JP2802830B2 - Traveling method for long span beams - Google Patents
Traveling method for long span beamsInfo
- Publication number
- JP2802830B2 JP2802830B2 JP33596790A JP33596790A JP2802830B2 JP 2802830 B2 JP2802830 B2 JP 2802830B2 JP 33596790 A JP33596790 A JP 33596790A JP 33596790 A JP33596790 A JP 33596790A JP 2802830 B2 JP2802830 B2 JP 2802830B2
- Authority
- JP
- Japan
- Prior art keywords
- jack
- long span
- traveling
- beams
- temporary gantry
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 この発明は地組みした複数の長大スパン梁を構造物の
桁方向に順次移動させて連結する長大スパン梁のトラベ
リング方法に関するものである。Description: BACKGROUND OF THE INVENTION The present invention relates to a method for traveling a long span beam in which a plurality of long span beams which are erected are sequentially moved in a girder direction of a structure and connected.
従来、50m程度の長さの長スパンの第1の梁を地組み
し、仮設構台上で組立てた後、その両端の支持脚で支持
した状態で油圧ジャッキ等で牽引して構造物の桁方向に
移動させ、移動した空所で第2の梁を地組みし仮設構台
上で組立て、第1の梁と第2の梁を連結し、この連結し
た第1と第2の梁を一緒に梁1個分桁方向に移動させ、
移動した空所で前記と同様に次位の梁を組立て連結して
移動させるというトラベリング工程を繰返して目的とす
る構造物を組立てる方法がトラベリング工法として知ら
れている。Conventionally, the first beam with a long span of about 50m is laid on the ground, assembled on a temporary gantry, and then pulled with a hydraulic jack, etc., while being supported by the supporting legs at both ends, in the direction of the girder of the structure. , The second beam is laid in the moved space, assembled on the temporary gantry, the first beam and the second beam are connected, and the connected first and second beams are joined together. Move one digit in the digit direction,
A method of assembling a target structure by repeating a traveling process of assembling, connecting, and moving the next beam in the moved space in the same manner as described above is known as a traveling method.
前記従来の工法によって100mを超すような長大スパン
の梁のトラベリングを行おうとして、梁を支持している
仮設構台の支持を外して両端の支持脚で支持した状態に
すると、梁は長大であるため自重が重くそのため自重に
より撓みを生じ10cm〜25cm程度も下がるためトラベリン
グを終った梁と仮設構台上で組立てた次位の梁とは、そ
の高さが著しく喰違って連結することができない問題点
があった。When trying to travel a beam having a long span exceeding 100 m by the conventional method, the support of the temporary gantry supporting the beam is removed and the beam is supported by the support legs at both ends, and the beam is long. Due to its heavy weight, it is bent by its own weight and drops by about 10cm to 25cm, so that the beam that has finished traveling and the next beam assembled on the temporary gantry are significantly different in height and cannot be connected. There was a point.
また、トラベリング時に移動させる梁の仮設構台によ
る支持を取除いた際、梁が長大スパンであると梁が風や
振動を受けてねじれや設計値を超える予想外の反力を生
じ、作業を継続すると危険な状態となる問題点があっ
た。In addition, when the beam to be moved during traveling is removed by the temporary gantry, if the beam has a long span, the beam will be subjected to wind and vibration, causing torsion and unexpected reaction forces exceeding the design value, and work will continue. Then, there was a problem that was in a dangerous state.
この発明は、これらの問題点を解消し、長大スパンの
梁であっても前進させた梁と次位の梁との連結が確実に
行えるとともに、ジャッキアップ、ジャッキダウンの作
業時において多支点の反力の集中管理を行うことにより
危険がなく作業を行えるようにした長大スパン梁のトラ
ベリング方法を提供することを課題とするものである。The present invention solves these problems, and can reliably connect the advanced beam and the next beam even if the beam is a long span beam, and also has multiple fulcrums when jacking up and jacking down. It is an object of the present invention to provide a traveling method for a long span beam which can perform work without danger by centrally managing a reaction force.
前記の課題を解決するためにこの発明は、仮設構台上
に設置したジャッキ上において梁を組立てた後、ジャッ
キダウンを行い、この状態で前記梁を前方へ牽引して移
動させ、移動した梁をジャッキアップし、この状態の梁
と梁が移動した位置の仮設構台上に設置したジャッキ上
において組立てた次位の梁とを連結した後、これらの梁
をジャッキダウンする操作を所要回繰返す長大スパン梁
のトラベリング方法およびこの方法において、仮設構台
のジャッキ上において組立てられる4本の梁の各数個所
に設置された支点に圧力センサーを取付け、その圧力の
変化を支点反力の変化グラフとして1個所に集中表示
し、支点反力の変化が危険注意値を超した場合に警戒色
に変化するか警告音を発するようにした手段を講じるも
のである。In order to solve the above problems, the present invention, after assembling a beam on a jack installed on a temporary gantry, jack down, pulling the beam forward in this state, moving the beam, After connecting the beam in this state and the next beam assembled on the jack installed on the temporary gantry at the position where the beam has been moved, the operation of jacking down these beams is repeated as many times as necessary. In the method of traveling a beam and the method, a pressure sensor is attached to a fulcrum installed at several places of each of four beams assembled on a jack of a temporary gantry, and a change in the pressure is represented as a change graph of a fulcrum reaction force in one place. Is displayed in a concentrated manner, and when the change in the fulcrum reaction force exceeds the danger caution value, a means for changing to a warning color or emitting a warning sound is taken.
この発明の実施例を図面を参照して説明する。 An embodiment of the present invention will be described with reference to the drawings.
梁間が100mを超すような長大スパンの梁を有する構造
物の建方を行うには、トラベリング工法を採用すれば安
全面、工期面で有利である。In order to construct a structure having a beam with a long span such that the distance between the beams exceeds 100 m, adopting the traveling method is advantageous in terms of safety and construction period.
第1図A図において、地組みした梁部材を数個所に設
けた仮設構台2上に設置したジャッキ3上で側面から見
て長方形の第1の梁1に組立て、これを両端の支持脚4
で支持させる。1′は梁1のつなぎ材である。In FIG. 1A, a ground beam member is assembled on a jack 3 installed on a temporary gantry 2 provided at several places, into a first beam 1 which is rectangular as viewed from the side, and this is attached to support legs 4 at both ends.
To support. 1 'is a connecting member of the beam 1.
支持脚4の下部はつなぎ材5で連結され、支持脚4の
下部に取付けたローラ6をレール7上に載置した状態に
し、つぎにB図に示すように、仮設構台2上のジャッキ
3を下降(この明細書ではジャッキダウンという)させ
ると、第1の梁1はジャッキ3の支持がなくなるので、
その自重により矢印で示すように鎖線位置から実線位置
に下降する。The lower part of the support leg 4 is connected by a connecting member 5, and the roller 6 attached to the lower part of the support leg 4 is placed on the rail 7, and then, as shown in FIG. Is lowered (referred to as jack-down in this specification), the first beam 1 loses the support of the jack 3, so that
Due to its own weight, it descends from the chain line position to the solid line position as shown by the arrow.
この状態でC図に示すように、支持脚4の右方からト
ラベリング工法で常用される油圧ジャッキ(図示しな
い)等により右方向へ牽引して梁1の1本分右方へ移動
させる。In this state, as shown in FIG. C, the support leg 4 is pulled rightward by a hydraulic jack (not shown) or the like commonly used in the traveling method and moved one beam 1 to the right.
つぎにD図に示すように、移動位置に設置されている
仮設構台2上のジャッキ3を上昇(この明細書ではジャ
ッキアップという)させて梁1の高さを鎖線の位置から
矢印のようにジャッキダウン以前と同じ高さの実線位置
となるようにした後、E図に示すように、第1の梁1を
移動した後の空所で第2の梁1aを仮設構台2上で組立
て、第1の梁1とつなぎ材1′で連結する。連結が終わ
るとF図に示すように、すべての仮設構台2のジャッキ
3を矢印のようにジャッキダウンさせ、第1の梁1およ
び第2の梁1aの高さを鎖線の位置から実線の位置になる
ようにする。Next, as shown in Fig. D, the jack 3 on the temporary gantry 2 installed at the moving position is raised (in this specification, referred to as jack-up), and the height of the beam 1 is changed from the position of the chain line as indicated by the arrow. After making the solid line position at the same height as before the jack down, as shown in Fig. E, assemble the second beam 1a on the temporary gantry 2 in the empty space after moving the first beam 1, It is connected to the first beam 1 by a connecting member 1 '. When the connection is completed, the jacks 3 of all the temporary gantry 2 are jacked down as shown by arrows as shown in FIG. So that
以下、C図〜F図に示す作業を繰返すことによって所
望の構造物の建方を終了する。Hereinafter, the construction of the desired structure is completed by repeating the operations shown in FIGS.
前記の作業において、ジャッキダウンやジャッキアッ
プを行う場合には風やジャッキ操作のばらつきによって
支点反力のバランスが崩れると予想外の反力が生じ作業
が危険となるので、仮設構台2の上端に設置されたジャ
ッキ3の油圧菅から分岐した油圧菅の途中に取付けられ
た圧力センサー8を梁1の下面の8個所に設置し、圧力
センサー8からの油圧の圧力の変化量をA/D変換ユニッ
ト9を介してパーソナルコンピュータ10によって8個所
の支点反力の数値に換算して第3図に示すように陰極線
管(CRT)11上にまとめて表示するようにする。In the above-described work, when jack-down or jack-up is performed, an unexpected reaction force occurs when the balance of the fulcrum reaction force is disrupted due to a variation in wind or jack operation, and the work becomes dangerous, so the upper end of the temporary gantry 2 The pressure sensors 8 attached in the middle of the hydraulic tube branched from the hydraulic tube of the installed jack 3 are installed at eight places on the lower surface of the beam 1, and the amount of change in the hydraulic pressure from the pressure sensor 8 is A / D converted. Numerical values of the fulcrum reaction force at eight points are converted by the personal computer 10 via the unit 9 and are collectively displayed on the cathode ray tube (CRT) 11 as shown in FIG.
第3図において、1〜4、5〜8、9〜12、13〜16の
数字は4列の梁1の各支点のうち同一反力が想定される
対称位置にある2支点を1個所として8個所の支点を4
個所の支点とし、これらの反力を4列の梁に分けて表わ
したもので、支点反力の値を危険値の100分率で表わし
た棒グラフ12の上欄の数値は危険値をtonで、その下方
の棒グラフ12の欄の横方向の点線は注意値を示してお
り、下欄の数値は実際の荷重値をtonで表わすものであ
り、棒グラフ12が注意値を超す場合は棒グラフ12の色を
赤色等の警戒色に変えるか、または警告音を発するよう
にされている。In FIG. 3, numerals 1 to 4, 5 to 8, 9 to 12, and 13 to 16 indicate that two fulcrums at symmetrical positions where the same reaction force is assumed among the fulcrums of the four rows of beams 1 are one. 8 fulcrum points to 4
The fulcrum of each point is shown and these reaction forces are divided into four rows of beams. The values in the upper column of the bar graph 12 in which the value of the fulcrum reaction force is expressed as a percentage of the danger value are the danger values in tons. , The horizontal dotted line in the column of the bar graph 12 below indicates the caution value, the numerical value in the lower column represents the actual load value in ton, and when the bar graph 12 exceeds the caution value, The color is changed to a warning color such as red, or a warning sound is emitted.
これによって、ジャッキダウンまたはジャッキアップ
時における4列の梁の仮設構台2の8個所の支点におけ
る支点反力の値をまとめて監視することができ、注意値
を超えると速かに認識でき直ちにジャッキダウンおよび
ジャッキアップを停止し、注意値より下がった時点でジ
ャッキダウンおよびジャッキアップを再開させ作業を安
全に行うことができる。This makes it possible to collectively monitor the values of the fulcrum reaction forces at the eight fulcrums of the temporary gantry 2 of four rows of beams when the jack is lowered or jacked up. The down and the jack-up are stopped, and the jack-down and the jack-up are resumed when the value falls below the caution value, so that the work can be performed safely.
大型構造物の建方工数を減らそうとしても従来のトラ
ベリング工法では不可能であった長大スパンの梁のトラ
ベリングを行うことが可能となり、大型構造物の建方の
工期を短縮できるとともに、トラベリング工法であるた
め、高所作業を削減できて安全性が向上する。Even if it is attempted to reduce the number of construction steps for large structures, it is possible to travel long and long span beams, which was impossible with the conventional traveling method, and the construction method for large structures can be shortened, and the traveling method Therefore, work at high places can be reduced and safety can be improved.
また、梁の各支点反力を集中管理できるので安全を確
認しながら作業を行えるので安全性が向上し、さらに実
際施工時の反応を確認できるのでより正確な設計が可能
となる。In addition, since the fulcrum reaction force of each beam can be centrally managed, the work can be performed while confirming the safety, so that the safety is improved. Further, since the reaction at the time of actual construction can be confirmed, a more accurate design can be performed.
第1図A図〜F図はトラベリング方法を側面から見た説
明図、第2図は梁を支持した状態の正面図、第3図はCR
Tの表示面を示す詳細図である。 1……梁、1a……梁、2……仮設構台、3……ジャッ
キ、4……支持脚、8……圧力センサー。1A to 1F are explanatory views of the traveling method viewed from the side, FIG. 2 is a front view of a state in which a beam is supported, and FIG. 3 is a CR.
FIG. 3 is a detailed view showing a display surface of T. 1 ... beam, 1a ... beam, 2 ... temporary gantry, 3 ... jack, 4 ... support leg, 8 ... pressure sensor.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 武政 高弘 東京都中央区銀座8丁目21番1号 株式 会社竹中工務店東京本店内 (56)参考文献 特開 平2−91339(JP,A) 特開 昭63−47439(JP,A) 特開 昭59−68454(JP,A) 特開 平2−8432(JP,A) (58)調査した分野(Int.Cl.6,DB名) E04G 21/14 E04B 1/342──────────────────────────────────────────────────続 き Continuation of front page (72) Inventor Takahiro Takemasa 8-21-1, Ginza, Chuo-ku, Tokyo Inside Takenaka Corporation Tokyo Main Store (56) References JP-A-2-91339 (JP, A) JP-A-63-47439 (JP, A) JP-A-59-68454 (JP, A) JP-A-2-8432 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E04G 21 / 14 E04B 1/342
Claims (3)
(3)上において梁(1)を組立てて支持脚(4)で支
持した後、ジャッキダウンを行い、この状態で前記梁
(1)を前方へ牽引して移動させ、移動した梁(1)を
ジャッキアップし、この状態の梁(1)と梁(1)が移
動した位置の仮設構台(2)上に設置したジャッキ
(3)上において組立てた次位の梁(1a)とを連結した
後、これらの梁(1),(1a)をジャッキダウンする操
作を所要回繰返す長大スパン梁のトラベリング方法。1. A beam (1) is assembled on a jack (3) installed on a temporary gantry (2) and supported by supporting legs (4), and then jack-down is performed. Is pulled forward, the moved beam (1) is jacked up, and the beam (1) in this state and the jack (3) installed on the temporary gantry (2) at the position where the beam (1) has moved. A method for traveling a long span beam in which the operation of jacking down these beams (1) and (1a) as required after connecting the next assembled beam (1a) is repeated.
て組立てられる4本の梁(1)の各数箇所に設置された
支点に圧力センサー(8)を取付け、その圧力の変化を
支点反力の変化グラフとして1個所に集中表示した請求
項1記載の長大スパン梁のトラベリング方法。2. A pressure sensor (8) is attached to a fulcrum set at each of several places of four beams (1) assembled on a jack (3) of a temporary gantry (2), and a change in the pressure is detected as a fulcrum. 2. The traveling method of a long span beam according to claim 1, wherein the change graph of the reaction force is displayed in one place.
に警戒色に変化するか警告音を発するようにした請求項
2記載の長大スパン梁のトラベリング方法。3. The traveling method of a long span beam according to claim 2, wherein when the change of the fulcrum reaction force exceeds a danger caution value, the color changes to a warning color or a warning sound is issued.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33596790A JP2802830B2 (en) | 1990-11-30 | 1990-11-30 | Traveling method for long span beams |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP33596790A JP2802830B2 (en) | 1990-11-30 | 1990-11-30 | Traveling method for long span beams |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH04203166A JPH04203166A (en) | 1992-07-23 |
JP2802830B2 true JP2802830B2 (en) | 1998-09-24 |
Family
ID=18294325
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP33596790A Expired - Lifetime JP2802830B2 (en) | 1990-11-30 | 1990-11-30 | Traveling method for long span beams |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2802830B2 (en) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106927404A (en) * | 2017-04-19 | 2017-07-07 | 中铁六局集团有限公司 | A kind of remote-controlled shifting beam dolly and beam shifting method with hydraulic system |
-
1990
- 1990-11-30 JP JP33596790A patent/JP2802830B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JPH04203166A (en) | 1992-07-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2802830B2 (en) | Traveling method for long span beams | |
CN216740047U (en) | Overhead tool type steel platform with high altitude and large span | |
JP3413584B2 (en) | Construction method of frame structure | |
CN103821360A (en) | Construction method for high-altitude long-span cantilever formwork | |
JPH0525933A (en) | Strut type scaffold form lifting device and concrete building frame construction method | |
JP3523223B2 (en) | Demolition equipment for high-rise buildings | |
CN112173043A (en) | Hyperboloid segmentation bed-jig | |
JP6814717B2 (en) | How to install horizontal members and how to build a building frame | |
CN110017032B (en) | Method for improving plant structure by penetrating beam and adding column | |
CN219430545U (en) | Operation platform for utilizing stiffness framework for tower column head section | |
JP3368483B2 (en) | Bridge pier construction method | |
CN219863951U (en) | Cantilever structural steel platform support frame | |
JP3417865B2 (en) | Method of constructing structure using strut and strut structure | |
JP3048548B2 (en) | Push-up device for steel structure | |
JP2634271B2 (en) | Jack-up method and device | |
JP2513376B2 (en) | How to build a building | |
JP2024093741A (en) | Method for constructing and dismantling concrete for device | |
CN112324166A (en) | Temporary anti-toppling device for steel beam | |
SU724669A1 (en) | Method of erecting a vertical structure | |
JP2653630B2 (en) | How to raise the temporary roof | |
JPH074060A (en) | Lift-up execution equipment for multistoried building | |
JPS62309B2 (en) | ||
CN118756716A (en) | Support column system structure containing slidable bracket and construction method thereof | |
JPH0213081B2 (en) | ||
JPH0160627B2 (en) |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080717 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 11 Free format text: PAYMENT UNTIL: 20090717 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090717 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 12 Free format text: PAYMENT UNTIL: 20100717 |