JP3729028B2 - Water stop method for joints in steel pipe sheet piles - Google Patents

Water stop method for joints in steel pipe sheet piles Download PDF

Info

Publication number
JP3729028B2
JP3729028B2 JP2000178096A JP2000178096A JP3729028B2 JP 3729028 B2 JP3729028 B2 JP 3729028B2 JP 2000178096 A JP2000178096 A JP 2000178096A JP 2000178096 A JP2000178096 A JP 2000178096A JP 3729028 B2 JP3729028 B2 JP 3729028B2
Authority
JP
Japan
Prior art keywords
joint
steel pipe
sheet pile
pipe sheet
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2000178096A
Other languages
Japanese (ja)
Other versions
JP2001355232A (en
Inventor
東興 落合
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2000178096A priority Critical patent/JP3729028B2/en
Publication of JP2001355232A publication Critical patent/JP2001355232A/en
Application granted granted Critical
Publication of JP3729028B2 publication Critical patent/JP3729028B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Description

【0001】
【発明の属する技術分野】
本発明は、鋼管矢板における継手部の止水方法の改良に関する。
【0002】
【従来の技術】
鋼管矢板を用いた止水工法は、鋼管矢板の両側部にその長手方向に沿って一体化された継手部を介して隣接する矢板同士を順次接続しながら打設することで、止水を行う工法である。これに用いられる継手部は図4に示すように、矢板本体1の両側部に平行に溶接され、かつ長手方向に沿って細長状のスリット2aを形成した継手パイプ2からなっており、スリット2aを通じて両継手パイプ2同士が断面鈎形に係合することで矢板間の接続を行う。
【0003】
この場合における継手部の止水性を確保するために、従来では矢板の建て込み後、継手パイプ2の内部に詰った土砂を洗浄除去し、次いで係合状態での両継手パイプ2に形成される隙間a,b,cのうち大きな隙間の部分を選んで不織布などで作られた細長状の袋を隙間内に挿入し、次いで、袋内にモルタルを充填することで、袋をパイプ内部に密着させることで止水を行っていた。
【0004】
【発明が解決しようとする課題】
しかしながら、この止水方法は、充填作業の前に内部洗浄を行うため、作業が面倒である。また、矢板の鉛直精度により、継手部分の間隔が確保できない場合に、継手部内の洗浄が不可能となったり、深い位置でのエアーリフトの効率低下により、洗浄が十分に出来なかったり、あるいは袋の挿入深度が制限されることにより、モルタル充填が十分になされなかった。例えば、図示の場合には、目視外観上、aの隙間が一番大きいと仮定しても、下方は次第に狭くなることもあるため、以上の不具合が生ずる可能性が高い。従って、このような場合に備えて、矢板背面の地盤中に薬液を注入することで止水性を確保することが必須であり、この種の補助工法の付加により工費のコストアップを招来するという課題があった。
【0005】
本発明は、以上の課題を解決するものであって、その目的は、止水のために洗浄の必要がなく、しかも、パイプ内部に固化材を確実に充填することで、十分な止水性を確保できるようにした鋼管矢板における継手部の止水方法を提供するものである。
【0006】
【課題を解決するための手段】
前記目的を達成するため、本発明方法は、鋼管矢板の本体両側に設けた継手パイプのうち、次に建て込む鋼管矢板と連結する継手パイプの底面を閉塞し、かつ継手パイプの鉛直方向に形成されたスリットを閉塞する部材を継手パイプ内に取外し可能に配置し、鋼管矢板の建て込み後、前記継手部パイプ内に遅延性固化材を充填し、しかる後、閉塞部材を引抜きつつ、閉塞部材の容積分に相当する量の遅延性固化材を追加充填することを特徴とする。従って、本発明方法では、打設後の止水性確保のための作業としては遅延性固化材の充填作業と閉塞部材の引抜き作業のみにより、固化材が継手内部に確実に充填される。また次の鋼管矢板を継ぐ時には、固化材は固化していない状態であるため充填処置を施した継手パイプ内に鈎形に貫入させながら継ぐことが出来、最終的には固化材が固化することで、継手部分の止水性が確保される。
【0007】
この発明においては、閉塞部材が鋼管であることが簡易で好ましい。また、前記閉塞部材の頭部に共上がり防止用金具を取外し可能に設けることにより、矢板打設時の貫入圧力により閉塞部材が取付位置からはずれることを確実に防止できる。
【0008】
【発明の実施の形態】
以下、本発明の好ましい実施の形態につき、添付図面を参照して詳細に説明する。図1,2は本発明方法が適用される鋼管矢板10を示している。この矢板10は、前記と同様に矢板本体12と、本体12の両側にその長手方向に沿って溶接などにより一体化された左右の継手パイプ14,16とからなっている。
【0009】
このうち一方の継手パイプ14は、次に建て込む鋼管矢板と連結するもの、他方の継手パイプ16は、前に建て込んだ鋼管矢板と連結するもので、各スリット14a,16aは、本体12を中心としてその対角線位置に形成されている。
【0010】
そして、一方の継手パイプ14の底部開口は底蓋18の溶接によって閉塞されている。これに対し他方の継手パイプ16の先端は、底蓋18の厚みd分だけ短く形成されている。
【0011】
また、一方の継手パイプ14の内部には閉塞部材としての小径パイプ20が挿通され、スリット14aの開口位置に仮止用の溶接22によって固定され、これによってスリット14aを閉塞している。仮止溶接22の位置は、長さ方向に沿って適宜間隔となっており、本体12の地中貫入時の圧力に対しては十分な固定力を持っているが、クレーンなど重機による外部からの引抜き力によって簡単に破断されることで、小径パイプ20の抜取りを可能ととしている。
【0012】
これに加え、例えば、継手パイプ14の上部及び小径パイプ20の上部にはピン挿通孔14b,20aが貫通し、この挿通孔14b,20aに共上がり防止用のストッパピン24を挿通することで、小径パイプ20を建て込み圧力に抗してスリット位置に確実に固定し、前記各溶接22の位置に破断応力が直接かからないようにしている。
【0013】
次に以上の構成の鋼管矢板10の止水方法について説明する。
【0014】
先ず、通常の鋼管矢板の建て込み方法と同様に地中に建て込んだ状態では、一方の継手パイプ14のスリット14aは、小径パイプ20によって閉塞された状態であるから、止水性はほぼ保たれ、内部に土砂が侵入することはない。この状態で図3(a)に示すように、小径パイプ20と継手パイプ14との隙間にセメント系材料からなる遅延性固化材26を充填する。この固化材26の固化時間は各鋼管矢板10の建て継ぎサイクルを考慮した設定となっている。
【0015】
次いで、ストッパピン24を引抜き、クレーンなどを用いて小径パイプ20を引抜きつつ同遅延性固化材26の充填作業を継続する。
【0016】
引抜き時においては、小径パイプ20の挿通孔20aはクレーンのフックブロックに引っかけるためのシャックルなど連結金具の取付孔を兼用する。以上のごとく小径パイプ20は無理抜きすることで各溶接22を破断しながら継手パイプ14より引抜かれる。
【0017】
小径パイプ20の上昇に応じて遅延性固化材26はパイプ後の空隙内に回り込み、地下水圧に対抗するため、この状態においても継手パイプ14の内部の止水性は確保され、最終的には図3(b)に示すように、継手パイプ14の内部にはその鉛直方向全体に亘って固化材26が充填されることになる。
【0018】
そして、固化材26の固化が始る前までに、図3(c)に示すように、次の鋼管継手10における他方側継手パイプ16を前打設の鋼管継手10における一方側継手パイプ14に鈎形係合しつつ建て込むことで、他方の継手パイプ16は、固化材26を押しのけながら一方の継手パイプ14内に貫入される。
【0019】
経時後は固化材26は固化するため、継手部分における止水性が確保されることになる。
【0020】
【発明の効果】
以上の説明により明らかなように、本発明による鋼管矢板における継手部の止水方法にあっては、従来の止水方法に比べて洗浄の必要がなく、しかも、パイプ内部に充填材を確実に充填することで、十分な止水性を確保できる。また、薬液注入などの補助工法が不要であるため、工費を削減できる。
【図面の簡単な説明】
【図1】本発明方法に用いられる鋼管矢板の平面図である。
【図2】同鋼管矢板の分解斜視図である。
【図3】(a)〜(c)は同鋼管矢板を用いた止水手順及び建て継ぎ手順を示す平面図である。
【図4】従来の鋼管矢板の建て継ぎ構造を示す平面図である。
【符号の説明】
10 鋼管矢板
12 矢板本体
14 一方の継手パイプ
16 他方の継手パイプ
14a,16a スリット
18 底蓋
20 閉塞部材(小径パイプ)
22 仮止用溶接
24 ピン
26 遅延性固化材
[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an improvement in a water stopping method for a joint portion in a steel pipe sheet pile.
[0002]
[Prior art]
The water stop construction method using steel pipe sheet piles stops water by placing adjacent sheet piles sequentially on both sides of the steel pipe sheet piles via joints integrated along the longitudinal direction thereof. It is a construction method. As shown in FIG. 4, the joint part used for this consists of a joint pipe 2 welded in parallel to both sides of the sheet pile main body 1 and formed with an elongated slit 2a along the longitudinal direction. The joint pipes 2 are engaged with each other in a hook shape in cross section, thereby connecting the sheet piles.
[0003]
In order to ensure the water stoppage of the joint part in this case, conventionally, after the sheet pile is built, the earth and sand clogged in the joint pipe 2 is washed and removed, and then formed into the joint pipe 2 in the engaged state. Insert the elongated bag made of non-woven fabric, etc., into the gap by selecting the large gap part of the gaps a, b, and c, and then filling the bag with mortar, so that the bag adheres inside the pipe The water was stopped.
[0004]
[Problems to be solved by the invention]
However, this water stopping method is troublesome because the internal cleaning is performed before the filling operation. In addition, when the gap between the joints cannot be secured due to the vertical accuracy of the sheet piles, the inside of the joints cannot be cleaned, the efficiency of the air lift at a deep position is reduced, or the bag cannot be cleaned sufficiently, or the bag Due to the limited insertion depth of the mortar, the mortar was not sufficiently filled. For example, in the case shown in the figure, even if it is assumed that the gap “a” is the largest in terms of visual appearance, the lower part may become gradually narrower, so the above-described problems are likely to occur. Therefore, in preparation for such a case, it is essential to ensure water-stopping by injecting a chemical into the ground on the back of the sheet pile, and the problem of incurring cost increases due to the addition of this type of auxiliary method was there.
[0005]
The present invention solves the above problems, and its purpose is to eliminate the need for cleaning for water stopping, and to ensure sufficient water stopping by filling the pipe with a solidified material. The present invention provides a water stopping method for a joint portion of a steel pipe sheet pile that can be secured.
[0006]
[Means for Solving the Problems]
In order to achieve the above object, the method of the present invention closes the bottom surface of the joint pipe connected to the steel pipe sheet pile to be built next and is formed in the vertical direction of the joint pipe among the joint pipes provided on both sides of the main body of the steel pipe sheet pile. A member that closes the slit formed is detachably arranged in the joint pipe, and after the steel pipe sheet pile is built, the joint pipe is filled with a delayed solidifying material, and then the closure member is pulled out while the closure member is pulled out. It is characterized by additionally filling a delayed solidifying material in an amount corresponding to the volume of. Therefore, according to the method of the present invention, the solidified material is reliably filled into the joint by only the delayed solidifying material filling operation and the closing member pulling operation as the work for ensuring the water stop after the placing. In addition, when the next steel pipe sheet pile is to be joined, the solidified material is not solidified, so it can be joined while it is penetrating into a fitting pipe that has been filled, and eventually the solidified material will solidify. Thus, the water stoppage of the joint portion is ensured.
[0007]
In this invention, it is simple and preferable that the closing member is a steel pipe. In addition, by providing the head for the closing member so as to be detachable, it is possible to reliably prevent the closing member from being displaced from the mounting position due to the penetration pressure when the sheet pile is driven.
[0008]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. 1 and 2 show a steel pipe sheet pile 10 to which the method of the present invention is applied. The sheet pile 10 includes a sheet pile main body 12 and left and right joint pipes 14 and 16 which are integrated on both sides of the main body 12 by welding or the like along the longitudinal direction thereof.
[0009]
One of the joint pipes 14 is connected to a steel pipe sheet pile to be built next, and the other joint pipe 16 is connected to a steel pipe sheet pile previously built. Each slit 14a, 16a It is formed at the diagonal position as the center.
[0010]
The bottom opening of one joint pipe 14 is closed by welding the bottom lid 18. On the other hand, the tip of the other joint pipe 16 is formed shorter by the thickness d of the bottom lid 18.
[0011]
A small-diameter pipe 20 as a closing member is inserted into one of the joint pipes 14, and is fixed to the opening position of the slit 14a by a temporary welding 22 to thereby close the slit 14a. The positions of the temporary welding 22 are appropriately spaced along the length direction, and have a sufficient fixing force against the pressure when the main body 12 penetrates into the ground. The small diameter pipe 20 can be pulled out by being easily broken by the pulling force.
[0012]
In addition to this, for example, pin insertion holes 14b and 20a pass through the upper part of the joint pipe 14 and the upper part of the small-diameter pipe 20, and a stopper pin 24 for preventing the joint from rising is inserted into the insertion holes 14b and 20a. The small-diameter pipe 20 is securely fixed at the slit position against the built-in pressure so that the breaking stress is not directly applied to the position of each weld 22.
[0013]
Next, the water stop method of the steel pipe sheet pile 10 of the above structure is demonstrated.
[0014]
First, in a state where the steel pipe sheet pile is built in the same manner as in a normal steel pipe sheet pile method, the slit 14a of one joint pipe 14 is closed by the small-diameter pipe 20, so that the water-stopping property is substantially maintained. , Earth and sand will not invade inside. In this state, as shown in FIG. 3A, the space between the small-diameter pipe 20 and the joint pipe 14 is filled with a delayed solidifying material 26 made of a cement-based material. The solidification time of the solidified material 26 is set in consideration of the continuation cycle of each steel pipe sheet pile 10.
[0015]
Next, the stopper pin 24 is pulled out, and the filling operation of the delayed solidifying material 26 is continued while pulling out the small-diameter pipe 20 using a crane or the like.
[0016]
At the time of drawing, the insertion hole 20a of the small-diameter pipe 20 also serves as a mounting hole for a connection fitting such as a shackle for hooking on a hook block of a crane. As described above, the small-diameter pipe 20 is pulled out from the joint pipe 14 while breaking the welds 22 by forcibly pulling out.
[0017]
As the small-diameter pipe 20 rises, the delayed solidification material 26 wraps around the gap after the pipe and counters the groundwater pressure, so that even in this state, the water stoppage inside the joint pipe 14 is ensured. As shown in FIG. 3B, the joint pipe 14 is filled with the solidified material 26 over the entire vertical direction.
[0018]
Then, before the solidification material 26 starts to solidify, the other side joint pipe 16 in the next steel pipe joint 10 is changed to the one side joint pipe 14 in the previously placed steel pipe joint 10 as shown in FIG. The other joint pipe 16 is inserted into the one joint pipe 14 while pushing the solidified material 26 by being built with the hook-shaped engagement.
[0019]
Since the solidified material 26 is solidified after a lapse of time, the water stoppage at the joint portion is ensured.
[0020]
【The invention's effect】
As is clear from the above explanation, the water stop method for the joint portion of the steel pipe sheet pile according to the present invention does not require cleaning as compared with the conventional water stop method, and moreover, the filler is reliably put inside the pipe. By filling, sufficient water stoppage can be secured. Moreover, since an auxiliary construction method such as chemical injection is unnecessary, the construction cost can be reduced.
[Brief description of the drawings]
FIG. 1 is a plan view of a steel pipe sheet pile used in the method of the present invention.
FIG. 2 is an exploded perspective view of the steel pipe sheet pile.
FIGS. 3A to 3C are plan views showing a water stopping procedure and a continuation procedure using the steel pipe sheet pile. FIG.
FIG. 4 is a plan view showing a conventional joint structure of steel pipe sheet piles.
[Explanation of symbols]
DESCRIPTION OF SYMBOLS 10 Steel pipe sheet pile 12 Sheet pile main body 14 One joint pipe 16 The other joint pipe 14a, 16a Slit 18 Bottom cover 20 Closure member (small diameter pipe)
22 Temporary welding 24 Pin 26 Delayed solidification material

Claims (3)

鋼管矢板の本体両側に設けた継手パイプのうち、次に建て込む鋼管矢板と連結する継手部パイプの底面を閉塞し、かつ継手パイプの鉛直方向に形成されたスリットを閉塞する部材を継手パイプ内に取外し可能に配置し、
鋼管矢板の建て込み後、前記継手部パイプ内に遅延性固化材を充填し、
しかる後、閉塞部材を引抜きつつ、閉塞部材の容積分に相当する量の遅延性固化材を追加充填することを特徴とする鋼管矢板における継手部の止水方法。
Of the joint pipes provided on both sides of the main body of the steel pipe sheet pile, a member that closes the bottom surface of the joint pipe connected to the steel pipe sheet pile to be built next and closes the slit formed in the vertical direction of the joint pipe is provided in the joint pipe. Placed in a removable manner,
After erection of the steel pipe sheet pile, the joint pipe is filled with a delayed solidification material,
After that, the water-stopping method for the joint portion in the steel pipe sheet pile is characterized by additionally filling the delayed solidifying material in an amount corresponding to the volume of the closing member while pulling out the closing member.
前記閉塞部材が鋼管であることを特徴とする請求項1に記載の鋼管矢板における継手部の止水方法。The said blocking member is a steel pipe, The water stop method of the joint part in the steel pipe sheet pile of Claim 1 characterized by the above-mentioned. 前記閉塞部材の頭部に共上がり防止用金具を取外し可能に設けたことを特徴とする請求項1に記載の鋼管矢板における継手部の止水方法。The method for water-stopping a joint portion in a steel pipe sheet pile according to claim 1, wherein a joint-preventing metal fitting is detachably provided on the head of the closing member.
JP2000178096A 2000-06-14 2000-06-14 Water stop method for joints in steel pipe sheet piles Expired - Fee Related JP3729028B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2000178096A JP3729028B2 (en) 2000-06-14 2000-06-14 Water stop method for joints in steel pipe sheet piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2000178096A JP3729028B2 (en) 2000-06-14 2000-06-14 Water stop method for joints in steel pipe sheet piles

Publications (2)

Publication Number Publication Date
JP2001355232A JP2001355232A (en) 2001-12-26
JP3729028B2 true JP3729028B2 (en) 2005-12-21

Family

ID=18679583

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2000178096A Expired - Fee Related JP3729028B2 (en) 2000-06-14 2000-06-14 Water stop method for joints in steel pipe sheet piles

Country Status (1)

Country Link
JP (1) JP3729028B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5367537B2 (en) * 2009-10-30 2013-12-11 鹿島建設株式会社 Construction method and structure of steel pipe sheet pile
JP5966162B2 (en) * 2012-04-25 2016-08-10 西武ポリマ化成株式会社 Steel pipe sheet pile watertight joint structure
CN112211209A (en) * 2020-09-24 2021-01-12 中铁大桥局集团第一工程有限公司 Water stopping method for locking notch of steel pipe pile

Also Published As

Publication number Publication date
JP2001355232A (en) 2001-12-26

Similar Documents

Publication Publication Date Title
CN109937282A (en) Reinforced concrete frame antidetonation is reinforced using PC wallboard, reinforced concrete frame antidetonation reinforcement structure and its construction method using PC wallboard
JP3729028B2 (en) Water stop method for joints in steel pipe sheet piles
KR101381782B1 (en) Reinforcing structure and construction method for greening vegetation articles
JP3733772B2 (en) Joint structure of cast-in-place steel pipe concrete pile and SRC column and its joining method
RU2262572C2 (en) Method for permanent sheet pile connection
JP3774886B2 (en) Anchor construction method
JP4045563B2 (en) Joint of continuous sheet pile wall
JP2979115B2 (en) Construction method of cast-in-place concrete pile
JP3022736B2 (en) Bag and method of filling gap between ridge and wall using this bag
JP2000220140A (en) Cast-in-place steel pipe concrete pile and its erecting method
JP3755641B2 (en) Steel pipe sheet pile wall construction method
JP3468749B2 (en) Construction method of parent pile horizontal sheet pile
JP2690361B2 (en) Pile construction method
JP3851695B2 (en) Reinforcement method for existing structure and fixing material leakage prevention jig used in the method
JP3615083B2 (en) Steel pipe pile head connection method
JP3470954B2 (en) Method of laying interruption of manhole to existing buried pipe
JP2004316207A (en) Structure for connecting earth retaining wall with floor slab, and construction method therefor
JPS6039812B2 (en) Steel sheet pile construction method
JP2001146745A (en) Method and device for pulling out pile
JP2876041B2 (en) Asphalt injection into caisson joints.
JPH042134B2 (en)
JP3076720B2 (en) Underground diaphragm wall
JPH08253927A (en) Joint structure in underground continuous wall
JPS59130919A (en) Removal of existing hollow pile
JP3808546B2 (en) Pile spacer

Legal Events

Date Code Title Description
RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20040924

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20050909

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20050913

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20050926

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091014

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101014

Year of fee payment: 5

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101014

Year of fee payment: 5

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111014

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121014

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131014

Year of fee payment: 8

LAPS Cancellation because of no payment of annual fees