KR102372473B1 - Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket - Google Patents

Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket Download PDF

Info

Publication number
KR102372473B1
KR102372473B1 KR1020210041188A KR20210041188A KR102372473B1 KR 102372473 B1 KR102372473 B1 KR 102372473B1 KR 1020210041188 A KR1020210041188 A KR 1020210041188A KR 20210041188 A KR20210041188 A KR 20210041188A KR 102372473 B1 KR102372473 B1 KR 102372473B1
Authority
KR
South Korea
Prior art keywords
column
girder
temporary
temporary bracket
vertical
Prior art date
Application number
KR1020210041188A
Other languages
Korean (ko)
Inventor
정성대
민현식
황성윤
Original Assignee
정성대
민현식
황성윤
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 정성대, 민현식, 황성윤 filed Critical 정성대
Priority to KR1020210041188A priority Critical patent/KR102372473B1/en
Application granted granted Critical
Publication of KR102372473B1 publication Critical patent/KR102372473B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • E04B1/215Connections specially adapted therefor comprising metallic plates or parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/58Connections for building structures in general of bar-shaped building elements

Abstract

본 발명은 PC기둥과 PC거더의 접합부 시공에서 가설브라켓을 활용하는 한편, PC거더를 가설브라켓과 PC기둥에 동시에 거치하고 접합부를 현장콘크리트 타설로 일체화 시공하는 시공기술에 관한 것이다.
본 발명에 따른 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공구조는, PC거더와의 접합 위치에서 콘크리트가 채워지지 아니하여 콘크리트 상단면이 노출 형성된 PC기둥; 수직슬로트홀에 의한 볼트구멍이 형성된 수직부와 수평부로 구분되는 ㄱ자형 부재로, 수직부가 PC기둥의 측면에 맞대어지고 수평부가 PC기둥의 콘크리트 상단면과 일치하게 설치되어 수직부의 수직슬로트홀에 의한 볼트구멍을 통해 볼트접합으로 PC기둥에 고정되는 가설브라켓; 가설브라켓의 수평부와 PC기둥의 콘크리트 상부면 위에 거치되게 설치되는 PC거더;를 포함하여 구성되며, 특히 가설브라켓은 수직부의 외표면이 삼각톱니 요철로 형성되어, 수직부의 삼각톱니 요철과 동일하게 삼각톱니 요철로 표면처리된 톱니와셔가 가설브라켓 수직부에 맞물리게 설치되면서 볼트접합되는 것을 특징으로 한다. 여기서 톱니와셔를 생략하는 대신에, 가설브라켓과 PC거더 사이에 가설받침철골과 한쌍의 경사플레이트에 의한 베이스플레이트를 더 설치하는 구조로 완성할 수 있다.
The present invention relates to a construction technique that utilizes a temporary bracket in the joint construction of a PC column and a PC girder, while simultaneously mounting the PC girder on the temporary bracket and the PC column, and integrating the joint with on-site concrete pouring.
The joint construction structure of a PC column and a PC girder using a temporary bracket according to the present invention includes: a PC column in which concrete is not filled at the joint position with the PC girder, so that the upper surface of the concrete is exposed; It is a L-shaped member that is divided into a vertical part and a horizontal part in which a bolt hole is formed by a vertical slot hole. Temporary bracket fixed to the PC column by bolting through the bolt hole; The horizontal part of the temporary bracket and the PC girder installed to be mounted on the concrete upper surface of the PC column; in particular, the temporary bracket is composed of, in particular, the outer surface of the vertical part is formed with triangular serrations, so that it is identical to the triangular serrations of the vertical part. It is characterized in that the toothed washer surface-treated with triangular tooth irregularities is bolted while being installed to engage the vertical part of the temporary bracket. Here, instead of omitting the toothed washer, it can be completed with a structure in which a base plate is further installed between the temporary bracket and the PC girder by a temporary support steel frame and a pair of inclined plates.

Description

가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공구조 및 시공방법{Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket} Construction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket

본 발명은 PC기둥과 PC거더의 접합부 시공에서 PC기둥에 일체형 브라켓을 돌출 형성시키지 않고 쉽게 설치 및 해체가 가능한 가설브라켓을 활용하는 한편, PC거더를 가설브라켓과 PC기둥에 동시에 거치하고 접합부를 현장콘크리트 타설로 일체화 시공하는 시공기술에 관한 것이다.The present invention utilizes a temporary bracket that can be easily installed and dismantled without protruding an integral bracket on the PC column in the construction of the joint between the PC column and the PC girder. It is related to the construction technology for integrated construction by pouring concrete.

철근콘크리트 구조는 구조물의 뼈대가 되는 주요구조부를 철근과 콘크리트로 구성한 구조로, 건축구조로 가장 널리 쓰인다. 철근콘크리트 구조는 현장에서 거푸집 내부에 콘크리트를 타설하는 현장타설공법이 일반적이나, 최근에는 공장제작된 부재를 현장에서 조립식으로 설치하는 PC공법이 주목받고 있다. Reinforced concrete structure is a structure composed of reinforcing bars and concrete, which is the main structural part of the structure, and is most widely used as a building structure. In the case of reinforced concrete structures, the on-site casting method of pouring concrete inside the formwork at the site is common, but recently, the PC method of installing factory-fabricated members in a prefabricated manner at the site is attracting attention.

PC공법은 공장제작된 부재를 현장에서 조립하는 것이므로, 부재 간 접합부 처리가 중요하다. 도 1은 종래 PC거더와 PC보의 접합부에 대한 다양한 시공사진을 보여준다. 보는 바와 같이 종래에는 주로 PC기둥 상부면에 PC거더를 거치하고 PC기둥과 PC거더 사이 공간에 현장 콘크리트를 타설하여 PC기둥과 PC거더를 일체화하는 방법으로 접합부를 시공하였다. 이때 PC기둥은 상부에 브라켓이 일체형으로 형성되도록 제작되며, PC기둥의 브라켓에는 PC거더가 거치된다. 그런데 PC기둥은 브라켓이 일체형으로 돌출 형성에 따라 제작비가 상승하고 운반시에는 돌출된 브라켓에 의해 적재량이 감소하여 운송비가 증가하는 단점이 있으며, 또한 일체형 브라켓의 레벨 조정 어려워 시공오차에 유연하게 대응하지 못하거나 일체형 브라켓에 하중 집중이 일어나 브라켓의 전단파괴의 우려가 있었다.Since the PC method is to assemble factory-made members on site, it is important to treat the joints between members. 1 shows various construction photos for the joint of the conventional PC girder and PC beam. As can be seen, in the prior art, the joint was constructed by integrating the PC column and the PC girder by mounting the PC girder on the upper surface of the PC column and pouring on-site concrete in the space between the PC column and the PC girder. At this time, the PC column is manufactured so that the bracket is integrally formed on the upper part, and the PC girder is mounted on the bracket of the PC column. However, PC poles have disadvantages in that the production cost increases as the brackets are integrally formed, and the transportation cost increases due to the reduction in the loading by the protruding brackets during transportation. There was a risk of shear failure of the bracket due to failure or concentration of loads on the integral bracket.

한편 특허공개 제10-2017-0027233호와 같은 강접합 PC공법이 있다. 특허공개 제10-2017-0027233호의 강접합 PC공법은 일체형 브라켓 대신에 가설브라켓을 활용하는 공법으로, 가설브라켓에 PC보를 거치하여 시공하고 보철근을 커플러 연결하면서 강접합하는 공법이다. 그런데 이 공법은 접합부가 현장콘크리트 시공없이 철근의 기계적 연결에만 의존하기 때문에 가설브라켓 해체시 접합부의 안정성에서 우려가 있었다.On the other hand, there is a strong bonding PC method such as Patent Publication No. 10-2017-0027233. The strong bonding PC method of Patent Publication No. 10-2017-0027233 uses a temporary bracket instead of an integrated bracket. However, this method had concerns about the stability of the joint when dismantling the temporary bracket because the joint only relied on the mechanical connection of rebar without on-site concrete construction.

KR 10-2017-0027233 AKR 10-2017-0027233 A

본 발명은 PC기둥과 PC거더의 접합부 시공에서 일체형 브라켓 대신에 가설브라켓을 활용하면서도 접합부의 안정성을 확보할 수 있는 새로운 시공구조를 제공하는데 기술적 과제가 있다.The present invention has a technical problem in providing a new construction structure that can secure the stability of the joint while using a temporary bracket instead of an integral bracket in the joint construction of a PC column and a PC girder.

또한 본 발명은 하중재하상태에서 가설자재의 해체가 용이하고 PC기둥과 PC거더의 접합부 시공기술을 제공하고자 한다.In addition, the present invention is intended to provide a technology for easy dismantling of temporary materials in a load-bearing state, and to provide a joint construction technology between a PC column and a PC girder.

본 발명은 PC거더가 거치되는 가설자재의 레벨 조정이 가능하여 시공오차를흡수하고 시공품질을 향상시킬 수 있는 PC기둥과 PC거더의 접합부 시공기술을 제공하고자 한다.An object of the present invention is to provide a joint construction technology of a PC column and a PC girder that can adjust the level of the temporary material on which the PC girder is mounted, thereby absorbing construction errors and improving the construction quality.

상기한 기술적 과제를 해결하기 위해 본 발명은 PC기둥과 PC거더의 접합부 시공에서, PC거더와의 접합 위치에서 콘크리트가 채워지지 아니하여 콘크리트 상단면이 노출 형성된 PC기둥; 수직슬로트홀에 의한 볼트구멍이 형성된 수직부와 수평부로 구분되는 ㄱ자형 부재로, 수직부가 PC기둥의 측면에 맞대어지고 수평부가 PC기둥의 콘크리트 상단면과 일치하게 설치되어 수직부의 수직슬로트홀에 의한 볼트구멍을 통해 볼트접합으로 PC기둥에 고정되는 가설브라켓; 가설브라켓의 수평부와 PC기둥의 콘크리트 상부면 위에 거치되게 설치되는 PC거더;를 포함하여 구성되며, 특히 가설브라켓은 수직부의 외표면이 삼각톱니 요철로 형성되어, 수직부의 삼각톱니 요철과 동일하게 삼각톱니 요철로 표면처리된 톱니와셔가 가설브라켓 수직부에 맞물리게 설치되면서 볼트접합되는 것을 특징으로 하는 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공구조를 제공한다. 여기서 톱니와셔를 생략하는 대신에, 가설브라켓과 PC거더 사이에 가설받침철골과 한쌍의 경사플레이트에 의한 베이스플레이트를 더 설치하는 구조로 완성할 수 있다.In order to solve the above technical problem, the present invention is a PC column in which the concrete top surface is exposed because the concrete is not filled at the joint position with the PC girder in the joint construction of the PC column and the PC girder; It is a L-shaped member that is divided into a vertical part and a horizontal part in which a bolt hole is formed by a vertical slot hole. Temporary bracket fixed to the PC column by bolting through the bolt hole; The horizontal part of the temporary bracket and the PC girder installed to be mounted on the concrete upper surface of the PC column; in particular, the temporary bracket is composed of, in particular, the outer surface of the vertical part is formed with triangular serrations, so that it is identical to the triangular serrations of the vertical part. It provides a joint construction structure of a PC column and a PC girder using a temporary bracket, characterized in that the toothed washer surface-treated with triangular toothed irregularities is bolted to the vertical part of the temporary bracket while being engaged. Here, instead of omitting the toothed washer, it can be completed with a structure in which a base plate is further installed between the temporary bracket and the PC girder by a temporary support steel frame and a pair of inclined plates.

또한 본 발명은 PC기둥과 PC거더의 접합부를 시공하는 방법으로, PC기둥을 기둥위치에 시공하는 기둥시공단계; 수직부를 PC기둥의 측면에 맞대면서 수평부를 PC기둥의 콘크리트 상단면과 일치하게 설치하고 수직부의 수직슬로트홀에 의한 볼트구멍을 통해 볼트접합하여 가설브라켓을 PC기둥에 밀착 고정하는 가설브라켓설치단계; 가설브라켓의 수평부와 PC기둥의 콘크리트 상단면 위에 PC거더를 거치하여 설치하는 거더시공단계; PC기둥과 PC거더 접합부에 현장콘크리트를 타설하는 콘크리트타설단계; 가설브라켓의 볼트접합을 해제하여 가설브라켓을 PC거더 아래로 하강 탈락시키고 톱니와셔와 가설브라켓을 해체하는 가설해체단계;를 포함하여 이루어지는 것을 특징으로 하는 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공방법을 제공한다. 여기서 톱니와셔를 생략하는 대신에 가설받침철골과 한쌍의 경사플레이트에 의한 베이스플레이트를 더 설치하는 경우에는, 가설브라켓설치단계와 거더시공단계 사이에 베이스플레이트와 가설받침철골을 설치하는 가설받침철골설치단계를 더 실시하고, 거더시공단계에서 PC거더는 가설철골받침 위로 거치하면서 실시할 수 있다.In addition, the present invention is a method of constructing a junction between a PC column and a PC girder, comprising: a column construction step of constructing a PC column at a column position; A temporary bracket installation step of fitting the vertical part to the side of the PC column while installing the horizontal part to match the top surface of the concrete of the PC column, and bolting the vertical part through the bolt hole by the vertical slot hole to fix the temporary bracket to the PC column; A girder construction step of mounting and installing a PC girder on the horizontal part of the temporary bracket and the concrete upper surface of the PC column; Concrete pouring step of pouring on-site concrete to the junction of PC column and PC girder; A temporary dismantling step of releasing the bolt connection of the temporary bracket to lower the temporary bracket below the PC girder and dismantling the tooth washer and the temporary bracket; provide a way In the case of further installing a base plate with a temporary support steel frame and a pair of inclined plates instead of omitting the tooth washer, a temporary support steel frame installation that installs the base plate and the temporary support steel frame between the temporary bracket installation step and the girder construction step Steps are further carried out, and in the girder construction stage, the PC girder can be carried out while being mounted on the temporary steel frame support.

본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention, the following effects can be expected.

첫째, PC기둥과 PC거더의 접합부 시공에서 일체형 브라켓 대신에 가설브라켓을 활용하면서 현장콘크리트를 타설하여 시공하기 때문에, 일체형 브라켓에 의한 단점(PC기둥 제작비 증가, 적재량 감소에 의한 운송비 증가)을 해소하고 접합부의 안정성을 확보할 수 있다. 나아가 접합부 완성 후에는 가설브라켓을 해체하고 해체한 가설브라켓을 다른 공사에서 전용할 수 있기 때문에, 자재비 절감이 가능하다.First, since the on-site concrete is poured and constructed while using temporary brackets instead of integrated brackets in the joint construction of PC pillars and PC girder, the disadvantages of integrated brackets (increase in PC pillar production cost and increase in transportation cost due to reduction in loading) are eliminated and The stability of the joint can be secured. Furthermore, since the temporary bracket can be dismantled after the joint is completed and the dismantled temporary bracket can be used for other construction projects, material cost can be reduced.

둘째, PC기둥과 PC거더의 접합부 시공에서 PC거더가 거치되는 가설브라켓 등의 가설자재를 PC거더의 시공레벨에 맞게 위치조절하면서 설치할 수 있기 때문에 시공오차를 흡수 극복할 수 있어 접합부의 시공품질을 향상시킬 수 있다. Second, in the joint construction between PC column and PC girder, temporary materials such as temporary brackets on which the PC girder is mounted can be installed while adjusting the position according to the construction level of the PC girder. can be improved

셋째, PC기둥과 PC거더의 접합부 시공에서 PC거더가 거치되는 가설브라켓 등의 가설자재를 볼트와 너트의 조립으로 설치하기 때문에 설치 및 해체가 간편하며, 특히 가설자재의 해체과정에서 너트 내지 볼트의 해제만으로 가설자재를 PC거더로부터 쉽게 분리, 해체시킬 수 있어 작업성을 향상시킬 수 있다.Third, installation and dismantling are easy because temporary materials such as temporary brackets on which PC girder is mounted are installed by assembling bolts and nuts in the joint construction of PC columns and PC girder. The workability can be improved because temporary materials can be easily separated and dismantled from the PC girder only by releasing.

도 1은 종래 PC거더와 PC보의 접합부에 대한 다양한 시공사진을 보여준다.
도 2는 특허공개 제10-2017-0027233호에 개시된 강접합 PC공법의 접합부 시공상세이다.
도 3은 본 발명에 따른 PC기둥과 PC거더의 접합부 시공구조에 대한 제1실시예의 시공상세이다.
도 4는 도 3의 제1실시예에 적용된 가설브라켓과 톱니와셔의 상세이다.
도 5는 도 3의 제1실시예를 적용하여 실시하는 PC기둥과 PC거더의 접합부 시공방법에 대한 시공순서도이다.
도 6은 본 발명에 따른 PC기둥과 PC거더의 접합부 시공구조에 대한 제2실시예의 시공상세이다.
도 7은 본 발명에 따른 PC기둥과 PC거더의 접합부 시공구조에 대한 제3실시예의 시공상세이다.
도 8은 본 발명에 따른 PC기둥과 PC거더의 접합부 시공구조에 대한 제4실시예의 시공상세이다.
도 9는 도 8의 제4실시예에서 베이스플레이트의 설치상세이다.
도 10은 도 8의 제4실시예를 적용하여 실시하는 PC기둥과 PC거더의 접합부 시공방법에 대한 시공순서도 시공순서도이다.
1 shows various construction photos for the joint of the conventional PC girder and PC beam.
2 is a joint construction detail of the steel joint PC method disclosed in Patent Publication No. 10-2017-0027233.
3 is a construction detail of the first embodiment of the joint construction structure of the PC column and the PC girder according to the present invention.
4 is a detailed view of the temporary bracket and tooth washer applied to the first embodiment of FIG.
Figure 5 is a construction flow chart for the construction method of the junction of the PC column and PC girder carried out by applying the first embodiment of Figure 3;
6 is a construction detail of the second embodiment of the joint construction structure of the PC column and the PC girder according to the present invention.
7 is a construction detail of the third embodiment of the joint construction structure of the PC column and the PC girder according to the present invention.
8 is a construction detail of the fourth embodiment for the construction structure of the joint between the PC column and the PC girder according to the present invention.
9 is an installation detail of the base plate in the fourth embodiment of FIG.
Figure 10 is a construction flow chart construction flow chart for the joint construction method of the PC column and PC girder carried out by applying the fourth embodiment of Figure 8.

이하 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.

본 발명은 PC기둥(100)과 PC거더(300)의 접합부 시공에서, PC기둥(100)에 일체형 브라켓을 돌출 형성시키지 않고 쉽게 설치 및 해체가 가능한 가설브라켓(210) 등의 가설자재를 활용하는 한편, PC거더(300)를 가설브라켓(210) 등의 가설자재와 PC기둥(100)에 동시에 거치하여 설치하고 접합부에 현장콘크리트(400)를 타설하여 일체화 시공한다는데 특징이 있다. 본 발명은 가설브라켓(210) 등 가설자재의 구체적인 형태에 따라 다양한 실시예를 제안한다.The present invention utilizes temporary materials such as a temporary bracket 210 that can be easily installed and dismantled without protruding an integral bracket on the PC column 100 in the joint construction of the PC column 100 and the PC girder 300. On the other hand, it is characterized in that the PC girder 300 is mounted and installed on the temporary material such as the temporary bracket 210 and the PC column 100 at the same time, and the on-site concrete 400 is poured at the junction to perform the integrated construction. The present invention proposes various embodiments according to the specific shape of the temporary material, such as the temporary bracket 210.

도 3은 본 발명에 따른 PC기둥과 PC거더의 접합부 시공구조에 대한 제1실시예의 시공상세이고, 도 4는 도 3의 제1실시예에 적용된 가설브라켓(210)과 톱니와셔(240)의 상세이다. 제1실시예에 따른 PC기둥과 PC거더의 접합부 시공구조는 PC기둥(100), PC거더(300), 가설브라켓(210), 톱니와셔(240)를 포함하여 구성된다.3 is a construction detail of the first embodiment of the joint construction structure of the PC column and the PC girder according to the present invention, and FIG. 4 is a temporary bracket 210 and a tooth washer 240 applied to the first embodiment of FIG. It's detailed. The joint construction structure of the PC column and the PC girder according to the first embodiment is configured to include a PC column 100 , a PC girder 300 , a temporary bracket 210 , and a toothed washer 240 .

PC기둥(100)은 통상의 프리캐스트콘크리트 기둥부재로, PC거더(300)와의 접합 위치에서 콘크리트가 채워지지 아니하여 콘크리트 상단면(110)이 노출 형성되도록 제작된다. 가령 1개층 1절 단위라면 PC기둥(100) 상부에서 PC거더(300)와의 접합부가 형성되므로 PC기둥(100) 상부에 콘크리트 상단면(110)이 노출 형성되고, 2개층 1절 단위라면 PC기둥(100) 상부와 PC기둥 중간에서 각각 PC거더(300)와의 접합부가 형성되므로 PC기둥(100) 상부는 물론 PC기둥(100) 중간에도 콘크리트 상단면(110)이 노출 형성되며, 노출 형성된 콘크리트 상단면(110)에는 기둥철근의 연속배근, 정착을 위해 기둥철근이 노출/돌출 제작된다. PC기둥의 콘크리트 상단면(110)은 PC거더(300)가 거치되고 현장콘크리트(400)가 타설됨으로써 PC기둥(100)과 PC거더(300)가 일체화되는 접합부 공간이 된다. 더불어 PC기둥(100)은 PC거더(300)의 접합 위치 아래에 PC거더(300) 시공방향으로 관통슬리브(120) 또는 앵커볼트(130)가 매설되게 제작될 수 있는데, 관통슬리브(120) 내지 앵커볼트(130)는 가설브라켓(210)을 PC기둥(100)에 볼트체결방식으로 고정 설치하기 위한 구성이 된다. 제1실시예는 관통슬리브(120)가 매설된 예가 된다.The PC column 100 is a conventional precast concrete column member, and the concrete is not filled at the joint position with the PC girder 300 so that the concrete upper surface 110 is exposed. For example, if it is a one-story unit, the junction with the PC girder 300 is formed at the upper part of the PC column 100, so the concrete upper surface 110 is exposed on the upper part of the PC column 100, and if it is a unit of two floors, the PC column (100) Since the junction with the PC girder 300 is formed between the upper part and the PC column, respectively, the upper surface of the concrete 110 is exposed in the middle of the PC column 100 as well as the upper part of the PC column 100, and the exposed concrete upper end is formed. On the surface 110 , column reinforcement is exposed/protruded for continuous reinforcement and fixation of the column reinforcement. The concrete upper surface 110 of the PC column becomes a joint space in which the PC girder 300 is mounted and the on-site concrete 400 is poured, whereby the PC column 100 and the PC girder 300 are integrated. In addition, the PC column 100 may be manufactured so that the through sleeve 120 or the anchor bolt 130 is buried in the PC girder 300 construction direction under the bonding position of the PC girder 300, through the sleeve 120 to Anchor bolt 130 is a configuration for fixing the temporary bracket 210 to the PC column 100 in a bolt fastening method. The first embodiment is an example in which the through sleeve 120 is embedded.

가설브라켓(210)은 수직슬로트홀에 의한 볼트구멍(H)이 형성된 수직부(211)와 수평부(212)로 구분되는 ㄱ자형 부재로 마련되며, 수직부(211)가 PC기둥(100)의 측면에 맞대어지고 수평부(212)가 PC기둥(100)의 콘크리트 상단면(100)과 일치하게 설치되어 수직부의 수직슬로트홀에 의한 볼트구멍(H)을 통해 볼트접합됨으로써 PC기둥(100)에 고정된다. 도 4에서는 수직부(211)에 수직슬로트홀에 의한 볼트구멍(H)이 4개 형성되면서 수직부(211) 외표면이 삼각톱니 요철로 형성되고, 수직부(211)와 수평부(212) 사이에 보강리브(213)가 더 접합된 가설브라켓(210)을 예시하고 있다. The temporary bracket 210 is provided as a L-shaped member divided into a vertical part 211 and a horizontal part 212 in which a bolt hole (H) is formed by a vertical slot hole, and the vertical part 211 is a PC column (100). The horizontal part 212 is installed to coincide with the concrete upper surface 100 of the PC column 100, and is bolted through the bolt hole (H) by the vertical slot hole of the vertical part, thereby the PC column 100. is fixed on In FIG. 4, as four bolt holes (H) are formed by a vertical slot hole in the vertical part 211, the outer surface of the vertical part 211 is formed with triangular sawtooth irregularities, and the vertical part 211 and the horizontal part 212 are formed. An example of a temporary bracket 210 in which the reinforcing rib 213 is further joined therebetween.

제1실시예는 PC기둥(100)에 관통슬리브(120)가 매설된 경우로서, 관통볼트(220)를 이용하여 가설브라켓(210)을 PC기둥(100)에 볼트접합하는 예가 된다. 관통볼트(220)가 관통슬리브(120)에 삽입되고, 관통볼트(220)가 가설브라켓 수직부(211)의 수직슬로트홀에 의한 볼트구멍(H)을 통과하게 가설브라켓(210)이 설치된 상태에서 톱니와셔(240) 및 체결너트(230)와 체결됨으로써 볼트접합되며, 이로써 가설브라켓(210)가 PC기둥(100)에 밀착 고정된다. 이때 가설브라켓(210)은 수직부의 수직슬로트홀(slot hole)에 의한 볼트구멍(H)을 통해 체결위치 조절이 가능하므로 수평부(212)를 PC기둥의 콘크리트 상단면(110)과 일치되게 위치조절하면서 설치할 수 있다.The first embodiment is a case in which the through sleeve 120 is embedded in the PC column 100 , and is an example in which the temporary bracket 210 is bolted to the PC column 100 using the through bolt 220 . The through bolt 220 is inserted into the through sleeve 120, and the temporary bracket 210 is installed so that the through bolt 220 passes through the bolt hole H by the vertical slot hole of the vertical part 211 of the temporary bracket. By being fastened with the tooth washer 240 and the fastening nut 230 in the bolt connection, the temporary bracket 210 is closely fixed to the PC column 100 . At this time, the temporary bracket 210 can adjust the fastening position through the bolt hole (H) by the vertical slot hole of the vertical part, so the horizontal part 212 is positioned to match the concrete upper surface 110 of the PC column. It can be installed while adjusting.

특히 제1실시예는 가설브라켓의 수직부(211) 외표면이 삼각톱니 요철로 형성되고, 이러한 수직부(211)에는 동일하게 삼각톱니 요철로 표면처리된 톱니와셔(240)가 맞물리게 설치되면서 볼트접합된다. 이와 같은 가설브라켓의 수직부(211)와 톱니와셔(240)의 삼각톱니 맞물림 결합은 가설브라켓(210)의 해체 과정에서 가설브라켓(210)의 하강 탈락을 돕는다. 다시 말해 가설브라켓의 수직부(211)가 톱니와셔(240)와 삼각톱니 요철로 맞물려져 있기 때문에 가설브라켓의 수직부(211)는 수직하중이 가해질 경우 삼각톱니 요철을 따라 미끄러짐이 가능해지는데, 이로써 체결너트(230)를 풀어 볼트접합을 해제하면 가설브라켓의 수직부(211)가 톱니와셔(240) 함께 관통볼트(220)에 끼워져 있더라도 가설브라켓(210)은 자중에 의해 수직부(211)가 톱니와셔(240)에서 미끄러지면서 수직슬롯트홀(H)을 따라 하강하기 때문에 톱니와셔(240)의 방해없이 PC거더(300) 아래로 하강 탈락이 이루어질 수 있게 된다(도 4).In particular, in the first embodiment, the outer surface of the vertical part 211 of the temporary bracket is formed with triangular sawtooth irregularities, and the toothed washer 240 surface-treated with the same triangular toothed irregularities is installed in the vertical part 211 to engage the bolts. are joined The engagement of the vertical part 211 of the temporary bracket and the triangular toothed washer 240 helps the temporary bracket 210 fall off during the dismantling process of the temporary bracket 210 . In other words, since the vertical part 211 of the temporary bracket is engaged with the tooth washer 240 and the triangular serrations, the vertical part 211 of the temporary bracket can slide along the triangular serrations when a vertical load is applied. When the bolt connection is released by loosening the fastening nut 230, even if the vertical part 211 of the temporary bracket is inserted into the through bolt 220 together with the tooth washer 240, the temporary bracket 210 is the vertical part 211 by its own weight. Since it slides from the toothed washer 240 and descends along the vertical slot hole (H), it is possible to descend and drop down the PC girder 300 without the interference of the toothed washer 240 (FIG. 4).

PC거더(300)는 PC기둥(100)과 마찬가지로 통상의 프리캐스트콘크리트 거더부재가 되며, 가설브라켓의 수평부(212)와 PC기둥의 콘크리트 상부면(110) 위에 거치되게 설치된다. 본 발명에서 PC거더(300)는 가설브라켓의 수평부(212)와 함께 PC기둥의 콘크리트 상부면(110) 위에도 거치되기 때문에, 접합부 내지 슬래브 시공 중에는 PC거더(300)는 시공하중을 안정적으로 지지할 수 있게 된다. 또한 접합부 시공 후에는 가설브라켓(210)이 해체되더라도 PC거더(300)의 단부가 PC기둥의 콘크리트 상단면(110)에 거치된 채 접합부의 현장콘크리트(400)에 정착되고, PC거더(300의 상부도 현장시공 부분에 일체화되기 때문에 구조적인 안정성을 확보하게 된다.The PC girder 300 is a conventional precast concrete girder member like the PC column 100, and is installed to be mounted on the horizontal part 212 of the temporary bracket and the concrete upper surface 110 of the PC column. In the present invention, since the PC girder 300 is mounted on the concrete upper surface 110 of the PC column together with the horizontal part 212 of the temporary bracket, the PC girder 300 stably supports the construction load during the joint or slab construction. be able to do In addition, after the joint construction, even if the temporary bracket 210 is dismantled, the end of the PC girder 300 is fixed to the on-site concrete 400 of the joint while being mounted on the concrete upper surface 110 of the PC column, and the PC girder 300 Since the upper part is also integrated with the on-site construction part, structural stability is secured.

도 5는 도 3의 제1실시예를 적용하여 실시하는 PC기둥(100)과 PC거더(300)의 접합부 시공방법에 대한 시공순서도이며, 이를 참고하여 본 발명에 따른 PC기둥과 PC거더의 접합부 시공방법을 살펴본다. 먼저 콘크리트 상단면(110)이 노출 형성되면서 관통슬리브(120)가 관통 매설된 PC기둥(100)을 제작 준비하고, PC기둥(100)을 기둥위치에 시공한다(기둥시공단계). 도 5(a)(b)는 PC기둥(100) 제작과정을 보여주는데, 보는 바와 같이 기둥철근을 배근하고 관통슬리브(120) 양단부에 템플레이트(130)를 설치하여 배치한 후 기둥콘크리트를 타설하여 PC기둥(100)을 제작할 수 있다. 관통슬리브(120)의 개수, 템플레이트(130)의 크기 등은 구조계산된 가설브라켓(210)의 규모, 개수 등에 따라 적절하게 설계될 수 있다.Figure 5 is a construction flow chart for the construction method of the joint of the PC column 100 and the PC girder 300 carried out by applying the first embodiment of Fig. 3, with reference to this, the junction of the PC column and the PC girder according to the present invention Let's look at the construction method. First, as the concrete upper surface 110 is exposed and formed, the PC column 100 in which the penetrating sleeve 120 is penetrated is prepared to be manufactured, and the PC column 100 is constructed at the column position (pillar construction step). Figure 5 (a) (b) shows the manufacturing process of the PC column 100. As shown, the column reinforcement is reinforced and the template 130 is installed and arranged at both ends of the penetrating sleeve 120, and then the column concrete is poured and the PC The pillar 100 can be manufactured. The number of through sleeves 120, the size of the template 130, etc. may be appropriately designed according to the size, number, etc. of the structural calculation of the temporary bracket (210).

다음으로 가설브라켓(210)을 PC기둥(100)에 고정 설치한다(가설브라켓설치단계). 가설브라켓(210)의 고정 설치는, 먼저 관통슬리브(120)에 관통볼트(220)를 삽입하면서 관통볼트(220)의 양단부가 PC기둥(100)에서 돌출되게 설치하고(도 5(c)), 이어 돌출된 관통볼트(220)의 양단부 각각에 가설브라켓(210)을 설치하되 관통볼트(220)를 수직슬로트홀에 의한 볼트구멍(H)에 끼우면서 가설브라켓의 수직부(211)를 PC기둥에 맞대어지게 설치하고 동시에 가설브라켓의 수평부(212)를 PC기둥의 콘크리트 상단면(110)과 일치되도록 설치한 다음(도 (5(d)), 관통볼트(220)에 톱니와셔(240) 및 체결너트(230)를 체결하는 과정으로 실시할 수 있다(도 5(e)(f)). 특히 가설브라켓(210)은 톱니와셔(240)와 체결너트(230)의 체결위치를 적절히 조절하는 것으로 수평부(212)가 PC기둥의 콘크리트 상단면(110)과 일치되게 하면서도 PC거더(300)의 시공레벨에 맞게 설치한다.Next, the temporary bracket 210 is fixedly installed on the PC pole 100 (temporary bracket installation step). For the fixed installation of the temporary bracket 210, first, while inserting the through bolt 220 into the through sleeve 120, both ends of the through bolt 220 are installed to protrude from the PC column 100 (FIG. 5 (c)) , then install the temporary brackets 210 at both ends of the protruding through-bolt 220, but insert the through-bolt 220 into the bolt hole (H) by the vertical slot hole, and connect the vertical part 211 of the temporary bracket to the PC. Install to face the column and at the same time install the horizontal part 212 of the temporary bracket to match the concrete upper surface 110 of the PC column (Fig. 5(d)), and then install the toothed washer 240 on the through bolt 220 ) and the process of fastening the fastening nut 230 (Fig. 5(e)(f)). In particular, the temporary bracket 210 is provided by properly setting the fastening position of the toothed washer 240 and the fastening nut 230. By adjusting, the horizontal portion 212 is installed to match the construction level of the PC girder 300 while making it coincide with the concrete upper surface 110 of the PC column.

다음으로 PC거더(300)를 거치하여 설치하고(거더시공단계, 도 5(g)), PC기둥(100)과 PC거더(300) 접합부에 현장콘크리트(400)를 타설한다(콘크리트타설단계, 도 5(h)). PC거더(300)는 가설브라켓의 수평부(212)와 PC기둥의 콘크리트 상단면(110) 에 동시에 걸쳐지게 거치하며, 이로써 PC거더(300)는 시공하중(슬래브시공하중, 콘크리트 타설하중, 작업자의 작업하중 등)을 안정적으로 지지하게 된다. 접합부는 현장콘크리트(400)를 타설함으로써 PC기둥(100)과 PC거더(300)가 일체화되는 구조로 완성된다. 접합부 시공은 슬래브 시공과 동시에 진행할 수 있으며, 가령 PC거더(300)를 거치한 후에 하프PC슬래브를 설치하고 접합부와 하프PC슬래브 위로 현장콘크리트(400)를 동시타설하여 접합부와 슬래브를 일체 시공할 수 있다.Next, the PC girder 300 is mounted and installed (girder construction step, Fig. 5 (g)), and the on-site concrete 400 is poured at the junction of the PC column 100 and the PC girder 300 (concrete pouring step, Fig. 5(h)). The PC girder 300 is mounted so that it spans over the horizontal part 212 of the temporary bracket and the concrete upper surface 110 of the PC column at the same time, whereby the PC girder 300 is installed under the construction load (slab construction load, concrete pouring load, worker of the working load, etc.) will be stably supported. The joint portion is completed in a structure in which the PC column 100 and the PC girder 300 are integrated by pouring the on-site concrete 400 . The joint construction can proceed simultaneously with the slab construction. For example, after mounting the PC girder 300, the half PC slab is installed, and the on-site concrete 400 is simultaneously poured over the joint and the half PC slab to construct the joint and the slab. there is.

마지막으로 가설브라켓(210)의 볼트접합을 해제하여 가설브라켓(210)을 PC거더(300) 아래로 하강 탈락시키고 톱니와셔(240)와 가설브라켓(210)을 해체한다(가설해체단계, 도 5(i)). 체결너트(230)를 풀면 가설브라켓(210)이 톱니와셔(240)와 함께 관통볼트(220)에 끼워져 있더라도 가설브라켓(210)은 자중에 의해 수직부(211)가 삼각톱니 요철을 따라 미끄러짐이 가능해지며, 이로써 가설브라켓(210)은 톱니와셔(240)의 방해없이 PC거더(300) 아래로 하강 탈락이 이루어져 가설브라켓(210)의 해체가 쉬워진다. 가설브라켓(210)이 해체되어도 PC거더(300)는 PC기둥의 콘크리트 상단부(110)에 거치된 상태로 접합부에 정착되기 때문에 PC거더의 설치 안정성은 확보된다. 가설해체단계의 실시로 PC기둥(100)과 PC거더(300)의 접합부가 완성되며, 해체된 가설브라켓(210), 관통볼트(220), 체결너트(230), 톱니와셔(240)는 다른 공사에 전용할 수 있다.Finally, by releasing the bolt connection of the temporary bracket 210, the temporary bracket 210 is dropped below the PC girder 300, and the tooth washer 240 and the temporary bracket 210 are dismantled (temporary dismantling step, Fig. 5) (i)). When the fastening nut 230 is loosened, even if the temporary bracket 210 is inserted into the through bolt 220 together with the tooth washer 240, the vertical part 211 by its own weight prevents the vertical part 211 from sliding along the irregularities of the triangular teeth. This becomes possible, whereby the temporary bracket 210 is made to fall down below the PC girder 300 without the interference of the tooth washer 240, so that the temporary bracket 210 is easily dismantled. Even if the temporary bracket 210 is dismantled, the PC girder 300 is fixed to the joint while mounted on the concrete upper end 110 of the PC column, so the installation stability of the PC girder is ensured. The joint of the PC column 100 and the PC girder 300 is completed by the implementation of the temporary dismantling step, and the dismantled temporary bracket 210, the through bolt 220, the fastening nut 230, and the toothed washer 240 are different. It can be used for construction.

도 6은 본 발명에 따른 PC기둥과 PC거더의 접합부 시공구조에 대한 제2실시예의 시공상세이다. 제2실시예는 PC기둥(100) 단면보다 넓은 폭의 와이드 PC거더(300)가 적용되는 접합부의 예로서, 제1실시예와 전체적으로 유사하며, 다만 가설브라켓(210)의 형태에서 차이가 있다. 제2실시예에서 가설브라켓(210)은 와이드 PC거더(300)를 더욱 안정적으로 지지하기 위해 수직부(211) 및 수평부(212)가 PC기둥 밖으로 연장되는 크기로 확장 형성된다. 6 is a construction detail of the second embodiment of the joint construction structure of the PC column and the PC girder according to the present invention. The second embodiment is an example of a joint to which a wide PC girder 300 of a width wider than the cross section of the PC column 100 is applied, and is generally similar to the first embodiment, but there is a difference in the form of the temporary bracket 210 . In the second embodiment, the temporary bracket 210 is formed to extend to a size in which the vertical portion 211 and the horizontal portion 212 extend out of the PC column in order to support the wide PC girder 300 more stably.

도 7은 본 발명에 따른 PC기둥과 PC거더의 접합부 시공구조에 대한 제3실시예의 시공상세이다. 제3실시예는 가설브라켓(210)의 고정 설치를 위해 앵커볼트(130)가 매설된 PC기둥(100)이 적용된 예가 된다. 제3실시예는 전체적으로 제1실시예와 유사하며, 다만 PC기둥(100)에 관통슬리브 대신에 앵커볼트(130)가 매설되고 별도의 관통볼트 없이 앵커볼트(130)에 직접 톱니와셔(240)와 체결너트(230)가 체결된다는 점에서 차이가 있다. 제3실시예에서는 앵커볼트(130)는 영구적으로 PC기둥에 매설되며, 이후 접합부가 완성된 후에는 가설브라켓(210), 체결너트(230), 톱니와셔(240)가 해체된다. 7 is a construction detail of the third embodiment of the joint construction structure of the PC column and the PC girder according to the present invention. The third embodiment is an example in which the PC column 100 in which the anchor bolt 130 is embedded is applied for the fixed installation of the temporary bracket 210 . The third embodiment is generally similar to the first embodiment, except that the anchor bolt 130 is embedded in the PC column 100 instead of the through sleeve, and the tooth washer 240 is directly attached to the anchor bolt 130 without a separate through bolt. There is a difference in that and the fastening nut 230 is fastened. In the third embodiment, the anchor bolt 130 is permanently embedded in the PC column, and after the joint is completed, the temporary bracket 210, the fastening nut 230, and the toothed washer 240 are dismantled.

도 8은 본 발명에 따른 PC기둥과 PC거더의 접합부 시공구조에 대한 제4실시예의 시공상세이고, 도 9는 도 8의 제4실시예에서 베이스플레이트(260)의 설치상세와 동작상세이다. 제4실시예는 와이드 PC거더(300)가 적용되는 접합부의 다른 실시예로서, 전체적으로 제1실시예와 유사하며 다만 와이드 PC거더(300)를 더욱 안정적으로 지지하기 위해 가설브라켓(210) 외에 가설받침철골(250)과 베이스플레이트(260)가 더 설치되고 가설브라켓(210)의 하강 탈락을 톱니와셔 대신에 베이스플레이트(260)로 유도하는 점에서 큰 차이가 있다. 8 is a construction detail of the fourth embodiment of the joint construction structure of the PC column and the PC girder according to the present invention, and FIG. 9 is the installation and operation details of the base plate 260 in the fourth embodiment of FIG. The fourth embodiment is another embodiment of the joint to which the wide PC girder 300 is applied, and is similar to the first embodiment as a whole, except that the wide PC girder 300 is erected in addition to the temporary bracket 210 to more stably support it. There is a big difference in that the supporting steel frame 250 and the base plate 260 are further installed and the lowering of the temporary bracket 210 is guided to the base plate 260 instead of the tooth washer.

제4실시예에서 가설브라켓(210)은 수직부(211)가 PC기둥(100)의 측면에 맞대어지고 수평부(212)가 PC기둥의 콘크리트 상단면(120) 아래 위치에 위치하도록 설치되며, 이렇게 설치된 가설브라켓의 수평부(212) 위에 가설받침철골(250)이 베이스플레이트(260)와 함께 설치된다. 제4실시예는 제1실시예와 마찬가지로 가설브라켓(210)이 관통슬리브(120), 관통볼트(220), 체결너트(230)를 이용하여 설치된 예가 되나, 제2,3실시예에서와 같이 가설브라켓(210)이 확장 형성되는 예는 물론 앵커볼트, 체결너트를 이용하면서 설치되는 예로 변경도 가능하다.In the fourth embodiment, the temporary bracket 210 is installed so that the vertical part 211 is abutted to the side of the PC column 100 and the horizontal part 212 is located below the concrete upper surface 120 of the PC column, The temporary support steel frame 250 is installed together with the base plate 260 on the horizontal part 212 of the temporary bracket installed in this way. In the fourth embodiment, as in the first embodiment, the temporary bracket 210 is installed using the through sleeve 120, the through bolt 220, and the fastening nut 230, but as in the second and third embodiments, It is possible to change the example in which the temporary bracket 210 is expanded and formed, as well as an example in which an anchor bolt and a fastening nut are used while being installed.

가설철골받침(250)은 H형강과 같이 상·하부플랜지(251, 253)와 웨브로 구분되는 철골부재로 마련되어 PC거더(300)의 너비방향으로 설치되는데, 하부플랜지(252)가 가설브라켓의 수평부(212) 위에 거치되고 상부플랜지(251)가 PC기둥의 콘크리트 상단면(110)과 일치하게 설치되어 하부플랜지(252)가 볼트접합(B)으로 가설브라켓(210)에 고정된다. 도 8에서와 같이 가설브라켓(210)이 PC기둥(100) 일측면에 나란하게 설치된 경우라면 가설받침철골(250)은 이웃하는 가설브라켓(210) 상호간을 연결하면서 와이드 PC거더(300)를 충분히 지지할 수 있는 길이로 설치된다. The temporary steel frame support 250 is provided as a steel member divided into upper and lower flanges 251 and 253 and a web like H-beam and is installed in the width direction of the PC girder 300, and the lower flange 252 is the temporary bracket. It is mounted on the horizontal part 212 and the upper flange 251 is installed to coincide with the concrete upper surface 110 of the PC column, and the lower flange 252 is fixed to the temporary bracket 210 by bolting (B). As in FIG. 8, if the temporary bracket 210 is installed side by side on one side of the PC column 100, the temporary support steel frame 250 connects the adjacent temporary brackets 210 to each other and the wide PC girder 300 is sufficiently secured. It is installed in a length that can be supported.

베이스플레이트(260)는 가설브라켓의 수평부(212)와 가설받침철골의 하부플랜지(252) 사이에 설치되는데, 베이스플레이트(260)의 두께를 적절히 조절하는 것으로 가설받침철골의 상부플랜지(251)가 PC기둥의 콘크리트 상단면(110)과 일치하게 설치될 수 있다. 베이스플레이트(260)는 도 9에서와 같이 직사다리꼴 단면의 경사플레이트(261, 262) 한쌍의 부재로 마련되며, 이러한 베이스플레이트(260)는 한쌍의 경사플레이트(261, 262)를 경사면끼리 서로 맞대게 설치함으로써 상부의 경사플레이트(261)가 하부의 경사플레이트(262)를 따라 미끄러짐이 가능해져 미끄러짐 정도로 베이스플레이트(260)의 두께를 조절할 수 있다. 또한 한쌍의 경사플레이트(261, 262)에 의한 베이스플레이트(260)는 가설받침철골(250)의 해체 과정에서 볼트접합(B)을 해제하면 자중에 의해 상부의 경사플레이트(261)가 하부의 경사플레이트(262)를 따라 미끄러져 내려오기 때문에 가설받침철골(250)의 하강 탈락도 돕는다(도 9(b)). 이때 베이스플레이트(260)는 볼트접합(B) 사이 공간에 맞춤 설치되는 것이 바람직한데(도 9(a)), 볼트접합(B)으로 베이스플레이트(260), 가설받침철골(250)이 고정 설치된 상태에서 상부 경사플레이트(261)의 미끄러짐을 억제하여 고정 상태를 안정적으로 유지하기 위함이다. 이와 더불어 가설받침철골의 하부플랜지(262)에는 볼트구멍이 수평슬로트홀(slot hole)로 형성되는 것이 더욱 바람직하며, 이로써 볼트접합(B)의 접합위치를 좌우 조절하는 것으로 한쌍의 경사플레이트(261, 262)의 미끄러짐 정도를 조절하면서 베이스플레이트(260)의 두께를 조절할 수 있고 동시에 베이스플레이트(260)를 볼트접합(B) 사이 공간에서 맞춤 설치할 수 있다. The base plate 260 is installed between the horizontal part 212 of the temporary bracket and the lower flange 252 of the temporary support steel frame, by appropriately adjusting the thickness of the base plate 260, the upper flange 251 of the temporary support steel frame. may be installed to coincide with the concrete upper surface 110 of the PC column. The base plate 260 is provided with a pair of members of the inclined plates 261 and 262 having a rectangular cross section as shown in FIG. By usually installing, the upper inclined plate 261 can slide along the lower inclined plate 262, so that the thickness of the base plate 260 can be adjusted to the extent of sliding. In addition, when the base plate 260 by a pair of inclined plates 261 and 262 releases the bolt junction (B) in the process of dismantling the temporary support steel frame 250, the inclined plate 261 of the upper part is inclined by its own weight. Since it slides down along the plate 262, it also helps the falling off of the temporary support steel frame 250 (FIG. 9(b)). At this time, it is preferable that the base plate 260 be fitted to the space between the bolt junctions (B) (FIG. 9 (a)), and the base plate 260 and the temporary support steel frame 250 are fixedly installed by the bolt junction (B). This is to suppress the sliding of the upper inclined plate 261 in the state to stably maintain the fixed state. In addition, it is more preferable that the bolt hole is formed as a horizontal slot hole in the lower flange 262 of the temporary supporting steel frame, thereby adjusting the joint position of the bolt joint (B) to the left and right, and a pair of inclined plates 261 , 262, the thickness of the base plate 260 can be adjusted while controlling the degree of sliding, and at the same time, the base plate 260 can be custom-installed in the space between the bolt junctions (B).

도 10은 도 8의 제4실시예를 적용하여 실시하는 PC기둥과 PC거더의 접합부 시공방법에 대한 시공순서도로, 전체적으로 도 5에서 살펴본 시공방법과 유사하며 다만 가설브라켓(210)의 설치위치, 베이스플레이트(260)와 가설받침철골(250)의 추가설치, 톱니와셔의 생략에서 차이가 있다. 먼저 콘크리트 상단면(110)이 노출 형성되면서 PC기둥(100)을 기둥위치에 시공한다(기둥시공단계, 도 10(a)(b)). 다음으로 가설브라켓(210)을 고정 설치하며, 이때 가설브라켓(210)은 수직부(211)가 PC기둥(100)에 맞대어지면서 수평부(212)가 PC기둥의 콘크리트 상단면(110) 아래에 위치하도록 설치한다(가설브라켓설치단계, 도 10(c)). 다음으로 가설브라켓의 수평부(212) 위에 베이스플레이트(260)를 설치하고(도 10(d)), 배아스플레이트(260) 위에 가설받침철골(250)을 거치하며(도 10(e)), 이때 가설받침철골(250)은 그 상부플랜지(251)를 PC기둥의 콘크리트 상단면(110)과 일치되게 하면서 하부플랜지(252)를 설브라켓의 수평부(212)에 볼트접합(B)하여 고정 설치한다(가설받침철골설치단계). 다음으로 PC거더(300)를 거치하여 설치하고(거더시공단계), PC기둥(100)과 PC거더(300) 접합부에 현장콘크리트(400)를 타설한다(콘크리트타설단계). 10 is a construction flow diagram for a construction method of a junction between a PC column and a PC girder carried out by applying the fourth embodiment of FIG. 8, which is similar to the construction method shown in FIG. 5 as a whole, except that the installation position of the temporary bracket 210, There is a difference in the additional installation of the base plate 260 and the temporary support steel frame 250, and the omission of the toothed washer. First, as the concrete upper surface 110 is exposed, the PC column 100 is constructed at the column position (pillar construction step, Fig. 10(a)(b)). Next, the temporary bracket 210 is fixedly installed, and in this case, the vertical part 211 is abutted to the PC column 100 while the horizontal part 212 is located below the concrete upper surface 110 of the PC column. It is installed so as to be positioned (temporary bracket installation step, Fig. 10(c)). Next, the base plate 260 is installed on the horizontal part 212 of the temporary bracket (FIG. 10(d)), and the temporary support steel frame 250 is mounted on the embryo plate 260 (FIG. 10(e)) , At this time, the temporary support steel frame 250 is bolted (B) to the lower flange 252 to the horizontal part 212 of the installation bracket while making the upper flange 251 coincide with the concrete upper surface 110 of the PC column. Fixed installation (steel frame installation stage for temporary support). Next, the PC girder 300 is mounted and installed (girder construction step), and the site concrete 400 is poured at the junction of the PC column 100 and the PC girder 300 (concrete pouring step).

마지막으로 가설받침철골(250)의 볼트접합(B)을 해제하여 가설받침철골을 PC거더(300) 아래로 하강 탈락시키고 베이스플레이트(260), 가설받침철골(250), 가설브라켓(210)을 해체한다(가설해체단계). 볼트접합(B)을 해제하면 한쌍의 경사플레이트(261, 262)로 마련된 베이스플레이트(260)는 상부의 경사플레이트(261)가 자중에 의해 하부의 경사플레이트(262)를 따라 미끄러져 내려오고 상부의 경사플레이트(261)가 미끄러져 내려온 만큼 가설받침철골(250)도 자중에 의해 내려오기 때문에, 가설받침철골(250)은 PC거더(300) 아래로 쉽게 하강 탈락하며, 이로써 가설받침철골(250)과 베이스플레이트(260)는 물론 그 아래의 가설브라켓(210)의 해체가 쉬워진다. 가설해체단계의 실시로 PC기둥(100)과 PC거더(300)의 접합부가 완성되며, 해체된 베이스플레이트(260), 가설받침철골(250), 가설브라켓(210) 등은 다른 공사에 전용할 수 있다.Finally, by releasing the bolt connection (B) of the temporary support steel frame 250, the temporary support steel frame is dropped below the PC girder 300, and the base plate 260, the temporary support steel frame 250, and the temporary bracket 210 are removed. Dismantle (provision dismantling stage). When the bolt joint (B) is released, the base plate 260 provided with a pair of inclined plates 261 and 262 slides down along the inclined plate 262 of the lower part by the weight of the upper inclined plate 261 and the upper part As the inclined plate 261 of the slanted plate 261 slides down as much as the temporary support steel frame 250 also descends by its own weight, the temporary support steel frame 250 easily descends below the PC girder 300, and thereby the temporary support steel frame 250 ) and the base plate 260, as well as the dismantling of the temporary bracket 210 below it is easy. The joint of the PC column 100 and the PC girder 300 is completed by the implementation of the temporary dismantling stage, and the dismantled base plate 260, the temporary support steel frame 250, the temporary bracket 210, etc. can be used for other construction. can

이상에서 본 발명은 구체적인 실시예를 참조하여 상세히 설명되었으나, 실시예는 본 발명을 예시하기 위한 것일 뿐이므로, 본 발명의 기술적 사상을 벗어나지 않는 범위 내에서 치환, 부가 및 변형된 실시 형태들 역시 아래에 첨부한 청구범위에 의하여 정하여지는 본 발명의 보호범위에 속한다고 할 것이다.In the above, the present invention has been described in detail with reference to specific examples, but since the examples are only for illustrating the present invention, substituted, added and modified embodiments are also provided below without departing from the technical spirit of the present invention. It will be said that it falls within the protection scope of the present invention as defined by the claims appended hereto.

100: PC거더
110: 콘크리트 상단면
120: 관통슬리브
130: 앵커볼트
210: 가설브라켓
220: 관통볼트
230: 체결너트
240: 톱니와셔
250: 가설받침철골
260: 베이스플레이트
261, 262: 경사플레이트
300: PC거더
400: 현장콘크리트
H: 볼트구멍
B: 볼트접합
100: PC girder
110: concrete top surface
120: through sleeve
130: anchor bolt
210: temporary bracket
220: through bolt
230: fastening nut
240: tooth washer
250: temporary support steel frame
260: base plate
261, 262: inclined plate
300: PC girder
400: field concrete
H: bolt hole
B: bolted connection

Claims (9)

PC기둥(100)과 PC거더(300)의 접합부 시공에서,
PC거더(300)와의 접합 위치에서 콘크리트가 채워지지 아니하여 콘크리트 상단면(110)이 노출 형성된 PC기둥(100);
외표면이 삼각톱니 요철로 형성되면서 수직슬로트홀에 의한 볼트구멍(H)이 형성된 수직부(211);와 수평부(212);로 구분되는 ㄱ자형 부재로, 수직부(211)가 PC기둥(100)의 측면에 맞대어지고 수평부(212)가 PC기둥(100)의 콘크리트 상단면(100)과 일치하게 설치되는 가설브라켓(210);
상기 가설브라켓의 수직부(211)의 삼각톱니 요철과 동일하게 삼각톱니 요철로 표면처리된 와셔부재로, 상기 가설브라켓 수직부(211)에 맞물리게 설치되는 톱니와셔(240);
상기 가설브라켓의 수평부(212)와 PC기둥의 콘크리트 상부면(110) 위에 거치되게 설치되는 PC거더(300);를 포함하여 구성되며,
상기 가설브라켓(210)은, 수직부에 톱니와셔가 맞물려 설치된 상태에서 수직부의 수직슬로트홀에 의한 볼트구멍(H)을 통해 볼트접합으로 PC기둥(100)에 위치 고정되고, 볼트접합이 풀리면 자중에 의해 가설브라켓의 수직부(211)가 톱니와셔(240)에서 미끄러지면서 수직슬롯트홀(H)을 따라 하강하면서 PC거더(300) 아래로 하강 탈락하게 되는 것을 특징으로 하는 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공구조.
In the joint construction of the PC column 100 and the PC girder 300,
PC column 100 in which the concrete top surface 110 is exposed because the concrete is not filled at the joint position with the PC girder 300;
A vertical part 211 with a bolt hole (H) formed by a vertical slot hole while the outer surface is formed with triangular sawtooth irregularities; and a horizontal part 212; A L-shaped member divided into a vertical part 211 is a PC column Temporary bracket (210) butt to the side of (100) and the horizontal part (212) is installed to coincide with the concrete upper surface (100) of the PC column (100);
A washer member surface-treated with triangular serrated irregularities in the same manner as the triangular serrated irregularities of the vertical portion 211 of the temporary bracket, and a toothed washer 240 installed to engage the vertical portion 211 of the temporary bracket;
and a PC girder 300 installed to be mounted on the horizontal portion 212 of the temporary bracket and the concrete upper surface 110 of the PC column.
The temporary bracket 210 is fixed in position on the PC column 100 by bolting through the bolt hole (H) by the vertical slot hole of the vertical part in a state where the tooth washer is installed in the vertical part, and when the bolt connection is loosened, its own weight A PC column using a temporary bracket, characterized in that the vertical part 211 of the temporary bracket slides from the tooth washer 240 and descends along the vertical slot hole (H) while falling down below the PC girder 300. and PC girder joint construction structure.
제1항에서,
상기 PC기둥(100)은, PC거더(300)와의 접합 위치 아래에 관통슬리브(120)가 매설되며,
상기 가설브라켓(210)은, 상기 PC기둥의 관통슬리브(120)에 관통볼트(230)가 삽입되고 관통볼트(230)가 수직부의 수직슬로트홀에 의한 볼트구멍(H)을 통과하여 톱니와셔(240) 및 체결너트(230)와 체결됨으로써 볼트접합되는 것을 특징으로 하는 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공구조.
In claim 1,
The PC column 100, the through sleeve 120 is buried under the joint position with the PC girder 300,
The temporary bracket 210, a through bolt 230 is inserted into the through sleeve 120 of the PC column, and the through bolt 230 passes through the bolt hole (H) by the vertical slot hole of the vertical part, and the tooth washer ( 240) and a joint construction structure of a PC column and a PC girder using a temporary bracket, characterized in that it is bolted by being fastened with the fastening nut 230.
제1항에서,
상기 PC기둥(100)은, PC거더(300)와의 접합 위치 아래에 앵커볼트(130)가 매설되며,
상기 가설브라켓(210)은, 상기 PC기둥의 앵커볼트(130)가 수직부의 수직슬로트홀에 의한 볼트구멍(H)을 통과하여 톱니와셔(240) 및 체결너트(230)와 체결됨으로써 볼트접합되는 것을 특징으로 하는 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공구조.
In claim 1,
The PC column 100, the anchor bolt 130 is buried under the joint position with the PC girder 300,
The temporary bracket 210, the anchor bolt 130 of the PC column passes through the bolt hole (H) by the vertical slot hole of the vertical part and is bolted by being fastened with the tooth washer 240 and the fastening nut 230 A joint construction structure of a PC column and a PC girder using a temporary bracket, characterized in that.
PC기둥(100)과 PC거더(300)의 접합부 시공에서,
PC거더(300)와의 접합 위치에서 콘크리트가 채워지지 아니하여 콘크리트 상단면(110)이 노출 형성되며, PC거더(300)의 접합 위치 아래에 PC거더 시공방향으로 관통슬리브(120)가 관통 매설된 PC기둥(100);
볼트구멍(H)이 형성된 수직부(211)와 수평부(212)로 구분되는 ㄱ자형 부재로, 수직부(211)가 PC기둥(100)의 측면에 맞대어지고 수평부(212)가 PC기둥(100)의 콘크리트 상단면(100) 아래에 위치하게 설치되어 수직부의 볼트구멍(H)을 통해 볼트접합으로 PC기둥에 고정되는 가설브라켓(210);
상·하부플랜지(251, 252)와 웨브로 구분되는 철골부재로, PC거더(300)의 너비방향으로 설치되되, 하부플랜지(252)가 상기 가설브라켓의 수평부(212) 위에 거치되고 상부플랜지(251)가 상기 PC기둥의 콘크리트 상단면(110)과 일치하게 설치되어 하부플랜지(252)가 볼트접합(B)으로 상기 가설브라켓(210)에 고정되는 가설받침철골(250);
상기 가설받침철골의 상부플랜지(251)와 PC기둥의 콘크리트 상단면(110) 위에 거치되게 설치되는 PC거더(300);를 포함하여 구성되며,
상기 가설브라켓의 수평부(212)와 가설받침철골의 하부플랜지(252) 사이에는, 베이스플레이트(260)가 더 설치되며,
상기 베이스플레이트(260)는, 직사다리꼴 단면의 경사플레이트(261, 262) 한쌍의 부재로 마련되어, 경사면끼리 서로 맞대게 설치됨으로써 상부의 경사플레이트(261)가 하부의 경사플레이트(262)를 따라 미끄러짐이 가능한 것을 특징으로 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공구조.
In the joint construction of the PC column 100 and the PC girder 300,
At the joint position with the PC girder 300, the concrete is not filled, so the concrete upper surface 110 is exposed, and the penetrating sleeve 120 is embedded under the joint position of the PC girder 300 in the PC girder construction direction. PC pillar (100);
As a L-shaped member divided into a vertical portion 211 and a horizontal portion 212 having a bolt hole (H) formed, the vertical portion 211 is abutted to the side of the PC column 100 and the horizontal portion 212 is the PC column Temporary bracket 210 installed to be positioned below the concrete upper surface 100 of (100) and fixed to the PC column by bolting through the bolt hole (H) of the vertical part;
A steel frame member divided into upper and lower flanges 251 and 252 and a web, which is installed in the width direction of the PC girder 300, the lower flange 252 is mounted on the horizontal part 212 of the temporary bracket, and the upper flange (251) is installed to coincide with the concrete upper surface 110 of the PC column, the lower flange 252 is fixed to the temporary bracket 210 by bolting (B), a temporary support steel frame 250;
and a PC girder 300 installed to be mounted on the upper flange 251 of the temporary support steel frame and the concrete upper surface 110 of the PC column.
Between the horizontal part 212 of the temporary bracket and the lower flange 252 of the temporary support steel frame, a base plate 260 is further installed,
The base plate 260 is provided with a pair of members of the inclined plates 261 and 262 having a rectangular cross section, and the inclined surfaces are installed to face each other so that the upper inclined plate 261 slides along the lower inclined plate 262. A joint construction structure of a PC column and a PC girder using a temporary bracket.
제4항에서,
상기 PC기둥(100)은, PC거더(300)와의 접합 위치 아래에 관통슬리브(120)가 매설되며,
상기 가설브라켓(210)은, 상기 PC기둥의 관통슬리브(120)에 관통볼트(230)가 삽입되고 관통볼트(230)가 수직부의 볼트구멍(H)을 통과하여 체결너트(230)와 체결됨으로써 볼트접합되는 것을 특징으로 하는 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공구조.
In claim 4,
The PC column 100, the through sleeve 120 is buried under the joint position with the PC girder 300,
The temporary bracket 210 is a through-bolt 230 is inserted into the through-sleeve 120 of the PC column, and the through-bolt 230 passes through the bolt hole H of the vertical part and is fastened with the fastening nut 230. A joint construction structure of a PC column and a PC girder using a temporary bracket, characterized in that it is bolted.
제4항에서,
상기 PC기둥(100)은, PC거더(300)와의 접합 위치 아래에 앵커볼트(130)가 매설되며,
상기 가설브라켓(210)은, 상기 PC기둥의 앵커볼트(130)가 수직부의 볼트구멍(H)을 통과하여 체결너트(230)와 체결됨으로써 볼트접합되는 것을 특징으로 하는 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공구조.
In claim 4,
The PC column 100, the anchor bolt 130 is buried under the joint position with the PC girder 300,
The temporary bracket 210 is a PC column using a temporary bracket, characterized in that the anchor bolt 130 of the PC column passes through the bolt hole (H) of the vertical part and is fastened with the fastening nut 230 to be bolted together. Connection construction structure of PC girder.
제4항 내지 제6항 중 어느 한 항에서,
상기 베이스플레이트(260)는, 상기 가설브라켓의 수평부(212)와 가설받침철골의 하부플랜지(252) 사이에서 볼트접합(B) 사이 공간에 한쌍의 경사플레이트(261, 262)가 경사면끼리 서로 맞대면서 맞춤 설치되는 것을 특징으로 하는 PC기둥과 PC거더의 접합부 시공구조.
7. In any one of claims 4 to 6,
The base plate 260 has a pair of inclined plates 261 and 262 in the space between the bolt joint (B) between the horizontal part 212 of the temporary bracket and the lower flange 252 of the temporary support steel frame. A joint construction structure of a PC column and a PC girder, characterized in that they are custom-installed while facing each other.
제1항 내지 제3항 중 어느 한 항에 따른 PC기둥과 PC거더의 접합부 시공구조를 적용하면서 PC기둥과 PC거더의 접합부를 시공하는 방법으로,
PC기둥(100)을 기둥위치에 시공하는 기둥시공단계;
수직부(211)를 PC기둥(100)의 측면에 맞대고 수평부(212)를 PC기둥의 콘크리트 상단면(100)과 일치하게 하면서 가설브라켓(210)을 설치하고 수직부의 수직슬로트홀에 의한 볼트구멍(H)을 통해 볼트접합하여 가설브라켓(210)을 PC기둥(100)에 밀착 고정하는 가설브라켓설치단계;
가설브라켓의 수평부(212)와 PC기둥의 콘크리트 상단면(110) 위에 PC거더(300)를 거치하여 설치하는 거더시공단계;
PC기둥(100)과 PC거더(300) 접합부에 현장콘크리트(400)를 타설하는 콘크리트타설단계;
가설브라켓(210)의 볼트접합을 해제하여 가설브라켓을 PC거더(300) 아래로 하강 탈락시키고 톱니와셔(240)와 가설브라켓(210)을 해체하는 가설해체단계;
를 포함하여 이루어지는 것을 특징으로 하는 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공방법.
A method of constructing a joint between a PC column and a PC girder while applying the joint construction structure of the PC column and PC girder according to any one of claims 1 to 3,
A pillar construction step of constructing the PC pillar 100 at the pillar position;
Install the temporary bracket 210 while placing the vertical part 211 against the side of the PC column 100 and making the horizontal part 212 coincide with the concrete upper surface 100 of the PC column, and bolt by the vertical slot hole of the vertical part. A temporary bracket installation step of fixing the temporary bracket 210 in close contact with the PC column 100 by bolting through the hole (H);
A girder construction step of mounting and installing the PC girder 300 on the horizontal part 212 of the temporary bracket and the concrete upper surface 110 of the PC column;
A concrete pouring step of pouring the on-site concrete 400 to the junction of the PC column 100 and the PC girder 300;
A temporary dismantling step of releasing the bolt connection of the temporary bracket 210 to drop the temporary bracket below the PC girder 300 and dismantling the tooth washer 240 and the temporary bracket 210;
A joint construction method of a PC column and a PC girder using a temporary bracket, characterized in that it comprises a.
제4항 내지 제6항 중 어느 한 항에 따른 PC기둥과 PC거더의 접합부 시공구조를 적용하면서 PC기둥과 PC거더의 접합부를 시공하는 방법으로,
PC기둥(100)을 기둥위치에 시공하는 기둥시공단계;
수직부(211)를 PC기둥(100)의 측면에 맞대고 수평부(212)를 PC기둥의 콘크리트 상단면(100) 아래에 위치하게 하면서 가설브라켓(210)을 설치하고 수직부의 볼트구멍(H)을 통해 볼트접합하여 가설브라켓(210)을 PC기둥(100)에 밀착 고정하는 가설브라켓설치단계;
가설브라켓의 수평부(2120 위에 베이스플레이트(260)를 설치하면서 가설받침철골(250)을 거치하고, 가설받침철골의 상부플랜지(251)가 PC기둥의 콘크리트 상단면(110)과 일치되게 하면서 가설받침철골의 하부플랜지(252)를 가설브라켓의 수평부(212)에 볼트접합(B)하여 고정 설치하는 가설받침철골설치단계;
가설받침철골의 상부플랜지(251)와 PC기둥의 콘크리트 상단면(110) 위에 PC거더(300)를 거치하여 설치하는 거더거치단계;
가설받침철골의 볼트접합(B)을 해제하여 가설받침철골을 PC거더(300) 아래로 하강 탈락시키고 베이스플레이트(260), 가설받침철골(250), 가설브라켓(210)을 해체하는 가설해체단계;
를 포함하여 이루어지는 것을 특징으로 하는 가설브라켓을 이용한 PC기둥과 PC거더의 접합부 시공방법.
A method of constructing a joint between a PC column and a PC girder while applying the joint construction structure of a PC column and a PC girder according to any one of claims 4 to 6,
A pillar construction step of constructing the PC pillar 100 at the pillar position;
Install the temporary bracket 210 while placing the vertical part 211 against the side of the PC column 100 and placing the horizontal part 212 below the concrete upper surface 100 of the PC column, and then install the vertical part bolt hole (H) A temporary bracket installation step of fixing the temporary bracket 210 to the PC column 100 by bolting through;
While installing the base plate 260 on the horizontal part 2120 of the temporary bracket, the temporary support steel frame 250 is mounted, and the upper flange 251 of the temporary support steel frame is installed while matching the concrete upper surface 110 of the PC column. A temporary support steel frame installation step of fixing and installing the lower flange 252 of the support steel frame by bolting (B) to the horizontal part 212 of the temporary bracket;
A girder mounting step of mounting and installing the PC girder 300 on the upper flange 251 of the temporary support steel frame and the concrete upper surface 110 of the PC column;
Temporary dismantling step of releasing the bolt connection (B) of the temporary support steel frame to drop the temporary support steel frame below the PC girder 300 and dismantling the base plate 260, the temporary support steel frame 250, and the temporary bracket 210 ;
A joint construction method of a PC column and a PC girder using a temporary bracket, characterized in that it comprises a.
KR1020210041188A 2021-03-30 2021-03-30 Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket KR102372473B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020210041188A KR102372473B1 (en) 2021-03-30 2021-03-30 Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020210041188A KR102372473B1 (en) 2021-03-30 2021-03-30 Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket

Publications (1)

Publication Number Publication Date
KR102372473B1 true KR102372473B1 (en) 2022-03-10

Family

ID=80816210

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020210041188A KR102372473B1 (en) 2021-03-30 2021-03-30 Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket

Country Status (1)

Country Link
KR (1) KR102372473B1 (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101214246B1 (en) * 2011-02-18 2012-12-20 (주) 에스와이씨 A plat board for fixing having anti-skid surface
KR101514144B1 (en) * 2013-10-02 2015-04-21 삼성물산 주식회사 Precast Concrete Frame and Construction Method thereof
KR20170027233A (en) 2015-08-28 2017-03-09 경희대학교 산학협력단 the rigid connection structure between precast concrete column and precast concrete beam using the temporary bracket installing precast concrete column, the modular system using the same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101214246B1 (en) * 2011-02-18 2012-12-20 (주) 에스와이씨 A plat board for fixing having anti-skid surface
KR101514144B1 (en) * 2013-10-02 2015-04-21 삼성물산 주식회사 Precast Concrete Frame and Construction Method thereof
KR20170027233A (en) 2015-08-28 2017-03-09 경희대학교 산학협력단 the rigid connection structure between precast concrete column and precast concrete beam using the temporary bracket installing precast concrete column, the modular system using the same

Similar Documents

Publication Publication Date Title
KR100926140B1 (en) Structure for using precast members and construction method thereof
KR101242395B1 (en) Construction method for rhamen bridge
KR20060064994A (en) A pile head reinforcement structure of precastconcrete pile
KR102372473B1 (en) Constuction Structure for Joint of PC-Colunm and PC-Girder Using Temporay Bracket
JP2986751B2 (en) Seismic performance enhancement method for buildings and seismic blocks
JP2011214221A (en) Stiffening girder of suspension bridge, and method for constructing the same
KR20100018877A (en) Structure for jointing framework of vertical construction supporting precast concrete girder panel and method thereof
JP2004250932A (en) Rapid construction method of precast structure
JP2520354B2 (en) Construction method of precast concrete beams and columns, and earthquake-resistant walls using them
KR20130042526A (en) Attachment plates adjoining ends of concrete beam with walls of abutments, and method of building concrete structure using the same
KR101398435B1 (en) Constructing method of complex girder and the structure thereby
JP4520830B2 (en) Exterior wall panel construction method and exterior wall panel mounting structure
KR102247787B1 (en) Partial reinforced concrete permanent Cement Mortar form and method of constructing the same
JP2001311247A (en) Construction method for concrete structure
KR102398605B1 (en) Construction method of seismic retrofit system using pc panel
KR102187993B1 (en) Prefabricated Bridge Structure and Construction Method
KR102269141B1 (en) Deck plate wall installation method using underground pavement
KR102400565B1 (en) Reinforcing bar using Precast Concrete Panels and Construction Method for this same
JPH11166294A (en) Steel frame-contained concrete beam and floor construction method using the concrete beam
JP7010709B2 (en) How to build prefabricated and concrete structures
KR102029301B1 (en) Prefabricated column assembly with foundation reinforcement part
KR101665626B1 (en) the construction method of the hybrid steel joint construction
JP2578671B2 (en) Column and beam construction method
JPH07292683A (en) Anchor frame and foundation construction method using the frame
JPH11190068A (en) Building structure

Legal Events

Date Code Title Description
GRNT Written decision to grant