JP3241896B2 - Steel frame stair hang down method - Google Patents

Steel frame stair hang down method

Info

Publication number
JP3241896B2
JP3241896B2 JP24627793A JP24627793A JP3241896B2 JP 3241896 B2 JP3241896 B2 JP 3241896B2 JP 24627793 A JP24627793 A JP 24627793A JP 24627793 A JP24627793 A JP 24627793A JP 3241896 B2 JP3241896 B2 JP 3241896B2
Authority
JP
Japan
Prior art keywords
floor
steel
basement
staircase
root cutting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP24627793A
Other languages
Japanese (ja)
Other versions
JPH0776914A (en
Inventor
正幸 小股
俊夫 堀
逹司 伊藤
正信 星
一郎 戸村
恭幸 柴田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP24627793A priority Critical patent/JP3241896B2/en
Publication of JPH0776914A publication Critical patent/JPH0776914A/en
Application granted granted Critical
Publication of JP3241896B2 publication Critical patent/JP3241896B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Steps, Ramps, And Handrails (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】本発明は、地下階の本設鉄骨階段
を根切時の仮設階段に利用する鉄骨階段ハングダウン工
法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a steel staircase hang-down method in which a permanent steel staircase on a basement floor is used as a temporary staircase at the time of root cutting.

【0002】[0002]

【従来の技術】近年、各種コンクリート建物の地下躯体
工事には、工期の短縮などの利点から、しばしば逆打工
法が採用される。この逆打工法は、山止めと構真柱を施
工した後、地下へ向かって根切と躯体施工とを繰り返し
て、地下躯体を順次に構築するものであり、地下躯体の
早期構築だけでなく、地上躯体工事を同時進行させ得る
点でも優れている。
2. Description of the Related Art In recent years, a reverse striking method is often employed in the construction of an underground skeleton of various concrete buildings due to the advantage of shortening the construction period. This reverse striking method is to construct the underground skeleton sequentially by constructing the pier and constructing the pillar, then repeating the root cutting and framing construction to the underground, and not only the early construction of the underground skeleton but also It is also excellent in that the ground frame construction can be performed simultaneously.

【0003】[0003]

【発明が解決しようとする課題】しかし、この逆打工法
は、通常、作業床を兼ねる地上一階部分の床を施工した
後、順次に下階の床を造って行くので、最下階の床が出
来上がるまでは、本設鉄骨階段の組み立て及び利用がで
きず、そのために、根切時には、専ら仮設の昇降設備を
利用している。したがって、その昇降設備の組立・解体
撤去に甚だ手間がかかる上に、本設鉄骨階段の施工が遅
れ、折角の逆打工法の利点を減退させている。また、仮
設の昇降設備には、利便性、安全性の面で十分とはいい
難いところがある。そこで、本発明は、逆打工法におい
て本設鉄骨階段を昇降設備として仮設利用できるように
することにより、上記従来の問題点を解決し、併せて、
コストの低減を図ろうとするものである。
However, in this reverse striking method, usually, the floor of the first floor above the ground, which also serves as the working floor, is constructed, and then the floors of the lower floor are sequentially formed. Until the floor is completed, it is not possible to assemble and use the main steel stairs. For this reason, temporary elevating equipment is exclusively used at the time of root cutting. Therefore, it takes a lot of time to assemble and disassemble the elevating equipment, and the construction of the permanent steel stairs is delayed, and the advantage of the angled reverse striking method is reduced. In addition, the temporary elevating equipment has difficulty in terms of convenience and safety. Therefore, the present invention solves the above-mentioned conventional problems by allowing the permanent steel staircase to be temporarily used as an elevating facility in a reverse driving method, and at the same time,
It is intended to reduce costs.

【0004】[0004]

【課題を解決するための手段】上記目的達成のため、本
発明は、地下階の本設鉄骨階段を先行作業床からの吊り
構造とし、該本設鉄骨階段を根切の進捗状況に合わせて
随時下方へと挿入することを特徴とする。
In order to achieve the above object, the present invention provides a construction in which a permanent steel staircase on a basement floor is suspended from a preceding work floor, and the permanent steel staircase is adapted to the progress of root cutting. It is characterized by being inserted downward as needed.

【0005】[0005]

【作用】如上の構成であるから、最終的には地下躯体に
定着される本設鉄骨階段が昇降設備に仮設利用できるこ
ととなり、従来の仮設の昇降設備を無用乃至極僅かにま
で削減することを可能にする。
[Function] Since the above construction is adopted, the permanent steel stairs which are finally fixed to the underground skeleton can be temporarily used for the elevating equipment, and the conventional temporary elevating equipment can be reduced to unnecessary or extremely small. enable.

【0006】[0006]

【実施例】図面は、本発明の鉄骨階段ハングダウン工法
に係る実施例を示し、その内、図1乃至図5は、施工の
手順を示している。以下、これを順次に説明する。 (1) 第1工程(図1) まず、山止めと構真柱を施工して、作業床を兼ねた地上
階一階部の床1を構築し、この地上階一階部の床1に
は、拡大平面図たる図6にも示す本設鉄骨階段用開口部
2を形成するとともに、該開口部2の上縁適所に、それ
ぞれ本設鉄骨階段3の四隅の鋼製支柱31に対応させてブ
ラケット4を仮設する。次いで、地下一階部分の構築に
適合する第1次根切Aを行い、その第1次根切底Aaに捨
てコンクリートAbを打つ。一方、地上では、第1次根切
Aに対応させて、本設鉄骨階段3の内、最下階たる地下
階三階部下半に適応する第1層部3aを組み立てる。この
第1層部3aは、四隅の鋼製支柱31の前後相互に複数の鋼
製受梁32を上下互い違いに接合して、それら前後相互の
鋼製受梁32間で、複数の踊り場34付き鋼製階段33を互い
違いに架設するとともに、所要の鋼製手摺35を付設す
る。ただし、上端の踊り場34での内側の手摺は、後に不
要となるために、仮設の手摺枠15を用いる。また、鋼製
支柱31相互の下端にフレーム補強材36を横設する。な
お、上記第1層部3aを地下階三階部下半に適応させてい
るのは、地下階三階部の階高を地下階一階部のほぼ二倍
に設計しているからである。而して、その本設鉄骨階段
3の第1層部3aを、吊り手段5を介してクレーン等(図
示せず)により揚重して上記開口部2内へと挿入し、当
該各鋼製支柱31の上部を上記各ブラケット4にボルト・
ナットで取り外し可能に連繋させて、吊り下げ状態に保
持する。また、上記捨てコンクリートAbと本設鉄骨階段
3の第1層部3aの下端との間には、仮設のスロープ桟橋
6をかけわたす。斯様にして、本設鉄骨階段3の第1層
部3aを仮設利用することにより、地下階一階部の床7、
柱、外周壁等の地下躯体工事を遂行する。
BRIEF DESCRIPTION OF THE DRAWINGS The drawings show an embodiment of the steel frame staircase hang-down method of the present invention, and FIGS. 1 to 5 show construction procedures. Hereinafter, this will be described sequentially. (1) First step (Fig. 1) First, a hill stop and a timber pillar are constructed to construct a floor 1 on the ground floor, which also serves as a working floor, and the floor 1 on the ground floor, 1 6 forms an opening 2 for a permanent steel staircase also shown in FIG. 6 which is an enlarged plan view, and has a steel pillar 31 at each of the four corners of the permanent steel staircase 3 at an appropriate upper edge of the opening 2. The bracket 4 temporarily. Next, the first root cutting A suitable for the construction of the first basement is performed, and the concrete Ab is thrown into the first root cutting Aa. On the other hand, on the ground, the first layer portion 3a that is adapted to the lower half of the third floor of the basement floor, which is the lowest floor, of the main steel staircase 3 is assembled in correspondence with the first root cutting A. The first layer portion 3a has a plurality of steel supports 32 at the four corners and a plurality of steel support beams 32 joined alternately up and down, and a plurality of landings 34 are provided between the front and rear steel support beams 32. Steel stairs 33 are erected alternately, and required steel handrails 35 are attached. However, since the inner handrail at the landing 34 at the upper end becomes unnecessary later, the temporary handrail frame 15 is used. At the lower ends of the steel columns 31, frame reinforcing members 36 are provided horizontally. The reason why the first layer 3a is adapted to the lower half of the third basement floor is that the height of the third basement floor is designed to be approximately twice as high as that of the first basement floor. Then, the first layer portion 3a of the main steel staircase 3 is lifted by a crane or the like (not shown) via the suspending means 5 and inserted into the opening 2 so as to be inserted into each of the steel members. The upper part of the column 31 is bolted to each bracket 4
It is detachably connected with a nut and held in a suspended state. Further, a temporary slope pier 6 is provided between the discarded concrete Ab and the lower end of the first layer portion 3a of the permanent steel staircase 3. In this way, by temporarily using the first layer portion 3a of the permanent steel staircase 3, the floor 7, the first floor of the basement floor,
Underground work such as pillars and outer walls will be performed.

【0007】(2) 第2工程(図2) 地下階一階部の地下躯体構築後、地下階二階部の構築に
適合する第2次根切Bを行い、第2次根切底Baに捨てコ
ンクリートBbを打つ。また、作業床たる地上階一階部の
床1上では、第2次根切Bに対応させて、本設鉄骨階段
3の内、最下階たる地下階三階部上半に適応する第2層
部3bを組み立て、上記第1層部3aの上端に連結一体化さ
せる。ただし、前回の上端の踊り場34に仮設した手摺枠
15は無用となるので取り外すが、これを今回の上端の踊
り場34に転用する。この第2層部3bの各部の構造も地下
階三階部上半とした理由も上記第1層部3aの場合と同様
である。次に、その第2層部3bの上端にて、吊り手段5
を介してクレーン等により荷重を支えつつ、前回第1層
部3aの各鋼製支柱31と上記各ブラケット4とを連ねたボ
ルト・ナットを取り外し、自由となった一連の第1層部
3a及び第2層部3bを、そのクレーン等を操作して下降さ
せ、下端を第2次根切B内へと十分に挿入させたところ
で、第2層部3bの各鋼製支柱31の上部を上記各ブラケッ
ト4にボルト・ナットで取り外し可能に連繋させて、吊
り下げ状態に保持する。更に、要所に垂直養生ネット37
を仮張りする。上記捨てコンクリートBbと本設鉄骨階段
3の第1層部3aの下端との間には、前回同様に仮設のス
ロープ桟橋6をかけわたす。斯様にして、本設鉄骨階段
3の第1層部3a及び第2層部3bを仮設利用することによ
り、地下階二階部の床8、柱、外周壁等の地下躯体工事
を遂行する。
(2) Second step (FIG. 2) After the construction of the basement on the first floor of the basement floor, a second root cutting B suitable for the construction of the second floor of the basement floor is performed, and the second root cutting Ba is formed. Hit the discarded concrete Bb. On the floor 1 of the first floor of the ground floor, which is the working floor, the second half of the main steel staircase 3 is adapted to the upper half of the third floor of the basement floor, which is the lowest floor, corresponding to the second rooting B. The two-layer part 3b is assembled and connected and integrated with the upper end of the first layer part 3a. However, the handrail frame temporarily set at the landing 34 at the upper end of the previous time
Since 15 becomes useless, it is removed, but this is diverted to the landing 34 at the upper end this time. The structure of each part of the second layer part 3b is also the same as that of the first layer part 3a because the upper half of the third floor part of the basement floor is used. Next, at the upper end of the second layer portion 3b, suspending means 5
The bolts and nuts connecting the steel struts 31 of the first layer section 3a and the brackets 4 were removed last time while supporting the load with a crane or the like via
3a and the second layer portion 3b are lowered by operating the crane and the like, and when the lower end is sufficiently inserted into the second root cutting B, the upper portion of each steel column 31 of the second layer portion 3b is reached. Are detachably connected to the brackets 4 with bolts and nuts, and are held in a suspended state. In addition, vertical curing nets 37
Temporarily. A temporary slope pier 6 is extended between the discarded concrete Bb and the lower end of the first layer portion 3a of the permanent steel staircase 3 as in the previous case. In this manner, by temporarily using the first layer portion 3a and the second layer portion 3b of the permanent steel staircase 3, the underground framing work such as the floor 8, the pillars, the outer peripheral wall and the like of the second basement floor is performed.

【0008】(3) 第3工程(図3) 地下階二階部の地下躯体構築後、地下階三階部上半の構
築に適合する第3次根切Cを行い、第3次根切底Caに捨
てコンクリートCbを打つ。ただし、上述のように、設計
上、地下階三階部の階高を地下階一階部のほぼ二倍程度
にまで高いものにしているため、第3次根切Cは地下階
三階部の階高のほぼ半分までとしている。ここでは、作
業性等の理由から、作業床たる地上階一階部の床1上で
の本設鉄骨階段3の組立作業は、残部のすべて、つま
り、地下階一階部及び二階部に適応する部分を第3層部
3cとして組み立て、上記第2層部3bの上端に連結一体化
させる。勿論、前回の上端の踊り場34に仮設した手摺枠
15は無用となるので取り外す。この第3層部3cの各部の
構造も上記第1層部3aと実質的に同じであるが、最上部
の鋼製階段33については設計上から長尺に形成する。こ
うして、連結一体化させた第1層部3a乃至第3層部3c
は、前回同様にして下降させ、下端を第3次根切C内へ
と十分に挿入させて、第3層部3cの各鋼製支柱31の中途
部を上記各ブラケット4にボルト・ナットで取り外し可
能に連繋させて、吊り下げ状態に保持する。また、垂直
養生ネット37の仮張りを適宜に伸長させる。上記捨てコ
ンクリートCbと本設鉄骨階段3の第3層部3cの下端との
間には、仮設の自在ステップ9をかけわたすとともに、
仮設手摺10を添える。ここでも、本設鉄骨階段3の第1
層部3a乃至第3層部3cを仮設利用して、地下階三階部の
地下躯体工事を遂行するが、床については、作業床等と
して用いる仮設スラブ11を設ける。なお、該仮設スラブ
11は、最終的には撤去するものである。
(3) Third step (FIG. 3) After the construction of the basement on the second floor of the basement floor, a third root cutting C suitable for the construction of the upper half of the third floor of the basement floor is performed, and the third root cutting is performed. Pour concrete Cb into Ca. However, as described above, since the height of the third floor of the basement floor is set to be about twice as high as the first floor of the basement floor, the third root cutting C is the third floor of the basement floor. Up to almost half the floor height. Here, for reasons of workability and the like, the assembling work of the permanent steel staircase 3 on the floor 1 of the first floor of the ground floor, which is the work floor, is applied to all of the rest, that is, the first floor and the second floor of the basement floor. 3rd layer part
Assembled as 3c and connected and integrated with the upper end of the second layer 3b. Of course, the handrail frame temporarily set at the last landing 34
Remove 15 as it becomes useless. The structure of each part of the third layer portion 3c is also substantially the same as that of the first layer portion 3a, but the uppermost steel stairs 33 are formed to be long from the viewpoint of design. In this way, the first layer portion 3a to the third layer portion 3c integrated and connected.
Is lowered in the same manner as the previous time, the lower end is sufficiently inserted into the third root cutting C, and the middle part of each steel support 31 of the third layer portion 3c is attached to each bracket 4 with bolts and nuts. It is detachably connected and held in a suspended state. Further, the temporary tension of the vertical curing net 37 is appropriately extended. Between the discarded concrete Cb and the lower end of the third layer portion 3c of the permanent steel staircase 3, a temporary free step 9 is applied,
A temporary handrail 10 is attached. Again, the first of the main steel stairs 3
The underground skeleton construction on the third floor of the basement floor is performed by temporarily using the layer portions 3a to 3c, and a temporary slab 11 used as a work floor or the like is provided on the floor. The temporary slab
11 is to finally remove.

【0009】(4) 第4工程(図4) 地下階三階部上半の地下躯体構築後、地下階三階部下半
乃至基礎スラブの構築に適合する第4次根切Dを行い、
第4次根切底Daに捨てコンクリートDbを打つ。次に、連
結一体化させた第1層部3a乃至第3層部3cは、前回同様
にして下降させ、下端を第4次根切D内へと十分に挿入
させて(この際は最終設置位置となる。)、第3層部3c
の各鋼製支柱31の上端を上記各ブラケット4にボルト・
ナットで取り外し可能に連繋させて、吊り下げ状態に保
持する。ここでの上記捨てコンクリートDbと本設鉄骨階
段3の第3層部3cの下端との間には、基礎スラブ12を設
ける関係上、これまでより高い空間となることから階段
枠14及び手摺枠15を組み込みした枠組足場13を設け、不
足分を補うために下端に仮設のスロープ桟橋6を使用す
る。また、ここでも、本設鉄骨階段3の第1層部3a乃至
第3層部3cを仮設利用して、地下階三階部の地下躯体工
事を遂行するが、特に、床については、基礎スラブ12を
構築することとなる。
(4) Fourth Step (FIG. 4) After the construction of the upper half of the upper half of the third floor of the basement floor, a fourth root cutting D suitable for the construction of the lower half of the third floor of the basement floor or the foundation slab is performed.
Discard concrete Db at the 4th root incision Da. Next, the first layer portion 3a to the third layer portion 3c that are connected and integrated are lowered in the same manner as the previous time, and the lower end is sufficiently inserted into the fourth root cutting D (in this case, the final installation is performed). Position), the third layer portion 3c
The upper end of each steel column 31 is bolted to each bracket 4 above.
It is detachably connected with a nut and held in a suspended state. Since the foundation slab 12 is provided between the discarded concrete Db and the lower end of the third layer portion 3c of the permanent steel staircase 3, the space becomes higher than before, so that the stair frame 14 and the handrail frame are provided. A framed scaffold 13 incorporating 15 is provided, and a temporary slope pier 6 is used at the lower end to compensate for the shortage. Also, in this case, the first floor portion 3a to the third floor portion 3c of the permanent steel staircase 3 are temporarily used to perform the underground skeleton construction on the third floor of the basement floor. 12 will be built.

【0010】(5) 第5工程(図5) 地下階三階部下半の地下躯体構築後、つまり、地下躯体
全体を構築した後、基礎スラブ12上に捨てコンクリート
Dcを打ち、本設鉄骨階段3の下端を定着させるととも
に、出来上がった地下躯体の適所にその本設鉄骨階段3
の各箇所を適宜に定着させ、当初から吊り下げに使用し
てきた地上階一階部の床1のブラケット4を撤去し、本
設鉄骨階段3の最終的設置を完了する。
(5) Fifth Step (FIG. 5) After constructing the underground skeleton of the lower half of the third floor of the basement floor, that is, after constructing the entire underground skeleton, discard the concrete on the foundation slab 12
Hit Dc to fix the lower end of the permanent steel staircase 3 and place the permanent steel staircase 3 in the appropriate place in the completed underground skeleton.
Are properly fixed, the bracket 4 of the floor 1 on the ground floor which has been used for suspension from the beginning is removed, and the final installation of the permanent steel staircase 3 is completed.

【0011】[0011]

【発明の効果】本発明によれば、地下階の本設鉄骨階段
を先行作業床からの吊り構造として、根切の進捗状況に
合わせて随時下方へと挿入するので、最終的に地下躯体
へ定着させる本設鉄骨階段を昇降設備に仮設利用でき、
したがって、従来の仮設の昇降設備を無用乃至極僅かに
まで削減することができ、かつ、これに伴う昇降設備の
組立・解体撤去の手間を無くすことができて、従来の本
設鉄骨階段の施工の遅れを解消でき、逆打工法における
利点を十分に発揮させることができる。しかも、コスト
を大幅に低減できる。また、このように本設鉄骨階段を
昇降設備に仮設利用するので、仮設の昇降設備とは異な
り作業上の利便性、安全性を向上させることができる。
According to the present invention, the permanent steel staircase on the basement floor is suspended from the preceding work floor and inserted downward at any time in accordance with the progress of root cutting. The permanent steel staircase to be established can be temporarily used for lifting equipment,
Therefore, the conventional temporary elevating equipment can be reduced to useless or negligible, and the trouble of assembling and disassembling the elevating equipment can be eliminated. Can be eliminated, and the advantage of the reverse punching method can be fully exhibited. In addition, the cost can be significantly reduced. Further, since the permanent steel stairs are temporarily used for the elevating equipment in this manner, the convenience and safety in work can be improved unlike the temporarily elevating equipment.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の鉄骨階段ハングダウン工法の実施例
に係る第1工程説明図である。
FIG. 1 is an explanatory view of a first step according to an embodiment of a steel staircase hang-down method of the present invention.

【図2】 同第2工程説明図である。FIG. 2 is an explanatory view of a second step.

【図3】 同第3工程説明図である。FIG. 3 is an explanatory view of a third step.

【図4】 同第4工程説明図である。FIG. 4 is an explanatory view of a fourth step.

【図5】 同第5工程説明図である。FIG. 5 is an explanatory view of a fifth step.

【図6】 同第1工程説明図に係る要部の拡大平面図で
ある。
FIG. 6 is an enlarged plan view of a main part according to the first step explanatory view.

【符号の説明】[Explanation of symbols]

1…地上階一階部の床 2…本設鉄骨階段用
開口部 3…本設鉄骨階段 31…鋼製支柱 32…鋼製受梁 33…鋼製階段 34…鋼製踊り場 35…鋼製手摺 36…フレーム補強材 37…養生ネット 4…ブラケット 5…吊り手段 6…スロープ桟橋 7…地下階一階部の
床 8…地下階二階部の床 9…自在ステップ 10…仮設手摺 11…仮設スラブ 12…基礎スラブ 13…枠組足場 14…階段枠 15…手摺枠 A…第1次根切 B…第2次根切 C…第3次根切 D…第4次根切 Aa,Ba,Ca,Da,Dc…根切底 Ab,Bb,Cb,Db …捨て
コンクリート
1: Floor on the first floor of the ground floor 2: Opening for permanent steel stairs 3: Main steel stairs 31: Steel struts 32: Steel struts 33: Steel stairs 34: Steel landing 35: Steel handrails 36 ... frame reinforcing material 37 ... curing net 4 ... bracket 5 ... hanging means 6 ... slope pier 7 ... floor of the basement floor 1st floor 8 ... floor of the basement floor 2nd floor 9 ... free steps 10 ... temporary handrail 11 ... temporary slab 12 … Foundation slab 13… Framework scaffold 14… Staircase frame 15… Handrail frame A… Primary root cutting B… Secondary root cutting C… Third root cutting D… Fourth root cutting Aa, Ba, Ca, Da , Dc… Root incision Ab, Bb, Cb, Db… Discard concrete

フロントページの続き (72)発明者 星 正信 東京都中央区銀座八丁目21番1号 株式 会社 竹中工務店 東京本店内 (72)発明者 戸村 一郎 東京都中央区銀座八丁目21番1号 株式 会社 竹中工務店 東京本店内 (72)発明者 柴田 恭幸 東京都中央区銀座八丁目21番1号 株式 会社 竹中工務店 東京本店内 (56)参考文献 特開 平6−108604(JP,A) (58)調査した分野(Int.Cl.7,DB名) E04F 11/00 - 11/116 E02D 29/045 E04G 21/14 Continued on the front page (72) Inventor Masanobu Hoshi 8-21-1, Ginza, Chuo-ku, Tokyo Co., Ltd. Takenaka Corporation Inside the Tokyo Head Office (72) Inventor Ichiro Tomura 8-21-1, Ginza, Chuo-ku, Tokyo Co., Ltd. Takenaka Corporation Tokyo Main Store (72) Inventor Yasuyuki Shibata 8-21-1, Ginza, Chuo-ku, Tokyo Takenaka Corporation Tokyo Main Store (56) References JP-A-6-108604 (JP, A) (58) ) Surveyed field (Int.Cl. 7 , DB name) E04F 11/00-11/116 E02D 29/045 E04G 21/14

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 地下階の本設鉄骨階段を先行作業床から
の吊り構造とし、該本設鉄骨階段を根切の進捗状況に合
わせて随時下方へと挿入することを特徴とする鉄骨階段
ハングダウン工法。
1. A steel staircase hang wherein a permanent steel staircase on a basement floor is suspended from a preceding work floor, and the permanent steel staircase is inserted downward at any time according to the progress of root cutting. Down construction method.
JP24627793A 1993-09-06 1993-09-06 Steel frame stair hang down method Expired - Fee Related JP3241896B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP24627793A JP3241896B2 (en) 1993-09-06 1993-09-06 Steel frame stair hang down method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP24627793A JP3241896B2 (en) 1993-09-06 1993-09-06 Steel frame stair hang down method

Publications (2)

Publication Number Publication Date
JPH0776914A JPH0776914A (en) 1995-03-20
JP3241896B2 true JP3241896B2 (en) 2001-12-25

Family

ID=17146151

Family Applications (1)

Application Number Title Priority Date Filing Date
JP24627793A Expired - Fee Related JP3241896B2 (en) 1993-09-06 1993-09-06 Steel frame stair hang down method

Country Status (1)

Country Link
JP (1) JP3241896B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100930281B1 (en) * 2001-01-25 2009-12-09 가부시키가이샤 요코모리 세이사쿠쇼 Attachment bracket of steel stairway and attachment device and attachment method of steel stairway
CN110318507B (en) * 2019-07-30 2024-03-12 中国建筑第七工程局有限公司 Atrium tie rod steel staircase system and its construction method
CN114017097B (en) * 2021-09-29 2023-07-25 中铁第四勘察设计院集团有限公司 High-evacuation platform for high-speed magnetic levitation railway shield tunnel

Also Published As

Publication number Publication date
JPH0776914A (en) 1995-03-20

Similar Documents

Publication Publication Date Title
JP3218519B2 (en) Building demolition method
JP3241896B2 (en) Steel frame stair hang down method
JP2927320B2 (en) How to assemble a large hanging boiler
JP2957328B2 (en) Peripheral holding self-elevating construction method
JPH06146578A (en) Method of constructing climbing-stage of cylindrical structure and construction of chimney
JP3177735B2 (en) An erect scaffold used to reinforce the perimeter of existing buildings
JP2945917B2 (en) Construction method of large space building
JP3328790B2 (en) High-rise building assembly method
JP2696486B2 (en) Building construction method
JP3192543B2 (en) Building demolition method
JP2945326B2 (en) Gas tank dismantling method
JP3944870B2 (en) Method for constructing staircase with staircase and unit staircase used in this construction method
JP2718188B2 (en) Building exterior wall mounting method
JP2876991B2 (en) Steel frame method for high-rise buildings
JP3125205B2 (en) Construction method of temporary side wall
JP3008054B2 (en) Horizontal material temporary fixing device
JP3124152B2 (en) Collapse prevention frame
JP3230012B2 (en) Building construction equipment
JP2802568B2 (en) Construction method
JPH0417262B2 (en)
JP2785112B2 (en) All-weather construction method for high-rise buildings
JPH03197734A (en) Lift up method by replacement of scaffold body
JPH1046838A (en) Demolition method of building
JP3078389B2 (en) Temporary scaffolding method
JP3060333B2 (en) Construction method of building frame

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20071019

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20081019

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091019

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20091019

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20101019

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111019

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121019

Year of fee payment: 11

LAPS Cancellation because of no payment of annual fees