JP3599394B2 - Well stop device for side hole of manhole pipe - Google Patents

Well stop device for side hole of manhole pipe Download PDF

Info

Publication number
JP3599394B2
JP3599394B2 JP32995194A JP32995194A JP3599394B2 JP 3599394 B2 JP3599394 B2 JP 3599394B2 JP 32995194 A JP32995194 A JP 32995194A JP 32995194 A JP32995194 A JP 32995194A JP 3599394 B2 JP3599394 B2 JP 3599394B2
Authority
JP
Japan
Prior art keywords
pipe
manhole
wellhead
propulsion
rubber plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP32995194A
Other languages
Japanese (ja)
Other versions
JPH08158391A (en
Inventor
宣郎 岩渕
一記 小倉
武文 松村
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fukoku Co Ltd
Original Assignee
Fukoku Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fukoku Co Ltd filed Critical Fukoku Co Ltd
Priority to JP32995194A priority Critical patent/JP3599394B2/en
Publication of JPH08158391A publication Critical patent/JPH08158391A/en
Application granted granted Critical
Publication of JP3599394B2 publication Critical patent/JP3599394B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Sewage (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【0001】
【産業上の利用分野】
本発明は、沈設した立坑マンホール管の側面から排水管等の配管を推進施工する場合の、マンホール管側面の坑口に設ける土砂や水等の侵入防止用の止水器に関する。
【0002】
【従来の技術】
従来より、マンホール内部から、埋設管に向けて排水管等を推進掘削させて配管接続する工事が行われている。かかる工事では、立坑側面に打ち込まれた鋼矢板に、地下内部からバーナー切断により配管施工用の坑口を開け、図8に示す坑口止水器を坑口開口部に取り付けている。
坑口止水器は、環状フランジの一方の面に、配管施工時の土砂等の流入防止用の円形ゴム板が重ねられ、バーナー切断して開けられた鋼矢板の穴にフランジを溶接し、円形ゴム板を挟んで環状フランジとでボルト止めする。その後に推進機で管を推進させて配管敷設する。
配管敷設後、コンクリート打設又はマンホール管等を設置して、マンホール管に上記配管の接続を行い、施工配管の周囲とマンホール管坑口との間にモルタル詰めを行って、水や土砂等が流入しないように止水処置を施す。その後に埋め戻し、鋼矢板を引き抜く。坑口止水器については溶断して取り除いておくのが一般的である。
【0003】
【発明が解決しようとする課題】
しかし、従来の工法では、立坑の掘削、鋼矢板の設置、前記立坑内からの管推進、推進終了後のマンホール管の設置、マンホール管と鋼矢板の間の埋め戻し、鋼矢板撤去等の工程をとっている。かかる工法では、特に、立坑掘削、埋め戻し、及び鋼矢板の撤去等に多大の時間を要し、施工費の削減及び工期の短縮という面からその改善が強く要望されていた。
そのため、最近では、漸次縦方向に掘削しながら、予め側面に配管用の穴を設けたコンクリート製のマンホール管を、掘削深度に合わせて継ぎ足しながら沈設し、沈設したマンホール管の側面坑口から側方に配管を掘削する方法が開発されている。かかる工法では、在来の坑口止水器は使用できず、新たに沈設マンホール管に使用可能な坑口止水器の開発が必要であった。
【0004】
また、坑口止水器は、マンホール管沈設時には周辺地盤との摩擦にならず、そしてマンホール管内の土砂を掘削するクラムシェル等のバケットにひっかかることがないように、マンホール管壁厚内にセット可能でなければならない。
また、配管推進後は、従来と異なり止水器を取り外すことなく埋め殺し可能な構成でなければならない。
さらには、予め沈設したマンホール管の外周部には土砂の硬化剤を注入するため、かかる硬化剤のマンホール管内への流入をも効果的に防げるものでなければならない。
そこで、本発明は上記問題点及び必要性に鑑み提案されるもので、沈設したマンホール管の側面から排水管等の配管を推進施工する場合の、マンホール管側面に設けた坑口に使用する坑口止水器を提供する。
【0005】
【課題を解決するための手段】
上記目的を達成するための本発明は、沈設工法により地中に沈設されるマンホール管に形成されて推進先行管および配管を施工するための貫通配管施工用坑口に設けられる坑口止水器であって、前記坑口に組み付けられるフランジと、前記推進先行管の推進後に推進される配管が通る穴が設けられ、前記フランジに保持されるシールゴム板と、前記坑口の外面側に配置して前記フランジに固定される軟質部材よりなり、前記坑口を前記マンホール管の外面から出っ張ることなく覆う蓋と、前記フランジに内側から撤去可能に取り付けられ、前記蓋および前記シールゴム板を土圧に抗して支持する補強板とを有することを特徴とする。また、本発明のマンホール管側面坑口用の坑口止水器は、前記マンホール管の内面および外面からそれぞれ出っ張ることなく前記マンホール管の壁厚内に配置されることを特徴とする。
【0006】
本発明のマンホール管側面坑口用の坑口止水器は、前記シールゴム板が、配管施工時の推進先行管が貫通する第1のシールゴム板と、前記推進先行管の推進後に推進される配管が通る穴が設けられた第2のシールゴム板との2枚よりなることを特徴とする。また、前記シールゴム板に配管施工時の推進先行管用の小孔を設けるとともに、前記小孔の外側に推進先行管の推進後に推進される配管が貫通する配管用の穴を形成する切り溝を設けたことを特徴とする。さらに、前記シールゴム板の外径は前記坑口の内径よりも大きく形成され、前記坑口止水器を前記坑口に取り付ける際に前記シールゴム板の外縁部分が前記坑口に密接することを特徴とする。
【0007】
本発明のマンホール管側面坑口用の坑口止水器は、前記フランジと前記シールゴム板と前記補強板と前記蓋とを、前記マンホール管の外側から挿通するボルトと当該ボルトにねじ止めされるナットにより共締めしたことを特徴とする。また、前記坑口の内周面に密接する略環状のパッキングを前記フランジに取り付けたことを特徴とする。さらに、前記蓋が発砲スチロール樹脂または木材で形成されていることを特徴とする。
【0008】
【作用】
本発明の坑口止水器にあっては、坑口に嵌合される環状のフランジにシールゴム板が取り付けられており、止水器本体は、マンホール管の内面および外面から出っ張ることなくマンホール管の壁厚内にセットできるので、マンホール管の沈設時に周辺地盤との摩擦を極力起こさず、マンホール管内の土砂を掘削する装置の邪魔にもなることなくマンホール管の沈設が行える。また、フランジが蓋で覆われているため、この蓋側をマンホールの外側に向けるようにして、坑口止水器を取り付けて沈設すれば、マンホール管内への土砂や硬化剤などの侵入を防止することができる。
【0009】
さらに、蓋により硬化剤の侵入が防止されるため、シールゴム板のすぐ後ろに硬化剤が硬くなって着くことがなく、推進管を推進させるときに管先頭の刃物でシールゴム板の切れを発生させる虞がない。
また、蓋は推進先行管及び配管で穿孔可能な軟質部材により形成されているので、配管の推進施工時には、マンホール管の内側から推進先行管や配管を推進させるだけで、必要な穴を蓋部分に開けることができる。特に、蓋を発泡スチロール樹脂や木材で形成すれば、より穿孔し易すくなる。
さらに、シールゴム板に隣接する蓋部材が軟質部材で形成されているため、推進管を推進させるときの管先頭の刃物によるシールゴム板の切れを効果的に防止できる。
【0010】
他方のフランジ面には補強板が設けられているので、蓋やシールゴム板等をマンホール管の内側に押そうとする土圧に抗して、それを押し止めることが可能である。さらに、この補強板は撤去可能であるため、推進施工時には補強板を外して作業を行うことができる。
シールゴム板を二枚合わせに構成した場合は、蓋に近い側のシールゴム板の略中央に推進施工時の先行管用の小孔が設けられているため、推進施工時に先行管をその小孔に通すことにより、シールゴム板の小孔の周縁部分が少しめくれ気味になりながら先行管の管壁に密着して、土砂や水等の侵入を防ぎながら先行管を通すことができる。マンホール管の周囲に硬化剤を圧入しながら行う工法では、かかる硬化剤の侵入をも防止することができる。
また、他方のシールゴム板の略中央には、配管用の穴が設けられているので、上記要領で穴の周縁部分を配管の管壁に密着させて土砂や水等の侵入を防ぎながら、配管を上記先行管の推進後に通すことができる。
【0011】
一方、シールゴム板を一枚構成にする場合には、シールゴム板の略中央の小孔を利用して上記要領で土砂や水等の侵入を防ぎながら推進先行管を通すことができる。さらに、小孔の周囲には、配管用の穴形成ができるように切溝が設けられているので、推進先行管を通している間はこの切溝から切り取らずにそのままで土砂等の侵入を防ぐ一方、配管を通すときには上記切溝から切り取って簡単に配管用の穴を形成できる。
さらに、切溝を、小孔を中心に同心円状に複数設けることにより、種々の配管口径に合わせた穴径の選択ができる。
また、シールゴム板は、2枚合わせ或は1枚構成に拘らず、坑口止水器をマンホール管側面の貫通配管施工用坑口に取り付ける際に、シールゴム板の外縁部分が前記坑口の内壁に沿って止水可能に密接できるように、その外径が前記坑口の内径より大きく形成されているので、止水器をマンホール管の外側から坑内に取り付けるようにすれば、シールゴム板の外縁部分がまくれるようにして坑内壁に密接して、マンホール管沈設時の硬化剤等の侵入をより効果的に防ぐことができる。
【0012】
また、補強板は、フランジとの間に、蓋側から挿通させたボルトに、蓋、止水器取付部材、フランジ及びシールゴム板とを共締め固定するナットを介在させ、さらに前記ボルトにナットで取り付けられているので、他の部分を緩めることなく補強板を簡単に撤去できる。補強板以外は、緩めることなくマンホール管に取り付けた状態になっているため、推進施工後はそのまま坑口止水器を埋め殺しにできる。さらに、万一推進方向や沈設位置が大きくズレた場合、フランジ及びシールゴム板等もナットを外すことによって取り除くことができる。即ち、フランジ分だけ坑口の有効内径を大きく使用することができる。
さらに、かかる構成では、補強板とフランジとの間にリブを介在させているので、補強板とフランジとの間にナット介在分の間隙ができても、その間隙をリブで埋めてシールゴム板を背後から土圧に抗すことができるように支えられる。
また、リブを介在させた補強板とフランジの間の外周縁部分に、マンホール管側面の貫通配管施工用坑口の内壁に止水可能に密接する略環状のパッキングを、前記補強板とフランジとに挟んで設けることにより、止水器と坑内壁とがパッキングを介在させて隙間なく接するので、マンホール管沈設時の硬化剤等の侵入をより確実に防止できる。
【0013】
【実施例】
本発明の実施例を図により説明する。
本発明の坑口止水器は、立坑側面に予め打ち込まれた鋼矢板に、地中の立坑内部から貫通配管施工用の坑口を開口し、これに坑口止水器を取り付けて、この坑口から配管等を推進施工する従来の工法に使用するものではなく、掘削しながらコンクリート製のマンホール管を暫時直接沈設して形成する立坑の側面坑口から配管等を推進施工する沈設工法に使用するものである。そこで、本発明の坑口止水器の使用前提である沈設工法について、その概略を説明する。
【0014】
沈設工法では、図7に示すように、地中を先ず浅く掘削して、そこにコンクリート製のマンホール管10を沈める。次にマンホール管10内部から掘削を進めるとともに、沈潜するマンホール管10の周囲に土壌崩壊等を防ぐための硬化剤を注入しながら、マンホール管10の自重を利用して漸次マンホール管10を沈めて行く。形成する立坑の深さに応じて、マンホール管を暫時積み重ねるようにして、マンホール管10内部の土砂をショベルでかき出しながら所定深度まで沈め、所望の立坑を形成する。
その後沈めたマンホール管10の側面から、この側面に予め設けた貫通配管施工用の坑口20を利用して、推進機イにより推進先行管ロ及び配管ハを二工程で推進施工する工法、又は、配管ハを一工程で推進施工する工法である。
本発明の坑口止水器Aは、上記工法で使用するマンホール管10側面に設けた貫通配管施工用の坑口20に予め取り付けられ、上記要領でマンホール管10を沈潜して立坑を形成し、さらに、上記坑口20から土砂の流入を防ぎながらマンホール管10側面に推進施工により配管接続を行い、そのまま坑口止水器Aを埋め殺しにする工法で使用されるものである。
【0015】
(実施例1)
本実施例1の坑口止水器Aは、図1に示すように、上記沈設工法に使用するコンクリート製のマンホール管10側面の貫通配管施工用の坑口20に取り付けられるもので、二枚合わせのシールゴム板30a、30bを有した構成である。
二枚合わせのシールゴム板30a、30bは、二枚の環状の金属製フランジ40a、40bに両側から挟まれて、配管施工時に推進先行管等を通しても形態保持ができるようになっている。フランジ40a、40bは、上記坑口20の開口部分の内側に丁度嵌合できるような外形を有した環状に形成されている。フランジ40a、40b中央の円形開口部分は、貫通配管施工時に邪魔にならない程度の大きさに設定され、また周縁部分には後記する固定用のボルトB挿通用の穴40cが等間隔に4個設けられている。
【0016】
シールゴム板30aは肉薄の円形に成され、シールゴム板30bは肉厚の円形に形成され、両者は互いに面合わせに合わされて、その周縁部分が上記のように二枚の環状フランジ40a、40bにより両側から圧着状態で強く挟まれて形成されている。
肉薄のシールゴム板30aは、フランジ40aの径より少し大きめの径に形成され、坑口止水器Aを上記坑口20の開口内部に嵌合させて取り付けるときに、坑内壁20aに隙間なく密着できるようになっている。さらに、シールゴム板30aの略中央には推進先行管の口径より少し小径の小孔31が開けられている。この小孔31を通して推進先行管を通すと、小孔31の周縁部分のゴムがめくれて推進先行管の管壁周囲に密着し、土砂や水等がマンホール管10内へ侵入できないようになっている。
【0017】
他方の肉厚に形成されたシールゴム板30bの略中央には、上記小孔31と同心円状の配管口径より少し小径で、上記小孔31より大きな円形の穴32が開けられている。このようにして、推進先行管を通した後で、上記推進先行管を通す際の要領で土砂や水等のマンホール管10内部への侵入を防ぎながら、配管を通せるようになっている。
尚、シールゴム板30a、30bには、本実施例ではSBR(スチレン−ブタジエンゴム)が使用されている。SBR以外にも、NR(天然ゴム)、CR(クロロプレンゴム)、NBR(ニトリルブタジエンゴム)、IIR(ブチルゴム)、EPDM(エチレン・プロピレンゴム)等も使用できる。
また、それぞれのシールゴム板30a、30bの周縁部分には、上記フランジ部分40a、40bに設けたボルト挿通用の穴40cと符号できる位置に、ボルト挿通用の穴30cが設けられている。
【0018】
一方、肉薄のシールゴム板30aに接したフランジ40aの外面側では、フランジ40aの環状面と肉薄のシールゴム板30a面とを合わせた円形表面全面が蓋50に覆われている。蓋50は、発泡スチロール樹脂や木材等の軟質部材を用いて形成されている。このようにして、蓋50を設けることにより、硬化剤のマンホール管10内部への侵入を防ぐとともに、ゴム板変形の逃げ代となることから、推進時の推進管先頭(先導体)の刃物と硬化剤との間に挟まれてシールゴム板30aが切れるのを防ぐことができる。
さらに、蓋50の形状は、図1(a)及び(b)に示すように、Y−Y線から周縁部に向けて外側部分がマンホール管10側面の外周曲率に合わせられるようテーパー状で、且つ全体が略台形状に形成され、坑口止水器Aをマンホール管10の坑口20に取り付けたとき、坑口20前面を蓋50で蓋をするようにして閉塞できるようになっている。木材を蓋50に使用する場合には、推進先行管や配管等の推進側の管端部に切り込み用の刃を設けるようにすればより穿孔し易くなる。
【0019】
さらに、蓋50の周縁部分にも、前記フランジ40a、40b及びシールゴム板30a、30bのボルト挿通用の穴40c、30c位置と符合できる位置にボルト挿通用の4個の穴50cが設けられ、この穴50cにはボルトBのねじ部分を挿通させる金属製スリーブ51が嵌め込まれている。
また、上記4個の穴50cには、坑口止水器Aを貫通配管施工用の坑口20に設けるための止水器取付部材60が設けられている。止水器取付部材60は、矩形金属板を長手方向の途中でマンホール管10の外周の曲率に合わせて曲げた形状に形成され、曲げ部分61が蓋50のボルト挿通用の穴50c部分から、四方に突設するように上記ボルトBで他の部分とともに共締めにより取り付けられるようになっている。
マンホール管10側面に坑口止水器Aを取り付ける場合には、図6に示すように、止水器取付部材60が丁度マンホール側面にたすき掛け状に交差するようにして、曲げ部分61をマンホール管10外周面に密着させながらボルト穴62からボルト止めすればよい。
【0020】
上記のように構成された蓋50、止水器取付部材60、フランジ40a、40b、シールゴム板30a、30bは、ボルトBのねじ部分を蓋50側から挿通して、フランジ40b側でナット70aにより共締め固定されている。
さらに、上記フランジ40b側に面して、フランジ40bの径に略匹敵する程度の円形鉄板の補強板80が、補強板80の周縁部に設けたボルト挿通用の穴80c位置に前記ボルトBを挿通させてナット70bにより取り付けられている。補強板80とフランジ40b面との間には、フランジ40b面と補強板80の間に挟まれたナット70aと略同じ厚みを有した十文字状のリブ90が設けられ、このリブ90を介して、フランジ40a、40bやシールゴム板30a、30b等が土圧によりマンホール管10の内側へ押されないように、補強板80で支えることができるようになっている。
【0021】
補強板80はこのように構成されているため、推進施工時には、このナット70bを外すだけで、前記ナット70aを緩めることなくリブ90と補強板80とを簡単に撤去することができる。
また、配管施工が終了した後は、補強板を外した状態で、マンホール管と施工された配管の周囲の隙間にモルタルを詰めて、坑口止水器を埋め殺しにする。
また、円形の補強板80の中心を挟んで両側に、略矩形の窓80aが開けられ、補強板80からシールゴム板30b側の状況確認ができるようになっている。また、この窓80a部分に手をかければ、坑口止水器Aの持ち運びに便利である。
尚、坑口止水器Aをマンホール管10に取り付けるに際しては、図2に示すように、坑口止水器Aの蓋50と坑内壁20aとの間の隙間全周にモルタルを詰めて、マンホール管の沈設時に使用される硬化剤や水等の侵入が防止されている。
【0022】
(実施例2)
本実施例2で使用する坑口止水器Aは、基本的構成は実施例1と同様であるが、図3(a)及び(b)に示すように、坑内壁20aと坑口止水器Aとの隙間部分からの硬化剤や水等の侵入防止機能をより高めた構成をさらに加えたものである。
図3(a)に示す坑口止水器Aでは、実施例1に示す坑口止水器Aの薄い方のシールゴム板30aの外径が、坑口20の内径より大きく形成されている。シールゴム板30aの外径の大きさは、坑口止水器Aがセットされた状態で、シールゴム板30a外周縁部分が、図3(a)に示すように、坑口20のマンホール管10の外側へ向けて捲れ、捲れた外周縁部分が坑口内壁20aに密接できる程度に設定されている。このようにして、坑口20から坑内へ万一硬化剤や水等が侵入してきても、坑口内壁20aに全周が密接しているシールゴム板30aの外周縁部分で効果的に阻止できるようになっている。
本実施例では、シールゴム板30aの外径を大きくする構成としたが、例えば、厚手のシールゴム板30bの外周部分に、上記のように坑内壁20aに密接できるように薄手のゴムリングを一体に形成するようにしてもよい。
【0023】
図3(b)に示す坑口止水器Aでは、実施例1の坑口止水器Aの補強板80とフランジ40bとの外周縁部分に、環状のパッキング81が設けられている。パッキング81は、ゴムスポンジ等の素材で形成され、坑口20の内径より少し大きい環状に形成されている。そのため、坑口止水器Aを坑内にセットした状態では、図3(b)に示すように、坑口止水器Aの上記パッキング81が坑内壁20aに密接している。そのため、坑口20から坑内へ万一硬化剤や水等が侵入してきても、坑口内壁20aに全周が密接しているパッキング81でそれらを効果的に阻止できるようになっている。
さらに、かかるパッキング81は、シールゴム板30aの外径を上記のように大きくする構成と併用することにより、或は実施例1の図2に示すように坑口止水器Aをセットするときに蓋50の外周と坑内壁20aとの間をモルタル詰めすることにより、硬化剤等の坑内への侵入防止機能をより高めることができる。
【0024】
(実施例3)
本実施例3で使用する坑口止水器Aは、図4に示すように、コンクリート製のマンホール管10側面に設けた貫通配管施工用の円形坑口20に使用されるもので、一枚のシールゴム板100を有した構成である。
本実施例3は、シールゴム板100以外の構成は上記実施例1と同様の構成である。シールゴム板100は、実施例1と同一の環状のフランジ40a、40bの径より少し大きめの円板状に形成され、坑口20のの開口内部に嵌合させて取り付けるときに、坑内壁に隙間なく密着できるようになっている。
さらに円板状のシールゴム板100は、中央部分に向けて、肉厚が徐々に薄くなるとともに、周囲より徐々に高くなるように形成され、且つ突端部分100aが平らに形成されている。シールゴム板100中央の平らな突端部分100aには、推進先行管の径より少し小径の小孔31が開口され、実施例1で述べたように土砂や水等の侵入を防ぎながら、推進先行管を通すことができるようになっている。
【0025】
また、小孔31を設けた平らな突端部分100aを円形に区画する切溝110は、その部分だけ少しゴムの肉厚が薄く溝状に形成され、その切溝110から円形状に切り取りできるようになっている。この切溝110により円形に切り取り可能な突端部分100aの大きさは、配管口径に合わせて設定されている。かかるシールゴム板100の周縁部分は、前記二枚の環状フランジ40a、40bで両側から挟まれている。
また、実施例1と同様の構成を有する蓋50を、その底面部分がシールゴム板100の中央が高くなっている前記切取可能な突端部分100aに接触して設け、シールゴム板100の他方の側に実施例1と同様の補強板80が設けられている。
本実施3では、蓋50周縁部にボルト挿通用に設けた金属製スリーブ51の長さを蓋50の厚みより少し長くして、蓋50の底面部分50aがシールゴム板100の中央の平らで高くなっている突端部分100aに丁度接触できるようになっている。
【0026】
本実施例3でも、上記蓋50、止水器取付部材60、フランジ40a、40b、シールゴム板100、リブ90及び補強板80は、実施例1と同様の構成と要領でボルトBにより共締め固定されている。このようにして、本実施例3では、一枚のシールゴム板100を使用して、配管の推進施工法における二工程推進工法に対応できるようになっている。
また、実施例2のように、シールゴム板100の外径を大きく形成して、硬化剤等の侵入防止機能をより高めるようにしても構わない。
勿論、推進施工時に切溝110で切取可能な突端部分100aを切り取れば、このままの構成で従来の一工程推進工法に使用することもできる。
【0027】
(実施例4)
本実施例4は、図5に示すように、実施例3のシールゴム板100の切溝110を、種々の口径で構成することにより、種々の配管口径に対応して切り取りできるようにしたものである。
本実施例4は、シールゴム板200以外の構成は上記実施例3と同様の構成である。円板状のシールゴム板200は、実施例3と同様に、中央部分に向けて、肉厚が徐々に薄くなるとともに、周囲より徐々に高くなるように形成され、且つ突端部分200aが平らに形成されている。突端部分200aに、推進先行管の径より少し小径の小孔31が開口され、推進先行管を通せるようになっている。
【0028】
また、小孔31の周囲の平らな部分を区画する円形の切溝210は、その部分だけ少しゴムの肉厚が薄く溝状に形成され、その部分を円形状に切り取れるようになっている。切溝210に囲まれたこの突端部分200aの大きさは、配管口径に合わせて設定されている。さらに、上記円形の切溝210の周囲には、切溝210と同心円状にそれより大きな配管口径に合わせた円形の切溝220、230が形成され、使用する配管口径に合わせて切り取り範囲を変えて、適切な口径の穴を形成できるようになっている。
【0029】
上記実施例1、2、3及び4を通じて、坑口止水器Aの形状は、通常使用する丸管に合わせた円形形状に形成されているが、必要に応じて角管等その他の使用管形状に合わせた形状にしても構わない。
また、止水器取付部材60の形状も、上記実施例に限定されるものではなく、本発明の主旨を逸脱しない範囲で種々の変形をしても構わない。
本発明では、シールゴム板に推進先行管用の小孔又は配管用の穴を予め開けておく構成としたが、最初から穴を開けることなく、随時切り取り可能な切溝を設けておくだけの構成とすることもできる。
【0030】
【発明の効果】
本発明により、周辺地盤との摩擦にならず、またマンホール管内の土砂を掘削する装置の邪魔になることなくマンホール管沈設を行うことができ、沈設したマンホール管側面からの配管敷設を、土砂等のマンホール管への流入を防ぎながら推進施工で行うことができる。そのため、従来は鋼矢板で行っていた立坑形成を、掘削しながらマンホール管を漸次沈設して立坑を形成する沈設工法に代えることができ、施工工数等の低減を図ることができる。
さらに、本発明では坑口止水器をそのまま埋め殺しにすることができるため、従来のような坑口止水器の取り外しに伴う工数の削減、及び土砂等の立坑内への流入を確実に防止することができる。
特に、シールゴム板の外径を大きくしたり、或は環状のパッキングを設ける等して、坑口止水器と坑内壁とのシール性が強化されているので、硬化剤等の侵入防止がより確実に行える。
また、推進先行管用のシールゴム板及び配管用のシールゴム板を二枚合わせにしているため、二工程推進工法に対応できる坑口止水器とすることができる。また、シールゴム板に切溝を形成することにより、一枚のシールゴム板で二工程推進工法に対応できる構成となる。切溝を同心円状に形成することにより、種々の配管口径に応じた穴を随時シールゴム板に形成できるので、配管変更等の緊急な作業変更等にも応急対応して作業効率を上げることができるとともに、また種々の口径の穴に応じたシールゴム板を予め在庫する無駄を省くこともできる。
【図面の簡単な説明】
【図1】実施例1に係る坑口止水器の平面図(a)、及び平面図(a)のA−A線で切断した側断面図(b)。側断面図(b)の円で囲んだ部分の部分拡大側断面図(c)。
【図2】実施例1に係る坑口止水器の坑内への取り付け状況を示す部分断面図。
【図3】実施例2に係る坑口止水器の坑内への取り付け状況を示す部分断面図(a)、(b)。
【図4】実施例3に係る坑口止水器の平面図(a)、及び平面図(a)のA−A線で切断した側断面図(b)。側断面図(b)の円で囲んだ部分の部分拡大側断面図(c)。
【図5】実施例4に係る坑口止水器の平面図(a)、及び平面図(a)の円で囲んだ部分の部分拡大側断面図(b)。
【図6】坑口止水器をマンホール管に取り付けた状態を示した斜視図。
【図7】沈設工法の説明図。
【図8】従来の坑口止水器を示す部分平面図(a)、及び部分平面図(a)のA−A線で切断した側断面図(b)。
【符号の説明】
10 マンホール管
20 坑口
30a シールゴム板
30b シールゴム板
31 小孔
32 穴
40a フランジ
40b フランジ
50 蓋
60 止水器取付部材
70a ナット
70b ナット
80 補強板
81 パッキング
90 リブ
100 シールゴム板
110 切溝
200 シールゴム板
210 切溝
220 切溝
230 切溝
A 坑口止水器
B ボルト
[0001]
[Industrial applications]
TECHNICAL FIELD The present invention relates to a water stop device for preventing intrusion of earth and sand, water, and the like provided at a wellhead on a side of a manhole pipe when a pipe such as a drain pipe is propelled and constructed from a side face of a buried manhole pipe.
[0002]
[Prior art]
2. Description of the Related Art Conventionally, drainage pipes and the like are propelled and excavated from inside a manhole toward a buried pipe to connect the pipes. In this construction, a steel sheet pile driven into the side of the shaft is opened by a burner from inside the basement to open a pit for pipe construction, and a pit stop shown in FIG. 8 is attached to the opening of the pit.
In the wellhead stop, a circular rubber plate is placed on one side of the annular flange to prevent the inflow of earth and sand during piping work, and the flange is welded to the hole in the steel sheet pile that was opened by cutting with a burner. The rubber plate is sandwiched and bolted to the annular flange. After that, the pipe is propelled by the propulsion device and the pipe is laid.
After laying the pipes, placing concrete or installing manhole pipes, connecting the above pipes to the manhole pipes, filling the mortar between the surroundings of the construction pipes and the manhole pipe well, and inflow of water, earth and sand, etc. Take a water stoppage measure so that it does not. Then backfill and pull out the sheet pile. It is common to blow off and remove wellhead waterstops.
[0003]
[Problems to be solved by the invention]
However, in the conventional construction method, excavation of a shaft, installation of a steel sheet pile, pipe propulsion from the inside of the shaft, installation of a manhole pipe after completion of the propulsion, backfilling between the manhole pipe and the steel sheet pile, removal of the steel sheet pile, etc. Has taken. In such a construction method, digging, backfilling, and removal of steel sheet piles require a great deal of time, and there has been a strong demand for improvement in terms of reducing construction costs and shortening the construction period.
For this reason, recently, concrete manhole pipes with holes for piping provided in advance in the vertical direction have been sunk while being added in accordance with the excavation depth while gradually excavating in the vertical direction. A method of drilling pipes has been developed. In such a construction method, a conventional well stop was not able to be used, and it was necessary to develop a well stop newly usable for a submerged manhole pipe.
[0004]
In addition, the wellhead stop can be set within the manhole pipe wall thickness so that it does not friction with the surrounding ground when the manhole pipe is laid, and does not get caught on buckets such as clamshells that excavate soil inside the manhole pipe. Must.
In addition, after the pipe is propelled, the structure must be able to be buried and killed without removing the water stop unlike the conventional method.
Furthermore, since a hardening agent for earth and sand is injected into the outer peripheral portion of the manhole pipe that has been previously set, it is necessary to effectively prevent the hardening agent from flowing into the manhole pipe.
Therefore, the present invention is proposed in view of the above problems and necessity, and in the case where a drainage pipe or the like is propelled from the side of a sunk manhole pipe, a wellhead used for a wellhead provided on the side of the manhole pipe. Provide a water bowl.
[0005]
[Means for Solving the Problems]
In order to achieve the above object, the present invention Sunk underground by construction method Manhole tube Formed into For penetration pipe construction to construct propulsion leading pipes and pipes of At the wellhead Be A water stop device which is installed in the well hole Be A flange is provided with a hole through which a pipe propelled after propulsion of the propulsion preceding pipe passes, and a seal rubber plate held by the flange, and a soft member arranged on the outer surface side of the wellhead and fixed to the flange. Cover the wellhead without protruding from the outer surface of the manhole pipe A lid and a detachably attached to the flange from the inside , Supporting the lid and the sealing rubber plate against earth pressure And a reinforcing plate. Further, the well stop device for a side hole of a manhole pipe according to the present invention is arranged within the wall thickness of the manhole pipe without protruding from the inner surface and the outer surface of the manhole pipe.
[0006]
In the mouth stop device for a side hole of a manhole pipe according to the present invention, the seal rubber plate passes through the first seal rubber plate through which the propulsion preceding pipe at the time of piping is penetrated, and the pipe propelled after the propulsion preceding pipe is propelled. The second seal rubber plate provided with a hole is characterized by comprising two sheets. Further, the seal rubber plate is provided with a small hole for a propulsion leading pipe at the time of pipe construction, and a cut groove is formed outside the small hole to form a hole for a pipe through which a pipe propelled after propulsion of the propulsion leading pipe penetrates. It is characterized by having. Further, an outer diameter of the seal rubber plate is formed to be larger than an inner diameter of the wellhead, and an outer edge portion of the seal rubber plate comes into close contact with the well when the well stop is attached to the well.
[0007]
A well stop device for a manhole tube side wellhead according to the present invention includes a bolt that penetrates the flange, the seal rubber plate, the reinforcing plate, and the lid from outside the manhole tube, and a nut that is screwed to the bolt. It is characterized by being tightened together. A substantially annular packing closely attached to the inner peripheral surface of the wellhead is attached to the flange. Further, the lid is made of foamed styrene resin or wood.
[0008]
[Action]
In the wellhead water stop according to the present invention, a seal rubber plate is attached to an annular flange fitted to the wellhead, and the waterstop main body does not protrude from the inner surface and the outer surface of the manhole tube, and the wall of the manhole tube does not protrude. Since the manhole pipe can be set within the thickness, the manhole pipe can be sunk without causing friction with the surrounding ground as much as possible when the manhole pipe is sunk, and without obstructing a device for excavating the earth and sand in the manhole pipe. In addition, since the flange is covered with a lid, this lid side is turned to the outside of the manhole, if a wellhead water stop is attached and sunk, the intrusion of sediment and hardener etc. into the manhole pipe is prevented. be able to.
[0009]
Furthermore, since the hardener is prevented from entering by the lid, the hardener does not harden immediately after the seal rubber plate, and does not arrive, and when the propulsion tube is propelled, the seal rubber plate is cut by the blade at the head of the tube. There is no fear.
In addition, since the lid is formed of a soft member that can be pierced with the propulsion pipe and the pipe, only the propulsion pipe or pipe is propelled from the inside of the manhole pipe at the time of propulsion construction of the pipe, and the necessary holes are covered. Can be opened. In particular, if the lid is made of styrofoam resin or wood, perforation becomes easier.
Further, since the lid member adjacent to the seal rubber plate is formed of a soft member, the seal rubber plate can be effectively prevented from being cut by the blade at the head of the tube when the propulsion tube is propelled.
[0010]
Since a reinforcing plate is provided on the other flange surface, it is possible to prevent the lid or the seal rubber plate from pressing against the inside of the manhole tube against the earth pressure. Furthermore, since this reinforcing plate can be removed, the work can be performed by removing the reinforcing plate during propulsion construction.
When two sealing rubber plates are combined, a small hole for the leading pipe at the time of propulsion construction is provided at approximately the center of the sealing rubber plate near the lid, so the leading pipe is passed through the small hole at the time of propulsion construction Thus, the peripheral portion of the small hole of the seal rubber plate is slightly turned up and closely adheres to the pipe wall of the preceding pipe, so that the preceding pipe can be passed while preventing intrusion of earth and sand, water, and the like. In the construction method in which the hardener is pressed into the periphery of the manhole tube, the hardener can be prevented from entering.
In addition, since a hole for piping is provided substantially at the center of the other seal rubber plate, the peripheral portion of the hole is closely attached to the pipe wall of the pipe in the above-described manner to prevent intrusion of soil, water, etc. After the propulsion of the preceding pipe.
[0011]
On the other hand, when a single sealing rubber plate is formed, the propulsion leading pipe can be passed through the small hole substantially at the center of the sealing rubber plate while preventing intrusion of soil, water, and the like in the above-described manner. Furthermore, since a cut groove is provided around the small hole so that a hole for piping can be formed, while passing through the propulsion leading pipe, it is not cut off from the cut groove to prevent intrusion of soil and the like as it is. When the pipe is passed, the hole for the pipe can be easily formed by cutting from the above-mentioned kerf.
Further, by providing a plurality of cut grooves concentrically around the small hole, the hole diameter can be selected according to various pipe diameters.
Regarding the seal rubber plate, regardless of the configuration of two or one, the outer edge portion of the seal rubber plate is placed along the inner wall of the well when the well stop is attached to the well for penetrating piping on the side of the manhole pipe. The outer diameter is formed larger than the inner diameter of the wellbore so that it can be tightly closed so that water can be stopped.If the waterstop is installed inside the pit from the outside of the manhole pipe, the outer edge of the seal rubber plate is rolled up. Thus, it is possible to more effectively prevent the hardening agent or the like from intruding when the manhole pipe is laid down.
[0012]
Further, the reinforcing plate, between the flange, a bolt inserted from the lid side, a lid, a water stop device mounting member, a nut for fixing together with the flange and the seal rubber plate is interposed, and the nut is further tightened with the nut. Since it is attached, the reinforcement plate can be easily removed without loosening other parts. Except for the reinforcing plate, it is attached to the manhole pipe without loosening, so after propulsion construction, the wellhead stop can be buried and killed. Furthermore, if the propulsion direction or the sunk position is greatly displaced, the flange, the seal rubber plate and the like can be removed by removing the nut. That is, the effective inner diameter of the wellhead can be increased by the amount of the flange.
Furthermore, in such a configuration, since a rib is interposed between the reinforcing plate and the flange, even if a gap is formed between the reinforcing plate and the flange due to the interposition of the nut, the gap is filled with the rib to seal the rubber seal plate. It is supported from behind so that it can withstand the earth pressure.
In addition, on the outer peripheral edge portion between the reinforcing plate and the flange with the rib interposed, a substantially annular packing that is in close contact with the inner wall of the well for through pipe construction on the side of the manhole pipe so as to be able to stop water, the reinforcing plate and the flange. Since the water stop device and the inner wall of the pit are in contact with each other with no space therebetween by interposing the packing, the intrusion of the curing agent or the like when the manhole pipe is laid can be more reliably prevented.
[0013]
【Example】
An embodiment of the present invention will be described with reference to the drawings.
The wellhead stopper of the present invention is a steel sheet pile previously driven into the side of the shaft, opening a wellhead for through pipe construction from the inside of the underground shaft, attaching a wellhead stopper to this, and piping from this wellhead. It is not used for the conventional construction method of propelling construction, etc., but for the submersion construction method of propelling and constructing pipes etc. from the side entrance of the vertical shaft formed by directly laying concrete manhole pipes temporarily while excavating . Therefore, an outline of a submersion method, which is a prerequisite for using the wellhead stoppage device of the present invention, will be described.
[0014]
In the submersion method, as shown in FIG. 7, the ground is first dug shallowly, and a manhole pipe 10 made of concrete is submerged there. Next, while excavating from the inside of the manhole pipe 10, the manhole pipe 10 is gradually sunk using the own weight of the manhole pipe 10 while a hardening agent for preventing soil collapse or the like is injected around the submerged manhole pipe 10. go. Depending on the depth of the shaft to be formed, the manhole pipes are temporarily stacked, and the earth and sand inside the manhole pipe 10 is sunk with a shovel and sunk to a predetermined depth to form a desired shaft.
Then, from the side of the manhole pipe 10 that has been sunk, a construction method in which the propulsion leading pipe B and the pipe C are propelled and constructed in two steps by a propulsion device using a wellhead 20 for through pipe construction previously provided on this side, or This is a construction method in which plumbing is promoted in one process.
The wellhead stop A of the present invention is attached in advance to a wellhead 20 for penetrating piping provided on the side of the manhole pipe 10 used in the above-mentioned construction method, sinks the manhole pipe 10 in the above-described manner to form a shaft, The piping is connected to the side surface of the manhole pipe 10 by propulsion construction while preventing the inflow of earth and sand from the wellhead 20, and the wellhead stop A is directly buried and used.
[0015]
(Example 1)
As shown in FIG. 1, a wellhead stop A of the first embodiment is attached to a wellhead 20 for penetrating piping on the side of a concrete manhole pipe 10 used for the above-mentioned submerging method, and is a two-piece joint. This is a configuration having seal rubber plates 30a and 30b.
The two sealing rubber plates 30a, 30b are sandwiched between the two annular metal flanges 40a, 40b from both sides, so that the shape can be maintained even when a propulsion leading pipe or the like is passed during piping. The flanges 40a and 40b are formed in an annular shape having an outer shape that can be fitted exactly inside the opening of the wellhead 20. The circular openings at the center of the flanges 40a and 40b are set to a size that does not interfere with the construction of the through pipe, and four holes 40c for fixing bolts B to be described later are provided at equal intervals in the peripheral portion. Has been.
[0016]
The seal rubber plate 30a is formed in a thin circular shape, and the seal rubber plate 30b is formed in a thick circular shape. The two are face-to-face with each other, and the peripheral portions thereof are formed on both sides by the two annular flanges 40a and 40b as described above. It is formed so as to be strongly sandwiched in a pressure-bonded state.
The thin seal rubber plate 30a is formed to have a diameter slightly larger than the diameter of the flange 40a, so that when the wellhead stop A is fitted and installed inside the opening of the wellhead 20, it can be closely attached to the inner wall 20a without any gap. It has become. Further, a small hole 31 having a diameter slightly smaller than the diameter of the propulsion leading pipe is formed substantially at the center of the seal rubber plate 30a. When the propulsion precedence pipe is passed through the small hole 31, the rubber at the peripheral portion of the small hole 31 is turned up and adheres to the periphery of the pipe wall of the propulsion precedence pipe, so that earth and sand, water and the like cannot enter the manhole pipe 10. I have.
[0017]
At the approximate center of the other thick seal rubber plate 30b, a circular hole 32 having a diameter slightly smaller than the diameter of the pipe concentric with the small hole 31 and larger than the small hole 31 is formed. In this way, after passing through the propulsion preceding pipe, the pipe can be passed while preventing intrusion of earth, sand, water, etc. into the inside of the manhole pipe 10 in the same manner as when passing the propulsion preceding pipe.
In this embodiment, SBR (styrene-butadiene rubber) is used for the seal rubber plates 30a and 30b. In addition to SBR, NR (natural rubber), CR (chloroprene rubber), NBR (nitrile butadiene rubber), IIR (butyl rubber), EPDM (ethylene propylene rubber) and the like can also be used.
A bolt insertion hole 30c is provided in a peripheral portion of each of the seal rubber plates 30a, 30b at a position that can be referred to as a bolt insertion hole 40c provided in the flange portions 40a, 40b.
[0018]
On the other hand, on the outer surface side of the flange 40a in contact with the thin seal rubber plate 30a, the lid 50 covers the entire circular surface including the annular surface of the flange 40a and the thin seal rubber plate 30a. The lid 50 is formed using a soft member such as styrene foam resin or wood. By providing the lid 50 in this manner, the hardener is prevented from entering the inside of the manhole tube 10 and serves as a margin for deformation of the rubber plate. It is possible to prevent the seal rubber plate 30a from being cut off by being sandwiched between the hardening agent.
Further, as shown in FIGS. 1 (a) and 1 (b), the shape of the lid 50 is tapered so that the outer portion is adapted to the outer peripheral curvature of the side surface of the manhole tube 10 from the YY line toward the peripheral portion. Moreover, the whole is formed in a substantially trapezoidal shape, and when the wellhead stop A is attached to the wellhead 20 of the manhole pipe 10, the front of the wellhead 20 can be closed with the lid 50. In the case where wood is used for the lid 50, it is easier to pierce by providing a cutting blade at the end of the propulsion-side pipe such as the propulsion pipe or pipe.
[0019]
Further, four holes 50c for bolt insertion are also provided on the periphery of the lid 50 at positions that can match the positions of the holes 40c, 30c for bolt insertion of the flanges 40a, 40b and the seal rubber plates 30a, 30b. A metal sleeve 51 through which the screw portion of the bolt B is inserted is inserted into the hole 50c.
The four holes 50c are provided with a water stop device mounting member 60 for providing the water stop A in the well 20 for penetrating piping. The water stop device mounting member 60 is formed in a shape in which a rectangular metal plate is bent in the longitudinal direction according to the curvature of the outer periphery of the manhole tube 10, and a bent portion 61 is formed from a bolt insertion hole 50 c portion of the lid 50. The bolt B is attached together with the other parts by joint tightening so as to project in four directions.
When the well stop A is mounted on the side of the manhole pipe 10, as shown in FIG. 6, the water stop mounting member 60 just crosses over the side of the manhole so as to cross the bent portion 61 into the manhole pipe. It is only necessary that the bolt 10 is bolted from the bolt hole 62 while being in close contact with the outer peripheral surface.
[0020]
The lid 50, the water stop device mounting member 60, the flanges 40a and 40b, and the sealing rubber plates 30a and 30b configured as described above are inserted through the screw portion of the bolt B from the lid 50 side, and the nut 70a is connected to the flange 40b side. They are fixed together.
Further, a reinforcing plate 80 made of a circular iron plate having a diameter substantially equal to the diameter of the flange 40b facing the flange 40b side is provided with the bolt B at a position of a bolt insertion hole 80c provided in a peripheral portion of the reinforcing plate 80. It is inserted and attached by a nut 70b. Between the reinforcing plate 80 and the surface of the flange 40b, there is provided a cross-shaped rib 90 having substantially the same thickness as the nut 70a sandwiched between the surface of the flange 40b and the reinforcing plate 80. , The flanges 40a, 40b and the seal rubber plates 30a, 30b can be supported by the reinforcing plate 80 so as not to be pushed into the inside of the manhole tube 10 by earth pressure.
[0021]
Since the reinforcing plate 80 is configured as described above, the rib 90 and the reinforcing plate 80 can be easily removed without loosening the nut 70a only by removing the nut 70b at the time of propulsion construction.
After the completion of the piping work, mortar is filled in the gap around the manhole pipe and the installed pipe with the reinforcing plate removed, and the wellhead stop is buried.
A substantially rectangular window 80a is opened on both sides of the center of the circular reinforcing plate 80 so that the situation on the sealing rubber plate 30b side from the reinforcing plate 80 can be checked. If the user touches the window 80a, the wellhead stop A is convenient to carry.
When attaching the wellhead stop A to the manhole pipe 10, as shown in FIG. 2, mortar is packed around the gap between the lid 50 of the wellhead stopper A and the inner wall 20a, and the manhole pipe The penetration of a hardening agent, water, and the like used during the precipitation is prevented.
[0022]
(Example 2)
The wellhead stop A used in the second embodiment has the same basic configuration as that of the first embodiment, but as shown in FIGS. 3A and 3B, the inner wall 20a of the wellhead A and the wellhead A The structure further enhances the function of preventing the intrusion of a hardener, water, or the like from a gap portion between them.
In the wellhead stop A shown in FIG. 3A, the outer diameter of the thinner sealing rubber plate 30 a of the wellhead stopper A shown in the first embodiment is formed larger than the inner diameter of the wellhead 20. The outer diameter of the seal rubber plate 30a is set such that the outer peripheral edge portion of the seal rubber plate 30a is located outside the manhole tube 10 at the wellhead 20 as shown in FIG. The outer peripheral edge portion is turned so as to be able to come into close contact with the wellhead inner wall 20a. In this manner, even if a hardening agent, water, or the like intrudes into the pit from the wellhead 20, it can be effectively prevented by the outer peripheral edge portion of the seal rubber plate 30 a whose entire circumference is in close contact with the wellhead inner wall 20 a. ing.
In this embodiment, the outer diameter of the seal rubber plate 30a is increased. For example, a thin rubber ring is integrally formed on the outer peripheral portion of the thick seal rubber plate 30b so as to be able to be in close contact with the inner wall 20a as described above. It may be formed.
[0023]
In the wellhead stop A shown in FIG. 3B, an annular packing 81 is provided on the outer peripheral edge of the reinforcing plate 80 and the flange 40 b of the wellhead stop A of the first embodiment. The packing 81 is formed of a material such as rubber sponge, and is formed in an annular shape slightly larger than the inner diameter of the wellhead 20. Therefore, when the wellhead stop A is set in the pit, the packing 81 of the wellhead A is in close contact with the inner wall 20a as shown in FIG. 3B. Therefore, even if a hardening agent, water, or the like intrudes into the pit from the wellhead 20, it can be effectively prevented by the packing 81 whose entire circumference is in close contact with the wellhead inner wall 20 a.
Further, the packing 81 is used in combination with the configuration in which the outer diameter of the sealing rubber plate 30a is increased as described above, or when the wellhead stop A is set as shown in FIG. By filling the space between the outer periphery of the pit 50 and the pit wall 20a with mortar, the function of preventing the hardener or the like from entering the pit can be further enhanced.
[0024]
(Example 3)
As shown in FIG. 4, a wellhead stop A used in the third embodiment is used for a circular wellhead 20 for penetrating piping provided on the side of a concrete manhole pipe 10, and one seal rubber is used. This is a configuration having a plate 100.
The third embodiment is similar to the first embodiment except for the configuration of the seal rubber plate 100. The seal rubber plate 100 is formed in a disk shape slightly larger than the diameter of the same annular flanges 40a and 40b as in the first embodiment, and when fitted and mounted inside the opening of the wellhead 20, there is no gap on the inner wall of the well. It can be closely attached.
Further, the disk-shaped seal rubber plate 100 is formed so that the thickness gradually becomes thinner toward the center portion and becomes gradually higher than the periphery, and the protruding end portion 100a is formed flat. A small hole 31 having a diameter slightly smaller than the diameter of the propulsion leading pipe is opened in the flat protruding end portion 100a at the center of the sealing rubber plate 100, and as described in the first embodiment, while preventing intrusion of earth and sand, water, etc. Can be passed through.
[0025]
In addition, the incision 110 which partitions the flat protruding end portion 100a provided with the small hole 31 into a circle is formed in a groove shape having a slightly thinner rubber thickness only in that portion, and can be cut out from the incision groove 110 in a circular shape. It has become. The size of the protruding end portion 100a that can be circularly cut by the cut groove 110 is set according to the pipe diameter. The peripheral portion of the sealing rubber plate 100 is sandwiched between the two annular flanges 40a and 40b from both sides.
In addition, a lid 50 having the same configuration as that of the first embodiment is provided in contact with the cut-out protruding end portion 100 a whose bottom portion is higher in the center of the seal rubber plate 100, and is provided on the other side of the seal rubber plate 100. A reinforcing plate 80 similar to that of the first embodiment is provided.
In the third embodiment, the length of the metal sleeve 51 provided for bolt insertion in the peripheral portion of the lid 50 is slightly longer than the thickness of the lid 50 so that the bottom portion 50 a of the lid 50 is flat and high at the center of the seal rubber plate 100. It can be brought into contact with the protruding tip portion 100a.
[0026]
Also in the third embodiment, the lid 50, the water stop device mounting member 60, the flanges 40a and 40b, the sealing rubber plate 100, the rib 90, and the reinforcing plate 80 are fixed together by bolts B in the same configuration and manner as in the first embodiment. Have been. As described above, in the third embodiment, a single sealing rubber plate 100 is used, so that it is possible to cope with the two-step propulsion construction method in the plumbing construction method.
Further, as in the second embodiment, the outer diameter of the seal rubber plate 100 may be formed large to further enhance the function of preventing the intrusion of the curing agent or the like.
Of course, if the protruding end portion 100a that can be cut off by the cutting groove 110 is cut off during the propulsion construction, the structure can be used as it is in a conventional one-step propulsion method.
[0027]
(Example 4)
In the fourth embodiment, as shown in FIG. 5, by forming the cut grooves 110 of the seal rubber plate 100 of the third embodiment with various diameters, it is possible to cut out corresponding to various pipe diameters. is there.
The fourth embodiment has the same configuration as that of the third embodiment except for the configuration of the seal rubber plate 200. As in the third embodiment, the disk-shaped seal rubber plate 200 is formed so that the thickness gradually decreases toward the center portion and gradually increases from the periphery, and the protruding end portion 200a is formed flat. Have been. A small hole 31 having a diameter slightly smaller than the diameter of the propulsion leading pipe is opened in the protruding end portion 200a so that the propulsion leading pipe can pass therethrough.
[0028]
In addition, the circular incision 210 that defines a flat portion around the small hole 31 is formed in a groove having a slightly thinner rubber thickness in that portion, and the portion can be cut in a circular shape. . The size of the protruding end portion 200a surrounded by the cut groove 210 is set according to the pipe diameter. Further, around the circular cut groove 210, circular cut grooves 220 and 230 are formed concentrically with the cut groove 210 and adapted to a larger pipe diameter, and the cutting range is changed according to the pipe diameter to be used. Thus, a hole having an appropriate diameter can be formed.
[0029]
Through the above Examples 1, 2, 3 and 4, the wellhead water stop A is formed in a circular shape in accordance with a generally used round tube, but if necessary, other used tube shapes such as a square tube are used. The shape may be adjusted according to the shape.
Further, the shape of the water stoppage mounting member 60 is not limited to the above embodiment, and various modifications may be made without departing from the gist of the present invention.
In the present invention, a small hole for the propulsion pipe or a hole for piping is previously formed in the seal rubber plate, but without providing a hole from the beginning, a structure in which only a cut groove that can be cut off at any time is provided. You can also.
[0030]
【The invention's effect】
According to the present invention, the manhole pipe can be laid without causing friction with the surrounding ground and without obstructing a device for excavating the earth and sand in the manhole pipe. It can be done by propulsion construction while preventing inflow into the manhole pipe. For this reason, the shaft formation conventionally performed with steel sheet piles can be replaced with a sinking method in which a manhole pipe is gradually settled while excavating to form a shaft, and the number of construction steps and the like can be reduced.
Furthermore, in the present invention, since the wellhead stoppage can be buried and killed as it is, the man-hour associated with the removal of the wellhead stoppage as in the prior art can be reduced, and the inflow of earth and sand into the shaft can be reliably prevented. be able to.
In particular, by increasing the outer diameter of the seal rubber plate or by providing an annular packing, the sealing performance between the well stop and the inner wall of the well is strengthened, so that the hardener and the like can be more reliably prevented from entering. Can be done.
In addition, since the seal rubber plate for the propulsion leading pipe and the seal rubber plate for the piping are combined, it is possible to provide a wellhead stop that can be used in a two-step propulsion method. In addition, by forming a cut groove in the seal rubber plate, a configuration in which one seal rubber plate can cope with the two-step propulsion method is provided. By forming the cut grooves concentrically, holes corresponding to various pipe diameters can be formed in the seal rubber plate at any time, so that the work efficiency can be improved by urgently responding to urgent work changes such as pipe changes. In addition, it is also possible to eliminate the waste of stocking seal rubber plates corresponding to holes of various diameters in advance.
[Brief description of the drawings]
FIG. 1 is a plan view (a) of a wellhead water stop according to a first embodiment, and a side cross-sectional view (b) taken along line AA of the plan view (a). Partial enlarged side sectional view (c) of the part circled in the side sectional view (b).
FIG. 2 is a partial cross-sectional view showing a state where the well stop device according to the first embodiment is installed in a pit.
FIGS. 3A and 3B are partial cross-sectional views showing how a wellhead water stop according to a second embodiment is installed in a pit.
FIG. 4 is a plan view (a) of a wellhead water stop according to a third embodiment, and a side cross-sectional view (b) taken along line AA of the plan view (a). Partial enlarged side sectional view (c) of the part circled in the side sectional view (b).
FIG. 5 is a plan view (a) of a wellhead water stop according to a fourth embodiment, and a partially enlarged side cross-sectional view (b) of a portion surrounded by a circle in the plan view (a).
FIG. 6 is a perspective view showing a state in which a wellhead water stop is attached to a manhole pipe.
FIG. 7 is an explanatory view of a laying method.
FIG. 8 is a partial plan view (a) showing a conventional wellhead water stop, and a side cross-sectional view (b) cut along line AA of the partial plan view (a).
[Explanation of symbols]
10 Manhole tube
20 wellhead
30a Seal rubber plate
30b Seal rubber plate
31 small hole
32 holes
40a flange
40b flange
50 lid
60 Water stop device mounting member
70a nut
70b nut
80 Reinforcement plate
81 packing
90 rib
100 Seal rubber plate
110 kerf
200 Seal rubber plate
210 Groove
220 kerf
230 kerf
A wellhead stop
B bolt

Claims (7)

沈設工法により地中に沈設されるマンホール管に形成されて推進先行管および配管を施工するための貫通配管施工用坑口に設けられる坑口止水器であって、
前記坑口に組み付けられるフランジと、
前記推進先行管の推進後に推進される配管が通る穴が設けられ、前記フランジに保持されるシールゴム板と、
前記坑口の外面側に配置して前記フランジに固定される軟質部材よりなり、前記坑口を前記マンホール管の外面から出っ張ることなく覆う蓋と、
前記フランジに内側から撤去可能に取り付けられ、前記蓋および前記シールゴム板を土圧に抗して支持する補強板とを有することを特徴とするマンホール管側面坑口用の坑口止水器。
A wellhead water stop device that provided the wellhead of through-pipe construction for applying a propulsion preceding tube and pipe are formed in the manhole tube is sinking into the ground by sinking method,
A flange assembled to the wellhead;
A hole through which a pipe propelled after propulsion of the propulsion preceding pipe is provided, and a seal rubber plate held by the flange,
Ri Na softer member fixed to the flange disposed on the outer surface of the wellhead, a lid covering without protrude the wellhead from the outer surface of the manhole tube,
A water stop device for a side hole of a manhole pipe , comprising: a reinforcing plate that is removably attached to the flange from the inside and supports the lid and the seal rubber plate against earth pressure .
前記マンホール管の内面および外面からそれぞれ出っ張ることなく前記マンホール管の壁厚内に配置されることを特徴とする請求項1記載のマンホール管側面坑口用の坑口止水器。2. The well stop device for a side hole of a manhole tube according to claim 1, wherein the water stop device is disposed within the wall thickness of the manhole tube without protruding from the inner surface and the outer surface of the manhole tube. 前記シールゴム板は、配管施工時の推進先行管が貫通する第1のシールゴム板と、前記推進先行管の推進後に推進される配管が通る穴が設けられた第2のシールゴム板との2枚よりなることを特徴とする請求項1または2記載のマンホール管側面坑口用の坑口止水器。The seal rubber plate is composed of a first seal rubber plate through which a propulsion leading pipe at the time of piping is penetrated, and a second seal rubber plate provided with a hole through which a pipe propelled after propulsion of the propulsion preceding pipe is provided. The well stop device for a side hole of a manhole pipe according to claim 1 or 2, wherein 前記シールゴム板に配管施工時の推進先行管用の小孔を設けるとともに、前記小孔の外側に推進先行管の推進後に推進される配管が貫通する配管用の穴を形成する切り溝を設けたことを特徴とする請求項1〜3のいずれか1項に記載のマンホール管側面坑口用の坑口止水器。The seal rubber plate is provided with a small hole for a propulsion leading pipe at the time of piping construction, and a cut groove is formed outside the small hole to form a pipe hole through which a pipe propelled after propulsion of the propulsion leading pipe penetrates. The well stop device for a side hole of a manhole pipe according to any one of claims 1 to 3, characterized in that: 前記シールゴム板の外径は前記坑口の内径よりも大きく形成され、前記坑口止水器を前記坑口に取り付ける際に前記シールゴム板の外縁部分が前記坑口に密接することを特徴とする請求項1〜4のいずれか1項に記載のマンホール管側面坑口用の坑口止水器。The outer diameter of the seal rubber plate is formed to be larger than the inner diameter of the wellhead, and the outer edge portion of the seal rubber plate comes into close contact with the well when the well stop is attached to the well. 4. The pit stop for a manhole pipe side pit according to any one of the items 4 to 5. 前記坑口の内周面に密接するパッキングを前記フランジに取り付けたことを特徴とする請求項1〜のいずれか1項に記載のマンホール管側面坑口用の坑口止水器。The well stop device for a side hole of a manhole pipe according to any one of claims 1 to 5 , wherein a packing closely contacting an inner peripheral surface of the well hole is attached to the flange. 前記蓋が発砲スチロール樹脂または木材で形成されていることを特徴とする請求項1〜のいずれか1項に記載のマンホール管側面坑口用の坑口止水器。The well stop device for a manhole pipe side wellhead according to any one of claims 1 to 6 , wherein the lid is formed of foamed styrene resin or wood.
JP32995194A 1994-12-05 1994-12-05 Well stop device for side hole of manhole pipe Expired - Fee Related JP3599394B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP32995194A JP3599394B2 (en) 1994-12-05 1994-12-05 Well stop device for side hole of manhole pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP32995194A JP3599394B2 (en) 1994-12-05 1994-12-05 Well stop device for side hole of manhole pipe

Publications (2)

Publication Number Publication Date
JPH08158391A JPH08158391A (en) 1996-06-18
JP3599394B2 true JP3599394B2 (en) 2004-12-08

Family

ID=18227092

Family Applications (1)

Application Number Title Priority Date Filing Date
JP32995194A Expired - Fee Related JP3599394B2 (en) 1994-12-05 1994-12-05 Well stop device for side hole of manhole pipe

Country Status (1)

Country Link
JP (1) JP3599394B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002285785A (en) * 2001-03-26 2002-10-03 Japan Found Eng Co Ltd Waterstop and drilling method using it

Also Published As

Publication number Publication date
JPH08158391A (en) 1996-06-18

Similar Documents

Publication Publication Date Title
JP3762017B2 (en) Wellhead water stop for manhole pipe side wellhead
JP3599394B2 (en) Well stop device for side hole of manhole pipe
JP5653868B2 (en) Structure joint water stop structure and water stop method
JP2002220991A (en) Partition wall installed in main-tunnel shield tunnel and construction method therefor
JP2018003264A (en) Pipeline connection structure and construction method for the same
JP3177468B2 (en) Standing block, standing excavation method and sewer propulsion method
JP3776987B2 (en) Vertical shaft construction method using a manhole wall combined tubular body
JP3196697U (en) Shaft casing
JP2576945B2 (en) Construction method of manhole combined sinking pit and cutting edge to promote sinking
JP3882572B2 (en) Shield tunnel connection structure
JPH0223633Y2 (en)
JPH11117686A (en) Segment corresponding to opening covered with resin on inner surface
JP4086400B2 (en) Propulsion shaft, its construction method and propulsion method
JP7243305B2 (en) Water stop structure of steel pipe sheet pile joint
JP2985063B2 (en) Caisson prefabricated manhole and its construction method
JP3615594B2 (en) Piping laying method and piping structure
JPH1162466A (en) Receiving method of shield boring machine into arrival shaft, and structure of receiving part of shield boring machine in arrival shaft
JP4275296B2 (en) A sinking body having an opening forming portion structure
JPH02115420A (en) Execution method for assembly manhole and body block for assembly manhole
JP2001026937A (en) Manhole joint and its connecting work method
JP6009294B2 (en) Manhole construction method using steel circular casing
JP2011241614A (en) Earthquake resisting method for existing manhole
JPH06346683A (en) Retaining material for shaft
JP4010966B2 (en) Barrier pipe for impermeable wall installation
JPH07127051A (en) Construction and erecting method for reinforcement cage for continuous underground wall execution

Legal Events

Date Code Title Description
A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20040518

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20040720

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20040831

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20040914

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070924

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080924

Year of fee payment: 4

LAPS Cancellation because of no payment of annual fees