JP3882572B2 - Shield tunnel connection structure - Google Patents
Shield tunnel connection structure Download PDFInfo
- Publication number
- JP3882572B2 JP3882572B2 JP2001326103A JP2001326103A JP3882572B2 JP 3882572 B2 JP3882572 B2 JP 3882572B2 JP 2001326103 A JP2001326103 A JP 2001326103A JP 2001326103 A JP2001326103 A JP 2001326103A JP 3882572 B2 JP3882572 B2 JP 3882572B2
- Authority
- JP
- Japan
- Prior art keywords
- tunnel
- plate
- segment
- attached
- water stop
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
この発明は、先に掘進されたシールドトンネル(以下「先行トンネル」という)と、その後から掘進されたシールドトンネル(以下「後行トンネル」という)との接続部の構造に関し、先行トンネルと後行トンネルとの接続部の確実な止水処理と接続部の効率的施工を可能にすべく開発されたものである。
【0002】
【従来の技術】
例えば、地下河川や共同溝などとして利用されるトンネルの場合、図5(a),(b)に図示するように先行トンネル20の側部に後行トンネル21を接続して双方のトンネルを互いに連通させることがある。
【0003】
この場合、特に先行トンネル20と後行トンネル21との接続部22においては、先行トンネル20側の地山に覆工材として複数のセグメントからなるセグメントリング23が設置され、その内周に仕上げライニングとして仕上げコンクリート24が所定の厚さに打設されている。また、セグメントリング23の側部には後行トンネル21側と連通する開口部25が設けられている。
【0004】
一方、接続部22の後行トンネル21側には、後行トンネル21を掘進してきたシールドマシン29のシールドスキンプレート(外殻)26が後行トンネル21の一次覆工材として放置され、その内周に仕上げライニングとして仕上げコンクリート24が先行トンネル20側の仕上げコンクリート24と連続して所定の厚さに打設されている。
【0005】
さらに、先行トンネル20と後行トンネル21との接続部22には、例えば図5(b)に図示するように止水板27が開口部25の円周方向に連続して取り付けられている。この場合の止水板27は、先行トンネル20側においてはセグメントリング23の外側の開口部25の周囲に、後行トンネル21側においてはシールドスキンプレート26の外側にそれぞれ溶接することにより取り付けられている。
【0006】
また、このようにして構成された接続部22の施工方法について説明すると、例えば図6(a)〜(d)に図示するように、最初に先行トンネル20と後行トンネル21間の地盤に対して、一定範囲に渡って薬液注入工法や凍結工法による地盤改良を行い(以下、この部分を「地盤改良部28」という)、シールドマシン29を解体する。
【0007】
続いて、後行トンネル21側より地盤改良部28を掘削する。次に、先行トンネル20側のセグメントリング23の一部を撤去して先行トンネル20の側部に開口部25を形成することにより先行トンネル20と後行トンネル21とを連通させる。
【0008】
次に、図5(b)に図示するように先行トンネル20側のセグメントリング23と後行トンネル21側のスキンプレート26間に止水板27を取り付け、続いて先行トンネル20側のセグメントリング23の内側と後行トンネル21側のシールドスキンプレート26の内側に仕上げライニングとして仕上げコンクリート24を連続して打設する。
【0009】
【発明が解決しようとする課題】
しかし、上述したような接続部の施工方法では、施工に際し、接続部22の周囲に対してあらかじめ大規模な地盤改良部28を施工する必要があり、また先行トンネル20と後行トンネル21とを連通させるべく、大規模な地盤の掘削作業もあって工期の長期化が免れない等の課題があり、最近では、先行トンネル20のセグメントリングを後行トンネル21のシールド機で直接切削して、先行トンネル20の側部に後行トンネル21を接続する施工方法も検討されている。
【0010】
しかし、直接切削工法の場合、先行トンネル20と後行トンネル21の地山は一般に、セグメントリングで覆工されているため、特に接続部22の先行トンネル20側においては、切断されたセグメント間の各目地部がトンネルの地山側から内側に通じる水道になり、確実な止水処理ができないという課題があった。
【0011】
この発明は以上の課題を解決するためになされたもので、先行トンネルと後行トンネルとの接続部の止水処理を確実に行うことができ、かつ接続部の施工をきわめて効率的に行うことができるシールドトンネルの接続部の構造を提供することを目的とする。
【0012】
【課題を解決するための手段】
請求項1記載のシールドトンネルの接続部の構造は、周面にセグメントシール材が取り付けられ、内面には止水板が取り付けられるとともに、当該止水板上にシール材がその両端を前記セグメントシール材に連続させた状態で取り付けられたセグメントが、前記止水板どうし及びシール材どうしが連続した状態で開口予定部を取囲むように組立てられた先行トンネルの前記開口部予定部の側壁を掘削して貫入した後行トンネル掘削用シールドマシンのスキンプレートを、先行トンネルの開口部予定部周囲のセグメント内面に取り付けられた前記止水板、前記シール材及びこれに重ねて取り付けられたシール材押圧板で囲み止水してなることを特徴とするものである。
【0013】
この場合のセグメントには、鋼殻内にコンクリートを充填した鋼殻セグメントの他にRCセグメント等も使用することができる。
【0014】
また、止水板とシール材は原則として、開口部の周囲に設置された各セグメントの内側に、工場などでセグメントを成形する際に予め取り付けられているが、場合によっては、現地でセグメントリングの内側に開口部を形成した後に取り付けることもできる。
【0015】
請求項2記載のシールドトンネルの接続部の構造は、請求項1記載のシールドトンネルの接続部の構造において、止水板は、開口部の周囲に設置された各セグメントの内側に開口部の周方向にドーナッツ板状に連続して取り付けられてなることを特徴とするものである。
【0016】
この場合の止水板は、開口部の内径(シールドスキンプレートの外径)よりやや大きい径のドーナッツ板状に連続して取り付けることが望ましい。このように開口部が止水板より外側に達する等の切削シールド機の施工上の誤差を考慮して、止水板を取り付けることで、開口部の位置が少々ずれた場合でも施工上の問題を回避することができる。
【0017】
請求項3記載のシールドトンネルの接続部の構造は、請求項1または2記載のシールドトンネルの接続部の構造において、開口部の周囲に設置された各セグメントの内側に取り付けられたシール材が、開口部の周方向にビード状または帯状に連続して取り付けられてなることを特徴とするものである。この場合のシール材は、より確実に止水を行うために開口部の周方向に二重に設置される場合もある。
【0018】
請求項4記載のシールドトンネルの接続部の構造は、請求項1、2または3記載のシールドトンネルの接続部の構造において、シール材押圧板の内側に複数の縦リブが開口部の周方向に所定間隔おきに取り付けられてなることを特徴とするものである。
【0019】
【発明の実施の形態】
図1〜図3は、先行トンネル1とその側部に接続された後行トンネル2との接続部の構造を示し、図において先行トンネル1の側部に開口部3が設けられ、先行トンネル1と後行トンネル2は接続部Aにおいて開口部3を介して互いに連通している。
【0020】
接続部Aの先行トンネル1側においては、一次覆工材として複数のセグメント4をトンネルの円周方向と軸方向に連続して設置することによりセグメントリング4Aが形成され、かつセグメントリング4Aの内周に仕上げライニング材として仕上げコンクリート5が所定の厚さに打設されている。
【0021】
一方、接続部Aの後行トンネル2側においては、一次覆工材としてシールドスキンプレート6が設置され、その内周に仕上げライニング材として仕上げコンクリート7が所定の厚さに打設されている。
【0022】
こうして、先行トンネル1と後行トンネル2との接続部Aの地山が覆工されている。この場合のシールドスキンプレート6の先端側6aは、例えば図2(b)に図示するようにセグメントリング4Aを貫通し、かつ開口部3よりセグメントリング4A内に所定長さ突出している。
【0023】
また、仕上げコンクリート7は接続部Aの仕上げライニング材として先行トンネル1側の仕上げコンクリート5と連続して打設されている。
【0024】
さらに接続部Aの開口部3の周囲には、止水板8とシール材9とシール材押圧板10がシールドシキンプレート6の外側に位置して、それぞれ順に重ねて取り付けられている。
【0025】
止水板8は帯板状の金属板(鉄板等)であり、開口部3の円周方向に連続するドーナッツ板状に形成され、かつ開口部3の周囲のセグメントリング4Aの内側に取り付けられている。また、止水板8は各セグメント4の内側に一定長さづつ個別に取り付けられ、全体で開口部3の円周方向に連続するドーナッツ板状に形成されている。
【0026】
したがって、各セグメント4に取り付けられた止水板8の形状および取付位置は、セグメント4ごとに異なっており、また各止水板8は各セグメント4のコンクリート内に定着されたアンカー部材11によってそれぞれ固定されている。
【0027】
シール材9は、止水板8の内側に開口部3の円周方向にビード状(断面ほぼ蒲鉾形状)または帯状に連続して取り付けられている。
【0028】
また、シール材9と同様のセグメントシール材12が、セグメントリング4Aの円周方向と軸方向にそれぞれ連続する、各セグメント4,4間の目地部aに連続して取り付けられている。そして、シール材9とセグメントシール材12はセグメントシール材12aを介して連続している。
【0029】
なお、この場合のシール材9、セグメントシール材12および12aはいずれも、ゴムや合成樹脂などの弾性材から形成され、また一重ないし二重に取り付けられている。
【0030】
シール材押圧板10は、止水板8より幅狭な帯板状の金属板(鉄板等)から開口部3の円周方向に連続するドーナッツ板状に形成され、かつ外側寄りに複数の溶接用孔10aが円周方向に所定間隔おきに形成されている。また、シール材押圧板10は、止水板8の内側にシール材9を上から強く押圧するように添え付けて取り付けられている。この場合、シール材押圧板10の溶接用孔10aの周縁部が止水板8に溶接され、かつシール材押圧板10のシールドスキンプレート6側の端部10aがシールドスキンプレート6の外周にそれぞれ溶接され、さらにシールドスキンプレート6とシール材押圧板10との溶接部に三角形板状の縦リブ13がシールドスキンプレート6の円周方向に所定間隔おきに取り付けられている。
【0031】
なお、シール材押板10を止水板8の内側に固定する他の方法として、例えば止水板8の内側に予め袋ナット等のインサート(図省略)を取り付ける一方、シール材押板10にボルト孔(図省略)を形成し、このボルト孔からインサートにボルト(図省略)を締め付けて固定することもできる。
【0032】
開口部3の周囲がこのように構成されていることで、開口部3周囲の地山側からセグメントリング4Aの内側に通じる水道、特にセグメント4,4間の目地部aを通る水道がシール材9、セグメントシール材12および12aによって完全に遮断されるため、開口部3周囲の止水処理が確実になされる。
【0033】
なお、ここで先行トンネル1の一次覆工材として設置されているセグメント4は、例えば図3(a),(b)に図示するようにトンネルの周方向に平行に設置された主桁板4aとこの主桁板4a同士の端部間にそれぞれ設置された継手板4bと主桁板4aおよび継手板4bの地山側に取り付けられたスキンプレート4cとからなる鋼殻内にコンクリート4dを打設して形成されている。また、主桁板4aと継手板4bの外側部にセグメントシール材12が二重に設置されている。
【0034】
また、特に開口部3の周囲に設置される各セグメント4の内側には止水板8とシール材9が取り付けられ、さらに主桁板4aの外側部にセグメントシール材12aがシール材9とセグメントシール材12に連続させて取り付けられている。
【0035】
なお、この場合の各セグメント4の止水板8とシール材は、セグメント4が接続部Aに設置された際に、各セグメント4の止水板8とシール材9は互いに連なって円形状に連続する必要があることから、各セグメント4ごとに形状および取付位置が違っている。
【0036】
次に、接続部の施工方法を順を追って説明する(図4参照)。
(1) 最初に、先行トンネル1を掘進し、特に接続部Aは図3(a)に図示するセグメント4によって覆工することにより、接続部Aの内側に止水板8とシール材9を取り付ける。
【0037】
(2) 次に、先行トンネル1の接続部Aに後行トンネル2を接続するに備えて、接続部Aの先行トンネル1内にソイルモルタルや発泡モルタル等の充填材14を充填し、また接続部Aの周囲の地盤15に対しては薬液注入工法や凍結工法などによって一定範囲を地盤改良することにより、接続部Aの内側と外側を補強し、かつ接続時の水の浸入を押さえる。
【0038】
(3) 次に、後行トンネル2のシールドマシン16をさらに前進させ、シールドマシン16のカッタービット16aによって先行トンネル1のセグメントリング4Aを直接切削することにより、セグメントリング4Aの接続部Aに開口部3を形成する。この場合、シールドマシン16のシールドスキンプレート6の先端6aがセグメントリング4Aを貫通し、セグメントリング4Aの内方に所定長さ突出するまで、シールドマシン16を前進させる。
また、セグメントリング4Aの内側にドーナッツ板状に連続して取り付けられた止水板8の内側を切削して開口部3を形成するものとする。したがって、止水板8はシールドスキンプレート6の外径よりやや大きい径のドーナッツ板状に取り付けておくのが、施工誤差を吸収できて望ましい。
【0039】
(4) 次に、シールドマシン16のカッタービット16aと内部の機器類(図省略)を全て撤去し、外周のシールドスキンプレート6のみを後行トンネル2の覆工材として接続部Aに残す。また、先行トンネル1内に充填された充填材14を掘削して全て撤去する。
【0040】
(5) 次に、開口部3の周囲に取り付けられた止水板8の内側にシール材押圧板10をシール材9の上から強く押圧するように添え付ける。そして、シール材押圧板10の溶接用孔10aの周縁部を止水板8に溶接し、シール材押圧板10のシールドスキンプレート6側の端部をシールドスキンプレート6の外周に溶接し、さらにシールドスキンプレート6とシール材押圧板10との溶接部に縦リブ13をシールドスキンプレート6の円周方向に所定間隔おきに取り付ける。こうして、開口部3周囲の止水処理を確実に行うことができる。
【0041】
(6) 次に、シールドスキンプレート6の内周にコンクリート7を、セグメントリング4Aの内周にコンクリート5を連続して打設する。この場合当然、止水板8、シール材9およびシール材押圧板10はすべてコンクリート5で被覆するものとする。こうして、接続部Aの施工は完了する。
【0042】
【発明の効果】
この発明は以上説明したとおりであり、特に先行トンネル側の側部に後行トンネル側と連通させて設けられた開口部の周囲に止水板とシール材とシール材押圧板が順に重ねて取り付けられ、かつ前記セグメント間の目地部にセグメントシール材が前記シール材と連続して取り付けられてなるので、特に先行トンネルのセグメント間の目地部を通る水道が完全に遮断されるため、開口部周囲の止水処理を確実に行うことができる。
【0043】
また、開口部周囲の止水処理を確実に行うことができることで、先行トンネルのセグメントリングを後行トンネルのシールドマシンで直接切削することにより、先行トンネルの側部に後行トンネル側に連通する開口部を設けることが可能になる。このため、これまでのような大規模な地盤改良や掘削作業を省略することができ、きわめて効率的で経済的な施工を行うことができる。
【図面の簡単な説明】
【図1】先行トンネルと後行トンネルとの接続部を示す断面図である。
【図2】先行トンネルと後行トンネルとの接続部を示し、(a)は図1におけるa−a線断面図、(b)は図1におけるイ部拡大図、(c)は図2(b)におけるロ部拡大図である。
【図3】セグメントの一例を示し、(a)はセグメントの全体を示す斜視図、(b)は一部が切削されたセグメントを示す斜視図である。
【図4】先行トンネルと後行トンネルとの接続部の施工方法を示す工程図である。
【図5】従来の先行トンネルと後行トンネルとの接続部を示し、(a)はその外観を示す斜視図、(b)は(a)におけるb−b線断面図である。
【図6】(a)〜(d)は、先行トンネルと後行トンネルとの接続部の施工方法の従来例を示す工程図である。
【符号の説明】
1 先行トンネル
2 後行トンネル
3 開口部
4 セグメント
4A セグメントリング
5 仕上げコンクリート(仕上げライニング材)
6 スキンプレート(シールドスキンプレート)
7 仕上げコンクリート(仕上げライニング材)
8 止水板
9 シール材
10 シール材押圧板
10a 溶接用孔
11 アンカー部材
12 セグメントシール材
12a セグメントシール材
13 縦リブ
14 充填材
15 接続部の周囲の地盤
16 シールドマシン
16a カッタービット
20 先行トンネル
21 後行トンネル
22 接続部
23 セグメントリング
24 仕上げコンクリート
25 開口部
26 シールドスキンプレート(外殻)
27 止水板
28 地盤改良部
29 シールドマシン
29a カッターピット[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a structure of a connecting portion between a shield tunnel dug first (hereinafter referred to as “preceding tunnel”) and a shield tunnel excavated thereafter (hereinafter referred to as “following tunnel”). It was developed to enable reliable water stop treatment at the connection with the tunnel and efficient construction of the connection.
[0002]
[Prior art]
For example, in the case of a tunnel used as an underground river or a common ditch, as shown in FIGS. 5 (a) and 5 (b), a
[0003]
In this case, in particular, in the connecting
[0004]
On the other hand, the shield skin plate (outer shell) 26 of the
[0005]
Further, a
[0006]
The construction method of the connecting
[0007]
Subsequently, the
[0008]
Next, as shown in FIG. 5B, a
[0009]
[Problems to be solved by the invention]
However, in the construction method of the connection part as described above, it is necessary to construct a large
[0010]
However, in the case of the direct cutting method, since the ground of the preceding
[0011]
The present invention has been made to solve the above-mentioned problems, and can reliably perform the water stop treatment of the connecting portion between the preceding tunnel and the succeeding tunnel, and perform the construction of the connecting portion extremely efficiently. An object of the present invention is to provide a shield tunnel connection structure that can perform the above-mentioned.
[0012]
[Means for Solving the Problems]
The structure of the connecting part of the shield tunnel according to claim 1 , wherein a segment seal material is attached to the peripheral surface, a water stop plate is attached to the inner surface, and the seal material is attached to the both ends of the segment seal on the water stop plate. The segment attached in a continuous state to the material excavates the side wall of the planned opening portion of the preceding tunnel assembled so as to surround the planned opening portion in a state where the water blocking plates and the sealing materials are continuous. The skin plate of the shield machine for excavation of the following tunnel excavating the water stop plate attached to the inner surface of the segment around the planned opening portion of the preceding tunnel, the seal material, and the seal material press attached to the seal plate It is characterized by being surrounded by a plate and water-stopping .
[0013]
In this case, in addition to the steel shell segment in which the steel shell is filled with concrete, an RC segment or the like can be used.
[0014]
In addition, as a general rule, the water stop plate and seal material are attached in advance to the inside of each segment installed around the opening when a segment is formed at a factory, etc. It can also be attached after the opening is formed inside.
[0015]
The structure of the connection part of the shield tunnel according to
[0016]
In this case, it is desirable that the water stop plate is continuously attached in a donut plate shape having a diameter slightly larger than the inner diameter of the opening (outer diameter of the shield skin plate). Considering the construction error of the cutting shield machine such that the opening reaches the outside of the water stop plate in this way, by installing the water stop plate, even if the position of the opening is slightly shifted, it is a construction problem Can be avoided.
[0017]
The structure of the connection part of the shield tunnel according to
[0018]
The structure of the shield tunnel connection portion according to
[0019]
DETAILED DESCRIPTION OF THE INVENTION
1 to 3 show a structure of a connection portion between a preceding tunnel 1 and a succeeding
[0020]
On the preceding tunnel 1 side of the connecting portion A, a
[0021]
On the other hand, on the
[0022]
Thus, the natural ground of the connection portion A between the preceding tunnel 1 and the succeeding
[0023]
Further, the finishing concrete 7 is continuously placed as the finishing lining material of the connection portion A with the finishing concrete 5 on the preceding tunnel 1 side.
[0024]
Further, a
[0025]
The
[0026]
Therefore, the shape and the mounting position of the
[0027]
The sealing material 9 is attached to the inner side of the
[0028]
Further, a
[0029]
In this case, both the sealing material 9 and the
[0030]
The sealing
[0031]
As another method for fixing the sealing
[0032]
Since the periphery of the
[0033]
Here, the
[0034]
Further, in particular, a
[0035]
In this case, when the
[0036]
Next, the construction method of the connecting portion will be described in order (see FIG. 4).
(1) First, the preceding tunnel 1 is dug, and in particular, the connection portion A is covered by the
[0037]
(2) Next, in preparation for connecting the succeeding
[0038]
(3) Next, the
Moreover, the
[0039]
(4) Next, the
[0040]
(5) Next, the sealing
[0041]
(6) Next, the
[0042]
【The invention's effect】
The present invention is as described above, and in particular, a water stop plate, a sealing material, and a sealing material pressing plate are sequentially stacked around the opening provided in the side portion on the preceding tunnel side so as to communicate with the subsequent tunnel side. In addition, since the segment sealing material is continuously attached to the joint between the segments, the water supply passing through the joint between the segments of the preceding tunnel is completely blocked, It is possible to reliably perform the water stop treatment.
[0043]
In addition, since the water stop treatment around the opening can be performed reliably, the segment ring of the preceding tunnel is directly cut by the shield machine of the succeeding tunnel, so that the side of the preceding tunnel communicates with the succeeding tunnel side. An opening can be provided. For this reason, the conventional large-scale ground improvement and excavation work can be omitted, and extremely efficient and economical construction can be performed.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view showing a connection portion between a preceding tunnel and a succeeding tunnel.
2A and 2B show a connecting portion between a preceding tunnel and a succeeding tunnel, wherein FIG. 2A is a cross-sectional view taken along the line aa in FIG. 1, FIG. 2B is an enlarged view of a portion in FIG. It is the B section enlarged view in b).
FIG. 3 shows an example of a segment, (a) is a perspective view showing the whole segment, and (b) is a perspective view showing a segment partially cut.
FIG. 4 is a process diagram showing a construction method of a connecting portion between a preceding tunnel and a succeeding tunnel.
5A and 5B show a connecting portion between a conventional leading tunnel and a trailing tunnel, in which FIG. 5A is a perspective view showing an appearance thereof, and FIG. 5B is a cross-sectional view taken along line bb in FIG.
FIGS. 6A to 6D are process diagrams showing a conventional example of a method for constructing a connection portion between a preceding tunnel and a succeeding tunnel.
[Explanation of symbols]
1 preceding
6 Skin plate (shield skin plate)
7 Finished concrete (finished lining material)
8 Water stop plate 9
12a
27
29a Cutter pit
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001326103A JP3882572B2 (en) | 2001-10-24 | 2001-10-24 | Shield tunnel connection structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2001326103A JP3882572B2 (en) | 2001-10-24 | 2001-10-24 | Shield tunnel connection structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2003129789A JP2003129789A (en) | 2003-05-08 |
JP3882572B2 true JP3882572B2 (en) | 2007-02-21 |
Family
ID=19142548
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2001326103A Expired - Lifetime JP3882572B2 (en) | 2001-10-24 | 2001-10-24 | Shield tunnel connection structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3882572B2 (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE102004010043A1 (en) * | 2004-03-02 | 2005-09-15 | Ed. Züblin Ag | Method and device for producing a watertight connection between a crosscut and a tunnel with segmental lining |
CN104612723B (en) * | 2015-02-02 | 2016-11-23 | 同济大学 | Duct pieces of shield tunnel seam waterproof seals structure |
CN105649658A (en) * | 2015-12-29 | 2016-06-08 | 上海隧道工程有限公司 | Waterproof joint structure of rectangle-like tunnel segment |
CN106948829B (en) * | 2017-04-29 | 2023-03-14 | 中铁一局集团有限公司 | Sealing structure of originating tunnel portal of slurry shield and construction method thereof |
-
2001
- 2001-10-24 JP JP2001326103A patent/JP3882572B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JP2003129789A (en) | 2003-05-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3882572B2 (en) | Shield tunnel connection structure | |
JP2006188918A (en) | Tunnel waterproof structure | |
JPH09217594A (en) | Timbering method for tunnel | |
JP2007040018A (en) | Tunnel structure for branch section or junction section of underground passage and its execution method | |
JP2002220991A (en) | Partition wall installed in main-tunnel shield tunnel and construction method therefor | |
JP2007309474A (en) | Branch pipe connecting device and branch pipe connecting method | |
JPH04357293A (en) | Flexible pipe and executing method thereof | |
JP2006291457A (en) | Flexible joint mounting structure | |
JP2656894B2 (en) | Method of projecting horizontal members into the ground | |
JP6229400B2 (en) | Tunnel connection structure and tunnel connection method | |
JPH11117686A (en) | Segment corresponding to opening covered with resin on inner surface | |
JP4153636B2 (en) | Vertical tunnel wellhead stop device | |
JPH0788759B2 (en) | Tunnel lining method | |
JP3867156B2 (en) | Liner piece | |
JP3900686B2 (en) | Underground structure and its construction method | |
JP2019031772A (en) | Structure and method for connecting between shield tunnels | |
JP6935640B2 (en) | Construction method of underground widening part | |
JP2007009562A (en) | Construction method of shield tunnel inside road having width expanded part and segment used therefor | |
JP2006152680A (en) | Joining construction method for shield tunnel and structure of shield tunnel by its construction method | |
JP3590429B2 (en) | How to assemble a segment with a cutter | |
JP3474445B2 (en) | Construction method of segment and shield tunnel | |
JP2021008725A (en) | Construction method for soil retaining structure and pipe for soil retaining structure | |
JP3599394B2 (en) | Well stop device for side hole of manhole pipe | |
JP3466457B2 (en) | Closed structure of segment and working hole in segment | |
JP2558168B2 (en) | Backfill injection method of segment in shield method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040623 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060706 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060718 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060915 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061024 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061106 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 3882572 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20091124 Year of fee payment: 3 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121124 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121124 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20151124 Year of fee payment: 9 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
EXPY | Cancellation because of completion of term |