JP2000220140A - Cast-in-place steel pipe concrete pile and its erecting method - Google Patents

Cast-in-place steel pipe concrete pile and its erecting method

Info

Publication number
JP2000220140A
JP2000220140A JP11024774A JP2477499A JP2000220140A JP 2000220140 A JP2000220140 A JP 2000220140A JP 11024774 A JP11024774 A JP 11024774A JP 2477499 A JP2477499 A JP 2477499A JP 2000220140 A JP2000220140 A JP 2000220140A
Authority
JP
Japan
Prior art keywords
steel pipe
concrete
cast
place
opening
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP11024774A
Other languages
Japanese (ja)
Inventor
Yasuhisa Imamoto
泰久 今本
Shigeki Ito
茂樹 伊藤
Kazuchika Konno
和近 今野
Kimihisa Takano
公寿 高野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JFE Engineering Corp
Original Assignee
NKK Corp
Nippon Kokan Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NKK Corp, Nippon Kokan Ltd filed Critical NKK Corp
Priority to JP11024774A priority Critical patent/JP2000220140A/en
Publication of JP2000220140A publication Critical patent/JP2000220140A/en
Pending legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

PROBLEM TO BE SOLVED: To easily connect a cage and a steel pipe and contrive the reduction of labors and costs and the reduction of a construction period by inserting steel pipe connected to the cages in a shaft, and providing an opening and closing means for opening and closing an edge opening part. SOLUTION: A cover plate 8 is provided on an opening part 7a to be welded on a bottom plate 6 by a connection member on the outer periphery, and the vertical bar 4a of a cage 4 and the connection member of a steel pipe 5 are overlapped to be tied by a wire or the like. During execution, an integrated vertical bar 4a and the connection member is inserted in a shaft 2, and a tremie pipe is inserted in the cage 4 from the opening part 7a of the cover plate 8 of the bottom plate 6 of the steel pipe 5. Next, the level of cast-in-place concrete 22 is charged down to the neighborhood of the bottom plate 6 in the shaft 2 to pull out the tremie pipe so as to block the opening part 7a by the cover plate 8, and a casing 20 is pulled out from the upper part of the shaft 2. A column material 40 is set up in the steel pipe 5, filling concrete 23 is charged in the steel pipe 5, and an outer periphery is filled with concrete 24 to complete steel pipe pile 1. Thereby a time and a cost can be reduced.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、鉄筋篭とこれに連
結された鋼管とを坑内に挿入し、この坑内にコンクリー
トを充填して造成する場所打ち鋼管コンクリート杭及び
その施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a cast-in-place steel pipe concrete pile in which a steel cage and a steel pipe connected to the steel cage are inserted into a pit, and concrete is filled into the pit to form the pile. .

【0002】[0002]

【従来の技術】地震時におけるせん断抵抗性や曲げ抵抗
性が鉄筋コンクリート杭より優れた場所打ち鋼管コンク
リート杭において、鉄筋とこれに連結した鋼管とを坑内
に挿入して場所打ちコンクリートが充填された鋼管内
に、上部構造物である鋼管柱、鉄骨柱などの柱材を建込
み、その後コンクリートを充填して場所打ち鋼管コンク
リート杭と柱材とを一体化して、耐震性をより高めた基
礎構造物とする工法が最近注目されている。
2. Description of the Related Art Cast-in-place steel pipe concrete piles, which have better shear resistance and bending resistance during an earthquake than reinforced concrete piles, have a steel pipe filled with cast-in-place concrete by inserting a steel bar and a steel pipe connected to the steel pipe. Within the building, a pillar structure such as a steel pipe column or a steel frame column, which is the upper structure, is built, and then concrete is filled, and the cast-in-place steel pipe concrete pile and the column material are integrated to improve the seismic resistance. Has recently attracted attention.

【0003】図16は従来の場所打ち鋼管コンクリート
杭の一例の説明図である。図において、42は地中に掘
削した坑(穴)、44は鉄筋を結束してなる鉄筋篭、4
5は鋼管で、その下部には鉄筋篭44の複数の鉄筋が溶
接により連結されて一体化されている。このような一体
化された鉄筋篭44と鋼管45は、坑42内に挿入され
てトレミー管などによりコンクリート47を投入して構
成された場所打ちコンクリート杭43と、内外にコンク
リート47が充填された鋼管45とにより場所打ち鋼管
コンクリート杭41が造成される。
FIG. 16 is an explanatory view of one example of a conventional cast-in-place steel pipe concrete pile. In the figure, 42 is a pit (hole) excavated in the ground, 44 is a reinforced cage formed by binding rebars,
Reference numeral 5 denotes a steel pipe, and a plurality of rebars of a rebar cage 44 are integrally connected to each other by welding at a lower portion thereof. The integrated reinforced cage 44 and the steel pipe 45 were inserted into the pit 42 and cast in place with concrete 47 by a tremy tube or the like, and the concrete 47 was filled inside and outside. The cast-in-place steel pipe concrete pile 41 is formed by the steel pipe 45.

【0004】[0004]

【発明が解決しようとする課題】上記のような従来の場
所打ち鋼管コンクリート杭41においては、コンクリー
ト47を充填したのち、鋼管45の上部及びその近傍に
は、泥水あるいはコンクリート47と泥水が混り合った
スライムなど、コンクリートにとって好ましくない不純
物が含まれた品質の悪いコンクリート(以下、不良コン
クリートという)48が存在する。
In the above-mentioned conventional cast-in-place steel pipe concrete pile 41, after the concrete 47 is filled, muddy water or concrete 47 and muddy water are mixed in the upper part of the steel pipe 45 and in the vicinity thereof. There is poor quality concrete (hereinafter referred to as bad concrete) 48 containing impurities that are not desirable for concrete such as combined slime.

【0005】そのため、コンクリート47の固化後に、
鋼管45の上部の深さ1m程度のコンクリートを除去し
ていた。この作業を一般に杭頭処理と呼んでいる。この
ような杭頭処理は非常に大きな労力と時間を必要とする
ばかりでなく、コンクリートを除去する際に、鋼管45
を損傷したり、鋼管45の内面に付着したコンクリート
の除去が不完全のために、柱材を建込んだのちに充填す
るコンクリートと、鋼管45の内面との付着性が悪いな
どの問題があった。
Therefore, after the concrete 47 is solidified,
The concrete having a depth of about 1 m above the steel pipe 45 was removed. This operation is generally called pile head processing. Such a pile head treatment requires not only a very large amount of labor and time, but also a steel pipe 45 when removing concrete.
There is a problem such as damage to the concrete or poor adhesion of the concrete adhering to the inner surface of the steel pipe 45 with the concrete to be filled after the column material is built due to incomplete removal of the concrete adhering to the inner surface of the steel pipe 45. Was.

【0006】また、鉄筋篭44の鉄筋を鋼管45に溶接
により接合しているが、このような溶接作業は工事現場
で行うために、工事現場に溶接装置を搬入しなければな
らなず、また溶接に多くの時間を要していた。このよう
に、従来の場所打ち鋼管コンクリート杭41は、造成に
あたって多くの労力と費用を要し、その上工期の長期化
は避けられなかった。
Further, the reinforcing bars of the reinforcing bar cage 44 are joined to the steel pipes 45 by welding. In order to perform such welding work at the construction site, a welding device must be carried into the construction site. It took a lot of time for welding. As described above, the conventional cast-in-place steel pipe concrete pile 41 requires a great deal of labor and cost for the construction, and the prolonged construction period is inevitable.

【0007】本発明は、上記の課題を解決するためにな
されたもので、杭頭処理を省略し、簡単な手段により鉄
筋篭と鋼管を連結することにより、労力と費用の軽減及
び工期の短縮をはかることのできる信頼性の高い場所打
ち鋼管コンクリート杭及びその施工方法を得ることを目
的としたものである。
SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned problems, and eliminates the processing of pile heads and connects a steel cage and a steel pipe by simple means, thereby reducing labor and cost and shortening the construction period. It is an object of the present invention to obtain a highly reliable cast-in-place steel pipe concrete pile that can be measured and a method of constructing the same.

【0008】[0008]

【課題を解決するための手段】(1)本発明に係る場所
打ち鋼管コンクリート杭は、鉄筋篭とこの鉄筋篭に連結
された鋼管とを坑内に挿入し、杭内にコンクリートを充
填して造成するにあたり、鋼管の先端部に、先端開口部
を開閉する開閉手段を設けたものである。
(1) A cast-in-place steel pipe concrete pile according to the present invention is constructed by inserting a steel cage and a steel pipe connected to the steel cage into a pit, and filling the pile with concrete. In doing so, an opening and closing means for opening and closing the tip opening is provided at the tip of the steel pipe.

【0009】(2)上記(1)の鋼管の先端部を漏斗状
に形成した。 (3)また、上記(1)又は(2)の鋼管の内壁の管軸
方向の全部又は一部にプレキャストコンクリートを設け
た。
(2) The tip of the steel pipe of (1) was formed in a funnel shape. (3) Precast concrete was provided on all or a part of the inner wall of the steel pipe of the above (1) or (2) in the pipe axis direction.

【0010】(4)また、本発明に係る場所打ち鋼管コ
ンクリート杭において、鉄筋篭とこの鉄筋篭に連結され
た鋼管とを坑内に挿入し、坑内にコンクリートを充填す
るにあたり、鋼管に、内壁の管軸方向の全部又は一部に
プレキャストコンクリートが設けられたプレキャストコ
ンクリート鋼管を用いたものである。
(4) In the cast-in-place steel pipe concrete pile according to the present invention, the steel pipe and the steel pipe connected to the steel cage are inserted into the pit, and when the pit is filled with concrete, the steel pipe has an inner wall. A precast concrete steel pipe in which precast concrete is provided in all or a part of the pipe axis direction is used.

【0011】(5)上記1〜4の何れかの鋼管又はプレ
キャストコンクリートの先端部に、鉄筋篭と固縛等によ
り連結する複数の連結部材を設けた。
(5) A plurality of connecting members are provided at the tip of the steel pipe or the precast concrete according to any one of the above-mentioned items 1 to 4, which are connected to the reinforcing bar by securing or the like.

【0012】(6)また、本発明に係る場所打ち鋼管コ
ンクリート杭の施工方法は、現場において鉄筋篭と鋼管
に設けた連結部材とを固縛等により連結して一体化する
工程と、この一体化された鉄筋篭と鋼管を坑内に挿入す
る工程と、鋼管の先端開口部から鉄筋篭内にトレミー管
を挿入する工程と、トレミー管を徐々に引上げながら坑
内にコンクリートを投入する工程と、坑内に充填された
コンクリートのレベルが鋼管の先端部近傍に達したとき
はコンクリートの投入を中止してトレミー管を引上げる
と共に、鋼管の先端部に設けた開閉手段により先端開口
部を閉じる工程と、鋼管内及び鋼管の外周にコンクリー
トを充填する工程とを備えたものである。
(6) In the method for constructing a cast-in-place steel pipe concrete pile according to the present invention, a step of connecting a reinforcing member and a connecting member provided on a steel pipe at a site by securing them or the like, and integrating the steps. Inserting the reinforced cage and the steel pipe into the pit, inserting the tremy pipe into the reinforced basket from the tip opening of the steel pipe, introducing concrete into the pit while gradually pulling up the tremy pipe, When the level of the concrete filled in reaches the vicinity of the tip of the steel pipe, stop charging the concrete and pull up the tremie pipe, and closing the tip opening by opening and closing means provided at the tip of the steel pipe, Filling concrete inside the steel pipe and the outer periphery of the steel pipe.

【0013】(7)上記(6)の鋼管に、内壁の管軸方
向の全部又は一部にプレキャストコンクリートが設けら
れたプレキャストコンクリート鋼管を使用した。
(7) As the steel pipe of (6), a precast concrete steel pipe in which precast concrete is provided on all or a part of the inner wall in the pipe axis direction is used.

【0014】[0014]

【発明の実施の形態】[実施の形態1]図1は本発明の
実施の形態1に係る場所打ち鋼管コンクリート杭の説明
図である。図において、1は地中に造成した場所打ち鋼
管コンクリート杭で、4は縦筋4aと帯筋4bを組込ん
でなる鉄筋篭、5は鋼管である。
[First Embodiment] FIG. 1 is an explanatory diagram of a cast-in-place steel pipe concrete pile according to a first embodiment of the present invention. In the figure, reference numeral 1 denotes a cast-in-place steel pipe concrete pile formed in the ground, reference numeral 4 denotes a steel cage incorporating a vertical bar 4a and a band bar 4b, and reference numeral 5 denotes a steel pipe.

【0015】この鋼管5は、図2に示すように、先端開
口部7には中心部に開口部7aを有する底板6が溶接に
より接合されており、この開口部7aにはヒンジを介し
て開閉手段である蓋板8が開閉可能に設けられている。
9は開口部7aの外周に、例えば鉄筋からなり、底板6
を貫通して下方に突出する複数本(図には2本だけ示し
てある)の連結部材で、溶接により底板6に固定されて
いる。そして、鉄筋篭4の縦筋4aと、鋼管5に設けた
連結部材9とをそれぞれ重ね合わせて針金など9aによ
り固縛し、鉄筋篭4と鋼管5が一体化される。なお、2
0は坑2の上部に設けたケーシングである。
As shown in FIG. 2, the steel pipe 5 has a bottom plate 6 having a central opening 7a joined to the distal end opening 7 by welding. The opening 7a is opened and closed via a hinge. A cover plate 8 as a means is provided so as to be openable and closable.
Reference numeral 9 denotes an outer periphery of the opening 7a, which is made of, for example, a reinforcing bar.
And a plurality of (only two are shown in the figure) connecting members protruding downward and fixed to the bottom plate 6 by welding. Then, the vertical bar 4a of the reinforcing bar 4 and the connecting member 9 provided on the steel pipe 5 are overlapped with each other and fastened by a wire 9a, so that the reinforcing bar 4 and the steel pipe 5 are integrated. In addition, 2
Reference numeral 0 denotes a casing provided at the upper part of the pit 2.

【0016】次に、図3、図4により上記のように構成
した本実施の形態の施工方法の一例について説明する。 (1)先ず、鉄筋篭4の縦筋4aと鋼管5の連結部材9
aを工事現場で針金等で固縛して一体化し、これを図3
(a)に示すように、坑2内に挿入する。 (2)図3(b)に示すように、鋼管5の底板6に設け
た蓋板8を開放し、開口部7aから鉄筋篭4内にその先
端部が坑2の底部近傍に達するまでトレミー管21を挿
入し、坑2内に場所打ちコンクリート22を投入しなが
ら徐々に引上げる。
Next, an example of the construction method of the present embodiment configured as described above will be described with reference to FIGS. (1) First, the connecting member 9 between the vertical bar 4a of the reinforcing bar 4 and the steel pipe 5
a is tied up with a wire or the like at the construction site and integrated.
As shown in FIG. (2) As shown in FIG. 3 (b), the cover plate 8 provided on the bottom plate 6 of the steel pipe 5 is opened, and the tremee is inserted into the reinforcing bar 4 from the opening 7a until the tip thereof reaches the vicinity of the bottom of the pit 2. The pipe 21 is inserted, and the cast-in-place concrete 22 is put into the pit 2 and gradually pulled up.

【0017】(3)坑2内に場所打ちコンクリート22
が充填されてそのレベルが鋼管5の底板6の近傍に達し
たときは、場所打ちコンクリート22の投入を中止し、
図3(c)に示すように、トレミー管21を引抜くと共
に、蓋板8により底板6の開口部7aを閉塞する。これ
により場所打ちコンクリート22は、鉄筋篭4が配設さ
れた鋼管5の下方の坑2内に充填されて場所打ちコンク
リート杭3が構成され、スライムなどを含む不良コンク
リートの大部分は、鋼管5の外周に回り込み、鋼管5内
には侵入しない。
(3) Cast-in-place concrete 22 in the pit 2
When the level reaches the vicinity of the bottom plate 6 of the steel pipe 5, the casting of the cast-in-place concrete 22 is stopped,
As shown in FIG. 3C, the tremy tube 21 is pulled out, and the opening 7 a of the bottom plate 6 is closed by the cover plate 8. As a result, the cast-in-place concrete 22 is filled into the pit 2 below the steel pipe 5 in which the reinforcing steel cage 4 is disposed to form the cast-in-place concrete pile 3, and most of the defective concrete including slime and the like is removed from the steel pipe 5. And does not enter the steel pipe 5.

【0018】(4)ついで、図4(a)に示すように、
坑2からケーシング20を引抜き、鋼管5内に柱材40
を建込んで鋼管5内に充填コンクリート23を充填す
る。なお、鋼管5内に充填コンクリート23を充填し、
これが固化する前に柱材40を建込んでもよい。
(4) Next, as shown in FIG.
The casing 20 is pulled out from the pit 2 and the column member 40 is placed in the steel pipe 5.
And the filling concrete 23 is filled in the steel pipe 5. In addition, the filling concrete 23 is filled in the steel pipe 5,
The column member 40 may be built before this solidifies.

【0019】(5)そして、鋼管5内の充填コンクリー
ト23がある程度固化したのち、図4(b)に示すよう
に、鋼管5の外周にコンクリート24を充填すれば、場
所打ち鋼管コンクリート杭1が完成する。なお、先に鋼
管5の外周にコンクリート24を充填したのち、鋼管5
内に充填コンクリート23を充填してもよいが、こうす
ると鋼管5が浮上るおそれがあるので、先に鋼管5内に
充填コンクリート23を充填することが望ましい。
(5) After the filled concrete 23 in the steel pipe 5 is solidified to some extent, as shown in FIG. 4 (b), when the outer periphery of the steel pipe 5 is filled with concrete 24, the cast-in-place steel pipe concrete pile 1 becomes Complete. After the concrete 24 is first filled in the outer periphery of the steel pipe 5, the steel pipe 5
The concrete 23 may be filled therein, but since the steel pipe 5 may float up in this case, it is desirable to fill the steel pipe 5 with the concrete 23 first.

【0020】上記のように構成した本実施の形態によれ
ば、鋼管5内に不良コンクリートが侵入することがない
ので杭頭処理を省略することができ、また、鉄筋篭4と
鋼管5との連結は、鉄筋4aと鋼管5に設けた連結部材
9とを、針金など9aで固縛するだけでよいので、労
力、時間及び費用を大幅に低減することができ、その
上、工期を短縮することができる。
According to the present embodiment configured as described above, since the defective concrete does not enter into the steel pipe 5, the pile head treatment can be omitted. Since the connection only needs to secure the reinforcing member 4a and the connecting member 9 provided on the steel pipe 5 with a wire 9a or the like, labor, time and cost can be significantly reduced, and the construction period is shortened. be able to.

【0021】[実施の形態2]本実施の形態は、図5〜
図11により鋼管5、特に、底部の構造及び底部に設け
た開口部の開閉手段の他の例を示すものである。上述し
た実施の形態1においては、鋼管5の先端開口部7を中
心部に開口部7aを有する平板状の底板6で閉塞し、こ
の開口部7aを開閉する蓋板8を設けた場合を示した
が、このように構成すると、スライムなどを含む不良コ
ンクリートの一部が、底板6の下に滞留するおそれがあ
る。
[Embodiment 2] In this embodiment, FIGS.
FIG. 11 shows another example of the structure of the steel pipe 5, in particular, the structure of the bottom and the means for opening and closing the opening provided in the bottom. In the above-described first embodiment, a case is shown in which a front end opening 7 of a steel pipe 5 is closed with a flat bottom plate 6 having an opening 7a at the center, and a lid plate 8 for opening and closing the opening 7a is provided. However, with such a configuration, a part of the defective concrete including the slime may stay under the bottom plate 6.

【0022】そこで、図5(a)に示すように、鋼管5
の先端部を逆截頭円錐状(漏斗状)に形成し、その先端
開口部7を開閉する蓋板8を設けたものである。このよ
うに構成したことにより、不良コンクリートは、図5
(b)に矢印で示すように、鋼管5の下部の傾斜面に沿
ってスムーズに上方に移動して鋼管5の外周に回り込む
ため、底部に滞留するおそれはほとんどない。
Therefore, as shown in FIG.
Is formed in an inverted truncated conical shape (funnel shape), and a lid plate 8 for opening and closing the distal end opening 7 is provided. Due to such a configuration, the defective concrete can be obtained as shown in FIG.
As shown by the arrow in (b), since it smoothly moves upward along the inclined surface of the lower part of the steel pipe 5 and goes around the outer periphery of the steel pipe 5, there is almost no danger of stagnation at the bottom.

【0023】図6(a)は、鋼管5の先端開口部7に開
閉可能に設けた蓋板8と鋼管5との間にばね10を介装
し、蓋板8に常時先端開口部7を閉塞する方向の付勢力
を与えたものである。なお、図6〜図11には、鋼管5
の下部に設けた連結部材9は省略してある。そして、鋼
管5内にトレミー管21を挿入してその先端部が蓋板8
に当って押圧すると、蓋板8は図6(b)に示すよう
に、ばね10の付勢力に抗して矢印方向に回動して先端
開口部7を開放するので、トレミー管21を容易に挿入
することができる。
FIG. 6A shows a state in which a spring 10 is interposed between a steel plate 5 and a cover plate 8 which is openably and closably provided at a distal end opening 7 of a steel pipe 5. A biasing force is applied in the closing direction. 6 to 11 show the steel pipe 5.
The connecting member 9 provided at the lower part is omitted. Then, the tremee pipe 21 is inserted into the steel pipe 5, and the distal end portion thereof is
6B, the lid plate 8 pivots in the direction of the arrow against the urging force of the spring 10 to open the distal end opening 7 as shown in FIG. Can be inserted.

【0024】トレミー管21を引上げると、蓋板8はば
ね10に付勢されて反矢印方向に回動し、先端開口部7
を自動的に閉塞する。本例によれば、簡単な構造で、ト
レミー管21の挿入、引上げに対応して先端開口部7を
自動的に開閉することができる。
When the tremee tube 21 is pulled up, the cover plate 8 is urged by the spring 10 to rotate in the direction opposite to the arrow, and the tip opening 7 is opened.
Automatically closes. According to this example, the distal end opening 7 can be automatically opened and closed in response to insertion and pulling up of the tremy tube 21 with a simple structure.

【0025】図7(a)は、鋼管5の先端開口部7に開
閉可能に設けた蓋板8に、地上で操作できる紐、鎖等1
1を取付けておき、紐等11を緩めると先端開口部7が
開放され、紐等11を引張ると、図7(b)に示すよう
に、先端開口部7を閉塞するようにしたものである。本
例によれば、きわめて簡単な構造で地上から操作するこ
とにより、先端開口部7を開閉することができる。
FIG. 7 (a) shows a string, a chain, etc., which can be operated on the ground, on a cover plate 8 which can be opened and closed at the end opening 7 of the steel pipe 5.
When the string 11 is loosened, the tip opening 7 is opened, and when the string 11 is pulled, the tip opening 7 is closed as shown in FIG. 7B. . According to this example, the tip opening 7 can be opened and closed by operating from the ground with a very simple structure.

【0026】図8は鋼管5の先端開口部7のほぼ2分の
1の範囲に半円状の底板6aを取付けて閉塞して開口部
7bを形成し、その縁部(先端開口部の中心部)に設け
た軸12に、一部がオーバーラップする半円状の蓋板8
aを回動可能に取付け、軸12と蓋板8aとの間にばね
13を介装して蓋板8aに図8(b)に示すような回転
力を与えると共に、図の位置(開口部7bを閉塞する位
置)で保持されるようにしたものである。なお、14は
底板6aに設けた着脱可能のストッパピンで、地上で操
作できる紐、鎖など(図示せず)が取付けられている。
FIG. 8 shows a state in which a semicircular bottom plate 6a is mounted and closed in a region approximately one-half of the distal end opening 7 of the steel pipe 5 to form an opening 7b, and its edge (the center of the distal opening) is formed. Part), a semicircular cover plate 8 partially overlapping with the shaft 12 provided in
a is rotatably mounted, a spring 13 is interposed between the shaft 12 and the cover plate 8a to apply a rotational force to the cover plate 8a as shown in FIG. 7b is closed). Reference numeral 14 denotes a detachable stopper pin provided on the bottom plate 6a, to which a string, a chain, etc. (not shown) which can be operated on the ground is attached.

【0027】上記のように構成した鋼管5は、連結部材
9に鉄筋篭4を連結する前(又は連結後)に、図8
(c)に示すように、蓋板8aをばね13に抗して矢印
方向に回動し、ストッパピン14を装着して蓋板8aを
その位置に保持する。これにより、底板6aと鋼管5の
先端部との間には開口部7bが形成されるので、この開
口部7bからトレミー管21を挿入することができる。
トレミー管21を引上げたときは、地上から紐等を引張
ってストッパピン14を引抜けば、蓋板8aはばね13
に付勢されて回動し、図8(b)の状態に戻って開口部
7bを閉塞する。
The steel pipe 5 constructed as described above is connected to the connecting member 9 before (or after) the reinforcing bar 4 in FIG.
As shown in (c), the cover plate 8a is rotated in the direction of the arrow against the spring 13, and the stopper plate 14 is mounted to hold the cover plate 8a at that position. As a result, an opening 7b is formed between the bottom plate 6a and the tip of the steel pipe 5, so that the tremy tube 21 can be inserted through the opening 7b.
When the tremy tube 21 is pulled up, if a string or the like is pulled from the ground to pull out the stopper pin 14, the lid plate 8a
8B, and returns to the state of FIG. 8B to close the opening 7b.

【0028】図9(a)は鋼管5の先端開口部7にヒン
ジを介して開閉可能に蓋板8を取付けたもので、常時は
自重により垂下しており、先端開口部7からトレミー管
21を容易に挿入することができる。トレミー管21が
徐々に引上げられて場所打ちコンクリートのレベルが上
昇すると、蓋板8はその圧力により先端開口部7を閉塞
する方向に回動する。トレミー管21が引き上げられて
場所打ちコンクリートのレベルが鋼管5の先端部近傍に
達すると、蓋板8は場所打ちコンクリートの圧力により
先端開口部7を閉塞する。本例によれば、きわめて簡単
な構造で先端開口部7を開閉することができる。
FIG. 9 (a) shows a steel pipe 5 in which a lid plate 8 is attached via a hinge so as to be openable and closable via a hinge. The lid plate 8 is normally suspended by its own weight. Can be easily inserted. When the tremy tube 21 is gradually pulled up and the level of the cast-in-place concrete rises, the cover plate 8 rotates in a direction to close the tip opening 7 by the pressure. When the tremy tube 21 is pulled up and the level of the cast-in-place concrete reaches near the tip of the steel pipe 5, the cover plate 8 closes the tip opening 7 by the pressure of the cast-in-place concrete. According to this example, the tip opening 7 can be opened and closed with a very simple structure.

【0029】図10(a)は鋼管5の先端開口部7の近
傍に、ゴム、合成樹脂等からなり、折曲げ、伸縮可能な
蛇腹状の可撓部材16の一端を固定すると共に、他端に
トレミー管21の内径とほぼ等しい外径の円筒17を固
定して伸縮部15を設け、また、先端開口部7にヒンジ
により回動可能に取付けた一対の蓋板8bを設けたもの
である。
FIG. 10 (a) shows one end of a bellows-shaped flexible member 16 made of rubber, synthetic resin, etc., which is made of rubber, synthetic resin, etc., is fixed near the front end opening 7 of the steel pipe 5, and the other end is fixed. A telescoping portion 15 is provided by fixing a cylinder 17 having an outer diameter substantially equal to the inner diameter of the tremee tube 21, and a pair of lid plates 8 b rotatably mounted by hinges on the distal end opening 7. .

【0030】このような鋼管5においては、鋼管5内に
挿入したトレミー管21の先端部を円筒17に嵌合し、
例えば、トレミー管21を若干回動させてフック等(図
示せず)により両者を一体に結合する。そして、トレミ
ー管21を下降させれば、図10(b)に示すように、
可撓部材16が伸張するので、この状態でトレミー管2
1から場所打ちコンクリートを投入する。
In such a steel pipe 5, the tip of the tremee pipe 21 inserted into the steel pipe 5 is fitted to the cylinder 17,
For example, the tremee tube 21 is slightly rotated, and the two are integrally connected by a hook or the like (not shown). Then, if the tremie tube 21 is lowered, as shown in FIG.
Since the flexible member 16 is expanded, the tremee tube 2 is in this state.
Pour cast-in-place concrete from 1.

【0031】トレミー管21を徐々に引上げながら場所
打ちコンクリートを投入すると、場所打ちコンクリート
のレベルが上昇し、伸縮部15が鋼管5内に取込まれる
と共に、蓋板8bが場所打ちコンクリートの圧力により
回動し、先端開口部7を閉塞する(図10(a)に破線
で示す)。ついで、トレミー管21を反対方向に僅かに
回転させてフック等を外し、トレミー管21を引上げ
る。なお、蓋板8bには、図6で説明したようにばねを
設けてもよく、あるいは、蓋板8bを1枚の板で構成し
てもよい。
When the cast-in-place concrete is poured in while gradually pulling up the tremy tube 21, the level of the cast-in-place concrete rises, the expansion and contraction portion 15 is taken into the steel pipe 5, and the cover plate 8b is moved by the pressure of the cast-in-place concrete. It turns to close the distal end opening 7 (shown by a broken line in FIG. 10A). Next, the tremy tube 21 is slightly rotated in the opposite direction to release the hooks and the like, and the tremy tube 21 is pulled up. Note that the cover plate 8b may be provided with a spring as described with reference to FIG. 6, or the cover plate 8b may be formed of a single plate.

【0032】図11(a)は、漏斗状の鋼管5の先端開
口部7に開口部7aを有する底板6を取付けると共に、
この開口部7aに鋼管5内に突出するトレミー管21の
内径とほぼ等しい外径の円筒18を取付けて、円筒18
の内壁に開閉弁19を設けたものである。このような鋼
管5においては、鋼管5内に挿入したトレミー管21の
先端部を円筒18に嵌合する。そして、トレミー管21
から坑2内に場所打ちコンクリートを投入すれば、場所
打ちコンクリートは坑2内に充填されるが、そのレベル
が上昇すると圧力により開閉弁体19が閉塞されるの
で、トレミー管21を引上げても、不良コンクリートの
鋼管5内への侵入を防止することができる。
FIG. 11A shows a state in which a bottom plate 6 having an opening 7a is attached to a tip opening 7 of a funnel-shaped steel pipe 5, and
A cylinder 18 having an outer diameter substantially equal to the inner diameter of the tremy tube 21 protruding into the steel pipe 5 is attached to the opening 7a.
Is provided with an on-off valve 19 on the inner wall of the. In such a steel pipe 5, the tip of the tremee pipe 21 inserted into the steel pipe 5 is fitted to the cylinder 18. And the tremy tube 21
When the cast-in-place concrete is poured into the pit 2, the cast-in-place concrete is filled into the pit 2, but when the level rises, the on-off valve body 19 is closed by pressure. In addition, intrusion of defective concrete into the steel pipe 5 can be prevented.

【0033】図11(b)は、図11(a)の円筒18
の内壁に漏斗状のオリフィス19aを設けて場所打ちコ
ンクリートの逆流を防止すると共に、底板6の開口部7
aに、図10で説明したような一対の蓋板8bを設けた
もので、トレミー管21を引抜くと同時に蓋板8bが場
所打ちコンクリートの圧力により開口部7aを閉塞する
ようにしたものであり、これにより、不良コンクリート
の鋼管5内への侵入を防止したものである。なお、本例
においても、蓋板8bと鋼管5との間にばねを介装して
もよく、あるいは、蓋板2bを1枚の板で構成してもよ
い。
FIG. 11B shows the cylinder 18 shown in FIG.
A funnel-shaped orifice 19a is provided on the inner wall of the bottom plate to prevent the backflow of cast-in-place concrete, and the opening 7
a is provided with a pair of cover plates 8b as described in FIG. 10, and the cover plate 8b closes the opening 7a by the pressure of the cast-in-place concrete at the same time as the tremy tube 21 is pulled out. This prevents the defective concrete from entering the steel pipe 5. Also in this example, a spring may be interposed between the cover plate 8b and the steel pipe 5, or the cover plate 2b may be formed of a single plate.

【0034】以上、鋼管5の各種の実施の形態について
説明したが、本発明はこれに限定するものではなく、ト
レミー管21を挿脱することができ、かつ、不良コンク
リートの鋼管5内への侵入を防止又は抑制しうるもので
あれば、他の手段を用いてもよい。なお、図6〜図11
においては、鋼管5の先端部を漏斗状に形成した場合を
示したが、実施の形態1で説明したように、鋼管5の先
端開口部7を、中心部に開口部を有する平板状の底板6
で閉塞した鋼管5にも本実施の形態を実施することがで
きる。
Although various embodiments of the steel pipe 5 have been described above, the present invention is not limited to this, and the tremy pipe 21 can be inserted and removed, and defective concrete can be inserted into the steel pipe 5. Other means may be used as long as intrusion can be prevented or suppressed. 6 to 11.
Has shown the case where the tip of the steel pipe 5 is formed in a funnel shape, but as described in the first embodiment, the tip opening 7 of the steel pipe 5 is replaced with a flat bottom plate having an opening in the center. 6
This embodiment can be applied to the steel pipe 5 closed by the above.

【0035】[実施の形態3]図12は本実施の形態に
係る鋼管の説明図である。図12(a)において、30
はプレキャストコンクリート鋼管で、鋼管31の内壁面
の管軸方向の全体に、例えば、遠心成型によりプレキャ
ストコンクリート32を設け、中心部に上下に貫通する
中空部34を形成したものである。33はプレキャスト
コンクリート32の下部に埋設され、場所打ちコンクリ
ート杭の鉄筋篭に連結するための鉄筋等からなる複数本
の連結部材である。本例は、主として、鋼管31とプレ
キャストコンクリート32とにより全耐力を負担するタ
イプのもので、下部に造成された場所打ちコンクリート
杭には強度を期待しないため、内部に不良コンクリート
が侵入しても差支えない。
[Embodiment 3] FIG. 12 is an explanatory view of a steel pipe according to the present embodiment. In FIG. 12A, 30
Is a precast concrete steel pipe in which a precast concrete 32 is provided on the entire inner wall surface of the steel pipe 31 in the pipe axis direction, for example, by centrifugal molding, and a hollow part 34 vertically penetrating is formed at the center. Reference numeral 33 denotes a plurality of connecting members buried in the lower part of the precast concrete 32 and formed of reinforcing bars for connecting to a reinforcing bar of a cast-in-place concrete pile. This example is of a type that bears the total strength mainly by the steel pipe 31 and the precast concrete 32. Since the cast-in-place concrete pile formed in the lower part is not expected to have strength, even if defective concrete enters the inside, No problem.

【0036】図12(b)は、図12(a)のプレキャ
ストコンクリート鋼管30の先端部に、中心部に開口部
36を有する底板35を取付けて、この開口部36に開
閉手段である開閉可能の蓋板37を設けたものである。
本例は、主として、鋼管31、プレキャストコンクリー
ト32及びその下部に造成された場所打ちコンクリート
杭により全耐力を負担するタイプで、場所打ちコンクリ
ート杭に打設したコンクリートの不良コンクリートが内
部に侵入しないように蓋板37を設けたものである。
FIG. 12B shows a precast concrete steel pipe 30 shown in FIG. 12A in which a bottom plate 35 having an opening 36 in the center is attached to the front end thereof, and the opening 36 can be opened and closed as opening and closing means. Is provided.
In this example, the steel pipe 31, the precast concrete 32, and the cast-in-place concrete pile formed in the lower part bear the full strength mainly, so that the poor concrete of the concrete cast in the cast-in-place concrete pile does not enter into the inside. Is provided with a lid plate 37.

【0037】図12(c)は、地中のモーメントの大き
い部分、すなわち、鋼管31の先端部から中央部近傍に
かけて内壁にプレキャストコンクリート32aを設けた
ものである。本例は、下部に造成された場所打ちコンク
リート杭と鋼管31との打継ぎ部近傍では、場所打ちコ
ンクリート杭の耐力を考慮せず、鋼管31と場所打ちコ
ンクリート杭のみで耐力を負担するタイプのものであ
る。
FIG. 12 (c) shows a precast concrete 32a provided on the inner wall from the tip of the steel pipe 31 to the vicinity of the center, where the moment underground is large. In this example, in the vicinity of the joint between the cast-in-place concrete pile and the steel pipe 31 formed in the lower part, the strength of the cast-in-place concrete pile is borne only by the steel pipe 31 and the cast-in-place concrete pile without considering the strength of the cast-in-place concrete pile. Things.

【0038】図12(d)は、図12(c)のプレキャ
ストコンクリート鋼管30の先端部に、中心部に開口部
36を有する底板36を取付けて、この開口部36に開
閉可能の蓋板37を設けたものである。本例はすべての
部分に対して鋼管31と場所打ちコンクリートが耐力を
負担するタイプで、不良コンクリートがプレキャストコ
ンクリート鋼管30内に侵入しないように蓋板37を設
けたものである。
FIG. 12D shows a state in which a bottom plate 36 having an opening 36 in the center is attached to the front end of the precast concrete steel pipe 30 shown in FIG. Is provided. In this embodiment, the steel pipe 31 and the cast-in-place concrete bear the proof stress for all parts, and the cover plate 37 is provided so that the defective concrete does not enter the precast concrete steel pipe 30.

【0039】なお、図12(b)及び(d)のように、
プレキャストコンクリート鋼管30の先端部に開口部3
6を有する底板35を取付け、この開口部36を開閉す
る蓋板37を設ける場合は、鋼管31の先端部を漏斗状
に形成してもよく、また、実施の形態2で説明したよう
な蓋板による開口部の各種の開閉手段を実施してもよ
い。
As shown in FIGS. 12B and 12D,
Opening 3 at the end of precast concrete steel pipe 30
In the case where a bottom plate 35 having a base plate 6 is attached and a cover plate 37 for opening and closing the opening 36 is provided, the tip of the steel pipe 31 may be formed in a funnel shape, or the cover as described in the second embodiment. Various opening / closing means for opening the plate may be implemented.

【0040】次に、図13により、図12(a)で説明
したプレキャストコンクリート鋼管30を用いた場所打
ち鋼管コンクリート杭の施工の一例を説明する。 (1)鉄筋篭4とプレキャストコンクリート鋼管30の
連結部材33とを針金等で固縛して両者を一体化し、こ
れを図13(a)に示すように、坑2内に挿入する。 (2)図13(b)に示すように、プレキャストコンク
リート鋼管30の中空部34から鉄筋篭4内に、その先
端部が坑2の底部近傍に達するまでトレミー管21を挿
入し、坑2内に場所打ちコンクリート22を投入しなが
ら徐々に引上げる。
Next, an example of the construction of a cast-in-place steel pipe concrete pile using the precast concrete steel pipe 30 described in FIG. (1) The reinforcing bar 4 and the connecting member 33 of the precast concrete steel pipe 30 are fastened with a wire or the like to integrate them, and this is inserted into the pit 2 as shown in FIG. (2) As shown in FIG. 13 (b), the tremy tube 21 is inserted from the hollow portion 34 of the precast concrete steel tube 30 into the reinforced cage 4 until its tip reaches near the bottom of the pit 2, and The cast-in-place concrete 22 is gradually poured up.

【0041】(3)図13(c)に示すように、場所打
ちコンクリート22が坑2内に充填されてそのレベルが
プレキャストコンクリート鋼管30の下端部近傍に達し
たときは、場所打ちコンクリート22の投入を中止し、
トレミー管21を引抜く。 (4)図13(d)に示すように、ケーシング20を抜
取り、プレキャストコンクリート鋼管30の外周にコン
クリート24を充填すれば、場所打ち鋼管コンクリート
杭1が完成する。
(3) As shown in FIG. 13C, when the cast-in-place concrete 22 is filled into the pit 2 and its level reaches near the lower end of the precast concrete steel pipe 30, the cast-in-place concrete 22 is removed. Stop feeding,
Pull out the tremy tube 21. (4) As shown in FIG. 13 (d), if the casing 20 is removed and the outer periphery of the precast concrete steel pipe 30 is filled with the concrete 24, the cast-in-place steel pipe concrete pile 1 is completed.

【0042】なお、図示してないが、この場所打ち鋼管
コンクリート杭1に上部構造物を接合するにあたって
は、フーチングを介して中空部34内に柱材を建込み、
中空部34内に充填コンクリートを充填して一体に接合
すればよい。上記のように構成した場所打ち鋼管コンク
リート杭1は、全耐力を鋼管31とプレキャストコンク
リート32とによって負担する。
Although not shown, when joining the superstructure to the cast-in-place steel pipe concrete pile 1, a pillar is built in the hollow portion 34 via footing.
What is necessary is just to fill the hollow part 34 with the filling concrete and join it integrally. The cast-in-place steel pipe concrete pile 1 constructed as described above bears the entire proof by the steel pipe 31 and the precast concrete 32.

【0043】図14、図15は、図12(d)で説明し
たプレキャストコンクリート鋼管30を用いた場所打ち
鋼管コンクリート杭の施工の一例を示すものである。 (1)鉄筋篭4とプレキャストコンクリート鋼管30の
連結部材33とを針金等で固縛して両者を一体化し、こ
れを図14(a)に示すように、坑2内に挿入する。 (2)図14(b)に示すように、プレキャストコンク
リート鋼管30の底板35に設けた蓋板37を開放し、
中空部34から鉄筋篭4内に、その先端部が坑2の底部
近傍に達するまでトレミー管21を挿入し、坑2内に場
所打ちコンクリート22を投入しながら徐々に引上げ
る。
FIGS. 14 and 15 show an example of construction of a cast-in-place steel pipe concrete pile using the precast concrete steel pipe 30 described with reference to FIG. (1) The reinforced cage 4 and the connecting member 33 of the precast concrete steel pipe 30 are fastened with a wire or the like to integrate them, and this is inserted into the pit 2 as shown in FIG. (2) As shown in FIG. 14B, the cover plate 37 provided on the bottom plate 35 of the precast concrete steel pipe 30 is opened,
The tremy tube 21 is inserted from the hollow portion 34 into the reinforced cage 4 until the tip thereof reaches near the bottom of the pit 2, and the cast-in-place concrete 22 is poured into the pit 2 and gradually pulled up.

【0044】(3)杭2内に場所打ちコンクリート22
が充填されてそのレベルがプレキャストコンクリート鋼
管30の底板6の近傍に達したときは、場所打ちコンク
リート22の投入を中止し、図14(c)に示すよう
に、トレミー管21を引抜くと共に、蓋板37により底
板35の開口部36を閉塞する。これにより、場所打ち
コンクリート22はプレキャストコンクリート鋼管30
の下方に充填され、スライムなどを含む不良コンクリー
トの大部分は、プレキャストコンクリート鋼管30の外
周に回り込み、内部には侵入しない。
(3) Cast-in-place concrete 22 in pile 2
Is filled and reaches a level near the bottom plate 6 of the precast concrete steel pipe 30, the casting of the cast-in-place concrete 22 is stopped, and as shown in FIG. The opening 36 of the bottom plate 35 is closed by the cover plate 37. As a result, the cast-in-place concrete 22 becomes a precast concrete steel pipe 30.
Most of the defective concrete, including slime and the like, filled below the steel pipe goes around the outer periphery of the precast concrete steel pipe 30 and does not enter the inside.

【0045】(4)ついで、図15(a)に示すよう
に、坑2からケーシング2を引抜き、プレキャストコン
クリート鋼管30の外周にコンクリート24を充填す
る。 (5)そして、コンクリート24が固化したのち、図1
5(b)に示すように、プレキャストコンクリート鋼管
30内に柱材40を建込んで、内部に充填コンクリート
23を充填すれば、場所打ち鋼管コンクリート杭1と柱
材40との接合が完了する。
(4) Next, as shown in FIG. 15A, the casing 2 is pulled out from the pit 2 and concrete 24 is filled around the outer periphery of the precast concrete steel pipe 30. (5) After the concrete 24 has solidified,
As shown in FIG. 5 (b), when the column member 40 is erected in the precast concrete steel pipe 30 and the filled concrete 23 is filled therein, the joining between the cast-in-place steel pipe concrete pile 1 and the column member 40 is completed.

【0046】本例によれば、地中の曲げモーメントの大
きい部分に鋼管31とプレキャストコンクリート32が
配設され、かつ、すべての部分に対して場所打ち鋼管コ
ンクリート杭3が耐力を負担する。
According to the present embodiment, the steel pipe 31 and the precast concrete 32 are disposed in a portion of the ground where the bending moment is large, and the cast-in-place steel pipe concrete pile 3 bears the proof stress in all the portions.

【0047】[0047]

【発明の効果】(1)本発明に係る場所打ち鋼管コンク
リート杭は、鉄筋篭とこの鉄筋篭に連結された鋼管とを
坑内に挿入し、坑内にコンクリートを充填して造成する
にあたり、鋼管の先端部に、先端開口部を開閉する開閉
手段を設けることにより柱材を建込む鋼管内への不良コ
ンクリートの侵入を防止し、杭頭処理を省略するように
したので、労力を低減し作業時間を短縮することがで
き、低コストで信頼性の高い場所打ち鋼管コンクリート
杭を得ることができる。
(1) The cast-in-place steel pipe concrete pile according to the present invention is constructed by inserting a steel cage and a steel pipe connected to the steel cage into the pit, filling the pit with concrete, and forming the steel pipe. The opening and closing means that opens and closes the opening at the tip prevents the intrusion of defective concrete into the steel pipe in which the column is built, and eliminates the pile head treatment, reducing labor and reducing work time. And a highly reliable cast-in-place steel pipe concrete pile at low cost can be obtained.

【0048】(2)上記(1)の鋼管の先端部を漏斗状
に形成したので、下方に充填したコンクリートを傾斜面
に沿って鋼管の外周にスムーズに移動させることがで
き、鋼管の下部に不良コンクリートが滞留するのを防止
することができる。
(2) Since the tip of the steel pipe of the above (1) is formed in a funnel shape, the concrete filled downward can be smoothly moved to the outer periphery of the steel pipe along the inclined surface, and the lower part of the steel pipe can be formed. It is possible to prevent poor concrete from staying.

【0049】(3)上記(1)又は(2)の鋼管の管軸
方向の全部又は一部にプレキャストコンクリートを設
け、地中のモーメントが最大の部分にプレキャストコン
クリートを配設するようにしたので、構造性能の信頼性
を向上させることができる。
(3) Since the precast concrete is provided on all or a part of the steel pipe of the above (1) or (2) in the pipe axis direction, and the precast concrete is disposed on the portion where the moment in the ground is maximum. In addition, the reliability of the structural performance can be improved.

【0050】(4)また、本発明に係る場所打ち鋼管コ
ンクリート杭は、鉄筋篭とこの鉄筋篭に連結された鋼管
とを坑内に挿入し、坑内にコンクリートを充填するにあ
たり、鋼管に、内壁の管軸方向の全部又は一部にプレキ
ャストコンクリートが設けられたプレキャストコンクリ
ート鋼管を用いたので、上記(3)とほぼ同様の効果を
得ることができる。
(4) In the cast-in-place steel pipe concrete pile according to the present invention, a steel pipe and a steel pipe connected to the steel cage are inserted into the pit and concrete is filled into the pit. Since the precast concrete steel pipe in which the precast concrete is provided in all or a part of the pipe axis direction is used, almost the same effect as the above (3) can be obtained.

【0051】(5)上記(1)〜(4)の何れかの鋼管
又はプレキャストコンクリートの先端部に、鉄筋篭と固
縛等により連結する複数の連結部材を設けたので、鉄筋
篭と鋼管との連結をきわめて容易に行うことができる。
(5) Since a plurality of connecting members are provided at the tip of the steel pipe or the precast concrete according to any one of the above (1) to (4), which are connected to the reinforcing steel cage by fastening or the like. Can be connected very easily.

【0052】(6)また、本発明に係る場所打ち鋼管コ
ンクリート杭の施工方法は、現場において鉄筋篭と鋼管
に設けた連結部材とを固縛等により連結して一体化する
工程と、この一体化された鉄筋篭と鋼管を坑内に挿入す
る工程と、鋼管の先端開口部から鉄筋篭内にトレミー管
を挿入する工程と、トレミー管を徐々に引上げながら坑
内にコンクリートを投入する工程と、坑内に充填された
コンクリートのレベルが鋼管の先端部近傍に達したとき
はコンクリートの投入を中止してトレミー管を引上げる
と共に、鋼管の先端部に設けた開閉手段により先端開口
部を閉じる工程と、鋼管内及び鋼管の外周にコンクリー
トを充填する工程とを備えたので、上記(1)、(2)
及び(5)とほぼ同様の効果を得ることができる。
(6) In the method for constructing a cast-in-place steel pipe concrete pile according to the present invention, a step of connecting a reinforcing bar and a connecting member provided on a steel pipe at a site by securing them or the like, and integrating the steps. Inserting the reinforced cage and the steel pipe into the pit, inserting the tremy pipe into the reinforced basket from the tip opening of the steel pipe, introducing concrete into the pit while gradually pulling up the tremy pipe, When the level of the concrete filled in reaches the vicinity of the tip of the steel pipe, stop charging the concrete and pull up the tremie pipe, and closing the tip opening by opening and closing means provided at the tip of the steel pipe, A step of filling concrete in the steel pipe and in the outer periphery of the steel pipe, the above (1), (2)
Almost the same effect as (5) can be obtained.

【0053】(7)上記(6)の鋼管に、内壁の管軸方
向の全部又は一部にプレキャストコンクリートが設けら
れたプレキャストコンクート鋼管を使用したので、上記
(3)、(4)及び(6)とほぼ同様の効果を得ること
ができる。
(7) Since a precast concrete steel pipe in which precast concrete is provided on all or a part of the inner wall in the pipe axis direction is used for the steel pipe of (6), the above (3), (4) and (6) ) Can be obtained substantially the same effect.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の実施の形態1の説明図である。FIG. 1 is an explanatory diagram of Embodiment 1 of the present invention.

【図2】 図1の鋼管の斜視図及び縦断面図である。FIG. 2 is a perspective view and a longitudinal sectional view of the steel pipe of FIG. 1;

【図3】 実施の形態1の施工方法の一例の説明図であ
る。
FIG. 3 is an explanatory diagram of an example of a construction method according to the first embodiment.

【図4】 実施の形態1の施工方法の一例の説明図であ
る。
FIG. 4 is an explanatory diagram of an example of a construction method according to the first embodiment.

【図5】 本発明の実施の形態2の鋼管の縦断面図及び
作用説明図である。
FIG. 5 is a vertical sectional view and an operation explanatory view of a steel pipe according to a second embodiment of the present invention.

【図6】 本発明の実施の形態2の鋼管の他の例の縦断
面図及び作用説明図である。
FIG. 6 is a longitudinal sectional view and an operation explanatory view of another example of the steel pipe according to Embodiment 2 of the present invention.

【図7】 本発明の実施の形態2の鋼管の他の例の縦断
面図及び作用説明図である。
FIG. 7 is a longitudinal sectional view and an operation explanatory view of another example of the steel pipe according to the second embodiment of the present invention.

【図8】 本発明の実施の形態2の鋼管の他の例の縦断
面図及び作用説明図である。
FIG. 8 is a longitudinal sectional view and an operation explanatory view of another example of the steel pipe according to the second embodiment of the present invention.

【図9】 本発明の実施の形態2の鋼管の他の例の縦断
面図及び作用説明図である。
FIG. 9 is a longitudinal sectional view and an operation explanatory view of another example of the steel pipe according to the second embodiment of the present invention.

【図10】 本発明の実施の形態2の鋼管の他の例の縦
断面図及び作用説明図である。
FIG. 10 is a longitudinal sectional view and an operation explanatory view of another example of the steel pipe according to the second embodiment of the present invention.

【図11】 本発明の実施の形態2の鋼管の他の例の説
明図である。
FIG. 11 is an explanatory view of another example of the steel pipe according to the second embodiment of the present invention.

【図12】 本発明の実施の形態3のプレキャストコン
クリート鋼管の説明図である。
FIG. 12 is an explanatory view of a precast concrete steel pipe according to Embodiment 3 of the present invention.

【図13】 実施の形態3の施工方法の一例の説明図で
ある。
FIG. 13 is an explanatory diagram of an example of a construction method according to the third embodiment.

【図14】 実施の形態3の施工方法の他の例の説明図
である。
FIG. 14 is an explanatory diagram of another example of the construction method according to the third embodiment.

【図15】 実施の形態3の施工方法の他の例の説明図
である。
FIG. 15 is an explanatory diagram of another example of the construction method according to the third embodiment.

【図16】 従来の場所打ち鋼管コンクリート杭の一例
の説明図である。
FIG. 16 is an explanatory view of an example of a conventional cast-in-place steel pipe concrete pile.

【符号の説明】[Explanation of symbols]

1 場所打ち鋼管コンクリート杭、2 坑、3 場所打
ちコンクリート杭、4鉄筋篭、5,31 鋼管、6,3
5 底板、7a,36 開口部,8,37蓋板(開閉手
段)、9,33 連結部材、21 トレミー管、22
場所打ちコンクリート、23 充填コンクリート、24
コンクリート、30 プレキャストコンクリート鋼
管、32,32a プレキャストコンクリート、40
柱材。
1 cast-in-place concrete pile, 2 pits, 3 cast-in-place concrete pile, 4 steel cage, 5,31 steel pipe, 6,3
5 bottom plate, 7a, 36 opening, 8, 37 lid plate (opening / closing means), 9, 33 connecting member, 21 tremy tube, 22
Cast-in-place concrete, 23 Filled concrete, 24
Concrete, 30 precast concrete steel pipe, 32, 32a precast concrete, 40
Pillar material.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 今野 和近 東京都千代田区丸の内一丁目1番2号 日 本鋼管株式会社内 (72)発明者 高野 公寿 東京都千代田区丸の内一丁目1番2号 日 本鋼管株式会社内 Fターム(参考) 2D041 AA03 BA19 BA44 DA03 DA04 DB02 DB05 DB07 EB02  ──────────────────────────────────────────────────続 き Continuing on the front page (72) Kazuyoshi Konno, 1-2-1, Marunouchi, Chiyoda-ku, Tokyo Nihon Kokan Co., Ltd. (72) Kotoshi Takano 1-2-1, Marunouchi, Chiyoda-ku, Tokyo, Japan F-term (reference) in Nippon Kokan Co., Ltd. 2D041 AA03 BA19 BA44 DA03 DA04 DB02 DB05 DB07 EB02

Claims (7)

【特許請求の範囲】[Claims] 【請求項1】 鉄筋篭と該鉄筋篭に連結された鋼管とを
坑内に挿入し、該坑内にコンクリートを充填して造成す
る場所打ち鋼管コンクリート杭において、 前記鋼管の先端部に、先端開口部を開閉する開閉手段を
設けたことを特徴とする場所打ち鋼管コンクリート杭。
1. A cast-in-place steel pipe concrete pile in which a steel cage and a steel pipe connected to the steel cage are inserted into a pit, and concrete is filled in the pit to form the steel pipe. Cast-in-place steel pipe concrete piles provided with opening / closing means for opening / closing.
【請求項2】 鋼管の先端部を漏斗状に形成したことを
特徴とする請求項1記載の場所打ち鋼管コンクリート
杭。
2. The cast-in-place steel pipe concrete pile according to claim 1, wherein the tip of the steel pipe is formed in a funnel shape.
【請求項3】 鋼管の内壁の管軸方向の全部又は一部に
プレキャストコンクリートを設けたことを特徴とする請
求項1又は2記載の場所打ち鋼管コンクリート杭。
3. The cast-in-place steel pipe concrete pile according to claim 1, wherein precast concrete is provided on all or a part of the inner wall of the steel pipe in the pipe axis direction.
【請求項4】 鉄筋篭と該鉄筋篭に連結された鋼管とを
坑内に挿入し、該坑内にコンクリートを充填して造成し
た場所打ち鋼管コンクリート杭において、 前記鋼管に、内壁の管軸方向の全部又は一部にプレキャ
ストコンクリートが設けられたプレキャストコンクリー
ト鋼管を用いたことを特徴とする場所打ち鋼管コンクリ
ート杭。
4. A cast-in-place steel pipe concrete pile formed by inserting a steel cage and a steel pipe connected to the steel cage into the pit and filling the pit with concrete, wherein the steel pipe has A cast-in-place steel pipe concrete pile using a precast concrete steel pipe in which all or part of precast concrete is provided.
【請求項5】 鋼管又はプレキャストコンクリートの先
端部に、鉄筋篭と固縛等により連結する複数の連結部材
を設けたことを特徴とする請求項1〜4の何れかに記載
の場所打ち鋼管コンクリート杭。
5. The cast-in-place steel pipe concrete according to claim 1, wherein a plurality of connecting members are provided at a tip end of the steel pipe or precast concrete to be connected to a reinforcing steel cage by securing or the like. Pile.
【請求項6】 鉄筋篭と該鉄筋篭に連結された鋼管とを
坑内に挿入し、該坑内にコンクリートを充填して造成す
る場所打ち鋼管コンクリート杭の施工方法において、 現場において前記鉄筋篭と鋼管に設けた連結部材とを固
縛等により連結して一体化する工程と、 前記一体化された鉄筋篭と鋼管を坑内に挿入する工程
と、 前記鋼管の先端開口部から前記鉄筋篭内にトレミー管を
挿入する工程と、 該トレミー管を徐々に引上げながら坑内にコンクリート
を投入する工程と、 坑内に充填されたコンクリートのレベルが前記鋼管の先
端部近傍に達したときはコンクリートの投入を中止して
前記トレミー管を引上げると共に、前記鋼管の先端部に
設けた開閉手段により先端開口部を閉じる工程と、 前記鋼管内及び鋼管の外周にコンクリートを充填する工
程とを備えたことを特徴とする場所打ち鋼管コンクリー
ト杭の施工方法。
6. A method for constructing a cast-in-place steel pipe concrete pile in which a reinforced cage and a steel pipe connected to the reinforced cage are inserted into a pit, and concrete is filled in the pit to form the pile. Connecting the connecting member provided in the above by tying or the like, integrating the integrated steel cage and the steel pipe into the pit, and tremie into the steel cage from the tip opening of the steel pipe. A step of inserting a pipe, a step of pouring concrete into the pit while gradually pulling up the tremy pipe, and stopping the input of concrete when the level of concrete filled in the pit reaches near the tip of the steel pipe. Pulling up the tremy tube and closing the tip opening by opening and closing means provided at the tip of the steel pipe, and filling concrete in the steel pipe and the outer periphery of the steel pipe. A method for constructing a cast-in-place steel pipe concrete pile, comprising:
【請求項7】 鋼管が、内壁の管軸方向の全部又は一部
にプレキャストコンクリートが設けられたプレキャスト
コンクリート鋼管である請求項6記載の場所打ち鋼管コ
ンクリート杭の施工方法。
7. The method for constructing a cast-in-place steel pipe concrete pile according to claim 6, wherein the steel pipe is a precast concrete steel pipe in which precast concrete is provided on all or a part of an inner wall in a pipe axis direction.
JP11024774A 1999-02-02 1999-02-02 Cast-in-place steel pipe concrete pile and its erecting method Pending JP2000220140A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP11024774A JP2000220140A (en) 1999-02-02 1999-02-02 Cast-in-place steel pipe concrete pile and its erecting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP11024774A JP2000220140A (en) 1999-02-02 1999-02-02 Cast-in-place steel pipe concrete pile and its erecting method

Publications (1)

Publication Number Publication Date
JP2000220140A true JP2000220140A (en) 2000-08-08

Family

ID=12147531

Family Applications (1)

Application Number Title Priority Date Filing Date
JP11024774A Pending JP2000220140A (en) 1999-02-02 1999-02-02 Cast-in-place steel pipe concrete pile and its erecting method

Country Status (1)

Country Link
JP (1) JP2000220140A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101899831A (en) * 2010-08-26 2010-12-01 姚攀峰 Active variable-stiffness leveling pile and construction method thereof
CN102493446A (en) * 2011-11-22 2012-06-13 中冶天工集团有限公司 Steel tube column capable of preventing concrete spillover and method for mounting steel tube column
CN103205964A (en) * 2013-04-01 2013-07-17 中冶交通工程技术有限公司 Cast-in-place pile construction method using steel pipe column splicing piles
CN105568963A (en) * 2015-12-18 2016-05-11 中国石油天然气集团公司 Concrete pile and manufacturing method thereof
JP2017193909A (en) * 2016-04-22 2017-10-26 株式会社日本コムダック anchor
CN116892202A (en) * 2023-06-21 2023-10-17 中冶武勘工程技术有限公司 Steel reinforcement cage and guide pipe positioning and mounting device for pile foundation filling pile construction
CN118048990A (en) * 2024-04-16 2024-05-17 中铁四局集团有限公司 Non-bearing prefabricated shear wall connection structure and construction method

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101899831A (en) * 2010-08-26 2010-12-01 姚攀峰 Active variable-stiffness leveling pile and construction method thereof
CN102493446A (en) * 2011-11-22 2012-06-13 中冶天工集团有限公司 Steel tube column capable of preventing concrete spillover and method for mounting steel tube column
CN102493446B (en) * 2011-11-22 2013-12-25 中冶天工集团有限公司 Steel tube column capable of preventing concrete spillover and method for mounting steel tube column
CN103205964A (en) * 2013-04-01 2013-07-17 中冶交通工程技术有限公司 Cast-in-place pile construction method using steel pipe column splicing piles
CN105568963A (en) * 2015-12-18 2016-05-11 中国石油天然气集团公司 Concrete pile and manufacturing method thereof
JP2017193909A (en) * 2016-04-22 2017-10-26 株式会社日本コムダック anchor
CN116892202A (en) * 2023-06-21 2023-10-17 中冶武勘工程技术有限公司 Steel reinforcement cage and guide pipe positioning and mounting device for pile foundation filling pile construction
CN116892202B (en) * 2023-06-21 2024-04-12 中冶武勘工程技术有限公司 Steel reinforcement cage and guide pipe positioning and mounting device for pile foundation filling pile construction
CN118048990A (en) * 2024-04-16 2024-05-17 中铁四局集团有限公司 Non-bearing prefabricated shear wall connection structure and construction method

Similar Documents

Publication Publication Date Title
CN110258651A (en) Basement roof post-cast strip shifts to an earlier date enclosed construction and construction method
JP3733772B2 (en) Joint structure of cast-in-place steel pipe concrete pile and SRC column and its joining method
JP3689840B2 (en) Seismic reinforcement method for existing structure foundation
JP2000220140A (en) Cast-in-place steel pipe concrete pile and its erecting method
JP2008150910A (en) Prefabricated concrete pile
JP2506398B2 (en) Construction method of cast-in-place concrete pile
JP3131688B2 (en) Construction method of shaft
JPS60203738A (en) Pile head reinforcing method
CN213596966U (en) Self-anchoring cast-in-place pile
KR200291837Y1 (en) The multi-column concrete structure that is made by cast-in-place device
JP2001090060A (en) Driving method for pile and constructing method for cut- off wall using the method
JPH0250246B2 (en)
JPS61151325A (en) Method of reinforcing pile head part against horizontal force
KR101983954B1 (en) Bridge columns using geotextile form
JPH0420443B2 (en)
JP2766194B2 (en) Heater tube installation method
KR101670825B1 (en) Lower part expansion type beam for cast in place pile and pile construction method using the same
JP2004225414A (en) Construction method for foundation pile, and prefabricated pile with spiral blade
JP2002348887A (en) Connecting method of pc pile and footing foundation
JP2002339351A (en) Cage for pile foundation, foundation structure and construction method therefor
JPS642730B2 (en)
JPH0517958A (en) Execution method for steel pipe pile
JPH028089B2 (en)
JPS63201208A (en) Foundation consolidation work for embedded pile
JPS5810531B2 (en) Bashiyochi Concrete Dodomekouhou

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20040528

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20060404

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20060801