JP4185835B2 - 停電作業計画システム、停電作業計画方法、及びプログラム - Google Patents
停電作業計画システム、停電作業計画方法、及びプログラム Download PDFInfo
- Publication number
- JP4185835B2 JP4185835B2 JP2003310706A JP2003310706A JP4185835B2 JP 4185835 B2 JP4185835 B2 JP 4185835B2 JP 2003310706 A JP2003310706 A JP 2003310706A JP 2003310706 A JP2003310706 A JP 2003310706A JP 4185835 B2 JP4185835 B2 JP 4185835B2
- Authority
- JP
- Japan
- Prior art keywords
- power
- work
- outage
- candidate
- supply reliability
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/70—Smart grids as climate change mitigation technology in the energy generation sector
Description
前記運用制約としては、例えば、作業の安全を考慮した潮流量の制限や供給力の確保の観点から課されるものがある。なお、前記作業系統候補が前記運用制約を満たしているかどうかの判断を行う処理は、判断される制約ごとに分割することとしてもよい。
前記常時系統とは、通常の運用状態における電力系統である。常時系統では、通常の安定した電力供給を維持するのに必要となる電力設備のみが機能している。一般に、停電作業計画において構成可能な全ての作業系統候補を生成すると計算量が膨大となるが、作業系統は常時系統周辺に存在することが経験的に知られており、常時系統周辺の作業系統のみを前記作業系統候補として生成するようにすることで、最適化の精度を低下させることなく計算量を減らすことができる。
ここで複数の時点のそれぞれにおける電力設備の電力消費量とは、例えば、後述するバランス断面である。同じ作業系統候補であっても、発電機の起動停止状態や負荷の違いによって供給信頼度が異なることがあるので、このようにバランス断面ごとに供給信頼度を求めることにより日程が決定され、より最適な停電作業計画を立案することができる。
このようにすることで、作業期間内に収まるように、最適な作業系統候補を選択して最適な作業計画を立てることができる。
このように前記作業系統候補が前記運用制約を満たしているかどうかの判断を行う処理が前記運用制約に対応する処理ごとに分割されて記述されているプログラムを実行することにより実現されるようにすることで、運用箇所によって異なり様々なバリエーションに変更される性質である運用制約に迅速かつ柔軟に対応することができる。
停電作業計画システムは、作業計画期間内で供給信頼度が最大化されるように最適な停電作業計画を作成するシステムである。ここで供給信頼度とは、電力の安定性を示す指標であり、例えば、停電作業により電力設備の機能が停止されると電力系統の冗長性が低下し、これにより供給信頼度は低下することになる。図1は供給信頼度の指標の一例である。この図において、アデカシーとは、電力系統を構成する電力設備の運用制約を考慮に入れ、電力系統に異常を生じることなく電力を供給することができる電力系統の能力の尺度であり、静的な供給信頼度である。これらの指標は、電力設備ごとに、あるいは電力系統全体の値(総和や平均)として評価される。
次に、本実施例の停電作業計画システムを実現するハードウエア構成について説明する。図2は本発明の停電作業計画システムを実現する情報処理装置200である。CPU201は、情報処理装置200の全体の制御を司るもので、記憶手段としてのメモリ202や記憶装置208に格納されたプログラム202cを実行することにより停電作業計画システムの機能やデータベースの機能等を実現する。記録媒体読取装置204は、記録媒体207に記録されているプログラムやデータを読み取るための装置である。読み取られたプログラムやデータは、メモリ202や記憶装置208に格納される。従って、例えば記録媒体207に記録された停電作業計画システムの機能を実現するためのプログラム202cを、記録媒体読取装置204を用いて上記記録媒体207から読み取って、メモリ202や記憶装置208に格納するようにすることができる。例えば、上述のデータベースに記憶されるデータは、メモリ202や記憶装置208に格納される。記録媒体207としてはフレキシブルディスクやCD−ROM、DVD−ROM/RAM、DVD−RAM/RAM、半導体メモリ等を用いることができる。
停電作業計画システムは、上述の情報処理装置200上で動作するプログラムにより提供される。情報処理装置200では、各種のデータを記憶するためのデータベースが動作している。このデータベースには、停電作業計画の対象となる電力系統の構成や電力系統を構成している各電力設備に関する情報(例えば、消費電力、定格電力、送電容量、電力損失等)が記憶されている。また、このデータベースには、以下に説明する処理で用いられる各種のデータが適宜記憶される。
作業系統候補生成処理(I)では、当該処理に後続する処理において用いられる作業系統の候補を生成する。生成された作業系統候補は、情報処理装置200で機能するデータベースに記憶される。作業系統候補生成処理(I)は、縮約系統生成処理(S311)、詳細系統生成処理(S312)、停電作業設備の組合せ処理(S313)、候補生成処理(S314)、等の処理が含まれる。
次に、2.系統運用制約判断処理(II)には、系統損失電力計算処理(S315)及び作業系統候補に対するN−M系統作成処理(S316)、N−M系統に対し運用制約を満たすかどうかの判断処理(S317)が含まれる。
3.系統構成組合せ処理(III)では、2.系統運用制約判断処理(II)により抽出された作業系統候補に対して、諸条件を課すことにより順位付けを行い、最適な系統を抽出する。系統構成組合せ処理(III)は、N−M供給支障電力計算処理(S318)、N−M過負荷量計算処理(S319)、N−M余裕電力量計算処理(S320)、バランス断面ごとの繰り返し計算処理(S321)、ソート処理(S322)、作業系統候補を完全に順序づけることができたかどうかの判断処理(S323)、停電作業要求を満たす系統構成の選択処理(S324)、所要日数が計画期間内であるかどうかを判断する処理(S325)〜(S326)、最適停電作業計画の作成処理(S327)等の処理が含まれる。
以上の処理は、停電作業計画を最適化する問題を電力系統の構成の組合せを最適化する問題に置き換えている。ここで電力系統の構成の組合せを最適化する問題を具体的に定式化すると、数式3に示す目的関数zの供給信頼度(例えば、N−2供給支障電力)を、数式4に示す制約条件下で最小化するような最適解を求める問題となる。
以上の構成からなる停電作業計画システムについて、41母線実系統に対して、作業系統候補の生成処理、系統運用制約判断処理を、N−2供給支障電力を供給信頼度とした場合について検証を行った。なお、停電作業数は11件、同調作業数は最大2件、作業系統候補の探索範囲(常時系統周辺)は常時系統に対し電力設備の数が±1の範囲内とした。その結果、作業系統を常時系統周辺に制約することで、容易に作業系統候補を生成できることを確認した。また、作業系統候補を運用制約によって大幅に削減することにより、比較的容易にN−2供給支障電力を計算することが可能なことを確認した。その結果を表1に示す。
161 CPU
162 メモリ
162c プログラム
165 入力装置
166 出力装置
167 記録媒体
168 記憶装置
S311 縮約系統生成処理
S312 詳細系統生成処理
S313 停電作業設備の組合せ処理
S314 候補生成処理
S315 運用制約を満たすかどうかの判断処理
S316 系統損失電力計算処理
S317 N−2供給支障電力計算処理
S318 N−2過負荷量計算処理
S319 N−2余裕電力量計算処理
S320 バランス断面ごとの繰り返し計算処理
S321 ソート処理
S322 停電作業要求を満たす系統構成の選択処理
S325 最適停電作業計画の作成処理
Claims (17)
- 複数の電力設備によって構成される電力系統の停電作業計画に用いられる停電作業計画システムであって、
停電作業計画の対象となる電力系統の構成と前記電力系統を構成している各電力設備に関する情報とが記憶される記憶手段と、
前記電力系統に含まれる電力設備のうち、停電作業を行うべき複数の電力設備(停電対象設備)が入力される入力手段と、
前記入力される停電対象設備と、前記記憶手段に記憶されている電力系統の構成とに基づいて、停電作業のための作業系統の候補である作業系統候補を生成する作業系統候補生成手段と、
前記生成される作業系統候補の各々について、互いに異なるバランス断面毎に、前記記憶手段に記憶されている各電力設備に関する情報に基づいて、供給信頼度を決定する供給信頼度決定手段と、
前記決定される供給信頼度に基づいて、前記作業系統候補のうち停電作業計画として採用すべき作業系統を決定し、当該決定した作業系統の供給信頼度を決定するために使用したバランス断面に基づいて当該作業系統による作業日を決定する作業計画決定手段と、
を備えることを特徴とする停電作業計画システム。 - 請求項1に記載の停電作業計画システムにおいて、前記作業計画決定手段は、前記決定される前記作業系統候補の供給信頼度と前記電力系統の運用制約とに基づいて、前記停電作業計画として採用すべき作業系統を決定することを特徴とする停電作業計画システム。
- 請求項1に記載の停電作業計画システムにおいて、前記作業系統候補生成手段は、常時系統周辺の作業系統のみを前記作業系統候補として生成する手段であることを特徴とする停電作業計画システム。
- 請求項1に記載の停電作業計画システムにおいて、前記作業系統候補生成手段は、常時系統周辺の系統に対して停電作業の対象となる電力設備の組合せを適用した作業系統を前記作業系統候補として生成する手段であること、を特徴とする停電作業計画システム。
- 請求項1〜4のいずれかに記載の停電作業計画システムにおいて、前記供給信頼度として、前記電力系統を構成する電力設備のうち二つ電力設備が同時に機能を停止した場合における電力系統の供給支障電力を用いることを特徴とする停電作業計画システム。
- 請求項1〜5のいずれかに記載の停電作業計画システムにおいて、前記供給信頼度として、前記電力系統を構成する電力設備のうち二つの電力設備が同時に機能を停止した場合における電力系統の過負荷量を用いることを特徴とする停電作業計画システム。
- 請求項1〜6のいずれかに記載の停電作業計画システムにおいて、前記供給信頼度として、前記電力系統を構成する電力設備のうち二つの電力設備が同時に機能を停止した場合における電力系統の余裕電力量を用いることを特徴とする停電作業計画システム。
- 請求項1〜7のいずれかに記載の停電作業計画システムにおいて、前記作業計画決定手段は、前記作業系統候補のうち前記供給信頼度の高い作業系統候補を他の作業系統候補に優先して選出する手段を含むことを特徴とする停電作業計画システム。
- 請求項1〜8のいずれかに記載の停電作業計画システムにおいて、前記作業計画決定手段は、前記供給信頼度が最大となる前記作業系統候補が複数存在する場合には、前記作業系統候補のうち損失電力の少ない前記作業系統候補を優先して選出する手段を含むことを特徴とする停電作業計画システム。
- 請求項1〜9のいずれかに記載の停電作業計画システムにおいて、前記作業計画決定手段は、前記供給信頼度が最大となるような前記作業系統候補が複数存在する場合には、前記供給信頼度として、前記電力系統を構成する電力設備のうちM(M=3,4,5・・・・・)個の電力設備が同時に機能を停止した場合における、供給支障電力、過負荷量、余裕電力量のうちの少なくともいずれかを用いることを特徴とする停電作業計画システム。
- 請求項1〜10のいずれかに記載の停電作業計画システムにおいて、前記作業計画決定手段は、複数の時点のそれぞれにおける電力設備の電力消費量に基づいて前記供給信頼度を求める手段を備えることを特徴とする停電作業計画システム。
- 請求項1〜11のいずれかに記載の停電作業計画システムにおいて、前記作業系統候補生成手段は、前記電力系統を構成する電力設備のうち冗長構成されている電力設備について、前記電力設備を一つの電力設備として扱うことにより前記作業系統候補を生成する手段を備えること、を特徴とする停電作業計画システム。
- 請求項1〜12のいずれかに記載の停電作業計画システムにおいて、前記作業計画決定手段は、前記決定した作業系統を実施した場合における作業期間が所定の作業期間内に収まらない場合には、既に採用されている前記作業系統候補に代えて、まだ採用されていない前記作業系統候補の中から前記供給信頼度が最も高く、同時に作業可能な停電作業を含む前記作業系統候補を採用すること、を特徴とする停電作業計画システム。
- 請求項1〜13のいずれかに記載の停電作業計画システムにおいて、前記電力系統を構成する電力設備には、発電所、送電線、変圧器、のうち少なくともいずれかが含まれること、を特徴とする停電作業計画システム。
- 請求項2に記載の停電作業計画システムにおいて、前記作業系統候補が前記運用制約を満たしているかどうかの判断を行う処理は、前記運用制約に対応する処理ごとに分割されて記述されているプログラムを実行することにより実現されることを特徴とする停電作業計画システム。
- 複数の電力設備により構成される電力系統の停電作業計画に用いられる停電作業計画方法であって、
停電作業計画の対象となる電力系統の構成と前記電力系統を構成している各電力設備に関する情報とを記憶手段に記憶し、
前記電力系統に含まれる電力設備のうち、停電作業を行うべき複数の電力設備(停電対象設備)を記憶し、
記憶している停電対象設備と、前記記憶手段に記憶されている電力系統の構成とに基づいて、停電作業のための作業系統の候補である作業系統候補を生成し、
前記作業系統候補の各々について、互いに異なるバランス断面毎に、前記記憶手段に記憶されている各電力設備に関する情報に基づいて供給信頼度を決定し、
前記作業系統候補の中から前記決定される供給信頼度に基づいて停電作業計画として採用すべき作業系統を決定し、当該決定した作業系統の供給信頼度を決定するために使用したバランス断面に基づいて当該作業系統による作業日を決定すること、
を特徴とする停電作業計画方法。 - 複数の電力設備により構成される電力系統の停電作業計画に用いられるプログラムであって、
情報処理装置に、
停電作業計画の対象となる電力系統の構成と前記電力系統を構成している各電力設備に関する情報とを記憶手段に記憶する機能と、
前記電力系統に含まれる電力設備のうち、停電作業を行うべき複数の電力設備(停電対象設備)を入力させる機能と、
前記入力される停電対象設備と、前記記憶手段に記憶される電力系統の構成とに基づいて、停電作業のための作業系統の候補である作業系統候補を生成する機能と、
前記作業系統候補の各々について、互いに異なるバランス断面毎に、前記記憶手段に記憶された各電力設備に関する情報に基づいて供給信頼度を決定する機能と、
前記作業系統候補の中から前記決定される供給信頼度に基づいて停電作業計画として採用すべき作業系統を決定し、当該決定した作業系統の供給信頼度を決定するために使用したバランス断面に基づいて当該作業系統による作業日を決定する機能と、
を実現させるためのプログラム。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003310706A JP4185835B2 (ja) | 2003-09-02 | 2003-09-02 | 停電作業計画システム、停電作業計画方法、及びプログラム |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003310706A JP4185835B2 (ja) | 2003-09-02 | 2003-09-02 | 停電作業計画システム、停電作業計画方法、及びプログラム |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2005080471A JP2005080471A (ja) | 2005-03-24 |
JP4185835B2 true JP4185835B2 (ja) | 2008-11-26 |
Family
ID=34412496
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003310706A Expired - Fee Related JP4185835B2 (ja) | 2003-09-02 | 2003-09-02 | 停電作業計画システム、停電作業計画方法、及びプログラム |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4185835B2 (ja) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4725199B2 (ja) * | 2005-06-03 | 2011-07-13 | 東京電力株式会社 | 電力系統停止評価方法及び装置、並びに電力系統管理方法及び装置 |
JP2008086152A (ja) * | 2006-09-28 | 2008-04-10 | Chugoku Electric Power Co Inc:The | 作業系統の生成方法、停電作業計画方法、作業系統生成システム、停電作業計画システム、及びプログラム |
JP5084774B2 (ja) * | 2009-03-31 | 2012-11-28 | 中国電力株式会社 | 発変電器点検・停電計画支援処理における画面操作方法 |
JP5568914B2 (ja) * | 2009-07-28 | 2014-08-13 | 東京電力株式会社 | ネットワークの作業管理システムとその管理方法 |
KR101278309B1 (ko) * | 2011-11-07 | 2013-06-25 | 엘에스산전 주식회사 | Ems의 휴전관리 장치 및 방법 |
CN112446614A (zh) * | 2020-11-26 | 2021-03-05 | 深圳供电局有限公司 | 一种基于用户停电损失的不停电作业优先级评估方法 |
CN114565297A (zh) * | 2022-03-03 | 2022-05-31 | 国网山东省电力公司临沂供电公司 | 一种配网停电检修计划自动校核平衡工具 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6416221A (en) * | 1987-07-08 | 1989-01-19 | Toshiba Corp | Stoppage regulation/calculation system for power system facility |
JPH0591665A (ja) * | 1991-09-24 | 1993-04-09 | Tohoku Electric Power Co Inc | 作業停止計画支援装置 |
JP3408891B2 (ja) * | 1995-05-29 | 2003-05-19 | 三菱電機株式会社 | 作業停電調整装置 |
JPH0928036A (ja) * | 1995-07-11 | 1997-01-28 | Mitsubishi Electric Corp | 電力系統の設備停止計画立案方式 |
JP3559387B2 (ja) * | 1996-03-25 | 2004-09-02 | ティーエム・ティーアンドディー株式会社 | 作業停止計画作成支援システム |
JP2003032892A (ja) * | 2001-07-19 | 2003-01-31 | Mitsubishi Electric Corp | 電力系統の設備停止計画立案装置及び設備停止計画立案方法 |
-
2003
- 2003-09-02 JP JP2003310706A patent/JP4185835B2/ja not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JP2005080471A (ja) | 2005-03-24 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Heidari et al. | Power distribution network expansion planning considering distribution automation | |
US7203622B2 (en) | Value-based transmission asset maintenance management of electric power networks | |
US20130218494A1 (en) | Systems for Real-Time Available Transfer Capability Determination of Large Scale Power Systems | |
CN105474523A (zh) | 用于配电网络重配置的系统、方法和装置及有形计算机可读介质 | |
CN107887879A (zh) | 一种继电保护定值在线校核系统 | |
Esmaili et al. | Transmission expansion planning including TCSCs and SFCLs: A MINLP approach | |
JP2008086152A (ja) | 作業系統の生成方法、停電作業計画方法、作業系統生成システム、停電作業計画システム、及びプログラム | |
Home-Ortiz et al. | Increasing RES hosting capacity in distribution networks through closed-loop reconfiguration and Volt/VAr control | |
JPH11146560A (ja) | 疎結合電力系統制御装置 | |
Wu et al. | Optimal siting of batteries in distribution systems to enhance reliability | |
Wong et al. | Transmission planning in a deregulated environment | |
JP4185835B2 (ja) | 停電作業計画システム、停電作業計画方法、及びプログラム | |
JP4341034B2 (ja) | 系統切替手順計画方法、系統切替手順計画システム、プログラム、および記録媒体 | |
Luo et al. | Research and application of GIS‐based medium‐voltage distribution network comprehensive technical evaluation system | |
JP2021117935A (ja) | 系統制約調整支援装置および方法 | |
Seifi et al. | Multi-voltage approach to long-term network expansion planning | |
Nayeripour et al. | Interactive fuzzy binary shuffled frog leaping algorithm for multi-objective reliable economic power distribution system expansion planning | |
Mondol et al. | Commercial scale solar power generation (5MW to 50 MW) and its connection to distribution power network in the United Kingdom | |
JP5493170B2 (ja) | 復旧作業計画システム、停電作業計画方法およびプログラム | |
EP4235997A1 (en) | System for assisting with creation of grid plan for changing structure of power grid, and method for same | |
Suslov et al. | Expansion planning of active power supply systems | |
Pourbeik et al. | Review of the current status of tools and techniques for risk-based and probabilistic planning in power systems | |
Martínez-Ramos et al. | Optimal and secure operation of transmission systems | |
Billinton et al. | Indices for use in composite generation and transmission system adequacy evaluation | |
Tavakkoli et al. | A new AC OPF tool for sub‐transmission networks considering distribution switching actions and load‐transferring capability |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20060711 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20080125 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20080205 |
|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20080407 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20080812 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20080908 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110912 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 4185835 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110912 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110912 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120912 Year of fee payment: 4 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120912 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120912 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130912 Year of fee payment: 5 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |