JPH0788759B2 - Tunnel lining method - Google Patents

Tunnel lining method

Info

Publication number
JPH0788759B2
JPH0788759B2 JP61205809A JP20580986A JPH0788759B2 JP H0788759 B2 JPH0788759 B2 JP H0788759B2 JP 61205809 A JP61205809 A JP 61205809A JP 20580986 A JP20580986 A JP 20580986A JP H0788759 B2 JPH0788759 B2 JP H0788759B2
Authority
JP
Japan
Prior art keywords
lining
tunnel
secondary lining
prefabricated plate
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP61205809A
Other languages
Japanese (ja)
Other versions
JPS6363899A (en
Inventor
恭孝 中島
元男 江口
毅熾 栄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP61205809A priority Critical patent/JPH0788759B2/en
Publication of JPS6363899A publication Critical patent/JPS6363899A/en
Publication of JPH0788759B2 publication Critical patent/JPH0788759B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 <産業上の利用分野> 本発明はシールドトンネルや山岳トンネル等のトンネル
の覆工法に関するものである。
The present invention relates to a method of lining tunnels such as shield tunnels and mountain tunnels.

<従来の技術> 掘削直後の地山を覆工するに際し、一次覆工と二次覆工
の二度の覆工を施工する新オーストリアトンネル工法
(NATM工法)が存在する。
<Conventional technology> There is a new Austrian tunnel method (NATM method) that performs two linings, a primary lining and a secondary lining, when lining the ground immediately after excavation.

この工法の一次覆工は掘削直後の地山の崩壊防止を目的
とした支保層であり、一般にはコンクリートの吹き付け
によって施工されている。
The primary lining of this method is a support layer for the purpose of preventing collapse of the ground immediately after excavation, and is generally constructed by spraying concrete.

また、二次覆工は一次覆工と協動した支保を目的とする
他に、トンネル内の外観整備と止水を目的とした施工さ
れ、一般には鋼製の移動型枠装置を使用した場所打ちコ
ンクリートで構築される。
In addition to the purpose of supporting the secondary lining in cooperation with the primary lining, the secondary lining was constructed for the purpose of maintaining the exterior of the tunnel and stopping water. Generally, it is a place where a mobile formwork device made of steel is used. Constructed of poured concrete.

<本発明が解決しようとする問題点> 前述したトンネルの覆工技術には次のような問題点が存
在する。
<Problems to be Solved by the Present Invention> The above-mentioned tunnel lining technique has the following problems.

(イ)二次覆工用の移動型枠装置がトンネルの作業空間
の大半を占有するため、排土作業や坑内への各種資材の
搬入作業あるいは作業者の通行に不便である。
(A) Since the movable formwork device for the secondary lining occupies most of the work space of the tunnel, it is inconvenient for the work of discharging soil, carrying in various materials into the mine, or passing by workers.

(ロ)二次覆工は掘削作業が完了した後に施工されてい
る。
(B) The secondary lining is constructed after the excavation work is completed.

そのため、全体としての工期が長くかかる。Therefore, it takes a long construction period as a whole.

(ハ)一次覆工および二次覆工を施工するに当たり、十
分な設計強度を持たせて施工するわけであるが、実際に
は地盤の変形量が大きい等の理由でコンクリートに亀裂
を生じると止水する部材が存在しないので止水性の点で
問題が残る。
(C) When constructing the primary and secondary linings, the construction should be done with sufficient design strength, but in reality, if cracks occur in the concrete due to large deformation of the ground, etc. Since there is no member for stopping water, there remains a problem in terms of water stopping.

(ニ)常時トンネル内を監視して漏水の発見と補修を強
いられるため、メンテナンスの経費が高くつく。
(D) Maintenance costs are high because the inside of the tunnel is constantly monitored to detect and repair leaks.

(ホ)トンネルの掘削径を決定する場合、理論的には一
次覆工と二次覆工の設計巻立厚によって決定されるわけ
であるが、実際には地山の凹凸の影響で覆工の巻立厚に
差が出るため、その分トンネルの掘削径を大きく設定し
ている。
(E) When deciding the tunnel excavation diameter, it is theoretically determined by the design winding thickness of the primary lining and secondary lining, but in reality, the lining is affected by the unevenness of the ground. Since there is a difference in the roll-up thickness, the tunnel excavation diameter is set larger accordingly.

しかし、トンネルの掘削径がわずかでも大きくなると、
土砂の掘削量は掘削長に比例して莫大となり、掘削に要
する時間および経費が増加する。
However, if the excavation diameter of the tunnel increases even slightly,
The amount of earth and sand excavated will be enormous in proportion to the excavation length, and the time and cost required for excavation will increase.

<本発明の目的> 本発明は以上の点に鑑みなされたもので、次のようなト
ンネルの覆工法を提供することを目的とする。
<Object of the present invention> The present invention has been made in view of the above points, and an object thereof is to provide a tunnel covering method as follows.

(イ)二次覆工が薄肉であって止水性に優れたトンネル
の覆工法。
(B) A tunnel lining method in which the secondary lining is thin and has excellent waterproofness.

(ロ)工期の大幅な短縮が可能なトンネルの覆工法。(B) A tunnel lining method that can significantly reduce the construction period.

(ハ)高品質で品質管理が容易な、トンネルの覆工法。(C) Tunnel lining method with high quality and easy quality control.

(ニ)トンネルの掘削径を縮径できる、トンネルの覆工
法。
(D) A tunnel lining method that can reduce the tunnel excavation diameter.

<本発明の構成> 以下、図面を参照しながら本発明の一実施例について説
明する。
<Structure of the Present Invention> An embodiment of the present invention will be described below with reference to the drawings.

なお、本実施例ではシールドトンネルの場合について説
明する。
In this embodiment, the case of a shield tunnel will be described.

<イ>トンネル断面の構造 第1、2図に本発明に係るトンネルの断面を示す。<B> Tunnel Cross Section Structure FIGS. 1 and 2 show the cross section of the tunnel according to the present invention.

1は一次覆工材としてのセグメントであり、2は二次覆
工材としてのプレハブ版であり、3はセグメント1とプ
レハブ版2の間に介在する止水材である。
Reference numeral 1 is a segment as a primary lining material, 2 is a prefabricated plate as a secondary lining material, and 3 is a water blocking material interposed between the segment 1 and the prefabricated plate 2.

従来の二次覆工は厚巻のコンクリート体であったが、本
発明では現場組立て式で薄肉のプレハブ版2を二次覆工
として使用する。
The conventional secondary lining was a thick-rolled concrete body, but in the present invention, a prefabricated plate 2 of the field assembly type and thin is used as the secondary lining.

また、セグメント1とプレハブ版2の間に止水材3を介
在してトンネルの止水性を改善した。
Further, the water blocking material 3 is interposed between the segment 1 and the prefabricated plate 2 to improve the water blocking performance of the tunnel.

<ロ>プレハブ版(第3図) プレハブ版2は、二次覆工としての仕上げ材であるとと
もに、止水材3を介在する際の型枠材としても機能する
湾曲した分割板であって、薄肉、軽量であって高強度の
素材で形成する。
<B> Prefabricated plate (Fig. 3) The prefabricated plate 2 is a curved dividing plate that functions as a finishing material as a secondary lining and also as a form material when the water blocking material 3 is interposed. Made of thin, lightweight, high-strength material.

このプレハブ版2は工場で高品質に製造できるPIC板やP
C板等のプレキャスト板を使用できる。
This prefab plate 2 is a PIC board or P that can be manufactured in high quality at the factory.
A precast plate such as C plate can be used.

プレハブ版2の板面には、注入孔21と取付孔22を開設す
る。
An injection hole 21 and a mounting hole 22 are formed in the plate surface of the prefabricated plate 2.

次にトンネルの施工法について説明する。(第1〜3
図) <1>掘削 シールドマシーン4を発進立坑A内に吊り降ろして掘削
を開始する。
Next, a tunnel construction method will be described. (First to third
Figure) <1> Excavation The shield machine 4 is suspended in the starting shaft A to start excavation.

<2>一次覆工 掘削作業と並行して、坑内にセグメント1を搬入して組
み立てて、掘削直後の地山を順次覆工していく。
<2> Primary lining In parallel with the excavation work, segment 1 will be loaded into the mine and assembled, and the ground immediately after excavation will be lined up sequentially.

セグメント1は、シールドマシン4に装備されたエレク
タ装置で吊り上げ、各セグメント1をボルト止めして組
み立てる。
The segment 1 is hoisted by an erector device installed in the shield machine 4, and each segment 1 is bolted to assemble.

また、セグメント1と地山7との間に発生した空隙内に
は、公知の要領で裏込材8を充填する。
In addition, the backfill material 8 is filled in the space generated between the segment 1 and the ground 7 in a known manner.

次にセグメント1の底部にPCコンクリート製の枕木5を
水平に配置して順次固定する。
Next, a sleeper 5 made of PC concrete is horizontally arranged on the bottom of the segment 1 and sequentially fixed.

枕木5の上面にレール51を取付け、各種運搬車の通孔路
を形成する。
A rail 51 is attached to the upper surface of the sleeper 5 to form a passageway for various vehicles.

また、各枕木5の間には、トンネル方向にPC板52を敷設
していく。
A PC board 52 is laid between the sleepers 5 in the tunnel direction.

<3>二次覆工 トンネルの掘進作業および一次覆工作業と並行して二次
覆工を行う。
<3> Secondary lining Secondary lining is performed in parallel with tunnel excavation work and primary lining work.

この二次覆工作業は、工場で生産したプレハブ版2を坑
内に運搬し、セグメント1の内方でボルト止めして組み
立てる。
In this secondary lining work, the prefabricated plate 2 produced in the factory is transported to the mine and bolted inside the segment 1 for assembly.

すなわち、各プレハブ版2の円周方向間の接続は、第4
図に示すようにシール材6を介在して連結ボルト23とナ
ット24で締結して円環状に組み立てていく。
That is, the connection between the circumferential directions of the prefabricated plates 2 is the fourth.
As shown in the figure, the seal member 6 is interposed and the connecting bolt 23 and the nut 24 are fastened together to assemble in an annular shape.

なお、第4図において25はフランジ26をプレハブ版2の
端面に固定するためのスタッドである。
In FIG. 4, reference numeral 25 is a stud for fixing the flange 26 to the end face of the prefabricated plate 2.

また、各プレハブ版2のトンネル軸方向間の接続は、第
5図に示すように一方のプレハブ版2の一側に取り付け
た断面クランク形のフランジ27と、他のプレハブ版2の
側面間にシール材61を介在させて接続する。
Further, as shown in FIG. 5, the connection between the prefabricated plates 2 in the direction of the tunnel axis is made between the flange 27 having a crank-shaped cross section attached to one side of the prefabricated plate 2 and the side surface of the other prefabricated plate 2. Connection is made with a sealant 61 interposed.

さらにプレハブ版2の取付孔22内には固定ボルト28を貫
通し、固定ボルト28の先端をセグメント1の板に凹設し
た埋込みナット11に螺合して固定する。(第6図) このとき、プレハブ版2はセグメント1の内周に密着さ
せるのではなく、セグメント1の内周との間に連続した
間隙を確保して組み立てる。
Further, a fixing bolt 28 is passed through the mounting hole 22 of the prefabricated plate 2, and the tip of the fixing bolt 28 is screwed and fixed to an embedded nut 11 recessed in the plate of the segment 1. (FIG. 6) At this time, the prefabricated plate 2 is not brought into close contact with the inner circumference of the segment 1, but is assembled while ensuring a continuous gap with the inner circumference of the segment 1.

プレハブ版2の組み立てに際し、プレハブ版2の内径は
仕上がり内径に合わせて組み立てる。
When assembling the prefabricated plate 2, the inner diameter of the prefabricated plate 2 is assembled according to the finished inner diameter.

<4>止水材の注入 円環状にプレハブ版2を一定スパン組み立てたら、プレ
ハブ版2の注入孔21に止水材注入用のホースを接続し
て、セグメント1とプレハブ版2の周面間に止水材3を
注入する。
<4> Injecting the waterproof material After the prefabricated plate 2 is assembled into a ring with a constant span, connect a hose for injecting the waterproof material to the injection hole 21 of the prefabricated plate 2, and connect the peripheral surface between the segment 1 and the prefabricated plate 2. Inject the water blocking material 3 into the.

止水材3としては、例えばハイタイベックスモルタル、
タスコンモルタル等を使用できる。
As the water blocking material 3, for example, high tyvex mortar,
Tascon mortar etc. can be used.

止水材3はセグメント1とプレハブ版2の間の間隙の全
域に行き渡るまで注入する。
The water blocking material 3 is poured until it reaches the entire area of the gap between the segment 1 and the prefabricated plate 2.

以上の掘削作業、一次覆工作業、二次覆工作業および止
水材3の注入作業の各作業をそれぞれ並行して行いなが
ら、所定の長さのトンネルを完成させる。
The above-mentioned excavation work, primary lining work, secondary lining work, and work of injecting the water blocking material 3 are carried out in parallel while completing a tunnel of a predetermined length.

<その他の実施例> 前記実施例は二次覆工を掘削作業や一次覆工と並行して
行う場合について説明したが、掘削作業の後に二次覆工
を一括して行うことも可能である。
<Other Examples> In the above examples, the case where the secondary lining is performed in parallel with the excavation work and the primary lining has been described, but it is also possible to collectively perform the secondary lining after the excavation work. .

この場合には、任意の位置でプレハブ版2を組立てるこ
とが可能であり、二次覆工版の組立て効率が向上する。
In this case, the prefabricated plate 2 can be assembled at any position, and the efficiency of assembling the secondary lining plate is improved.

また、セグメントを使用しない山岳トンネルの覆工や推
進管の二次覆工としても使用できる。
It can also be used as a lining for mountain tunnels without segments and as a secondary lining for propulsion pipes.

<本発明の効果> 本発明は以上説明したようになるから次のような効果を
得ることができる。
<Effects of the Present Invention> Since the present invention is as described above, the following effects can be obtained.

(イ)一次覆工と二次覆工の周面間に連続して止水材を
介在させ、また二次覆工のプレハブ版の接続面の間にも
シール材を介在して止水処理を施した。
(A) Water-stopping material is continuously interposed between the peripheral surfaces of the primary and secondary linings, and a sealing material is also interposed between the prefabricated plate connecting surfaces of the secondary linings Was applied.

そのため、巻立厚の薄い二次覆工であっても、高い止水
効果が得られ、そのうえメンテナンス経費を軽減でき
る。
Therefore, even with a secondary lining having a thin roll thickness, a high water-stopping effect can be obtained, and the maintenance cost can be reduced.

(ロ)コンクリート製の巻立圧の大きいコンクリートで
二次覆工する従来技術によるトンネル掘削径と、本発明
のトンネル掘削径とを比較すると、本発明では二次覆工
材として薄肉とプレハブ版を使用するため、従来に比べ
てトンネル掘削径を縮径できる。
(B) Comparing the tunnel excavation diameter of the prior art in which the secondary lining is made with concrete with a high roll-up pressure and the tunnel excavation diameter of the present invention, in the present invention, a thin wall and a prefabricated plate are used as the secondary lining material. Therefore, the tunnel excavation diameter can be reduced compared to the conventional one.

従って、土砂の掘削量が減り、経済的に掘削できる。Therefore, the amount of excavated earth and sand is reduced, and it is possible to excavate economically.

(ハ)掘進作業、一次覆工作業、二次覆工作業および止
水材の注入作業の各作業をそれぞれ並行して行える。
(C) The excavation work, the primary lining work, the secondary lining work, and the injection work of the waterproofing material can be performed in parallel.

また、従来のような二次覆工の養生期間が不要となる。In addition, the conventional curing period for the secondary lining is unnecessary.

従って、全体の工期を著しく短縮でき、施工費を節約で
きる。
Therefore, the whole construction period can be remarkably shortened and the construction cost can be saved.

(ニ)二次覆工は軽量なプレハブ版を運搬して作業者が
現場で組み立てている。
(D) For the secondary lining, workers carry the lightweight prefabricated plates and assemble them on site.

そのため、二次覆工作業を行うための大型機械は不要で
あり、トンネル内の作業空間を、例えば排土作業、一次
覆工資材の搬入作業、作業者の通行にと有効に使用でき
る。
Therefore, a large machine for performing the secondary lining work is unnecessary, and the work space in the tunnel can be effectively used for, for example, soil discharging work, loading work of the primary lining material, and passage of workers.

(ホ)二次覆工材であるプレハブ版は、工場で高品質に
生産したものを使用する。
(E) For the prefabricated plate that is the secondary lining material, use the one produced with high quality at the factory.

従って、二次覆工の品質管理が容易である。Therefore, the quality control of the secondary lining is easy.

(ヘ)従来技術には、ゴム、プラスチック、合成樹脂フ
ィルム等の薄いシート材を用いて止水層を形成する方法
があるが、このような方法では止水層の強度が小さく、
さらに止水性にも限界がある。
(F) In the prior art, there is a method of forming a water blocking layer using a thin sheet material such as rubber, plastic, or a synthetic resin film. However, in such a method, the strength of the water blocking layer is small,
Furthermore, there is a limit to the waterproofness.

それに対して本発明は、二次覆工を型枠代わりにして、
一次覆工と二次覆工との周面間に止水材を充填して止水
層を形成する方法であるため、肉厚な壁体状の止水層を
形成でき、高い止水性と止水層の大きな強度を得ること
ができる。
On the other hand, the present invention uses the secondary lining as a formwork,
Since it is a method of forming a water blocking layer by filling a water blocking material between the peripheral surfaces of the primary lining and the secondary lining, it is possible to form a thick wall-shaped water blocking layer and to achieve high water blocking performance. Greater strength of the water blocking layer can be obtained.

【図面の簡単な説明】[Brief description of drawings]

第1図:本発明に係るトンネルの覆工方法の説明図 第2図:第1図のII−IIの断面図 第3図:プレハブ版の組立て時の説明図 第4、5図:プレハブ版の接続方法の説明図 第6図:プレハブ版をセグメントに固定する固定方法の
説明図
FIG. 1: Illustration of tunnel lining method according to the present invention FIG. 2: Sectional view taken along line II-II of FIG. 1 FIG. 3: Illustration of prefabricated plate during assembly FIGS. 4 and 5: Prefabricated plate Illustration of the connection method of Fig. 6: Illustration of the fixing method for fixing the prefab plate to the segment

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】掘削作業と並行して掘削直後の地山に一次
覆工を施工し、 掘削作業と並行して一次覆工の内方に既製の分割体を組
立てて二次覆工を施工し、 一次覆工と二次覆工の周面間に連続した間隙を確保し、 前記連続空間内に止水材を注入して一次覆工と二次覆工
との間に止水層を形成して行うことを特徴とする、 トンネルの覆工法
1. A primary lining is constructed on the ground immediately after the excavation work in parallel with the excavation work, and a secondary division is constructed by assembling a ready-made divided body inside the primary lining in parallel with the excavation work. Then, a continuous gap is secured between the peripheral surfaces of the primary lining and the secondary lining, and a waterproof material is injected into the continuous space to form a waterproof layer between the primary lining and the secondary lining. Tunnel lining method characterized by forming and performing
JP61205809A 1986-09-03 1986-09-03 Tunnel lining method Expired - Lifetime JPH0788759B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61205809A JPH0788759B2 (en) 1986-09-03 1986-09-03 Tunnel lining method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61205809A JPH0788759B2 (en) 1986-09-03 1986-09-03 Tunnel lining method

Publications (2)

Publication Number Publication Date
JPS6363899A JPS6363899A (en) 1988-03-22
JPH0788759B2 true JPH0788759B2 (en) 1995-09-27

Family

ID=16513052

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61205809A Expired - Lifetime JPH0788759B2 (en) 1986-09-03 1986-09-03 Tunnel lining method

Country Status (1)

Country Link
JP (1) JPH0788759B2 (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2579499B2 (en) * 1987-10-08 1997-02-05 新日本製鐵株式会社 Repair method of horseshoe-shaped existing tunnel lining
JPH0735918Y2 (en) * 1989-12-21 1995-08-16 株式会社奥村組 Concrete segment
JPH0739998Y2 (en) * 1989-12-21 1995-09-13 株式会社奥村組 Concrete segment
JP2590023B2 (en) * 1990-08-17 1997-03-12 日本電信電話株式会社 Secondary lining construction method using precast panel
JP2575940B2 (en) * 1990-09-20 1997-01-29 西松建設株式会社 Conduit construction method
JPH0561297U (en) * 1992-01-28 1993-08-13 前田建設工業株式会社 Shield segment

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5835730Y2 (en) * 1978-03-28 1983-08-11 株式会社大林組 Water tunnel lining structure
JPS6129840Y2 (en) * 1980-02-20 1986-09-02

Also Published As

Publication number Publication date
JPS6363899A (en) 1988-03-22

Similar Documents

Publication Publication Date Title
CN105484765A (en) Fabricated secondary lining structure of bored tunnel and construction method of fabricated secondary lining structure
CN110700857B (en) Composite tunnel supporting system and construction method
CN110206073B (en) Waterproof construction method for lattice column pile and main structure joint
CN109026079A (en) Tunnel joint waterproof structure and waterproof construction method
US6193439B1 (en) Process for cladding substrates and constructions produced thereby
JP3321697B2 (en) Tunnel lining method using composite panels
JPH0788759B2 (en) Tunnel lining method
CN109505612A (en) Big descending bored tunnel shield sky selection structure and construction technology
CN112012763B (en) Construction method of double-layer primary support multi-arch tunnel structure
KR20030096697A (en) A tunnel lining structure system using curved corrugated steel plates and consrution method therof
CN210380191U (en) Lightweight power communication combination prefabricated cable channel
KR102103978B1 (en) Reinforcement and waterproof structure of vertical shafts for utility interface
CN115898469A (en) Tunnel secondary lining construction method
KR101234401B1 (en) Protective structure for a tunnel entrance
CN112228076B (en) Fast excavation construction method for hard rock large-span tunnel
CN114278333A (en) Construction method of ingate
JPH04306398A (en) Repairing method of concrete wall surface
JP2994243B2 (en) External wall construction method and external wall structure for underground structures
US3449916A (en) Tunnel liner and method of making same
JP3633397B2 (en) Tunnel lining method
CN109098718A (en) Assembled roadway construction method
JP2019157620A (en) Manufacturing method for composite segment
JPH0353439B2 (en)
JPH084033A (en) Structure method of building underground outer periphery pressure bulkhead
CN219973299U (en) Prefabricated assembled basement roof post-cast strip advanced sealing structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term