JP3459917B1 - Composite caisson structure and method of constructing composite caisson - Google Patents

Composite caisson structure and method of constructing composite caisson

Info

Publication number
JP3459917B1
JP3459917B1 JP2002378781A JP2002378781A JP3459917B1 JP 3459917 B1 JP3459917 B1 JP 3459917B1 JP 2002378781 A JP2002378781 A JP 2002378781A JP 2002378781 A JP2002378781 A JP 2002378781A JP 3459917 B1 JP3459917 B1 JP 3459917B1
Authority
JP
Japan
Prior art keywords
steel sheet
concrete
sheet pile
concrete skeleton
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2002378781A
Other languages
Japanese (ja)
Other versions
JP2004211302A (en
Inventor
秀樹 宮下
Original Assignee
株式会社守谷商会
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社守谷商会 filed Critical 株式会社守谷商会
Priority to JP2002378781A priority Critical patent/JP3459917B1/en
Application granted granted Critical
Publication of JP3459917B1 publication Critical patent/JP3459917B1/en
Publication of JP2004211302A publication Critical patent/JP2004211302A/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

【要約】 【課題】 コンクリート部と鋼材部から成る複合型ケー
ソンで、鋼材部の着脱が可能な複合型ケーソンの構造を
提供する。 【解決手段】 刃口部12と、刃口部12の上方に設け
たコンクリート躯体部14と、コンクリート躯体部14
の上方に鋼矢板を複数連結して筒状に形成した除去可能
な鋼材部21を有する複合型ケーソン構造において、コ
ンクリート躯体部14の上面に所定間隔でコンクリート
躯体部14上面に立設した筒状のソケット部16を設
け、閉断面鋼矢板18をソケット部16に嵌入して、隣
接する閉断面鋼矢板18同士を連結して鋼材部21が形
成した後、ソケット部16に埋設したアンカー20aに
接続したロッド20cを、閉断面鋼矢板18の上端部で
押圧ボルトにより締め付けることにより、鋼材部21を
コンクリート躯体部14に着脱可能に押圧する複合型ケ
ーソン構造である。
【wrap up】 PROBLEM TO BE SOLVED: To provide a composite case comprising a concrete part and a steel part.
Song,Detachable steel partsComplex caisson structure
provide. SOLUTION: A blade port 12 is provided above the blade port 12.
Concrete skeleton 14 and concrete skeleton 14
Can be removed by connecting multiple steel sheet piles above the cylinder
In a composite caisson structure having a
Predetermined spacing on top of concrete frameIn concrete
A cylindrical socket portion 16 erected on the upper surface of the frame portion 14 is provided.
The steel sheet pile 18 is inserted into the socket 16
The steel part 21 is formed by connecting the steel sheet piles 18 in close contact with each other.
After completion, the anchor 20a embedded in the socket 16
The connected rod 20c is held at the upper end of the steel sheet pile 18 with a closed section.
By tightening with the pressing bolt, the steel part 21 is
Detachably presses on concrete skeleton 14Composite type
It is a Johnson structure.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、ケーソンに閉断面
鋼矢板を組み合わせた複合型ケーソンにおいて、コンク
リートケーソンに閉断面鋼矢板を着脱自在に組み合わせ
た複合型ケーソンに関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a composite caisson in which a caisson is combined with a closed section steel sheet pile, and a composite caisson in which a closed section steel sheet pile is detachably combined with a concrete caisson.

【0002】[0002]

【従来の技術】従来より、基礎工事等の土木工事をする
際において、オープンケーソンやニューマチックケーソ
ン等といったケーソン工法が広く用いられている。施工
現場の条件によっては、地中深くまでケーソンを沈下さ
せなければならないこともしばしば見受けられる。この
ように地中深くまでケーソンを沈下させる場合において
は、ニューマチックケーソンが用いられる。ニューマチ
ックケーソンは、刃口部の空間部分に圧縮空気を送り込
み、地盤を掘削してケーソンを沈下させる工法である。
ニューマチックケーソンにおいては、圧縮空気の供給に
関わる諸設備が必要であるため設備費が嵩むことや、高
圧空気の下での作業となるため、作業者の労働時間が法
律により厳密に定められていて、必ずしも施工効率が良
いものではない。
2. Description of the Related Art Conventionally, caisson construction methods such as open caisson and pneumatic caisson have been widely used in civil engineering works such as foundation works. Depending on the conditions of the construction site, it is often found that the caisson must be submerged deep in the ground. When the caisson is submerged deep in the ground like this, a pneumatic caisson is used. Pneumatic caisson is a construction method in which compressed air is sent to the space of the blade edge to excavate the ground and sink the caisson.
Pneumatic caisson requires various facilities related to the supply of compressed air, which increases equipment costs and requires working under high pressure air, so the working hours of workers are strictly defined by law. Therefore, the construction efficiency is not always good.

【0003】オープンケーソン工法で地中深くまで施工
するためには、図6に示すようにケーソン100の上端
側に鋼矢板若しくは鉄筋コンクリート(図示せず)によ
り仮壁110を形成して、仮壁の内面にブラケット13
0や切梁140、腹起し150等の補強材を配して、仮
壁によって掘削穴の側壁面の安定を図りながらケーソン
100の施工が行われていた(例えば非特許文献1参
照)。
In order to construct deeply into the ground by the open caisson method, a temporary wall 110 is formed on the upper end side of the caisson 100 with steel sheet pile or reinforced concrete (not shown) as shown in FIG. Bracket 13 on the inner surface
The caisson 100 has been constructed while a reinforcing material such as 0, a truss 140, and an upset 150 is arranged, and the side wall surface of the excavation hole is stabilized by the temporary wall (for example, see Non-Patent Document 1).

【0004】[0004]

【非特許文献1】北陸地方建設局、建設技術協会著「設
計要綱[道路編]」平成12年4月:9−130〜9−1
32
[Non-Patent Document 1] Hokuriku Regional Construction Bureau, Construction Technology Association, "Design Guidelines [Road Edition]" April 2000: 9-130 to 9-1
32

【0005】[0005]

【発明が解決しようとする課題】施工箇所が河川敷内で
ある場合においては、河川法の規制により、建設すべき
構造物を構成する直接的な部分(ケーソン100および
橋柱部160)以外は、所定深度以浅に残留させること
ができないため、仮設構造物である仮壁は撤去しなけれ
ばならず、仮壁は撤去が容易である必要がある。反面、
掘削作業中においては、作業安全上仮壁が強固に支持さ
れていなければならない。非特許文献1に記載されてい
るケーソン100において、仮壁110に鋼矢板を用い
る場合においては、ケーソン100との接続を容易にす
ることができ、ケーソンに対する鋼矢板の着脱はある程
度は困難を伴わずに行うことが可能ではあるが、使用さ
れる鋼矢板はU字形の開断面鋼矢板であるため、剛性が
低く、仮壁110が高くなると仮壁110自体の剛性不
足による倒壊や、ケーソンと鋼矢板の接続部の拘束力
が、支持地盤に鋼矢板を打ちこんだ場合に得られる拘束
力に比べてはるかに小さいため、掘削作業中において、
鋼矢板が接続部から外れてしまう虞があるといった課題
がある。
When the construction site is inside the riverbed, except for the direct parts (caisson 100 and bridge post 160) that constitute the structure to be constructed, due to the regulations of the River Law, The temporary wall, which is a temporary structure, must be removed because it cannot remain below a predetermined depth, and the temporary wall must be easy to remove. On the other hand,
During excavation work, the temporary wall must be firmly supported for work safety. In the caisson 100 described in Non-Patent Document 1, when a steel sheet pile is used for the temporary wall 110, connection with the caisson 100 can be facilitated, and attachment / detachment of the steel sheet pile to / from the caisson involves some difficulty. However, since the steel sheet pile used is a U-shaped open section steel sheet pile, the rigidity is low, and if the temporary wall 110 becomes high, collapse due to insufficient rigidity of the temporary wall 110 itself and caisson. Since the binding force of the connection part of the steel sheet pile is much smaller than the binding force obtained when the steel sheet pile is driven into the support ground, during excavation work,
There is a problem that the steel sheet pile may come off from the connection portion.

【0006】そこで、開断面の鋼矢板とケーソン100
の接続部を、より強固な拘束力が得られるような構造に
すれば、掘削作業中の安全性は向上するが、鋼矢板を撤
去する際においては、容易に撤去ができなくなるばかり
でなく、場合によっては、鋼矢板や接続部を完全に撤去
することができなくなるという課題がある。これによ
り、仮壁110を鋼矢板で形成した複合オープンケーソ
ンは、地中深くまで施工を要する場合においてあまり適
していない。
[0006] Therefore, a steel sheet pile with an open cross section and a caisson 100.
If the connection part of is made to have a structure capable of obtaining a stronger binding force, the safety during excavation work is improved, but when removing the steel sheet pile, not only can it not be easily removed, In some cases, there is a problem that the steel sheet pile and the connecting portion cannot be completely removed. As a result, the composite open caisson in which the temporary wall 110 is made of steel sheet pile is not very suitable when it is necessary to work deep into the ground.

【0007】一方、ケーソン100において、仮壁11
0に鉄筋コンクリートを用いる場合には、仮壁110を
強固にすることはできるが、反面、仮壁110の撤去に
は非常に手間がかかる上、完全撤去も困難であるため、
事実上は施工機械の作業範囲内である地表面下2〜3m
程度までが適用限界であり、地中深くへのオープンケー
ソンの適用には現実的ではない。また、仮壁110の鉄
筋コンクリート強度が十分に発現するまでは掘削作業を
することができないため、工事工程短縮の大きな障害に
なる。このようにケーソン100の仮壁110は、ケー
ソン100の施工中には、土圧に抵抗するため、ケーソ
ン100との連結は強固であることが要求されるのに対
し、仮壁110を撤去する際においては、ケーソン10
0から簡単に取り外し可能であることが要求されるとい
う、作業者の安全を確保するための二律背反する条件を
満たさなければならず、仮壁110における課題の解決
は非常に困難であった。
On the other hand, in the caisson 100, the temporary wall 11
When reinforced concrete is used for 0, the temporary wall 110 can be strengthened, but on the other hand, it is very time-consuming to remove the temporary wall 110 and it is difficult to completely remove it.
Effectively within the working range of the construction machine 2-3 m below the ground surface
The application limit is up to the degree, and it is not realistic to apply the open caisson deep into the ground. In addition, excavation work cannot be performed until the strength of the reinforced concrete of the temporary wall 110 is sufficiently developed, which is a major obstacle to shortening the construction process. As described above, since the temporary wall 110 of the caisson 100 resists earth pressure during construction of the caisson 100, the connection with the caisson 100 is required to be strong, whereas the temporary wall 110 is removed. By the way, caisson 10
It is very difficult to solve the problem of the temporary wall 110, because it is necessary to satisfy the contradictory condition for ensuring the safety of the worker, which is required to be easily removable from 0.

【0008】[0008]

【課題を解決するための手段】本発明者は以上に説明し
た課題を解決すべく種々の検討を行った結果、ケーソン
の仮壁を閉断面鋼矢板で構成し、ケーソンに閉断面鋼矢
板を着脱自在に取り付け可能であると共に強固な拘束力
を得ることができる構造にすることで、本発明を完成さ
せた。すなわち、筒状をなす刃口部と、該刃口部に連続
して刃口部の上方に設けられた筒状をなすコンクリート
躯体部と、鋼材からなる矢板が複数連結されて筒状に形
成され、前記コンクリート躯体部の上方に設けられた、
除去可能な鋼材部とを有する複合型ケーソン構造におい
て、前記コンクリート躯体部の上面に、所定間隔をおい
、下部側が前記コンクリート躯体部に埋設され、上部
側がコンクリート躯体部上端面から突出する筒状のソケ
ット部が設けられ、前記矢板に、該ソケット部が嵌入す
る筒状の本体部と、該本体部の両側壁から延出され、隣
接する矢板どうし間を連結可能な連結部とを有する閉断
面鋼矢板が用いられて、各閉断面鋼矢板の前記筒状の本
体部下部内に前記ソケット部が抜脱可能に嵌入されると
共に、各閉断面鋼矢板が前記連結部により隣接するもの
どうし連結されて前記鋼材部が形成され、前記コンクリ
ート躯体部上面には、前記閉断面鋼矢板が当接するシー
ル部材が設けられていると共に、前記コンクリート躯体
部上端面から延出するアンカーと、該アンカーの延出部
先端に接続可能なカプラを設けたロッド部と、該ロッド
部上部に配設され、前記鋼材部の上面に当接可能な押圧
板と、前記ロッド部に接続され、前記押圧板を介して前
記鋼材部を前記コンクリート躯体部に押圧する押圧ボル
トとを有する押圧手段により、前記閉断面鋼矢板が前記
コンクリート躯体部に押圧されていることを特徴とする
複合型ケーソン構造である。これにより、鋼材部をコン
クリート躯体部に押圧可能になるので、コンクリート躯
体部を沈下させる際において鋼材部が抜けてしまうこと
がなく、掘削作業中においては鋼材部が土圧の作用に対
し強固に抵抗する。さらには、鋼材部を撤去する際にお
いては、押圧力を解除することができるので、引抜機に
より容易に撤去することができることから、より安全な
構築が可能な複合型ケーソンとするこ とができる。
As a result of various studies to solve the above-mentioned problems, the present inventor constructed a temporary wall of a caisson with a closed section steel sheet pile and a caisson with a closed section steel sheet pile. The present invention has been completed by adopting a structure that can be detachably attached and can obtain a strong restraining force. That is, a tubular blade portion, a tubular concrete skeleton portion continuously provided above the blade opening portion, and a plurality of sheet piles made of steel are connected to form a tubular shape. Provided above the concrete skeleton,
In a composite caisson structure having a removable steel material part, on the upper surface of the concrete skeleton part, at a predetermined interval , the lower side is embedded in the concrete skeleton part, and the upper part
A cylindrical socket part projecting from the upper end surface of the concrete skeleton part is provided, and a cylindrical main body part into which the socket part is fitted in the sheet pile and extending from both side walls of the main body part. And a closed section steel sheet pile having a connecting portion capable of connecting between adjacent sheet piles is used, and the tubular book of each closed section steel sheet pile is used.
Together with the socket portion to the body portion in the lower is fitted so as to be pulled out, the steel part is connected to each other adjacent ones are formed by the closed-section sheet piles are the connecting portions, the concrete
A sheet with which the closed cross section steel sheet pile abuts on the upper surface of the frame body.
And a concrete member provided with
Anchor extending from the upper end surface of the section and the extension of the anchor
A rod portion provided with a coupler connectable to the tip, and the rod
Pressed on the upper part of the part so that it can contact the upper surface of the steel part
Connected to the plate and the rod part, and the front via the pressing plate.
A pressing bolt for pressing the steel material part against the concrete skeleton part.
And a pressing means having a
The composite caisson structure is characterized in that it is pressed against the concrete skeleton . This allows the steel material part to be
Since it can be pressed against the cleat body,
When the steel part is pulled out when the body part is sunk
The steel part is not affected by earth pressure during excavation work.
And strongly resist. Furthermore, when removing the steel part
In addition, since the pressing force can be released,
Safer because it can be removed more easily
Build it is a composite type caisson and the child as possible.

【0009】また、前記ソケット部は、前記コンクリー
ト躯体部上面に配設された鉄板にあらかじめ取り付けら
れていることが好ましい。これにより、コンクリート躯
体部に連結させる閉断面鋼矢板の位置精度が向上すると
共に、コンクリート躯体部上面に垂直に立設させること
が可能になるので、閉断面鋼矢板の引き抜き作業をさら
に容易にすることができる。
Further, the socket portion is provided with the concrete cleaner.
To be attached in advance to the iron plate placed on the upper surface of the
Preferably. This allows the concrete frame
If the positional accuracy of the closed section steel sheet pile connected to the body is improved,
Both shall be erected vertically on the upper surface of the concrete structure.
This makes it easier to pull out steel sheet piles with closed cross sections.
Can be made easier.

【0010】さらに、前記ロッド部は、前記閉断面鋼矢
板の中空部分に挿通されていることが好ましい。これに
よれば、ケーソンの掘削作業中に誤って鋼材部の押圧部
を損傷してしまい、鋼材部が不安定になることを防止す
ることができるので、安全な作業を確実に行うことがで
きる。
Further, it is preferable that the rod portion is inserted into a hollow portion of the steel sheet pile with a closed cross section. According to this, since it is possible to prevent the pressing portion of the steel material portion from being accidentally damaged during excavation work of the caisson and the steel material portion becoming unstable, it is possible to reliably perform safe work. .

【0011】また、他の発明は、施工箇所に筒状の刃口
部を設置する工程と、該刃口部の上方に、筒状のコンク
リート躯体部分を形成し、刃口部内を掘り進めて刃口部
およびコンクリート躯体部分を沈下させるコンクリート
躯体部形成工程と、該コンクリート躯体部上面に、所要
間隔をおいて、下部側が前記コンクリート躯体部に埋設
され、上部側がコンクリート躯体部上端面から突出する
筒状のソケット部を形成する工程と、前記コンクリート
躯体部上端面から延出するアンカーを配設する工程と、
該ソケット部が嵌入する、筒状の本体部および該本体部
の両側壁から延出され、隣接する矢板どうし間を連結可
能な連結部を有する閉断面鋼矢板を用い、各閉断面鋼矢
の前記筒状の本体部下部内に前記ソケット部を嵌入さ
せ、かつ隣接する閉断面鋼矢板どうしを前記連結部によ
り連結して、複数の閉断面鋼矢板により、前記コンクリ
ート躯体上方に抜脱可能な筒状の鋼材部を形成する工程
、前記アンカーの延出部先端に接続可能なカプラを設
けたロッド部を接続する工程と、前記ロッド部に、前記
鋼材部の上面に当接可能な押圧板を配設し、前記ロッド
部に押圧ボルトを螺合して、該押圧ボルトにより、前記
押圧板を介して前記鋼材部を前記コンクリート躯体部に
押圧する工程を含むことを特徴とする複合型ケーソンの
構築方法である。これにより、鋼材部をコンクリート躯
体部に押圧可能になるので、コンクリート躯体部を沈下
させる際において鋼材部が抜けてしまうことがなく、掘
削作業中においては鋼材部が土圧の作用に対し強固に抵
抗する。さらには、鋼材部を撤去する際においては、押
圧力を簡単に解除することができるので、引抜機により
容易に撤去することができることから、より安全に複合
型ケーソンを構築することができる。
Another aspect of the present invention is the step of installing a tubular blade mouth portion at a construction site, forming a tubular concrete skeleton portion above the blade mouth portion, and digging inside the blade mouth portion. Concrete skeleton part forming step of sinking the blade mouth part and the concrete skeleton part, and burying the lower part in the concrete skeleton part at a predetermined interval on the upper surface of the concrete skeleton part
And the upper side projects from the upper end surface of the concrete skeleton
The step of forming a cylindrical socket portion, and the concrete
A step of disposing an anchor extending from the upper end surface of the body part;
Using a closed cross section steel sheet pile having a tubular main body section into which the socket section fits and extending from both side walls of the main body section and having a connecting section capable of connecting adjacent sheet piles , A cylinder that is fitted into the lower portion of the tubular main body , and has adjacent closed-section steel sheet piles connected to each other by the connecting portion, and a plurality of closed-section steel sheet piles that can be pulled out above the concrete skeleton. The step of forming a steel-shaped steel part and a coupler connectable to the tip of the extension part of the anchor.
The step of connecting the beam rod portion, and the rod portion,
A pressing plate that can contact the upper surface of the steel material is arranged
A pressure bolt is screwed onto the
The steel material part to the concrete skeleton part via a pressing plate
A method for constructing a composite caisson, which comprises the step of pressing . As a result, the steel part is
Since it can be pressed against the body, it sinks the concrete body
The steel part does not come off when
During the cutting work, the steel part is strongly resistant to the action of earth pressure.
To withstand. Furthermore, when removing the steel part, push
Since the pressure can be released easily,
It can be removed easily, making it safer to combine.
A type caisson can be constructed.

【0012】さらにまた、前記ソケット部を形成する工
程において、前記コンクリート躯体部分の上面に鉄板を
水平に配設し、当該ソケット部を前記閉断面鋼矢板に嵌
入する際に、当該閉断面鋼矢板が、前記鉄板に当接する
位置にあらかじめシール部材を配設しておくことが好ま
しい。これによれば、ソケット部からの水の浸入を防ぐ
ことができると共に、閉断面鋼矢板をコンクリート躯体
の上面に垂直に立設することができる。また、ソケット
をあらかじめ鉄板に取り付けておくことにより、閉断面
鋼矢板の設置位置の精度を正確にすることができ、鋼矢
板どうしの連結部に無理な力が作用しないので、閉断面
鋼矢板の転用回数を増やすことができ、引き抜き作業も
容易に行うことができる。
Furthermore, in the step of forming the socket portion, an iron plate is horizontally arranged on the upper surface of the concrete skeleton portion, and when the socket portion is fitted into the closed cross section steel sheet pile, the closed cross section steel sheet pile. However, it is preferable to dispose a seal member in advance at a position where it abuts on the iron plate. According to this, it is possible to prevent intrusion of water from the socket portion, and it is possible to vertically install the closed cross section steel sheet pile on the upper surface of the concrete skeleton. In addition, by installing the socket on the steel plate in advance, the accuracy of the installation position of the closed section steel sheet pile can be made accurate, and no unreasonable force acts on the joint between the steel sheet piles. The number of times of diversion can be increased, and the drawing operation can be easily performed.

【0013】[0013]

【発明の実施の形態】以下、本発明に係る複合型ケーソ
ン構造の好適な実施の形態を図面に従って詳細に説明す
る。図1は、本実施の形態における複合型ケーソンの正
面図である。図2は、本実施の形態における複合型ケー
ソンの平面図である。図3は、コンクリート躯体最上端
部の拡大説明図である。図4は、本実施の形態に用いる
閉断面鋼矢板の断面図である。本実施の形態における複
合型ケーソン10は、刃口部分12と、刃口部分12に
載置されるコンクリート躯体部分14と、コンクリート
躯体部分14の最上端部に配設されたソケット部16と
ソケット部16によりコンクリート躯体部分14の最上
端部に立設される閉断面鋼矢板18と、コンクリート躯
体部分14の最上端部に埋設されるとともに、閉断面鋼
矢板18の中空部分を通り抜け、閉断面鋼矢板18の上
端部からはみ出すようにして配設される押圧手段20と
によって概略が形成される。閉断面鋼矢板18による筒
状体が鋼材部21である。本実施の形態における複合型
ケーソン10の断面形状は扁平した円筒形(小判型)の
ものを想定しているが円形形状等の他の形状であっても
よいのはもちろんである。
BEST MODE FOR CARRYING OUT THE INVENTION Preferred embodiments of the composite caisson structure according to the present invention will be described in detail below with reference to the drawings. FIG. 1 is a front view of the composite caisson according to the present embodiment. FIG. 2 is a plan view of the composite caisson according to the present embodiment. FIG. 3 is an enlarged explanatory diagram of the uppermost end of the concrete skeleton. FIG. 4 is a cross-sectional view of a closed section steel sheet pile used in the present embodiment. The composite caisson 10 according to the present embodiment includes a blade opening portion 12, a concrete skeleton portion 14 placed on the blade opening portion 12, a socket portion 16 and a socket arranged at the uppermost end of the concrete skeleton portion 14. Closed cross section steel sheet pile 18 which is erected at the uppermost end of the concrete frame portion 14 by the part 16 and is embedded in the uppermost end portion of the concrete frame portion 14 and passes through the hollow portion of the closed cross section steel sheet pile 18 to form a closed cross section. The outline is formed by the pressing means 20 arranged so as to protrude from the upper end portion of the steel sheet pile 18. The tubular member formed of the steel sheet pile 18 having the closed cross section is a steel material portion 21. The cross-sectional shape of the composite caisson 10 in the present embodiment is assumed to be a flat cylindrical shape (oval shape), but it goes without saying that it may be another shape such as a circular shape.

【0014】また、必要に応じて、鋼材部21の内周面
にブラケット30を設け、切梁32や腹起し34により
鋼材部21の補強をすれば、地中深くにおいても土圧に
より鋼材部21が倒れこみを防ぐことができるのでさら
に好適である。
If necessary, a bracket 30 is provided on the inner peripheral surface of the steel material portion 21 and the steel material portion 21 is reinforced by a sill beam 32 or an uprising 34. It is more preferable because the portion 21 can prevent the portion from falling down.

【0015】刃口部分12は、鋼板を溶接することによ
り組み立てた扁平した円環状である。刃口部分12は掘
削現場に搬送され、所定位置に設置された後、開口部分
からコンクリートが打設される。刃口部分12の上端部
に鉄筋(図示せず)を立設しておけば、刃口部分12と
コンクリート躯体部分14の応力伝達を確実にすること
ができるので好都合である。
The blade edge portion 12 is a flat annular ring assembled by welding steel plates. The blade mouth portion 12 is transported to the excavation site, installed at a predetermined position, and then concrete is poured from the opening portion. If a reinforcing bar (not shown) is erected on the upper end of the blade edge portion 12, stress transmission between the blade edge portion 12 and the concrete skeleton portion 14 can be ensured, which is convenient.

【0016】コンクリート躯体部分14は、刃口部分1
2の上面に構築される筒状体であり、ケーソンの側壁部
を構成するものである。本実施の形態におけるコンクリ
ート躯体部分14は、現場打ちコンクリートにより形成
されるものを想定している。刃口部分12の上端面に立
設させた鉄筋に連続させて、図示しない鉄筋および型枠
を組み立てた後、型枠内にコンクリートを打設してコン
クリート躯体部分14が形成される。コンクリート躯体
部分14は複数回に分けて構築されることがあるので、
次層のコンクリート躯体部分14の鉄筋とラップさせる
ようにして鉄筋を配設しておけば、上下層のコンクリー
ト躯体部分14どうしの応力伝達が確実になるため好適
である。打設したコンクリートが硬化し、所定の強度が
発現した後に、刃口部分12に囲まれている部分の地盤
を掘削する。刃口部分12とコンクリート躯体部分14
の自重により、刃口部分12とコンクリート躯体部分1
4とを所定深さまで沈下させた後、コンクリート躯体部
分14の上端部に次の層のコンクリート躯体部分14を
追加する。以上の作業を繰り返すことにより、コンクリ
ート躯体部分14が地盤内に構築される。
The concrete skeleton portion 14 is a blade edge portion 1.
It is a cylindrical body constructed on the upper surface of No. 2 and constitutes the side wall of the caisson. The concrete skeleton portion 14 in the present embodiment is assumed to be formed of cast-in-place concrete. After assembling a rebar and a form which are not shown in succession to the rebar erected on the upper end surface of the blade mouth part 12, concrete is poured into the form to form a concrete skeleton part 14. Since the concrete skeleton part 14 may be constructed in multiple steps,
It is preferable to arrange the reinforcing bars so as to wrap them with the reinforcing bars of the concrete skeleton portion 14 of the next layer, because the stress transmission between the concrete skeleton portions 14 of the upper and lower layers will be sure. After the poured concrete is hardened and a predetermined strength is developed, the ground in the portion surrounded by the blade opening 12 is excavated. Blade part 12 and concrete skeleton part 14
Due to its own weight, the blade edge part 12 and the concrete skeleton part 1
After sinking 4 and a predetermined depth, the concrete skeleton portion 14 of the next layer is added to the upper end of the concrete skeleton portion 14. By repeating the above work, the concrete skeleton portion 14 is constructed in the ground.

【0017】ソケット部16は、コンクリート躯体部分
14の最上段部(以下、最終コンクリート躯体14fと
いう)の上端面に配設され、複合型ケーソン10のコン
クリート部分と閉断面鋼矢板部分18とを連結するため
のものである。本実施の形態におけるソケット部16
は、図3に示すように最終コンクリート躯体部分14f
の上端面に埋設され、閉断面鋼矢板18の本体部18a
に挿通する筒状体により成っている。ソケット部16
は、最終コンクリート躯体部分14fの上端面におい
て、一定間隔をおいて鉛直に立設されている。
The socket portion 16 is disposed on the upper end surface of the uppermost step (hereinafter referred to as the final concrete skeleton 14f) of the concrete skeleton portion 14 and connects the concrete portion of the composite caisson 10 and the closed section steel sheet pile portion 18. It is for doing. Socket part 16 in the present embodiment
Is the final concrete skeleton part 14f as shown in FIG.
Embedded in the upper end surface of the main body 18a of the steel sheet pile 18 with a closed cross section
It is made up of a cylindrical body that is inserted into. Socket part 16
Are erected vertically at regular intervals on the upper end surface of the final concrete skeleton portion 14f.

【0018】閉断面鋼矢板18が最終コンクリート躯体
部分14fの上端面と当接する部分には、止水用のシー
ル部材17が設けられている。シール部材17を押し潰
すようにして閉断面鋼矢板18をソケット部16に挿入
すれば、ソケット部16と閉断面鋼矢板18の嵌入部か
らの水の浸入を好適に防ぐことができる。閉断面鋼矢板
18の本体部18aとソケット部16との隙間にはスペ
ーサ19を介在させれば、ソケット部16と閉断面鋼矢
板18のガタつきを防止することができる。なお、最終
コンクリート躯体部分14fの上端面に、鉄板50を配
設し、鉄板50にあらかじめソケット部16を溶接等に
より取り付けておけば、閉断面鋼矢板18の設置位置の
精度を正確にすることができると共に、コンクリート躯
体部分14の上面に垂直に立設することができる。ま
た、閉断面鋼矢板18どうしの連結部に無理な力が作用
しないので、閉断面鋼矢板18の引き抜き作業も容易に
なり、閉断面鋼矢板18の転用が可能になるため好適で
ある。
A seal member 17 for stopping water is provided at a portion where the closed cross section steel sheet pile 18 contacts the upper end surface of the final concrete skeleton portion 14f. If the closed cross section steel sheet pile 18 is inserted into the socket section 16 by crushing the seal member 17, water can be suitably prevented from entering from the fitting section between the socket section 16 and the closed cross section steel sheet pile 18. By interposing a spacer 19 in the gap between the main body 18a of the closed cross section steel sheet pile 18 and the socket section 16, it is possible to prevent rattling between the socket section 16 and the closed cross section steel sheet pile 18. In addition, if the iron plate 50 is disposed on the upper end surface of the final concrete skeleton portion 14f and the socket portion 16 is previously attached to the iron plate 50 by welding or the like, the accuracy of the installation position of the closed cross section steel sheet pile 18 can be made accurate. In addition to the above, it can be erected vertically on the upper surface of the concrete skeleton portion 14. Further, since an unreasonable force does not act on the connecting portion between the closed cross section steel sheet piles 18, the work for pulling out the closed cross section steel sheet pile 18 is facilitated and the closed cross section steel sheet pile 18 can be diverted, which is preferable.

【0019】引き続き図3を用いて押圧手段20の説明
をする。押圧手段20は、ソケット部16に挿入した閉
断面鋼矢板18(鋼材部21)がソケット部16から抜
けないように、閉断面鋼矢板18をソケット部16に押
圧させるものである。押圧手段20は、アンカー鉄筋2
0aの延出部先端に螺合部を形成し、アンカー鉄筋20
aの延出部先端に形成された螺合部に螺着可能なカプラ
20bを一端部に取り付けたタイロッド20cを、カプ
ラ20bを介して互いに連結し、タイロッド20cの他
端側部分に閉断面鋼矢板18の上端部に係止する押圧板
20dを設け、押圧板20dの上側からタイロッド20
cを締め付けるボルト等の締め付け手段20eを設ける
ことにより構成される。
The pressing means 20 will be described with reference to FIG. The pressing means 20 presses the closed cross section steel sheet pile 18 against the socket section 16 so that the closed cross section steel sheet pile 18 (steel material section 21) inserted into the socket section 16 does not come off from the socket section 16. The pressing means 20 is the anchor rebar 2
A threaded portion is formed at the tip of the extension portion of 0a, and the anchor rebar 20
A tie rod 20c having a coupler 20b attached at one end to a screwing portion formed at the tip of the extending portion of a is connected to each other via the coupler 20b, and a steel pipe having a closed cross section is formed at the other end of the tie rod 20c. A pressing plate 20d that engages with the upper end of the sheet pile 18 is provided, and the tie rod 20 is inserted from above the pressing plate 20d.
It is configured by providing a tightening means 20e such as a bolt for tightening c.

【0020】アンカー鉄筋20aは、最終コンクリート
躯体部分14fの上端面から一部が突出しているソケッ
ト部16の中央部分の空間に先端部が延出するようにし
て埋設されている。最終コンクリート躯体部分14fの
上端面から延出しているアンカー鉄筋20aの先端部に
は、螺合部が形成されている。タイロッド20cの一端
部にはアンカー鉄筋20aの螺合部に螺着可能なカプラ
20bが取り付けられている。したがって、アンカー鉄
筋20aとタイロッド20cは、互いにカプラ20bを
介して接続される。なお、カプラ20bはアンカー鉄筋
20a側に取り付けてもよく、アンカー鉄筋20aとカ
プラ20cとをあらかじめ溶接等により固着させておい
てもよい。
The anchor rebar 20a is embedded in the space of the central portion of the socket portion 16 partly protruding from the upper end surface of the final concrete skeleton portion 14f so that the tip portion thereof extends. A threaded portion is formed at the tip of the anchor reinforcing bar 20a extending from the upper end surface of the final concrete skeleton portion 14f. A coupler 20b is attached to one end of the tie rod 20c so that the coupler 20b can be screwed into the screwed portion of the anchor rebar 20a. Therefore, the anchor rebar 20a and the tie rod 20c are connected to each other via the coupler 20b. The coupler 20b may be attached to the side of the anchor reinforcing bar 20a, or the anchor reinforcing bar 20a and the coupler 20c may be fixed in advance by welding or the like.

【0021】タイロッド20cはソケット部16に挿入
した閉断面鋼矢板18の本体部18aの中空部分(図4
参照)を挿通し、閉断面鋼矢板18の上端部分から突出
する長さに設定している。タイロッド20cが閉断面鋼
矢板18から突出する端部には、螺合部が加工されてい
るとともに、閉断面鋼矢板18をソケット部16に押さ
えつける押圧板20dが設けられている。押圧板20d
は、タイロッド20cに挿通されていて、閉断面鋼矢板
18の外端縁より大きく形成されている。押圧板20d
を閉断面鋼矢板18の上端部に当接させた後、ボルト等
の締め付け手段20eを締め付けることにより、閉断面
鋼矢板18と、タイロッド20cを緊張させれば、閉断
面鋼矢板18をソケット部16に押圧して連結させるこ
とが可能になる。これにより、閉断面鋼矢板18(つま
りは鋼材部21)を安定して最終コンクリート躯体部1
4fに立設させることができるため、安全な作業環境を
提供することが可能になり好適である。
The tie rod 20c is a hollow portion of the main body portion 18a of the steel sheet pile 18 having a closed cross section inserted in the socket portion 16 (see FIG. 4).
(Refer to FIG. 3), and the length is set so as to project from the upper end portion of the steel sheet pile 18 having the closed cross section. A threaded portion is formed at the end of the tie rod 20c protruding from the closed section steel sheet pile 18, and a pressing plate 20d for pressing the closed section steel sheet pile 18 against the socket portion 16 is provided. Pressing plate 20d
Is inserted into the tie rod 20c and is formed to be larger than the outer end edge of the steel sheet pile 18 having the closed cross section. Pressing plate 20d
After contacting the upper end portion of the closed cross section steel sheet pile 18, by tightening the tightening means 20e such as a bolt, the closed cross section steel sheet pile 18 and the tie rod 20c are tensioned, so that the closed cross section steel sheet pile 18 becomes the socket section. It becomes possible to press 16 and connect. As a result, the closed section steel sheet pile 18 (that is, the steel material portion 21) is stabilized and the final concrete frame portion 1
Since it can be installed upright on 4f, it is possible to provide a safe working environment, which is preferable.

【0022】閉断面鋼矢板18は、例えば図4(a)に
示すように本体部18aが四角形の筒型に形成され、対
向する一組の側壁の両端部からそれぞれ継手18bが設
けられている。継手18bは、平面視が略C形に形成さ
れていて、閉断面鋼矢板18の長手方向から互いの開口
部分18cを対向させることにより連結可能に形成され
ている。
In the closed section steel sheet pile 18, for example, as shown in FIG. 4A, a main body portion 18a is formed in a quadrangular tubular shape, and joints 18b are provided from both ends of a pair of opposing side walls. . The joint 18b is formed in a substantially C shape in a plan view, and is formed so as to be connectable by allowing the opening portions 18c of the closed section steel sheet piles 18 to face each other in the longitudinal direction.

【0023】本実施の形態においては、コンクリート躯
体部14の平面断面が扁平した円筒状(小判型)に形成
されている。コンクリート躯体部14の平面断面に沿っ
て一定間隔に立設されたソケット部16に隣接する閉断
面鋼矢板どうしを継手18bにより互いに連結させてか
らソケット部16に嵌入することにより、連続した閉断
面鋼矢板18(鋼材部21)を形成することができる。
このように、複数の閉断面鋼矢板18を用いて、コンク
リート躯体部14の平面断面と同様な筒状体である鋼材
部21を形成するためには、閉断面鋼矢板18により曲
線部分を形成しなければならない。曲線部分に用いる閉
断面鋼矢板18は、例えば図4(b)に示すように、対
向する継手18bの長さをそれぞれ異にして製作する。
すなわち、曲線部分に割り当てられる閉断面鋼矢板18
の外側にあたる継手18boは長く形成され、内側にあ
たる継手18biは外側の継手18boより短く形成さ
れている。また、例えば図4(c)に示すように、隣接
する閉断面鋼矢板18どうしを連結する際においても、
開口部分18cに図示しないシール材を用いることによ
り閉断面鋼矢板18どうしの連結部分から水の浸入をな
くすことができるため好都合である。
In the present embodiment, the concrete skeleton portion 14 is formed in a flat cylindrical shape (oval shape). Closed cross section steel sheet piles adjacent to the socket parts 16 standing at regular intervals along the plane cross section of the concrete skeleton part 14 are connected to each other by a joint 18b and then fitted into the socket parts 16 to form a continuous closed cross section. The steel sheet pile 18 (steel material portion 21) can be formed.
As described above, in order to form the steel material portion 21 that is a tubular body similar to the plane cross section of the concrete skeleton portion 14 by using a plurality of closed cross section steel sheet piles 18, a curved section is formed by the closed cross section steel sheet piles 18. Must. The closed cross section steel sheet piles 18 used for the curved portions are manufactured, for example, as shown in FIG.
That is, the closed section steel sheet pile 18 assigned to the curved portion
The outer joint 18bo is formed longer, and the inner joint 18bi is formed shorter than the outer joint 18bo. Further, for example, as shown in FIG. 4 (c), when connecting adjacent steel sheet piles 18 having closed cross sections,
It is convenient to use a sealing material (not shown) for the opening portion 18c because it is possible to prevent water from entering the connecting portion between the steel sheet piles 18 having the closed cross sections.

【0024】図5は、本実施の形態における複合型ケー
ソンの構築における作業工程の概略を示すフロー図であ
る。以下に本発明に係る複合型ケーソンの施工方法につ
いて図5を参照しながら説明する。まず、鋼板を溶接す
ることにより組み立てられた刃口部分12をケーソンの
施工対象現場に設置する(S101)。刃口部分12の
設置が完了したら、刃口部分12にコンクリートを打設
する(S102)。また、刃口部分12の上端面からは
コンクリート躯体部分14どうしの応力伝達を確実にす
るために、互いの鉄筋をラップさせることができるよう
に配設しておけば好適である。
FIG. 5 is a flow chart showing an outline of work steps in the construction of the composite caisson according to the present embodiment. Hereinafter, a method for constructing the composite caisson according to the present invention will be described with reference to FIG. First, the blade edge portion 12 assembled by welding a steel plate is installed at the caisson construction target site (S101). When the installation of the blade edge portion 12 is completed, concrete is poured into the blade edge portion 12 (S102). Further, in order to ensure the stress transmission between the concrete skeleton portions 14 from the upper end surface of the blade edge portion 12, it is preferable to dispose them so that the reinforcing bars can be wrapped with each other.

【0025】刃口部分12のコンクリートが硬化した
ら、刃口部分12から延出している鉄筋にコンクリート
躯体部分14のコンクリートの鉄筋をラップさせ、型枠
を組んでコンクリート躯体部分14のコンクリート打設
の準備をする(S103)。現在コンクリート打設の準
備をしているコンクリート躯体部分14が最終コンクリ
ート躯体部分14fであるか設計図により施工者が確認
し、現在のコンクリート躯体部分14が最終コンクリー
ト躯体部分14fでない場合には、上端部からラップ用
の鉄筋を配設した後に、型枠を組み立てた後、型枠内に
コンクリートの打設を行う(SC1)。コンクリート躯
体部分14のコンクリートが硬化した後に、刃口部分1
2の内側部分の地盤を掘削し、刃口部分12とコンクリ
ート躯体部分14を所定深さまで沈下させる(SC
2)。そして、最終コンクリート躯体部分14fが最上
段部になるまで引き続きコンクリート躯体部分14を同
様の手順により形成し、掘削・沈下作業を継続して行
う。
When the concrete at the blade mouth portion 12 is hardened, the rebar extending from the blade mouth portion 12 is wrapped with the concrete rebar of the concrete skeleton portion 14, and a formwork is assembled to lay the concrete skeleton of the concrete skeleton portion 14. Prepare (S103). The operator confirms from the design drawing whether the concrete skeleton part 14 currently preparing for concrete placement is the final concrete skeleton part 14f, and if the current concrete skeleton part 14 is not the final concrete skeleton part 14f, the upper end After arranging the reinforcing bars for wrapping from the section, after assembling the formwork, concrete is placed in the formwork (SC1). After the concrete of the concrete skeleton portion 14 is hardened, the blade edge portion 1
2 excavates the ground in the inner part and sinks the blade tip part 12 and the concrete skeleton part 14 to a predetermined depth (SC
2). Then, the concrete skeleton portion 14 is continuously formed by the same procedure until the final concrete skeleton portion 14f becomes the uppermost step portion, and excavation and subsidence work is continuously performed.

【0026】現在コンクリートの打設準備をしているコ
ンクリート躯体部分14が最終コンクリート躯体部分1
4fである場合には、最終コンクリート躯体部分14f
の上端部に、先端部に螺合部が形成されたアンカー鉄筋
20aを最終コンクリート躯体部分14fの上端面から
延出するようにして配設する(S104)。また、ソケ
ット部16の中空部分にアンカー鉄筋20aが収まるよ
うにしてソケット部16を最終コンクリート躯体部分1
4fの上端面に一定間隔に立設する(S105)。ソケ
ット部16は最終コンクリート躯体部分14fの上端面
において鉛直に立設されるようにしっかりと固定する。
なお、ソケット部16を鉄板50にあらかじめ取り付け
ておき、ソケット部16と鉄板50を最終コンクリート
躯体部分14fの上端面に配設し、止水材としてのシー
ル部材17を配設しておけば、ソケット部16の配設位
置を正確にすることができると共に、ソケット部16に
閉断面鋼矢板18を立設した際において最終コンクリー
ト躯体部分14fと閉断面鋼矢板18との連結部分から
の水の浸入を防ぐことができ、さらには閉断面鋼矢板1
8の引き抜き作業が容易に行え、閉断面鋼矢板18の転
用がしやすくなるため好適である。このようにして最終
コンクリート躯体部分14fの上端面が整備された後
に、最終コンクリート躯体部分14fのコンクリート打
設を行う(S106)。コンクリートの打設において
は、上端面に配設したアンカー鉄筋20aやソケット部
16、ソケット部16と鉄板50がずれないようにしな
がら十分注意して作業する。
The concrete skeleton portion 14 which is currently preparing for placing concrete is the final concrete skeleton portion 1.
If it is 4f, the final concrete skeleton part 14f
An anchor rebar 20a having a threaded portion formed at the tip is disposed at the upper end of the so as to extend from the upper end surface of the final concrete skeleton portion 14f (S104). In addition, the socket portion 16 is inserted into the hollow portion of the socket portion 16 so that the anchor rebar 20a fits into the final concrete skeleton portion 1.
The upper end surface of 4f is erected at regular intervals (S105). The socket portion 16 is firmly fixed so as to stand vertically on the upper end surface of the final concrete skeleton portion 14f.
In addition, the socket portion 16 is attached to the iron plate 50 in advance , the socket portion 16 and the iron plate 50 are disposed on the upper end surface of the final concrete skeleton portion 14f, and the seal member 17 as a water blocking material is disposed. If this is done, the position where the socket portion 16 is arranged can be made precise, and when the closed section steel sheet pile 18 is erected on the socket portion 16, the connection portion between the final concrete skeleton portion 14f and the closed section steel sheet pile 18 is provided. Can prevent the intrusion of water from the inside, and further has a closed cross section steel sheet pile 1
This is preferable because the pulling out work of No. 8 can be easily performed and the closed section steel sheet pile 18 can be diverted easily. After the upper end surface of the final concrete skeleton portion 14f is prepared in this manner, concrete placing of the final concrete skeleton portion 14f is performed (S106). When pouring concrete, the anchor rebar 20a disposed on the upper end surface, the socket portion 16, and the socket portion 16 and the iron plate 50 are carefully displaced while being prevented from being displaced.

【0027】最終コンクリート躯体部分14fが硬化し
た後、ソケット部16に閉断面鋼矢板18を挿入して、
躯体コンクリートの上端部に立設する(S107)。そ
れぞれのソケット部16に閉断面鋼矢板18を挿入し、
隣り合う閉断面鋼矢板18どうしの継手18bを連結さ
せて、閉断面鋼矢板18により鋼材部21である筒状体
を形成する。すべてのソケット部16に閉断面鋼矢板1
8の立設が完了したら、カプラ20bを取り付けたタイ
ロッド20cを各閉断面鋼矢板18の中空部分に挿通
し、先端部分をアンカー鉄筋20aの螺合部に螺着させ
て取り付ける(S108)。
After the final concrete skeleton portion 14f is hardened, a steel sheet pile 18 having a closed cross section is inserted into the socket portion 16,
It is erected on the upper end of the skeleton concrete (S107). Insert the closed section steel sheet pile 18 into each socket 16,
The joints 18b of the adjacent closed cross section steel sheet piles 18 are connected to each other, and the closed cross section steel sheet pile 18 forms a tubular body which is the steel material portion 21. Closed-section steel sheet pile 1 for all socket parts 16
When the standing of No. 8 is completed, the tie rod 20c to which the coupler 20b is attached is inserted into the hollow portion of each closed section steel sheet pile 18, and the tip end portion is screwed and attached to the screwed portion of the anchor rebar 20a (S108).

【0028】タイロッド20cは閉断面鋼矢板18の上
端部からはみ出す長さを有し、閉断面鋼矢板18からは
み出している端部側には螺合部が形成されている。タイ
ロッド20cに閉断面鋼矢板18の外形より大きく形成
され、中央部に挿通孔20dsを有する押圧板20dを
タイロッド20cに挿通させて、閉断面鋼矢板18の上
端部に当接させた後、押圧板20dの上側からボルト等
の締め付け手段20eにより締め付けることによって、
押圧板20dにより閉断面鋼矢板18をソケット16に
押圧する(S109)。
The tie rod 20c has a length protruding from the upper end of the closed section steel sheet pile 18, and a threaded portion is formed on the end side protruding from the closed section steel sheet pile 18. The tie rod 20c is formed to be larger than the outer shape of the closed section steel sheet pile 18, and the pressing plate 20d having the insertion hole 20ds in the central portion is inserted into the tie rod 20c and brought into contact with the upper end portion of the closed section steel sheet pile 18 and then pressed. By tightening from the upper side of the plate 20d with tightening means 20e such as bolts,
The pressing section 20d presses the closed section steel sheet pile 18 against the socket 16 (S109).

【0029】すべての閉断面鋼矢板18と、タイロッド
20cを押圧板20dおよび締め付け手段20eにより
押圧させた後に、鋼材部21の内周面にブラケット3
0、切梁32や腹起し34等の補強部材を取り付ける
(S110)ことにより、鋼材部21が土圧により倒壊
することを防止する。このような補強部材は、鋼材部2
1に作用する土圧の大きさに応じて複数箇所に配設する
ことが好ましい。なお、施工箇所の地盤条件や鋼材部2
1の形状によっては、ブラケット30や切梁32、腹起
し34などの補強部材を配設しなくても済む場合があ
り、補強部材を用いない形態も十分考えられる。
After all the closed section steel sheet piles 18 and the tie rods 20c are pressed by the pressing plate 20d and the tightening means 20e, the bracket 3 is attached to the inner peripheral surface of the steel material portion 21.
By attaching reinforcing members such as 0, the truss 32, and the uprising 34 (S110), the steel material portion 21 is prevented from collapsing due to earth pressure. Such a reinforcing member is a steel member 2
It is preferable to dispose at a plurality of locations depending on the magnitude of earth pressure acting on 1. In addition, the ground conditions of the construction site and the steel part 2
Depending on the shape of No. 1, there is a case where it is not necessary to dispose a reinforcing member such as the bracket 30, the truss 32, and the uprising 34, and it is also conceivable that no reinforcing member is used.

【0030】以上の工程により形成された複合型ケーソ
ン10は、掘削穴の側壁部が閉断面鋼矢板18(鋼材部
21)により保護されているので、掘削穴が崩壊するお
それがなく、安全な作業環境を提供することが可能にな
る。また、最終コンクリート躯体部分14fと閉断面鋼
矢板18との間や、閉断面鋼矢板18どうしを連結する
継手18bの開口部18cに止水材としてシール部材を
配設していることから、閉断面鋼矢板18どうしの連結
部からの地下水の浸入も防止することができる。このよ
うに好適な作業環境において、刃口部分12の内側部分
を掘削し、複合型ケーソン10の沈下作業を継続して行
い(S111)、複合型ケーソン10が支持地盤等の設
計位置に到達するまで掘削・沈下・コンクリート躯体部
分14のコンクリート打設の作業を繰り返す。なお、閉
断面鋼矢板18(鋼材部21)は剛性が高いので、複合
型ケーソン10を沈下させる作業において、ケーソン外
周の摩擦が大きく、沈下荷重が不足する場合において
は、水等の付加荷重を複合型ケーソン10の天端に作用
させることにより沈下の促進が可能になる。
Since the side wall of the excavation hole is protected by the closed section steel sheet pile 18 (steel material portion 21) in the composite caisson 10 formed by the above steps, there is no risk of the excavation hole collapsing, and it is safe. It becomes possible to provide a working environment. In addition, since the seal member is disposed as a water blocking material between the final concrete skeleton portion 14f and the closed cross section steel sheet pile 18, or in the opening 18c of the joint 18b for connecting the closed cross section steel sheet piles 18, the sealing member is closed. It is also possible to prevent the infiltration of groundwater from the connecting portion between the steel sheet piles 18 in cross section. As described above, in the suitable working environment, the inner portion of the blade opening 12 is excavated, and the sinking work of the composite caisson 10 is continuously performed (S111), and the composite caisson 10 reaches the design position such as the support ground. The work of excavation, subsidence, and concrete placement of the concrete skeleton portion 14 is repeated. Since the closed cross section steel sheet pile 18 (steel material portion 21) has high rigidity, in the work of sinking the composite caisson 10, when the friction of the outer periphery of the caisson is large and the sink load is insufficient, an additional load such as water is applied. The subsidence can be promoted by acting on the top of the composite caisson 10.

【0031】複合型ケーソン10が所定位置(支持地
盤)に到達した後、刃口部分12の上面に底板コンクリ
ート60を打設する(S112)。底板コンクリートが
硬化したら、コンクリート躯体部14の内部空間に土砂
等を埋め戻しする(S113)。その後、最終コンクリ
ート躯体部14fの上端面に頂板コンクリート62を打
設(S114)し、頂板コンクリート62が硬化した後
に、頂板コンクリート62上に橋柱等の構造物70を構
築する(S115)。構造物70の最下層部の構築が完
了したら、最下段に配設されているブラケット30、切
梁32、腹起し34等の補強部材を取り外し(S11
6)て、埋め戻しを行う(S117)。構造物70の構
築(S115)と補強部材の取り外し(S116)と埋
め戻し(S117)作業は複数回に分けて行う。埋め戻
し面が所定位置まで到達していない場合には、構造物7
0の構築作業(S115)と、補強部材の取り外し作業
(S116)と、埋め戻し作業(S117)を所定回数
繰り返し、所定位置まで埋め戻しを行う。埋め戻し面が
所定位置に到達した場合には、タイロッド20cと閉断
面鋼矢板18とを緊張させているボルト等の締め付け手
段20eと押圧板20dを緩めて、閉断面鋼矢板18
(鋼材部21)のソケット部16への押圧を解除する
(S118)。押圧力が解除された閉断面鋼矢板18
は、引抜き機により引抜かれて(S119)複合型ケー
ソン10の施工作業が完了(S120)する。
After the composite caisson 10 reaches a predetermined position (supporting ground), the bottom plate concrete 60 is placed on the upper surface of the cutting edge portion 12 (S112). After the bottom plate concrete is hardened, earth and sand or the like is backfilled in the internal space of the concrete skeleton portion 14 (S113). Thereafter, the top plate concrete 62 is cast on the upper end surface of the final concrete skeleton portion 14f (S114), and after the top plate concrete 62 is hardened, the structure 70 such as a bridge pillar is constructed on the top plate concrete 62 (S115). When the construction of the lowermost layer portion of the structure 70 is completed, the reinforcing members such as the bracket 30, the girder 32, and the uprising 34 arranged at the lowermost stage are removed (S11).
6) Then, backfilling is performed (S117). The construction of the structure 70 (S115), the removal of the reinforcing member (S116), and the backfilling (S117) are divided into a plurality of operations. If the backfill surface has not reached the specified position, the structure 7
The construction work of 0 (S115), the removal work of the reinforcing member (S116), and the backfill work (S117) are repeated a predetermined number of times to perform backfill to a predetermined position. When the backfill surface reaches a predetermined position, the tightening means 20e such as a bolt for tensioning the tie rod 20c and the closed cross section steel sheet pile 18 and the pressing plate 20d are loosened to close the closed cross section steel sheet pile 18.
The pressing of the (steel material portion 21) to the socket portion 16 is released (S118). Closed-section steel sheet pile 18 with pressing force released
Is pulled out by a pulling machine (S119), and the construction work of the composite caisson 10 is completed (S120).

【0032】以上に本実施の形態における複合型ケーソ
ンについて説明してきたが、本発明はこの実施の形態に
限定されるものではなく、発明の要旨を変更しない範囲
において各種の改変をしても本発明の技術的範囲に属す
るのはいうまでもない。例えば、本実施の形態において
は、コンクリート躯体部分14のコンクリートを現場打
ちにより形成しているが、工場生産されたコンクリート
製品を組み立てる形態としても良い。なお、この形態に
おいては、工場生産されたコンクリート製品の継ぎ目に
シール部材を配設し、継ぎ目部分からの水の浸入を防止
する処理をすることが必要になる。また、ニューマチッ
クケーソンの上端面に鋼材部21を採用することも可能
であるのはもちろんである。
Although the composite caisson in the present embodiment has been described above, the present invention is not limited to this embodiment, and the present invention can be made even if various modifications are made without changing the gist of the invention. It goes without saying that it belongs to the technical scope of the invention. For example, in this embodiment, the concrete of the concrete skeleton portion 14 is formed by in-situ casting, but a concrete product manufactured at a factory may be assembled. In this embodiment, it is necessary to dispose a seal member at the joint of the concrete product produced at the factory and perform a treatment to prevent water from entering from the joint. Further, it goes without saying that the steel material portion 21 can be adopted on the upper end surface of the pneumatic caisson.

【0033】[0033]

【発明の効果】本発明を採用することにより、以下に示
す効果を得ることができる。具体的には、コンクリート
ケーソンと鋼材部を有する複合型ケーソンにおいて、使
用する鋼矢板を閉断面鋼矢板とし、コンクリートケーソ
ンに抜脱自在に連結したことにより、掘削作業中におい
ては鋼材部(仮壁)を強固に接合可能にし、鋼材部(仮
壁)を撤去する際においては安全に容易に、しかも確実
に鋼材部の撤去をすることができる。
The following effects can be obtained by adopting the present invention. Specifically, in a composite caisson with a concrete caisson and a steel material part, the steel sheet pile used is a steel sheet pile with a closed cross section and is detachably connected to the concrete caisson so that the steel material portion (temporary wall ) Can be firmly joined, and the steel material portion (temporary wall) can be safely and easily and reliably removed when removing the steel material portion (temporary wall).

【0034】また、ソケットが、コンクリート躯体部上
面に配設された鉄板にあらかじめ取り付けられているの
で、コンクリート躯体部に連結させる閉断面鋼矢板の位
置精度が向上すると共に、コンクリート躯体部上面に垂
直に立設させることが可能になるので、閉断面鋼矢板の
引き抜き作業をさらに容易にすることができる。
Further, the socket is on the concrete skeleton part.
Pre-attached to the iron plate placed on the surface
The position of the steel sheet pile with a closed cross section to be connected to the concrete frame.
The placement accuracy is improved and the
Since it is possible to set it upright directly,
The pulling out work can be further facilitated.

【0035】さらに、ロッドは、閉断面鋼矢板の中空部
分に挿通されていることにより、掘削作業中に誤って鋼
材部の押圧部を損傷してしまい、鋼材部が不安定になる
ことを防止することができるので、安全な作業を確実に
行うことができる。
Further, since the rod is inserted into the hollow portion of the steel sheet pile with a closed cross section, the pressing portion of the steel material portion is prevented from being accidentally damaged during excavation work, and the steel material portion is prevented from becoming unstable. Therefore, safe work can be surely performed.

【0036】また、複合型ケーソンの施工において、施
工箇所に筒状の刃口部を設置する工程と、該刃口部の上
方に、筒状のコンクリート躯体部分を形成し、刃口部内
を掘り進めて刃口部およびコンクリート躯体部分を沈下
させるコンクリート躯体部形成工程と、該コンクリート
躯体部上面に、所要間隔をおいて、下部側が前記コンク
リート躯体部に埋設され、上部側がコンクリート躯体部
上面に立設される筒状のソケット部を形成する工程と、
前記コンクリート躯体部上面からアンカーを配設する工
程と、該ソケット部が嵌入する、筒状の本体部および該
本体部の両側壁から延出され、隣接する矢板どうし間を
連結可能な連結部を有する閉断面鋼矢板を用い、各閉断
面鋼矢板の前記筒状の本体部下部内に前記ソケット部を
嵌入させ、かつ隣接する閉断面鋼矢板どうしを前記連結
部により連結して、複数の閉断面鋼矢板により、前記コ
ンクリート躯体上方に抜脱可能な筒状の鋼材部を形成す
る工程と、前記アンカーの延出部先端に接続可能なカプ
ラを設けたロッド部を接続する工程と、前記ロッド部
に、前記鋼材部の上面に当接可能な押圧板を配設し、前
記ロッド部に押圧ボルトを螺合して、該押圧ボルトによ
り、前記押圧板を介して前記鋼材部を前記コンクリート
躯体部に押圧する工程を含むことにより、掘削作業中に
おいては鋼材部(仮壁)を強固に接合可能にし、鋼材部
(仮壁)を撤去する際においては安全に容易に、しかも
確実に鋼材部の撤去をすることができる。
Further, in the construction of the composite caisson, a step of installing a tubular blade mouth portion at a construction site, and forming a tubular concrete skeleton portion above the blade mouth portion, and excavating the inside of the blade mouth portion. The concrete skeleton part forming step of further advancing the blade mouth part and the concrete skeleton part, and at the upper surface of the concrete skeleton part with a required interval , the lower side is the concrete
It is embedded in the REIT skeleton and the upper side is the concrete skeleton
A step of forming a cylindrical socket portion standing on the upper surface ,
A process of arranging anchors from the top surface of the concrete skeleton
And a closed cross-section steel sheet pile having a tubular main body portion into which the socket portion is fitted and extending from both side walls of the main body portion and having a connecting portion capable of connecting between adjacent sheet piles. The socket portion is inserted into the lower portion of the tubular main body portion of the steel sheet pile, and adjacent closed cross section steel sheet piles are connected by the connecting portion, and the plurality of closed cross section steel sheet piles are pulled out above the concrete skeleton. And a cap that can be connected to the tip of the extension part of the anchor.
And a step of connecting the rod portion provided with
A pressure plate that can contact the upper surface of the steel material
A pressure bolt is screwed onto the rod part,
The steel material through the pressing plate to the concrete
By including the step of pressing on the body part, the steel material part (temporary wall) can be firmly joined during excavation work, and when removing the steel material part (temporary wall), the steel material can be safely and easily and reliably Part can be removed.

【0037】また、ソケット部を形成する工程におい
て、コンクリート躯体部上面には板材が配設され、ま
た、板材にあらかじめソケット部を取り付けていること
により、閉断面鋼矢板の設置位置の精度を正確にするこ
とができ、閉断面鋼矢板をコンクリート躯体の上面に垂
直に立設することができると共に、ソケット部からの水
の浸入を防ぐこともできる。また、鋼矢板どうしの連結
部に無理な力が作用しないので、閉断面鋼矢板の引き抜
き作業も容易になる等といった著効を奏する。
Further, in the step of forming the socket portion, a plate material is provided on the upper surface of the concrete skeleton portion, and the socket portion is previously attached to the plate material .
Accordingly, it is possible to accurately accuracy of the installation position of the closed section sheet piles, with a closed section sheet piles can be erected vertically to the top surface of the concrete skeleton, also prevent ingress of water from the socket part it can. Also, because unreasonable force does not act on the joint between steel sheet piles, pulling out steel sheet piles with closed cross sections
It has a remarkable effect such as easy work.

【図面の簡単な説明】[Brief description of drawings]

【図1】 本実施の形態における複合型ケーソンの正面
図である。
FIG. 1 is a front view of a composite caisson according to the present embodiment.

【図2】 本実施の形態における複合型ケーソンの平面
図である。
FIG. 2 is a plan view of the composite caisson according to the present embodiment.

【図3】 コンクリート躯体最上端部の拡大説明図であ
る。
FIG. 3 is an enlarged explanatory view of the uppermost end of the concrete skeleton.

【図4】 本実施の形態に用いる閉断面鋼矢板の断面図
である。
FIG. 4 is a cross-sectional view of a closed section steel sheet pile used in the present embodiment.

【図5】 本実施の形態における作業工程の概略を示す
フロー図である。
FIG. 5 is a flowchart showing an outline of a work process in the present embodiment.

【図6】 従来技術の一例を示す説明図である。FIG. 6 is an explanatory diagram showing an example of a conventional technique.

【符号の説明】[Explanation of symbols]

10 複合型ケーソン 12 刃口部分 14 コンクリート躯体 16 ソケット部 18 閉断面鋼矢板 20 押圧手段 20a アンカー鉄筋 20b カプラ 20c タイロッド 20d 押圧板 50 鉄板 10 composite caisson 12 Blade part 14 Concrete frame 16 Socket 18 Closed-section steel sheet pile 20 Pressing means 20a anchor rebar 20b coupler 20c tie rod 20d pressing plate 50 iron plate

フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 23/06 E02D 5/16 E02D 23/08 Front page continued (58) Fields surveyed (Int.Cl. 7 , DB name) E02D 23/06 E02D 5/16 E02D 23/08

Claims (5)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 筒状をなす刃口部と、該刃口部に連続し
て刃口部の上方に設けられた筒状をなすコンクリート躯
体部と、鋼材からなる矢板が複数連結されて筒状に形成
され、前記コンクリート躯体部の上方に設けられた、除
去可能な鋼材部とを有する複合型ケーソン構造におい
て、 前記コンクリート躯体部の上面に、所定間隔をおいて
下部側が前記コンクリート躯体部に埋設され、上部側が
コンクリート躯体部上端面から突出する筒状のソケット
部が設けられ、 前記矢板に、該ソケット部が嵌入する筒状の本体部と、
該本体部の両側壁から延出され、隣接する矢板どうし間
を連結可能な連結部とを有する閉断面鋼矢板が用いられ
て、各閉断面鋼矢板の前記筒状の本体部下部内に前記ソ
ケット部が抜脱可能に嵌入されると共に、各閉断面鋼矢
板が前記連結部により隣接するものどうし連結されて前
記鋼材部が形成され、 前記コンクリート躯体部上面には、前記閉断面鋼矢板が
当接するシール部材が設けられていると共に、 前記コンクリート躯体部上端面から延出するアンカー
と、 該アンカーの延出部先端に接続可能なカプラを設けたロ
ッド部と、 該ロッド部上部に配設され、前記鋼材部の上面に当接可
能な押圧板と、 前記ロッド部に接続され、前記押圧板を介して前記鋼材
部が前記コンクリート躯体部に押圧する押圧ボルトとを
有する押圧手段により、前記閉断面鋼矢板が前記コンク
リート躯体部に押圧されている ことを特徴とする複合型
ケーソン構造。
1. A cylinder comprising a tubular blade mouth portion, a tubular concrete skeleton portion continuously provided to the blade mouth portion and provided above the blade mouth portion, and a plurality of sheet piles made of steel. Formed in a shape, provided above the concrete skeleton portion, in the composite caisson structure having a removable steel material portion, on the upper surface of the concrete skeleton portion, at a predetermined interval ,
The lower side is embedded in the concrete body part, and the upper side is
A cylindrical socket portion protruding from the upper end surface of the concrete skeleton portion is provided, and in the sheet pile, a cylindrical main body portion into which the socket portion is fitted,
A closed cross section steel sheet pile having a connecting portion extending from both side walls of the main body section and having a connection section capable of connecting adjacent sheet piles is used , and the socket is provided in the lower portion of the tubular main body section of each closed cross section steel sheet pile. While the parts are removably fitted, the closed cross section steel sheet piles are connected to each other by the connection section so that the steel material sections are formed, and the closed cross section steel sheet pile is formed on the upper surface of the concrete skeleton section.
An anchor that is provided with a sealing member that abuts and that extends from the upper end surface of the concrete skeleton part
And a coupler that is connectable to the tip of the extension of the anchor.
It is placed on the head part and the upper part of the rod part , and can contact the upper surface of the steel part.
Functioning pressure plate and the steel material connected to the rod portion through the pressure plate.
Part and a pressing bolt that presses against the concrete body part
The pressing means having the closed cross section steel sheet pile
Composite caisson structure characterized by being pressed against the rib body .
【請求項2】 前記ソケット部は、前記コンクリート躯
体部上面に配設された鉄板にあらかじめ取り付けられて
いることを特徴とする請求項1記載の複合型ケーソン構
造。
2. The socket portion is the concrete frame.
Pre-installed on the iron plate placed on the top of the body
The composite caisson structure according to claim 1, characterized in that
Structure.
【請求項3】 前記ロッド部は、 前記閉断面鋼矢板の中空部分に挿通されていることを特
徴とする請求項1または2に記載の複合型ケーソン構
造。
3. The composite caisson structure according to claim 1, wherein the rod portion is inserted into a hollow portion of the steel sheet pile with a closed cross section.
【請求項4】 施工箇所に筒状の刃口部を設置する工程
と、 該刃口部の上方に、筒状のコンクリート躯体部分を形成
し、刃口部内を掘り進めて刃口部およびコンクリート躯
体部分を沈下させるコンクリート躯体部形成工程と、 該コンクリート躯体部上面に、所要間隔をおいて、下部
側が前記コンクリート躯体部に埋設され、上部側がコン
クリート躯体部上端面から突出する筒状のソケット部を
形成する工程と、前記コンクリート躯体部上端面から延出するアンカーを
配設する工程と、 該ソケット部が嵌入する、筒状の本体部および該本体部
の両側壁から延出され、隣接する矢板どうし間を連結可
能な連結部を有する閉断面鋼矢板を用い、各閉断面鋼矢
の前記筒状の本体部下部内に前記ソケット部を嵌入さ
せ、かつ隣接する閉断面鋼矢板どうしを前記連結部によ
り連結して、複数の閉断面鋼矢板により、前記コンクリ
ート躯体上方に抜脱可能な筒状の鋼材部を形成する工程
前記アンカーの延出部先端に接続可能なカプラを設けた
ロッド部を接続する工程と、 前記ロッド部に、前記鋼材部の上面に当接可能な押圧板
を配設し、前記ロッド部に押圧ボルトを螺合して、該押
圧ボルトにより、前記押圧板を介して前記鋼材部を前記
コンクリート躯体部に押圧する工程 を含むことを特徴と
する複合型ケーソンの構築方法。
4. A step of installing a tubular blade mouth portion at a construction site, and a tubular concrete skeleton portion is formed above the blade mouth portion, and the inside of the blade mouth portion is dug to advance the blade mouth portion and the concrete. A concrete skeleton part forming step of sinking the skeleton part, and a lower part at a predetermined interval on the upper surface of the concrete skeleton part.
Side is embedded in the concrete skeleton, and the upper side is
A step of forming a cylindrical socket portion projecting from the upper end surface of the cleat body portion ; and an anchor extending from the concrete body portion upper end surface.
The step of disposing, the socket portion is fitted, using a tubular cross-section steel sheet pile extending from both side walls of the main body portion and the main body portion, having a connecting portion capable of connecting between adjacent sheet piles, The socket portion is fitted into the lower portion of the tubular main body portion of each closed cross section steel sheet pile, and adjacent closed cross section steel sheet piles are connected by the connecting portion, and the plurality of closed cross section steel sheet piles allow the concrete skeleton to move upward. forming a steel material portion of the pulled out possible cylindrically, provided coupler that can be connected to the extending tip of the anchor
A step of connecting the rod portion, and a pressing plate capable of contacting the upper surface of the steel material portion with the rod portion
Is installed, and a pressing bolt is screwed onto the rod part to
With the pressure bolt, the steel material portion is
A method of constructing a composite caisson, comprising the step of pressing against a concrete skeleton .
【請求項5】 前記ソケット部を形成する工程におい
て、前記コンクリート躯体部分の上面に鉄板を水平に配
設し、当該ソケット部を前記閉断面鋼矢板に嵌入する際
に、当該閉断面鋼矢板が、前記鉄板に当接する位置にあ
らかじめシール部材を配設しておくことを特徴とする請
求項4記載の複合型ケーソンの構築方法。
5. In the step of forming the socket portion, an iron plate is horizontally disposed on the upper surface of the concrete skeleton portion, and when the socket portion is fitted into the closed section steel sheet pile, the closed section steel sheet pile is 5. The method for constructing a composite caisson as set forth in claim 4, wherein a seal member is arranged in advance at a position where it abuts on the iron plate.
JP2002378781A 2002-12-27 2002-12-27 Composite caisson structure and method of constructing composite caisson Expired - Fee Related JP3459917B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2002378781A JP3459917B1 (en) 2002-12-27 2002-12-27 Composite caisson structure and method of constructing composite caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2002378781A JP3459917B1 (en) 2002-12-27 2002-12-27 Composite caisson structure and method of constructing composite caisson

Publications (2)

Publication Number Publication Date
JP3459917B1 true JP3459917B1 (en) 2003-10-27
JP2004211302A JP2004211302A (en) 2004-07-29

Family

ID=29398074

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2002378781A Expired - Fee Related JP3459917B1 (en) 2002-12-27 2002-12-27 Composite caisson structure and method of constructing composite caisson

Country Status (1)

Country Link
JP (1) JP3459917B1 (en)

Also Published As

Publication number Publication date
JP2004211302A (en) 2004-07-29

Similar Documents

Publication Publication Date Title
KR101302743B1 (en) Phc pile and its using the same soil cement wall construction methode
KR101696916B1 (en) Construction method of permanent wall with retaining wall combined PHC pile and steel pipe
JP5308116B2 (en) How to build a tunnel
JP6762800B2 (en) Reinforcement method and structure of existing pile foundation
KR100884289B1 (en) Composite type steel temporary construction and construction method thereof
JP2010090608A (en) Method for constructing underground space and structure of the underground space
JP4881555B2 (en) Construction method of underground structure
KR101840226B1 (en) The guide holes of the form for soil auger dredges
JP3625892B2 (en) Construction method of underground structure using precast concrete column
KR101571648B1 (en) Retaining wall construction method using precast pile attached wale supporting member
JP2005120663A (en) Structure of earth retaining wall
KR101893658B1 (en) Apparatus for a mold for joint part between case in place uper end of pile and rear bridge for monopile construnction
JPH11303087A (en) Retaining wall using corrosion-resistant structure anchor
JP5480744B2 (en) Foundation for structure and its construction method
KR101974826B1 (en) The Precast Pile Having Interlocking Secant and The Earth Retaining Wall Method Constructed by It's Continuous Pile
KR100862387B1 (en) Tensional kit for top-down constructing of acupressure lasting anchor and top-down constructing method of acupressure lasting anchor using this
JP3459917B1 (en) Composite caisson structure and method of constructing composite caisson
KR101818428B1 (en) Filler for forming mating surface of concrete pile and construction method of concrete pile using the same
JP6006004B2 (en) Pile head space formation auxiliary tool, hollow ready-made pile provided with the same, pile head processing method using the hollow ready-made pile, and pile head space forming method
KR101545713B1 (en) Composite type cutoff wall of steel temporary facility and construction method of the same
JP4349708B2 (en) Structural underground wall and its construction method
KR101069706B1 (en) Method for constructing structure for forming underground tunnel on boundary of rock bed
KR100802164B1 (en) Structure for reinforcing steel pile head of footing foundation structure
JP2741387B2 (en) Construction manhole construction method
JP3790310B2 (en) Construction method of the building by the prior construction of steel frame

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120808

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130808

Year of fee payment: 10

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees