JP4235079B2 - Structure of joint between reinforced concrete column and steel beam - Google Patents

Structure of joint between reinforced concrete column and steel beam Download PDF

Info

Publication number
JP4235079B2
JP4235079B2 JP2003362712A JP2003362712A JP4235079B2 JP 4235079 B2 JP4235079 B2 JP 4235079B2 JP 2003362712 A JP2003362712 A JP 2003362712A JP 2003362712 A JP2003362712 A JP 2003362712A JP 4235079 B2 JP4235079 B2 JP 4235079B2
Authority
JP
Japan
Prior art keywords
reinforced concrete
steel
steel beam
concrete column
plate portion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2003362712A
Other languages
Japanese (ja)
Other versions
JP2005126973A (en
Inventor
順子 細辻
丈士 片山
勝道 田渕
達男 中野
英二 友行
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Corp
Original Assignee
Takenaka Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Corp filed Critical Takenaka Corp
Priority to JP2003362712A priority Critical patent/JP4235079B2/en
Publication of JP2005126973A publication Critical patent/JP2005126973A/en
Application granted granted Critical
Publication of JP4235079B2 publication Critical patent/JP4235079B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Description

本発明は、鉄筋コンクリート柱と鉄骨梁を接合する接合部の構造に関するものである。   The present invention relates to a structure of a joint for joining a reinforced concrete column and a steel beam.

近年、地球環境への負荷の少ない循環型社会経済システムの構築の必要性に鑑み、建設工事の分野においても、建設資材の省資源化および循環利用を目指した建設リサイクルが推進されており、建設副産物の発生抑制、再使用、再生利用(再資源化)を追及したリサ
イクル建築システムの開発が強く望まれている。
In recent years, in view of the need to build a recycling-type socio-economic system that has a low impact on the global environment, construction recycling has been promoted in the field of construction work with the aim of conserving construction resources and recycling them. There is a strong demand for the development of a recycling building system that pursues the suppression, reuse, and recycling (recycling) of by-products.

プレキャスト鉄筋コンクリート柱(PCa柱)と鉄骨梁をピン接合とすることは、一般的に、剛接合の構造に比べて解体が容易になり、廃材の発生量の抑制や鉄骨材の再使用などの面で有効である。しかしながら、従来では、PCa柱と鉄骨梁をピン接合するにあたっては、純鉄骨造のピン接合と同様に、PCa柱の側面から跳ねだした1枚のガセットプレートに、鉄骨梁のウエブを、当て板(ジョイントプレート)を介してボルト接合していたため、クレーン等で支持した鉄骨梁を仮固定するための仮ボルトが必要であるばかりでなく、建方時と解体時の双方に、作業中、鉄骨梁を支持するクレーン等による仮設サポートが必要とされ、施工性や安全性の面で問題があった。   It is generally easier to disassemble precast reinforced concrete columns (PCa columns) and steel beams than rigid connections, reducing the amount of waste generated and reusing steel frames. It is effective in. However, conventionally, when pin-connecting a PCa column and a steel beam, the steel beam web is applied to a single gusset plate that has jumped out from the side surface of the PCa column in the same manner as a pin connection of a pure steel frame. Since the bolts are joined via the (joint plate), not only temporary bolts are required to temporarily fix the steel beams supported by cranes, but also during construction, both during construction and during dismantling. Temporary support by a crane or the like that supports the beam was required, and there were problems in terms of workability and safety.

尚、特許文献1には、PCa柱と鉄骨梁を剛接合する構造ではあるが、鉄骨梁の重量をPCa柱に預けた状態で、両者を接合する技術が記載されている。これは、図10、図11に示すように、PCa柱aの側面に突出部(アゴ)bを一体成形しておく一方、鉄骨梁cの端部には、ウエブの下半部と下フランジを切除して、前記突出部bに載る支持部dを形成すると共に、支持部dの先端と、支持部dの下部の先端に、夫々、垂直な接合プレートe,fを溶接し、上側の接合プレートeと上フランジ、下側の接合プレートfと下フランジ間に、夫々、補強プレートg,hを溶接しておき、鉄骨梁cの端部に形成された支持部dを前記突出部bに載置した状態で、上下の接合プレートe,fとPCa柱aの側面との間に、無収縮モルタルからなる充填材iを充填し、充填材iの硬化後、予めPCa柱aに埋設されたシースと、その両側に接合すべき鉄骨梁cの接合プレートe,e、f,fに形成された貫通孔にわたってPC鋼棒jを挿通し、PC鋼棒jの一端を圧着グリップ等によって固定し、PC鋼棒jの他端をジャッキ等で緊張させた状態で、圧着グリップ等によって固定したものである。   In addition, although it is the structure which joins a PCa pillar and a steel beam rigidly in patent document 1, the technique which joins both in the state which left the weight of the steel beam to the PCa pillar is described. As shown in FIGS. 10 and 11, a protrusion (ago) b is integrally formed on the side surface of the PCa column a, while the lower half of the web and the lower flange are formed at the end of the steel beam c. To form a support portion d that rests on the protrusion b, and welds vertical joining plates e and f to the tip of the support portion d and the tip of the lower portion of the support portion d, respectively. Reinforcing plates g and h are welded between the joining plate e and the upper flange, and the lower joining plate f and the lower flange, respectively, and the support portion d formed at the end of the steel beam c is used as the protrusion b. In a state of being mounted on the upper and lower joining plates e and f and the side surface of the PCa pillar a, a filler i made of non-shrink mortar is filled, and after the filler i is cured, embedded in the PCa pillar a in advance. Formed on the bonded plates e, e, f, and f of the steel beam c to be bonded to both sides thereof. PC steel rod j is inserted through the through-hole, one end of PC steel rod j is fixed with a crimping grip etc., and the other end of PC steel rod j is fixed with a crimping grip etc. It is.

上記の接合構造によれば、鉄骨梁cの端部に形成された支持部dを突出部bに載置することにより、鉄骨梁cの重量をPCa柱aに預けた状態で、両者を接合できるので、仮ボルトや作業中に鉄骨梁を支持するクレーン等による仮設サポートが不要で、建方を容易に行える等の利点がある。   According to said joining structure, both are joined in the state which left the weight of the steel beam c in the PCa pillar a by mounting the support part d formed in the edge part of the steel beam c on the protrusion part b. Therefore, there is an advantage that a temporary bolt or a temporary support by a crane or the like that supports the steel beam during work is unnecessary, and the construction can be easily performed.

しかしながら、この接合構造は、解体時の施工性まで考慮したものではなく、解体にあたっては、緊張状態にあるPC鋼棒jの抜取り、充填材iのはつり取りなど多くの煩雑な作業が必要である。また、鉄骨梁cの端部を、上記のような複雑な形状に加工してあるため、解体後、鉄骨梁cを、例えば、山留め壁の芯材、親杭横矢板工法の親杭、切梁などとして再利用する際、不要な部分(支持部d、接合プレートe,f、補強プレートg,h等)を切り落とす必要があり、材料ロスが多くて、リサイクル建築システムには不向きである。   However, this joining structure does not take into consideration the workability at the time of dismantling, and when disassembling, many complicated operations such as pulling out the PC steel rod j in tension and lifting off the filler i are necessary. . Moreover, since the end part of the steel beam c is processed into a complicated shape as described above, after dismantling, the steel beam c is, for example, a core material of a retaining wall, a parent pile of a main pile cross-sheet pile method, When it is reused as a beam or the like, it is necessary to cut off unnecessary portions (support portion d, joining plates e and f, reinforcing plates g and h, etc.), and there are many material losses, which are not suitable for a recycling building system.

特許第3407164号公報Japanese Patent No. 3407164

本発明は、上記の事柄に留意してなされたもので、その目的とするところは、建方時および解体時の施工性がよく、解体後、鉄骨梁等の再利用や柱の再生利用に際して、材料ロスが殆ど生じない、リサイクル建築システムに好適な鉄筋コンクリート柱と鉄骨梁の接合部の構造を提供することにある。   The present invention has been made in consideration of the above-mentioned matters, and the purpose of the present invention is good workability at the time of erection and dismantling, and after dismantling, when reusing steel beams or recycling of columns An object of the present invention is to provide a structure of a joint portion between a reinforced concrete column and a steel beam that is suitable for a recycled building system with little material loss.

上記の目的を達成するために、本発明が講じた技術的手段は、次のとおりである。即ち、請求項1に記載の発明は、水平板部と垂直板部と両板部にわたって設けられた補強部と
を備えた鋼製ブラケットの前記垂直板部を鉄筋コンクリート柱の側面にボルト接合し、前記水平板部に鉄骨梁を載置した状態で、当該鉄骨梁の下フランジを水平板部に、梁幅方向に2本並べて配置され且つ両者を貫通するボルトとそれに螺合するナットでボルト接合することにより鉄筋コンクリート柱と鉄骨梁をピン接合としたことを特徴としている。
In order to achieve the above object, the technical measures taken by the present invention are as follows. That is, in the invention according to claim 1, the vertical plate portion of the steel bracket provided with the horizontal plate portion, the vertical plate portion, and the reinforcing portion provided over both plate portions is bolted to the side surface of the reinforced concrete column, With the steel beam placed on the horizontal plate part , two lower flanges of the steel beam are arranged on the horizontal plate part side by side in the beam width direction and bolted with a bolt that penetrates both and a nut that is screwed to the bolt. By doing so, the reinforced concrete columns and steel beams are pin-joined.

請求項2に記載の発明は、互いに直交する方向の鉄骨梁が夫々鋼製ブラケットを介してボルト接合されていることを特徴としている。   The invention described in claim 2 is characterized in that steel beams in directions orthogonal to each other are bolted via steel brackets.

請求項3に記載の発明は、最上階の柱頭において、鋼製ブラケットを介してボルト接合された鉄骨梁と直交する方向の鉄骨梁を鉄筋コンクリート柱の柱頭に載置した状態で、当該鉄骨梁の下フランジを柱頭に、梁幅方向に2本並べて配置されたアンカーボルト又は雌ねじ状インサート金物によってボルト接合することにより鉄筋コンクリート柱と鉄骨梁をピン接合としたことを特徴としている。 According to the third aspect of the present invention, the steel beam in a direction orthogonal to the steel beam bolted through the steel bracket is placed on the top of the reinforced concrete column at the top of the top column. It is characterized in that the reinforced concrete column and the steel beam are pin-joined by bolting with two anchor bolts or female threaded insert hardware arranged side by side in the beam width direction with the lower flange as the column head.

尚、請求項1〜3に記載の発明において、鉄筋コンクリート柱としては、コンクリートの現場打ちによって構築された鉄筋コンクリート柱、工場又はサイトで成形されたプレキャスト鉄筋コンクリート柱の何れであってもよい。また、鋼製ブラケットの垂直板部を鉄筋コンクリート柱の側面にボルト接合するにあたっては、鉄筋コンクリート柱に埋設したアンカーボルト、雌ねじ状インサート金物、鉄筋コンクリート柱を貫通する通しボルトの何れを採用してもよい。   In the first to third aspects of the present invention, the reinforced concrete column may be a reinforced concrete column constructed by in-situ concrete casting or a precast reinforced concrete column formed at a factory or site. In addition, when the vertical plate portion of the steel bracket is bolted to the side surface of the reinforced concrete column, any of an anchor bolt embedded in the reinforced concrete column, a female threaded insert metal, and a through bolt penetrating the reinforced concrete column may be employed.

上記の構成によれば、鉄筋コンクリート柱と鉄骨梁をピン接合するにあたり、鉄筋コンクリート柱の側面にボルト接合した鋼製ブラケットや鉄筋コンクリート柱の柱頭に鉄骨梁を載置して、鉄骨梁の重量を鉄筋コンクリート柱に預けた状態で、下フランジのボルト接合を行えるので、クレーン等で支持した鉄骨梁を仮固定するための仮ボルトや、作業中、鉄骨梁を支持するクレーン等による仮設サポートが不要で、建方時の施工性がよく、解体の場合も、鉄骨梁の重量を鉄筋コンクリート柱に預けた状態で、ボルトの抜取りを行えるので、解体時の施工性がよい。   According to the above configuration, when pinning a reinforced concrete column and a steel beam, the steel beam is placed on the head of the steel bracket or reinforced concrete column bolted to the side of the reinforced concrete column, and the weight of the steel beam is reinforced. Since the lower flange bolts can be joined to the machine, the temporary bolts for temporarily fixing the steel beam supported by the crane and the temporary support by the crane supporting the steel beam during the work are unnecessary. In the case of dismantling, the workability at the time of dismantling is good because the bolts can be removed while the weight of the steel beam is left in the reinforced concrete column.

殊に、鉄骨梁や鋼製ブラケットはボルト接合であり、健全な状態で取り外すことができるので、100%の再利用が可能であり、鉄骨梁の端部には、下フランジにボルト孔を形成するだけで済むので、解体後の鉄骨梁を、例えば、山留め壁の芯材、親杭横矢板工法の親杭、切梁等として再利用する際、鉄骨梁の端部を切り落とす必要がなく、材料ロスが生じない。また、鉄筋コンクリート柱も、解体のうえ、鉄筋、アンカーボルト、雌ねじ状インサート金物の分離、再資源化が可能であり、骨材の再利用も可能である。従って、リサイクル建築システムに好適である。   In particular, steel beams and steel brackets are bolted and can be removed in a healthy state, allowing 100% reuse. Bolt holes are formed in the lower flange at the ends of steel beams. It is not necessary to cut off the end of the steel beam when reusing the steel beam after dismantling, for example, as a core material for a retaining wall, a main pile of a main pile cross-sheet pile method, a cutting beam, etc. There is no material loss. In addition, reinforced concrete columns can be disassembled, and the reinforcing bars, anchor bolts, female threaded insert hardware can be separated and recycled, and aggregates can be reused. Therefore, it is suitable for a recycling building system.

以下、本発明の実施形態を、図面を参照しながら説明するが、それによって本発明は限定されるものではない。図1は、リサイクル建築システムを採用した建物の概要を示す。図1において、1は鉄筋コンクリート柱(この例ではプレキャスト鉄筋コンクリート柱であるから、以下、プレキャスト鉄筋コンクリート柱1と記載する。)、2は鉄骨梁、3は折版屋根、4はコンクリートの現場打ちにより構築された1階の床構造スラブ、5は外壁を構成するプレキャスト鉄筋コンクリートパネルである。プレキャスト鉄筋コンクリート柱1の柱脚は、床構造スラブ4の剛に接合されている。   Hereinafter, embodiments of the present invention will be described with reference to the drawings, but the present invention is not limited thereby. FIG. 1 shows an outline of a building adopting a recycling building system. In FIG. 1, 1 is a reinforced concrete column (in this example, it is a precast reinforced concrete column, henceforth referred to as a precast reinforced concrete column 1), 2 is a steel beam, 3 is a folded roof, 4 is constructed by casting concrete on the spot The floor structure slab of the first floor, 5 is a precast reinforced concrete panel constituting the outer wall. The column base of the precast reinforced concrete column 1 is joined to the rigidity of the floor structure slab 4.

上記の建物においては、前記柱や外壁をフルプレキャスト化することにより、廃材の発生を抑制すると共に、骨材の再生利用を可能にしている。外壁を構成するプレキャスト鉄筋コンクリートパネル5は、化粧打ち放し仕上げとすることにより、外装仕上げ工事を省
力化すると共に、必要強度に合わせて配筋量を設定することによって、補強用の下地鉄骨を不要にしてあり、更に、解体時には、取り外したプレキャスト鉄筋コンクリートパネル5を地面に敷き並べて、建機の走行が可能な作業床として使用できるように配慮されている。また、基礎梁のない床構造スラブ4とする一方、工事前地盤レベルと工事後の設計GLレベルの調整により、切土と盛土の土量を均等化することによって、掘削残土の発生を抑制してある。
In the above-mentioned building, the pillars and the outer wall are made full-cast, thereby suppressing the generation of waste materials and enabling the reuse of aggregates. The precast reinforced concrete panel 5 that constitutes the outer wall is made with a decorative finish to save the exterior finishing work, and by setting the amount of reinforcement according to the required strength, it eliminates the need for a foundation steel frame for reinforcement. Furthermore, at the time of dismantling, it is considered that the removed precast reinforced concrete panels 5 are laid on the ground and can be used as a work floor on which construction equipment can travel. In addition, while the floor structure slab 4 has no foundation beam, the amount of cut and fill soil is equalized by adjusting the ground level before construction and the design GL level after construction. It is.

照明器具6、空調室内機7、空調室外機8、発電機9、防火シャッター10、配線配管ビットを形成する二重床11等の設備類としては、解体した他の建物の設備類が再使用されている。   Equipment such as lighting fixtures 6, air conditioner indoor units 7, air conditioner outdoor units 8, generators 9, fire shutters 10, double floors 11 forming wiring pipe bits, etc. are reused from facilities in other dismantled buildings Has been.

鉄骨梁2としては、モジュールの統一化による解体後の再利用を容易にするために、例えば、山留め材(山留め壁の芯材、親杭横矢板工法の親杭、切梁、仮設構台などである。)として用いるリース材と同じ断面のものが使用されている。   For the steel beam 2, in order to facilitate reuse after dismantling by unifying the modules, for example, a mountain retaining material (core material of a retaining wall, a parent pile of a main pile cross-sheet pile method, a cross beam, a temporary gantry, etc.) The same cross-section as the leasing material used.

プレキャスト鉄筋コンクリート柱1と鉄骨梁2の接合構造には、建方時および解体時の施工性を考慮して、鉄骨梁2の取付け、取外しが容易なように、次のようなピン接合が採用されている。   The joint structure between the precast reinforced concrete column 1 and the steel beam 2 adopts the following pin connection to facilitate installation and removal of the steel beam 2 in consideration of workability during construction and dismantling. ing.

即ち、図2、図3に示すように、プレキャスト鉄筋コンクリート柱1と鉄骨梁2をピン接合とするにあたり、水平板部12aと垂直板部12bと両板部12a,12bにわたって設けられた板状の補強部12cとを備えた鋼製ブラケット12の前記垂直板部12bをプレキャスト鉄筋コンクリート柱1の側面に、当該側面から先端が突出する状態に埋設されたアンカーボルト13によってボルト接合し、前記水平板部12aに鉄骨梁2を載置した状態で、当該鉄骨梁2の下フランジ2aを水平板部12aにボルト接合してある。14は、前記アンカーボルト13に螺合するナット、15は、前記下フランジ2aと水平板部12aを貫通するボルト、16は前記ボルト15に螺合するナットである。尚、鉄骨梁2の下フランジ2aを鋼製ブラケット12の水平板部12aに2本のボルト15で接合するにあたっては、図3に示すように、2本のボルト15を梁幅方向に並べて配置することによってプレキャスト鉄筋コンクリート柱1と鉄骨梁2のピン接合が実現される。   That is, as shown in FIG. 2 and FIG. 3, when the precast reinforced concrete column 1 and the steel beam 2 are pin-joined, a plate-like plate provided across the horizontal plate portion 12a, the vertical plate portion 12b, and both plate portions 12a and 12b. The vertical plate portion 12b of the steel bracket 12 provided with the reinforcing portion 12c is bolted to the side surface of the precast reinforced concrete column 1 by an anchor bolt 13 embedded in a state in which the tip protrudes from the side surface, and the horizontal plate portion With the steel beam 2 placed on 12a, the lower flange 2a of the steel beam 2 is bolted to the horizontal plate portion 12a. Reference numeral 14 denotes a nut that is screwed to the anchor bolt 13, 15 is a bolt that penetrates the lower flange 2 a and the horizontal plate portion 12 a, and 16 is a nut that is screwed to the bolt 15. When the lower flange 2a of the steel beam 2 is joined to the horizontal plate portion 12a of the steel bracket 12 with the two bolts 15, the two bolts 15 are arranged side by side in the beam width direction as shown in FIG. By doing so, the pin joint of the precast reinforced concrete pillar 1 and the steel beam 2 is implement | achieved.

また、最上階の柱頭においては、図2に示すように、前記鋼製ブラケット12を介して接合された鉄骨梁2と直交する方向の鉄骨梁2をプレキャスト鉄筋コンクリート柱1の柱頭に載置した状態で、当該鉄骨梁2の下フランジ2aを柱頭に、柱頭から上方へ突出したアンカーボルト13によってボルト接合してあるが、中間階梁の場合は、図4、図5に示すように、互いに直角な二方向の鉄骨梁2の夫々を、鋼製ブラケット12を介して接合することになる。尚、鉄骨梁2の下フランジ2aを柱頭に、柱頭から上方へ突出した2本のアンカーボルト13で接合するにあたっては、図3に示すように、2本のアンカーボルト13を梁幅方向に並べて配置することによってプレキャスト鉄筋コンクリート柱1と鉄骨梁2のピン接合が実現される。図2、図4に示すLは、屋根勾配を確保するための段差である。図2に示す17は、プレキャスト鉄筋コンクリート柱1の立設後、現場で柱頭に施工された天端レベル調整用のモルタルであり、プレキャスト鉄筋コンクリート柱1の柱頭が平滑で且つレベルの精度が確保できる場合は、モルタル17は省略できる。   Moreover, in the top of the capital of the top floor, as shown in FIG. 2, the steel beam 2 in a direction perpendicular to the steel beam 2 joined via the steel bracket 12 is placed on the capital of the precast reinforced concrete column 1. The lower flange 2a of the steel beam 2 is bolted to the stigma by anchor bolts 13 protruding upward from the stigma. In the case of an intermediate floor beam, as shown in FIGS. 4 and 5, they are perpendicular to each other. Each two-way steel beam 2 is joined via a steel bracket 12. When joining the lower flange 2a of the steel beam 2 to the stigma with two anchor bolts 13 protruding upward from the stigma, as shown in FIG. 3, the two anchor bolts 13 are arranged in the beam width direction. By arranging the pins, the pin connection between the precast reinforced concrete column 1 and the steel beam 2 is realized. L shown in FIGS. 2 and 4 is a step for securing a roof gradient. 2 shown in FIG. 2 is a mortar for adjusting the top level constructed on the head of the column after the precast reinforced concrete column 1 is erected. When the column head of the precast reinforced concrete column 1 is smooth and level accuracy can be secured The mortar 17 can be omitted.

鋼製ブラケット12として、図示の例では、水平板部12aと垂直板部12bの両側に板状の補強部12cを設けた箱状のものを使用しているが、補強部12cの形状や数及び位置などは適宜変更可能であり、鋼製ブラケット12の形状は図示のものに限定されるものではない。   In the example shown in the drawing, the steel bracket 12 is a box-shaped member provided with plate-like reinforcing portions 12c on both sides of the horizontal plate portion 12a and the vertical plate portion 12b. The position and the like can be changed as appropriate, and the shape of the steel bracket 12 is not limited to the illustrated one.

上記の接合構造によれば、例えば、予め、側面に鋼製ブラケット12がボルト接合され
たプレキャスト鉄筋コンクリート柱1を立設し、クレーン等で吊り上げた鉄骨梁2の端部を前記鋼製ブラケット12やプレキャスト鉄筋コンクリート柱1の柱頭に載置し、鉄骨梁2の重量をプレキャスト鉄筋コンクリート柱1に預けた状態で、下フランジ2aのボルト接合を行えるので、クレーン等で支持した鉄骨梁2を仮固定するための仮ボルトや、作業中、鉄骨梁2を支持するクレーン等による仮設サポートが不要で、建方時の施工性がよく、解体の場合も、鉄骨梁2の重量をプレキャスト鉄筋コンクリート柱1に預けた状態で、ボルトの抜取りを行えるので、解体時の施工性がよい。
According to the above-described joining structure, for example, the precast reinforced concrete column 1 with the steel bracket 12 bolted to the side surface is erected in advance, and the end of the steel beam 2 lifted by a crane or the like is attached to the steel bracket 12 or the like. In order to temporarily fix the steel beam 2 supported by a crane or the like because the lower flange 2a can be bolted with the steel beam 2 placed on the head of the precast reinforced concrete column 1 and the weight of the steel beam 2 being deposited in the precast reinforced concrete column 1. No temporary bolts or temporary support by a crane that supports the steel beam 2 during work is necessary, and the workability during construction is good. In the case of dismantling, the weight of the steel beam 2 was left in the precast reinforced concrete column 1 Since the bolts can be removed in the state, workability at the time of dismantling is good.

殊に、鉄骨梁2や鋼製ブラケット12はボルト接合であり、健全な状態で取り外すことができるので、100%の再利用が可能であり、鉄骨梁2の端部には、下フランジ2aにボルト孔を形成するだけで済むので、解体後の鉄骨梁2を、例えば、山留め壁の芯材、親杭横矢板工法の親杭、切梁等として再利用する際、鉄骨梁2の端部を切り落とす必要がなく、材料ロスが生じない。   In particular, the steel beam 2 and the steel bracket 12 are bolted and can be removed in a healthy state, so that 100% reuse is possible. The end of the steel beam 2 is connected to the lower flange 2a. Since it is only necessary to form a bolt hole, when the steel beam 2 after dismantling is reused as a core material of a retaining wall, a parent pile of a main pile cross-sheet pile method, a cut beam, etc., the end of the steel beam 2 There is no need to cut off and no material loss occurs.

また、プレキャスト鉄筋コンクリート柱1も、解体のうえ、鉄筋やアンカーボルト13を分離回収して、再資源化することが可能であり、骨材の再生利用も可能である。   Further, the precast reinforced concrete column 1 can be disassembled, separated and recovered from the reinforcing bars and the anchor bolts 13, and recycled, and the aggregate can be recycled.

図2〜図5に示した実施形態では、何れも、プレキャスト鉄筋コンクリート柱1に埋設したアンカーボルト13によって鋼製ブラケット12を取り付けているが、図6、図7に示すように、プレキャスト鉄筋コンクリート柱1の少なくとも一面には、アンカーボルト13に代えて、雌ねじ状インサート金物18を埋設し、当該雌ねじ状インサート金物18に螺合するボルト19で鋼製ブラケット12の垂直板部12bをボルト接合するようにして実施することも可能である。図7に示す20は雌ねじ状インサート金物18の内端に挿通したアンカー鉄筋である。   In each of the embodiments shown in FIGS. 2 to 5, the steel bracket 12 is attached by the anchor bolt 13 embedded in the precast reinforced concrete column 1. However, as shown in FIGS. 6 and 7, the precast reinforced concrete column 1 is used. In place of the anchor bolt 13, an internal thread-like insert metal 18 is embedded in at least one surface of the steel plate 12, and the vertical plate portion 12 b of the steel bracket 12 is bolted by a bolt 19 that is screwed into the internal thread-like insert metal 18. It is also possible to implement. Reference numeral 20 shown in FIG. 7 denotes an anchor rebar inserted through the inner end of the female screw-shaped insert 18.

この構成によれば、プレキャスト鉄筋コンクリート柱1の雌ねじ状インサート金物18を埋設した面が平坦になるので(アンカーボルト13先端の突出部がなくなるので)、プレキャスト鉄筋コンクリート柱1を製造する際、図7に示すように、上面が平坦な底型枠21を用いることができ、アンカーボルト13先端の突出部を挿入するための凹部を形成する必要がなく、底型枠21の構造を単純化できる利点がある。   According to this configuration, the surface of the precast reinforced concrete column 1 in which the internal thread-like insert hardware 18 is embedded becomes flat (since there is no protrusion at the tip of the anchor bolt 13), and therefore when the precast reinforced concrete column 1 is manufactured, FIG. As shown, the bottom mold 21 having a flat upper surface can be used, and there is no need to form a recess for inserting the protrusion at the tip of the anchor bolt 13, and the structure of the bottom mold 21 can be simplified. is there.

図示しないが、プレキャスト鉄筋コンクリート柱1の四面全てのアンカーボルト13及び柱頭のアンカーボルト13を雌ねじ状インサート金物18に置き換えて実施できる。また、プレキャスト鉄筋コンクリート柱1の側面に鋼製ブラケット12の垂直板部12bをボルト接合するにあたっては、前記アンカーボルト13や雌ねじ状インサート金物18に代え、図8、図9に示すように、プレキャスト鉄筋コンクリート柱1を貫通する通しボルト22を採用してもよい。   Although not shown, the anchor bolts 13 on all four sides of the precast reinforced concrete column 1 and the anchor bolts 13 on the stigma can be replaced with female threaded insert hardware 18. In addition, when bolting the vertical plate portion 12b of the steel bracket 12 to the side surface of the precast reinforced concrete column 1, instead of the anchor bolt 13 and the female threaded insert metal piece 18, as shown in FIGS. 8 and 9, precast reinforced concrete is used. A through bolt 22 penetrating the pillar 1 may be employed.

尚、図1〜図9では、何れもプレキャスト鉄筋コンクリート柱1を例にとって本発明の実施形態を説明したが、コンクリートの現場打ちによって構築される鉄筋コンクリート柱と鉄骨梁の接合部についても本発明が適用できることは勿論である。   1 to 9, the embodiment of the present invention has been described by taking the precast reinforced concrete column 1 as an example. However, the present invention is also applied to a joint portion between a reinforced concrete column and a steel beam constructed by spot casting of concrete. Of course you can.

リサイクル建築システムを採用した建物の概要を示す一部切欠き斜視図である。It is a partially cutaway perspective view showing an outline of a building adopting a recycled building system. 最上階における柱・梁の接合部の構造を示す一部切欠き側面図である。It is a partially notched side view which shows the structure of the junction part of the pillar and beam in the top floor. 最上階における柱・梁の接合部の構造を示す一部切欠き平面図である。It is a partially notched top view which shows the structure of the junction part of the pillar and beam in the top floor. 中間階における柱・梁の接合部の構造を示す一部切欠き側面図である。It is a partially notched side view which shows the structure of the junction part of the pillar and beam in an intermediate floor. 中間階における柱・梁の接合部の構造を示す一部切欠き平面図である。It is a partially notched top view which shows the structure of the junction part of the pillar and beam in an intermediate floor. 他の実施形態を示す一部切欠き側面図である。It is a partially notched side view which shows other embodiment. プレキャスト鉄筋コンクリート柱の断面図である。It is sectional drawing of a precast reinforced concrete pillar. 他の実施形態を示す一部切欠き側面図である。It is a partially notched side view which shows other embodiment. 一部切欠き平面図である。It is a partially cutaway plan view. 従来例を示す縦断側面図である。It is a vertical side view which shows a prior art example. 従来例を示す横断平面図である。It is a cross-sectional top view which shows a prior art example.

符号の説明Explanation of symbols

1 プレキャスト鉄筋コンクリート柱
2 鉄骨梁
2a 下フランジ
12 鋼製ブラケット
12a 水平板部
12b 垂直板部
12c 補強部
13 アンカーボルト
18 雌ねじ状インサート金物
22 通しボルト
DESCRIPTION OF SYMBOLS 1 Precast reinforced concrete pillar 2 Steel beam 2a Lower flange 12 Steel bracket 12a Horizontal flat plate part 12b Vertical plate part 12c Reinforcement part 13 Anchor bolt 18 Female thread insert metal fitting 22 Through bolt

Claims (3)

水平板部と垂直板部と両板部にわたって設けられた補強部とを備えた鋼製ブラケットの前記垂直板部を鉄筋コンクリート柱の側面にボルト接合し、前記水平板部に鉄骨梁を載置した状態で、当該鉄骨梁の下フランジを水平板部に、梁幅方向に2本並べて配置され且つ両者を貫通するボルトとそれに螺合するナットでボルト接合することにより鉄筋コンクリート柱と鉄骨梁をピン接合としたことを特徴とする鉄筋コンクリート柱と鉄骨梁の接合部の構造。 The vertical plate portion of the steel bracket provided with a horizontal plate portion, a vertical plate portion, and a reinforcing portion provided over both plate portions is bolted to a side surface of a reinforced concrete column, and a steel beam is placed on the horizontal plate portion. In this state, the reinforced concrete column and the steel beam are pin-joined by bolting the bottom flange of the steel beam to the horizontal plate part with two bolts arranged side by side in the beam width direction and a bolt that penetrates both of them and a nut that is screwed to it. The structure of the joint between a reinforced concrete column and a steel beam. 互いに直交する方向の鉄骨梁が夫々鋼製ブラケットを介してボルト接合されていることを特徴とする請求項1に記載の鉄筋コンクリート柱と鉄骨梁の接合部の構造。   The structure of the joint part of a reinforced concrete column and a steel beam according to claim 1, wherein steel beams in directions orthogonal to each other are bolted via steel brackets. 最上階の柱頭において、鋼製ブラケットを介してボルト接合された鉄骨梁と直交する方向の鉄骨梁を鉄筋コンクリート柱の柱頭に載置した状態で、当該鉄骨梁の下フランジを柱頭に、梁幅方向に2本並べて配置されたアンカーボルト又は雌ねじ状インサート金物によってボルト接合することにより鉄筋コンクリート柱と鉄骨梁をピン接合としたことを特徴とする請求項1に記載の鉄筋コンクリート柱と鉄骨梁の接合部の構造。 In the top floor of the stigma, a direction of the steel beam which is perpendicular to the bolt joined steel beams through a steel bracket in a state placed on the stigma of reinforced concrete column, the lower flange of the steel beam to stigma, the beam width direction 2. The reinforced concrete column and the steel beam according to claim 1, wherein the reinforced concrete column and the steel beam are pin-connected by bolting with two anchor bolts or female threaded insert hardware arranged side by side. Construction.
JP2003362712A 2003-10-23 2003-10-23 Structure of joint between reinforced concrete column and steel beam Expired - Fee Related JP4235079B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003362712A JP4235079B2 (en) 2003-10-23 2003-10-23 Structure of joint between reinforced concrete column and steel beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003362712A JP4235079B2 (en) 2003-10-23 2003-10-23 Structure of joint between reinforced concrete column and steel beam

Publications (2)

Publication Number Publication Date
JP2005126973A JP2005126973A (en) 2005-05-19
JP4235079B2 true JP4235079B2 (en) 2009-03-04

Family

ID=34642254

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003362712A Expired - Fee Related JP4235079B2 (en) 2003-10-23 2003-10-23 Structure of joint between reinforced concrete column and steel beam

Country Status (1)

Country Link
JP (1) JP4235079B2 (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4279846B2 (en) * 2006-03-24 2009-06-17 株式会社サニックス Reinforcement structure of wooden frame building
JP2008007949A (en) * 2006-06-27 2008-01-17 Toyota T & S Kensetsu Kk Skeleton system between precast concrete column or wall and beam
JP5042612B2 (en) * 2006-12-25 2012-10-03 新日本製鐵株式会社 Joint structure of concrete-filled steel pipe column and steel member
JP5697204B2 (en) * 2011-03-15 2015-04-08 戸田建設株式会社 Column / beam bracket connection method for prestressed concrete structures.
JP2013249705A (en) * 2012-06-04 2013-12-12 Mutsumi Giken Kk Construction method of tsunami embankment
JP6164479B2 (en) * 2013-09-25 2017-07-19 清水建設株式会社 Underground pit structure
JP6442314B2 (en) * 2015-02-06 2018-12-19 鹿島建設株式会社 Joint structure of reinforced concrete column and steel beam
KR101849940B1 (en) * 2017-04-27 2018-04-18 (주)하경엔지니어링 Bracket structure and construction method there of
CN107152563A (en) * 2017-06-02 2017-09-12 安徽奥睿德科技发展有限公司 A kind of Pipe installing mechanism for concrete column
CN108824202B (en) * 2018-07-05 2023-06-09 中交第二航务工程局有限公司 Support system for concrete cable-stayed bridge hanging basket installation and tower area beam cast-in-situ construction
JP7265417B2 (en) * 2019-05-31 2023-04-26 株式会社竹中工務店 Column-beam connection method
JP7256698B2 (en) * 2019-06-17 2023-04-12 大成建設株式会社 Joint structure of stepped beam

Also Published As

Publication number Publication date
JP2005126973A (en) 2005-05-19

Similar Documents

Publication Publication Date Title
JP4823790B2 (en) Column unit and method of building building using column unit
US7647742B2 (en) Construction method for SRC structured high rise building
JPH102018A (en) Building unit, unit building, and its constructing method
AU2020100657A4 (en) Methods and apparatus for constructing multi-storey buildings
JP4235079B2 (en) Structure of joint between reinforced concrete column and steel beam
KR101766807B1 (en) the rigid connection structure between precast concrete column and precast concrete girder and the rigid connection structure between precast concrete girder and precast concrete beam using the plate, the modular system using the same
CN202969586U (en) Prefabricated concrete beam-column anchor welding combined structure
CN107989228A (en) A kind of prefabricated steel reinforced concrete shear wall structure and its preparation and installation method
KR101277751B1 (en) Precast Concrete Blocks and Remodeling Reinforcing Construction Methods for Low and Middle-rise Beam-column Buildings by Using that Blocks
JP2011157720A (en) Method for constructing railway reinforced concrete rigid-frame structure viaduct
JP3878900B2 (en) Remodeling method to remove pillar of existing building
JP2011214221A (en) Stiffening girder of suspension bridge, and method for constructing the same
JP5662677B2 (en) Multistory building
CN102155095B (en) Arranging method of concrete reinforcements of steel rib of large-scale metallurgical workshop
KR20140137665A (en) Enlarged capital of steel framed reinforced concrete column and method for construction of the enlarged capital
JP2006299660A (en) Temporary receiving construction method and temporary receiving structure
CN113931304B (en) Detachable clamping groove assembly type beam column joint connecting structure
JP2007217108A (en) Method of supporting tower crane
KR20150120779A (en) Bracket for the horizontal frame of a one-way steel structure
CN209907886U (en) Adjustable assembled stair construction platform
KR20210007111A (en) Partial reinforced concrete permanent Cement Mortar form and method of constructing the same
KR101766805B1 (en) the hybrid joint construction between column plate and column
CN215054690U (en) Temporary steel wall-attached frame for roof on construction elevator
JP3830062B2 (en) Seismic reinforcement method for reinforced concrete buildings
JP4872301B2 (en) Construction method of RC structure

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060929

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080212

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080226

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080411

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080722

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080918

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20081209

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20081212

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111219

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Ref document number: 4235079

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111219

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121219

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121219

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131219

Year of fee payment: 5

LAPS Cancellation because of no payment of annual fees