2B is a front view;
FIGS. 3A and 3B show a state where top end concrete is formed, in which FIG. 3A is a sectional view of construction and FIG. 3B is a front view;
FIGS. 4A and 4B show a state where the lower ground of the retaining wall block is excavated so that the excavation slope portion and the unexcavated ground portion alternate, (a) is a construction sectional view, and (b) is a front view. It is.
FIGS. 5A and 5B show a state in which a lower retaining wall block is arranged on the excavation slope portion, where FIG. 5A is a construction sectional view, and FIG. 5B is a front view.
FIG. 6 is a construction cross-sectional view showing a state in which the concrete is filled with the concrete from the concrete placement port in front of the upper retaining wall block and integrated with the lower retaining wall block.
FIG. 7 is a front view of a retaining wall example completed as a result of the construction of the retaining wall construction method of the present invention.
FIG. 8 is a front perspective view of a retaining wall block example used in the retaining wall construction method of the present invention.
FIG. 9 is a rear perspective view of the retaining wall block.
FIG. 10 is a cross-sectional view of a main part after construction using the retaining wall block.
FIG. 11 is a front view of the main part.
FIG. 12 is a plan view of the main part.
FIG. 13 is a construction sectional view showing a state in which the lower retaining wall block is horizontally moved and arranged.
FIG. 14 is a plan view of an example in which a lateral outflow prevention plate is formed above the rear beam portion.
FIG. 15 is a front view of the same.
16 is a cross-sectional view taken along line AA in FIGS. 14 and 15. FIG.
FIG. 17 is a front perspective view of an example in which a notch for inserting a mold plate is provided.
FIG. 18 is a rear perspective view of a simplified retaining wall block.
FIG. 19 is a construction cross-sectional view illustrating a state where the lower retaining wall block is disposed while being rotated.
FIG. 20 is a cross-sectional view of the main part of an example in which the retaining wall constructed by the retaining wall construction method of the present invention is a multi-natural type that can be vegetated.
FIG. 21 is a cross-sectional view of a conventional method for constructing a retaining wall from above to below.
[Explanation of symbols]
1 Retaining wall block
1a Upper retaining wall block
1b Lower retaining wall block
1n Lowermost retaining wall block 2
2a Drilling slope
2b Unexcavated ground part 3 Retaining part of retaining wall block 4 Top end concrete 5 Concrete pouring port 6 Digging slope 7 Upper front plate 8 Depression plate 9 Lower front plate
10 Torso
11 Concrete placement gap
12 Beam
13 Back beam
14 Through hole
15 Superposition edge
16 Drain hole
17 Drainage material
18 Clearance treatment material
19 Engagement means
19a hook-shaped hook fitting
19b
20 Filling room for planting soil
24 foundation
25 Lateral outflow prevention version
26 Fitting groove
27 Notch for inserting form plate
28 Notch for inserting form plate
29 Front version

Claims (10)

前面版と、梁部を介して前記前面版に対して傾斜して設けた控版とにより上方にコンクリート打設口を有するコンクリート打設間隙を形成すると共に控版背部に設けた背面梁部と前記控版とにより上方を開口した胴込部を形成してなる擁壁ブロック。A front plate, to form the concreting gap with concrete設口upward by copy version and provided inclined with respect to the front plate through the beam portion, the rear beam provided on the back of copy edition A retaining wall block formed by forming a barrel portion opened upward by the portion and the plate . 部前面版と、上部前面版下部へ屈曲状態で形成され、梁部を介して前記前面版に対して傾斜して設けた控版とにより、上方にコンクリート打設口を有するコンクリート打設間隙を形成すると共に、上部前面版又は控版の背部に設けた背面梁部と前記控版とにより上方を開口した胴込部を形成してなる擁壁ブロック。A lower portion front plate, are formed at the bottom to the flexion of the upper front plate, by a copy plate provided to be inclined with respect to the front plate through the beam portion, concreting with concrete設口upward A retaining wall block that forms a gap and forms a trunk portion that opens upwardly by a back beam portion provided on the back portion of the upper front plate or plate and the plate . 上部前面版が擁壁勾配に略平行であり、控版が上部前面版と逆勾配でくの字状屈曲状態で形成されており、下部前版が略垂直状態に形成されてなる請求項記載の擁壁ブロック。Substantially parallel upper front plate is in the retaining wall slope, copy version is formed by shaped flexion of the upper front plate and the inverse gradient Do, claim 2 lower front plate is formed in a substantially vertical state Retaining wall block as described. 上部前面版の上部に上段の擁壁ブロックとの重合突縁を形成してなる請求項又は記載の擁壁ブロック。 The retaining wall block according to claim 2 or 3, wherein a superposed protruding edge with an upper retaining wall block is formed on the upper front plate. 擁壁ブロックの上部又は底部に上段の擁壁ブロックと下段の擁壁ブロック間の係合手段を設けた請求項又は記載の擁壁ブロック。 The retaining wall block according to claim 2 or 3, wherein an engaging means between the upper retaining wall block and the lower retaining wall block is provided at an upper portion or a bottom portion of the retaining wall block. 係合手段が上段の擁壁ブロックに下段の擁壁ブロックを吊る鈎状フック金具である請求項記載の擁壁ブロック。6. The retaining wall block according to claim 5, wherein the engaging means is a hook-shaped hook fitting for suspending the lower retaining wall block from the upper retaining wall block. 背面梁部の上方へコンクリートの横方向流出防止版を形成すると共に下部前面版下方に嵌合い溝を設けた請求項2又は3記載の擁壁ブロック。And forming a transverse outflow prevention plate of the concrete above the rear beam portion, retaining wall blocks according to claim 2 or 3, wherein providing the groove mutual fit below the lower front plate. 上部前面版上部又は下部前面版の下部に型枠板挿入用切欠を設けた請求項又は記載の擁壁ブロック。 Top front plate of the upper or retaining wall block according to claim 2 or 3, wherein providing the notch for mold plate inserted into the bottom of the lower front plate. 請求項1〜請求項8いずれか記載の擁壁ブロックを用い、法面上部の横方向に上段の擁壁ブロックを配置連結し、その下方一部の地山を掘削して掘削法面部分に形成し、前記掘削法面部分に下段の擁壁ブロックを配置し、上段の擁壁ブロックのコンクリート打設間隙と下段の擁壁ブロックの胴込部とに打設するコンクリートによって一体化する擁壁構築方法。 Using the retaining wall block according to any one of claims 1 to 8 , the upper retaining wall block is arranged and connected in the lateral direction above the slope surface, and a part of the lower ground is excavated to the excavation slope surface portion. formed, the place lower retaining wall blocks drilling method surface section, integrated with the concrete to Da設to the Dokomi of concrete設間gap and lower retaining wall blocks of the upper retaining wall block retaining wall Construction method. 請求項1〜請求項8いずれか記載の擁壁ブロックを用い、法面上部の横方向に連結した上段の擁壁ブロック群間の下方一部の地山を掘削して掘削法面部分と未掘削地山部分とし、前記掘削法面部分に下の擁壁ブロック群を配置して、前記上段の擁壁ブロック群のコンクリート打設間隙と前記下段の擁壁ブロック群の胴込部とに打設するコンクリートによって、下段の擁壁ブロック群と上段の擁壁ブロック群の一部とを上下に一体化させ、次に下段の擁壁ブロック群の横方向で上段の擁壁ブロック群の下方に残る未掘削地山部分を掘削して形成した掘削法面部分へ他の下段の擁壁ブロック群を配置し上下及び左右を一体化する一連の工程を上下方向と左右方向に複数回繰り返しながら擁壁を上方から下方へと構築する擁壁構築方法。 Using the retaining wall block according to any one of claims 1 to 8 , excavating a part of the ground below the upper retaining wall block group connected in the lateral direction at the upper part of the slope, and drilling natural ground portion, by arranging the retaining wall blocks of the lower stage to the excavation slopes part, to the Dokomi portion of retaining wall blocks of said lower and concrete設間gap retaining wall blocks of the upper by concrete for pouring, it is integrated and part of the lower retaining wall blocks and the upper retaining wall blocks vertically, then the lower of the lower retaining wall block upper retaining wall blocks in the transverse direction of the group Place a group of other lower retaining wall blocks on the excavation slope part formed by excavating the unexcavated ground part remaining in the area , and repeat a series of processes in the vertical and horizontal directions multiple times in the vertical and horizontal directions Retaining wall construction method that constructs retaining wall from top to bottom.
JP2002030098A 2002-02-06 2002-02-06 Retaining wall block and retaining wall construction method using the same Expired - Fee Related JP3955763B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002030098A JP3955763B2 (en) 2002-02-06 2002-02-06 Retaining wall block and retaining wall construction method using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002030098A JP3955763B2 (en) 2002-02-06 2002-02-06 Retaining wall block and retaining wall construction method using the same

Publications (2)

Publication Number Publication Date
JP2003232047A JP2003232047A (en) 2003-08-19
JP3955763B2 true JP3955763B2 (en) 2007-08-08

Family

ID=27773987

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002030098A Expired - Fee Related JP3955763B2 (en) 2002-02-06 2002-02-06 Retaining wall block and retaining wall construction method using the same

Country Status (1)

Country Link
JP (1) JP3955763B2 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7089956B2 (en) * 2018-06-18 2022-06-23 聡 糸井 Retaining wall blocks and retaining walls
CN114197504A (en) * 2021-12-31 2022-03-18 中铁一局集团有限公司 Comprehensive treatment construction method for unstable side slope
JP7194850B1 (en) 2022-02-15 2022-12-22 株式会社エスイー Auxiliary support device for retaining wall panels
JP7234438B1 (en) 2022-03-25 2023-03-07 株式会社エスイー How to construct a slope-stabilizing retaining wall
JP7194853B1 (en) 2022-05-25 2022-12-22 株式会社エスイー Support structure for retaining wall panel in slope-stabilized retaining wall

Also Published As

Publication number Publication date
JP2003232047A (en) 2003-08-19

Similar Documents

Publication Publication Date Title
CN107250460A (en) Pre- ingot bar keeping wall method for preventing landslide
JP4809431B2 (en) Foundation structure of structure and retaining wall
JPH08218401A (en) Block for lean type retaining wall and construction method of lean type retaining wall in which the block is used
KR101077949B1 (en) Block for reinforcement and construction method
US5222342A (en) Component elements of protecting structures against erosion and process for assembling and placing the protection structure
JP3955763B2 (en) Retaining wall block and retaining wall construction method using the same
KR100447331B1 (en) execution method of landscape architecture for cutting ground using blasting stone and landscape architecture apparatus using the same
JPS6140914A (en) Erosion control dam and its construction
KR20180040095A (en) Construction method for soil retaining wall using cap slab
JP2000144769A (en) Method of landslide protection work for preparing housing lot
JP4573964B2 (en) Retaining wall construction method using blocks
JP2000104260A (en) Construction of slope face protecting block
JP2004204670A (en) Retaining wall block
KR19990021988U (en) Block for breastwall
JP3561436B2 (en) Retaining wall block for planting and method of constructing retaining wall for planting using the block
JPS5851092B2 (en) Earth retaining installation method using advance shoring frame
JP6899057B2 (en) Foundation block of concrete block for retaining wall
JP2004204669A (en) Retaining wall block and stacking method therefor
JP4127020B2 (en) Vertical embankment method and retaining wall used in this method
JP3724306B2 (en) Legal block
KR200405490Y1 (en) Basic structure of a bank
JP4155519B2 (en) Construction method of concrete frame with underdrain
WO2007049773A1 (en) Retaining wall block
JPS6015774B2 (en) like wall
JP2881235B2 (en) Slope stabilization method and formwork block for slope stabilization

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20050202

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20061010

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20061031

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20061227

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20070410

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20070507

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110511

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120511

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120511

Year of fee payment: 5

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130511

Year of fee payment: 6

LAPS Cancellation because of no payment of annual fees