JP3876429B2 - Construction method of bulkhead in shield tunnel - Google Patents
Construction method of bulkhead in shield tunnel Download PDFInfo
- Publication number
- JP3876429B2 JP3876429B2 JP20296097A JP20296097A JP3876429B2 JP 3876429 B2 JP3876429 B2 JP 3876429B2 JP 20296097 A JP20296097 A JP 20296097A JP 20296097 A JP20296097 A JP 20296097A JP 3876429 B2 JP3876429 B2 JP 3876429B2
- Authority
- JP
- Japan
- Prior art keywords
- vertical
- block
- bulkhead
- horizontal
- partition
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Description
【0001】
【発明の属する技術分野】
本発明は、セグメントの組み立てにより一次覆工を形成するシールドトンネル内に、水平及び垂直の隔壁を築造するシールドトンネル内の隔壁築造方法に関する。
【0002】
【従来の技術】
従来、シールドトンネルにおいて、トンネル内部を水平及び垂直の隔壁をもって仕切り、仕切られた各空間をそれぞれ各種の用途に使用することが一般に行われている。
【0003】
この隔壁の構築に際し従来は、セグメントによる一次覆工の内面に場所打ちコンクリートによる二次覆工を打設していたため、隔壁の構築もこれと同様に場所打ちコンクリートによる築造が一般的であった。
【0004】
しかし近年においては、シールドトンネルの一次覆工自体の止水性、内面平滑性、防錆機能の向上により、二次覆工の省略が可能になってきている。また隔壁の築造についても、垂直隔壁に関してはプレキャスト版の使用が検討されている。
【0005】
また、従来の隔壁築造方法では、隔壁を覆工に固定するために、二次覆工が構築される場合には、その構築時にアンカー筋を埋め込んでおき、これと一体に場所打ちの隔壁を築造しており、二次覆工がない場合は、組み立てられたセグメントに、予めアンカーホールを設けておくか、後付けアンカーを、打ち込みなどによって設置し、これに支持させて場所打ちの隔壁を築造している。
【0006】
【発明が解決しようとする課題】
このような従来の隔壁築造方法にあっては、ほとんどが場所打ちにより築造されるものであるため、型枠の組み立てや、そのための支保工の設置、多量のコンクリートの打設等の多数の作業を狭いトンネル内にて行わなければならず、工期も長く要する等の問題があった
本発明は、このような従来の問題に鑑み、少ない工数で、短期間にて隔壁築造ができるシールドトンネル内の隔壁築造方法の提供を目的としてなされたものである。
【0007】
【課題を解決するための手段】
上述の如き従来の問題を解決し、所期の目的を達成するための本発明の特徴は、セグメントの組み立てにより一次覆工を構築したシールドトンネル内に水平隔壁と、該水平隔壁下の空間を左右に仕切る垂直隔壁とを築造するシールドトンネル内の隔壁築造方法において、
前記垂直隔壁を構成させるプレキャストコンクリート製の垂直隔壁ブロックと、該垂直隔壁の上端からそれぞれトンネル両側の内面に到る左側水平隔壁ブロックと右側水平隔壁ブロックを別々に形成しておき、前記垂直隔壁ブロックを一次覆工完了後のシールドトンネル内に搬入して立てた後、左右側の各水平隔壁ブロックを搬入し、該ブロックをそれぞれ一端側を前記垂直隔壁ブロックの上端に他端側を前記トンネルの一次覆工内面に突設した受け台にそれぞれ支持させて固定し、同様にして前記各垂直隔壁ブロック及び両水平隔壁ブロックをそれぞれ順次並べて設置することにより連続した水平隔壁と垂直隔壁を築造することにある。
【0008】
尚、受け台は組み立て前のセグメントに予め突設しておき、該セグメントを所定の位置に組み込むことにより一次覆工の内面に受け台を突設させてもよく、予めセグメントに受け台取り付け用の埋め込み栓を備えておき、一次覆工完了後に該埋め込み栓にボルトを螺嵌して、受け台を固定してもよい。また、トンネル内底部に打設するインバートコンクリートの上面に、垂直隔壁ブロックの下端を挿入させるための溝を設け、該溝内に前記垂直ブロックの下端を挿入して立てた後、水平隔壁ブロックを固定した方が好ましく、また、溝内に垂直ブロックの下端を挿入後、該溝内の空隙をモルタルで充填することにより、該垂直ブロックを立ててもよく、溝内に垂直ブロックの下端を挿入後、仮支え材にて支えることにより、該垂直ブロックを立ててもよい。
【0009】
【作用】
本発明においては、プレキャストコンクリート製の垂直隔壁ブロック及び両水平隔壁ブロックを搬入し、垂直隔壁ブロックを立てた後、両水平ブロックをそれぞれ、垂直隔壁と一次覆工内面の受け台との間にそれぞれ架設し、これを並べることににより、水平隔壁と垂直隔壁が順次構築される。その際のトンネル内作業はブロックの搬入、据付、ボルト止め及び部分的なモルタル打ちが必要であるが、全体として作業工数が少なく、部材の高所への吊り上げや、作業者の高所における不安定な場所での危険作業が少なく、安全性が高い。
【0010】
【実施の形態】
次に本発明の実施の形態を図面示した実施例について説明する。
【0011】
図1は、本発明方法にて築造される隔壁の一例を示しており、図において、1はセグメントを組み立てて形成した一次覆工である。この一次覆工1を施したトンネルの略上半部をトンネル掘進作業に必要な輸送空間として使用しており、一次覆工の両側部の中央稍上側の対称な位置に取り付けたブラケット2,2に枕木3を一定間隔毎に支持させ、その上にレール4,4を付設して作業台車5が走行できるようにするとともに、図には示してないが、各種の配線、配管を枕木上の空間に設置する。
【0012】
また、トンネル内の一次覆工1の構築時に、予め、受け台10を一体に突設した受け台付きセグメント11をトンネル両側部に使用し、一次覆工1の構築と同時に受け台10,10をトンネル内面の左右の位置に突設させている。
【0013】
受け台付きセグメント11は、図5に示すように、セグメントの成形時に弧状をしたセグメント本体11aの内側面に、幅方向に連続させて受け台10を突設させたものを使用する。受け台10の上面には隔壁固定用のアンカーナットからなる埋め込み栓12を設置しておく。
【0014】
この他、図8に示すようにセグメント本体11aの内面の所定位置に、アンカーナットからなる埋め込み栓13を設置しておき、これに別途成形した受け台ピース10aをボルト14を介して固定してもよい。尚、この受け台ピース10aを使用する場合は、セグメントによる一次覆工1の構築後に受け台ピース10aを取り付けることにより、受け台10を突設させてもよい。
【0015】
このようにしてシールドトンネルを順次掘進し、その一次覆工完了後のトンネル内において、枕木3下に異物落下防止シート(図示せず)を敷設する。然る後、インバートコンクリート21を打設する。このインバートコンクリートの打設に際し、その上面の垂直隔壁の設置位置に垂直隔壁ブロック20の下端を挿入させるための溝31を形成しておく。このインバートコンクリート21の固化後
、図2に示すように台車30aによりプレキャストコンクリート製の垂直隔壁ブロック20をトンネル内に搬入する。
【0016】
そして搬入された垂直隔壁ブロック20下端を溝31内に挿入し、該ブロック20の側面とインバートコンクリート21の表面間に斜材からなる仮支え材32を固定して立て、溝31内の空隙をモルタル33にて埋める。
【0017】
次いで、図3に示すように左右側の各水平隔壁ブロック22、23をそれぞれ台車30bによりインバートコンクリート21上を搬入し、それぞれを垂直隔壁Aの上端と受け台10、10との間に架設する。
【0018】
尚、水平隔壁ブロック22、23は図4に示すように、一次覆工のセグメントリングCの幅の2倍の幅に成形し、1つおきのセグメントリングCに受け台10を突設し、互いに隣り合う各水平隔壁部ブロック22又は23の両端の縁部を1つの受け台10上で接合させて支持させる。尚、トンネルの曲率の大きさによっては、セグメントリングC、水平隔壁ブロック22、23の幅を同じくしてもよい。
【0019】
垂直隔壁ブロック20の上端には、図7に示すように両側に段状の受部24、24を予め成形しておくとともに、その受部にアンカーナットからなる埋め込み栓25、25を埋設しておき、各水平隔壁ブロック22、23の端部を貫通させたボルト26、26をこれに螺嵌させることにより固定させる。また、図6に示すように各水平隔壁ブロック22、23の一次覆工内面側端部も予め形成したボルト用穴にボルト27、27を上下に貫通させて受け台10、10の埋め込み栓12、12に螺嵌することによってそれぞれ固定するとともに、各ブロック22、23の端面とセグメント本体11aの内側側面との間の隙間をモルタル28、28にて埋める。
【0020】
このようにして順次水平隔壁ブロック22、23を並べて架設することにより、連続した水平隔壁Bを築造する。
【0021】
尚、図示のように垂直隔壁Aをトンネル内の左右いずれかの側に片寄せすることにより、これによって仕切られる片側の空間が、その上に架設する水平隔壁ブロック23の搬入に充分な広さがない場合は、広い側の水平隔壁ブロック22を架設後、図9に示すように該水平隔壁ブロック22上に台車30cを走行させて水平隔壁ブロック23の搬入、架設を行う。
【0022】
【発明の効果】
上述したように本発明の方法においては、シールドトンネル内にプレキャストコンクリート製の垂直隔壁ブロック及び左右分割の水平隔壁ブロックをそれぞれ搬入し、垂直隔壁ブロックをトンネル内底部に支持させて立設した後、両水平隔壁ブロックを先に立設された垂直隔壁ブロックの上端とトンネル一次覆工内面の受け台との間に掛け渡して固定することにより、水平、垂直の隔壁を築造するようにしたため、従来の場所打コンクリートによる構築に比べて搬入する質材及び作業工数が著しく少なく、工期短縮され、また不安定な足場の高所作業や設材の吊り上げ等の作業が少なく、安全性が高い。
【0023】
また、水平、垂直の隔壁をそれぞれ別々の隔壁ブロックにより構成させたことにより、ブロックの搬入を容易なものとすることができる。
【0024】
更に、予め受け台を設置した受け台付きセグメントを使用することにより、従来のようなトンネルにおけるアンカー筋や埋め込み栓の打ち込み等の作業が不要になり、トンネル内での作業性が著しく向上し、工期の短縮、工費の節減がなされる。
【図面の簡単な説明】
【図1】本発明方法により築造される隔壁の一例の断面図である。
【図2】同上の垂直隔壁ブロック搬入工程の断面図である。
【図3】同上の水平隔壁ブロック搬入工程の断面図である。
【図4】本発明方法における受け台に対する水平隔壁ブロック配置の一例を示す縦断側面図である。
【図5】本発明方法に使用する受け台付きセグメントの一例の斜視図である。
【図6】本発明方法における受け台に対する水平隔壁ブロックの固定状態の一例を示す断面図である。
【図7】本発明方法における垂直隔壁と水平隔壁ブロックの固定状態の一例を示す断面図である。
【図8】本発明における受け台の他の例の断面図である。
【図9】本発明方法における水平隔壁ブロックの搬入工程の他の側の断面図である。
【符号の説明】
1 一次覆工
2 ブラケット
3 枕木
4 レール
5 作業台車
10 受け台
10a 受け台ピース
11 受け台付きセグメント
11a セグメント本体
12,13 埋め込み栓
14 ボルト
20 垂直隔壁ブロック
21 インバートコンクリート
22 右側水平隔壁ブロック
23 左側水平隔壁ブロック
24 受部
25 埋め込み栓
27 ボルト
28 モルタル
30a、30b、30c 台車
31 溝
32 仮支え材
33 モルタル
A 垂直隔壁
B 水平隔壁[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a partition wall construction method in a shield tunnel in which horizontal and vertical partition walls are built in a shield tunnel in which a primary lining is formed by assembling segments.
[0002]
[Prior art]
2. Description of the Related Art Conventionally, in shield tunnels, it has been generally performed that the inside of the tunnel is partitioned by horizontal and vertical partitions, and each partitioned space is used for various purposes.
[0003]
When constructing this bulkhead, conventionally, a secondary lining with cast-in-place concrete was placed on the inner surface of the primary lining with segments, so the construction of bulkheads was also generally done with cast-in-place concrete. .
[0004]
However, in recent years, the secondary lining can be omitted due to the improvement of the water-stopping property, the inner surface smoothness, and the rust prevention function of the primary lining itself of the shield tunnel. Also, regarding the construction of bulkheads, the use of precast plates is being considered for vertical bulkheads.
[0005]
In addition, in the conventional bulkhead construction method, when a secondary lining is constructed to fix the bulkhead to the lining, anchor bars are embedded at the time of construction, and a cast-in-place partition is integrated with this. If it is built and there is no secondary lining, an anchor hole will be provided in the assembled segment in advance, or a retrofitting anchor will be installed by driving in, etc. is doing.
[0006]
[Problems to be solved by the invention]
In such a conventional bulkhead construction method, most of them are built by cast-in-place, so a lot of work such as assembly of formwork, installation of support for that, and placement of a large amount of concrete In view of such conventional problems, the present invention has a problem that a bulkhead can be built in a short period of time with a small number of man-hours. It was made for the purpose of providing a bulkhead building method.
[0007]
[Means for Solving the Problems]
The feature of the present invention for solving the conventional problems as described above and achieving the intended purpose is that a horizontal bulkhead and a space under the horizontal bulkhead are formed in a shield tunnel in which a primary lining is constructed by assembling segments. In the method of building a bulkhead in a shield tunnel that builds a vertical bulkhead that divides left and right,
A vertical partition block made of precast concrete that constitutes the vertical partition, and a left horizontal partition block and a right horizontal partition block that respectively reach the inner surfaces of both sides of the tunnel from the upper end of the vertical partition are formed separately. After the primary lining is completed, the horizontal barrier block is loaded into the shield tunnel and the horizontal partition blocks on the left and right sides are loaded, and the blocks are respectively connected at one end to the upper end of the vertical partition block and the other end to the tunnel. Supporting and fixing each of the vertical bulkhead blocks and the horizontal bulkhead blocks one after another in a similar manner, by constructing continuous horizontal bulkheads and vertical bulkheads by supporting and fixing each to a cradle protruding from the inner surface of the primary lining. It is in.
[0008]
In addition, the cradle may be projected in advance on the segment before assembly, and the cradle may be projected on the inner surface of the primary lining by incorporating the segment at a predetermined position. The embedment plug may be provided, and after completion of the primary lining, a bolt may be screwed into the embedment plug to fix the cradle. Further, the upper surface of the invert concrete to pouring into tunnel bottom, a groove for inserting the lower end of the vertical partition wall block provided, after standing by inserting the lower end of the vertical block into the groove, the horizontal partition wall block preferably better fixed, also inserted after inserting the lower end of the vertical block in the groove, the void in the groove by filling with mortar, may make a the vertical block, the lower end of the vertical block in the groove Then, the vertical block may be erected by supporting it with a temporary support material.
[0009]
[Action]
In the present invention, the vertical partition block made of precast concrete and both horizontal partition blocks are carried in, and after setting up the vertical partition block, both horizontal blocks are respectively placed between the vertical partition and the cradle on the primary lining inner surface. A horizontal partition and a vertical partition are constructed in sequence by installing and arranging them. The work inside the tunnel at that time requires loading, installation, bolting, and partial mortaring of the block, but the overall work is small, and the lifting of the parts to high places and the inconvenience at the high places of the workers are difficult. Less dangerous work in a stable place and high safety.
[0010]
[Embodiment]
Next, examples illustrating the embodiments of the present invention will be described.
[0011]
FIG. 1 shows an example of a partition wall constructed by the method of the present invention. In the figure, 1 is a primary lining formed by assembling segments. The upper half of the tunnel with the primary lining 1 is used as a transport space necessary for tunnel excavation work, and the
[0012]
In addition, when the primary lining 1 in the tunnel is constructed,
[0013]
As shown in FIG. 5, the
[0014]
In addition, as shown in FIG. 8, an embedded
[0015]
In this way, the shield tunnel is sequentially dug, and a foreign matter fall prevention sheet (not shown) is laid under the sleepers 3 in the tunnel after the completion of the primary lining. Thereafter, invert
[0016]
Then, the lower end of the carried
[0017]
Next, as shown in FIG. 3, the horizontal partition blocks 22 and 23 on the left and right sides are respectively carried on the
[0018]
In addition, as shown in FIG. 4, the horizontal partition blocks 22 and 23 are formed to have a width twice as large as the segment ring C of the primary lining, and the
[0019]
At the upper end of the
[0020]
In this way, a continuous horizontal partition wall B is constructed by sequentially arranging the horizontal partition wall blocks 22 and 23 and arranging them.
[0021]
As shown in the figure, the vertical partition wall A is shifted to either the left or right side in the tunnel, so that the space on one side partitioned by this is wide enough to carry in the
[0022]
【The invention's effect】
As described above, in the method of the present invention, the vertical partition block made of precast concrete and the horizontal partition block of the left and right divisions are respectively carried into the shield tunnel, and the vertical partition block is supported on the bottom of the tunnel and is erected, Since both horizontal bulkhead blocks were fixed between the upper end of the vertical bulkhead block that was erected first and the cradle on the inner surface of the primary tunnel lining, horizontal and vertical bulkheads were constructed. Compared with the construction using cast-in-place concrete, the material and work man-hours to be carried in are remarkably reduced, the construction period is shortened, and the work such as the high work of the unstable scaffolding and the lifting of the construction material is less, and the safety is high.
[0023]
In addition, since the horizontal and vertical partition walls are configured by separate partition blocks, it is possible to easily carry in the blocks.
[0024]
Furthermore, by using a segment with a cradle in which a cradle is installed in advance, work such as driving anchor bars and embedded plugs in a conventional tunnel becomes unnecessary, and workability in the tunnel is significantly improved. The construction period is shortened and the construction cost is reduced.
[Brief description of the drawings]
FIG. 1 is a cross-sectional view of an example of a partition wall constructed by the method of the present invention.
FIG. 2 is a sectional view of a vertical partition block carrying-in step according to the same.
FIG. 3 is a cross-sectional view of the horizontal partition block carrying-in process of the above.
FIG. 4 is a longitudinal side view showing an example of horizontal partition block arrangement with respect to a cradle in the method of the present invention.
FIG. 5 is a perspective view of an example of a segment with a cradle used in the method of the present invention.
FIG. 6 is a cross-sectional view showing an example of a fixed state of the horizontal partition block with respect to the cradle in the method of the present invention.
FIG. 7 is a cross-sectional view showing an example of a fixed state of a vertical partition wall and a horizontal partition block in the method of the present invention.
FIG. 8 is a cross-sectional view of another example of a cradle according to the present invention.
FIG. 9 is a sectional view on the other side of the horizontal partition block carrying-in step in the method of the present invention.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 1
Claims (5)
前記垂直隔壁を構成させるプレキャストコンクリート製の垂直隔壁ブロックと、該垂直隔壁の上端からそれぞれトンネル両側の内面に到る左側水平隔壁ブロックと右側水平隔壁ブロックを別々に形成しておき、前記垂直隔壁ブロックを一次覆工完了後のシールドトンネル内に搬入して立てた後、左右側の各水平隔壁ブロックを搬入し、該ブロックをそれぞれ一端側を前記垂直隔壁ブロックの上端に他端側を前記トンネルの一次覆工内面に突設した受け台にそれぞれ支持させて固定し、同様にして前記各垂直隔壁ブロック及び両水平隔壁ブロックをそれぞれ順次並べて設置することにより連続した水平隔壁と垂直隔壁を築造することを特徴としてなるシールドトンネル内の隔壁築造方法。In the method of building a bulkhead in a shield tunnel that builds a horizontal bulkhead in a shield tunnel in which a primary lining is constructed by assembling segments, and a vertical bulkhead that partitions the space under the horizontal bulkhead to the left and right,
A vertical partition block made of precast concrete that constitutes the vertical partition, and a left horizontal partition block and a right horizontal partition block that respectively reach the inner surfaces of both sides of the tunnel from the upper end of the vertical partition are formed separately. After the primary lining is completed, the horizontal barrier block is loaded into the shield tunnel and the horizontal partition blocks on the left and right sides are loaded, and the blocks are respectively connected at one end to the upper end of the vertical partition block and the other end to the tunnel. Supporting and fixing each of the vertical bulkhead blocks and the horizontal bulkhead blocks one after another in a similar manner, by constructing a continuous horizontal bulkhead and a vertical bulkhead by respectively supporting and fixing them on a cradle protruding from the inner surface of the primary lining. A bulkhead construction method in a shield tunnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20296097A JP3876429B2 (en) | 1997-07-29 | 1997-07-29 | Construction method of bulkhead in shield tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP20296097A JP3876429B2 (en) | 1997-07-29 | 1997-07-29 | Construction method of bulkhead in shield tunnel |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH1144188A JPH1144188A (en) | 1999-02-16 |
JP3876429B2 true JP3876429B2 (en) | 2007-01-31 |
Family
ID=16466021
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP20296097A Expired - Fee Related JP3876429B2 (en) | 1997-07-29 | 1997-07-29 | Construction method of bulkhead in shield tunnel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3876429B2 (en) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP3448520B2 (en) * | 1999-08-04 | 2003-09-22 | 株式会社ホクコン | Panel for narrow carry-in path and method of erection |
JP2002180797A (en) * | 2000-12-13 | 2002-06-26 | Ishikawajima Constr Materials Co Ltd | Column joint structure of tunnel structure |
JP5594629B2 (en) * | 2010-10-20 | 2014-09-24 | 興建産業株式会社 | Construction method of tunnel bottom structure with drainage equipment |
JP5037672B2 (en) * | 2010-10-29 | 2012-10-03 | 鹿島建設株式会社 | Construction equipment inside the tunnel |
JP6954770B2 (en) * | 2017-06-15 | 2021-10-27 | 清水建設株式会社 | Box connection structure of precast members and construction method of box connection structure |
JP6695927B2 (en) * | 2018-05-07 | 2020-05-20 | 本清鋼材株式会社 | Floor slab installation method |
CN108798701A (en) * | 2018-06-01 | 2018-11-13 | 中铁第四勘察设计院集团有限公司 | Precast construction and its construction method in a kind of roads and tunnels |
-
1997
- 1997-07-29 JP JP20296097A patent/JP3876429B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH1144188A (en) | 1999-02-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101630235B1 (en) | Precast truss wall structure and construction method of underground structure using thereof | |
WO2010134731A9 (en) | Top-down construction method using a branch-type steel frame with channels for the continuous construction of an underground retaining wall | |
KR102243984B1 (en) | Non-supporting formwork system for retaining wall using self-supporting form and construction method thereof | |
JP3029022B2 (en) | Formwork apparatus for tunnel lining and lining method using the same | |
US20130333318A1 (en) | Reinforced masonry panel structures | |
CN110499779B (en) | Construction method of air duct structure sharing side wall with subway station | |
WO2009096725A2 (en) | Precast temporary facility structure and a construction method for the same | |
JP3881210B2 (en) | Tunnel floor slab construction method and tunnel | |
JP3876429B2 (en) | Construction method of bulkhead in shield tunnel | |
JPH10176488A (en) | Lining structure for existing tunnel | |
JP3690437B2 (en) | Seismic reinforcement structure for existing buildings | |
JP3823279B2 (en) | Construction method of bulkhead in shield tunnel | |
JP3823278B2 (en) | Construction method of bulkhead in shield tunnel | |
JP6360769B2 (en) | Widening method of existing road bridge | |
AU2012101074A4 (en) | A component tunnel ceiling structure and method of installing the same | |
KR20210119935A (en) | Underground structure using strut and method construturing the same | |
JP6796160B2 (en) | Tunnel internal structure and its construction method | |
JPH09195438A (en) | Precast concrete plate and reinforcing structure of building | |
KR20040001642A (en) | Lining building method for tunnel | |
JP4415838B2 (en) | Construction method inside tunnel | |
JP3194615B2 (en) | How to repair a cave | |
JP2021001453A (en) | Top plate construction method of vertical shaft and top plate structure | |
JP2009046842A (en) | Finisher track laying method and track laying base block | |
JP3250647B2 (en) | Construction method of arched tunnel | |
KR20190123408A (en) | Mounting Apparatus For Supporting Frames |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040308 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20060502 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060530 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060725 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061003 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061020 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121110 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121110 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131110 Year of fee payment: 7 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |