JP2917235B2 - Steel construction method - Google Patents

Steel construction method

Info

Publication number
JP2917235B2
JP2917235B2 JP12843591A JP12843591A JP2917235B2 JP 2917235 B2 JP2917235 B2 JP 2917235B2 JP 12843591 A JP12843591 A JP 12843591A JP 12843591 A JP12843591 A JP 12843591A JP 2917235 B2 JP2917235 B2 JP 2917235B2
Authority
JP
Japan
Prior art keywords
steel
column
work
stage
panel zone
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP12843591A
Other languages
Japanese (ja)
Other versions
JPH04330169A (en
Inventor
宮脇正信
立花賢治
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP12843591A priority Critical patent/JP2917235B2/en
Publication of JPH04330169A publication Critical patent/JPH04330169A/en
Application granted granted Critical
Publication of JP2917235B2 publication Critical patent/JP2917235B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は鉄骨鉄筋コンクリート
構造の建物の鉄骨建方工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing a steel-framed reinforced concrete structure.

【0002】[0002]

【従来の技術】鉄骨鉄筋コンクリート構造の建物は、工
場にて製造した鉄骨柱及び鉄骨梁を建築現場に搬入し、
それらをクレーンにより建込んで接続したのち、足場を
組んで鉄骨周囲の鉄筋工事などを行っている。
2. Description of the Related Art Steel-framed reinforced concrete structures carry steel columns and beams manufactured in factories to a construction site.
After building and connecting them with a crane, they are constructing scaffolds and performing rebar construction around steel frames.

【0003】[0003]

【発明が解決しようとする課題】この従来の建方工法で
は、鉄筋工事の殆どが高所作業となるため、鉄骨構造の
場合に比べて作業能率が悪く、工期も長くかかるばかり
か、品質の確保なる点からも改善が望まれている。
In this conventional construction method, since most of the reinforcing steel work is performed at a high place, the work efficiency is lower than in the case of a steel frame structure, the construction period is longer, and the quality is lower. Improvement is also desired from the point of securing.

【0004】この発明は上記従来の事情から考えられた
ものであって、その目的は、高所における作業をパネル
ゾーン部分に限定し、それにより作業能率の向上と品質
の確保をなし得る新たな鉄骨建方工法を提供することに
ある。
The present invention was conceived in view of the above-mentioned conventional circumstances, and an object of the present invention is to limit work at a high place to a panel zone portion, thereby improving work efficiency and ensuring quality. An object of the present invention is to provide a steel frame construction method.

【0005】[0005]

【課題を解決するための手段】上記目的によるこの発明
は、鉄骨柱と鉄骨梁の周囲の鉄筋工事と、その鉄骨柱に
コラムステージを各階のパネルゾーンごとに受金具を設
けて着脱自在に取付け、そのコラムステージに手摺及び
昇降梯子を取付ける工程とを地上にて行い、鉄骨柱建込
み後の鉄骨梁の取付け及びパネルゾーン部分の鉄筋工事
などのみを、鉄骨柱と共に建込んだ上記コラムステージ
上での高所作業とすることによって、従来工法の課題を
解決するものである。
SUMMARY OF THE INVENTION According to the present invention, there is provided a steel column and a steel bar surrounding a steel beam, and a column stage is provided on the steel column for each panel zone on each floor so as to be detachably mounted. The steps of installing handrails and lifting ladders on the column stage are performed on the ground, and only the installation of steel beams after the construction of the steel columns and the rebar construction of the panel zone are performed on the column stages built together with the steel columns. This solves the problems of the conventional construction method by working at a high place.

【0006】[0006]

【作 用】上記工法では、パネルゾーン部分の工事が高
所作業となるため、鉄骨柱及び鉄骨梁に対する鉄筋工事
を高所作業とする従来工法よりも、作業能率が著しく向
上する。
[Operation] In the above method, since the work in the panel zone is performed at a high place, the work efficiency is remarkably improved as compared with the conventional method in which the reinforcing work on steel columns and beams is performed at a high place.

【0007】また鉄筋工事を足元の良い地上にて行うこ
とから、品質の管理も行き届き、品質の確保が容易とな
る。
[0007] Further, since the rebar construction is performed on the ground with good feet, the quality is well controlled and the quality is easily secured.

【0008】[0008]

【実施例】先ず工場にて、H型鋼による所要階高の鉄骨
柱1の周囲に、多数の環状のフープ筋2を各階毎に挿通
する。このフープ筋2の挿通を完了した後に、各階のパ
ネルゾーンに梁接合用のガセットプレート3をドッキン
グする(図1参照)。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS First, at a factory, a number of annular hoop bars 2 are inserted for each floor around a steel column 1 of required floor height made of H-section steel. After the insertion of the hoop 2 is completed, the gusset plate 3 for beam connection is docked in the panel zone of each floor (see FIG. 1).

【0009】フープ筋2の挿通と、各階のガセットプレ
ート3のドッキングとを完了した鉄骨柱1を建築現場に
搬入し、地組場に横に配置する。
[0009] The steel column 1 in which the hoop bars 2 have been inserted and the gusset plates 3 on each floor have been docked is carried into a construction site, and placed laterally in a terrain.

【0010】地組場において、鉄骨柱1のパネルゾーン
部分にマーキングを行い、決めフープ筋2aを溶接して
から、柱周囲のフープ筋2,2aの内側四隅に、鉄骨柱
1とほぼ長さを同じくする柱筋4を挿通する。
[0010] At the ground site, marking is made on the panel zone portion of the steel column 1, the determined hoop 2 a is welded, and then the length of the steel column 1 is substantially equal to the length of the steel column 1 at the four inner corners of the hoop 2, 2 a around the column. Is inserted through the same column 4.

【0011】この柱筋4に各階のフープ筋2,2aを一
定間隔ごとに溶接して鉄筋組立を行ってから、鉄骨柱1
の各階の両フランジ側に、コラムステージの受金物5を
取付ける(図2及び図3参照)。
After the hoop bars 2 and 2a of each floor are welded to the column bars 4 at regular intervals to assemble the reinforcing bars, the steel columns 1
At each of the two flange sides of each floor, the column stage receiver 5 is attached (see FIGS. 2 and 3).

【0012】上記受金物5のボルト接合による取付けが
完了したら、各受金物5にコラムステージ6を取付け
る。このコラムステージ6は鉄骨造の建物の施工に使用
されているジュラルミン製の物をそのまま利用し、後に
取外しができるように、各受金物5に着脱自在に取付け
る(図4及び図5)。
When the mounting of the receivers 5 by the bolt connection is completed, the column stage 6 is mounted on each receiver 5. The column stage 6 uses a duralumin product used for construction of a steel-framed building as it is, and is detachably attached to each receiving object 5 so that it can be removed later (FIGS. 4 and 5).

【0013】また同一階のコラムステージ6を足場板7
により接続してから、各コラムステージ6に手摺8を取
付け、最後に片側のコラムステージ5の上下にわたり昇
降用梯子9を取付けて、鉄骨柱1に対する地組を完了す
る(図6及び図7参照)。
Further, the column stage 6 on the same floor is
After that, a handrail 8 is attached to each column stage 6, and finally a ladder 9 for raising and lowering is attached to the upper and lower sides of the column stage 5 on one side, thereby completing the formation of the steel column 1 (see FIGS. 6 and 7). ).

【0014】上記柱の地組に並行して、図は省略した
が、鉄骨梁も地組場に並べて鉄筋組立を行う。この際、
主筋の長さは梁長より50cmほど短くしておく。
In parallel with the column erection, though not shown, steel beams are also arranged on the erection site to perform rebar assembly. On this occasion,
The length of the main bar should be about 50 cm shorter than the beam length.

【0015】鉄骨柱1と鉄骨梁に対する鉄筋などの地組
が完了したら、先ず鉄骨柱1をクレーンにより吊り上げ
て、基礎柱或は先行して建込んだ下階の同様な鉄骨柱1
Aの上に建込んでジョイントする。
When the construction of the steel columns 1 and the reinforcing bars for the steel beams is completed, the steel columns 1 are first lifted by a crane, and the foundation columns or the similar steel columns 1 on the lower floor previously erected.
Build on A and join.

【0016】次にクレーンの玉外しを昇降梯子9を利用
して行ってから、同じく昇降梯子9を利用して作業員が
コラムステージ5に上がり、クレーンにより柱間に吊り
込んだ鉄骨梁10の鉄骨柱1への取付作業を行う(図8
参照)。
Next, after removing the balls of the crane using the elevating ladder 9, the worker similarly ascends to the column stage 5 using the elevating ladder 9 and removes the steel beam 10 suspended between the columns by the crane. An installation work to the steel column 1 is performed (FIG. 8)
reference).

【0017】コラムステージ上では、ガセットプレート
と梁側の両方のウエブをジョイントするハイテンション
ボルトの取付けと、フランジ相互の溶接、梁主筋の配筋
及び圧接、パネルゾーンの割りフープ筋の配筋、フープ
クリップの取付けなどの作業が行われる。
On the column stage, installation of high tension bolts for jointing the webs on both the gusset plate and the beam side, welding of flanges, reinforcement and press-welding of beam main reinforcement, reinforcement of panel zone split hoop reinforcement, Work such as attachment of a hoop clip is performed.

【0018】[0018]

【発明の効果】この発明は上述のように、鉄骨柱と鉄骨
梁の周囲の鉄筋工事を足元の良い地上にて先に行うこと
から、品質の管理も行き届き、品質の確保が容易とな
る。
As described above, according to the present invention, since the reinforce work around the steel column and the steel beam is performed first on the ground with good feet, the quality is well controlled and the quality can be easily secured.

【0019】また高所での鉄筋工事はパネルゾーンまわ
りのみとなり、これまでのような鉄筋工事のための大掛
かりな足場を組む必要がなく、パネルゾーンの作業も配
筋を先行させることができるため、作業の段取も有利に
行える。
In addition, the reinforcement work at high places is only around the panel zone, and it is not necessary to construct a large-scale scaffold for the reinforcement work as in the past, and the reinforcement in the panel zone can be preceded by the reinforcement. In addition, work setup can be advantageously performed.

【0020】さらにまた、パネルゾーンにおける鉄骨梁
の取付作業及び鉄筋工事も、地上にて鉄骨柱に取付けた
コラムステージを足場として行い、しかも昇降梯子及び
手摺が既に取付けてあるので作業を安全に能率良く行う
ことができる。
Further, the work of installing the steel beams in the panel zone and the rebar work are performed using the column stage mounted on the steel column on the ground as a scaffold, and the work is safely and efficiently performed because the elevating ladder and the handrail are already mounted. Can do well.

【0021】コラムステージを各階のパネルゾーンごと
に受金具を設けて着脱自在に取付けたので、建方を完了
した後にコラムステージとともに手摺及び昇降梯子を取
外して、他に転用できるなどの利点を有する。
Since the column stage is provided with a metal fitting for each panel zone on each floor and is removably mounted, there is an advantage that the handrail and the elevating ladder can be removed together with the column stage after the construction is completed, so that the column stage can be diverted to another. .

【図面の簡単な説明】[Brief description of the drawings]

【図1】 この発明の鉄骨建方工法における鉄骨柱とフ
ープ筋との状態を示す平面図である。
FIG. 1 is a plan view showing the state of steel columns and hoop bars in a steel frame construction method of the present invention.

【図2】 鉄骨柱に対するフープ筋の配筋とコラムステ
ージの受金具の取付状態とを示す平面図である。
FIG. 2 is a plan view showing the arrangement of hoop reinforcements on a steel column and the mounting state of a metal fitting of a column stage.

【図3】 図2のA−A断面図である。FIG. 3 is a sectional view taken along line AA of FIG. 2;

【図4】 コラムステージを取付けた状態を示す平面図
である。
FIG. 4 is a plan view showing a state where a column stage is attached.

【図5】 図4のB−B線断面図である。FIG. 5 is a sectional view taken along line BB of FIG. 4;

【図6】 手摺と昇降梯子とを取付けた状態を示す平面
図である。
FIG. 6 is a plan view showing a state where a handrail and a lifting ladder are attached.

【図7】 図6のC−C線断面図である。FIG. 7 is a sectional view taken along line CC of FIG. 6;

【図8】 建込み状態を示す立面図である。FIG. 8 is an elevational view showing an installed state.

【符号の説明】[Explanation of symbols]

1 鉄骨柱 2 フープ筋 3 ガセットプレート 4 柱筋 5 コラムステージ受金具 6 コラムステージ 8 手摺 9 昇降梯子 10 鉄筋梁 DESCRIPTION OF SYMBOLS 1 Steel column 2 Hoop bar 3 Gusset plate 4 Column bar 5 Column stage bracket 6 Column stage 8 Handrail 9 Lifting ladder 10 Reinforced beam

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 鉄骨柱と鉄骨梁の周囲の鉄筋工事と、そ
の鉄骨柱にコラムステージを各階のパネルゾーンごとに
受金具を設けて着脱自在に取付け、そのコラムステージ
に手摺及び昇降梯子を取付ける工程とを地上にて行い、
鉄骨柱建込み後の鉄骨梁の取付け及びパネルゾーン部分
の鉄筋工事等のみを、鉄骨柱と共に建込んだ上記コラム
ステージ上での高所作業とすることを特徴とする鉄骨建
方工法。
1. Reinforcing work around a steel column and a steel beam, a column stage is provided on the steel column for each panel zone of each floor, and is removably mounted. A handrail and a lifting ladder are mounted on the column stage. Process and on the ground,
A steel frame construction method in which only the installation of steel beams after the steel columns are built and the rebar work in the panel zone portion are performed at heights on the column stage built together with the steel columns.
JP12843591A 1991-05-01 1991-05-01 Steel construction method Expired - Fee Related JP2917235B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12843591A JP2917235B2 (en) 1991-05-01 1991-05-01 Steel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12843591A JP2917235B2 (en) 1991-05-01 1991-05-01 Steel construction method

Publications (2)

Publication Number Publication Date
JPH04330169A JPH04330169A (en) 1992-11-18
JP2917235B2 true JP2917235B2 (en) 1999-07-12

Family

ID=14984675

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12843591A Expired - Fee Related JP2917235B2 (en) 1991-05-01 1991-05-01 Steel construction method

Country Status (1)

Country Link
JP (1) JP2917235B2 (en)

Also Published As

Publication number Publication date
JPH04330169A (en) 1992-11-18

Similar Documents

Publication Publication Date Title
US20050066609A1 (en) Preassembled roof and floor deck panel system
JP2917235B2 (en) Steel construction method
JP3177735B2 (en) An erect scaffold used to reinforce the perimeter of existing buildings
CN209907886U (en) Adjustable assembled stair construction platform
JP2004270377A (en) Column-beam preassembled reinforcement body, and preassembled reinforcement method using the same
CN214785936U (en) Core tube structure-based auxiliary steel structure for climbing of creeping formwork
CN220908941U (en) Adjustable assembled safety stair
JP3281421B2 (en) Construction method of horizontal beam erected on tower
CN217268854U (en) Bailey truss beam formwork support system
JP3241896B2 (en) Steel frame stair hang down method
JP3234442B2 (en) Building and scrap type building method
CN109577632B (en) Suspended scaffold and construction method thereof
JP3262600B2 (en) Construction method of concrete main tower and cross beam
JP3364426B2 (en) How to build pillars
JPH07166539A (en) Construction method for steel framed reinforced concrete continuous underground wall
JPS6137426B2 (en)
JPH10339042A (en) Working platform for riding and construction method therefor
JPH0881918A (en) Pipe and construction method thereof
JP2000226187A (en) Installation method of tower crane
JP2792806B2 (en) Construction method and capital piece of steel frame house
JP3236092B2 (en) Steel frame reinforced concrete reverse driving method
JP2023075789A (en) Temporary bridge and construction method of temporary bridge
JPH06287998A (en) Constructing method for preliminary assembling of reinforced concrete composite beam
JP3240270B2 (en) Scaffold assembling method and scaffolding device
JPH1113141A (en) Constructing method of composite structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees