JP3735600B2 - Concrete compaction method and apparatus - Google Patents

Concrete compaction method and apparatus Download PDF

Info

Publication number
JP3735600B2
JP3735600B2 JP2002329301A JP2002329301A JP3735600B2 JP 3735600 B2 JP3735600 B2 JP 3735600B2 JP 2002329301 A JP2002329301 A JP 2002329301A JP 2002329301 A JP2002329301 A JP 2002329301A JP 3735600 B2 JP3735600 B2 JP 3735600B2
Authority
JP
Japan
Prior art keywords
concrete
vibration
tunnel
vibration member
mold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP2002329301A
Other languages
Japanese (ja)
Other versions
JP2003227297A6 (en
JP2003227297A (en
Inventor
秀利 原
勉 北川
毅 相崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Maeda Corp
Original Assignee
Maeda Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Maeda Corp filed Critical Maeda Corp
Priority to JP2002329301A priority Critical patent/JP3735600B2/en
Publication of JP2003227297A publication Critical patent/JP2003227297A/en
Publication of JP2003227297A6 publication Critical patent/JP2003227297A6/en
Application granted granted Critical
Publication of JP3735600B2 publication Critical patent/JP3735600B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、トンネル内への覆工用、主に二次覆工用のコンクリート打設時に、打設コンクリートを振動させて締固める方法および装置に関するものである。
なお、本明細書中、「打設」とは、養生硬化させていない泥状のコンクリートを型枠とトンネル内壁面との間へ充填させることをいう。
【0002】
【従来の技術】
元来、トンネル内への覆工用、主に二次覆工用のコンクリートの打設は、コンクリートを打設するための型枠を、コンクリート打設終了後、折畳んで前方に搬送し、展開させて設置し、その個所でコンクリートを打設する移動式の型枠により行われていた。
【0003】
この型枠によるコンクリート打設は、トンネル内の所定位置への設置後、型枠に多数設けられた所定個所の開閉自在の検査窓からコンクリート搬送管を突出させ、あるいは専用のコンクリート打設口にコンクリート搬送管を接続して行われていた。
【0004】
また、打設コンクリートを補強するため、鉄筋等の補強材が、型枠とトンネル内壁面との間に、予め配設させていた。
【0005】
また、養生硬化後のコンクリートの強度、耐久性を向上させるため、打設した直後のコンクリート内にその都度同一あるいは別の検査窓から振動具を挿入突出させ、この振動具の振動により、打設したコンクリートを締固め、コンクリート内に混在する気泡を除去していた。
【0006】
この振動具は、電源ケーブルの先端に振動部を備えたものが主流であり、このため、作業者は電源ケーブルを直接把持し、検査窓を開放して突出させ、また必要に応じて検査窓から身を乗り出して振動部を打設したコンクリート内に挿入させ、振動部を前後左右および上下方向に移動させ(振り回し)、振動部の振動により、打設したコンクリートを締固め、締固め作業完了後、検査窓から収納させていた(図5参照)。
【0007】
なお、図5中、60は型枠、62は検査窓、64はコンクリート打設口、66は振動具、68は電源コード、70はコンクリート、72はトンネル内壁面、74はコンクリート搬送管、76は作業者を示す。
【0008】
このため、作業者の人手による打設コンクリート締固め作業において、以下の問題があった。
【0009】
第1に、作業者が振動具の電源ケーブルを把持し、人手により振動具の振動部を型枠の各検査窓から突出させ、打設コンクリート内に挿入させ、上下、左右方向に移動させ、振動部の振動により打設コンクリートを締固め、締固め作業完了後、検査窓から収納させていたため、打設コンクリートへの振動具による振動が局部的で不均一であり、締固め効率が良くなかった。
【0010】
第2に、振動させた振動具の検査窓からの突出、収納時に、振動具の振動部が検査窓の突出部位外周縁に接触することにより、振動により振動部が回動し、振動具を把持する作業者にこの回動力が必要以上に作用し、この回動力が電源ケーブルにまで伝達され、時には電源ケーブルがソケットから外れることもあり、作業に支障をきたしていた。
【0011】
第3に、必要に応じて検査窓から作業者が身を乗り出して締固め作業を行う必要があり、危険性を伴うため、作業を慎重に行うことを強いられ、安全、かつ短時間に作業を行うことができないばかりか、工程遅延の要因となっていた。
【0012】
第4に、締固め作業中の検査窓近部までコンクリートが打設された際には、この作業中の検査窓から振動具を収納させ、この検査窓を閉塞させ、別の検査窓へ移動し、この検査窓を開放させて振動具を突出させ、先のコンクリート打設された検査窓近部の振動を行う必要があり、締固め作業中の検査窓近部の振動を同一個所から行うことができなかった。
【0013】
第5に、振動中に振動具が型枠の外周面と接触し、その接触面において泥状のコンクリートが水分とコンクリートに分離し、硬化後コンクリートの強度、耐久性が低下する要因となっていた。
【0014】
上記欠点に鑑み、振動具を型枠の内側から外側に突出させる装置(例えば、特許文献1参照)、振動具を型枠の外側を移動させる装置(例えば、特許文献2参照)があった。
【0015】
【特許文献1】
特許第3278355号公報(第3−4頁、図1−6、9)
【特許文献2】
特開2001−82087号公報(第3−5頁、図1−7)
【0016】
また、使用後、直ちに振動具および電源コードに付着した打設コンクリートを人手により除去していた。
【0017】
【発明が解決しようとする課題】
特許文献1においては、振動具の打設コンクリートの締固め個所が限定され、特許文献2においては、作業者の目視により振動具を移動させる必要があり、また両者とも振動具を移動させる制御機構が必要不可欠であり、構成部品数も多く、コストが高騰する要因となっていた。
【0018】
また、両文献および従来技術において、コンクリートの強度、耐久性を向上させるための振動具による打設コンクリートの締固め作業は、コンクリートを打設した直後にその都度行っていたため、振動具により締固めたコンクリートは型枠の妻側に流動し、打設コンクリート全体を締固めることができなかった。
【0019】
また、型枠とトンネル内壁面との間には補強材が配設されており、また打設コンクリートに挿入させた振動具の位置が一定しないため、補強材に振動具が接触し易く、取扱性が良くなかった。
【0020】
また、型枠とトンネル内壁面との間に配設された補強材および型枠外周面に振動具が衝突あるいは接触し、不快音の発生、補強材と打設コンクリートとの密着低下、補強材の結束緩み、が生じるばかりか、振動具が損傷することがあり、耐久性に問題があった。
【0021】
また、使用後、直ちに振動具および電源コードに付着した打設コンクリートを人手により除去する必要があり、その作業が面倒であった。
【0022】
本発明は、以上のような欠点に鑑み、簡易かつ安全に、しかも効率良く打設コンクリートを締固め、付着した打設コンクリートをも除去することができるコンクリート締固め方法および装置を提供することを目的とするものである。
【0023】
【課題を解決するための手段】
本発明は、トンネル内に型枠を使用してコンクリートを打設する工程、装置において、長尺な牽引部の先端に振動部を備え、振動部材を、型枠とトンネル内壁面との間に、その基端を巻揚機構に装着して型枠の長さ方向に沿わせて配設させた後、型枠とトンネル内壁面との間へのコンクリート打設後、またはコンクリート打設時に、振動部材を振動させると共に、巻揚機構を介して振動部材を巻揚、繰出すことにより、型枠の長さ方向に沿わせて移動させ、コンクリートを締固めることを特徴とするもの、または、振動部材の先端を、牽引材を介して別の巻揚機構に装着し、振動部材に張力を付与することを特徴とするもの、または、振動部材の先端を、既コンクリート打設部に埋設されてトンネル前方に延出させた案内軌道部材に装着し、この案内軌道部材に沿わせて振動部材を移動させることを特徴とするもの、または、巻揚機構に近接させて洗浄機構を配備させることにより、巻揚機構による巻揚時に、振動部材に付着した打設コンクリートを洗浄除去することを特徴とするものである。
【0024】
【発明の実施の形態】
本発明に係るコンクリートの締固め装置は、トンネル12内に覆工用、主に二次覆工用のコンクリート14を打設するための移動式の型枠16に装着されるものであり、図1および図2に示すように、以下の構成からなるものである。
【0025】
長尺な牽引部18の先端に振動部20を備えてなる振動部材22の外周の長さ方向全域に、芯材24を配してある。
【0026】
本例において、振動部材22は電磁式振動体を収容した振動部20が、接続ケーブル(図示略)を内装させた長尺な牽引部18を介して電源(図示略)と接続されている。
【0027】
また、牽引部18は、軽量化、取扱性、耐摩耗性に優れた素材とすることが望ましい。
【0028】
また、芯材24はワイヤーであり、振動部材22の外周両側縁に二本配してある。
【0029】
この芯材24を振動部材22の外周に配することにより、振動部材22の強度、耐摩耗性を向上させ、後述の巻揚機構28への巻揚、繰出し時および型枠16とトンネル内壁面26との間に配設させた補強材(図示略)への接触時にも牽引部18が損傷することがなく、取扱性も向上し、牽引に適した構造となる。
【0030】
この振動部材22を、型枠16とトンネル内壁面26との間に、その基端を巻揚機構28に装着して型枠16の長さ方向に沿わせて、複数配設させてある。
【0031】
各振動部材22の振動部20の先端を、牽引材30を介して型枠16内の別の巻揚機構32に装着してある。
【0032】
本例において、巻揚機構28は電動ウインチであり、巻揚機構32はバネ式または電動式のリールである。
【0033】
また、牽引材30はワイヤーであり、型枠16のラップ側の既コンクリート打設部34に固定させた案内ローラ36に係止させてある。
【0034】
各巻揚機構28,32により、振動部材22に張力が付与され、振動部材22を打設コンクリート層の中間部位に保持させ、打設コンクリートを均一に振動できると共に、振動部材22の型枠16、型枠16とトンネル内壁面26との間に配設させた補強材、への衝突(不快音の発生)あるいは接触(不快音の発生、補強材と打設コンクリートとの密着低下、補強材の結束緩み)を防止することができ、しかも振動部材22の損傷をも防止することができるため、打設コンクリートの強度、品質が極めて向上する。
【0035】
型枠16の妻側外方の巻揚機構28に近接させた妻板38との間に、洗浄機構40が配備されている。
【0036】
本例において、洗浄機構40はリング管に、その中心部に向けて小孔を穿孔させたリング型シャワーであり、巻揚機構28による巻揚時に、振動部材22、特に牽引部18に付着した打設コンクリート16を、水圧(水)により洗浄除去する。
【0037】
また、妻板38の振動部材22の貫挿部位および型枠16の牽引材30の貫挿部位には、それぞれ打設コンクリートが妻板38外方あるいは型枠16内に浸出しないよう浸出防止材(図示略)が、配備されている。
【0038】
なお、図中42は芯材24を振動部材22の外周に止着する止具、44はコンクリート打設口、46はコンクリート搬送管、48は型枠16の天板部、50は作業者、52はホッパー、54は排水管を示す。
【0039】
本装置を使用して型枠16、例えば天板部48とトンネル内壁面26との間へ打設した二次覆工用のコンクリート14を締固める方法を以下に詳述する。
【0040】
まず、型枠16をトンネル12の所定位置まで移動させる。
【0041】
次に、型枠16の妻側38外方の巻揚機構28に、振動部材22の牽引部18の基端を装着させ、型枠16内の別の巻揚機構32に、牽引材30を介して振動部材22の振動部20の先端を装着させることにより、振動部材22を型枠16の長さ方向に沿わせて、複数配設させる。
【0042】
次に、型枠16とトンネル内壁面26との間へ、コンクリート14を打設する。
【0043】
この際、型枠16の各コンクリート打設口44からコンクリート14を、型枠16とトンネル内壁面26との間へ、順次打設する。
【0044】
次に、型枠16とトンネル内壁面26との間全体へのコンクリート14の打設完了後、各振動部材22を振動させると共に、巻揚機構28を介して巻揚げることにより、各振動部材22を型枠16の妻側(図1において右側)へ順次移動させる。
【0045】
この際、振動部材22には巻揚機構28,32により張力が付与されているため、振動部材22が打設完了後のコンクリート層の中間部位に保持された状態となり、この状態のまま妻側に順次移動するので、締固めたコンクリートが流動することなく、打設コンクリート全体を均一に振動させて締固めると共に、振動部材22の型枠16、型枠16とトンネル内壁面26との間に配設させた補強材、への衝突(不快音の発生)あるいは接触(不快音の発生、補強材と打設コンクリートとの密着低下、補強材の結束緩み)を防止することができ、しかも振動部材22の損傷をも防止することができるため、打設コンクリートの強度、品質が極めて向上する。
【0046】
また、振動部材22は型枠16の妻側から巻揚機構28を介して巻揚、繰出すことにより、型枠16の長さ方向に移動させることができ、従来のようにコンクリート打設に応じてその都度各検査窓を開閉させて振動部材を移動させる作業が皆無となる。
【0047】
また、振動部材22の外周に芯材24を配してあるため、振動部材22の強度、耐摩耗性が向上すると共に、巻揚機構28への巻揚、繰出し時、および型枠16とトンネル内壁面26との間に配設させた補強材(図示略)への接触時にも牽引部18が損傷することがなく、取扱性も向上する。
【0048】
また、振動部材22の振動部20を間欠振動させることにより、打設コンクリート14を長時間、連続振動させることがなく、コンクリートが水分とコンクリートとに分離することがなくなり、打設コンクリートの強度、耐久性をさらに向上させることができる。
【0049】
また、必要に応じて振動部材22を巻揚機構28を介して巻揚、繰出すことにより、振動部材22を型枠16の天板部48上方を往復移動させ、打設コンクリート全体を数回振動させ、締固め効率をより一層向上させることができる。
【0050】
また、打設コンクリートの振動完了後、振動部材22を巻揚機構28により妻側外方に巻揚後、振動部材22の振動部20の先端の牽引材30を取外し、この牽引材30を型枠16内の別の巻揚機構32に巻揚、収納する。
【0051】
さらに、巻揚機構28による振動部材22の巻揚毎に、巻揚げられた振動部材22、特に牽引部18に付着した打設コンクリート14が、洗浄機構40により洗浄除去される。
【0052】
このため、従来行っていた使用後直ちに付着した打設コンクリートを除去する洗浄作業を省略することができる。
【0053】
本使用方法において、型枠16の天板部48とトンネル内壁面26との間への打設コンクリートの締固め工程を説明してあるが、型枠16の下部または側部とトンネル内壁面26との間への打設コンクリートの締固めも、本使用方法と同様に行う。
【0054】
このように、本発明の方法および装置によれば、強度、耐摩耗性、取扱性を向上させた振動部材22により型枠16とトンネル内壁面26との間全体への打設完了後の打設コンクリートを簡易、安全、かつ均一で高品質に締固めることができ、しかも付着した打設コンクリートをも洗浄除去することができる。
【0055】
また、図3および図4に本装置の別の例が示してある。
【0056】
本例は、前記例の振動部材22の先端を、牽引材30を介して別の巻揚機構32に装着するのに代えて、振動部材22の先端を、既コンクリート打設部34に埋設されてトンネル前方に延出させた案内軌道部材56、例えばワイヤーに装着し、この案内軌道部材56に沿わせて振動部材22を移動させるものである。
【0057】
この案内軌道部材56のトンネル前方の延出端は、レバーブロック(登録商標)(図示略)により張力を付与しておくことが望ましい。
【0058】
本例の使用方法は、振動部材22を、コンクリート打設時に(コンクリート打設量に応じて)移動させて、打設コンクリートを振動させ、締固める。
【0059】
このため、前記例に対し、振動部材22の型枠16、型枠16とトンネル内壁面26との間に配設させた補強材への衝突あるいは接触を防止する効果がやや小さくなるものの、打設コンクリートの振動完了後、振動部材22を巻揚機構28により妻側外方に巻揚、振動部材22の振動部20の先端を案内軌道部材56から取外すだけで、案内軌道部材56をそのまま打設コンクリート中に埋設させるため、収納する必要がなく、この作業を省略することができる。
【0060】
また、打設コンクリート中に埋設された案内軌道部材56は、補強材としての役割を果たす。
【0061】
なお、両例において、型枠16を折畳み自在とすることは自由である。
【0062】
また、振動部材22を牽引に適した構造とするための芯材24の配置位置は、振動部材22の外周であるが、振動部材22の内部としてもよく、また外周および内部の両方に配してもよく、また芯材によらない牽引に適した他の構造を採用することは自明である。
【0063】
また、型枠16とトンネル内壁面26との間へのコンクリート打設量を感知するコンクリートセンサーを設置し、コンクリートセンサーのコンクリート打設完了の感知により、コンクリート打設口44からのコンクリート打設、停止、振動部材22の振動、各巻揚機構28の作動(振動部材22の型枠16の長さ方向への移動)、等を連動させることにより、作業の自動化を図り、作業性をより一層向上させることができる。
【0064】
また、振動部材22、巻揚機構28,32は複数であるが、1個としてもよく、その設置数は特に限定されるものではない。
【0065】
また、巻揚機構32は型枠16内に設置してあるが、型枠16外方の足場に設置させてもよく、その他の個所に設置させることは自明である。
【0066】
また、牽引材30はラップ側の既コンクリート打設部34に固定させた案内ローラ36に係止させてあるが、パイプ、フック等の係止手段とすることは自明である。
【0067】
また、型枠16内の巻揚機構32に装着させた牽引材30を、打設コンクリートの養生硬化後、巻揚機構32から切離し、打設コンクリート内に埋設させることは自由である。
【0068】
また、型枠16とトンネル内壁面26との間へのコンクリート打設はコンクリート打設口44からによるものであるが、コンクリート搬送管46を型枠16の各検査窓(図示略)から突出させてコンクリート打設することは自明である。
【0069】
また、各巻揚機構28,32により張力を付与させて配設された振動部材22を型枠16の周方向に移動させることにより、締固め効率をさらに向上させることは自明である。
【0070】
また、振動部材22の牽引部18は接続ケーブルであるが、接続ケーブルを内装させたロープ、無端チェーン、細幅ベルト、等とすることは自由である。
【0071】
また、牽引材30、案内軌道部材56はワイヤーであるが、ロープ、無端チェーン、細幅ベルト、等とすることは自由である。
【0072】
また、振動部材22の先端を牽引材30を介して別の巻揚機構32に装着してあるが、巻揚機構32に装着することなく、振動部材22の先端を自由端として使用しても、本発明特有の作業を簡易、安全に行え、振動部材22の強度、耐摩耗性、取扱性が向上する効果は十分に得られる。
【0073】
また、洗浄機構40はリング型シャワーであり、水圧(水)により振動部材22に付着した打設コンクリートを洗浄除去するものであるが、洗剤、コンクリート剥離剤等を混入して洗浄すること、あるいは他の洗浄機構を採用すること、は自明である。
【0074】
また、洗浄機構40を省略しても、本発明特有の作業を簡易、安全に行え、振動部材22の強度、耐摩耗性、取扱性が向上する効果は十分に得られる。
【0075】
また、本発明の方法および装置は、略半円形のトンネル、円形のトンネル、例えば海中トンネル、下水道等、特に用途は限定されない。
【0076】
【発明の効果】
本発明に係るコンクリート締固め方法および装置によれば、長尺な牽引部の先端に振動部を備え、振動部材を、型枠とトンネル内壁面との間に、その基端を巻揚機構に装着して型枠の長さ方向に沿わせて配設させた後、型枠とトンネル内壁面との間全体への打設完了後、またはコンクリート打設時に、打設コンクリートを、振動部材により振動させると共に、巻揚機構を介して振動部材を巻揚、繰出すことにより、振動部材を振動、移動させ、締固めるため、強度、耐摩耗性、取扱性を向上させた振動部材により、打設コンクリートを、簡易かつ安全に、しかも締固めた打設コンクリートが流動することなく、効率良く締固めることができる。
【0077】
また、振動部材の先端を、牽引材を介して別の巻揚機構に装着し、振動部材に張力を付与することにより、振動部材が打設完了後の打設コンクリート層の中間部位に保持された状態となり、この状態のまま妻側に順次移動するので、締固めたコンクリートが流動することなく、打設コンクリート全体を均一に振動させて締固めると共に、型枠、型枠とトンネル内壁面との間に配設させた補強材、への衝突(不快音の発生)あるいは接触(不快音の発生、補強材と打設コンクリートとの密着低下、補強材の結束緩み)を防止することができ、しかも振動部材の損傷をも防止することができるため、打設コンクリートの強度、品質が極めて向上する。
【0078】
また、振動部材の先端を、既コンクリート打設部に埋設されてトンネル前方に延出させた案内軌道部材に装着し、この案内軌道部材に沿わせて振動部材を移動させることにより、打設コンクリートの振動完了後、振動部材を巻揚機構により妻側外方に巻揚、振動部材の振動部の先端を案内軌道部材から取外すだけで、案内軌道部材をそのまま打設コンクリート中に埋設させるため、収納する必要がなく、この作業を省略することができるばかりか、打設コンクリート中に埋設された案内軌道部材が補強材としての役割を果たす。
【0079】
また、巻揚機構に近接させて洗浄機構を配備させることにより、巻揚機構による巻揚時に、振動部材に付着した打設コンクリートを洗浄除去することができ、従来行っていた使用後直ちに付着コンクリートを除去する洗浄作業を省略し、作業効率が極めて向上する。
【図面の簡単な説明】
【図1】本発明に係るコンクリート締固め装置の要部拡大側面図。
【図2】同、要部拡大正面図。
【図3】別の例を示す要部側面図。
【図4】同、要部拡大側面図。
【図5】従来のコンクリートの締固め作業を示す拡大側面図。
【符号の説明】
12 トンネル
14 コンクリート
16 型枠
18 牽引部
20 振動部
22 振動部材
24 芯材
26 トンネル内壁面
28,32 巻揚機構
30 牽引材
40 洗浄機構
56 案内軌道部材
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to a method and an apparatus for vibrating and compacting cast concrete when placing concrete for lining in a tunnel, mainly for secondary lining.
In this specification, “placement” refers to filling mud concrete that has not been cured and cured between the mold and the inner wall surface of the tunnel.
[0002]
[Prior art]
Originally, for concrete laying for tunnel lining, mainly for secondary lining, the formwork for placing concrete was folded and transported forward after the concrete placement, It was done with a mobile formwork that was unfolded and installed, and the concrete was cast there.
[0003]
Concrete placement with this formwork can be done by placing concrete transport pipes from the openable inspection windows at many places on the formwork after installation at a predetermined position in the tunnel, or using a dedicated concrete placement opening. It was done by connecting a concrete transfer pipe.
[0004]
Moreover, in order to reinforce the cast concrete, a reinforcing material such as a reinforcing bar has been disposed in advance between the formwork and the inner wall surface of the tunnel.
[0005]
In addition, in order to improve the strength and durability of the concrete after curing and curing, a vibration tool is inserted and protruded from the same or another inspection window into the concrete immediately after placement, and the vibration is caused by the vibration of the vibration tool. The concrete was compacted to remove bubbles mixed in the concrete.
[0006]
This vibration tool is mainly provided with a vibration part at the end of the power cable. For this reason, the operator directly grips the power cable, opens the inspection window to protrude, and if necessary, the inspection window. The vibration part is inserted into the placed concrete and moved to the front, back, left and right and up and down (shaking), and the placed concrete is compacted by the vibration of the vibration part, and the compaction work is completed. Then, it was stored from the inspection window (see FIG. 5).
[0007]
In FIG. 5, 60 is a mold, 62 is an inspection window, 64 is a concrete placement port, 66 is a vibration tool, 68 is a power cord, 70 is concrete, 72 is a tunnel inner wall surface, 74 is a concrete conveyance pipe, and 76. Indicates an operator.
[0008]
For this reason, there has been the following problem in the compaction work of placing concrete manually by the operator.
[0009]
First, the operator grips the power cable of the vibration tool, and manually projects the vibration part of the vibration tool from each inspection window of the formwork, inserts it into the cast concrete, moves it up and down, left and right, The cast concrete was compacted by the vibration of the vibration part, and after the compaction work was completed, it was stored from the inspection window, so the vibration due to the vibration tool to the concrete was local and uneven, and compaction efficiency was not good It was.
[0010]
Secondly, when the vibrating tool is vibrated from the inspection window and stored, the vibrating part of the vibrating tool comes into contact with the outer peripheral edge of the protruding part of the inspection window, so that the vibrating part is rotated by the vibration, This turning force acts on the gripping worker more than necessary, and this turning force is transmitted to the power cable, and sometimes the power cable is disconnected from the socket, which hinders work.
[0011]
Thirdly, it is necessary for the operator to get out of the inspection window and perform the compacting work as necessary, and there is a danger, so the work must be done carefully, and the work should be done safely and in a short time. In addition to being unable to perform the process, it was a cause of process delay.
[0012]
Fourth, when concrete is placed near the inspection window during compaction work, the vibration tool is stored from the inspection window under work, this inspection window is closed, and moved to another inspection window. However, it is necessary to open the inspection window and project the vibration tool, and to vibrate the vicinity of the inspection window where the concrete has been placed, and vibrate the vicinity of the inspection window during compaction work from the same location. I couldn't.
[0013]
Fifth, the vibrating tool comes into contact with the outer peripheral surface of the mold during vibration, and mud concrete separates into moisture and concrete at the contact surface, which is a factor that decreases the strength and durability of the concrete after curing. It was.
[0014]
In view of the above-mentioned drawbacks, there have been devices (for example, see Patent Document 1) for causing the vibration tool to protrude from the inside of the mold frame to the outside, and devices (for example, see Patent Document 2) for moving the vibration tool to the outside of the mold frame.
[0015]
[Patent Document 1]
Japanese Patent No. 3278355 (page 3-4, FIGS. 1-6, 9)
[Patent Document 2]
Japanese Patent Laid-Open No. 2001-82087 (page 3-5, FIG. 1-7)
[0016]
Further, immediately after use, the placing concrete attached to the vibration tool and the power cord was manually removed.
[0017]
[Problems to be solved by the invention]
In Patent Document 1, the place where the placing concrete of the vibration tool is compacted is limited, and in Patent Document 2, it is necessary to move the vibration tool visually by the operator, and both control mechanisms move the vibration tool. Is indispensable, the number of components is large, and the cost has increased.
[0018]
Also, in both documents and the prior art, the compacting work of the placing concrete with the vibration tool for improving the strength and durability of the concrete was performed every time immediately after the concrete was placed. The concrete flowed to the end of the formwork and could not compact the entire cast concrete.
[0019]
In addition, a reinforcing material is disposed between the formwork and the inner wall surface of the tunnel, and the position of the vibration tool inserted into the cast concrete is not constant. The sex was not good.
[0020]
In addition, the vibration member collides with or comes into contact with the reinforcing material disposed between the mold and the tunnel inner wall surface, and the outer peripheral surface of the mold, generating unpleasant noise, lowering the adhesion between the reinforcing material and the cast concrete, and the reinforcing material. In addition to the loosening of the binding, the vibration tool may be damaged, and there is a problem in durability.
[0021]
In addition, it is necessary to manually remove the cast concrete adhering to the vibration tool and the power cord after use, which is troublesome.
[0022]
In view of the above drawbacks, the present invention provides a concrete compacting method and apparatus capable of compacting cast concrete easily and safely and efficiently, and also removing cast concrete that has adhered. It is the purpose.
[0023]
[Means for Solving the Problems]
The present invention relates to a process and an apparatus for placing concrete in a tunnel using a formwork, comprising a vibration part at the end of a long traction part, and the vibration member is disposed between the formwork and the inner wall surface of the tunnel. In addition, after the base end is attached to the hoisting mechanism and disposed along the length direction of the formwork, the concrete is placed between the formwork and the inner wall surface of the tunnel, or at the time of concrete placement. The vibrating member is vibrated, and the vibrating member is wound and fed through a winding mechanism, thereby moving along the length direction of the formwork and compacting the concrete, or , Characterized in that the tip of the vibration member is attached to another hoisting mechanism via a pulling material and tension is applied to the vibration member, or the tip of the vibration member is embedded in the existing concrete placing part Attached to the guide track member extended forward of the tunnel The vibration member is moved along the guide track member, or the cleaning mechanism is provided in the vicinity of the winding mechanism, so that the vibration member is attached to the vibration member at the time of winding by the winding mechanism. The cast concrete is washed and removed.
[0024]
DETAILED DESCRIPTION OF THE INVENTION
The concrete compaction apparatus according to the present invention is mounted on a movable mold 16 for placing concrete 14 for lining, mainly secondary lining, in a tunnel 12. As shown in FIG. 1 and FIG. 2, it has the following configuration.
[0025]
A core member 24 is disposed over the entire length of the outer periphery of the vibration member 22 including the vibration unit 20 at the tip of the long traction unit 18.
[0026]
In this example, the vibrating member 22 is connected to a power source (not shown) via a long traction part 18 in which a connecting cable (not shown) is housed.
[0027]
Further, it is desirable that the traction portion 18 is made of a material excellent in weight reduction, handleability, and wear resistance.
[0028]
Further, the core member 24 is a wire, and two wires are arranged on both sides of the outer periphery of the vibration member 22.
[0029]
By disposing the core member 24 on the outer periphery of the vibration member 22, the strength and wear resistance of the vibration member 22 are improved. The traction portion 18 is not damaged even when contacting a reinforcing member (not shown) disposed between the traction member 26 and the structure, and the structure is suitable for traction.
[0030]
A plurality of vibrating members 22 are disposed between the mold 16 and the inner wall surface 26 of the tunnel along the length direction of the mold 16 with the base end attached to the hoisting mechanism 28.
[0031]
The tip of the vibration part 20 of each vibration member 22 is attached to another hoisting mechanism 32 in the mold 16 via a traction material 30.
[0032]
In this example, the hoisting mechanism 28 is an electric winch, and the hoisting mechanism 32 is a spring-type or electric-type reel.
[0033]
The pulling material 30 is a wire and is locked to a guide roller 36 fixed to a pre-concrete placing portion 34 on the lap side of the mold 16.
[0034]
Tension is applied to the vibration member 22 by each of the hoisting mechanisms 28 and 32, and the vibration member 22 is held at an intermediate portion of the placing concrete layer, so that the placement concrete can be vibrated uniformly. Collision (occurrence of unpleasant noise) or contact (occurrence of unpleasant noise), decrease in adhesion between the reinforcing material and the cast concrete, and reinforcement of the reinforcing member disposed between the formwork 16 and the inner wall surface 26 of the tunnel. (Binding loosening) can be prevented, and damage to the vibration member 22 can also be prevented, so that the strength and quality of the cast concrete are greatly improved.
[0035]
A cleaning mechanism 40 is provided between the form plate 16 and the end plate 38 that is brought close to the hoisting mechanism 28 outside the end side of the form frame 16.
[0036]
In this example, the cleaning mechanism 40 is a ring-type shower in which a small hole is drilled in the ring tube toward the center thereof, and is attached to the vibrating member 22, particularly the traction portion 18, when the lifting mechanism 28 is wound. The cast concrete 16 is removed by washing with water pressure (water).
[0037]
Further, a seepage preventing material (not shown) prevents the cast concrete from leaching out of the end plate 38 or into the form frame 16 at the insertion portion of the vibration member 22 of the end plate 38 and the insertion portion of the pulling member 30 of the form frame 16. Is omitted).
[0038]
In the figure, 42 is a stopper for fixing the core member 24 to the outer periphery of the vibration member 22, 44 is a concrete placing port, 46 is a concrete conveying pipe, 48 is a top plate portion of the mold 16, and 50 is an operator. 52 denotes a hopper, and 54 denotes a drain pipe.
[0039]
A method for compacting the concrete 14 for secondary lining placed between the mold 16, for example, the top plate portion 48 and the tunnel inner wall surface 26 using this apparatus will be described in detail below.
[0040]
First, the mold 16 is moved to a predetermined position in the tunnel 12.
[0041]
Next, the base end of the pulling portion 18 of the vibration member 22 is attached to the hoisting mechanism 28 on the outer side 38 of the formwork 16, and the pulling material 30 is attached to another hoisting mechanism 32 in the formwork 16. A plurality of vibration members 22 are arranged along the length direction of the mold 16 by attaching the tip of the vibration part 20 of the vibration member 22 via the front end.
[0042]
Next, the concrete 14 is placed between the mold 16 and the tunnel inner wall surface 26.
[0043]
At this time, the concrete 14 is sequentially placed between the formwork 16 and the tunnel inner wall surface 26 from each concrete placement port 44 of the formwork 16.
[0044]
Next, after completion of placing the concrete 14 between the mold 16 and the inner wall surface 26 of the tunnel, each vibration member 22 is vibrated and wound through the winding mechanism 28, whereby each vibration member 22. Are sequentially moved to the wife side (right side in FIG. 1) of the mold 16.
[0045]
At this time, since the tension is applied to the vibration member 22 by the hoisting mechanisms 28 and 32, the vibration member 22 is held in the intermediate portion of the concrete layer after the placement is completed. Since the compacted concrete does not flow, the entire cast concrete is uniformly vibrated and compacted, and the mold 16 of the vibration member 22, the mold 16 and the inner wall 26 of the tunnel It can prevent collision (occurrence of unpleasant noise) or contact (occurrence of unpleasant noise, decrease in adhesion between the reinforcing material and the cast concrete, loose binding of the reinforcing material) and vibration to the disposed reinforcing material, and vibration Since damage to the member 22 can also be prevented, the strength and quality of the cast concrete are greatly improved.
[0046]
Moreover, the vibrating member 22 can be moved in the length direction of the mold 16 by winding and unwinding from the wife side of the mold 16 via the winding mechanism 28. Accordingly, there is no work for moving the vibration member by opening and closing each inspection window each time.
[0047]
Further, since the core member 24 is disposed on the outer periphery of the vibration member 22, the strength and wear resistance of the vibration member 22 are improved, and at the time of winding and unwinding to the winding mechanism 28, and the mold 16 and the tunnel. Even when contacting a reinforcing material (not shown) disposed between the inner wall surface 26 and the traction portion 18 is not damaged, the handleability is improved.
[0048]
Further, by intermittently vibrating the vibrating portion 20 of the vibration member 22, the cast concrete 14 is not continuously vibrated for a long time, the concrete is not separated into moisture and concrete, and the strength of the cast concrete, The durability can be further improved.
[0049]
Further, if necessary, the vibrating member 22 is lifted and unwound through the hoisting mechanism 28 to reciprocate the vibrating member 22 above the top plate portion 48 of the mold 16 so that the entire placing concrete is moved several times. It can be vibrated and the compaction efficiency can be further improved.
[0050]
Further, after the vibration of the cast concrete is completed, the vibrating member 22 is wound outwardly by the hoisting mechanism 28 and then the pulling material 30 at the tip of the vibrating portion 20 of the vibrating member 22 is removed. Winding and storing in another hoisting mechanism 32 in the frame 16.
[0051]
Further, every time the vibration member 22 is wound by the winding mechanism 28, the wound concrete member 14, particularly the placement concrete 14 attached to the traction portion 18 is cleaned and removed by the cleaning mechanism 40.
[0052]
For this reason, the washing | cleaning operation | work which removes the cast concrete adhering immediately after use conventionally performed can be abbreviate | omitted.
[0053]
In this method of use, the process of compacting the cast concrete between the top plate portion 48 of the mold 16 and the tunnel inner wall surface 26 has been described. The concrete to be placed in between is also compacted in the same way as this method of use.
[0054]
As described above, according to the method and the apparatus of the present invention, the vibration member 22 with improved strength, wear resistance, and handleability can be used after the entire placement between the mold 16 and the tunnel inner wall surface 26 is completed. The installed concrete can be compacted simply, safely, uniformly and with high quality, and the cast concrete that has adhered can be removed by washing.
[0055]
3 and 4 show another example of the present apparatus.
[0056]
In this example, instead of attaching the tip of the vibration member 22 of the above example to another hoisting mechanism 32 via the traction member 30, the tip of the vibration member 22 is embedded in the existing concrete placing portion 34. The guide track member 56 extended to the front of the tunnel, for example, is attached to a wire, and the vibrating member 22 is moved along the guide track member 56.
[0057]
The extension end of the guide track member 56 in front of the tunnel is preferably tensioned by a lever block (registered trademark) (not shown).
[0058]
In the method of use of this example, the vibration member 22 is moved during concrete placement (in accordance with the amount of concrete placement) to vibrate and compact the placement concrete.
[0059]
For this reason, the effect of preventing collision or contact with the reinforcing member disposed between the mold 16 of the vibrating member 22 and the mold 16 and the tunnel inner wall surface 26 is slightly smaller than the above example. After the vibration of the installed concrete is completed, the vibrating member 22 is wound outwardly by the hoisting mechanism 28 and the tip of the vibrating portion 20 of the vibrating member 22 is simply removed from the guiding track member 56. Since it is buried in the concrete, it is not necessary to store it and this work can be omitted.
[0060]
The guide track member 56 embedded in the cast concrete serves as a reinforcing material.
[0061]
In both examples, the mold 16 can be freely folded.
[0062]
Further, the arrangement position of the core member 24 for making the vibration member 22 suitable for traction is the outer periphery of the vibration member 22, but may be inside the vibration member 22, and may be arranged both on the outer periphery and inside. It is obvious that other structures suitable for traction not depending on the core material may be adopted.
[0063]
In addition, a concrete sensor that detects the amount of concrete placed between the formwork 16 and the inner wall surface 26 of the tunnel is installed, and the concrete placement from the concrete placement port 44 is performed by detecting the completion of the concrete placement of the concrete sensor. By linking the stop, the vibration of the vibration member 22, the operation of each hoisting mechanism 28 (the movement of the vibration member 22 in the length direction of the mold 16), etc., the work is automated and the workability is further improved. Can be made.
[0064]
Moreover, although the vibration member 22 and the winding mechanisms 28 and 32 are plural, the number may be one, and the number of installation is not particularly limited.
[0065]
Further, although the hoisting mechanism 32 is installed in the mold 16, it may be installed on a scaffold outside the mold 16, and it is obvious that it is installed in other places.
[0066]
In addition, the traction member 30 is locked by a guide roller 36 fixed to the existing concrete placing portion 34 on the lap side, but it is obvious that the pulling member 30 is a locking means such as a pipe or a hook.
[0067]
Further, the traction material 30 attached to the hoisting mechanism 32 in the formwork 16 can be freely separated from the hoisting mechanism 32 after being cured and hardened, and embedded in the cast concrete.
[0068]
In addition, the concrete placement between the mold 16 and the tunnel inner wall surface 26 is from the concrete placement port 44, but the concrete transfer pipe 46 is projected from each inspection window (not shown) of the mold 16. It is obvious to cast concrete.
[0069]
Further, it is obvious that the compaction efficiency can be further improved by moving the vibrating member 22 provided with tension by the hoisting mechanisms 28 and 32 in the circumferential direction of the mold 16.
[0070]
The pulling portion 18 of the vibration member 22 is a connection cable, but it is free to use a rope, an endless chain, a narrow belt, or the like with the connection cable built therein.
[0071]
Moreover, although the traction material 30 and the guide track member 56 are wires, they can be freely used as a rope, an endless chain, a narrow belt, or the like.
[0072]
Further, although the tip of the vibration member 22 is attached to another hoisting mechanism 32 via the traction member 30, the tip of the vibration member 22 may be used as a free end without being attached to the hoisting mechanism 32. The work peculiar to the present invention can be performed easily and safely, and the effect of improving the strength, wear resistance, and handleability of the vibration member 22 can be sufficiently obtained.
[0073]
Further, the cleaning mechanism 40 is a ring-type shower and is used to clean and remove the cast concrete adhering to the vibration member 22 by water pressure (water). It is self-evident to employ other cleaning mechanisms.
[0074]
Even if the cleaning mechanism 40 is omitted, the work peculiar to the present invention can be performed easily and safely, and the effect of improving the strength, wear resistance, and handleability of the vibration member 22 can be sufficiently obtained.
[0075]
In addition, the method and apparatus of the present invention are not particularly limited in use, such as a substantially semicircular tunnel, a circular tunnel, such as a submarine tunnel, a sewer, and the like.
[0076]
【The invention's effect】
According to the concrete compaction method and apparatus of the present invention, a vibration part is provided at the distal end of a long traction part, and the vibration member is wound between the mold and the inner wall surface of the tunnel, and the proximal end thereof is a hoisting mechanism. And then placed along the length of the formwork, after the placement of the entire space between the formwork and the inner wall surface of the tunnel, or at the time of concrete placement, the cast concrete is used as a vibration member. In order to vibrate, move, and compact the vibration member by winding and unwinding the vibration member via the winding mechanism, the vibration member having improved strength, wear resistance, and handleability. The cast concrete can be compacted easily and safely, and without causing the compacted cast concrete to flow.
[0077]
In addition, by attaching the tip of the vibration member to another hoisting mechanism via a traction member and applying tension to the vibration member, the vibration member is held at an intermediate portion of the placement concrete layer after completion of placement. Since the compacted concrete does not flow, the entire cast concrete is uniformly vibrated and compacted, and the formwork, the formwork, and the tunnel inner wall surface. Collisions (occurrence of unpleasant noise) or contact (occurrence of unpleasant noise, reduced adhesion between the reinforcing material and the cast concrete, loose binding of the reinforcing material) can be prevented. Moreover, since the vibration member can be prevented from being damaged, the strength and quality of the cast concrete are greatly improved.
[0078]
Further, the tip of the vibration member is attached to a guide track member embedded in the existing concrete placement portion and extended forward of the tunnel, and the vibration member is moved along the guide track member, thereby placing the concrete. After the vibration is completed, the vibrating member is hoisted outward by the hoisting mechanism, and by simply removing the tip of the vibrating portion of the vibrating member from the guide track member, the guide track member is embedded in the cast concrete as it is. There is no need to store it and this work can be omitted, and the guide track member embedded in the cast concrete serves as a reinforcing material.
[0079]
In addition, by placing the cleaning mechanism close to the hoisting mechanism, it is possible to wash and remove the cast concrete adhering to the vibration member when the hoisting mechanism is hoisted. This eliminates the cleaning work to remove the slag, thus greatly improving the work efficiency.
[Brief description of the drawings]
FIG. 1 is an enlarged side view of a main part of a concrete compaction apparatus according to the present invention.
FIG. 2 is an enlarged front view of the main part of the same.
FIG. 3 is a side view of a main part showing another example.
FIG. 4 is an enlarged side view of the main part of the same.
FIG. 5 is an enlarged side view showing a conventional concrete compacting operation.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 12 Tunnel 14 Concrete 16 Formwork 18 Traction part 20 Vibration part 22 Vibration member 24 Core material 26 Tunnel inner wall surface 28,32 Lifting mechanism 30 Traction material 40 Cleaning mechanism 56 Guide track member

Claims (4)

トンネル(12)内に型枠(16)を使用して覆工用のコンクリート(14)を打設する装置において、長尺な牽引部(18)の先端に振動部(20)を備えなる振動部材(22)の外周または/および内部の長さ方向全域に芯材 (24) を配し、この振動部材 (22)、その基端を巻揚機構(28)に装着し型枠(16)の長さ方向に沿わせて配設させ、振動部材 (22) の先端を、牽引材 (30) を介して別の巻揚機構 (32) に装着し、振動部材 (22) に張力を付与することを特徴とするコンクリート締固め装置An apparatus for pouring concrete (14) for lining using tunnel (12) the mold in (16), comprising includes a vibrating portion (20) at the distal end of the elongated traction unit (18) arranged core (24) on the outer periphery or / and inside the longitudinal entire area of the vibrating member (22), equipped with the vibration member (22), the proximal end of it to the winch mechanism (28), the mold Arranged along the length direction of the frame (16), the tip of the vibration member (22 ) is attached to another hoisting mechanism (32) via the traction material (30) , and the vibration member (22) Concrete compaction device characterized by imparting tension to トンネル(12)内に型枠(16)を使用して覆工用のコンクリート(14)を打設する装置において、長尺な牽引部(18)の先端に振動部(20)を備えてなる振動部材(22)の外周または/および内部の長さ方向全域に芯材(24)を配し、この振動部材(22)を、その基端を巻揚機構(28)に装着し、型枠(16)の長さ方向に沿わせて配設させ、巻揚機構 (28) に近接させて洗浄機構 (40) を配備させることにより、巻揚機構 (28) による巻揚時に、振動部材 (22) に付着した打設コンクリートを洗浄除去することを特徴とするコンクリート締固め装置。In a device for placing concrete (14) for lining using a formwork (16) in a tunnel (12), a vibration part (20) is provided at the tip of a long traction part (18). A core member (24) is arranged on the entire circumference of the vibration member (22) and / or inside the longitudinal direction, and the vibration member (22) is attached to the hoisting mechanism (28) at its base end to form a frame. (16) placed along the lengthwise is disposed, by deploying the cleaning mechanism (40) in close proximity to the winch mechanism (28), when winch according winch mechanism (28), the vibration member ( A concrete compaction device characterized by washing and removing cast concrete adhering to 22) . 振動部材(22)の先端を、既コンクリート打設部 (34) に埋設されてトンネル前方に延出させた案内軌道部材 (56) に装着し、この案内軌道部材 (56) に沿わせて振動部材 (22) を移動させることを特徴とする請求項1又は2記載のコンクリート締固め装置。 Vibration of the tip of the vibrating member (22), is embedded in the already concrete portion (34) mounted on the guideway members by extending the tunnel front (56), and along with this guide track member (56) concrete compaction apparatus according to claim 1 or 2, wherein the moving member (22). 請求項1から3のいずれか一項に記載のコンクリート締固め装置を用いたコンクリート締固め方法において、長尺な牽引部 (18) の先端に振動部 (20) を備え、該振動部材 (22) を、型枠 (16) とトンネル内壁面 (26) との間に、その基端を巻揚機構 (28) に装着して型枠 (16) の長さ方向に沿わせて配設させた後、型枠 (16) とトンネル内壁面 (26) との間へのコンクリート (14) 打設後、またはコンクリート打設時に、振動部材 (22) を振動させると共に、巻揚機構 (28) を介して振動部材 (22) を巻揚、繰出すことにより、型枠 (16) の長さ方向に沿わせて移動させ、コンクリート (14) を締固めることを特徴とするコンクリート締固め方法 In the concrete compaction method using the concrete compaction apparatus as described in any one of Claim 1 to 3 , a vibration part (20) is provided in the front-end | tip of a long traction part (18) , and this vibration member (22 ) Between the formwork (16) and the inner wall surface (26) of the tunnel , with its proximal end attached to the hoisting mechanism (28) and being arranged along the length of the formwork (16). After the concrete (14) is placed between the formwork (16) and the inner wall surface (26) of the tunnel , or when the concrete is placed , the vibrating member (22) is vibrated and the hoisting mechanism (28) winch vibration member (22) via, by unwinding, is moved along a longitudinal direction of the mold (16), concrete (14) to said the compacting of Turkey Nkurito compaction Way .
JP2002329301A 2001-11-28 2002-11-13 Concrete compaction method and apparatus Expired - Lifetime JP3735600B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002329301A JP3735600B2 (en) 2001-11-28 2002-11-13 Concrete compaction method and apparatus

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
JP2001362578 2001-11-28
JP2001362578 2001-11-28
JP2001-362578 2001-11-28
JP2002329301A JP3735600B2 (en) 2001-11-28 2002-11-13 Concrete compaction method and apparatus

Publications (3)

Publication Number Publication Date
JP2003227297A JP2003227297A (en) 2003-08-15
JP2003227297A6 JP2003227297A6 (en) 2004-09-09
JP3735600B2 true JP3735600B2 (en) 2006-01-18

Family

ID=27759401

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002329301A Expired - Lifetime JP3735600B2 (en) 2001-11-28 2002-11-13 Concrete compaction method and apparatus

Country Status (1)

Country Link
JP (1) JP3735600B2 (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4691397B2 (en) * 2005-05-31 2011-06-01 前田建設工業株式会社 Vibrator system for concrete compaction
JP4557941B2 (en) * 2006-08-31 2010-10-06 株式会社奥村組 Tunnel lining concrete placement method and placement structure
JP4557942B2 (en) * 2006-08-31 2010-10-06 株式会社奥村組 Tunnel lining concrete placement method and placement structure
JP4610540B2 (en) * 2006-09-28 2011-01-12 株式会社奥村組 Tunnel lining concrete placement method and placement structure
JP5480067B2 (en) * 2010-08-26 2014-04-23 岐阜工業株式会社 Method and apparatus for placing lining concrete wall in tunnel
JP5480111B2 (en) * 2010-11-26 2014-04-23 鹿島建設株式会社 Covering concrete wall placing device in tunnel
CN109372552B (en) * 2018-11-26 2023-10-31 四川蓝海智能装备制造有限公司 Die spraying device with electromagnetic template
JP7289240B2 (en) * 2019-07-30 2023-06-09 前田建設工業株式会社 Automatic operation device for pull-out vibrator used for construction of tunnel lining
JP7148752B1 (en) 2022-06-16 2022-10-05 大栄工機株式会社 Concrete compaction method

Also Published As

Publication number Publication date
JP2003227297A (en) 2003-08-15

Similar Documents

Publication Publication Date Title
JP3735600B2 (en) Concrete compaction method and apparatus
JP2003227297A6 (en) Concrete compaction method and apparatus
JP2003003795A (en) Tunnel lining concrete compacting apparatus, and compacting method using the same
AU7154481A (en) Method and arrangement on extracting, reeling up, pulling in,etc., of a heavy cable or similar
JP4080300B2 (en) Method and apparatus for placing concrete for tunnel
JP3927550B2 (en) Concrete compaction device for tunnel arch crown
JP3278355B2 (en) Vibration method of cast concrete for tunnel and vibrating device of cast concrete for tunnel
JP2001262986A (en) Concrete compacting method and device therefor
JP4044827B2 (en) Concrete compaction method and apparatus
JP4799453B2 (en) Tunnel lining concrete placement method
JP4812666B2 (en) Tunnel lining concrete placement method
JP3338878B2 (en) Apparatus and method for applying anticorrosion sheet
JP4241204B2 (en) Method and apparatus for compacting concrete at the top of the tunnel
JP2001082087A (en) Concrete compacting method and its device
JP4610540B2 (en) Tunnel lining concrete placement method and placement structure
JPH0925724A (en) Concrete placing hopper
JP2004284154A (en) Device for preventing backward falling of concrete hopper gate
JP3871239B2 (en) Keren device for slide center
JP4150242B2 (en) Residual cable removal device
JPH08254098A (en) Stamping device of lining concrete for tunneling method
JP4459637B2 (en) Vibrator system for concrete compaction
JP2002227597A (en) Concrete placing method for tunnel and device thereof
CN218148322U (en) Construction device for reserving anchor cable holes
JPS63223239A (en) Apparatus for discharging accumulated substance in sewage
JP2000145149A (en) Concrete compaction method and its apparatus

Legal Events

Date Code Title Description
A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050707

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20050712

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20050912

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20051011

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20051024

R150 Certificate of patent or registration of utility model

Ref document number: 3735600

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081028

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111028

Year of fee payment: 6

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111028

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20141028

Year of fee payment: 9

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313532

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term