JP4436226B2 - Exterior wall panel construction method - Google Patents

Exterior wall panel construction method Download PDF

Info

Publication number
JP4436226B2
JP4436226B2 JP2004300989A JP2004300989A JP4436226B2 JP 4436226 B2 JP4436226 B2 JP 4436226B2 JP 2004300989 A JP2004300989 A JP 2004300989A JP 2004300989 A JP2004300989 A JP 2004300989A JP 4436226 B2 JP4436226 B2 JP 4436226B2
Authority
JP
Japan
Prior art keywords
wall panel
wall
upper layer
support
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2004300989A
Other languages
Japanese (ja)
Other versions
JP2006112131A (en
Inventor
麻起 大和矢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2004300989A priority Critical patent/JP4436226B2/en
Publication of JP2006112131A publication Critical patent/JP2006112131A/en
Application granted granted Critical
Publication of JP4436226B2 publication Critical patent/JP4436226B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Description

本発明は構築済みの躯体とその躯体に支持されている下層側の外壁パネルに上層側の外壁パネルを仮支持させながら、鉄筋コンクリート造の躯体を構築する外壁パネルの施工方法に関するものである。 The present invention relates to a pre-built while temporary support to the external wall panels on the upper layer side to the outer wall panels of the lower side of skeleton that is supported by the skeleton, construction how the external wall panel for building skeleton of reinforced concrete .

鉄筋コンクリート造躯体の建物の外壁をカーテンウォールのように予めプレキャスト化された外壁パネルから構成する場合、外壁パネルは腰壁から垂壁までに亘る部分を有するスパンドレル部とガラスやサッシ等が収納される窓部とに区分され、スパンドレル部と窓部が分離している場合、躯体に対してはスパンドレル部が外壁パネルとして窓部に先行して設置される。   When the outer wall of a reinforced concrete structure building is constructed from pre-cast outer wall panels such as curtain walls, the outer wall panel stores a spandrel part having a portion extending from the waist wall to the vertical wall, glass, sash, etc. In the case where the spandrel part and the window part are separated from each other, the spandrel part is installed in front of the window part as an outer wall panel for the housing.

外壁パネルは一般的にはタワークレーンや地上のクレーンから懸垂した状態で建物の外周部に吊り込まれ、躯体への接合が完了するまではクレーンに支持された状態に保たれるが、1枚の外壁パネルが特定のクレーンを占有する時間が長いため、クレーンの稼働率が低下し、工期に影響する可能性がある。   The outer wall panel is generally suspended from the tower crane or the crane on the ground and is suspended on the outer periphery of the building, and is kept supported by the crane until the connection to the frame is completed. Since the outer wall panel occupies a certain crane for a long time, the operation rate of the crane is lowered, which may affect the construction period.

そこで、躯体に先行して支持されている下層側の外壁パネル上にサポートを、構築済みの躯体とサポートとの間に控えサポートをそれぞれ設置し、両サポートに新たな上層側の外壁パネルを支持させることにより、クレーンの使用を吊り込み時に限定し、クレーンの占有時間を減らす方法がある(特許文献1参照)。   Therefore, a support is installed on the outer wall panel on the lower layer side that is supported prior to the chassis, and a backup support is installed between the constructed chassis and the support, and a new upper wall panel is supported on both supports. Therefore, there is a method of limiting the use of the crane at the time of suspension and reducing the occupation time of the crane (see Patent Document 1).

躯体に先行して支持されている下層側の外壁パネル上に、この下層側の外壁パネルと上層側の外壁パネルを同時に保持し得る取付治具を設置し、下層側の外壁パネルを保持した取付治具上に上層側の外壁パネルを設置すると共に、上下の外壁パネル間にサポートを、取付治具と構築済みの躯体とに間に斜めサポートをそれぞれ設置し、取付治具と両サポートに上層側の外壁パネルを支持させる方法もある(特許文献2参照)。   A mounting jig that can hold the lower wall panel and the upper wall panel at the same time is installed on the lower wall panel that is supported prior to the housing, and the lower wall panel is held. Install the upper-layer outer wall panel on the jig, install the support between the upper and lower outer wall panels, and install the diagonal support between the mounting jig and the built frame, and install the upper layer on the mounting jig and both supports. There is also a method of supporting the outer wall panel on the side (see Patent Document 2).

特開2004−124547号公報(段落0028、図1、図3〜図6)JP 2004-124547 A (paragraph 0028, FIG. 1, FIGS. 3 to 6) 特公平7−116843号公報(請求項2、第1図)Japanese Patent Publication No. 7-116843 (Claim 2, FIG. 1)

しかしながら、特許文献1の方法では先行して躯体に支持されている下層側の外壁パネルと新たに設置される上層側の外壁パネルとの間にサポートを設置し、そのサポートと構築済みのスラブとの間に控えサポートを設置している関係から、外壁パネルをサポート上に吊り込んだときの、外壁パネルの安定性を確保する上で、1枚の外壁パネルにつき、梁の上端位置と下端位置等、上下2箇所で躯体に接合することが必要になっており、外壁パネルを躯体に支持させるための作業が煩雑になり易い。   However, in the method of Patent Document 1, a support is installed between an outer wall panel on the lower layer side that is previously supported by the housing and an outer wall panel on the upper layer side that is newly installed, and the support and the constructed slab In order to ensure the stability of the outer wall panel when the outer wall panel is suspended on the support, the upper end position and the lower end position of the beam for each outer wall panel Thus, it is necessary to join the housing at two locations, upper and lower, and the work for supporting the outer wall panel on the housing tends to be complicated.

また特許文献1のように外壁パネルが腰壁と垂壁に相当する壁板しか持たない場合、外壁パネルは縦断面上、サポートには1点でしか支持されないため、サポートのみによっては外壁パネルを吊り込んだときの安定性が十分に得られない。このため、躯体への接合が完了するまではクレーンを切り離すことができず、結局、クレーンの占有時間を大幅に減らすことにはならない。   In addition, when the outer wall panel has only wall plates corresponding to the waist wall and the hanging wall as in Patent Document 1, the outer wall panel is supported only at one point on the support in the longitudinal section, and depending on the support alone, the outer wall panel may be Sufficient stability when suspended. For this reason, the crane cannot be separated until the joining to the frame is completed, and consequently the occupation time of the crane is not greatly reduced.

更に特許文献1では躯体としての鉄骨梁に外壁パネルを支持させる場合を想定していることから、プレキャストコンクリート製の外壁パネルが剛性の差から鉄骨梁と一体的に挙動しない可能性が高いため、外壁パネルが躯体に対して自由に相対変形できるためのファスナーを外壁パネルと鉄骨梁の双方に固定しておかなければならない。また双方のファスナーは外壁パネルと鉄骨梁間の相対変形である層間変位と、熱応力による鉄骨梁の伸縮に追従できる機能を持つ必要があるため、ファスナーの製作と外壁パネルの製作に要するコストが上昇する傾向がある。   Furthermore, in Patent Document 1, since it is assumed that the outer wall panel is supported by the steel beam as the casing, the outer wall panel made of precast concrete is unlikely to behave integrally with the steel beam due to the difference in rigidity. Fasteners that allow the outer wall panel to freely deform relative to the frame must be secured to both the outer wall panel and the steel beam. In addition, both fasteners must have the ability to follow the interlaminar displacement, which is the relative deformation between the outer wall panel and the steel beam, and the expansion and contraction of the steel beam due to thermal stress, which increases the cost required to manufacture the fastener and the outer wall panel. Tend to.

特許文献2の方法では外壁パネルを躯体の梁に接合する必要から、取付治具を外壁パネルの屋外側に配置せざるを得ず、斜めサポートを上層側の外壁パネルの下において取付治具に連結することになるため、上層側の外壁パネルの安定性が損なわれ易い。また取付治具が上下の外壁パネルに跨り、双方に接続される必要があるため、取付治具の外壁パネルへの着脱に時間を要し、上層側の外壁パネルを躯体に支持させた後の取付治具の転用効率が低下し易い。   In the method of Patent Document 2, since the outer wall panel needs to be joined to the frame beam, the mounting jig must be arranged on the outdoor side of the outer wall panel, and the diagonal support is used as the mounting jig under the outer wall panel on the upper layer side. Since it will connect, the stability of the outer wall panel of the upper layer side is easy to be impaired. In addition, since the mounting jig straddles the upper and lower outer wall panels and needs to be connected to both sides, it takes time to attach and detach the mounting jig to and from the outer wall panel, and after the upper wall panel is supported by the housing The diversion efficiency of the mounting jig tends to decrease.

本発明は上記背景より、従来方法の問題点を解決するために創案されたものであり、特許文献1、2の方法より外壁パネルをサポート上に吊り込んだときの、あるいは吊り込んだときからの安定性を確保でき、その結果、クレーンの占有時間を大幅に減らすことが可能で、製作コストを低減できる外壁パネルの施工方法を提案するものである。 From the above background, the present invention was devised to solve the problems of the conventional method, and when the outer wall panel is hung on the support or when it is hung from the method of Patent Documents 1 and 2. of can ensure stability, as a result, can significantly reduce the occupation time of the crane, it is to propose a construction how the outer wall panel capable of reducing manufacturing cost.

本請求項1に記載の発明は、構築済みの躯体とその躯体に支持されている下層側の外壁パネルにプレキャストコンクリート製の上層側の外壁パネルを仮支持させながら、前記上層側の外壁パネルが一体化する鉄筋コンクリート造の躯体を構築する外壁パネルの施工方法において、前記鉄筋コンクリート造の躯体に支持されるための定着材が屋内側に突出した前記上層側の外壁パネルを、前記下層側の外壁パネルの上方にサポートを介して設置すると共に、このサポートと前記構築済みの躯体との間、及び前記上層側の外壁パネルと前記構築済みの躯体との間に控え材を架設し、このサポートと控え材に前記上層側の外壁パネルを仮支持させる工程と、前記上層側の外壁パネルが一体化する鉄筋コンクリート造の躯体の中に前記上層側の外壁パネルの定着材が挿入される状態で、その鉄筋コンクリート造の躯体を構築し、その躯体に前記上層側の外壁パネルを支持させる工程と、を有することを構成要件とする。   According to the first aspect of the present invention, the upper-layer outer wall panel is temporarily supported by the pre-cast concrete upper-layer outer wall panel while the built-up housing and the lower-layer outer wall panel supported by the housing are temporarily supported. In the construction method of the outer wall panel for constructing the reinforced concrete frame to be integrated, the upper layer outer wall panel in which the fixing material to be supported by the reinforced concrete frame is projected indoors is used as the lower wall panel. And a support member is installed between the support and the constructed casing, and between the outer wall panel on the upper layer side and the constructed casing. A step of temporarily supporting the outer wall panel on the upper layer on a material, and an outer wall panel on the upper layer side in a reinforced concrete frame integrated with the outer wall panel on the upper layer side. In a state where the fixing member Le is inserted, its building a reinforced concrete skeleton and a step of supporting the external wall panels of the upper layer side to the skeleton, and configuration requirements to have a.

本請求項2に記載の発明は、構築済みの躯体とその躯体に支持されている下層側の外壁パネルにプレキャストコンクリート製の上層側の外壁パネルを仮支持させながら、前記上層側の外壁パネルが一体化する鉄筋コンクリート造の躯体を構築する外壁パネルの施工方法において、前記鉄筋コンクリート造の躯体に支持されるための定着材が屋内側に突出した前記上層側の外壁パネルを、前記下層側の外壁パネルの上方にサポートを介して設置すると共に、前記下層側の外壁パネルと前記上層側の外壁パネルとの間に、その両外壁パネルを連結する仮設部材を前記両外壁パネルの屋内側の面に沿って架設し、前記サポートと構築済みの躯体との間、及び前記仮設部材と構築済みの躯体との間に控え材を架設し、このサポートと仮設部材及び控え材に前記上層側の外壁パネルを仮支持させる工程と、前記上層側の外壁パネルが一体化する鉄筋コンクリート造の躯体の中に前記上層側の外壁パネルの定着材が挿入される状態で、その鉄筋コンクリート造の躯体を構築し、その躯体に前記上層側の外壁パネルを支持させる工程と、を有することを構成要件とする。   The invention according to claim 2 is characterized in that the upper layer side outer wall panel is temporarily supported by the precast concrete upper layer side wall panel while the constructed case and the lower side outer wall panel supported by the case are temporarily supported. In the construction method of the outer wall panel for constructing the reinforced concrete frame to be integrated, the upper layer outer wall panel in which the fixing material to be supported by the reinforced concrete frame is projected indoors is used as the lower wall panel. And a temporary member for connecting the outer wall panels between the lower outer wall panel and the upper outer wall panel along the indoor side surface of the outer wall panels. A support material is installed between the support and the constructed housing, and between the temporary member and the constructed housing. Temporarily supporting the upper-layer outer wall panel, and in a state where the fixing member for the upper-layer outer wall panel is inserted into a reinforced concrete frame in which the upper-layer outer wall panel is integrated. And a step of supporting the outer wall panel on the upper layer side on the casing.

請求項1及び請求項2に記載の発明は、上層側の外壁パネルを下層側の外壁パネルと構築済みの躯体に仮支持させることで、上層側の外壁パネルをその下端部と中間部の2箇所で、2方向に躯体に仮支持させ、上層側の外壁パネルをサポート上に吊り込んだときの、あるいは吊り込んだときからの、外壁パネルの安定性を確保する。特に外壁パネルを2方向に仮支持させることで、外壁パネルを転倒や傾斜に対しても安定させる。   According to the first and second aspects of the present invention, the outer wall panel on the upper layer side is temporarily supported by the outer wall panel on the lower layer side and the built casing, so that the outer wall panel on the upper layer side has two lower end portions and an intermediate portion. At this point, the outer wall panel is temporarily supported in two directions to ensure the stability of the outer wall panel when the upper wall panel is hung on the support or after it is hung. In particular, by temporarily supporting the outer wall panel in two directions, the outer wall panel is stabilized against overturning and tilting.

サポート上に吊り込まれた上層側の外壁パネルの安定性を確保することで、吊り込み後の外壁パネルが下層側の外壁パネルと構築済みの躯体の2箇所で仮支持された時点で、上層側の外壁パネルからクレーンを切り離せる状態にし、外壁パネルによるクレーンの占有時間を低減する。   By securing the stability of the outer wall panel on the upper layer suspended on the support, the upper layer is temporarily supported when the outer wall panel after suspension is temporarily supported at the lower wall panel and the built frame. The crane can be separated from the outer wall panel on the side, and the occupation time of the crane by the outer wall panel is reduced.

また上層側の外壁パネルが支持される躯体が、プレキャストコンクリート製の外壁パネルとの剛性の差が問題にならない鉄筋コンクリート造であることで、外壁パネルが躯体に、その両者が一体的に挙動するように接合されれば、外壁パネルが躯体に対して相対変形できるように接合される必要がない。よって外壁パネルの躯体への接合を、その屋内側に突出している定着材をこれから構築すべき躯体中に挿入し、そのまま躯体を構築するのみで完了させるため、定着材に層間変位に追従できる機能を持たせる必要がない。   In addition, the frame that supports the outer wall panel on the upper layer side is a reinforced concrete structure in which the difference in rigidity from the outer wall panel made of precast concrete does not become a problem, so that the outer wall panel acts as a frame and both of them behave integrally. If it is joined, it is not necessary to join so that an outer wall panel can be deformed relatively with respect to a housing. Therefore, the fixing of the outer wall panel to the housing can be completed simply by inserting the fixing material protruding to the indoor side into the housing to be constructed and constructing the housing as it is. It is not necessary to have.

特に請求項1に記載の発明は、上層側の外壁パネルをサポートと控え材に仮支持させることで、上層側の外壁パネルの鉛直荷重をサポートに負担させ、水平荷重を控え材に負担させるため、外壁パネルに対しては、外壁パネルを安定させる上で、最も合理的な位置に控え材を連結すればよく、施工時の外壁パネルの安定性と施工精度を向上させ得る。   In particular, the invention according to claim 1 is to temporarily support the upper wall panel on the support and the retaining material, thereby causing the support to bear the vertical load of the outer wall panel on the upper layer and causing the bearing material to bear the horizontal load. In order to stabilize the outer wall panel, the outer wall panel only needs to be connected with a retaining material at the most rational position, and the stability and construction accuracy of the outer wall panel during construction can be improved.

特に請求項2に記載の発明は、仮設部材を両外壁パネルの屋内側の面に沿って架設することで、控え材を上下の外壁パネルに跨る仮設部材のいずれかの部分に連結すればよく、外壁パネルに直接連結する必要がないため、これから構築すべき躯体と控え材が干渉しないような位置を選んで控え材を架設することを可能にする。上層側の外壁パネルの鉛直荷重はサポートが負担し、水平荷重は仮設部材と控え材が負担する。上下の外壁パネルに跨る仮設部材は控え材と共に下層側の外壁パネルに対する上層側の外壁パネルの構面外方向の変位を拘束する。   In particular, the invention according to claim 2 may be configured such that the temporary member is constructed along the indoor side surfaces of both outer wall panels so that the retentive material is connected to any part of the temporary member straddling the upper and lower outer wall panels. Since it is not necessary to directly connect to the outer wall panel, it is possible to install the retaining material by selecting a position where the housing to be constructed and the retaining material do not interfere with each other. The vertical load on the outer wall panel on the upper layer is borne by the support, and the horizontal load is borne by the temporary member and the retentive material. The temporary member straddling the upper and lower outer wall panels restrains the displacement of the upper layer side outer wall panel with respect to the lower layer side outer wall panel together with the retentive material in the construction surface direction.

請求項3に記載の発明は、請求項1、もしくは請求項2に記載の発明において、上層側の外壁パネルが腰壁と垂壁に相当する壁部と、壁部から屋内側へ張り出す張出部を持ち、この上層側の外壁パネルを壁部と張出部においてサポートに仮支持させることを構成要件とする。   The invention according to claim 3 is the invention according to claim 1 or 2, wherein the outer wall panel on the upper layer side is a wall portion corresponding to the waist wall and the hanging wall, and the tension projecting from the wall portion to the indoor side. It has a projecting portion, and the upper layer side outer wall panel is temporarily supported by the support at the wall portion and the overhanging portion.

この場合、縦断面上、外壁パネルを壁部と張出部の2箇所でサポートに仮支持させることで、サポートからの反力を2点で取るため、張出部を持たない場合より鉛直荷重と水平荷重に対する外壁パネルの安定性を向上させる。   In this case, on the vertical cross section, the outer wall panel is temporarily supported by the support at two locations, the wall and the overhang, so that the reaction force from the support is taken at two points, so the vertical load is higher than when there is no overhang. And improve the stability of the outer wall panel against horizontal load.

請求項1、2に記載の発明によれば、上層側の外壁パネルをその下端部と中間部の2箇所で、2方向に躯体に仮支持させて設置直後の外壁パネルの安定性を確保するため、躯体に対しては1枚の外壁パネルにつき、上下2箇所で接合する必要がない。よって外壁パネルを中間部の1箇所で躯体に接合すれば足りるため、外壁パネルを躯体に支持させるための作業を簡略化することができる。   According to the first and second aspects of the invention, the outer wall panel on the upper layer side is temporarily supported by the housing in two directions at the lower end portion and the middle portion to ensure the stability of the outer wall panel immediately after installation. For this reason, it is not necessary to join the casing at two locations on the upper and lower sides for each outer wall panel. Therefore, since it is sufficient to join the outer wall panel to the housing at one place in the intermediate portion, the work for supporting the outer wall panel on the housing can be simplified.

上層側の外壁パネルの安定性が確保されることで、上層側の外壁パネルの吊り込み後、下層側の外壁パネルと構築済みの躯体の2箇所に仮支持させた時点で、クレーンを外壁パネルから切り離すことができるため、1枚の外壁パネルが同一のクレーンを占有する時間を低減でき、クレーンの稼動率の上昇により工期の短縮を図ることができる。   By securing the stability of the outer wall panel on the upper layer side, after the upper outer wall panel is suspended, the crane is mounted on the outer wall panel when temporarily supported on the lower wall panel and the built frame. Therefore, the time for one outer wall panel to occupy the same crane can be reduced, and the construction period can be shortened by increasing the operation rate of the crane.

また躯体が鉄筋コンクリート造であることで、プレキャストコンクリート製の外壁パネルを躯体に、両者が一体的に挙動するように接合すればよいため、躯体の層間変位を考慮する必要がなく、外壁パネルの躯体への接合を、その屋内側に突出した定着材をこれから構築すべき躯体中に挿入し、そのまま躯体を構築するのみで完了させることができる。   In addition, because the frame is reinforced concrete, it is only necessary to join the outer wall panel made of precast concrete to the frame so that they both move together, so there is no need to consider the interlayer displacement of the frame, and the frame of the outer wall panel. The fixing member protruding to the indoor side can be inserted into the housing to be constructed and the construction of the housing can be completed as it is.

定着材を構築すべき躯体中に埋設するのみで外壁パネルを躯体に支持させることができることで、定着材に層間変位に追従できる機能を持たせる必要がなく、定着材の構成と、それを埋設して製作される外壁パネルの構成が単純化されるため、定着材の製作コストと外壁パネルの製作コストを低減することができる。   Since the outer wall panel can be supported by the housing simply by embedding the fixing material in the housing to be constructed, it is not necessary to provide the fixing material with a function to follow the interlayer displacement, and the structure of the fixing material and the embedding thereof Since the structure of the outer wall panel manufactured in this way is simplified, the manufacturing cost of the fixing material and the manufacturing cost of the outer wall panel can be reduced.

また請求項1に記載の発明によれば、控え材を外壁パネルの任意の位置に連結することができるため、外壁パネルを安定させる上で、最も合理的な位置を選択することができ、外壁パネルの振動や揺れを抑えるように控え材を連結し、架設することができる。結果として外壁パネルを最も安定させた状態で躯体に接合することができるため、外壁パネルの躯体への接合上の施工精度を向上させることができる。   According to the first aspect of the present invention, since the retaining material can be connected to an arbitrary position of the outer wall panel, the most rational position can be selected for stabilizing the outer wall panel. Retaining materials can be connected and installed so as to suppress the vibration and shaking of the panel. As a result, since the outer wall panel can be joined to the housing in the most stable state, construction accuracy on joining the outer wall panel to the housing can be improved.

請求項2に記載の発明によれば、これから構築すべき躯体と控え材が干渉しない位置を選んで控え材を架設することができるため、スラブ等の躯体に駄目穴を形成することがなく、控え材の撤去後に駄目穴を塞ぐ工事を必要としない。   According to the invention described in claim 2, since it is possible to select the position where the housing to be constructed and the retaining material do not interfere with each other, it is possible to construct the retaining material without forming a useless hole in the housing such as a slab, No work is needed to close the useless holes after removing the materials.

請求項3に記載の発明によれば、縦断面上、サポートからの反力を2点で取るため、張出部を持たない場合より鉛直荷重と水平荷重に対する外壁パネルの安定性が向上すると共に、控え材の負担を軽減し、控え材を簡素化することができる。安定性の向上によりクレーンを早期に外壁パネルから切り離すことができるため、クレーンの稼働率が一層向上し、工期の大幅な短縮が図られる。   According to the invention described in claim 3, since the reaction force from the support is taken at two points on the longitudinal section, the stability of the outer wall panel with respect to the vertical load and the horizontal load is improved as compared with the case without the overhanging portion. , Can reduce the burden of the material, and can simplify the material. Since the crane can be separated from the outer wall panel at an early stage by improving the stability, the operation rate of the crane is further improved, and the construction period can be greatly shortened.

以下、本発明を実施するための最良の形態について図面を参照して説明する。図1は本発明の第1実施形態に係る外壁パネルの施工方法の要領を示した縦断面図、図4は第2実施形態に係る外壁パネルの施工方法の要領を示した縦断面図である。   The best mode for carrying out the present invention will be described below with reference to the drawings. FIG. 1 is a longitudinal sectional view showing the outline of the construction method of the outer wall panel according to the first embodiment of the present invention, and FIG. 4 is a longitudinal sectional view showing the outline of the construction method of the outer wall panel according to the second embodiment. .

本実施形態は構築済みの躯体とその躯体に支持されている下層側の外壁パネル1にプレキャストコンクリート製の上層側の外壁パネル2を支持させながら、この上層側の外壁パネル2が一体化する鉄筋コンクリート造の躯体を下層側から上層側へ向けて構築する外壁パネルの施工方法である。図面を含め、以下の説明では下層側の外壁パネル1もプレキャストコンクリートで製作した場合を示しているが、下層側の外壁パネル1は現場打ちコンクリートで構築されている場合もある。   In the present embodiment, the reinforced concrete in which the upper layer outer wall panel 2 is integrated while the upper layer outer wall panel 2 made of precast concrete is supported by the constructed outer frame and the lower layer outer wall panel 1 supported by the case. This is a construction method for an outer wall panel in which a built-in frame is constructed from the lower layer side toward the upper layer side. In the following description including drawings, the lower outer wall panel 1 is also made of precast concrete. However, the lower outer wall panel 1 may be constructed of cast-in-place concrete.

本実施形態で言う鉄筋コンクリート造は鉄骨鉄筋コンクリート造や鋼管コンクリート造を含み、躯体、すなわち柱6、梁7、スラブ8、壁のそれぞれにつき、全断面を現場打ちコンクリートで構築する場合と躯体の一部断面をプレキャスト化しておき、残りの断面を現場打ちコンクリートで構築する場合がある。   The reinforced concrete structure referred to in the present embodiment includes a steel reinforced concrete structure and a steel pipe concrete structure. For each of the frames, that is, the column 6, the beam 7, the slab 8, and the wall, the entire cross section is constructed with on-site cast concrete and a part of the frame. In some cases, the cross section is precast and the remaining cross section is constructed with cast-in-place concrete.

第1実施形態は図1に示すように先行して躯体に支持されている下層側の外壁パネル1の上方にサポート4を設置すると共に、このサポート4と構築済みの躯体との間、及び設置されたばかりの上層側の外壁パネル2と構築済みの躯体との間に控え材5を傾斜させて架設し、このサポート4と控え材5に、前記上層側の外壁パネル2を仮支持させる方法である。   In the first embodiment, as shown in FIG. 1, a support 4 is installed above the outer wall panel 1 on the lower layer side that is supported by the chassis in advance, and between the support 4 and the constructed chassis, and the installation. In the method in which the retaining material 5 is inclined between the newly constructed upper-layer outer wall panel 2 and the built frame, and the upper-layer outer wall panel 2 is temporarily supported by the support 4 and the retaining material 5. is there.

図面では施工時の安定性を図り、躯体への接合をし易くする上で、外壁パネル1、2を、連続する腰壁と垂壁に相当する壁部1a、2aと、躯体への支持のために壁部1a、2aから屋内側へ張り出し、躯体に接合される張出部1b、2bを持ってプレキャストコンクリートで製作している。   In the drawing, the outer wall panels 1 and 2 are provided with wall portions 1a and 2a corresponding to the continuous waist wall and the vertical wall, and the support to the housing in order to improve the stability during construction and facilitate the joining to the housing. For this purpose, it is made of precast concrete with projecting portions 1b and 2b that project from the walls 1a and 2a to the indoor side and are joined to the housing.

外壁パネル1、2が張出部1b、2bを持つ場合、張出部1b、2bからは躯体に支持されるための鉄筋、アンカー、定着プレートその他の、躯体に支持されるのに十分な数、または大きさの定着材3が突出し、外壁パネル1、2の設置時には壁部1a、2aと張出部1b、2bにおいて直下のサポート4に仮支持される。   When the outer wall panels 1 and 2 have the overhang portions 1b and 2b, the overhang portions 1b and 2b have a sufficient number of reinforcing bars, anchors, fixing plates, and the like to be supported by the housing from the overhang portions 1b and 2b. Alternatively, the fixing material 3 having a size protrudes and is temporarily supported by the support 4 directly below the wall portions 1a and 2a and the overhang portions 1b and 2b when the outer wall panels 1 and 2 are installed.

図面では定着材3として、一端側において外壁パネル1、2中に埋設されて定着され、多端側においてスラブ8等の躯体中に埋設されて定着される鉄筋を用いた場合を示している。定着材3は主としてスラブ8中の主筋と連結されることにより、または梁7やスラブ8のコンクリート中に定着されることにより外壁パネル1、2中の鉄筋とスラブ8等の躯体中の主筋を連続させる役目を持つ。図示するように張出部1b、2bがスラブ8に連続する位置に張り出す場合、定着材3は後述のように外壁パネル2がサポート4上に設置されたときに、梁7やスラブ8の上端筋部分とスラブ8の下端筋部分に位置するよう、上下複数段に配置され、梁7やスラブ8のコンクリートの打設によってコンクリート中に埋設される。   In the drawing, as the fixing material 3, a reinforcing bar embedded in the outer wall panels 1 and 2 at one end side and fixed and fixed and embedded in a housing such as a slab 8 at the multi-end side is shown. The fixing material 3 is mainly connected to the main reinforcing bar in the slab 8 or fixed in the concrete of the beam 7 or the slab 8 to fix the reinforcing bars in the outer wall panels 1 and 2 and the main reinforcing bars in the frame such as the slab 8. Have a role to be continuous. As shown in the figure, when the projecting portions 1b and 2b project to a position continuous with the slab 8, the fixing material 3 is formed on the beam 7 and the slab 8 when the outer wall panel 2 is installed on the support 4 as will be described later. It is arranged in a plurality of upper and lower stages so as to be positioned at the upper end bar part and the lower end bar part of the slab 8, and is embedded in the concrete by placing concrete of the beam 7 and the slab 8.

外壁パネル1、2が張出部1b、2bを有するT形の断面形状をした場合、サポート4は構面外方向に並列し、壁部1a、2aを支持する支柱4aと張出部1b、2bを支持する支柱4bを持ち、並列する両支柱4a、4bはアーム4cで互いに連結される。張出部1b、2bがない場合や、あっても壁部1a、2aからの突出長さが小さい場合には、サポート4は支柱4aのみで構成される。並列する支柱4a、4bを持つ場合、サポート4は単独で使用状態での安定性を有する。   When the outer wall panels 1 and 2 have a T-shaped cross section having the overhanging portions 1b and 2b, the support 4 is juxtaposed in the outward direction of the construction surface, and the support 4a and the overhanging portion 1b for supporting the wall portions 1a and 2a The support column 4b which supports 2b is provided, and both the support columns 4a and 4b arranged in parallel are connected to each other by an arm 4c. If there is no overhanging portion 1b, 2b, or if the protruding length from the wall portions 1a, 2a is small, the support 4 is composed only of the support column 4a. When the support columns 4a and 4b are arranged in parallel, the support 4 alone has stability in use.

控え材5には、吊り込まれた外壁パネル1、2の建て入れ調整をし、調整後の屋外側への転倒と屋内側への転倒を防止する機能を持たせるために、例えば一端にねじの切られた鋼管51や棒鋼の両ねじ部を突き合わせ、その両ねじ部をターンバックル52で連結した部材が使用される。控え材5は外壁パネル1、2の屋内側の面とスラブ8、または壁、柱6、梁7との間に架設される。   In order to provide the retaining material 5 with a function of adjusting the erection of the suspended outer wall panels 1 and 2 and preventing the fall to the outdoor side and the indoor side after the adjustment, for example, a screw at one end A member in which both the threaded portions of the cut steel pipe 51 and the steel bar are abutted and the both threaded portions are connected by a turnbuckle 52 is used. The retentive material 5 is laid between the indoor side surface of the outer wall panels 1 and 2 and the slab 8 or the wall, column 6 and beam 7.

控え材5は外壁パネル1、2の断面形状や、後述する張出部1b、2bの位置によっては図1、図2に示すようにそのレベルのスラブ8を貫通する場合があるが、控え材5を構成する鋼管51や棒鋼には大きな断面を要しないことから、貫通しても隣接するスラブ筋間の合間を縫って控え材5を設置し、スラブ筋との干渉を回避することはできるため、コンクリートの打設から、控え材5の回収までの間、控え材5が一時的にスラブ8に埋設されることによる影響は小さい。   Depending on the cross-sectional shape of the outer wall panels 1 and 2 and the positions of the overhang portions 1b and 2b, which will be described later, the retainer 5 may penetrate the slab 8 at that level as shown in FIGS. Since the steel pipe 51 and the steel bar constituting 5 do not require a large cross section, it is possible to avoid interference with the slab bars by installing the retentive material 5 by sewing between the adjacent slab bars even if they penetrate. For this reason, during the period from the placement of the concrete to the recovery of the retaining material 5, the effect of temporarily embedding the retaining material 5 in the slab 8 is small.

図1、図2では現場作業の省力化のために梁7の全断面の内、上端筋7aの配筋部分を除いた部分を予めプレキャストコンクリートで製作し、そのコンクリート中に下端筋とせん断補強筋7bを埋設した梁部材71を用いた場合を示しているが、下端筋の配筋部分とせん断補強筋7bの下端寄りの配筋部分のみをプレキャストコンクリートでU字形断面に製作する場合の他、型枠を組み立てて梁7の全断面を現場打ちコンクリートで構築する場合もある。   In FIG. 1 and FIG. 2, in order to save labor in the field work, the entire section of the beam 7 excluding the bar arrangement portion of the upper end reinforcement 7a is manufactured in advance with precast concrete, and the lower end reinforcement and the shear reinforcement are included in the concrete. Although the case where the beam member 71 in which the reinforcement 7b is embedded is used is shown, other than the case where only the reinforcement arrangement portion of the lower end reinforcement and the reinforcement arrangement portion near the lower end of the shear reinforcement reinforcement 7b are made into a U-shaped cross section with precast concrete. In some cases, the formwork is assembled and the entire cross section of the beam 7 is constructed of cast-in-place concrete.

図示するようにプレキャストコンクリートの梁部材71を用いる場合、梁部材71はその長さ方向両端に設置されているサポート間、または柱型枠11、11間に架設された後、上端筋7aが配筋され、スラブ8と一体にコンクリートが打設され、コンクリートが梁部材71内に充填されることによりスラブ8と一体となる。   As shown in the figure, when a precast concrete beam member 71 is used, the beam member 71 is installed between the supports installed at both ends in the length direction or between the column molds 11 and 11, and then the upper end reinforcement 7a is arranged. The concrete is cast integrally with the slab 8, and the concrete is filled into the beam member 71 so as to be integrated with the slab 8.

図1、図2ではまた、設置されたばかりの上層側の外壁パネル2のレベルに位置する躯体の梁7にプレキャストコンクリート製の梁部材71を用いたことの利点を生かし、梁部材71の、外壁パネル1、2が設置される側を破線で示すようにふかし、そのふかし部分の上に外壁パネル1、2の張出部1b、2bの先端部を載置している。この場合、縦断面上、外壁パネル1、2の張出部1b、2bがサポート4の支柱4bと梁7の2箇所で支持される形になるため、サポート4のみに支持される場合より外壁パネル1、2の設置精度が向上し、設置状態での安定性も高まる利点がある。   In FIG. 1 and FIG. 2, the outer wall of the beam member 71 is also obtained by taking advantage of the use of the beam member 71 made of precast concrete for the frame beam 7 positioned at the level of the outer wall panel 2 on the upper layer side just installed. The side where the panels 1 and 2 are installed is spread as indicated by broken lines, and the end portions of the overhanging portions 1b and 2b of the outer wall panels 1 and 2 are placed on the covered portion. In this case, on the longitudinal section, the projecting portions 1b and 2b of the outer wall panels 1 and 2 are supported at two locations of the support 4 column 4b and the beam 7, so that the outer wall is more than the case where only the support 4 is supported. There is an advantage that the installation accuracy of the panels 1 and 2 is improved and the stability in the installed state is increased.

ここで、第1実施形態の施工手順を図2−(a)〜(f)により説明する。図2−(a)は下層側の外壁パネル1がサポート4と控え材5に仮支持された状態で、構築済みの躯体、ここでは梁7に支持されているときの様子を示す。躯体がフラットスラブ構造の場合には外壁パネル1、2はスラブ8に支持される。   Here, the construction procedure of the first embodiment will be described with reference to FIGS. FIG. 2- (a) shows a state in which the outer wall panel 1 on the lower layer side is temporarily supported by the support 4 and the retaining member 5 and is supported by the built frame, here the beam 7. When the casing has a flat slab structure, the outer wall panels 1 and 2 are supported by the slab 8.

下層側の外壁パネル1の張出部1bが接続する梁7、またはスラブ8のコンクリートは外壁パネル1に連結されている控え材5が下階のスラブ8等の躯体との間に架設された状態で打設される。図2−(a)に示すように梁7、またはスラブ8のコンクリートが打設された時点では直下の階の柱6の主筋6aがスラブ8の天端から突出している。   As for the concrete of the beam 7 or the slab 8 to which the overhanging portion 1b of the outer wall panel 1 on the lower layer side is connected, the retaining material 5 connected to the outer wall panel 1 is installed between the lower slab 8 and the like. Placed in state. As shown in FIG. 2A, when the concrete of the beam 7 or the slab 8 is placed, the main bar 6 a of the column 6 on the floor immediately below protrudes from the top end of the slab 8.

図1、図2に示すように張出部1b、2bに関し、壁部1a、2aの腰壁部分の高さと垂壁部分の高さがほとんど等しい外壁パネル1、2を使用し、壁部1a、2aの腰壁部分に控え材5を連結した場合、控え材5は一時的にスラブ8を貫通する形になるが、前記のようにスラブ筋との干渉がないように控え材5を架設することは可能であるため、一時的に貫通することによる問題は生じない。控え材5の撤去後、控え材5が貫通していた穴はコンクリートやモルタルによって塞がれる。   As shown in FIGS. 1 and 2, for the overhanging portions 1b and 2b, the outer wall panels 1 and 2 are used in which the height of the waist wall portion of the walls 1a and 2a is almost equal to the height of the vertical wall portion. When the retaining material 5 is connected to the waist wall portion 2a, the retaining material 5 temporarily penetrates the slab 8, but the retaining material 5 is installed so as not to interfere with the slab muscle as described above. Because it is possible to do so, there is no problem with penetrating temporarily. After removal of the masking material 5, the hole through which the masking material 5 penetrates is closed with concrete or mortar.

下層側の梁7、またはスラブ8のコンクリートの打設後、図2−(b)に示すように下層側の外壁パネル1の上にサポート4を設置し、サポート4の上に上層側の外壁パネル2を設置すると共に、サポート4と設置したばかりの上層側の外壁パネル2に新たに控え材5の一端を連結し、外壁パネル2の安定性を確保する。控え材5の他端は下階のスラブ8等に連結されている。控え材5の両端は外壁パネル2の壁部2aの屋内側の面とスラブ8の天端面等に一時的に突設されたブラケット10等に連結される(図4参照)。図2−(b)〜(e)中、4dは施工中の部品の落下を防止する養生ネットを示す。   After placing the concrete of the beam 7 on the lower layer side or the slab 8, the support 4 is installed on the outer wall panel 1 on the lower layer side and the outer wall on the upper layer side is placed on the support 4 as shown in FIG. In addition to installing the panel 2, one end of the retentive material 5 is newly connected to the support 4 and the outer wall panel 2 on the upper layer side just installed to ensure the stability of the outer wall panel 2. The other end of the backing material 5 is connected to a slab 8 on the lower floor. Both ends of the retentive material 5 are connected to a bracket 10 or the like temporarily projecting from the indoor side surface of the wall portion 2a of the outer wall panel 2 and the top end surface of the slab 8 (see FIG. 4). 2- (b)-(e), 4d shows the curing net which prevents the fall of the components under construction.

図2−(b)に示すように設置されたばかりの上層側の外壁パネル2の鉛直荷重はサポート4で負担され、サポート4から下層側の外壁パネル1を介して構築済みの躯体に伝達される。水平荷重は外壁パネル2に連結される控え材5で負担され、控え材5を介して構築済みの躯体に伝達される。   The vertical load on the outer wall panel 2 on the upper layer side just installed as shown in FIG. 2- (b) is borne by the support 4, and is transmitted from the support 4 to the already constructed frame via the outer wall panel 1 on the lower layer side. . The horizontal load is borne by the retainer 5 connected to the outer wall panel 2 and is transmitted to the built frame via the retainer 5.

図2ではサポート4と外壁パネル2を転倒に対して安全に支持できるよう、支柱4aの上端部と外壁パネル2の上端部にそれぞれ控え材5を連結している。このように躯体への接合が完了するまでの外壁パネル2の安定性を高める上では、外壁パネル2に連結される控え材5を外壁パネル2の上端寄りに連結することが有利であるが、外壁パネル2が張出部2bを有する場合には、外壁パネル2の屋内側への転倒防止は張出部2bの下に位置する支柱4bによっても図られているため、控え材5は外壁パネル2の屋外側への転倒を防止できる状態にあればよく、必ずしも外壁パネル2の上端部に連結される必要はない。   In FIG. 2, the support members 5 are respectively connected to the upper end portion of the support column 4 a and the upper end portion of the outer wall panel 2 so that the support 4 and the outer wall panel 2 can be safely supported against falling. Thus, in order to improve the stability of the outer wall panel 2 until the joining to the housing is completed, it is advantageous to connect the retaining material 5 connected to the outer wall panel 2 closer to the upper end of the outer wall panel 2. In the case where the outer wall panel 2 has the overhanging portion 2b, the fall of the outer wall panel 2 to the indoor side is also prevented by the support 4b positioned below the overhanging portion 2b. It is only necessary to be able to prevent 2 from falling to the outdoor side, and it is not always necessary to be connected to the upper end portion of the outer wall panel 2.

サポート4及び外壁パネル2の設置、並びに控え材5の架設と並行し、下層側のスラブ8上では図2−(c)に示すように上階側の柱6を構築するための柱型枠11の組み立て、または予め主筋6a等が埋設されてプレキャストコンクリートで製作された柱部材の設置が行われる。図2−(b)では柱型枠11の組み立てや柱部材の設置前にサポート4及び外壁パネル2の設置、控え材5の架設をしているが、図2−(f)に示すように柱型枠11の組み立てや柱部材の設置後にサポート4及び外壁パネル2の設置、控え材5の架設を行うこともある。図2−(b)、(c)に示す柱型枠11は木製の他、薄肉のプレキャストコンクリートや鋼板等で製作され、捨て型枠となる場合もある。   In parallel with the installation of the support 4 and the outer wall panel 2 and the construction of the retentive material 5, the column formwork for constructing the column 6 on the upper floor side on the lower slab 8 as shown in FIG. 11 or a column member made of precast concrete with the main reinforcement 6a or the like embedded in advance is installed. In FIG. 2 (b), the support 4 and the outer wall panel 2 are installed and the retaining material 5 is installed before the assembly of the column mold 11 and the installation of the column member, but as shown in FIG. 2 (f). The support 4 and the outer wall panel 2 may be installed and the retentive material 5 may be installed after assembling the column mold 11 and installing the column member. The column form 11 shown in FIGS. 2B and 2C may be made of thin precast concrete, steel plate, or the like in addition to wood, and may be a discarded form.

スラブ8上での柱型枠11の組み立てや柱部材の設置後、図2−(d)に示すように隣接する柱型枠11、11間や柱部材間に前記プレキャストコンクリート製の梁部材71を架設する、もしくは梁型枠を組み立てる。柱型枠11、11間や柱部材間には必要に応じてサポート9が設置され、梁部材71や梁型枠は長さ方向の中間部においても仮支持される。このとき、外壁パネル2の定着材3は梁7の上端筋7a部分やスラブ8の上端筋部分とスラブ8の下端筋部分に位置する。梁部材71の架設や梁型枠の組み立て時に上層側の外壁パネル2に連結されている控え材5が障害になる場合には、その控え材5の架設に先立って柱型枠11の組み立てや柱部材の設置、並びに梁部材71の架設や梁型枠の組み立てが行われる。   After assembling the column mold 11 on the slab 8 and installing the column members, the precast concrete beam members 71 between the adjacent column molds 11 and 11 and between the column members as shown in FIG. Or assemble a beam formwork. A support 9 is installed between the column molds 11 and 11 or between the column members as needed, and the beam member 71 and the beam mold frame are temporarily supported also in an intermediate portion in the length direction. At this time, the fixing material 3 of the outer wall panel 2 is located at the upper end 7 a portion of the beam 7, the upper end portion of the slab 8, and the lower end portion of the slab 8. If the retaining member 5 connected to the outer wall panel 2 on the upper layer side becomes an obstacle during the construction of the beam member 71 or the assembly of the beam formwork, the assembly of the column formwork 11 is performed prior to the construction of the retaining member 5. Installation of the column member, construction of the beam member 71, and assembly of the beam formwork are performed.

梁部材71の架設後、梁部材71への上端筋7aの配筋と、床型枠12の敷設及びスラブ筋の配筋をし、図2−(e)に示すように梁部材71の上端部分とスラブ8のコンクリートを打設する。梁型枠を組み立てた場合はその組み立て後、下端筋と上端筋7a及びせん断補強筋7bの配筋、並びに床型枠12の敷設とスラブ筋の配筋をし、梁7全体とスラブ8のコンクリートが打設される。   After the beam member 71 is installed, the upper end bar 7a is arranged on the beam member 71, the floor frame 12 is laid and the slab bar is arranged, and the upper end of the beam member 71 is arranged as shown in FIG. Place the concrete of the part and slab 8. When the beam formwork is assembled, after the assembling, the lower end reinforcement, the upper end reinforcement 7a and the shear reinforcement reinforcement 7b are arranged, the floor formwork 12 is laid and the slab reinforcement is arranged, and the entire beam 7 and the slab 8 are arranged. Concrete is cast.

コンクリートの打設後、コンクリートが外壁パネル2を支持するのに必要な強度、例えば18N/mm2程度以上の強度を発現した後、サポート4と控え材5は回収され、順次上層階へ盛り替えられる。控え材5の回収後にはスラブ8中の控え材5が存在していた箇所に開口が形成されるが、その開口はコンクリートやモルタルを充填することにより埋められる。 After the concrete is placed, after the concrete has developed a strength necessary for supporting the outer wall panel 2, for example, a strength of about 18 N / mm 2 or more, the support 4 and the backing material 5 are collected and sequentially replaced to the upper floor. It is done. An opening is formed in the slab 8 where the retaining material 5 was present after the collection of the retaining material 5, but the opening is filled by filling with concrete or mortar.

以後、図2−(a)〜(e)の作業を繰り返すことにより鉄筋コンクリート造の躯体が下層側から上層側へ向けて構築される。   Thereafter, the reinforced concrete frame is constructed from the lower layer side to the upper layer side by repeating the operations shown in FIGS. 2- (a) to (e).

図3は梁部材71の長さ方向に隣接する2枚の外壁パネル2、2をつなぎプレート14によって連結した状態で施工する場合の外壁パネル2と梁部材71との関係を示す。この場合、2枚の外壁パネル2、2は施工中に高さ方向と構面外方向及び構面内方向に互いにずれない程度に連結されればよく、つなぎプレート14は壁部2a、2a間、もしくは張出部2b、2b間に跨って双方に接合される。施工後の隣接する外壁パネル2、2の端面間には地震時等に相対変位が生じ得ることから、つなぎプレート14は回収され、両外壁パネル2、2間の目地にシーリング材やモルタル等の充填材が充填される。   FIG. 3 shows the relationship between the outer wall panel 2 and the beam member 71 when construction is performed in a state where the two outer wall panels 2 and 2 adjacent to each other in the length direction of the beam member 71 are connected by the connecting plate 14. In this case, the two outer wall panels 2 and 2 may be connected to each other so that they do not deviate from each other in the height direction, the outer surface of the surface and the inner surface of the surface during construction. Or it is joined to both over the extended parts 2b and 2b. Since the relative displacement between the end faces of the adjacent outer wall panels 2 and 2 after construction can occur during an earthquake or the like, the connecting plate 14 is recovered, and a sealant, mortar, or the like is applied to the joint between the outer wall panels 2 and 2. Filler is filled.

続いて第2実施形態の方法を説明する。この方法は図4に示すように躯体に支持されている下層側の外壁パネル1の上方にサポート4を設置すると共に、その下層側の外壁パネル1と設置されたばかりの上層側の外壁パネル2との間に、両外壁パネル1、2を連結する仮設部材13を架設し、前記サポート4と構築済みの躯体との間、及び仮設部材13と構築済みの躯体との間に控え材5を架設し、このサポート4と仮設部材13及び控え材5に上層側の外壁パネル2を仮支持させる施工方法である。   Next, the method of the second embodiment will be described. In this method, as shown in FIG. 4, the support 4 is installed above the lower-side outer wall panel 1 supported by the housing, and the lower-side outer wall panel 1 and the upper-layer outer wall panel 2 just installed A temporary member 13 for linking the outer wall panels 1 and 2 is installed between the support 4 and the constructed housing, and a retaining material 5 is constructed between the temporary member 13 and the constructed housing. In this construction method, the upper wall panel 2 is temporarily supported by the support 4, the temporary member 13 and the holding member 5.

図4においても外壁パネル1、2を、連続する腰壁と垂壁に相当する壁部1a、2aと、躯体への支持のために壁部1a、2aから屋内側へ張り出す張出部1b、2bを持って製作し、壁部1a、2aと張出部1b、2bにおいて直下のサポート4に仮支持させている。張出部1b、2bからは躯体に支持されるための定着材3が突出する。   Also in FIG. 4, the outer wall panels 1 and 2 are wall portions 1a and 2a corresponding to continuous waist walls and hanging walls, and an overhanging portion 1b projecting from the wall portions 1a and 2a to the indoor side for supporting the housing. 2b, and temporarily supported by the support 4 directly below the wall portions 1a and 2a and the overhang portions 1b and 2b. A fixing material 3 to be supported by the housing protrudes from the overhang portions 1b and 2b.

図4ではまた、梁7の全断面の内、上端筋7aの配筋部分を除いた部分を予めプレキャストコンクリートで製作しているが、下端筋の配筋部分とせん断補強筋7bの下端寄りの配筋部分のみをプレキャストコンクリートで製作する場合の他、梁7の全断面を現場打ちコンクリートで構築する場合もある。また梁7にプレキャストコンクリート製の梁部材71を用いたことの利点を活かし、梁部材71にふかし部分を形成し、そのふかし部分の上に外壁パネル1、2の張出部1b、2bが載るようにしている。   In FIG. 4, the entire section of the beam 7 excluding the bar arrangement portion of the upper end bar 7a is made of precast concrete in advance, but the lower bar bar arrangement part and the lower end of the shear reinforcement bar 7b are close to each other. In addition to the case where only the reinforcing bar portion is made of precast concrete, the entire cross section of the beam 7 may be constructed of on-site cast concrete. Further, taking advantage of the use of the beam member 71 made of precast concrete for the beam 7, a bulge portion is formed on the beam member 71, and the overhanging portions 1b and 2b of the outer wall panels 1 and 2 are placed on the burial portion. I am doing so.

下層側の外壁パネル1の張出部1bが接続する梁7、またはスラブ8のコンクリートは外壁パネル1直下のサポート4に連結されている控え材5が下階のスラブ8等の躯体との間に架設された状態で打設される。   The beam 7 connected to the overhanging portion 1b of the outer wall panel 1 on the lower layer side, or the concrete of the slab 8 is between the support member 5 connected to the support 4 directly below the outer wall panel 1 and the frame such as the slab 8 on the lower floor. It is placed in a state where it is erected.

図5−(a)〜(e)により第2実施形態の施工手順を説明する。図5−(a)は下層側の外壁パネル1がサポート4に支持された状態で、構築済みの躯体である梁7に支持されているときの様子を示す。躯体がフラットスラブ構造の場合には外壁パネル1はスラブ8に支持される。第2実施形態では上下に隣接する外壁パネル1、2間に、両外壁パネル1、2を連結する仮設部材13を架設し、この仮設部材13のいずれかの部分に控え材5を連結するため、控え材5がスラブ8を貫通する必要はない。   The construction procedure of the second embodiment will be described with reference to FIGS. FIG. 5- (a) shows a state in which the outer wall panel 1 on the lower layer side is supported by the support 4 and is supported by the beam 7 which is a built frame. When the housing has a flat slab structure, the outer wall panel 1 is supported by the slab 8. In the second embodiment, a temporary member 13 that connects both the outer wall panels 1 and 2 is installed between the outer wall panels 1 and 2 adjacent to each other in the vertical direction, and the retaining material 5 is connected to any part of the temporary member 13. It is not necessary for the backing material 5 to penetrate the slab 8.

梁7、またはスラブ8のコンクリートの打設後、図5−(b)に示すように外壁パネル1の上にサポート4を設置し、サポート4の上に上層側の外壁パネル2を設置し、下層側の外壁パネル1と設置したばかりの上層側の外壁パネル2間に、H形鋼や溝形鋼、角形鋼管等の鋼材等からなる仮設部材13を架設して双方に仮接合する。仮設部材13は外壁パネル1、2の屋内側の面である壁部1a、2aに沿って配置され、例えば図4に示すように外壁パネル1、2の壁部1a、2aに、屋内側の面を向いて埋設されたナット15に仮設部材13を貫通するボルト16を螺入させることにより外壁パネル1、2に着脱自在に接合される。   After placing the concrete of the beam 7 or the slab 8, as shown in FIG. 5- (b), the support 4 is installed on the outer wall panel 1, the outer wall panel 2 on the upper layer side is installed on the support 4, Between the outer wall panel 1 on the lower layer side and the outer wall panel 2 on the upper layer side just installed, a temporary member 13 made of a steel material such as H-shaped steel, groove-shaped steel, square steel pipe or the like is erected and temporarily joined to both. The temporary members 13 are arranged along the wall portions 1a and 2a which are the indoor side surfaces of the outer wall panels 1 and 2, and for example, as shown in FIG. By screwing a bolt 16 penetrating the temporary member 13 into a nut 15 embedded facing the surface, the nut 15 is detachably joined to the outer wall panels 1 and 2.

仮設部材13の架設と並行してサポート4と仮設部材13のそれぞれに新たに控え材5を連結し、上層側の外壁パネル2の安定性を確保する。仮設部材13は上層側への盛り替えの便宜を図る上では鉛直に架設される。設置されたばかりの上層側の外壁パネル2の鉛直荷重はサポート4で負担され、サポート4から下層側の外壁パネル1を介して構築済みの躯体に伝達される。水平荷重はサポート4と仮設部材13、及びそれぞれに連結される控え材5を介して構築済みの躯体に伝達される。   In parallel with the construction of the temporary member 13, the support member 5 is newly connected to each of the support 4 and the temporary member 13 to secure the stability of the outer wall panel 2 on the upper layer side. The temporary member 13 is installed vertically for the convenience of rearrangement to the upper layer side. The vertical load of the outer wall panel 2 on the upper layer side that has just been installed is borne by the support 4, and is transmitted from the support 4 to the already constructed casing through the outer wall panel 1 on the lower layer side. The horizontal load is transmitted to the built frame through the support 4, the temporary member 13, and the holding member 5 connected to each.

図5では外壁パネル1、2に張出部1b、2bを形成したことに伴い、張出部1b、2bに仮設部材13が貫通する貫通孔1c、2cを形成し、外壁パネル1、2の転倒や傾斜を確実に防止するために、上層側の外壁パネル2の張出部2bを貫通させて仮設部材13を外壁パネル2の腰壁部分に接合しているが、腰壁の高さが垂壁の高さより小さい場合等には必ずしも張出部2bを貫通させる必要はない。仮設部材13は外壁パネル1、2の長さ方向(構面内方向)の大きさに応じ、外壁パネル1、2の長さ方向の中央部に1箇所、もしくは図6に示すように長さ方向両側の2箇所に配置される。   In FIG. 5, along with the formation of the overhanging portions 1 b and 2 b in the outer wall panels 1 and 2, through holes 1 c and 2 c through which the temporary members 13 pass are formed in the overhanging portions 1 b and 2 b. In order to prevent overturning and tilting, the temporary member 13 is joined to the waist wall portion of the outer wall panel 2 through the overhanging portion 2b of the outer wall panel 2 on the upper layer side. When it is smaller than the height of the vertical wall, it is not always necessary to penetrate the overhanging portion 2b. The temporary member 13 has one length at the center in the length direction of the outer wall panels 1 and 2 or the length as shown in FIG. 6 according to the size of the outer wall panels 1 and 2 in the length direction (in-plane direction). It is arranged at two places on both sides in the direction.

図4〜図6に示すように仮設部材13が外壁パネル1、2の張出部1b、2bを貫通する場合には、仮設部材13を上層側へ盛り替えるときに張出部1b、2bの貫通孔1c、2cに沿って仮設部材13を単純に上方へスライドさせるのみで盛り替えを完了させられる利点がある。この場合、貫通孔1c、2cはコンクリートやモルタルを充填することにより埋められる。外壁パネル1、2に貫通孔1c、2cを形成する場合でも、建物の最下層に設置される外壁パネルには貫通孔を形成する必要はない。   As shown in FIGS. 4 to 6, when the temporary member 13 passes through the overhang portions 1 b and 2 b of the outer wall panels 1 and 2, when the temporary member 13 is rearranged to the upper layer side, the overhang portions 1 b and 2 b There is an advantage that the reordering can be completed by simply sliding the temporary member 13 upward along the through holes 1c and 2c. In this case, the through holes 1c and 2c are filled by filling concrete or mortar. Even when the through-holes 1c and 2c are formed in the outer wall panels 1 and 2, it is not necessary to form a through-hole in the outer wall panel installed in the lowest layer of the building.

仮設部材13を用いた場合、外壁パネル2が屋内側、または屋外側に転倒しようとするときの水平力は仮設部材13が負担し、下層側の外壁パネル1と控え材5に分担されることから、控え材5はサポート4と仮設部材13のいずれかの部分に連結されればよいため、これから構築される躯体との干渉を回避しながら、控え材5を架設することができる。   When the temporary member 13 is used, the horizontal force when the outer wall panel 2 is about to fall to the indoor side or the outdoor side is borne by the temporary member 13 and is shared by the outer wall panel 1 and the retaining material 5 on the lower layer side. Therefore, the retaining material 5 only needs to be connected to any part of the support 4 and the temporary member 13, so that the retaining material 5 can be installed while avoiding interference with the casing to be constructed.

サポート4及び外壁パネル2の設置、並びに仮設部材13と控え材5の架設と並行し、下層側のスラブ8上では図5−(c)に示すように上階側の柱6を構築するための柱型枠11の組み立て、または予めプレキャストコンクリートで製作された柱部材の設置が行われる。図5−(b)では柱型枠11の組み立てや柱部材の設置前にサポート4及び外壁パネル2の設置、控え材5の架設をしているが、図2の場合と同様に柱型枠11の組み立てや柱部材の設置後にサポート4及び外壁パネル2の設置、控え材5の架設を行うこともある。図5−(b)、(c)に示す柱型枠11は木製の他、薄肉のプレキャストコンクリートや鋼板等で製作され、捨て型枠となる場合もある。   In parallel with the installation of the support 4 and the outer wall panel 2 and the installation of the temporary member 13 and the retaining member 5, on the lower slab 8, the upper floor side pillar 6 is constructed as shown in FIG. The column form 11 is assembled or a column member previously made of precast concrete is installed. In FIG. 5B, the support 4 and the outer wall panel 2 are installed and the retentive material 5 is installed before assembling the column mold 11 and installing the column members. After assembling 11 or installing the column member, the support 4 and the outer wall panel 2 may be installed, and the retentive material 5 may be installed. The column form 11 shown in FIGS. 5B and 5C is made of thin precast concrete, steel plate or the like in addition to wood, and may be a discarded form.

柱型枠11の組み立てや柱部材の設置後、図5−(d)に示すように柱型枠11、11間や柱部材間に前記プレキャストコンクリート製の梁部材71を架設する、もしくは梁型枠を組み立てる。柱型枠11、11間や柱部材間には必要に応じてサポート9が設置され、梁部材71や梁型枠は長さ方向の中間部においても支持される。このとき、外壁パネル2の定着材3は梁7やスラブ8の上端筋部分とスラブ8の下端筋部分に位置する。   After assembling the column mold 11 and installing the column members, the precast concrete beam members 71 are installed between the column mold frames 11 and 11 or between the column members as shown in FIG. Assemble the frame. A support 9 is installed between the column molds 11 and 11 or between the column members as necessary, and the beam member 71 and the beam mold frame are also supported in the middle portion in the length direction. At this time, the fixing material 3 of the outer wall panel 2 is positioned at the upper end of the beam 7 or the slab 8 and the lower end of the slab 8.

梁部材71の架設後、梁部材71への上端筋7aの配筋とスラブ筋の配筋をし、図5−(e)に示すように梁部材71の上端部分とスラブ8のコンクリートを打設する。梁型枠を組み立てた場合はその組み立て後、下端筋と上端筋7a及びせん断補強筋7bの配筋、並びにスラブ筋の配筋をし、梁部材71の上端部分とスラブ8のコンクリートが打設される。   After the beam member 71 is installed, the upper end 7a and the slab bar are arranged on the beam member 71, and the upper end portion of the beam member 71 and the concrete of the slab 8 are applied as shown in FIG. Set up. When the beam form frame is assembled, the lower end bar, upper end bar 7a and shear reinforcement bar 7b, and the slab bar are arranged, and the upper end portion of the beam member 71 and the concrete of the slab 8 are placed. Is done.

コンクリートの打設後、コンクリートが外壁パネル2を支持するのに必要な強度を発現した後、サポート4と控え材5は回収され、順次上層側へ盛り替えられる。   After the concrete is placed, after the concrete has developed a strength necessary to support the outer wall panel 2, the support 4 and the holding member 5 are collected and sequentially replaced to the upper layer side.

以後、図5−(a)〜(e)の作業を繰り返すことにより鉄筋コンクリート造の躯体が下層側から上層側へ向けて構築される。   Thereafter, the reinforced concrete frame is constructed from the lower layer side to the upper layer side by repeating the operations of FIGS.

図6は図3と同様に梁部材71の長さ方向に隣接する2枚の外壁パネル2、2をつなぎプレート14によって連結した状態で施工する場合の外壁パネル2と梁部材71との関係を示す。この場合も2枚の外壁パネル2、2は施工中に高さ方向と構面外方向及び構面内方向に互いにずれない程度に連結されればよく、つなぎプレート14は壁部2a、2a間、もしくは張出部2b、2b間に跨って双方に接合される。施工後、つなぎプレート14は回収され、両外壁パネル2、2間の目地にシーリング材等の充填材が充填される。   FIG. 6 shows the relationship between the outer wall panel 2 and the beam member 71 when the two outer wall panels 2 and 2 adjacent to each other in the length direction of the beam member 71 are connected by the connecting plate 14 in the same manner as FIG. Show. In this case as well, the two outer wall panels 2 and 2 need only be connected to each other so that they do not deviate from each other in the height direction, the outer surface of the surface and the inner surface of the surface during construction. Or it is joined to both over the extended parts 2b and 2b. After the construction, the connecting plate 14 is recovered, and the joint between the outer wall panels 2 and 2 is filled with a filler such as a sealing material.

以上、本発明の実施形態について説明したが、本発明はこの実施形態に限定されることはなく、趣旨を逸脱しない範囲で変更して実施可能である。   As mentioned above, although embodiment of this invention was described, this invention is not limited to this embodiment, It can change and implement in the range which does not deviate from the meaning.

本発明の第1実施形態に係る外壁パネルの施工要領を示した縦断面図である。It is the longitudinal cross-sectional view which showed the construction point of the outer wall panel which concerns on 1st Embodiment of this invention. (a)〜(f)は図1に示す施工方法の施工手順を示した縦断面図である。(A)-(f) is the longitudinal cross-sectional view which showed the construction procedure of the construction method shown in FIG. 図1に示す外壁パネルを梁部材の長さ方向に2枚連結して施工したときの様子を示した斜視図である。It is the perspective view which showed the mode when two outer wall panels shown in FIG. 1 were connected and constructed in the length direction of a beam member. 本発明の第2実施形態に係る外壁パネルの施工要領を示した縦断面図である。It is the longitudinal cross-sectional view which showed the construction point of the outer wall panel which concerns on 2nd Embodiment of this invention. (a)〜(e)は図3に示す施工方法の施工手順を示した縦断面図である。(A)-(e) is the longitudinal cross-sectional view which showed the construction procedure of the construction method shown in FIG. 図4に示す外壁パネルを梁部材の長さ方向に2枚連結して施工したときの様子を示した斜視図である。It is the perspective view which showed the mode when two outer wall panels shown in FIG. 4 were connected and constructed in the length direction of a beam member.

符号の説明Explanation of symbols

1 下層側の外壁パネル
2 上層側の外壁パネル
2a 壁部
2b 張出部
2c 貫通孔
3 定着材
4 サポート
5 控え材
7 梁
71 梁部材
13 仮設部材
DESCRIPTION OF SYMBOLS 1 Outer wall panel of lower layer side 2 Outer wall panel of upper layer side 2a Wall part 2b Overhang | projection part 2c Through-hole 3 Fixing material 4 Support 5 Retaining material 7 Beam 71 Beam member 13 Temporary member

Claims (3)

構築済みの躯体とその躯体に支持されている下層側の外壁パネルにプレキャストコンクリート製の上層側の外壁パネルを仮支持させながら、前記上層側の外壁パネルが一体化する鉄筋コンクリート造の躯体を構築する外壁パネルの施工方法であって、
前記鉄筋コンクリート造の躯体に支持されるための定着材が屋内側に突出した前記上層側の外壁パネルを、前記下層側の外壁パネルの上方にサポートを介して設置すると共に、このサポートと前記構築済みの躯体との間、及び前記上層側の外壁パネルと前記構築済みの躯体との間に控え材を架設し、このサポートと控え材に前記上層側の外壁パネルを仮支持させる工程と、
前記上層側の外壁パネルが一体化する鉄筋コンクリート造の躯体の中に前記上層側の外壁パネルの定着材が挿入される状態で、その鉄筋コンクリート造の躯体を構築し、その躯体に前記上層側の外壁パネルを支持させる工程と、を有することを特徴とする外壁パネルの施工方法。
Build the reinforced concrete frame that integrates the upper layer outer wall panel while temporarily supporting the upper layer outer wall panel made of precast concrete to the built lower frame and the lower layer outer wall panel supported by the frame. A construction method of an outer wall panel,
The upper layer outer wall panel in which the fixing material to be supported by the reinforced concrete frame is projected to the indoor side is installed via a support above the outer wall panel on the lower layer side. A support member is erected between the housing and between the outer layer panel on the upper layer side and the constructed casing, and the outer wall panel on the upper layer side is temporarily supported by the support member and the retainer;
The reinforced concrete frame is constructed in a state where the fixing member for the upper layer outer wall panel is inserted into the reinforced concrete frame integrated with the upper layer outer wall panel, and the upper layer outer wall is formed in the frame. A method for constructing an outer wall panel, comprising the step of supporting the panel.
構築済みの躯体とその躯体に支持されている下層側の外壁パネルにプレキャストコンクリート製の上層側の外壁パネルを仮支持させながら、前記上層側の外壁パネルが一体化する鉄筋コンクリート造の躯体を構築する外壁パネルの施工方法であって、
前記鉄筋コンクリート造の躯体に支持されるための定着材が屋内側に突出した前記上層側の外壁パネルを、前記下層側の外壁パネルの上方にサポートを介して設置すると共に、前記下層側の外壁パネルと前記上層側の外壁パネルとの間に、その両外壁パネルを連結する仮設部材を前記両外壁パネルの屋内側の面に沿って架設し、前記サポートと構築済みの躯体との間、及び前記仮設部材と構築済みの躯体との間に控え材を架設し、このサポートと仮設部材及び控え材に前記上層側の外壁パネルを仮支持させる工程と、
前記上層側の外壁パネルが一体化する鉄筋コンクリート造の躯体の中に前記上層側の外壁パネルの定着材が挿入される状態で、その鉄筋コンクリート造の躯体を構築し、その躯体に前記上層側の外壁パネルを支持させる工程と、を有することを特徴とする外壁パネルの施工方法。
Build the reinforced concrete frame that integrates the upper layer outer wall panel while temporarily supporting the upper layer outer wall panel made of precast concrete to the built lower frame and the lower layer outer wall panel supported by the frame. A construction method of an outer wall panel,
The upper layer outer wall panel in which the fixing material to be supported by the reinforced concrete frame is projected to the indoor side is installed above the lower layer outer wall panel via a support, and the lower layer outer wall panel And a temporary member connecting the two outer wall panels between the outer wall panel and the upper layer side wall panel along the indoor side surface of the two outer wall panels, A step of laying a retaining material between the temporary member and the constructed housing, and temporarily supporting the outer wall panel on the upper layer side to the support and the temporary member and the retaining material;
The reinforced concrete frame is constructed in a state where the fixing member for the upper layer outer wall panel is inserted into the reinforced concrete frame integrated with the upper layer outer wall panel, and the upper layer outer wall is formed in the frame. A method for constructing an outer wall panel, comprising the step of supporting the panel.
前記上層側の外壁パネルは腰壁と垂壁に相当する壁部と、壁部から屋内側へ張り出す張出部を持ち、この上層側の外壁パネルを前記壁部と張出部において前記サポートに仮支持させることを特徴とする請求項1、もしくは請求項2記載の外壁パネルの施工方法。   The outer wall panel on the upper layer side has a wall portion corresponding to a waist wall and a hanging wall, and an overhang portion projecting from the wall portion to the indoor side. The upper wall panel is supported on the wall portion and the overhang portion by the support. The construction method of the outer wall panel according to claim 1, wherein the outer wall panel is temporarily supported by the outer wall panel.
JP2004300989A 2004-10-15 2004-10-15 Exterior wall panel construction method Active JP4436226B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2004300989A JP4436226B2 (en) 2004-10-15 2004-10-15 Exterior wall panel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2004300989A JP4436226B2 (en) 2004-10-15 2004-10-15 Exterior wall panel construction method

Publications (2)

Publication Number Publication Date
JP2006112131A JP2006112131A (en) 2006-04-27
JP4436226B2 true JP4436226B2 (en) 2010-03-24

Family

ID=36380881

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2004300989A Active JP4436226B2 (en) 2004-10-15 2004-10-15 Exterior wall panel construction method

Country Status (1)

Country Link
JP (1) JP4436226B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5259490B2 (en) * 2009-05-20 2013-08-07 株式会社竹中工務店 How to build a double skin curtain wall
JP5538169B2 (en) * 2010-09-30 2014-07-02 大和ハウス工業株式会社 Balcony unit, method for assembling balcony unit, jig, and method for hanging building unit
JP6317185B2 (en) * 2014-06-06 2018-04-25 大和ハウス工業株式会社 Upper panel fall prevention jig and wall construction method using the same
CN108951937A (en) * 2017-05-22 2018-12-07 北新集团建材股份有限公司 A kind of assembled wall origination end and installation method

Also Published As

Publication number Publication date
JP2006112131A (en) 2006-04-27

Similar Documents

Publication Publication Date Title
KR101107567B1 (en) For top down methode of rc structure, the connecting devices between beam structure and vertical steel material, the supporting structures of exclusive use, and the construction method using these devices
KR102312319B1 (en) Magnetic assembly type mold panel
JP6166560B2 (en) Extension structure of seismic isolation building
JP3799036B2 (en) Building basic structure and construction method
JP3690437B2 (en) Seismic reinforcement structure for existing buildings
JP4436226B2 (en) Exterior wall panel construction method
JP4472726B2 (en) Base-isolated building structure
KR100605560B1 (en) Assembling structure of tunnel lining using anchor pipe
JP2986751B2 (en) Seismic performance enhancement method for buildings and seismic blocks
JP4980782B2 (en) Seismic isolation mechanism for intermediate floors of buildings
KR101665626B1 (en) the construction method of the hybrid steel joint construction
JP3725818B2 (en) How to install seismic isolation devices on existing pillars
JP3991876B2 (en) Seismic reinforcement structure
JP4571904B2 (en) Seismic reinforcement method using concrete blocks
JP6849491B2 (en) Exposed column base structure of steel columns and its construction method
JP6300228B2 (en) Flat slab structure
KR102372473B1 (en) Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket
KR101766805B1 (en) the hybrid joint construction between column plate and column
JP4432581B2 (en) Building structure that can change floor height
JP4520830B2 (en) Exterior wall panel construction method and exterior wall panel mounting structure
JP2000129668A (en) Soil-cement composite wall and execution method thereof
JP2001193290A (en) Seismic isolation method for existing building
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JP4145733B2 (en) Exterior wall construction method
KR101675022B1 (en) the hybrid joint construction between column and beam, the hybrid joint construction between girder and beam

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070518

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090324

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20091006

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20091113

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20091215

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091225

R150 Certificate of patent or registration of utility model

Ref document number: 4436226

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130108

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160108

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250