JP3076898B2 - Slope greening method - Google Patents

Slope greening method

Info

Publication number
JP3076898B2
JP3076898B2 JP08354960A JP35496096A JP3076898B2 JP 3076898 B2 JP3076898 B2 JP 3076898B2 JP 08354960 A JP08354960 A JP 08354960A JP 35496096 A JP35496096 A JP 35496096A JP 3076898 B2 JP3076898 B2 JP 3076898B2
Authority
JP
Japan
Prior art keywords
slope
vegetation base
base material
aggregate
partition
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP08354960A
Other languages
Japanese (ja)
Other versions
JPH10183629A (en
Inventor
裕司 中野
Original Assignee
ライト工業株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ライト工業株式会社 filed Critical ライト工業株式会社
Priority to JP08354960A priority Critical patent/JP3076898B2/en
Publication of JPH10183629A publication Critical patent/JPH10183629A/en
Application granted granted Critical
Publication of JP3076898B2 publication Critical patent/JP3076898B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】 本発明は、法面の緑化工法に
関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a slope greening method.

【0002】[0002]

【従来技術】法面の修景を目的とした各種の緑化工法が
注目されている。なかでも建設副産物および産業廃棄物
などの廃棄物再生資材の有効利用のため、再生アスファ
ルトなどの骨材を混入させた植生基盤材による植生基盤
の造成が試みられている。
2. Description of the Related Art Attention has been paid to various greening methods for the purpose of improving the slope. Above all, in order to effectively utilize waste by-products such as construction by-products and industrial waste, attempts have been made to create a vegetation base using vegetation base materials mixed with aggregates such as recycled asphalt.

【0003】[0003]

【発明が解決しようとする課題】前述した骨材を含む植
生基盤材は、法面への吹付時に骨材のリバウンドロスが
非常に多い。具体的には、リバウンドロスにより骨材が
法面の所望する位置に思うように定着せず、ほとんど法
面の下方に落下してしまい、細粒分のみが付着し密実な
植生基盤が造成されてしまうため、骨材を混入した意味
が半減してしまう。しかも、落下して法面の下方に堆積
した骨材は、別途の撤去作業が必要となり、緑化作業が
非常に煩雑となる。またリバウンドロスは、法面下部や
凹部に集積し、部分的に空隙が多い箇所ができ、保水性
に欠けるため植生植物の発芽・生育が不良となる。さら
に密実に造成された植生基盤は、土壌が硬質でしまった
均一構造となり根系発達が抑制されるため、植生植物の
根付きなども遅く、緑化・被覆が遅れる。また、骨材を
多く含んだ植生基盤材はリバウンドロスが多く、充分な
吹付け厚を確保するには経済的に効率が悪い。従来から
使用されている有機質系の植生基盤材により植生基盤を
造成した場合、植生基盤が物理的に均一構造となるた
め、このような植生基盤では単純植生となり易く、生育
特性の異なる植生植物が共生できない。
The vegetation base material containing the above-mentioned aggregate has a large amount of rebound loss of the aggregate when sprayed on a slope. Specifically, the rebound dross does not allow the aggregate to settle at the desired position on the slope, but almost falls below the slope, leaving only the fine particles attached and creating a solid vegetation base. Therefore, the meaning of mixing the aggregate is reduced by half. In addition, the aggregate that has fallen and deposited below the slope requires a separate removal operation, which makes the greening operation very complicated. In addition, rebound dross accumulates in the lower part of the slope or in the depressions, and places where there are many voids are formed. Further, the densely formed vegetation base has a uniform structure in which the soil is hard and has a suppressed root system development, so that the rooting of vegetation plants is slow, and the greening and covering are delayed. In addition, vegetation base materials containing a large amount of aggregate have a large amount of rebound loss, and it is economically inefficient to secure a sufficient spray thickness. When a vegetation base is formed using organic vegetation base materials that have been used in the past, the vegetation base has a physically uniform structure. We cannot live together.

【0004】本発明は以上の点に鑑みて成されたもの
で、その目的とするところは、植生基盤材の吹付時の骨
材のリバウンドロスを有効利用し、骨材の集積部と植生
基盤材の集積部を植生基盤中に混在させることにより自
然土壌に近い構造とし、生育特性の異なる植生植物のそ
れぞれの生育に適した環境を法面上に造成する、法面緑
化工法および植生基盤を提供することにある。
The present invention has been made in view of the above points, and an object of the present invention is to make effective use of the rebound dross of the aggregate at the time of spraying the vegetation base material so that the aggregate portion of the aggregate and the vegetation base can be used. The slope revegetation method and the vegetation base that create a structure suitable for the growth of each vegetation with different growth characteristics on the slope by creating a structure close to natural soil by mixing the accumulation part of the timber in the vegetation base. To provide.

【0005】[0005]

【問題を解決するための手段】本発明は、植生基盤材を
吹き付けて法面上に植生基盤を形成して行う法面の緑化
工法において、通水性の仕切片を法面に設置した後、骨
材を含む植生基盤材を吹き付け、法面下方側へ向けて前
記骨材の層厚が漸増するように、前記仕切片の上流側で
骨材を集積して保持させながら、植生基盤の層厚を略均
一に造成することを特徴とする、法面緑化工法である。
本発明は、植生基盤材を吹き付けて法面上に植生基盤を
形成して行う法面の緑化工法において、複数の植生基盤
材単位仕切区画を形成する通水性の仕切片を法面に設置
した後、骨材を含む植生基盤材を前記植生基盤材単位仕
切区画に吹き付け、法面下方側へ向けて前記骨材の層厚
が漸増するように、前記植生基盤材単位仕切区画の上流
側で骨材を集積して保持させながら、植生基盤の層厚を
略均一に造成することを特徴とする、法面緑化工法であ
る。また本発明は、前記した法面緑化工法において、骨
材としては再生アスファルト、再生コンクリート、再生
プラスチックなどの廃棄物再生資材を用いたことを特徴
とする、法面緑化工法である。さらに本発明は、前記し
たいずれかの法面緑化工法において、骨材を含む植生基
盤材を、仕切片の上部側を露出させた状態で吹き付けた
後、前記植生基盤材上に有機質基盤材などの異なる性質
の基盤材を吹き付けたことを特徴とする、法面緑化工法
である。
SUMMARY OF THE INVENTION The present invention relates to a slope greening method in which a vegetation base material is sprayed to form a vegetation base on a slope, and a water-permeable partition piece is set on the slope, While spraying a vegetation base material containing aggregate and accumulating and holding the aggregate on the upstream side of the partition pieces so that the thickness of the aggregate gradually increases toward the lower side of the slope, the layer of the vegetation base is This is a slope greening method characterized in that the thickness is formed substantially uniformly.
According to the present invention, in a slope greening method performed by spraying a vegetation base material to form a vegetation base on a slope, a water-permeable partition piece that forms a plurality of vegetation base material unit partition sections is installed on the slope. after spraying the vegetation base material containing aggregate to the vegetation base Zaitan position compartments, as the layer thickness of the aggregate toward the slopes downward gradually increases, upstream of the vegetation base material units compartments A method of revegetation on a slope, characterized in that a layer thickness of a vegetation base is formed substantially uniformly while accumulating and holding aggregates. Further, the present invention is a slope revegetation method characterized in that in the above-described slope revegetation method, a waste recycle material such as reclaimed asphalt, recycle concrete, or recycle plastic is used as an aggregate. Further, according to the present invention, in any one of the above-described slope revegetation methods, after spraying a vegetation base material containing aggregate in a state where an upper side of a partition piece is exposed, an organic base material or the like is placed on the vegetation base material. This is a slope revegetation method characterized by spraying base materials of different properties.

【0006】[0006]

【発明の実施の形態1】以下図面を参照しながら本発明
の植生基盤について説明する。
First Embodiment A vegetation base of the present invention will be described below with reference to the drawings.

【0007】<イ>全体の構成 植生基盤1は、仕切片2と、植生基盤材3と、前記植生
基盤1中に包含する骨材4とより構成する。
<A> Overall Structure The vegetation base 1 is composed of a partition 2, a vegetation base material 3, and an aggregate 4 contained in the vegetation base 1.

【0008】<ロ>仕切片 仕切片は、基礎工として法面5に敷設する通水性を有す
る部材である。仕切片は、基本的には法面5に吹き付け
た植生基盤材3中に含まれる骨材4が保持・集積できる
構造であればよい。従って仕切片としては、法面の鉛直
方向に法面に対して垂直に立設できる直線状、略弧状、
円形、略V字型、波状、略コ字型などあらゆる形状の板
状部材を採用することが考えられる。仕切片の素材とし
ては、網体や、有孔板や、布などの通水性を有する公知
素材を用いることが考えられ、例えばポリエチレンなど
を用いることが考えられる。本実施の形態においては、
図2に示すように複数の仕切片2に囲まれた複数の植生
基盤材単位仕切区画21(以下仕切区画21とする)を
形成する一例について開示してある。仕切片2に囲まれ
た仕切区画2の平面形状は、菱形、六角形、円形など公
知形状とすることが考えられ、その高さhについても現
場状況などにより任意に変更が可能である。仕切片2の
高さhの一般的な数値としては、最大値10.0cm程
度、最小値0.5cm程度が考えられ、本発明において
は0.5〜3.0cmの範囲が好適である。また仕切区
画21の開口寸法は、5.0cm〜100.0cm程度
とすることが考えら、10.0cm〜50.0cmの範
囲が好適である。
<B> Partition Piece The partition piece is a water-permeable member laid on the slope 5 as a foundation work. The partition piece may basically have a structure capable of holding and accumulating the aggregate 4 contained in the vegetation base material 3 sprayed on the slope 5. Therefore, as a partition piece, a linear shape, a substantially arc shape, which can be erected perpendicularly to the slope in the vertical direction of the slope,
It is conceivable to employ a plate-like member of any shape such as a circle, a substantially V-shape, a wavy shape, and a substantially U-shape. As a material of the partition piece, a known material having water permeability such as a net, a perforated plate, or a cloth may be used. For example, polyethylene may be used. In the present embodiment,
An example of forming a plurality of vegetation base material unit partition sections 21 (hereinafter, referred to as partition sections 21) surrounded by a plurality of partition pieces 2 as shown in FIG. 2 is disclosed. The planar shape of the partition section 2 surrounded by the partition pieces 2 may be a known shape such as a rhombus, a hexagon, and a circle, and the height h thereof can be arbitrarily changed depending on site conditions and the like. Typical numerical values of the height h of the partition 2 may be a maximum value of about 10.0 cm and a minimum value of about 0.5 cm. In the present invention, a range of 0.5 to 3.0 cm is preferable. Further, considering that the opening dimension of the partitioning section 21 may be about 5.0 cm to 100.0 cm, a range of 10.0 cm to 50.0 cm is preferable.

【0009】<ハ>植生基盤材 植生基盤材3は、公知の基盤材を採用することが可能で
ある。即ち植生基盤材3としては、土壌改良材、粘結
剤、肥料、種子などの公知材料を主体としている。本発
明の緑化工法においては、前述した植生基盤材3に後述
する骨材4を加えたものを法面に吹付けて、植生基盤1
を造成する。
<C> Vegetation base material As the vegetation base material 3, a known base material can be adopted. That is, the vegetation base material 3 is mainly composed of known materials such as soil improvement materials, binders, fertilizers, and seeds. In the revegetation method of the present invention, the vegetation base 1 is sprayed with the above-mentioned vegetation base 3 and the aggregate 4 described later added to the slope.
Create

【0010】<ニ>骨材 骨材4としては、建設副産物、産業廃棄物、または一般
廃棄物から製造する再生アスファルト、再生コンクリー
ト、再生プラスチックなどの廃棄物再生資材を使用す
る。前述した骨材4は、所定粒度に調整して用いること
が肝要である。骨材4の粒度は、5.0mm〜15.0
mm程度であることが好ましいが、これ以上であっても
よい。なお骨材4は、天然骨材や人工骨材であっても良
いことは勿論である。
<4> Aggregate As the aggregate 4, waste materials such as recycled asphalt, recycled concrete, and recycled plastic produced from construction by-products, industrial waste, or general waste are used. It is important that the above-mentioned aggregate 4 is adjusted to a predetermined particle size before use. The particle size of the aggregate 4 is 5.0 mm to 15.0.
It is preferably about mm, but may be more. It is needless to say that the aggregate 4 may be a natural aggregate or an artificial aggregate.

【0011】[0011]

【施工方法】以下図面を参照に法面緑化工法について説
明する。
[Construction method] The slope greening method will be described below with reference to the drawings.

【0012】<イ>仕切片の設置工程 緑化を図る法面5に植生基盤1を造成するための基礎工
として、先ず法面5に仕切片2を設置する。法面5に設
置した仕切片2は、図2に示すように複数の植生基盤材
単位仕切区画21(以下仕切区画21とする)を形成す
る。仕切片2は、法面5の鉛直方向に立設し、アンカー
ピン(図示せず)などにより法面5にしっかりと定着さ
せ、ずれ落ちのないように設置する。この際、仕切片2
を可撓性の網体で構成すれば、法面5の起伏に沿って被
覆させることが可能である。なお、図2に示すような複
数の仕切片2を予め組合わせて仕切区画21群を形成し
たものを法面5に敷設することも勿論可能である。
<A> Partitioning Step of Partitioning As a foundation work for forming the vegetation base 1 on the slope 5 for greening, first, the partitioning piece 2 is set on the slope 5. The partition pieces 2 installed on the slope 5 form a plurality of vegetation base material unit partition sections 21 (hereinafter, referred to as partition sections 21) as shown in FIG. The partition piece 2 is erected in the vertical direction of the slope 5 and is firmly fixed to the slope 5 by an anchor pin (not shown) or the like, and is installed so as not to slip off. At this time, partition 2
If is formed of a flexible net, it is possible to cover along the undulation of the slope 5. In addition, it is of course possible to lay a group of partitions 21 formed by combining a plurality of partition pieces 2 as shown in FIG.

【0013】<ロ>植生基盤材の吹付工程 続いて図1に示すように、仕切片2を設置した法面5に
植生基盤材3を吹付ける。植生基盤材3は、貯槽に収容
した骨材4、土壌改良材、粘結剤、肥料、種子などの所
定量を吹付機6に投入し、吹付機6からホース61を通
じて吹付ノズル62へ圧送させる。この場合、植生基盤
材3は圧送元で加水する湿式、または吹付ノズルで加水
する乾式のいずれであってもよい。法面5に植生基盤材
3を吹付けると、植生基盤材3に含まれる骨材4が法面
2に当たりリバウンドする。リバウンドした骨材4は、
法面5を覆う仕切片2により形成した各仕切区画21に
引っ掛かって集積される。この際、骨材4は植生基盤材
3の構成物中で最重量物であるから、図3に示すように
法面5の下方側に特に集まる。このことから、図3に示
すように骨材4のリバウンドを利用することで、仕切片
2により形成した各仕切区画21内において、法面5を
被覆する薄い骨材層41と、法面5の下方側に多く溜っ
た厚い骨材層42をそれぞれに有する植生基盤1を造成
できる。この際、骨材4の集積した部分には多数の空隙
が形成されるが、その他の部分には植生基盤材3が充填
されるため、同じ仕切区画21内に骨材4の集積した乾
燥部分と、植生基盤材3が集積した保水部分が形成され
る。この乾燥部分と保水部分を有する多数の仕切区画2
1が組み合わさることにより、植生基盤1の構造が複雑
性のある自然土壌に近い構造となる。この後、植生基盤
材3により造成した植生基盤1の上面に、公知の有機質
基盤材(図示せず)を吹付けることも考えられる。有機
質基盤材としては、例えばバーク、ピートモス、家畜
糞、下水汚泥などを充分に発酵成熟させたコンポスト堆
肥を主材とするものを用いることが考えられる。
<B> Spraying step of vegetation base material Subsequently, as shown in FIG. 1, the vegetation base material 3 is sprayed on the slope 5 on which the partition pieces 2 are installed. The vegetation base material 3 is such that a predetermined amount of the aggregate 4, the soil improving material, the binder, the fertilizer, the seeds and the like stored in the storage tank is charged into the spraying machine 6, and is fed from the spraying machine 6 to the spraying nozzle 62 through the hose 61. . In this case, the vegetation base material 3 may be either a wet type in which water is added at a pressure feeding source or a dry type in which water is added by a spray nozzle. When the vegetation base material 3 is sprayed on the slope 5, the aggregate 4 contained in the vegetation base material 3 hits the slope 2 and rebounds. The rebound aggregate 4
Each of the partition sections 21 formed by the partition pieces 2 covering the slope 5 is hooked and accumulated. At this time, since the aggregate 4 is the heaviest in the composition of the vegetation base material 3, it aggregates particularly below the slope 5 as shown in FIG. From this, by using the rebound of the aggregate 4 as shown in FIG. 3, the thin aggregate layer 41 covering the slope 5 and the slope 5 A vegetation base 1 having a thick aggregate layer 42 that has accumulated a lot on the lower side of the vegetation can be formed. At this time, a large number of voids are formed in the portion where the aggregate 4 is accumulated, but the other portion is filled with the vegetation base material 3, so that the dried portion where the aggregate 4 is accumulated in the same partition section 21. Then, a water retaining portion where the vegetation base material 3 is accumulated is formed. A large number of partition sections 2 having the drying section and the water holding section
By combining them, the structure of the vegetation base 1 becomes a structure close to a complex natural soil. Thereafter, a known organic base material (not shown) may be sprayed on the upper surface of the vegetation base 1 formed by the vegetation base material 3. As the organic base material, for example, a material mainly composed of compost compost obtained by sufficiently fermenting and maturating bark, peat moss, livestock dung, sewage sludge, and the like can be used.

【0014】[0014]

【発明の実施の形態2】前述した実施の形態1に開示し
た法面緑化工法に対し、図4に示すように二層構造の植
生基盤を造成することも考えられる。この場合の緑化手
順は、以下の通りである。 <イ>先ず、実施の形態1で説明した仕切片2を法面5
上に敷設する。この際の仕切片2の高さとしては、例え
ば10.0cm程度など現場状況に適応する高さとする
ことが考えられる。 <ロ>前記仕切片2上より骨材4を混入した植生基盤材
3の吹き付けて下地を造成する。この際、前述したよう
に仕切片1の高さを10.0cmとした場合、植生基盤
材3の吹付け厚は、5.0cm程度とする。 <ハ>前記した5.0cm厚の植生基盤材3の層上に、
例えば苗木7、球根類の植物などを設置する。苗木7
は、骨材4の集積した位置に載置してラスピン71など
により固定する。<ニ>苗木7を設置した植生基盤材3
上に有機質基盤材8や砂質基盤材など性質の異なる基盤
材の吹付工を行う。有機質基盤材8は、植生基盤材3の
吹付け時に残った仕切片2の上部を含めた所定の厚さに
吹付けて二層構造の植生基盤9を完成する。この際、仕
切片2の露出した上部側を有機質基盤材8内に埋設した
状態とすることで、有機質基盤材8を支持させる。
Second Embodiment In contrast to the slope greening method disclosed in the first embodiment, a vegetation base having a two-layer structure as shown in FIG. 4 may be formed. The greening procedure in this case is as follows. <B> First, the partition 2 described in the first embodiment is
Lay on top. It is conceivable that the height of the partition 2 at this time is a height suitable for the on-site situation, for example, about 10.0 cm. <B> A base is formed by spraying the vegetation base material 3 mixed with the aggregate 4 from above the partition piece 2. At this time, when the height of the partition piece 1 is 10.0 cm as described above, the spray thickness of the vegetation base material 3 is about 5.0 cm. <C> On the layer of the 5.0 cm thick vegetation base material 3 described above,
For example, seedlings 7, bulbous plants, and the like are installed. Sapling 7
Is placed at the position where the aggregates 4 are accumulated and fixed with a raspin 71 or the like. <D> Vegetation base material 3 with seedlings 7
A base material having different properties such as an organic base material 8 or a sand base material is sprayed thereon. The organic base material 8 is sprayed to a predetermined thickness including the upper part of the partition 2 remaining when the vegetation base material 3 is sprayed, thereby completing the vegetation base 9 having a two-layer structure. At this time, the exposed upper side of the partition 2 is buried in the organic base material 8 to support the organic base material 8.

【0015】[0015]

【発明の効果】本発明は以上説明したようになるから次
のような効果を得ることができる。 <イ> 骨材を含む植生基盤材は、法面への吹付時の骨
材のリバウンドロスによる植生基盤の法面上および法面
の下方側に骨材を集積することができ、自然土壌に近い
複雑性のある植生基盤を造成することが可能である。 <ロ> また前記リバウンドロスにより、仕切片の仕切
区画単位の下方側に特に骨材を集積でき、また骨材が仕
切区画を亘って連続しているから、骨材群に含まれる必
要以上の水分(動水)は骨材伝いに法面の下方側へ効率
良く排水することが可能となり、大小適度の空隙を形成
することにより、植物に必要な保水性と通気性とを付与
できる。 <ハ> 骨材の集積により、植生基盤の下位には空隙が
あるため、植生植物の根はこの隙間伝いに法面に対して
立体的に伸び、広範囲に亘って根付きできるから、植生
植物の生育が良好となり、かつ吹付けた植生基盤の侵食
防止も図れる。 <ニ> 植生基盤中に骨材の集積による乾燥部分と植生
基盤材の集積による保水部分とを形成し、これを混在さ
せることにより自然土壌に近い複雑性のある構造にでき
る。これにより、生育特性の異なる多様な植生植物の組
合わせ導入が可能であり、かつ周辺からの植生遷移も順
調に行われため、緑化を実施した法面の自然回復を早急
に行うことができる。 <ホ> 仕切片により吹き付けでも植生基盤材の厚さを
充分に確保することが可能であり、苗木(植栽)の導入
も充分可能である。 <ヘ> リバウンドする骨材を有効利用できるから、吹
き付け厚を確保する場合でも経済的施工が可能である。
As described above, the present invention has the following effects. <A> The vegetation base material containing aggregate can be aggregated on the slope of the vegetation base and on the lower side of the slope due to the rebound dross of the aggregate when spraying the slope. It is possible to create a vegetation base of close complexity. <B> In addition, the rebound dross makes it possible to accumulate aggregates particularly below the partition units of the partition pieces, and since the aggregate is continuous across the partition sections, it is unnecessary to include the aggregates in the aggregate group. Moisture (hydraulic water) can be efficiently drained to the lower side of the slope along the aggregate, and by forming appropriate gaps of large and small sizes, water retention and air permeability required for plants can be imparted. <C> Due to the accumulation of aggregates, there is a gap below the vegetation base, and the roots of the vegetation grow three-dimensionally along the slope along this gap and can be rooted over a wide area. Growth is good, and erosion of the sprayed vegetation base can be prevented. <D> A dry structure formed by the accumulation of aggregates and a water retaining portion formed by the accumulation of vegetation base materials are formed in the vegetation base, and by mixing these, a complex structure close to natural soil can be obtained. As a result, it is possible to introduce a combination of various vegetation plants having different growth characteristics, and the vegetation transition from the surroundings is smoothly performed, so that the natural restoration of the slope where the greening has been performed can be promptly performed. <E> The thickness of the vegetation base material can be sufficiently secured even by spraying with the partition pieces, and the introduction of seedlings (planting) can be sufficiently performed. <F> Since rebound aggregate can be used effectively, economical construction is possible even when the spray thickness is secured.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明に係る法面緑化工法の説明図FIG. 1 is an explanatory view of a slope greening method according to the present invention.

【図2】 法面緑化工法に用いる仕切片の説明図FIG. 2 is an explanatory view of a partition used in a slope greening method.

【図3】 実施の形態1に係る植生基盤の断面図FIG. 3 is a cross-sectional view of the vegetation base according to the first embodiment.

【図4】 実施の形態2に係る植生基盤の説明図FIG. 4 is an explanatory diagram of a vegetation base according to the second embodiment.

───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 17/20 ──────────────────────────────────────────────────続 き Continued on front page (58) Field surveyed (Int.Cl. 7 , DB name) E02D 17/20

Claims (4)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 植生基盤材を吹き付けて法面上に植生
基盤を形成して行う法面の緑化工法において、 通水性の仕切片を法面に設置した後、 骨材を含む植生基盤材を吹き付け、法面下方側へ向けて前記骨材の層厚が漸増するように、
前記仕切片の上流側で骨材を集積して保持させながら、
植生基盤の層厚を略均一に造成することを特徴とする 、 法面緑化工法。
Claims 1. In a slope greening method in which a vegetation base material is sprayed to form a vegetation base on a slope, a water-permeable partition piece is installed on the slope, and then a vegetation base material including aggregate is removed. Spraying, so that the layer thickness of the aggregate gradually increases toward the lower side of the slope,
While collecting and holding aggregates on the upstream side of the partition,
A slope revegetation method, characterized in that the thickness of the vegetation base is almost uniform .
【請求項2】 植生基盤材を吹き付けて法面上に植生
基盤を形成して行う法面の緑化工法において、 複数の植生基盤材単位仕切区画を形成する通水性の仕切
片を法面に設置した後、 骨材を含む植生基盤材を前記植生基盤材単位仕切区画に
吹き付け、法面下方側へ向けて前記骨材の層厚が漸増するように、
前記植生基盤材単位仕切区画の上流側で骨材を集積して
保持させながら、植生基盤の層厚を略均一に造成するこ
とを特徴とする 、 法面緑化工法。
2. A slope revegetation method in which a vegetation base material is sprayed to form a vegetation base on a slope, and a water-permeable partition piece forming a plurality of vegetation base material unit partition sections is installed on the slope. after, as sprayed vegetation base material containing aggregate to the vegetation base Zaitan position compartments, the layer thickness of the aggregate toward the slopes downward gradually increases,
Aggregate is collected on the upstream side of the vegetation base material unit partition section.
While maintaining it, create a layer thickness of the vegetation base approximately uniform.
The slope greening method.
【請求項3】 請求項1または請求項2に記載の法面
緑化工法において、骨材としては再生アスファルト、再
生コンクリート、再生プラスチックなどの廃棄物再生資
材を用いたことを特徴とする、法面緑化工法。
3. The slope reclaiming method according to claim 1, wherein a waste material such as recycled asphalt, recycled concrete, or recycled plastic is used as the aggregate. Greening method.
【請求項4】 請求項1乃至請求項3のいずれかに記
載の法面緑化工法において、骨材を含む植生基盤材を、
仕切片の上部側を露出させた状態で吹き付けた後、前記
植生基盤材上に有機質基盤材などの異なる性質の基盤材
を吹き付けたことを特徴とする、法面緑化工法。
4. The slope greening method according to any one of claims 1 to 3, wherein the vegetation base material including the aggregate is
A slope revegetation method, characterized in that a base material having a different property such as an organic base material is sprayed on the vegetation base material after the upper surface of the partition piece is sprayed while exposing the upper side thereof.
JP08354960A 1996-12-20 1996-12-20 Slope greening method Expired - Fee Related JP3076898B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP08354960A JP3076898B2 (en) 1996-12-20 1996-12-20 Slope greening method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP08354960A JP3076898B2 (en) 1996-12-20 1996-12-20 Slope greening method

Publications (2)

Publication Number Publication Date
JPH10183629A JPH10183629A (en) 1998-07-14
JP3076898B2 true JP3076898B2 (en) 2000-08-14

Family

ID=18441053

Family Applications (1)

Application Number Title Priority Date Filing Date
JP08354960A Expired - Fee Related JP3076898B2 (en) 1996-12-20 1996-12-20 Slope greening method

Country Status (1)

Country Link
JP (1) JP3076898B2 (en)

Also Published As

Publication number Publication date
JPH10183629A (en) 1998-07-14

Similar Documents

Publication Publication Date Title
JP4883673B2 (en) Greening medium structure
KR101283514B1 (en) Restoration method based on reinforecment and organic vegetation material
JP2001115454A (en) Wall and method for protecting natural vegetation introduced slope
JP3076898B2 (en) Slope greening method
CN111484278A (en) Ecological concrete, ecological protection slope and construction method of ecological protection slope
CN113529754B (en) Granular-body slope ecological slope protection structure and construction method
CN110240280A (en) A kind of rainwater purification system of garden road greening isolation strip
JP2009121173A (en) Ground coating work and ground coating construction method
CN206928404U (en) A kind of high permeable impact-resistant eco-drainage ditch
JPH11131482A (en) Method of protecting and greening slope face with cut wood
KR101108002B1 (en) Eco-Friendly Afforestation Method
JP3452185B2 (en) Vegetation method
KR100592402B1 (en) Tree-planting construction method and it&#39;s structure
JP5827938B2 (en) Vegetation guidance method
JP3485547B2 (en) Partition material
JP2005021026A (en) Greening material and greening method using the same
JPH10306446A (en) Planting vessel for greening and greening method of concrete structure using the same
JP2987491B2 (en) Tree planting method using Futon basket
JPH1037199A (en) Greening work method for face of slope
JP2657978B2 (en) Creating a vegetation base for greening
JP2003105765A (en) Greening method for slope face
JPH11313560A (en) Plant-protecting structure
JPH08260467A (en) Base material for vegetation on earthwork structure such as side slope, and creation of vegetation bed for earthwork structure such as side slope
JPH0716022A (en) Mat-like ground-covering material and its production
JP3541655B2 (en) Plant growth base material, plant growth base and method for forming the same

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080616

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090616

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100616

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110616

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110616

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120616

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120616

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130616

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140616

Year of fee payment: 14

LAPS Cancellation because of no payment of annual fees