JP2019178588A - Building construction method - Google Patents

Building construction method Download PDF

Info

Publication number
JP2019178588A
JP2019178588A JP2018069523A JP2018069523A JP2019178588A JP 2019178588 A JP2019178588 A JP 2019178588A JP 2018069523 A JP2018069523 A JP 2018069523A JP 2018069523 A JP2018069523 A JP 2018069523A JP 2019178588 A JP2019178588 A JP 2019178588A
Authority
JP
Japan
Prior art keywords
wall panel
building
foundation
floor
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2018069523A
Other languages
Japanese (ja)
Other versions
JP7116574B2 (en
Inventor
孝博 島袋
Takahiro Shimabukuro
孝博 島袋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Daiwa House Industry Co Ltd
Original Assignee
Daiwa House Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Daiwa House Industry Co Ltd filed Critical Daiwa House Industry Co Ltd
Priority to JP2018069523A priority Critical patent/JP7116574B2/en
Publication of JP2019178588A publication Critical patent/JP2019178588A/en
Application granted granted Critical
Publication of JP7116574B2 publication Critical patent/JP7116574B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

To make it possible to shorten a construction period by making construction work for a building be efficient even in an environment in which it is difficult to provide a construction machine outside a construction area for the building for a long-term.SOLUTION: A building construction method includes: moving a self-traveling type crane 50 to the inside of a foundation formation area 4 for forming a foundation 2 for a building 1; using the crane 50, assembling a skeleton 6 for the building 1 in the foundation formation area 4; using the crane 50, installing an exterior wall panel 20 for a second side face part 12 other than a first side face part 11 to be a side for carrying out the crane 50 on the skeleton 6 for the building 1; after installing the exterior wall panel 20 at the second side face part 12, moving the crane 50 to the outside of the foundation formation area 4 through the first side face part 11; forming an erection part 2C of the foundation 2 for the first side face part 11 while suspending a first floor exterior wall panel 20A-1 at a first floor portion of the first side face part 11; and fixing the erection part 2C of the foundation 2 for the first side face part 11 to the first floor exterior wall panel 20A-1.SELECTED DRAWING: Figure 8

Description

本発明は、クレーン等の建設機械を用いて建物を施工する建物施工方法に関する。   The present invention relates to a building construction method for constructing a building using a construction machine such as a crane.

住宅等の建物の建設に際し、クレーン等の建設機械を用いることが行われている。例えば、特許文献1には、建物の建設エリアの外側にクレーンを設置して、躯体や建築資材を運搬することについて開示されている。   In the construction of a building such as a house, a construction machine such as a crane is used. For example, Patent Literature 1 discloses that a crane is installed outside a construction area of a building to transport a frame or a building material.

特開平9−317185号公報Japanese Patent Laid-Open No. 9-317185

ところで、市街地に住宅を建てる場合には、住宅の建設地にクレーンを設置するスペースが確保できないことがある。こうした場合には、建設地に面した道路にクレーンを設置することとなるが、細い道路では通行止めの必要があり、長期間のクレーンの設置ができないことがある。そのため、建物の建設エリアの外に長期的に建設機械を設置することが困難な環境下においても、建設機械を効率良く使用して工期を短縮可能な工法が望まれている。   By the way, when building a house in an urban area, it may not be possible to secure a space for installing a crane in the construction site of the house. In such a case, a crane is installed on the road facing the construction site, but it is necessary to close the road on a narrow road, and the crane may not be installed for a long period of time. Therefore, even in an environment where it is difficult to install a construction machine for a long time outside the building construction area, a construction method that can efficiently use the construction machine and shorten the construction period is desired.

本発明は上記の課題に鑑みてなされたものであって、その目的は、建物の建設エリアの外に長期的に建設機械を設置することが困難な環境下においても、建物の施工作業を効率化し、工期の短縮が可能となる建物施工方法を提供することにある。   The present invention has been made in view of the above-mentioned problems, and its purpose is to improve the efficiency of building construction work even in an environment where it is difficult to install construction machinery for a long time outside the building construction area. The purpose is to provide a building construction method that can shorten the construction period.

上記課題は、本発明に係る建物施工方法によれば、建物を施工する建物施工方法であって、前記建物の基礎を形成する基礎形成領域の内側に自走式の建設機械を移動する工程と、前記建設機械を用いて、前記基礎形成領域に前記建物の躯体を組み上げる工程と、前記建設機械を用いて、前記建物の前記躯体において前記建設機械の搬出側となる第1側面部以外の第2側面部について外壁パネルを設置する第1設置工程と、前記第2側面部に外壁パネルを設置した後に、前記第1側面部から前記基礎形成領域の外に前記建設機械を移動する工程と、前記第1側面部に外壁パネルを設置する第2設置工程と、を含み、前記第2設置工程は、前記第1側面部の一階部分に一階用外壁パネルを吊り下げる吊り下げ工程と、前記一階用外壁パネルを吊り下げたまま、前記第1側面部の基礎の立ち上がり部を形成する形成工程と、前記第1側面部の基礎の立ち上がり部と前記一階用外壁パネルを固定する固定工程と、を有することにより解決される。
こうすることで、建物の建設エリアの外に長期的に建設機械を設置することが困難な環境下においても、建設エリアの中に建設機械を入れて建物の大部分の躯体、外壁パネルの設置が可能となる。そして、建設機械を建物の基礎形成領域から外に出す第1側面部分については、効率的に外壁パネルの設置が可能となる。
すなわち、上記の建物施工方法によれば、建物の建設エリアの外に長期的に建設機械を設置することが困難な環境下においても、建物の施工作業を効率化し、工期の短縮が可能となる。
According to the building construction method according to the present invention, the above-mentioned problem is a building construction method for constructing a building, the step of moving a self-propelled construction machine inside a foundation forming region that forms the foundation of the building; A step of assembling the building frame in the foundation forming region using the construction machine, and a first side portion other than the first side surface part serving as a carry-out side of the construction machine in the building frame using the construction machine. A first installation step of installing an outer wall panel with respect to two side surfaces; and a step of moving the construction machine out of the foundation forming region from the first side surface after installing the outer wall panel on the second side surface portion; A second installation step of installing an outer wall panel on the first side surface portion, and the second installation step includes a hanging step of suspending the first floor outer wall panel on the first floor portion of the first side surface portion, Hanging the outer wall panel for the first floor It is solved by having a forming step of forming a rising portion of the foundation of the first side surface portion and a fixing step of fixing the rising portion of the foundation of the first side surface portion and the outer wall panel for the first floor while being laid. The
In this way, even in environments where it is difficult to install construction machinery for a long time outside the construction area of the building, the construction machine is placed inside the construction area and most of the building's frame and outer wall panels are installed. Is possible. And about the 1st side part which takes a construction machine out of the foundation formation area of a building, it becomes possible to install an outer wall panel efficiently.
That is, according to the building construction method described above, the construction work of the building can be made efficient and the construction period can be shortened even in an environment where it is difficult to install a construction machine in the long term outside the construction area of the building. .

上記の建物施工方法において、前記第2設置工程は、前記第1側面部に水平方向に延出する第1横架材を取り付ける工程と、前記一階用外壁パネルに前記第1横架材を取り付ける工程と、を有するとよい。
こうすることで、一階用外壁パネルの下部に第1横架材に取り付けることができる。これにより、一階用外壁パネルの位置を規制できる。
In the building construction method, the second installation step includes a step of attaching a first horizontal member extending in a horizontal direction to the first side surface portion, and a step of attaching the first horizontal member to the outer wall panel for the first floor. And a step of attaching.
By carrying out like this, it can attach to a 1st horizontal member at the lower part of the outer wall panel for 1st floors. Thereby, the position of the outer wall panel for the first floor can be regulated.

上記の建物施工方法において、前記一階用外壁パネルは、下端部に設けられたアンカー部材を有し、前記固定工程では、前記第1側面部の基礎の立ち上がり部と前記アンカー部材とを固定するとよい。
こうすることで、第1横架材により、一階用外壁パネルのアンカー部材の位置決めを行うことができる。これにより、一階用外壁パネルの上下位置を適正に設定できる。
In the building construction method, the first floor outer wall panel has an anchor member provided at a lower end portion, and in the fixing step, the rising portion of the foundation of the first side surface portion and the anchor member are fixed. Good.
By carrying out like this, the anchor member of the outer wall panel for 1st floors can be positioned with the 1st horizontal member. Thereby, the up-and-down position of the outer wall panel for the first floor can be set appropriately.

上記の建物施工方法において、前記アンカー部材は、前記一階用外壁パネルに対する取り付け位置を上下に調整するための位置調整部を有するとよい。
こうすることで、アンカー部材を適正な位置に配されるよう容易に調整することができる。
Said building construction method WHEREIN: The said anchor member is good to have a position adjustment part for adjusting the attachment position with respect to the said outer wall panel for 1st floors up and down.
By doing so, the anchor member can be easily adjusted so as to be arranged at an appropriate position.

上記の建物施工方法において、前記アンカー部材は、前記第1側面部の基礎から上方に延出するアンカーボルトが挿通される貫通孔を有し、前記第2設置工程は、前記貫通孔に挿通された前記アンカーボルトと、前記第1横架材とを連結部材により連結する工程を有するとよい。
こうすることで、基礎に対して適正な位置に一階用外壁パネルを吊り下げることができる。
In the building construction method, the anchor member has a through hole into which an anchor bolt extending upward from the foundation of the first side surface portion is inserted, and the second installation step is inserted into the through hole. The anchor bolt and the first horizontal member may be coupled by a coupling member.
By doing so, the first-floor outer wall panel can be suspended at an appropriate position with respect to the foundation.

上記の建物施工方法において、前記第2設置工程は、前記第1側面部において前記第1横架材よりも上部に水平方向に延出する第2横架材を取り付ける工程をさらに有し、前記一階用外壁パネルは、前記第2横架材に対し、水平方向に並べて取り付けられる複数のパネルユニットを有するとよい。
こうすることで、第2横架材により外壁パネルの水平方向の目地幅を調整しやすくなる。
In the building construction method, the second installation step further includes a step of attaching a second horizontal member extending in a horizontal direction above the first horizontal member in the first side surface portion, and The first-floor outer wall panel may have a plurality of panel units attached to the second horizontal member in a horizontal direction.
By doing so, the horizontal joint width of the outer wall panel can be easily adjusted by the second horizontal member.

上記の建物施工方法において、前記形成工程では、前記基礎形成領域において前記建設機械が設置されていた設置領域にコンクリートを打設して土間をさらに形成するとよい。
こうすることで、基礎の立ち上がり部と、土間とを並行して形成できる。これにより、更に工期の短縮が可能となる。
In the building construction method, in the forming step, concrete may be placed in an installation area where the construction machine is installed in the foundation formation area to further form a soil.
By doing so, the rising portion of the foundation and the soil can be formed in parallel. As a result, the construction period can be further shortened.

本発明によれば、建物の建設エリアの外に長期的に建設機械を設置することが困難な環境下においても、建物の施工作業を効率化し、工期の短縮が可能となる。   ADVANTAGE OF THE INVENTION According to this invention, even in the environment where it is difficult to install a construction machine for a long time outside the construction area of a building, the construction work of a building can be made efficient and a construction period can be shortened.

建物の基礎形成領域にクレーンを搬入する直前の状態を模式的に示す図である。It is a figure which shows typically the state just before carrying in a crane to the foundation formation area of a building. 建物の基礎形成領域に搬入したクレーンを用いて建物の躯体を組み上げた状態を模式的に示す図である。It is a figure which shows typically the state which assembled the building frame using the crane carried in to the foundation formation area of a building. 図2に対応する正面図である。FIG. 3 is a front view corresponding to FIG. 2. クレーンのジブを伸ばした状態を示す図である。It is a figure which shows the state which extended the jib of the crane. 図3に対応する側面図である。FIG. 4 is a side view corresponding to FIG. 3. 躯体の第2側面部に第2外壁パネルを取り付けた状態を模式的に示す図である。It is a figure which shows typically the state which attached the 2nd outer wall panel to the 2nd side part of the housing. 建物の基礎形成領域からクレーンを搬出した状態を模式的に示す図である。It is a figure which shows typically the state which carried out the crane from the foundation formation area of the building. 建物の基礎形成領域から搬出したクレーンを用いて、第1側面部に第1外壁パネルを取り付けた状態を模式的に示す図である。It is a figure which shows typically the state which attached the 1st outer wall panel to the 1st side part using the crane carried out from the foundation formation area of the building. 第1側面部の二階と三階に第1外壁パネルを取り付けた状態を示す図である。It is a figure which shows the state which attached the 1st outer wall panel to the 2nd floor and the 3rd floor of a 1st side part. 第1側面部の一階に第1外壁パネルを吊り下げた状態を示す図である。It is a figure which shows the state which suspended the 1st outer wall panel on the first floor of the 1st side part. 一階用外壁パネルを吊り下げた状態を屋内側から見た図である。It is the figure which looked at the state which suspended the outer wall panel for 1st floors from the indoor side. 第1横架材の近傍の構成を示す図である。It is a figure which shows the structure of the vicinity of a 1st horizontal member. アンカー部材の近傍の構成を示す図である。It is a figure which shows the structure of the vicinity of an anchor member. 基礎の立ち上がり部を打設した状態を示す図である。It is a figure which shows the state which laid the rising part of the foundation. 一階用外壁パネルのアンカー部材を基礎の立ち上がり部に固定した状態を示す図である。It is a figure which shows the state which fixed the anchor member of the outer wall panel for 1st floors to the standup | rising part of a foundation. 第1側面部の一階に吊り下げた第1外壁パネルを立ち上がり部に固定した状態を示す図である。It is a figure which shows the state which fixed the 1st outer wall panel hung on the first floor of the 1st side part to the standup | rising part.

<建物1の施工方法>
以下、図1乃至図16を参照しながら、本発明の実施の形態(以下、本実施形態)に係る建物1の施工方法(建物施工方法)について説明する。以下に説明する建物1は、複数階建ての住宅を例として説明するが、建物1は住宅に限られるものではなく、また建物1は複数階建てに限らず平屋であってもよい。
なお、以下に説明する実施形態は、本発明の理解を容易にするための一例に過ぎず、本発明を限定するものではない。すなわち、以下に説明する部材の形状、寸法、配置等については、本発明の趣旨を逸脱することなく、変更、改良され得るとともに、本発明にはその等価物が含まれる。
<Construction method for building 1>
Hereinafter, a construction method (building construction method) for the building 1 according to an embodiment of the present invention (hereinafter, this embodiment) will be described with reference to FIGS. 1 to 16. Although the building 1 described below will be described by taking a multi-storey house as an example, the building 1 is not limited to a house, and the building 1 is not limited to a multi-storey and may be a one-story building.
The embodiment described below is merely an example for facilitating the understanding of the present invention, and does not limit the present invention. That is, the shape, dimensions, arrangement, and the like of the members described below can be changed and improved without departing from the spirit of the present invention, and the present invention includes equivalents thereof.

<基礎2の形成>
図1に示されるように、建設エリアAには、建物1の基礎2が形成される。なお、建設エリアAにおいて基礎2が形成される領域を基礎形成領域4とする。そして、本実施形態では、基礎2の内部において、前面道路Rに近い出入り部2−1から侵入可能な領域を、建設機械としてのクレーン50を設置するための設置領域5とする。そのため、基礎2の出入り部2−1については当初の段階では基礎の立ち上がり部を形成しないこととする。
<Formation of foundation 2>
As shown in FIG. 1, the foundation 2 of the building 1 is formed in the construction area A. A region where the foundation 2 is formed in the construction area A is referred to as a foundation formation region 4. And in this embodiment, the area | region which can penetrate | invade from the entrance / exit part 2-1 near the front road R inside the foundation 2 is set as the installation area 5 for installing the crane 50 as a construction machine. Therefore, it is assumed that the rising portion of the foundation is not formed at the initial stage for the entrance / exit portion 2-1 of the foundation 2.

また、図1に示されるように、基礎2の内側の領域のうち、出入り部2−1に面していない領域に対してはコンクリートを打設し、第1土間3A、第2土間3Bを形成する。一方、設置領域5に対しては、図1に示す段階においては、コンクリートの打設を行わないこととする。
なお、以下において、建設エリアAにおいて前面道路Rの延出方向に直交する方向をX方向、X方向に対し直交する方向をY方向(すなわち前面道路Rの延出方向)とする。そして、鉛直方向をZ方向とする。
Moreover, as FIG. 1 shows, concrete is laid in the area | region which does not face the entrance / exit part 2-1 among the area | regions inside the foundation 2, and 3A of 1st soil, 3B of 2nd soil is used. Form. On the other hand, in the stage shown in FIG. 1, concrete placement is not performed for the installation area 5.
In the following, in the construction area A, the direction orthogonal to the extending direction of the front road R is defined as the X direction, and the direction orthogonal to the X direction is defined as the Y direction (that is, the extending direction of the front road R). The vertical direction is the Z direction.

<クレーン50の搬入、設置工程>
次に、図1に示されるように、クレーン50を前面道路Rから基礎形成領域4の内部(より詳細には設置領域5)に搬入する。具体的には、基礎2の出入り部2−1の上に金属板等の保護板52を設置して、前面道路Rから保護板52を通ってクレーン50を設置領域5に移動させる。
本実施形態では、クレーン50は、自走式のクレーンであり、クレーン50を運転することにより、クレーン50の移動が可能である。また、クレーン50は旋回、延長、部材の吊り下げ、吊り上げが可能なジブ51を有し、これにより各種建材の運搬が可能となっている。
そして、クレーン50を設置領域5に移動させた後に、クレーン50の脚を固定することで、クレーン50の設置工程が完了する。
<Crane 50 loading and installation process>
Next, as shown in FIG. 1, the crane 50 is carried from the front road R into the inside of the foundation formation region 4 (more specifically, the installation region 5). Specifically, a protective plate 52 such as a metal plate is installed on the entrance / exit 2-1 of the foundation 2, and the crane 50 is moved from the front road R through the protective plate 52 to the installation region 5.
In the present embodiment, the crane 50 is a self-propelled crane, and the crane 50 can be moved by operating the crane 50. Further, the crane 50 has a jib 51 that can be turned, extended, suspended, and lifted, thereby enabling transportation of various building materials.
And after moving the crane 50 to the installation area | region 5, the installation process of the crane 50 is completed by fixing the leg of the crane 50. FIG.

<躯体6の組み上げ工程>
次に、図2乃至図5に示されるように、設置領域5に設置したクレーン50を用いて、柱6A及び梁6B等の躯体6を基礎2の上に組み上げる。
具体的には、図3乃至図5に示されるように、本実施形態に係る建物1は三階建てとし、基礎2の上に柱6Aが固定され、さらに柱6Aの間に梁6Bが架け渡されて固定される。
ここで、図4に示されるように、クレーン50のジブ51は、最上階の梁6Bを超える長さに伸長可能となっている。
このように、設置領域5に設置したクレーン50を用いて柱6Aや梁6Bを含む建材を運搬することで、躯体6の組み上げを効率よく実施することができる。
<Assembly process of housing 6>
Next, as shown in FIGS. 2 to 5, the frame 6 such as the column 6 </ b> A and the beam 6 </ b> B is assembled on the foundation 2 using the crane 50 installed in the installation area 5.
Specifically, as shown in FIGS. 3 to 5, the building 1 according to the present embodiment is a three-story building, a column 6A is fixed on the foundation 2, and a beam 6B is built between the columns 6A. Passed and fixed.
Here, as shown in FIG. 4, the jib 51 of the crane 50 can be extended to a length exceeding the beam 6B on the uppermost floor.
Thus, by assembling the building material including the pillars 6A and the beams 6B using the crane 50 installed in the installation area 5, the assembly of the frame 6 can be efficiently performed.

ここで、建物1の躯体6において、基礎2の出入り部2−1の上部に当たる部分を第1側面部11、それ以外の部分を第2側面部12とする。
すなわち、第1側面部11は、躯体6において、クレーン50を前面道路Rに搬出する際の側面部に相当する。換言すれば、第1側面部11は、前面道路Rに面した部分であり、第2側面部12は、前面道路Rに面していない部分である。
そして、第1側面部11の一階部分に相当する一階部11−1と、二階部分に相当する二階部11−2の間に配される梁6B−1は、クレーン50を搬出する際に干渉しないように、本来の取り付け位置よりも上方に仮固定しておく。
Here, in the housing 6 of the building 1, a portion corresponding to the upper part of the entrance / exit 2-1 of the foundation 2 is defined as a first side surface portion 11, and the other portion is defined as a second side surface portion 12.
That is, the first side surface portion 11 corresponds to a side surface portion when the crane 50 is carried out to the front road R in the housing 6. In other words, the first side surface portion 11 is a portion facing the front road R, and the second side surface portion 12 is a portion not facing the front road R.
And the beam 6B-1 distribute | arranged between the 1st floor part 11-1 equivalent to the 1st floor part of the 1st side part 11 and the 2nd floor part 11-2 equivalent to a 2nd floor part is when carrying out the crane 50. Is temporarily fixed above the original mounting position so as not to interfere.

<第1設置工程>
次に、図6に示されるように、設置領域5に設置したクレーン50を用いて、第2側面部12に、外壁パネル20を取り付ける。なお、第2側面部12に取り付けられる外壁パネル20を第2外壁パネル20Bと称する。そして、第2側面部12に第2外壁パネル20Bを設置する工程を第1設置工程と称する。
第1設置工程では、クレーン50により第2外壁パネル20Bを吊り下げて運搬し、第2側面部12の各部に第2外壁パネル20Bを作業員が固定することとする。
<First installation process>
Next, as shown in FIG. 6, the outer wall panel 20 is attached to the second side surface portion 12 using the crane 50 installed in the installation region 5. In addition, the outer wall panel 20 attached to the 2nd side part 12 is called 2nd outer wall panel 20B. And the process of installing the 2nd outer wall panel 20B in the 2nd side part 12 is called a 1st installation process.
In the first installation step, the second outer wall panel 20 </ b> B is suspended and transported by the crane 50, and an operator fixes the second outer wall panel 20 </ b> B to each part of the second side surface part 12.

<クレーン50の搬出工程>
次に、図7に示されるように、設置領域5から前面道路Rにクレーン50を搬出する。具体的には、クレーン50のジブ51を短くした状態で、クレーン50を第1側面部11の一階部11−1から前面道路Rに向けて移動させる。この際、出入り部2−1は保護板52で覆っておくことで、出入り部2−1の損傷を抑制する。
クレーン50を前面道路Rに移動させた後に、クレーン50を建設エリアAに対して横付けして設置する。
そして、一階部11−1及び二階部11−2の間に設けられる梁6B−1を本来の取り付け位置に移動後に固定する。
<Crane 50 unloading process>
Next, as shown in FIG. 7, the crane 50 is carried out from the installation area 5 to the front road R. Specifically, the crane 50 is moved from the first floor portion 11-1 of the first side surface portion 11 toward the front road R with the jib 51 of the crane 50 being shortened. At this time, the entrance / exit 2-1 is covered with the protective plate 52 to suppress damage to the entrance / exit 2-1.
After moving the crane 50 to the front road R, the crane 50 is installed side by side with respect to the construction area A.
And the beam 6B-1 provided between the 1st floor part 11-1 and the 2nd floor part 11-2 is fixed after moving to an original attachment position.

<第2設置工程>
次に、図8に示されるように、前面道路Rに設置したクレーン50を用いて第1側面部11に外壁パネル20を取り付ける。なお、第1側面部11に取り付ける外壁パネル20を第1外壁パネル20Aと称する。そして、第1側面部11に第1外壁パネル20Aを設置する工程を第2設置工程と称する。
以下、図9乃至図16を参照しながら、第1側面部11への第1外壁パネル20Aの取り付け工程(第2設置工程)の詳細について説明する。
<Second installation process>
Next, as shown in FIG. 8, the outer wall panel 20 is attached to the first side surface portion 11 using the crane 50 installed on the front road R. The outer wall panel 20 attached to the first side surface portion 11 is referred to as a first outer wall panel 20A. The step of installing the first outer wall panel 20A on the first side surface portion 11 is referred to as a second installation step.
Hereinafter, the details of the attachment process (second installation process) of the first outer wall panel 20A to the first side surface portion 11 will be described with reference to FIGS. 9 to 16.

<二階用外壁パネル20A−2、三階用外壁パネル20A−3の取り付け>
図9に示されるように、クレーン50を用いて、第1側面部11の二階部11−2及び三階部11−3に対して、それぞれ二階用外壁パネル20A−2及び三階用外壁パネル20A−3を取り付ける。
具体的には、パネル化された三階用外壁パネル20A−3をクレーン50により吊り上げて、躯体6の三階部11−3に取り付ける。
そして、パネル化された二階用外壁パネル20A−2をクレーン50により吊り上げて、躯体6の二階部11−2に取り付ける。
なお、三階用外壁パネル20A−3及び二階用外壁パネル20A−2の取り付けに際しパネルユニット40を三階部11−3及び二階部11−2に取り付けるようにしてもよい。
そして、パネルユニット40の水平方向の隙間が縦目地41となり、パネルユニット40の垂直方向の隙間が横目地42となる。
<Installation of second-floor outer wall panel 20A-2 and third-floor outer wall panel 20A-3>
As shown in FIG. 9, the second-floor outer wall panel 20 </ b> A- 2 and the third-floor outer wall panel are respectively used for the second-floor portion 11-2 and the third-floor portion 11-3 of the first side surface portion 11 using the crane 50. Attach 20A-3.
Specifically, the paneled third-floor outer wall panel 20 </ b> A- 3 is lifted by the crane 50 and attached to the third-floor portion 11-3 of the frame 6.
The paneled second-floor outer wall panel 20 </ b> A- 2 is lifted by the crane 50 and attached to the second-floor portion 11-2 of the frame 6.
In addition, when attaching the outer wall panel 20A-3 for 3rd floors and the outer wall panel 20A-2 for 2nd floors, you may make it attach the panel unit 40 to the 3rd floor part 11-3 and the 2nd floor part 11-2.
The horizontal gap of the panel unit 40 becomes the vertical joint 41, and the vertical gap of the panel unit 40 becomes the horizontal joint 42.

<一階用外壁パネル20A−1の吊り下げ工程>
ここで、一階用外壁パネル20A−1の構成について説明する。一階用外壁パネル20A−1は、水平方向に並べられた複数のパネルユニット40を含み構成される。本実施形態では、一階用外壁パネル20A−1は、パネルユニット40を4枚水平に並べて構成したものである。
そして、パネルユニット40の下端部には、アンカー部材21が取り付けられている。このアンカー部材21は、一階用外壁パネル20A−1に対して複数設けられる。
<Hanging process of outer wall panel 20A-1 for the first floor>
Here, the configuration of the first-floor outer wall panel 20A-1 will be described. The first-floor outer wall panel 20A-1 includes a plurality of panel units 40 arranged in the horizontal direction. In the present embodiment, the first-floor outer wall panel 20A-1 is configured by horizontally arranging four panel units 40.
An anchor member 21 is attached to the lower end portion of the panel unit 40. A plurality of anchor members 21 are provided for the first-floor outer wall panel 20A-1.

ここで、アンカー部材21の構成について説明する。図13に示すように、アンカー部材21は、底壁部21A、立壁部21B及び左右の側壁部21Cを備える。   Here, the configuration of the anchor member 21 will be described. As shown in FIG. 13, the anchor member 21 includes a bottom wall portion 21A, a standing wall portion 21B, and left and right side wall portions 21C.

底壁部21Aは、水平の板状部を有し、中央に貫通孔21Aaが形成されている。この貫通孔21Aaには、基礎枠部2Aから上方に延出するアンカーボルト35が通される。
立壁部21Bは、底壁部21Aから鉛直方向に立ち上がる板状部であり、一階用外壁パネル20A−1に取り付けられる。
また、立壁部21Bには、一階用外壁パネル20A−1に対する取り付け位置を上下に調整可能な位置調整部22が設けられる。
具体的には、位置調整部22は、左右一対の長孔22A及び長孔22Aに通されるビス22Bを備える。そして、長孔22Aにおけるビス22Bの位置を変更することにより、アンカー部材21の一階用外壁パネル20A−1に対する上下方向の取り付け位置を調整可能となっている。
そして、側壁部21Cは、底壁部21A及び立壁部21Bに接続する略三角形状の板部である。このように、側壁部21Cが底壁部21A及び立壁部21Bを連結することにより、アンカー部材21の剛性を向上させている。
The bottom wall portion 21A has a horizontal plate-like portion, and a through hole 21Aa is formed at the center. An anchor bolt 35 extending upward from the base frame portion 2A is passed through the through hole 21Aa.
The standing wall portion 21B is a plate-like portion that rises in the vertical direction from the bottom wall portion 21A, and is attached to the first-floor outer wall panel 20A-1.
Further, the standing wall portion 21B is provided with a position adjusting portion 22 that can vertically adjust the mounting position with respect to the first floor outer wall panel 20A-1.
Specifically, the position adjustment unit 22 includes a pair of left and right elongated holes 22A and a screw 22B that passes through the elongated hole 22A. And the attachment position of the up-down direction with respect to the outer wall panel 20A-1 for 1st floors of the anchor member 21 can be adjusted by changing the position of screw 22B in 22 A of long holes.
The side wall portion 21C is a substantially triangular plate portion connected to the bottom wall portion 21A and the standing wall portion 21B. Thus, the rigidity of the anchor member 21 is improved by connecting the bottom wall portion 21A and the standing wall portion 21B with the side wall portion 21C.

そして、図10及び図11に示されるように、一階用外壁パネル20A−1を一階部11−1に吊り下げる。具体的には、一階用外壁パネル20A−1の各パネルユニット40を、吊り下げ部材43により梁6Bに吊り下げることとする。
ここで、上記の吊り下げ部材43は、梁6Bのフランジと、パネルユニット40とのそれぞれに取り付けられ、梁6Bに対してパネルユニット40を吊り下げるための金具である。
Then, as shown in FIGS. 10 and 11, the first-floor outer wall panel 20A-1 is suspended from the first-floor portion 11-1. Specifically, each panel unit 40 of the first-floor outer wall panel 20 </ b> A- 1 is suspended from the beam 6 </ b> B by the suspension member 43.
Here, the suspension member 43 is a bracket that is attached to each of the flange of the beam 6B and the panel unit 40 and suspends the panel unit 40 from the beam 6B.

<第1横架材31の取り付け工程>
次に、図10及び図11に示されるように、躯体6の一階部11−1の下部11−1aに対して第1横架材31を取り付ける。なお、一階部11−1の下部11−1aとは、一階部11−1において基礎枠部2Aのアンカーボルト35が届く範囲とする。
具体的には、第1横架材31の取り付けは、一階部11−1の両側の柱6Aに対して、第1横架材31を架設してボルト締結することにより行われる。また、第1横架材31の取り付けは、基礎枠部2Aから上方に立ち上がるアンカーボルト35に対して、第1横架材31を固定することにより行ってもよい。
<Attaching process of first horizontal member 31>
Next, as shown in FIGS. 10 and 11, the first horizontal member 31 is attached to the lower part 11-1 a of the first floor part 11-1 of the housing 6. In addition, let the lower part 11-1a of the 1st floor part 11-1 be the range which the anchor bolt 35 of the foundation frame part 2A reaches in the 1st floor part 11-1.
Specifically, the first horizontal member 31 is attached by installing the first horizontal member 31 and fastening the bolts to the pillars 6A on both sides of the first floor portion 11-1. Moreover, you may perform the attachment of the 1st horizontal member 31 by fixing the 1st horizontal member 31 with respect to the anchor bolt 35 which stands up from 2 A of foundation frames.

ここで、図11乃至図13に示されるように、第1横架材31は、Y方向に延出し、断面がL字状の金属部材である。
具体的には、第1横架材31は、一階用外壁パネル20A−1が取り付けられる取付部31Aと、取付部31Aに直交し、室内側に延出するフランジ部31Bとを有する。
Here, as shown in FIGS. 11 to 13, the first horizontal member 31 is a metal member extending in the Y direction and having an L-shaped cross section.
Specifically, the first horizontal member 31 includes an attachment portion 31A to which the first-floor outer wall panel 20A-1 is attached, and a flange portion 31B that is orthogonal to the attachment portion 31A and extends to the indoor side.

取付部31Aには、複数のボルト締結孔31Aaが形成されており、ボルト締結孔31Aaに一階用外壁パネル20A−1から室内側に延出するボルトが通されてナット61により締結される。これにより、一階用外壁パネル20A−1に第1横架材31が取り付けられる。このように、一階用外壁パネル20A−1に第1横架材31を取り付けることにより、一階用外壁パネル20A−1の位置、特にX方向における位置を拘束することが可能となる。   A plurality of bolt fastening holes 31Aa are formed in the attachment portion 31A, and bolts extending from the first floor outer wall panel 20A-1 to the indoor side are passed through the bolt fastening holes 31Aa and fastened by nuts 61. Thereby, the 1st horizontal member 31 is attached to the outer wall panel 20A-1 for 1st floors. In this manner, by attaching the first horizontal member 31 to the first floor outer wall panel 20A-1, the position of the first floor outer wall panel 20A-1, particularly in the X direction, can be constrained.

また、フランジ部31Bには、複数のボルト挿通孔31Baが形成されている。なお、フランジ部31Bの中央部に設けられるボルト挿通孔31Baには、出入り部2−1の基礎枠部2AのY方向中央から上方に延出する中央ボルト36が通される。これにより、第1横架材31のX方向及びY方向の位置決めが行われる。
そして、ボルト挿通孔31Baには、上方から連結部材33が通され、連結部材33の下端とアンカーボルト35の上端とが接続金物63により接続される。こうすることで、第1横架材31、アンカー部材21及びアンカーボルト35が互いに固定されることとなる。
Further, a plurality of bolt insertion holes 31Ba are formed in the flange portion 31B. A central bolt 36 extending upward from the center in the Y direction of the base frame portion 2A of the entry / exit portion 2-1 is passed through the bolt insertion hole 31Ba provided in the central portion of the flange portion 31B. As a result, the first horizontal member 31 is positioned in the X direction and the Y direction.
Then, the connecting member 33 is passed through the bolt insertion hole 31Ba from above, and the lower end of the connecting member 33 and the upper end of the anchor bolt 35 are connected by the connection hardware 63. By carrying out like this, the 1st horizontal member 31, the anchor member 21, and the anchor bolt 35 will be mutually fixed.

<第2横架材32の取り付け工程>
次に、図10及び図11に示されるように、躯体6の一階部11−1の上部11−1bに対して第2横架材32を取り付ける。なお、一階部11−1の上部11−1bとは、下部11−1aよりも梁6Bに近い側である。
具体的には、第2横架材32の取り付けは、一階部11−1の両側の柱6Aに対して、第2横架材32を架設してボルト締結することにより行われる。これにより、一階用外壁パネル20A−1に第2横架材32が取り付けられる。
<Attaching process of second horizontal member 32>
Next, as shown in FIGS. 10 and 11, the second horizontal member 32 is attached to the upper part 11-1 b of the first floor part 11-1 of the housing 6. The upper part 11-1b of the first floor part 11-1 is closer to the beam 6B than the lower part 11-1a.
Specifically, the second horizontal member 32 is attached by installing the second horizontal member 32 and fastening the bolts to the pillars 6A on both sides of the first floor portion 11-1. Thereby, the 2nd horizontal member 32 is attached to the outer wall panel 20A-1 for 1st floors.

ここで、図11乃至図13に示されるように、第2横架材32は、Y方向に延出し、断面がL字状の金属部材である。
具体的には、第2横架材32は、一階用外壁パネル20A−1が取り付けられる取付部32Aと、取付部32Aに直交し、室内側に延出するフランジ部32Bとを有する。
Here, as shown in FIGS. 11 to 13, the second horizontal member 32 is a metal member extending in the Y direction and having an L-shaped cross section.
Specifically, the second horizontal member 32 includes an attachment portion 32A to which the first-floor outer wall panel 20A-1 is attached, and a flange portion 32B that is orthogonal to the attachment portion 32A and extends to the indoor side.

取付部32Aには、複数のボルト締結孔32Aaが形成されており、ボルト締結孔32Aaに一階用外壁パネル20A−1から室内側に延出するボルトが通されてナットにより締結される。これにより、一階用外壁パネル20A−1と第2横架材32が固定される。
そして、取付部32Aに対するパネルユニット40の取り付け位置を調整することにより、パネルユニット40の縦目地41の幅を調整することができる。
A plurality of bolt fastening holes 32Aa are formed in the mounting portion 32A, and bolts extending from the first floor outer wall panel 20A-1 to the indoor side are passed through the bolt fastening holes 32Aa and fastened by nuts. Thereby, the outer wall panel 20A-1 for 1st floors and the 2nd horizontal member 32 are fixed.
And the width of the vertical joint 41 of the panel unit 40 can be adjusted by adjusting the attachment position of the panel unit 40 with respect to the attachment part 32A.

<基礎2の立ち上がり部2C、第3土間3Cの形成工程>
次に、図13に示されるように、基礎枠部2Aの上に型枠部材60を配置して、立ち上がり部2Cを形成するためのコンクリートの型を形成する。そして、型にコンクリートを打設して立ち上がり部2Cを形成する。
図14に示されるように、立ち上がり部2Cは、アンカー部材21の底壁部21Aに達する高さまで形成する。
ここで、設置領域5に対しても配筋37を設置した後に、コンクリートを流し込んで、第3土間3Cを形成する。
このように、立ち上がり部2Cと第3土間3Cの形成とを同時に行うことで、コンクリート硬化までの待ち時間を短縮することができる。
<Formation process of the rising part 2C of the foundation 2 and the third earth 3C>
Next, as shown in FIG. 13, a mold member 60 is disposed on the base frame portion 2A to form a concrete mold for forming the rising portion 2C. Then, the rising portion 2C is formed by placing concrete in the mold.
As shown in FIG. 14, the rising portion 2 </ b> C is formed to a height that reaches the bottom wall portion 21 </ b> A of the anchor member 21.
Here, after the reinforcing bar 37 is also installed in the installation area 5, concrete is poured to form the third soil 3C.
Thus, the waiting time until the concrete is hardened can be shortened by simultaneously forming the rising portion 2C and the third soil 3C.

<一階用外壁パネル20A−1のアンカー部材21と立ち上がり部2Cの固定工程>
次に、立ち上がり部2Cが硬化した後に、第1横架材31及び第2横架材32を取り外す。そして、図15に示されるように、一階用外壁パネル20A−1のアンカー部材21と、立ち上がり部2Cとの間にモルタル64を充填し硬化した後に、アンカーボルト35に対してナット62を締付けて固定する。これにより、図16に示されるように、一階用外壁パネル20A−1のアンカー部材21と立ち上がり部2Cとが固定される。
<Fixing process of anchor member 21 and rising part 2C of outer wall panel 20A-1 for the first floor>
Next, after the rising portion 2C is cured, the first horizontal member 31 and the second horizontal member 32 are removed. Then, as shown in FIG. 15, the mortar 64 is filled and cured between the anchor member 21 of the first-floor outer wall panel 20 </ b> A- 1 and the rising portion 2 </ b> C, and then the nut 62 is tightened against the anchor bolt 35. And fix. Thereby, as shown in FIG. 16, the anchor member 21 and the rising portion 2C of the first-floor outer wall panel 20A-1 are fixed.

以上の建物1の施工方法によれば、建物1の基礎2を形成する基礎形成領域4の内部にクレーン50を搬入し、クレーン50を用いて躯体6や外壁パネル20の取り付け作業を行うことができる。そして、クレーン50の設置領域5及びクレーン50を搬出するための第1側面部11については、クレーン50を搬出後に第1外壁パネル20Aの取り付け作業を効率よく実施することができる。
こうすることで、クレーン50を前面道路Rに長期間設置することが困難な状況下においてもクレーン50を効率よく利用して施工の省力化を図ることができる。
また、第1側面部11の一階部11−1に一階用外壁パネル20A−1を取り付ける際に、第1横架材31及び第2横架材32を用いることで、一階用外壁パネル20A−1の位置を拘束することができる。これにより、一階用外壁パネル20A−1の位置を固定した状態で、基礎2の立ち上がり部2Cを形成できる。そのため、基礎2の立ち上がり部2Cと一階用外壁パネル20A−1とを固定するための施工の作業性を向上できる。
According to the construction method of the building 1 described above, the crane 50 is carried into the foundation forming region 4 that forms the foundation 2 of the building 1, and the installation work of the frame 6 and the outer wall panel 20 is performed using the crane 50. it can. And about the installation area 5 of the crane 50 and the 1st side surface part 11 for carrying out the crane 50, after carrying out the crane 50, the attachment operation | work of 20 A of 1st outer wall panels can be implemented efficiently.
By carrying out like this, even if it is difficult to install the crane 50 on the front road R for a long period of time, the crane 50 can be used efficiently and labor saving of construction can be achieved.
Moreover, when attaching the 1st floor outer wall panel 20A-1 to the 1st floor part 11-1 of the 1st side part 11, the 1st floor outer wall is used by using the 1st horizontal member 31 and the 2nd horizontal member 32. The position of panel 20A-1 can be restrained. Thereby, the rising part 2C of the foundation 2 can be formed in a state where the position of the outer wall panel 20A-1 for the first floor is fixed. Therefore, the workability of construction for fixing the rising portion 2C of the foundation 2 and the first-floor outer wall panel 20A-1 can be improved.

<まとめ>
以上説明した本実施形態に係る建物施工方法の主な特徴は以下の通りである。
<Summary>
The main features of the building construction method according to the present embodiment described above are as follows.

[1]本実施形態に係る建物施工方法は、建物1の基礎2を形成する基礎形成領域4の内側に自走式のクレーン50(建設機械)を移動する工程と、クレーン50を用いて、基礎形成領域4に建物1の躯体6を組み上げる工程と、クレーン50を用いて、建物1の躯体6においてクレーン50の搬出側となる第1側面部11以外の第2側面部12について外壁パネル20を設置する第1設置工程と、第2側面部12に外壁パネル20を設置した後に、第1側面部11から基礎形成領域4の外にクレーン50を移動する工程と、第1側面部11に外壁パネル20を設置する第2設置工程と、を含む。第2設置工程は、第1側面部11の一階部分に一階用外壁パネル20A−1を吊り下げる吊り下げ工程と、一階用外壁パネル20A−1を吊り下げたまま、第1側面部11の基礎2の立ち上がり部2Cを形成する形成工程と、第1側面部11の基礎2の立ち上がり部2Cと一階用外壁パネル20A−1を固定する固定工程と、を有する。
こうすることで、建物1の建設エリアAの外に長期的にクレーン50を設置することが困難な環境下においても、建設エリアAの中にクレーン50を入れて建物1の大部分の躯体6、外壁パネル20の設置が可能となる。そして、クレーン50を建物1の基礎形成領域4から外に出す第1側面部11については、効率的に外壁パネル20の設置が可能となる。
すなわち、上記の建物施工方法によれば、建物1の建設エリアAの外に長期的にクレーン50を設置することが困難な環境下においても、建物1の施工作業を効率化し、工期の短縮が可能となる。
[1] The building construction method according to the present embodiment uses a step of moving a self-propelled crane 50 (construction machine) inside the foundation forming region 4 that forms the foundation 2 of the building 1, and the crane 50. The process of assembling the housing 6 of the building 1 in the foundation forming region 4 and the outer wall panel 20 with respect to the second side surface portion 12 other than the first side surface portion 11 serving as the carry-out side of the crane 50 in the housing 6 of the building 1 using the crane 50. A step of moving the crane 50 from the first side surface portion 11 to the outside of the foundation forming region 4 after the outer wall panel 20 is installed on the second side surface portion 12, and the first side surface portion 11. A second installation step of installing the outer wall panel 20. In the second installation step, the first side surface portion is suspended while the first floor outer wall panel 20A-1 is suspended while the first floor outer wall panel 20A-1 is suspended on the first floor portion of the first side surface portion 11. 11 forming step of forming the rising portion 2C of the foundation 2 and fixing step of fixing the rising portion 2C of the foundation 2 of the first side surface portion 11 and the first floor outer wall panel 20A-1.
In this way, even in an environment where it is difficult to install the crane 50 for a long time outside the construction area A of the building 1, the crane 50 is put into the construction area A and most of the housing 6 of the building 1. The outer wall panel 20 can be installed. And about the 1st side part 11 which takes the crane 50 out of the foundation formation area 4 of the building 1, the installation of the outer wall panel 20 becomes possible efficiently.
That is, according to the above-described building construction method, the construction work of the building 1 can be made efficient and the construction period can be shortened even in an environment where it is difficult to install the crane 50 outside the construction area A of the building 1 for a long time. It becomes possible.

[2]上記の建物施工方法において、第2設置工程は、第1側面部11に水平方向に延出する第1横架材31を取り付ける工程と、一階用外壁パネル20A−1に第1横架材31を取り付ける工程と、を有する。
こうすることで、一階用外壁パネル20A−1に第1横架材31に取り付けることができる。これにより、一階用外壁パネル20A−1の位置を規制できる。
[2] In the building construction method described above, the second installation step includes a step of attaching the first horizontal member 31 extending in the horizontal direction to the first side surface portion 11, and a first step on the first floor outer wall panel 20A-1. Attaching the horizontal member 31.
By doing so, the first horizontal member 31 can be attached to the first-floor outer wall panel 20A-1. Thereby, the position of outer wall panel 20A-1 for 1st floors can be controlled.

[3]上記の建物施工方法において、一階用外壁パネル20A−1は、下端部に設けられたアンカー部材21を有し、固定工程では、第1側面部11の基礎2の立ち上がり部2Cとアンカー部材21とを固定する。
こうすることで、第1横架材31により、一階用外壁パネル20A−1のアンカー部材21の位置決めを行うことができる。これにより、一階用外壁パネル20A−1の上下位置を適正に設定できる。
[3] In the building construction method described above, the first-floor outer wall panel 20A-1 has the anchor member 21 provided at the lower end portion, and in the fixing step, the rising portion 2C of the foundation 2 of the first side surface portion 11 and The anchor member 21 is fixed.
By doing so, the anchor member 21 of the first-floor outer wall panel 20A-1 can be positioned by the first horizontal member 31. Thereby, the up-and-down position of the outer wall panel 20A-1 for 1st floors can be set appropriately.

[4]上記の建物施工方法において、アンカー部材21は、一階用外壁パネル20A−1に対する取り付け位置を上下に調整するための位置調整部22を有する。
こうすることで、アンカー部材21を適正な位置に配されるよう容易に調整することができる。
[4] In the building construction method described above, the anchor member 21 has a position adjusting unit 22 for adjusting the mounting position of the first floor outer wall panel 20A-1 up and down.
By doing so, the anchor member 21 can be easily adjusted so as to be arranged at an appropriate position.

[5]上記の建物施工方法において、アンカー部材21は、第1側面部11の基礎2から上方に延出するアンカーボルト35が挿通される貫通孔21Aaを有し、第2設置工程は、貫通孔21Aaに挿通されたアンカーボルト35と、第1横架材31とを連結部材33により連結する工程を有する。
こうすることで、基礎2に対して適正な位置に一階用外壁パネル20A−1を吊り下げることができる。
[5] In the building construction method described above, the anchor member 21 has a through hole 21Aa through which the anchor bolt 35 extending upward from the foundation 2 of the first side surface portion 11 is inserted. There is a step of connecting the anchor bolt 35 inserted through the hole 21Aa and the first horizontal member 31 by the connecting member 33.
By doing so, the first-floor outer wall panel 20 </ b> A- 1 can be suspended at an appropriate position with respect to the foundation 2.

[6]上記の建物施工方法において、第2設置工程は、第1側面部11において第1横架材31よりも上部に水平方向に延出する第2横架材32を取り付ける工程をさらに有し、一階用外壁パネル20A−1は、第2横架材32に対し、水平方向に並べて取り付けられる複数のパネルユニット40を有する。
こうすることで、第2横架材32により外壁パネル20の水平方向の目地幅を調整しやすくなる。
[6] In the building construction method, the second installation step further includes a step of attaching a second horizontal member 32 extending in the horizontal direction above the first horizontal member 31 in the first side surface portion 11. The first-floor outer wall panel 20A-1 has a plurality of panel units 40 attached to the second horizontal member 32 in a horizontal direction.
By doing so, the joint width in the horizontal direction of the outer wall panel 20 can be easily adjusted by the second horizontal member 32.

[7]上記の建物施工方法において、形成工程では、基礎形成領域4においてクレーン50が設置されていた設置領域5にコンクリートを打設して土間3をさらに形成する。
こうすることで、基礎2の立ち上がり部2Cと、土間3とを並行して形成できる。これにより、更に工期の短縮が可能となる。
[7] In the building construction method described above, in the forming step, concrete is placed in the installation area 5 where the crane 50 is installed in the foundation formation area 4 to further form the soil 3.
By doing so, the rising portion 2C of the foundation 2 and the soil gap 3 can be formed in parallel. As a result, the construction period can be further shortened.

<その他の実施形態>
本発明は上記の実施形態に限定されるものではない。
例えば、一階用外壁パネル20A−1のパネルユニット40を一階部11−1に吊り下げた後に第1横架材31及び第2横架材32を取り付けてもよいし、第1横架材31及び第2横架材32を取り付けた後にパネルユニット40を吊り下げてもよい。
また、第1横架材31の取り付けと、第2横架材32の取り付けの間に一階部11−1にパネルユニット40を吊り下げるようにしてもよい。
建物1の建設に用いる建設装置は、クレーン50に限られるものではなく、3Dプリンタ等であってもよい。
また、図1乃至図16に示した工程の途中に他の工程が入っても構わない。
<Other embodiments>
The present invention is not limited to the above embodiment.
For example, the first horizontal member 31 and the second horizontal member 32 may be attached after the panel unit 40 of the outer wall panel 20A-1 for the first floor is suspended from the first floor portion 11-1, or the first horizontal member 32 may be attached. The panel unit 40 may be suspended after the material 31 and the second horizontal member 32 are attached.
Further, the panel unit 40 may be suspended from the first floor portion 11-1 between the attachment of the first horizontal member 31 and the attachment of the second horizontal member 32.
The construction apparatus used for construction of the building 1 is not limited to the crane 50, and may be a 3D printer or the like.
Further, other steps may be included in the middle of the steps shown in FIGS.

1 建物
2 基礎
2A 基礎枠部
2B 柱受け部
2C 立ち上がり部
2−1 出入り部
3 土間
3A 第1土間
3B 第2土間
3C 第3土間
4 基礎形成領域
5 設置領域
6 躯体
6A 柱
6B 梁
6B−1 梁
11 第1側面部
11−1 一階部
11−1a 下部
11−1b 上部
11−2 二階部
11−3 三階部
12 第2側面部
20 外壁パネル
20A 第1外壁パネル
20A−1 一階用外壁パネル
20A−2 二階用外壁パネル
20A−3 三階用外壁パネル
20B 第2外壁パネル
21 アンカー部材
21A 底壁部
21Aa 貫通孔
21B 立壁部
21C 側壁部
22 位置調整部
22A 長孔
22B ビス
23 ナット
31 第1横架材
31A 取付部
31Aa ボルト締結孔
31B フランジ部
31Ba ボルト挿通孔
32 第2横架材
32A 取付部
32Aa ボルト締結孔
32B フランジ部
33 連結部材
35 アンカーボルト
36 中央ボルト
37 配筋
40 パネルユニット
41 縦目地
42 横目地
43 吊り下げ部材
50 クレーン(建設機械)
51 ジブ
52 保護板
60 型枠部材
61 ナット
62 ナット
63 接続金物
64 モルタル
A 建設エリア
R 前面道路
DESCRIPTION OF SYMBOLS 1 Building 2 Foundation 2A Foundation frame part 2B Column receiving part 2C Standing part 2-1 Entrance / exit part 3 Soil 3A 1st soil 3B 2nd soil 3C 3rd soil 4 Foundation formation area 5 Installation area 6 Frame 6A Column 6B Beam 6B-1 Beam 11 First side part 11-1 First floor part 11-1a Lower part 11-1b Upper part 11-2 Second floor part 11-3 Third floor part 12 Second side part 20 Outer wall panel 20A First outer wall panel 20A-1 For first floor Outer wall panel 20A-2 Second floor outer wall panel 20A-3 Third floor outer wall panel 20B Second outer wall panel 21 Anchor member 21A Bottom wall part 21Aa Through hole 21B Standing wall part 21C Side wall part 22 Position adjusting part 22A Long hole 22B Screw 23 Nut 31 First horizontal member 31A Mounting portion 31Aa Bolt fastening hole 31B Flange portion 31Ba Bolt insertion hole 32 Second horizontal member 32A Mounting 32Aa bolt holes 32B flange portion 33 connecting member 35 the anchor bolt 36 central bolt 37 Reinforcement 40 panel unit 41 longitudinal joint 42 horizontal joint 43 suspension member 50 cranes (construction machine)
51 Jib 52 Protection plate 60 Formwork member 61 Nut 62 Nut 63 Metal fitting 64 Mortar A Construction area R Front road

Claims (7)

建物を施工する建物施工方法であって、
前記建物の基礎を形成する基礎形成領域の内側に自走式の建設機械を移動する工程と、
前記建設機械を用いて、前記基礎形成領域に前記建物の躯体を組み上げる工程と、
前記建設機械を用いて、前記建物の前記躯体において前記建設機械の搬出側となる第1側面部以外の第2側面部について外壁パネルを設置する第1設置工程と、
前記第2側面部に外壁パネルを設置した後に、前記第1側面部から前記基礎形成領域の外に前記建設機械を移動する工程と、
前記第1側面部に外壁パネルを設置する第2設置工程と、を含み、
前記第2設置工程は、
前記第1側面部の一階部分に一階用外壁パネルを吊り下げる吊り下げ工程と、
前記一階用外壁パネルを吊り下げたまま、前記第1側面部の基礎の立ち上がり部を形成する形成工程と、
前記第1側面部の基礎の立ち上がり部と前記一階用外壁パネルを固定する固定工程と、を有することを特徴とする建物施工方法。
A building construction method for constructing a building,
Moving a self-propelled construction machine inside a foundation forming area forming the foundation of the building;
Using the construction machine, assembling the building frame in the foundation forming region;
Using the construction machine, a first installation step of installing an outer wall panel on a second side surface portion other than the first side surface portion on the carry-out side of the construction machine in the housing of the building;
Moving the construction machine out of the foundation forming region from the first side surface after installing an outer wall panel on the second side surface; and
A second installation step of installing an outer wall panel on the first side surface portion,
The second installation step includes
A suspending step of suspending the first floor outer wall panel on the first floor portion of the first side surface portion;
A forming step of forming a rising portion of the foundation of the first side surface portion while suspending the outer wall panel for the first floor,
A building construction method comprising a rising step of a foundation of the first side surface portion and a fixing step of fixing the outer wall panel for the first floor.
前記第2設置工程は、
前記第1側面部に水平方向に延出する第1横架材を取り付ける工程と、
前記一階用外壁パネルに前記第1横架材を取り付ける工程と、を有することを特徴とする請求項1に記載の建物施工方法。
The second installation step includes
Attaching a first horizontal member extending horizontally to the first side surface;
The building construction method according to claim 1, further comprising a step of attaching the first horizontal member to the first floor outer wall panel.
前記一階用外壁パネルは、下端部に設けられたアンカー部材を有し、
前記固定工程では、前記第1側面部の基礎の立ち上がり部と前記アンカー部材とを固定することを特徴とする請求項2に記載の建物施工方法。
The first floor outer wall panel has an anchor member provided at the lower end,
The building construction method according to claim 2, wherein, in the fixing step, the rising portion of the foundation of the first side surface portion and the anchor member are fixed.
前記アンカー部材は、前記一階用外壁パネルに対する取り付け位置を上下に調整するための位置調整部を有することを特徴とする請求項3に記載の建物施工方法。   The said anchor member has a position adjustment part for adjusting the attachment position with respect to the said outer wall panel for 1st floors up and down, The building construction method of Claim 3 characterized by the above-mentioned. 前記アンカー部材は、前記第1側面部の基礎から上方に延出するアンカーボルトが挿通される貫通孔を有し、
前記第2設置工程は、前記貫通孔に挿通された前記アンカーボルトと、前記第1横架材とを連結部材により連結する工程を有することを特徴とする請求項3又は4に記載の建物施工方法。
The anchor member has a through hole through which an anchor bolt extending upward from the foundation of the first side surface portion is inserted;
5. The building construction according to claim 3, wherein the second installation step includes a step of connecting the anchor bolt inserted through the through hole and the first horizontal member with a connecting member. Method.
前記第2設置工程は、前記第1側面部において前記第1横架材よりも上部に水平方向に延出する第2横架材を取り付ける工程をさらに有し、
前記一階用外壁パネルは、前記第2横架材に対し、水平方向に並べて取り付けられる複数のパネルユニットを有することを特徴とする請求項2乃至5のいずれかに記載の建物施工方法。
The second installation step further includes a step of attaching a second horizontal member extending in the horizontal direction above the first horizontal member in the first side surface portion,
The building construction method according to any one of claims 2 to 5, wherein the first-floor outer wall panel has a plurality of panel units attached to the second horizontal member in a horizontal direction.
前記形成工程では、前記基礎形成領域において前記建設機械が設置されていた設置領域にコンクリートを打設して土間をさらに形成することを特徴とする請求項1乃至6のいずれかに記載の建物施工方法。
The building construction according to any one of claims 1 to 6, wherein in the forming step, concrete is placed in an installation area where the construction machine is installed in the foundation forming area to further form a soil. Method.
JP2018069523A 2018-03-30 2018-03-30 Building construction method Active JP7116574B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2018069523A JP7116574B2 (en) 2018-03-30 2018-03-30 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2018069523A JP7116574B2 (en) 2018-03-30 2018-03-30 Building construction method

Publications (2)

Publication Number Publication Date
JP2019178588A true JP2019178588A (en) 2019-10-17
JP7116574B2 JP7116574B2 (en) 2022-08-10

Family

ID=68278137

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2018069523A Active JP7116574B2 (en) 2018-03-30 2018-03-30 Building construction method

Country Status (1)

Country Link
JP (1) JP7116574B2 (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6089319U (en) * 1983-11-21 1985-06-19 ナショナル住宅産業株式会社 Structure of the lower part of the additional wall
JPS6124742A (en) * 1984-07-13 1986-02-03 ナショナル住宅産業株式会社 Structure of pillar
JPH0161312U (en) * 1987-10-09 1989-04-19
JPH10131495A (en) * 1996-10-30 1998-05-19 Natl House Ind Co Ltd Building method
JP2000291183A (en) * 1999-04-01 2000-10-17 Sekisui Chem Co Ltd Outer wall attaching structure and unit building
JP2001059298A (en) * 1999-08-20 2001-03-06 Sekisui House Ltd Fitting structure of external wall panel
US20080034706A1 (en) * 2004-09-06 2008-02-14 Hermann Preiss Construction Module
US20120168251A1 (en) * 2010-12-30 2012-07-05 Colonel August Baxter Self-climbing hoist, deck and scaffold platform system
JP2013096117A (en) * 2011-10-31 2013-05-20 Asahi Kasei Homes Co Building construction method
JP2014037705A (en) * 2012-08-15 2014-02-27 Nippon Steel & Sumitomo Metal Structure for fixing load bearing wall of thin-plate lightweight shape steel construction

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019132072A (en) 2018-02-01 2019-08-08 旭化成ホームズ株式会社 Foundation structure and construction method of the same

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6089319U (en) * 1983-11-21 1985-06-19 ナショナル住宅産業株式会社 Structure of the lower part of the additional wall
JPS6124742A (en) * 1984-07-13 1986-02-03 ナショナル住宅産業株式会社 Structure of pillar
JPH0161312U (en) * 1987-10-09 1989-04-19
JPH10131495A (en) * 1996-10-30 1998-05-19 Natl House Ind Co Ltd Building method
JP2000291183A (en) * 1999-04-01 2000-10-17 Sekisui Chem Co Ltd Outer wall attaching structure and unit building
JP2001059298A (en) * 1999-08-20 2001-03-06 Sekisui House Ltd Fitting structure of external wall panel
US20080034706A1 (en) * 2004-09-06 2008-02-14 Hermann Preiss Construction Module
US20120168251A1 (en) * 2010-12-30 2012-07-05 Colonel August Baxter Self-climbing hoist, deck and scaffold platform system
JP2013096117A (en) * 2011-10-31 2013-05-20 Asahi Kasei Homes Co Building construction method
JP2014037705A (en) * 2012-08-15 2014-02-27 Nippon Steel & Sumitomo Metal Structure for fixing load bearing wall of thin-plate lightweight shape steel construction

Also Published As

Publication number Publication date
JP7116574B2 (en) 2022-08-10

Similar Documents

Publication Publication Date Title
CN109577534B (en) Tool-based hanging die assembly type composite floor slab and construction method
US11814835B2 (en) Methods and apparatus for constructing multi-storey buildings
JP2011157720A (en) Method for constructing railway reinforced concrete rigid-frame structure viaduct
JP4235079B2 (en) Structure of joint between reinforced concrete column and steel beam
JP7116575B2 (en) Building construction method
JP2014095201A (en) Base isolation foundation construction method and precast concrete footing
KR101105883B1 (en) Basic mat constructing method of high rise concrete structure
JP2019178588A (en) Building construction method
KR20200107332A (en) The Simultaneous Construction Method for Wall and Slab of Building
JP2019132072A (en) Foundation structure and construction method of the same
JP3453895B2 (en) How to install anchor bolts on large steel frames
CN114382170A (en) Construction method for upper-layer prefabricated vertical component
KR101959068B1 (en) Jig structure for construction of building outer wall
JPH1129910A (en) Method for constructing concrete pier
JP2017031676A (en) Earthquake resistant reinforcement method and reinforcement device of existing building
JP2015101890A (en) Support structure and construction method
JP7025972B2 (en) Building construction method
JPH0681463A (en) Building method for stair
JP2012241311A (en) Half-precast beam, method of manufacturing half-precast beam, and method of constructing skeleton of building structure
JP7340390B2 (en) Support structure for heavy construction equipment
KR101285189B1 (en) External Drywall Unit Structure For PC Rahmen Structure, And Construction Method Thereof
RU46027U1 (en) CONSOLE-CROSSING FORESTS
JP2003213953A (en) Plant building constructing method
JP2002256643A (en) Construction method for steel-framed reinforced concrete(src) structure
KR20060028889A (en) Structure for plastic slab deck system and downward construction method using the same

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20210301

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20211222

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20220111

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20220309

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20220705

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20220729

R150 Certificate of patent or registration of utility model

Ref document number: 7116574

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150