JP4391011B2 - Fixing jig for construction steel material - Google Patents

Fixing jig for construction steel material Download PDF

Info

Publication number
JP4391011B2
JP4391011B2 JP2000399969A JP2000399969A JP4391011B2 JP 4391011 B2 JP4391011 B2 JP 4391011B2 JP 2000399969 A JP2000399969 A JP 2000399969A JP 2000399969 A JP2000399969 A JP 2000399969A JP 4391011 B2 JP4391011 B2 JP 4391011B2
Authority
JP
Japan
Prior art keywords
fixing
steel material
plate
construction
fixing jig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000399969A
Other languages
Japanese (ja)
Other versions
JP2002201612A (en
Inventor
浩樹 岡田
顕 田邊
芳樹 渡辺
文英 日向
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP2000399969A priority Critical patent/JP4391011B2/en
Publication of JP2002201612A publication Critical patent/JP2002201612A/en
Application granted granted Critical
Publication of JP4391011B2 publication Critical patent/JP4391011B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、外ケーブル張出架設工法によりプレストレストコンクリート橋を構築する際において、橋桁の落下を防止するために使用する架設鋼材定着用治具に関する。
【0002】
【従来の技術】
橋梁の架設方法として、橋脚を中心として両側へ釣り合いを保ちながら、所定長のブロックに分割した橋体コンクリートを打設し(以下、分割して構築された橋体の部分を「橋体ブロック」という)、所定の強度に達した後にプレストレスを導入するという作業を繰り返すことにより、順次、橋体ブロックを施工していく、張出架設工法が存在している。この張出架設工法において、プレストレスを導入する際に、大容量の外ケーブルを各ブロックに少数本ずつ(多くの場合は2本)、定着突起により定着する方法が採用される場合があり、この工法を特に、外ケーブル張出架設工法と称している。
【0003】
前記外ケーブル張出架設工法においては、少数本の外ケーブルを使用して、橋体にプレストレスを導入するため、1本の外ケーブルの破断または1箇所の定着突起の損傷は、架設時における橋梁の全体構造の安定性に重大なる影響を及ぼし、最悪の場合には落橋につながる恐れもある。そのため、外ケーブル張出架設工法を採用する場合には、フェールセーフシステムを備えておくことが一般的となっている。
ここで、外ケーブル張出架設工法におけるフェールセーフシステムとは、施工された最先端部の橋体ブロックと、当該最先端部の橋体ブロックに隣接する橋体ブロックとを、架設鋼材(フェールセーフ鋼材)により定着する作業を行うことにより、外ケーブルの破断時等において橋体の損傷などを防ぐことをいう。
【0004】
【発明が解決しようとする課題】
従来の外ケーブル張出架設工法におけるフェールセーフシステムにおいて、架設鋼材を橋体ブロックに定着するには、以下のような方法で行うことが代表的であった。
(1)第1の方法は、図6(a)に示すように、架設鋼材81を定着させる隣接する橋体ブロックB1’,B2’におけるコンクリート上床版80A,80B(以下、「上床版」という)に所定寸法の凹部82,83を2箇所形成し、当該両凹部82,83の壁面82a,83aを貫通する貫通孔80aを形成する。そして、当該貫通孔80aに架設鋼材81を挿通し、緊張力を導入した後に、アンカープレート84を介して定着用ナット85により、凹部82,83の壁面82a,83aに定着させる方法である(符号は、緊張用ナット86を示している)。
【0005】
(2)第2の方法は、図6(b)に示すように、架設鋼材91を定着させる隣接する橋体ブロックにおける上床版90の上面に鋼材定着ブロック92を設け、当該鋼材定着ブロック92の水平方向の挿通孔92aに架設鋼材91を挿通して、緊張力を導入した後に、アンカープレート93を介して定着用ナット94により定着させる方法である。前記鋼材定着ブロック92は、上床板90の下面まで貫通して設けられている鋼棒95の両端部に、プレート部材96を介してナット97を締結することにより、前記上床版90に固定されている。
【0006】
しかし、前記第1の方法では、上床版80A,80Bの上面に大寸法の凹部82,83を形成しなければならないため、架設中の橋体における応力状態が悪くなり構造物の品質に悪影響が生じてしまう可能性が高かった。また、架設鋼材81の撤去後に凹部82,83の穴埋め補修を行うことが必要であり、加えて、挿通孔80aの形成及び架設鋼材81の挿通作業を行わなければならないため、その作業が非常に繁雑であった。さらに、架設鋼材81の緊張に特殊なジャッキを使用しなければならず、施工費が増大することになっていた。
【0007】
また、前記第2の方法では、鋼材定着ブロック92を鋼棒95により固定しており、架設鋼材91の緊張力に抵抗させるために鋼棒95の摩擦抵抗を利用している構造であることから、所定の摩擦力を得るために大きな締め込み力が必要となるため、施工上の効率が悪かった。
【0008】
本発明は、前記の問題点を解決するためになされたものであり、構造物に悪影響を及ぼすことがなく、簡易な構造であり、かつ、施工が容易である架設鋼材定着用治具を提供することを目的とする。
【0009】
【課題を解決するための手段】
前記課題を解決するために、本発明の架設鋼材定着用治具は、コンクリート版の上面に付設され、少なくとも2体1組で架設鋼材の両端部を定着させるために用いられる架設鋼材定着用治具であって、底板と、前記底板に立設している前記架設鋼材の定着部と、前記定着部に前記架設鋼材を定着させる定着具(定着金具等)と、前記底板を前記コンクリート版に固定するためのピン部材及びボルト部材とから構成され、前記ピン部材は、前記コンクリート版に埋設されたピン受け管に挿入されていることを特徴としている。
また、前記定着部は、前記架設鋼材の長手方向と直行する向きに対向して並設されている定着板と、前記両定着板に接合されているリブ部材とから形成されているものであってもよい。
【0010】
ここで、「2体1組で架設鋼材の両端部を定着させるために用いられる」とは、架設鋼材定着用治具を架設鋼材の両端部に1体づつ設けることをいう。
【0011】
本発明の架設鋼材定着用治具において、定着部には、架設鋼材の緊張力に起因する水平力と曲げモーメントによる引抜力が作用することになるが、本発明によれば、定着部を備える底板をピン部材とボルト部材とで固定するため、定着部に作用する水平力に対してはピン部材により抵抗させ、引抜力に対してはボルト部材により抵抗させる構造とすることができる。そのため、簡易な構造により所定の強度を発揮させることができる。
【0012】
また、前記定着部は、平面視でコ字形状である前記架設鋼材の定着部材と、前記定着部材を両側から挟持する少なくとも2つのリブ部材とを備え、前記定着部材コ字形状である開口部の向きを変更可能となるように架設鋼材定着用治具が構成されているものであってもよい。
ここで、定着部材はピン接合により、前記少なくとも2つのリブ部材に支持(固定)される構造とすることが好適である。
【0013】
架設鋼材をコンクリート版の上面に定着する場合において、本発明の架設鋼材定着用治具は、架設鋼材の両端部に設けることになる。そのため、後記するように、架設鋼材定着用治具における架設鋼材の定着方向は、橋体ブロックの施工の進行に伴い、最初の場合とは逆側に変わることになる。
しかし、本発明によれば、定着部材コ字形状である開口部の向きが変更可能となるように架設鋼材定着用治具が構成されていることから、定着部材のみを回動させ、それ以外の要素は固定したままで動かすことなく、定着部材の向きを変更することが可能となることから、二方向から容易に架設鋼材の定着を行うことができる。
【0014】
【発明の実施の形態】
以下、本発明の実施の形態について、図面を参照して詳細に説明する。
なお、本実施形態の架設鋼材定着用治具1,2は、上床版Cの上面に付設され、2体1組でPC総ネジ棒鋼N(架設鋼材)の両端部を定着させるために用いられるが、それぞれの架設鋼材定着用治具1,2は同一構造であるため、一方のみについて説明を行う。
また、各実施形態の説明において、同一の構成要素に関しては同一の符号を付し、重複した説明は省略するものとする。
【0015】
[第1実施形態]
○架設鋼材定着用治具
図1に示すように、本発明の架設鋼材定着用治具1(第1実施形態)は、ベースプレート11(底板)と、前記ベースプレート11上に溶接されている定着部12と、当該定着部12にPC総ネジ棒鋼Nを定着させるための定着金具15(定着具)と、前記ベースプレート11を上床版Cに固定するためのせん断ピン18(高強度鋼材(ピン部材))及び高力ボルト19(ボルト部材)とを主要部として構成されている。
【0016】
ベースプレート11は矩形形状であり、4隅に高力ボルトの挿通孔11a(長孔)が穿設され、また、長辺の略中間部には、2つのせん断ピンの挿通孔11b(円孔)が短辺方向に対称に穿設されている。
このベースプレート11の略中央部には定着部12が溶接されている。この定着部12は、2枚のアンカープレート13(定着板)と、2枚の定着リブ14(リブ部材)とから形成されており、両部材13,14は、ともにベースプレート11に溶接されている。アンカープレート13はPC総ネジ棒鋼Nの長手方向と直行する向きに対向して並設されている。また、2枚のアンカープレート13の相対する各端部には、PC総ネジ棒鋼Nの長手方向と平行となる向きに各定着リブ14が溶接されており、定着部12は平面視で略ロ字形状に形成されている。なお、各アンカープレート13は、その中央部にPC総ネジ棒鋼Nの挿通孔13aが穿設されている。
【0017】
さらに、PC総ネジ棒鋼Nの定着時において、当該PC総ネジ棒鋼Nの先端側に位置することになるアンカープレート13の外面部には、PC総ネジ棒鋼Nを定着させるための定着金具15である、球面座金16と定着ナット17が設けられている。
【0018】
上床版Cには、せん断ピン18と上床版Cとの間で、円滑な応力伝達を行うことができるように、ピン受け管23(ガス管)が埋設されている。このピン受け管23は、上床版Cにおける被りコンクリートC1内に残らないように、当該被りコンクリートC1の下部位置(上床版Cの上面から50mm程度内側に入った部分)から設置されている。なお、本実施形態に示すように、必要に応じて、ピン受け管23の上面部から上床版Cの上面部に至る部位には、縁切材24を設けてもよい。
【0019】
また、上床版Cの所定位置には、高力ボルト19を挿入するための凹部21が形成されており、高力ボルト19と螺合するインサート22の開口部が前記凹部21の底面からわずかに突出するように設けられている。前記凹部21は、上床版Cの被りコンクリートC1の部分に設けられており、インサート22も前記ピン受け管23と同様に、被りコンクリートC1より下方に埋設されている。
なお、この凹部21は、高力ボルト19を挿入するために設けるものであるため、従来の方法に使用した凹部と比較して、非常に小さい寸法に形成すればよい。
また、上床版Cと架設鋼材定着用治具1のベースプレート11との間には、石膏などの均し材料25を敷設することにより不陸対策が施されている。
【0020】
架設鋼材定着用治具1のベースプレート11は、前記凹部21及び縁切材24に対応する位置に合わせて配置され、4本の高力ボルト19及び2本のせん断ピンに18より固定されている。
なお、架設鋼材定着用治具1は2体が一組であり、定着金具15が外側になるように対向して配置されるとともに、PC総ネジ棒鋼Nをアンカープレート13の挿通孔13aに挿通させ、緊張力を付与した後に、定着金具15によって、PC総ネジ棒鋼Nの先端部側におけるアンカープレート13に定着させることになる。
【0021】
○架設鋼材定着用治具を用いた外ケーブル張出架設工法
以下、前記架設鋼材定着用治具1を用いた外ケーブル張出架設工法を採用して、橋梁の架設を行う方法について簡単に説明する。
なお、以下の説明では、既に、橋脚Pの両側において、当該橋脚Pに隣接する橋体ブロック(第1橋体ブロックB1)が構築されている場合を想定している(図2(a)参照、符号K1は第1PC外ケーブルを示す)。また、橋体ブロックは、橋脚Pを中心として、バランスをとりながら、順次、その両側に架設されることになるが、左右の橋体ブロックの構築方法は同一であるため、便宜上、片側の橋体ブロックについてのみ説明を行う。
【0022】
まず、移動作業台車により型枠(ともに図示せず)を吊り下げ、第1橋体ブロックB1に隣接する第2橋体ブロックB2のコンクリート打設を行う(図2(b)参照)。コンクリートが所定の強度に達した後、前記架設鋼材定着治具1A,1Bを、第1橋体ブロックB1及び第2橋体ブロックB2のブロック先端部近傍の上面に固定し、PC総ネジ棒鋼Nを緊張させた後に、アンカープレート13に定着させる(図2(c)参照)。
そして、第2橋体ブロックB2に第2PC外ケーブルK2を定着させる(図2(d)参照)ことにより、第2橋体ブロックB2の施工を終了する。
続いて、移動式作業車を前進させて、前記と同様の作業を繰り返して行い、順次、第2橋体ブロックB2に隣接する第3橋体ブロックB3以降の橋体ブロックを施工していくことになる。
【0023】
なお、図3(a),(b)に示すように、第3橋体ブロックB3を施工する際には、資機材を有効に利用するために、第1橋体ブロックB1と第2橋体ブロックB2との間に架設されていたPC総ネジ棒鋼Nを取り外し、第2橋体ブロックB2と第3橋体ブロックB3との間に架設鋼材Nを架設することになる。その際、第2橋体ブロックB2に固定されている架設鋼材定着用治具1Bをそのままの状態にしておき、第1橋体ブロックB1に固定されていた架設鋼材定着用治具1Aを第3橋体ブロックB3に固定することになる。その場合には、第2橋体ブロックB2に固定されている架設鋼材定着用治具1BにおけるPC総ネジ棒鋼Nの定着方向は、図2に示す右側から、図3に示す左側に変わることになる。
そのため、本実施形態の架設鋼材定着用治具1では、相対する2枚のアンカープレート13を設け、それぞれのアンカープレート13に、その向きを変えた定着金具15を用いてPC総ネジ棒鋼Nを定着させることにより対応している。
【0024】
○作用効果
本発明の架設鋼材定着用治具1によれば、アンカープレート13に接合しているベースプレート11をせん断ピン18と高力ボルト19により上床版Cに固定し、アンカープレート13に作用する水平力に対してはせん断ピン18により抵抗させ、曲げモーメントに起因する引抜力に対しては高力ボルト19により抵抗させる構造とすることができる。従って、従来用いられていた、架設鋼材により作用する応力に対して、摩擦接合により抵抗する方法ではなく、高強度鋼材である高力ボルト19とせん断ピン18のせん断抵抗力を利用して抵抗する構造とすることができるため、所定の摩擦力を得るための大きな締め込み力が必要なく、非常に簡易な構造とすることができる。そのため、架設鋼材定着用治具1を軽量化することができ、施工性を格段に向上させることができる。
【0025】
また、上床版Cの上面に大きな凹部を設ける必要がないため、架設中における橋体の応力状態(上側引張)が悪化することもなく、橋体の耐久性に及ぼす影響を非常に小さくすることができる。なお、本発明の架設鋼材定着用治具1を使用する場合にも高力ボルト19を挿通するための凹部21が形成されるが、当該凹部21は微小寸法であるため、後埋め補修する際においても上床版Cの上側から対処することができ、また、特別な設備も必要ないため、その作業を容易に行うことができる。
さらに、PC総ネジ棒鋼Nを緊張させる作業を既存のジャッキを使用して行うことができる。
【0026】
[第2実施形態]
本発明の架設鋼材定着用治具2(第2実施形態)の最も大きな特長は、可変式アンカープレート31(架設鋼材の定着部材)を使用している点にある。
【0027】
図4に示すように、架設鋼材定着用治具2は、ベースプレート11’と、前記ベースプレート11’上に溶接されている定着部30と、当該定着部30にPC総ネジ棒鋼Nを定着させるための定着金具15と、前記ベースプレート11’を上床版Cに固定するための1本のせん断ピン18’及び4本の高力ボルト19とを主要部として構成されている。
【0028】
ベースプレート11’は矩形形状であり、4隅に高力ボルト19の挿通孔11a’(円孔)が穿設され、また、長辺の略中間部には、1箇所のせん断ピン18’の挿通孔11b’が穿設されている。
【0029】
前記定着部30は、1体の可動式アンカープレート31と、当該可動式アンカープレート31をピン41,42により両側から挟持する2体の定着リブ35とから形成されている。可動式アンカープレート31は、基板32とその両側の同一形状の側板33とを備え、基板32と対向する向きに開口部34が形成されており、平面視でコ字形状を呈している。前記相対する側板33には、中央部近傍の上下位置と、当該上下位置の貫通孔(以下、それぞれ「上部貫通孔33a」及び「下部貫通孔33b」という)の中間高さであり、基板32と反対側に突出している貫通孔(以下、「先端貫通孔33c」という)の3箇所に貫通孔33a〜33cが穿設されており、前記3箇所の貫通孔33a〜33cを結線した三角形は先端貫通孔33cを頂点とした二等辺三角形になっている。また、可動式アンカープレート31のコ字形状の開口部34と対向する基板32には、上下にPC総ネジ棒鋼Nを挿通するための貫通孔32aが穿設されている。
【0030】
前記定着リブ35は、略山形形状であり、その下面がベースプレート11’に溶接されている。定着リブ35においても、3箇所の貫通孔35a,35b,35cが穿設されており、当該3箇所の貫通孔35a〜35cを結線した三角形は上部貫通孔35aを頂点とした二等辺三角形になっている。この二等辺三角形は、前記可動式アンカープレート31の側板33における二等辺三角形と同一の三角形である。
【0031】
前記可動式アンカープレート31の基板32は、2枚の定着リブ35の間隔と略同一であり、可動式アンカープレート31は2枚の定着リブ35の間に2本のピン41,42により支持されている。2本のピン41,42は、可動式アンカープレート31の側板における貫通孔(図4における下部貫通孔33bと先端貫通孔33c)と、定着リブ35の貫通孔(図4における左側貫通孔35bと上側貫通孔35a)が重なり合うように位置させた状態で挿設されている。
なお、第1実施形態の場合と異なり、本実施形態では、可動式アンカープレート31は、ベースプレート11’に溶接されていない。
【0032】
ここで、本実施形態の架設鋼材定着用治具2では、前記2本のピン41,42のうち下方のピン(以下、「下方ピン41」という)を抜脱し、中央部のピン(以下、「中央ピン42」という)を残した状態で、中央ピン42を中心として、可動式アンカープレート31を180度回転させることにより、その向きを反転させ、開口部34の向きを変更することができるようになっている(図5参照)。
なお、可動式アンカープレート31を回転させた状態で使用する場合には、可変式アンカープレート31の側板33における貫通孔(図5における下部の貫通孔33a)と、定着リブ35の貫通孔(図5における右側貫通孔35c)とに、抜脱した下方ピン41を挿通することにより(中央ピン42はそのままの状態)、可変式アンカープレート31を定着リブ35により支持固定し、図4と比較して反対向きになった基板32の貫通孔32aにPC総ネジ棒鋼Nを挿通して定着させることになる。
【0033】
また、上床版Cには、高力ボルト16を挿入するためのカプラ43(長ナット)が埋設されており、ベースプレート11’の上面から高力ボルト19を螺合することにより、上床版Cに架設鋼材定着用治具2が固定されている。なお、カプラ43の下面には、プレート部材44を介して他の高力ボルト45を設け、上床版Cを構成するコンクリート中に埋設することにより、架設鋼材定着用治具2を強固に固定している(符号46は、上床版を補修するための微小寸法の凹部を示している)。
【0034】
従って、第2実施形態の架設鋼材定着用治具2によっても、前記と同様の作用効果が得られるとともに、可変式アンカープレート31における開口部34の向きを変更可能であることから、可変式アンカープレート31のみを回動させ、それ以外の要素は固定したままで動かすことなく、2方向からPC総ネジ棒鋼Nの定着を行うことができる。
【0035】
以上、本発明について、好適な実施形態についての一例を説明したが、本発明は当該実施形態に限られず、本発明の趣旨を逸脱しない範囲で適宜設計変更が可能である。
なお、架設鋼材はPC総ネジ棒鋼に限られるものではない。また、定着具についても、架設鋼材を確実に定着できるものであればよく、球面座金と定着ナット等に限られるものではない。さらに、ボルト部材及びピン部材の本数等についても適宜定めうるものである。
【0036】
【発明の効果】
本発明によれば、構造物に悪影響を及ぼすことがなく、簡易な構造であり、かつ、施工が容易である架設鋼材定着用治具を提供することが可能となる。
【図面の簡単な説明】
【図1】本発明の架設鋼材定着用治具(第1実施形態)を示す図であり、(a)は平面図、(b)は(a)におけるW−W断面図、(c)は(a)におけるX−X断面図である。
【図2】(a)〜(d)は、本発明の架設鋼材定着用治具を用いた外ケーブル張出架設工法の施工手順を示す側面図である。
【図3】(a)、(b)は、本発明の架設鋼材定着用治具を用いた外ケーブル張出架設工法の施工手順を示す側面図である。
【図4】本発明の架設鋼材定着用治具(第2実施形態)を示す図であり、(a)は平面図、(b)は(a)におけるY−Y断面図、(c)は(a)におけるZ−Z断面図である。
【図5】図4(b)における可変式アンカープレートを180度回転させた場合を示す図である。
【図6】(a)、(b)は、従来における橋体ブロックに架設鋼材を定着する方法を示す側面図である。
【符号の説明】
C 上床版(コンクリート上床版)
C1 被りコンクリート
N PC総ネジ棒鋼(架設鋼材)
1,2 架設鋼材定着用治具
11,11’ ベースプレート
12 定着部
13 アンカープレート(定着板)
14 定着リブ(リブ部材)
15 定着金具
16 球面座金
17 定着ナット
18,18’ せん断ピン(ピン部材)
19 高力ボルト(ボルト部材)
30 定着部
31 可動式アンカープレート
32 基板
33 側板
34 開口部
35 定着リブ
41,42 ピン
[0001]
BACKGROUND OF THE INVENTION
TECHNICAL FIELD The present invention relates to a construction steel material fixing jig used for preventing a bridge girder from dropping when a prestressed concrete bridge is constructed by an external cable overhanging construction method.
[0002]
[Prior art]
As a method of erection of the bridge, the bridge concrete is divided into blocks of a predetermined length while maintaining balance on both sides around the pier (hereinafter referred to as “bridge block”. There is an overhanging construction method in which bridge blocks are sequentially constructed by repeating the work of introducing prestress after reaching a predetermined strength. In this overhang construction method, when prestress is introduced, a method of fixing a small number of large-capacity external cables to each block (in many cases, two) and fixing by fixing protrusions may be adopted. This construction method is particularly referred to as an outer cable extension construction method.
[0003]
In the external cable overhang construction method, a small number of external cables are used to introduce prestress into the bridge body, so that one external cable breaks or one fixing protrusion is damaged at the time of installation. It has a serious impact on the stability of the overall structure of the bridge, and in the worst case it can lead to a fallen bridge. Therefore, when adopting the external cable overhang construction method, it is common to provide a fail-safe system.
Here, the fail-safe system in the external cable overhang construction method is the construction of the most advanced bridge body block and the bridge block adjacent to the most advanced bridge block. This refers to preventing damage to the bridge body when the outer cable breaks, etc.
[0004]
[Problems to be solved by the invention]
In the conventional fail-safe system in the external cable overhang construction method, in order to fix the construction steel material on the bridge block, the following method is typically used.
(1) In the first method, as shown in FIG. 6 (a), concrete upper floor slabs 80A and 80B (hereinafter referred to as "upper floor slabs") in adjacent bridge body blocks B1 'and B2' for fixing the construction steel material 81 are used. ), Two concave portions 82 and 83 having predetermined dimensions are formed, and through holes 80a penetrating the wall surfaces 82a and 83a of the concave portions 82 and 83 are formed. Then, the construction steel material 81 is inserted into the through-hole 80a, a tension force is introduced, and then fixed to the wall surfaces 82a and 83a of the recesses 82 and 83 by the fixing nut 85 via the anchor plate 84 (reference numeral Shows a tensioning nut 86).
[0005]
(2) In the second method, as shown in FIG. 6B, a steel material fixing block 92 is provided on the upper surface of the upper floor slab 90 in an adjacent bridge block that fixes the construction steel material 91, and the steel material fixing block 92 In this method, the installation steel material 91 is inserted into the horizontal insertion hole 92a to introduce a tension force, and then fixed by the fixing nut 94 via the anchor plate 93. The steel material fixing block 92 is fixed to the upper floor slab 90 by fastening nuts 97 to both ends of a steel bar 95 provided penetrating to the lower surface of the upper floor plate 90 via plate members 96. Yes.
[0006]
However, in the first method, since the large-sized concave portions 82 and 83 must be formed on the upper surfaces of the upper floor slabs 80A and 80B, the stress state in the bridge body during erection is worsened and the quality of the structure is adversely affected. It was highly likely that In addition, it is necessary to perform hole filling repair of the recesses 82 and 83 after the removal of the construction steel material 81, and in addition, since the insertion hole 80 a and the insertion work of the construction steel material 81 must be performed, the work is very It was complicated. Furthermore, a special jack has to be used for the tension of the erected steel material 81, which increases the construction cost.
[0007]
In the second method, the steel material fixing block 92 is fixed by the steel rod 95 and the frictional resistance of the steel rod 95 is used to resist the tension of the installed steel material 91. Since a large tightening force is required to obtain a predetermined frictional force, the construction efficiency is poor.
[0008]
The present invention has been made to solve the above-described problems, and provides a construction steel fixing jig that has a simple structure and that is easy to construct without adversely affecting the structure. The purpose is to do.
[0009]
[Means for Solving the Problems]
In order to solve the above-described problems, the installation steel material fixing jig of the present invention is attached to the upper surface of a concrete plate and used to fix both ends of the installation steel material in one set of at least two bodies. A fixing plate (fixing bracket or the like) for fixing the installation steel material to the fixing portion, a bottom plate, a fixing portion for the installation steel material standing on the bottom plate, and the bottom plate to the concrete plate is composed of a pin member and a bolt member for securing the pin member is characterized that you have been inserted into the pin receiving pipes embedded in the concrete panel.
In addition, the fixing portion is formed of a fixing plate that is arranged in parallel so as to face the longitudinal direction of the erected steel material, and a rib member that is joined to both the fixing plates. May be.
[0010]
Here, “used to fix both ends of the installed steel material in one set of two bodies” means that one jig for fixing the installed steel material is provided at each end of the installed steel material.
[0011]
In the installation steel material fixing jig of the present invention, a horizontal force resulting from the tension force of the installation steel material and a pulling force due to a bending moment act on the fixing unit. Since the bottom plate is fixed by the pin member and the bolt member, the horizontal force acting on the fixing portion is resisted by the pin member, and the pulling force is resisted by the bolt member. Therefore, a predetermined strength can be exhibited with a simple structure.
[0012]
Further, the fixing unit includes a fixing member of the erection steel is U-shaped in plan view, and at least two rib members sandwiching the fixing member from both sides, a U-shape of said fixing member aperture The construction steel material fixing jig may be configured so that the direction of the portion can be changed.
Here, the fixing member is preferably supported (fixed) by the at least two rib members by pin bonding.
[0013]
When fixing the construction steel material on the upper surface of the concrete plate, the construction steel material fixing jig of the present invention is provided at both ends of the construction steel material. Therefore, as will be described later, the fixing direction of the construction steel material in the construction steel material fixing jig is changed to the opposite side from the first case as the construction of the bridge block is progressed.
However, according to the present invention, since the installation steel material fixing jig is configured so that the orientation of the U-shaped opening of the fixing member can be changed, only the fixing member is rotated, Since it is possible to change the direction of the fixing member without moving the elements other than the fixed member, it is possible to easily fix the construction steel material from two directions.
[0014]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
The installed steel material fixing jigs 1 and 2 of this embodiment are attached to the upper surface of the upper floor slab C, and are used to fix both ends of the PC total threaded steel bar N (installed steel material) in one set. However, since the construction steel material fixing jigs 1 and 2 have the same structure, only one of them will be described.
In the description of each embodiment, the same constituent elements are denoted by the same reference numerals, and redundant descriptions are omitted.
[0015]
[First Embodiment]
As shown in FIG. 1, an installation steel material fixing jig 1 (first embodiment) of the present invention includes a base plate 11 (bottom plate) and a fixing portion welded onto the base plate 11. 12, a fixing bracket 15 (fixing tool) for fixing the PC total screw bar steel N to the fixing portion 12, and a shear pin 18 (high-strength steel (pin member)) for fixing the base plate 11 to the upper floor slab C ) And high-strength bolts 19 (bolt members).
[0016]
The base plate 11 has a rectangular shape, and is provided with high-strength bolt insertion holes 11a (long holes) at four corners, and two shear pin insertion holes 11b (circular holes) in the middle part of the long side. Are drilled symmetrically in the short side direction.
A fixing portion 12 is welded to a substantially central portion of the base plate 11. The fixing unit 12 is formed of two anchor plates 13 (fixing plates) and two fixing ribs 14 (rib members), and both the members 13 and 14 are welded to the base plate 11. . The anchor plate 13 is arranged in parallel so as to face in the direction orthogonal to the longitudinal direction of the PC total threaded steel bar N. In addition, fixing ribs 14 are welded to opposite end portions of the two anchor plates 13 in a direction parallel to the longitudinal direction of the PC total threaded steel bar N, and the fixing portion 12 is substantially lower in plan view. It is formed in a letter shape. Each anchor plate 13 is provided with an insertion hole 13a for the PC total threaded steel bar N at the center thereof.
[0017]
Further, at the time of fixing the PC total threaded bar steel N, a fixing bracket 15 for fixing the PC total threaded bar steel N is fixed to the outer surface portion of the anchor plate 13 which is positioned on the tip side of the PC total threaded bar steel N. A spherical washer 16 and a fixing nut 17 are provided.
[0018]
In the upper floor slab C, a pin receiving pipe 23 (gas pipe) is embedded so that smooth stress transmission can be performed between the shear pin 18 and the upper floor slab C. The pin receiving tube 23 is installed from the lower position of the covering concrete C1 (the portion entering about 50 mm from the upper surface of the upper floor slab C) so as not to remain in the covering concrete C1 in the upper floor slab C. In addition, as shown in this embodiment, you may provide the edge cutting material 24 in the site | part from the upper surface part of the pin receiving pipe 23 to the upper surface part of the upper floor slab C as needed.
[0019]
Further, a concave portion 21 for inserting the high strength bolt 19 is formed at a predetermined position of the upper floor slab C, and an opening portion of the insert 22 screwed with the high strength bolt 19 is slightly from the bottom surface of the concave portion 21. It is provided to protrude. The concave portion 21 is provided in the covered concrete C1 portion of the upper floor slab C, and the insert 22 is also embedded below the covered concrete C1 in the same manner as the pin receiving tube 23.
In addition, since this recessed part 21 is provided in order to insert the high strength volt | bolt 19, it should just be formed in a very small dimension compared with the recessed part used for the conventional method.
Further, a measure against unevenness is taken by laying a leveling material 25 such as gypsum between the upper floor slab C and the base plate 11 of the installation steel material fixing jig 1.
[0020]
The base plate 11 of the erection steel material fixing jig 1 is arranged at a position corresponding to the concave portion 21 and the edge cutting material 24, and is fixed by 18 to four high-strength bolts 19 and two shear pins. .
In addition, the construction steel material fixing jig 1 is a set of two, and is disposed so as to face the fixing bracket 15 on the outside, and the PC total threaded steel bar N is inserted into the insertion hole 13a of the anchor plate 13. Then, after applying the tension force, the fixing metal fitting 15 is fixed to the anchor plate 13 on the front end side of the PC total threaded steel bar N.
[0021]
○ External cable overhanging construction method using a construction steel material fixing jig Below, a brief description of a method for erection of a bridge by adopting the external cable overhang construction method using the construction steel material fixing jig 1 will be given. To do.
In the following description, it is assumed that a bridge block (first bridge block B1) adjacent to the pier P has already been constructed on both sides of the pier P (see FIG. 2A). , K1 indicates a first PC external cable). In addition, the bridge block is built on both sides of the bridge pier P in order while maintaining balance, but the construction method of the left and right bridge blocks is the same. Only the body block will be described.
[0022]
First, a formwork (both not shown) is suspended by a moving work carriage, and concrete is placed in the second bridge block B2 adjacent to the first bridge block B1 (see FIG. 2B). After the concrete reaches a predetermined strength, the construction steel material fixing jigs 1A and 1B are fixed to the upper surfaces of the first bridge body block B1 and the second bridge body block B2 in the vicinity of the block front end portions, and the PC total screw bar steel N Then, the anchor plate 13 is fixed (see FIG. 2C).
Then, by fixing the second PC external cable K2 to the second bridge block B2 (see FIG. 2D), the construction of the second bridge block B2 is finished.
Subsequently, the mobile work vehicle is advanced and the same operation as described above is repeated, and the bridge body blocks after the third bridge body block B3 adjacent to the second bridge body block B2 are sequentially constructed. become.
[0023]
As shown in FIGS. 3A and 3B, when the third bridge block B3 is constructed, the first bridge block B1 and the second bridge block are used in order to effectively use materials and equipment. The PC total threaded steel bar N installed between the block B2 is removed, and the installation steel material N is installed between the second bridge block B2 and the third bridge block B3. At that time, the construction steel material fixing jig 1B fixed to the second bridge block B2 is left as it is, and the construction steel material fixing jig 1A fixed to the first bridge block B1 is used as the third steel structure fixing jig 1A. It will be fixed to the bridge block B3. In that case, the fixing direction of the PC total screw bar N in the installation steel material fixing jig 1B fixed to the second bridge block B2 is changed from the right side shown in FIG. 2 to the left side shown in FIG. Become.
Therefore, in the construction steel material fixing jig 1 of the present embodiment, two opposing anchor plates 13 are provided, and the PC total threaded steel bar N is attached to each anchor plate 13 using the fixing metal fitting 15 whose direction is changed. It is supported by fixing.
[0024]
Effect According to the construction steel material fixing jig 1 of the present invention, the base plate 11 joined to the anchor plate 13 is fixed to the upper floor slab C by the shear pin 18 and the high strength bolt 19 and acts on the anchor plate 13. A structure in which a horizontal force is resisted by a shear pin 18 and a pulling force caused by a bending moment is resisted by a high-strength bolt 19 can be employed. Therefore, it resists by using the shear resistance force of the high-strength bolt 19 and the shear pin 18 which are high-strength steel materials, instead of the conventional method of resisting the stress acting by the installed steel material by friction bonding. Since the structure can be obtained, a large tightening force for obtaining a predetermined frictional force is not required, and a very simple structure can be obtained. Therefore, the construction steel material fixing jig 1 can be reduced in weight, and the workability can be remarkably improved.
[0025]
In addition, since it is not necessary to provide a large concave portion on the upper surface of the upper floor slab C, the stress state (upper tension) of the bridge body during erection is not deteriorated, and the influence on the durability of the bridge body is extremely reduced. Can do. In addition, although the recessed part 21 for inserting the high strength bolt 19 is formed also when using the construction steel material fixing jig 1 of the present invention, the recessed part 21 has a very small size, and therefore, when the backfilling is repaired. Can be dealt with from the upper side of the upper floor slab C, and since no special equipment is required, the operation can be easily performed.
Furthermore, the operation | work which tensions the PC total screw rod steel N can be performed using the existing jack.
[0026]
[Second Embodiment]
The greatest feature of the installation steel material fixing jig 2 of the present invention (second embodiment) is that a variable anchor plate 31 (an installation member for installation steel material) is used.
[0027]
As shown in FIG. 4, the installation steel material fixing jig 2 fixes a base plate 11 ′, a fixing portion 30 welded on the base plate 11 ′, and a PC total screw bar N to the fixing portion 30. The fixing bracket 15, one shear pin 18 ′ for fixing the base plate 11 ′ to the upper floor slab C, and four high-strength bolts 19 are configured as main parts.
[0028]
The base plate 11 ′ has a rectangular shape, and is provided with insertion holes 11a ′ (circular holes) for the high-strength bolts 19 at the four corners, and the insertion of one shear pin 18 ′ at a substantially middle portion of the long side. A hole 11b 'is formed.
[0029]
The fixing unit 30 includes a single movable anchor plate 31 and two fixing ribs 35 that sandwich the movable anchor plate 31 from both sides with pins 41 and 42. The movable anchor plate 31 includes a substrate 32 and side plates 33 having the same shape on both sides thereof, and an opening 34 is formed in a direction facing the substrate 32, and has a U shape in plan view. The opposing side plates 33 have an intermediate position between the vertical position in the vicinity of the central portion and through-holes in the vertical position (hereinafter referred to as “upper through-holes 33 a” and “lower through-holes 33 b”, respectively). Through-holes 33a to 33c are formed at three locations of through-holes projecting on the opposite side (hereinafter referred to as “tip through-holes 33c”), and the triangles connecting the three through-holes 33a to 33c are: It is an isosceles triangle having the tip through-hole 33c as a vertex. In addition, a through-hole 32a through which the PC total screw bar N is inserted vertically is formed in the substrate 32 facing the U-shaped opening 34 of the movable anchor plate 31.
[0030]
The fixing rib 35 has a substantially chevron shape, and the lower surface thereof is welded to the base plate 11 ′. Also in the fixing rib 35, three through holes 35a, 35b, and 35c are formed, and a triangle connecting the three through holes 35a to 35c is an isosceles triangle having the upper through hole 35a as a vertex. ing. This isosceles triangle is the same triangle as the isosceles triangle in the side plate 33 of the movable anchor plate 31.
[0031]
The substrate 32 of the movable anchor plate 31 is substantially the same as the interval between the two fixing ribs 35, and the movable anchor plate 31 is supported by the two pins 41 and 42 between the two fixing ribs 35. ing. The two pins 41 and 42 are formed through a through hole in the side plate of the movable anchor plate 31 (a lower through hole 33b and a front end through hole 33c in FIG. 4) and a through hole in the fixing rib 35 (a left through hole 35b in FIG. 4). The upper through hole 35a) is inserted in a state where it is positioned so as to overlap.
Unlike the case of the first embodiment, in this embodiment, the movable anchor plate 31 is not welded to the base plate 11 ′.
[0032]
Here, in the installation steel material fixing jig 2 of the present embodiment, a lower pin (hereinafter referred to as “lower pin 41”) is removed from the two pins 41 and 42, and a central pin (hereinafter referred to as “pin”) is removed. With the center pin 42 left), the movable anchor plate 31 is rotated 180 degrees around the center pin 42, thereby reversing the direction and changing the direction of the opening 34. (See FIG. 5).
When the movable anchor plate 31 is used in a rotated state, the through hole in the side plate 33 of the variable anchor plate 31 (the lower through hole 33a in FIG. 5) and the through hole of the fixing rib 35 (see FIG. 5 is inserted into the right through hole 35c) (the center pin 42 is left as it is), and the variable anchor plate 31 is supported and fixed by the fixing rib 35. Compared with FIG. Then, the PC total threaded steel bar N is inserted into the through hole 32a of the substrate 32 which is in the opposite direction and fixed.
[0033]
In addition, a coupler 43 (long nut) for inserting the high-strength bolt 16 is embedded in the upper floor plate C. By screwing the high-strength bolt 19 from the upper surface of the base plate 11 ′, the upper floor plate C is attached. The construction steel material fixing jig 2 is fixed. In addition, another high-strength bolt 45 is provided on the lower surface of the coupler 43 via a plate member 44, and is embedded in the concrete constituting the upper floor slab C, thereby firmly fixing the construction steel material fixing jig 2. (Reference numeral 46 indicates a recess having a small dimension for repairing the upper floor slab).
[0034]
Therefore, the construction steel material fixing jig 2 of the second embodiment can obtain the same effect as described above, and the direction of the opening 34 in the variable anchor plate 31 can be changed. It is possible to fix the PC total screw bar steel N from two directions without rotating only the plate 31 and moving the other elements while being fixed.
[0035]
As mentioned above, although an example about a suitable embodiment was explained about the present invention, the present invention is not restricted to the embodiment concerned, and a design change is possible suitably in the range which does not deviate from the meaning of the present invention.
In addition, construction steel materials are not restricted to PC total screw bar steel. Also, the fixing tool is not limited to a spherical washer and a fixing nut as long as it can reliably fix the construction steel material. Furthermore, the number of bolt members and pin members can be determined as appropriate.
[0036]
【The invention's effect】
ADVANTAGE OF THE INVENTION According to this invention, it becomes possible to provide the construction steel material fixing jig which has a simple structure and is easy to construct without adversely affecting the structure.
[Brief description of the drawings]
FIG. 1 is a view showing a construction steel material fixing jig (first embodiment) according to the present invention, in which (a) is a plan view, (b) is a WW sectional view in (a), and (c) is a cross-sectional view. It is XX sectional drawing in (a).
FIGS. 2A to 2D are side views showing a construction procedure of an external cable overhanging construction method using a construction steel material fixing jig of the present invention.
FIGS. 3A and 3B are side views showing a construction procedure of an external cable overhanging construction method using the construction steel material fixing jig of the present invention. FIGS.
FIGS. 4A and 4B are diagrams showing a construction steel material fixing jig (second embodiment) according to the present invention, wherein FIG. 4A is a plan view, FIG. 4B is a cross-sectional view along line YY in FIG. It is ZZ sectional drawing in (a).
5 is a view showing a case where the variable anchor plate in FIG. 4B is rotated by 180 degrees. FIG.
FIGS. 6A and 6B are side views showing a conventional method for fixing a construction steel material to a bridge body block. FIGS.
[Explanation of symbols]
C Upper floor slab (concrete upper floor slab)
C1 Covered concrete N PC thread steel bar (construction steel)
1, 2 Installation steel material fixing jig 11, 11 'Base plate 12 Fixing part 13 Anchor plate (fixing plate)
14 Fixing rib (rib member)
15 Fixing bracket 16 Spherical washer 17 Fixing nut 18, 18 'Shear pin (pin member)
19 High strength bolt (bolt member)
30 Fixing part 31 Movable anchor plate 32 Substrate 33 Side plate 34 Opening part 35 Fixing rib 41, 42 Pin

Claims (3)

コンクリート版の上面に付設され、少なくとも2体1組で架設鋼材の両端部を定着させるために用いられる架設鋼材定着用治具であって、
底板と、前記底板に立設している前記架設鋼材の定着部と、前記定着部に前記架設鋼材を定着させる定着具と、前記底板を前記コンクリート版に固定するためのピン部材及びボルト部材とから構成され
前記ピン部材は、前記コンクリート版に埋設されたピン受け管に挿入されていることを特徴とする架設鋼材定着用治具。
An installation steel material fixing jig attached to the upper surface of a concrete plate and used to fix both ends of the installation steel material in one set of at least two bodies,
A bottom plate, a fixing portion of the installation steel material standing on the bottom plate, a fixing tool for fixing the installation steel material to the fixing portion, a pin member and a bolt member for fixing the bottom plate to the concrete plate, Consisting of
It said pin member, erection steel fixing jig characterized that you have been inserted into the pin receiving pipes embedded in the concrete panel.
前記定着部は、前記架設鋼材の長手方向と直行する向きに対向して並設されている定着板と、前記両定着板に接合されているリブ部材とから形成されていることを特徴とする請求項1に記載の架設鋼材定着用治具。  The fixing portion is formed of a fixing plate that is arranged in parallel to face the longitudinal direction of the erected steel material, and a rib member that is joined to the fixing plates. The installation steel material fixing jig according to claim 1. コンクリート版の上面に付設され、少なくとも2体1組で架設鋼材の両端部を定着させるために用いられる架設鋼材定着用治具であって、
底板と、前記底板に立設している前記架設鋼材の定着部と、前記定着部に前記架設鋼材を定着させる定着具と、前記底板を前記コンクリート版に固定するためのピン部材及びボルト部材とから構成され、
前記定着部は、平面視でコ字形状である前記架設鋼材の定着部材と、前記定着部材を両側から挟持する少なくとも2つのリブ部材とを備え、
前記定着部材コ字形状である開口部の向きを変更可能となるように構成されていることを特徴とする架設鋼材定着用治具。
An installation steel material fixing jig attached to the upper surface of a concrete plate and used to fix both ends of the installation steel material in one set of at least two bodies,
A bottom plate, a fixing portion of the installation steel material standing on the bottom plate, a fixing tool for fixing the installation steel material to the fixing portion, a pin member and a bolt member for fixing the bottom plate to the concrete plate, Consisting of
The fixing unit includes a fixing member of the construction steel material that is U-shaped in plan view, and at least two rib members that sandwich the fixing member from both sides,
U-shaped in a rack設鋼member fixing jig you, characterized in that it is configured so that the orientation of the opening becomes possible change of the fixing member.
JP2000399969A 2000-12-28 2000-12-28 Fixing jig for construction steel material Expired - Fee Related JP4391011B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000399969A JP4391011B2 (en) 2000-12-28 2000-12-28 Fixing jig for construction steel material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000399969A JP4391011B2 (en) 2000-12-28 2000-12-28 Fixing jig for construction steel material

Publications (2)

Publication Number Publication Date
JP2002201612A JP2002201612A (en) 2002-07-19
JP4391011B2 true JP4391011B2 (en) 2009-12-24

Family

ID=18864640

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000399969A Expired - Fee Related JP4391011B2 (en) 2000-12-28 2000-12-28 Fixing jig for construction steel material

Country Status (1)

Country Link
JP (1) JP4391011B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103572701A (en) * 2013-10-08 2014-02-12 中铁十八局集团有限公司 Buckling anchor system combined rock anchor
KR101752224B1 (en) * 2014-06-16 2017-06-30 삼성물산 주식회사 Form traveler and construction method for fcm bridge using the same
CN111706073A (en) * 2020-06-29 2020-09-25 天津洪晟基业建材有限公司 Novel one-way ribbed template and installation method

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001262513A (en) * 2000-03-17 2001-09-26 Nippon Steel Corp Cable stayed bridge having composite synthetic steel tube beam material with slab and method of installing the beam material
CN100335728C (en) * 2006-03-30 2007-09-05 建研科技股份有限公司 Steel bar anchoring device and construction method thereof
KR101268375B1 (en) * 2010-12-22 2013-05-28 진승영 Construction method for bridge using temporary binder
KR101393497B1 (en) * 2012-03-09 2014-05-13 이창남 Step-shaped Wire Fixing Block
CN103374883B (en) * 2012-04-13 2016-05-25 中铁十局集团第五工程有限公司 A kind of Hanging Basket walking draw-gear
CN103215894B (en) * 2013-04-26 2015-10-28 中铁第一勘察设计院集团有限公司 Portable interim prestressed stretch-draw anchor block
CN108677729A (en) * 2018-06-19 2018-10-19 中国铁路总公司 A kind of interim prestressing apparatus for precast segment spliced girder
CN111779170B (en) * 2020-06-24 2021-12-10 天津洪晟基业建材有限公司 Dense rib support-free unit template device and installation method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103572701A (en) * 2013-10-08 2014-02-12 中铁十八局集团有限公司 Buckling anchor system combined rock anchor
KR101752224B1 (en) * 2014-06-16 2017-06-30 삼성물산 주식회사 Form traveler and construction method for fcm bridge using the same
CN111706073A (en) * 2020-06-29 2020-09-25 天津洪晟基业建材有限公司 Novel one-way ribbed template and installation method

Also Published As

Publication number Publication date
JP2002201612A (en) 2002-07-19

Similar Documents

Publication Publication Date Title
JP4391011B2 (en) Fixing jig for construction steel material
US11136777B2 (en) Seismic performance improvement of FRP-RC structures
JP2001303666A (en) Joint section structure between reinforced concrete column and steel frame beam
JP2011007018A (en) Joining device for reinforced concrete column and steel-frame beam, and joint structure of reinforced concrete column and steel-frame beam
JP4780457B2 (en) Seismic reinforcement structure for pile foundation structure and seismic reinforcement method
JP2008308872A (en) U-rib steel floor slab
JP2004324265A (en) Bridge fall preventing device, movement limiting device and bridge fall preventing method
Taghdi Seismic retrofit of low-rise masonry and concrete walls by steel strips.
JP6335489B2 (en) Movement limiter and construction method of movement limiter
KR101770988B1 (en) Reforcing panel for concrete structure and reinforcing method using the same
CN113109146B (en) Design method for upgrading plane loading frame system into space loading system
JP2007239270A (en) Pc box girder bridge
JP2019007134A (en) Reinforcing method of existing footing
KR100370177B1 (en) Compression bracket for external prestressing reinforcement of girder
Tawadrous Design of shear pocket connections in full-depth precast concrete bridge deck systems
JPH0542553B2 (en)
JP2002332645A (en) Foundation structure of rail for ground-traveling crane and laying method for foundation
KR200268160Y1 (en) Device for anchoring outer steel wire for reinforcing concrete structures
CN211340846U (en) Arched waist rail
JP5664000B2 (en) Method for improving reinforcement performance of floor slab and structure for improving reinforcement performance
KR102456492B1 (en) Damping fixture for seismic reinforcing of building
JP2005299150A (en) Joint metal fitting for column and beam of wooden building, column base supporting fitting, and method for evaluating strength of wooden building by using column base supporting fitting
Aoki Hybrid masonry connector plate and headed stud small-scale wall testing
KR100597859B1 (en) Performance Improvement Device of Continuous Bridges Using External Prestressing of V (V) Shaped Fixture and Its Construction Method
KR200274925Y1 (en) Apparatus for anchoring reinforcing steel material

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20070730

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20090618

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20090623

RD13 Notification of appointment of power of sub attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7433

Effective date: 20090805

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20090817

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A821

Effective date: 20090807

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090929

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20091007

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121016

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 4391011

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151016

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees