JP2019073962A - Method and device for predicting leveling work enabling period of concrete and method for constructing concrete - Google Patents

Method and device for predicting leveling work enabling period of concrete and method for constructing concrete Download PDF

Info

Publication number
JP2019073962A
JP2019073962A JP2017235501A JP2017235501A JP2019073962A JP 2019073962 A JP2019073962 A JP 2019073962A JP 2017235501 A JP2017235501 A JP 2017235501A JP 2017235501 A JP2017235501 A JP 2017235501A JP 2019073962 A JP2019073962 A JP 2019073962A
Authority
JP
Japan
Prior art keywords
time
concrete
inclination information
penetration resistance
leveling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017235501A
Other languages
Japanese (ja)
Other versions
JP6936718B2 (en
Inventor
喜昭 竹本
Yoshiaki Takemoto
喜昭 竹本
深瀬 勇太郎
Yutaro Fukase
勇太郎 深瀬
亮介 齊藤
Ryosuke Saito
亮介 齊藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Publication of JP2019073962A publication Critical patent/JP2019073962A/en
Application granted granted Critical
Publication of JP6936718B2 publication Critical patent/JP6936718B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

To provide a method and device for predicting a leveling work enabling period of concrete capable of easily grasping a leveling work enabling period before starting a leveling work of a concrete surface and a method for constructing concrete.SOLUTION: The method includes: a step S1 for considering that an air temperature of a construction time zone and a temperature of concrete are in a correlation relationship, and for applying a predicted air temperature predicted in the construction time zone to a relation between inclination information of an approximate expression expressing a relation between a preliminarily grasped penetration resistance value and a lapse time and the temperature of concrete to calculate inclination information; steps S2, S3 for estimating a conductivity reduction time corresponding to the calculated inclination information from a relation between a time from a preliminarily grasped water injection time to the conductivity reduction time and the inclination information; a step S4 for estimating a relation between the penetration resistance value and the lapse time corresponding to the calculated inclination information; and steps S5, S6 for predicting a leveling time enabling period from the estimated relation between the penetration resistance value and the lapse time and the conductivity reduction time.SELECTED DRAWING: Figure 6

Description

本発明は、例えばコンクリートスラブなどのコンクリートの均し作業可能時期の予測方法、予測装置およびコンクリートの施工方法に関するものである。   The present invention relates to, for example, a prediction method of a leveling possible time of concrete such as a concrete slab, a prediction device, and a construction method of concrete.

従来、コンクリートスラブを施工する際には、プラントからミキサーで運ばれたフレッシュコンクリートを型枠上に打設した後、全体を決められた高さになるように均していく作業が行われている(例えば、特許文献1を参照)。コンクリートは時間の経過とともに硬化が進み、作業者が上に乗ることができる硬さになってから、ブリーディング水や端部の処理などを行い、手押しトロウェルや鏝などで表面を繰返し押えていく。   Conventionally, when constructing a concrete slab, after placing fresh concrete carried by a mixer from a plant on a formwork, an operation is carried out in which the whole is leveled to a predetermined height. (See, for example, Patent Document 1). The concrete hardens with the passage of time, and after it becomes hard enough for the operator to get on, treatment of bleeding water and ends etc. is carried out, and the surface is repeatedly pressed with a hand-held trowell or scissors.

この繰返しの押え作業は、コンクリート表面の平滑化、緻密化に必要な作業であり、スラブの良し悪しに大きな影響を与える。ところが、この押えタイミングは、作業者がコンクリート表面を指で触った硬さ、見た目の色、ブリーディング水の発生具合などで判断している。したがって、スラブの平滑性などの仕上がりの良さ、表面の緻密さなどの品質は、特に施工が難しい環境条件では作業者の経験に左右されやすい。   This repeated pressing operation is an operation necessary for smoothing and densifying the concrete surface, which greatly affects the quality of the slab. However, the pressing timing is determined by the hardness of the operator touching the concrete surface with a finger, the color of the appearance, the generation of bleeding water, and the like. Therefore, the finish quality such as the smoothness of the slab and the quality such as the fineness of the surface are likely to be influenced by the experience of the worker particularly in the environmental conditions where construction is difficult.

コンクリートスラブの打設計画においては、施工当日の気温、打設面積、打設速度などの条件を考慮して、作業者の人数や配置、作業機械の数などを決定する。この決定は、作業者の経験的な判断に任されており、打設速度によってコンクリートの打設位置が大まかに決められている。その後の押え作業のタイミングは、施工当日のコンクリートの硬化具合を作業者が指触や目視で判断し、成り行きで進められていく。したがって、コンクリートの打設計画においては、コンクリートの硬化具合に応じた作業員数や施工手順を計画しない。押え開始時刻や終了時刻は、施工当日の成り行き次第であり、施工計画としては曖昧な部分が多い。   In the concrete slab casting design plan, the number of workers, the number of workers, the number of working machines, etc. are determined in consideration of conditions such as air temperature, casting area and casting speed on the day of construction. This decision is left to the operator's empirical judgment, and the placement position of concrete is roughly determined by the placement speed. As for the timing of the subsequent pressing work, the operator judges the degree of hardening of the concrete on the day of the construction day by finger touch and visual observation, and proceeds according to the circumstances. Therefore, in the concrete design plan, the number of workers and the construction procedure according to the degree of hardening of the concrete are not planned. The press start time and end time depend on the construction of the construction day, and there are many vague parts as a construction plan.

コンクリートの硬化具合を把握する方法としては、JISの貫入抵抗試験(JIS A 1147:2007)がある。これは、コンクリートから粗骨材を除去したモルタルを試験体とし、規定の貫入針を垂直に刺した際の貫入抵抗値を求める方法である。この方法によれば、図1の測定例に示すように、測定結果をプロットしてコンクリートの始発時間(貫入抵抗値が例えば3.4N/mmになるまでの時間)、終結時間(貫入抵抗値が例えば28.0N/mmになるまでの時間)と、これらプロットの近似曲線から傾きAと切片Bおよび近似式を求めることができる。作業者は、経験的に貫入抵抗値0.5(N/mm)あたりの、網下駄を履いて少し足が沈む程度の硬さになってからコンクリートの上に乗ってブリーディング水の除去などの作業の前準備を始め、始発時間から押え作業を開始し、終結時間で作業を終えている。 As a method of grasping the degree of hardening of concrete, there is a penetration resistance test (JIS A 1147: 2007) of JIS. This is a method of determining the penetration resistance value when a mortar obtained by removing coarse aggregate from concrete is used as a test body and a specified penetration needle is pierced vertically. According to this method, as shown in the measurement example of FIG. 1, the measurement results are plotted and the initial development time of the concrete (time until the penetration resistance value becomes 3.4 N / mm 2 , for example), the termination time (penetration resistance) The slope A, the intercept B, and the approximate expression can be obtained from the value of, for example, 28.0 N / mm 2 ) and the approximate curve of these plots. Workers wear a neta geta and have hardness slightly sinking their feet about 0.5 (N / mm 2 ) of penetration resistance empirically, then ride on concrete and remove bleeding water etc. The preparation of the work is started, the pressing work is started from the first flight time, and the work is finished at the closing time.

ところが、この貫入抵抗値は硬化が進むコンクリートをその都度、リアルタイムに測定して得られるものであるため、この方法で予め押えタイミング(押え作業を開始できる時間)を予測することはできない。また、試験作業も手間が掛かり、現場での施工管理に使用するケースはほとんどなく、貫入抵抗試験はデータの取得が主目的となっている、といった問題がある。   However, since this penetration resistance value is obtained by measuring in real time each time the hardening proceeds, it is impossible to predict the pressing timing (the time when the pressing operation can be started) in advance by this method. In addition, the test work is also time-consuming, and there are few cases where it is used for on-site construction management, and there is a problem that the penetration resistance test is mainly intended to acquire data.

特開2015−203204号公報JP, 2015-203204, A

このため、コンクリート表面の均し作業(押え作業)を始める前に、均し作業を適正に行うことが可能な時期(均し作業可能時期)を容易に把握することのできる技術が求められていた。   For this reason, there is a need for a technology that can easily grasp the time when the leveling operation can be properly performed (time when the leveling operation is possible) before starting the leveling operation (pressing operation) of the concrete surface. The

本発明は、上記に鑑みてなされたものであって、コンクリート表面の均し作業を始める前に、均し作業可能時期を容易に把握することのできるコンクリートの均し作業可能時期の予測方法、予測装置およびコンクリートの施工方法を提供することを目的とする。   The present invention has been made in view of the above, and is a method of predicting the leveling time of concrete leveling operation time of the leveling operation time which can be easily grasped before the leveling operation of concrete surface is started. It aims to provide a prediction device and a concrete construction method.

上記した課題を解決し、目的を達成するために、本発明に係るコンクリートの均し作業可能時期の予測方法は、施工中のコンクリートの表面に対する均し作業を実施する前に、均し作業を行うのに好適な均し作業可能時期を予測するための方法であって、施工時間帯の気温とコンクリートの温度が相関関係にあるとみなして、施工時間帯に予想される予想気温を、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、コンクリートの温度の関係に当てはめることで、予想気温に対応する傾き情報を求めるステップと、求めた傾き情報を、予め把握されたフレッシュコンクリートを作製する際の注水時刻からコンクリートの導電率低下時刻までの時間と、傾き情報の関係に当てはめることで、求めた傾き情報に対応する導電率低下時刻を推定するステップと、求めた傾き情報に対応する貫入抵抗値と経過時間の関係を推定するステップと、推定した貫入抵抗値と経過時間の関係と、推定した導電率低下時刻から、コンクリートの均し作業可能時期を予測するステップとを備えることを特徴とする。   In order to solve the above-mentioned problems and achieve the object, the method for predicting the time of the leveling operation of concrete according to the present invention comprises performing the leveling operation before performing the leveling operation on the surface of concrete under construction It is a method to predict the leveling time that is suitable for work, and the air temperature in the construction time zone and the temperature of concrete are considered to be in correlation, and the predicted air temperature expected in the construction time zone is Obtaining inclination information corresponding to the expected air temperature by applying to the relation between the temperature of concrete and the inclination information of the approximate expression representing the relation between penetration resistance value and elapsed time obtained by the predetermined penetration resistance test which has been grasped; Apply the obtained tilt information to the relationship between tilt information and the time from the water injection time when producing fresh concrete that was grasped in advance to the conductivity decrease time of the concrete The steps of: estimating the conductivity decrease time corresponding to the determined inclination information; estimating the relationship between the penetration resistance value and the elapsed time corresponding to the determined inclination information; and the relationship between the estimated penetration resistance value and the elapsed time And a step of predicting the leveling time of concrete leveling operation from the estimated conductivity lowering time.

また、本発明に係るコンクリートの均し作業可能時期の予測装置は、施工中のコンクリートの表面に対する均し作業を実施する前に、均し作業を行うのに好適な均し作業可能時期を予測するための装置であって、施工時間帯の気温とコンクリートの温度が相関関係にあるとみなして、施工時間帯に予想される予想気温を、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、コンクリートの温度の関係に当てはめることで、予想気温に対応する傾き情報を求める手段と、求めた傾き情報を、予め把握されたフレッシュコンクリートを作製する際の注水時刻からコンクリートの導電率低下時刻までの時間と、傾き情報の関係に当てはめることで、求めた傾き情報に対応する導電率低下時刻を推定する手段と、求めた傾き情報に対応する貫入抵抗値と経過時間の関係を推定する手段と、推定した貫入抵抗値と経過時間の関係と、推定した導電率低下時刻から、コンクリートの均し作業可能時期を予測する手段とを備えることを特徴とする。   Moreover, the prediction device of the leveling operation possible time of concrete according to the present invention predicts the leveling possible operation time suitable for performing the leveling operation before performing the leveling operation on the surface of the concrete under construction. It is an apparatus for setting the temperature of the construction time zone and the temperature of the concrete, and it is regarded that there is a correlation, and the predicted air temperature expected in the construction time zone is a penetration obtained by a predetermined penetration resistance test grasped in advance A means for determining inclination information corresponding to the predicted air temperature by applying to the relation between the temperature of concrete and the inclination information of an approximate expression representing the relation between the resistance value and the elapsed time, and the obtained inclination information, fresh concrete grasped in advance The conductivity decrease time corresponding to the obtained inclination information by applying the relationship between the time from the water injection time at the time of producing the water to the conductivity decrease time of the concrete and the inclination information The means for estimating, the means for estimating the relationship between penetration resistance value and elapsed time corresponding to the obtained inclination information, the relationship between estimated penetration resistance value and elapsed time, and the leveling of concrete from the estimated conductivity decrease time And means for predicting a workable time.

また、本発明に係るコンクリートの施工方法は、上述したコンクリートの均し作業可能時期の予測方法を用いて均し作業可能時期を予測するステップと、コンクリートを打設するステップと、予測した均し作業可能時期に基づいて、コンクリートの表面に対する均し作業を実施するステップとを備えることを特徴とする。   Further, in the method of constructing concrete according to the present invention, there are a step of predicting the time when the leveling operation is possible, a step of casting the concrete, and a leveling which is predicted And performing the leveling operation on the surface of the concrete based on the workable period.

本発明に係るコンクリートの均し作業可能時期の予測方法によれば、施工中のコンクリートの表面に対する均し作業を実施する前に、均し作業を行うのに好適な均し作業可能時期を予測するための方法であって、施工時間帯の気温とコンクリートの温度が相関関係にあるとみなして、施工時間帯に予想される予想気温を、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、コンクリートの温度の関係に当てはめることで、予想気温に対応する傾き情報を求めるステップと、求めた傾き情報を、予め把握されたフレッシュコンクリートを作製する際の注水時刻からコンクリートの導電率低下時刻までの時間と、傾き情報の関係に当てはめることで、求めた傾き情報に対応する導電率低下時刻を推定するステップと、求めた傾き情報に対応する貫入抵抗値と経過時間の関係を推定するステップと、推定した貫入抵抗値と経過時間の関係と、推定した導電率低下時刻から、コンクリートの均し作業可能時期を予測するステップとを備えるので、コンクリート表面の均し作業を始める前に、均し作業可能時期を容易に把握することができるという効果を奏する。   According to the prediction method of the leveling operation possible time of concrete according to the present invention, the leveling operation possible time suitable for performing the leveling operation is predicted before performing the leveling operation on the surface of the concrete under construction The method to determine the temperature of the construction time zone and the temperature of the concrete are correlated, and the predicted air temperature expected in the construction time zone can be obtained by a predetermined penetration resistance test obtained in advance. A step of obtaining inclination information corresponding to the predicted air temperature by applying to the relation between the temperature of concrete and the inclination information of an approximate expression representing the relation between the resistance value and the elapsed time, and the calculated inclination information in advance. The conductivity decrease corresponding to the obtained inclination information by applying to the relation of the inclination information with the time from the water injection time at the time of manufacturing the time to the conductivity decrease time of the concrete The step of estimating time, the step of estimating the relationship between the penetration resistance value and the elapsed time corresponding to the obtained inclination information, the relationship between the estimated penetration resistance value and the elapsed time, and the estimated conductivity decrease time, the concrete Since the step of predicting the leveling possible time is provided, it is possible to easily grasp the leveling possible time before starting the leveling operation of the concrete surface.

また、本発明に係るコンクリートの均し作業可能時期の予測装置によれば、施工中のコンクリートの表面に対する均し作業を実施する前に、均し作業を行うのに好適な均し作業可能時期を予測するための装置であって、施工時間帯の気温とコンクリートの温度が相関関係にあるとみなして、施工時間帯に予想される予想気温を、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、コンクリートの温度の関係に当てはめることで、予想気温に対応する傾き情報を求める手段と、求めた傾き情報を、予め把握されたフレッシュコンクリートを作製する際の注水時刻からコンクリートの導電率低下時刻までの時間と、傾き情報の関係に当てはめることで、求めた傾き情報に対応する導電率低下時刻を推定する手段と、求めた傾き情報に対応する貫入抵抗値と経過時間の関係を推定する手段と、推定した貫入抵抗値と経過時間の関係と、推定した導電率低下時刻から、コンクリートの均し作業可能時期を予測する手段とを備えるので、コンクリート表面の均し作業を始める前に、均し作業可能時期を容易に把握することができるという効果を奏する。   Moreover, according to the prediction device of the leveling operation possible time of concrete according to the present invention, the leveling operation possible time suitable for performing the leveling operation before performing the leveling operation on the surface of the concrete under construction It is an apparatus for predicting the temperature of the construction time zone, and the temperature of the construction time zone is considered to be correlated with the temperature of concrete, and the predicted air temperature expected during the construction time zone is obtained by a predetermined penetration resistance test grasped beforehand. The slope information corresponding to the predicted air temperature is obtained in advance by grasping the slope information corresponding to the predicted air temperature by applying it to the slope information of the approximate expression representing the relation between the penetration resistance value and the elapsed time and the temperature of the concrete. The conductivity low corresponding to the inclination information obtained by applying the relationship between the time from the water injection time when producing fresh concrete to the conductivity decrease time of the concrete and the inclination information From the means for estimating time, the means for estimating the relationship between penetration resistance value and elapsed time corresponding to the obtained inclination information, the relationship between estimated penetration resistance value and elapsed time, and from the estimated conductivity decrease time, concrete Since a means for predicting the leveling possible time is provided, it is possible to easily grasp the leveling possible time before starting the leveling operation of the concrete surface.

また、本発明に係るコンクリートの施工方法によれば、上述したコンクリートの均し作業可能時期の予測方法を用いて均し作業可能時期を予測するステップと、コンクリートを打設するステップと、予測した均し作業可能時期に基づいて、コンクリートの表面に対する均し作業を実施するステップとを備えるので、予測した均し作業可能時期に基づいて均し作業を適正に行うことが可能となり、安定した品質のコンクリートを施工することができるという効果を奏する。   Further, according to the method of constructing concrete according to the present invention, the step of predicting the leveling possible period of time using the above-described method of predicting the leveling possible period of concrete, the step of placing concrete, and the prediction Since the step of performing the leveling operation on the surface of the concrete based on the leveling possible time is provided, it is possible to properly perform the leveling operation based on the predicted leveling possible time, and stable quality The effect of being able to construct the concrete of

図1は、JISによる貫入抵抗試験の測定例を示す図である。FIG. 1 is a view showing a measurement example of a penetration resistance test according to JIS. 図2は、コンクリートの温度Tと傾きAとの関係を示す図である。FIG. 2 is a view showing the relationship between the temperature T of the concrete and the inclination A. As shown in FIG. 図3は、導電率の時間変化の一例を示す図である。FIG. 3 is a view showing an example of the time change of the conductivity. 図4は、注水時刻から導電率低下時刻までの時間tと傾きAの関係を示す図である。FIG. 4 is a diagram showing the relationship between the time t from the water injection time to the conductivity decrease time and the slope A. As shown in FIG. 図5は、傾きAが56.9である場合の貫入抵抗値と経過時間の関係を示す図である。FIG. 5 is a diagram showing the relationship between the penetration resistance value and the elapsed time when the slope A is 56.9. 図6は、本発明に係るコンクリートの均し作業可能時期の予測方法の実施の形態を示すフローチャート図である。FIG. 6 is a flow chart diagram showing an embodiment of a method of predicting the leveling possible time of concrete according to the present invention. 図7は、本発明に係るコンクリートの均し作業可能時期の予測装置の実施の形態を示す入出力画面図である。FIG. 7 is an input / output screen view showing an embodiment of the prediction device of the leveling possible time of concrete according to the present invention. 図8は、貫入抵抗値における経過時間と各作業時刻の算出例を示す図である。FIG. 8 is a diagram showing an example of calculation of elapsed time and penetration time in penetration resistance value. 図9は、「予想気温」と「注水予定時刻」による予測装置の表示例を示す図である。FIG. 9 is a diagram showing a display example of the prediction device based on “expected temperature” and “scheduled water supply time”. 図10は、他のコンクリートの均し作業可能時期の予測装置の一例を示す入出力画面図である。FIG. 10 is an input / output screen diagram showing an example of a prediction device of another concrete leveling possible time. 図11は、「注水時刻」と「導電率低下時刻」による予測装置の表示例を示す図である。FIG. 11 is a view showing a display example of the prediction device based on “water injection time” and “conductivity decrease time”.

以下に、本発明に係るコンクリートの均し作業可能時期の予測方法、予測装置およびコンクリートの施工方法の実施の形態を図面に基づいて詳細に説明する。なお、この実施の形態によりこの発明が限定されるものではない。   EMBODIMENT OF THE INVENTION Below, the prediction method of the leveling operation possible time of the concrete which concerns on this invention, embodiment of the prediction apparatus, and the construction method of concrete are described in detail based on drawing. The present invention is not limited by the embodiment.

[コンクリートの均し作業可能時期の予測方法]
まず、本発明に係るコンクリートの均し作業可能時期の予測方法の実施の形態について説明する。
[How to predict the time when concrete can be leveled]
First, an embodiment of a method of predicting the leveling possible time of concrete according to the present invention will be described.

(基本原理)
まず、本発明の基本原理について説明する。
一般に、凝結過程にあるコンクリートについて、例えばJIS A 1147に記載の貫入抵抗試験を行い、経過時間ごとに貫入抵抗値をプロットすると、図1に示すような散布図が得られる。これらのプロットから、貫入抵抗値Pと経過時間tの関係は、t=A×Ln(P)+Bという対数近似式で表すことができる。ここで、Aは傾き(傾き情報)、Bは切片である。
(Basic principle)
First, the basic principle of the present invention will be described.
Generally, the concrete in the setting process is subjected to the penetration resistance test described in, for example, JIS A 1147, and when the penetration resistance value is plotted at each elapsed time, a scatter diagram as shown in FIG. 1 is obtained. From these plots, the relationship between the penetration resistance value P and the elapsed time t can be represented by a logarithmic approximation formula t = A × Ln (P) + B. Here, A is inclination (inclination information) and B is an intercept.

図2は、コンクリートの温度Tと傾きAの関係を例示したものである。この図に示すように、コンクリートの温度Tは、傾きAと相関が高いことがわかる。したがって、施工当日(施工時間帯)の予想気温が得られれば、コンクリートの温度と大きく異ならないことを前提として、この図から傾きAを求めることができる。   FIG. 2 illustrates the relationship between the temperature T of the concrete and the slope A. As shown in this figure, it can be seen that the concrete temperature T has a high correlation with the slope A. Therefore, if the predicted air temperature on the day of construction (construction time zone) is obtained, the slope A can be obtained from this figure on the premise that the temperature does not differ significantly from the temperature of the concrete.

一方、コンクリートに導電率計の電極を設置し、導電率を測定すると、図3に示すように導電率は徐々に上昇していくが、ある時刻から低下を開始する(図の例では12:50頃)。この導電率が低下を開始する時刻を導電率低下時刻というものとする。この導電率低下時刻は、コンクリート中のセメントの反応に関係しており、0.1(N/mm)の貫入抵抗値が発現する時刻と一致することがわかっている。 On the other hand, when an electrode of a conductivity meter is placed on concrete and the conductivity is measured, the conductivity gradually increases as shown in FIG. 3, but starts decreasing at a certain time (12 in the example of the figure: Around 50). The time when the conductivity starts to decrease is referred to as the conductivity decrease time. The conductivity lowering time is related to the reaction of cement in concrete, and is known to coincide with the time at which a penetration resistance of 0.1 (N / mm 2 ) is developed.

図4は、注水時刻から導電率低下時刻までの時間tと傾きAの関係を示す図である。この図に示すように、コンクリートの注水時刻(フレッシュコンクリート作製の際にプラントでセメントと水を混ぜた時間)から導電率低下時刻までの時間tは、傾きAと相関が高いことがわかる。すなわち、傾きAがわかれば、注水時刻から導電率低下時刻までの時間tが求められる。   FIG. 4 is a diagram showing the relationship between the time t from the water injection time to the conductivity decrease time and the slope A. As shown in FIG. As shown in this figure, it can be seen that the time t from the water pouring time of concrete (the time when cement and water are mixed in the plant at the time of preparation of fresh concrete) to the conductivity decreasing time has a high correlation with the slope A. That is, if the inclination A is known, the time t from the water injection time to the conductivity decrease time can be obtained.

例えば、コンクリート施工当日の予想気温を20℃とすると、傾きAは、図2の近似式にT=20を代入してA=56.9と求められる。この傾きA=56.9から図4の近似式より、注水時刻から導電率低下時刻までの時間tは188分と求められる。したがって、例えば、注水時刻を9:00と設定した場合、導電率低下時刻は188分後の12:08と求めることができる。   For example, assuming that the predicted air temperature on the day of concrete construction is 20 ° C., the inclination A is determined as A = 56.9 by substituting T = 20 into the approximate expression of FIG. From the slope A = 56.9 to the approximate expression in FIG. 4, the time t from the water injection time to the conductivity decrease time is determined to be 188 minutes. Therefore, for example, when the water injection time is set to 9:00, the conductivity decrease time can be obtained as 12:08 after 188 minutes.

図5は、傾きA=56.9の場合の貫入抵抗値と経過時間の関係を示したものである。上述したように、導電率低下時刻は、貫入抵抗値0.1(N/mm)となる時刻と一致するため、この図においては、この時刻を原点(0分)としている。この図より、貫入抵抗値が0.5(N/mm)に達するのは導電率低下時刻の12:08から92分後であるから13:40であり、始発時間の貫入抵抗値3.4(N/mm)に達するのは201分後の15:29であり、終結時間の貫入抵抗値28.0(N/mm)に達するのは321分後の17:29であるとして求めることができる。 FIG. 5 shows the relationship between the penetration resistance value and the elapsed time in the case of the slope A = 56.9. As described above, since the conductivity lowering time coincides with the time when the penetration resistance value becomes 0.1 (N / mm 2 ), in this figure, this time is set as the origin (0 minutes). From this figure, it is 13:40 since the penetration resistance value reaches 0.5 (N / mm 2 ) from 12:08 to 92 minutes after the conductivity decrease time, and the penetration resistance value of the first flight time is 3. As it is 15:29 after 201 minutes to reach 4 (N / mm 2 ) and 17:29 after 321 minutes to reach penetration resistance value 28.0 (N / mm 2 ) at termination time It can be asked.

(具体的な予測手順)
次に、本実施の形態に係る予測方法により、コンクリートスラブ施工時の押えタイミングを予測する場合の手順について説明する。
(Specific prediction procedure)
Next, the procedure in the case of predicting the pressing timing at the time of construction of a concrete slab will be described by the prediction method according to the present embodiment.

図6に示すように、まず、施工当日の予想気温から、図2を用いて傾きAを算出する(ステップS1)。次に、傾きAから、図4を用いて注水時刻から導電率低下時刻までの時間を算出する(ステップS2)。次に、注水時刻を設定して導電率低下時刻を算出するとともに(ステップS3)、傾きAを用いて貫入抵抗値と経過時間の関係を算出する(ステップS4)。   As shown in FIG. 6, first, from the predicted air temperature on the day of construction, a slope A is calculated using FIG. 2 (step S1). Next, from the inclination A, the time from the water injection time to the conductivity decrease time is calculated using FIG. 4 (step S2). Next, the water injection time is set to calculate the conductivity decrease time (step S3), and the slope A is used to calculate the relationship between the penetration resistance value and the elapsed time (step S4).

次に、算出した貫入抵抗値と経過時間の関係を用い、導電率低下時刻に経過時間を加算することで、各貫入抵抗値における時刻を算出する(ステップS5)。これにより、以下の作業時刻(均し作業可能時期)および時間を施工前に予測することが可能となる(ステップS6)。   Next, using the relationship between the calculated penetration resistance value and the elapsed time, the elapsed time is added to the conductivity reduction time to calculate the time at each penetration resistance value (step S5). As a result, it is possible to predict the following work time (time when the work can be done) and time before construction (step S6).

すなわち、コンクリートスラブ表面に人が乗れる時刻、押え開始時刻、押え終了時刻といった作業時刻を予測することが可能となる。人が乗れる時刻から押え開始時刻までの時間は、ブリーディング水除去、コンクリートスラブ端部の直しなどの前準備が可能な時間である。押え開始時刻から押え終了時刻までの時間は、押え作業が可能な時間である。   That is, it is possible to predict the working time such as the time when a person can get on the surface of the concrete slab, the pressing start time, and the pressing end time. The time from the time when a person can get on to the time to start pressing is a time where preparation for removal of bleeding water, repair of the concrete slab end, etc. is possible. The time from the press start time to the press end time is a time when the press work is possible.

このように、本実施の形態の予測方法によれば、施工当日の予想気温などを用いて、コンクリートスラブの押えタイミングを施工前に容易に予測することができる。これにより、施工に適切な作業者や施工機械の数、配置を計画することが可能となり、さらに、施工準備および施工管理に活かすことが可能となる。このため、安定した品質のコンクリートスラブを施工することができる。   As described above, according to the prediction method of the present embodiment, it is possible to easily predict the pressing timing of the concrete slab before the construction using the predicted air temperature on the day of construction and the like. As a result, it becomes possible to plan the number and arrangement of workers and construction machines suitable for construction, and it is possible to make use of it for construction preparation and construction management. For this reason, a concrete slab of stable quality can be constructed.

[コンクリートの均し作業可能時期の予測装置]
次に、本発明に係るコンクリートの均し作業可能時期の予測装置の実施の形態について説明する。
[Prediction device for concrete leveling time]
Next, an embodiment of the prediction device of the concrete workable time of concrete according to the present invention will be described.

本実施の形態に係るコンクリートの均し作業可能時期の予測装置は、上述したコンクリートの均し作業可能時期の予測方法を装置として具現化したものであり、例えば入力部、出力部、演算部、表示部とからなる。この予測装置は、例えばCPUを有するコンピュータ、メモリ、ディスプレイ等のハードウェア、これらハードウェア上で稼働するコンピュータプログラム等のソフトウェアにより構成することができる。   The prediction apparatus of the leveling operation possible time of concrete according to the present embodiment embodies the above method of predicting the leveling operation possible time of concrete as an apparatus, and, for example, an input unit, an output unit, a calculation unit, It consists of a display part. The prediction device can be configured, for example, by a computer having a CPU, hardware such as a memory or a display, or software such as a computer program running on the hardware.

図7は、本実施の形態に係るコンクリートの均し作業可能時期の予測装置の入出力画面の一例である。ディスプレイ等の表示部には、図のような画面が表示される。この画面には、入力部(INPUT)と、出力部(OUTPUT)が配置される。   FIG. 7: is an example of the input-output screen of the prediction apparatus of the leveling operation possible time of the concrete based on this Embodiment. A screen as illustrated is displayed on a display unit such as a display. In this screen, an input unit (INPUT) and an output unit (OUTPUT) are arranged.

入力部(INPUT)は、施工当日の「予想気温」を入力するための欄と、フレッシュコンクリート作製時のセメントと水を混ぜる「注水予定時刻」を入力するための欄からなる。各欄に対する入力値は、演算部の演算処理に使用される。   The input unit (INPUT) includes a field for inputting the "expected temperature" on the day of construction, and a field for inputting "scheduled water injection time" for mixing cement and water at the time of preparation of fresh concrete. The input values for each column are used in the arithmetic processing of the arithmetic unit.

出力部(OUTPUT)は、中間出力項目である「傾きA」と「導電率低下時刻」を出力するための欄と、最終出力項目である「人が乗れる時刻」、「押え作業開始時刻」、「押え作業終了時刻」、「作業開始までの時間」、「押え作業可能時間」を出力するための欄からなる。各欄には、演算部の演算処理によって算出された算出値が出力される。   The output unit (OUTPUT) has a column for outputting “slope A” and “conductivity decrease time” which are intermediate output items, “time when people can get on” which is final output items, “pressing work start time”, It consists of columns for outputting "pressing work end time", "time to work start", and "time for pressing work available". The calculated value calculated by the arithmetic processing of the arithmetic unit is output to each column.

入力部の「予想気温」と「注水予定時刻」の2つの項目を入力すると、演算部の演算処理により、傾きAが算出されるとともに、導電率低下時刻が算出される。そして、これらの算出値から「人が乗れる時刻」、「押え作業開始時刻」、「押え作業終了時刻」、「作業開始までの時間」、「押え作業可能時間」が算出される。これらの算出値は出力部の各欄に瞬時に出力表示される。したがって、この予測装置の利用者は、この入出力画面を通じて、上記の作業時刻および時間を容易に把握することができる。なお、図の例では、予想気温に20℃、注水予定時刻に9:00を入力した場合の出力結果を示している。   When two items of “expected air temperature” and “water injection scheduled time” of the input unit are inputted, the inclination A is calculated by the arithmetic processing of the arithmetic unit, and the conductivity decrease time is calculated. Then, from these calculated values, the “time when a person can ride”, “pressing start time”, “pressing end time”, “time until work start”, and “pressing possible time” are calculated. These calculated values are instantaneously output and displayed in each column of the output unit. Therefore, the user of this prediction apparatus can easily grasp the above-mentioned work time and time through this input / output screen. In the example shown in the figure, the output result is shown when the predicted temperature is 20 ° C. and the scheduled water supply time is 9:00.

(傾きAの算出方法)
次に、演算部による傾きAの算出方法について説明する。
演算部は、入力された施工当日の予想気温を用いて、図2に示す近似式から傾きAを求める。ただし、コンクリートの温度Tは、極端に予想気温と異ならないことが前提である。例えば、予想気温を20℃とした場合、図2の近似式にT=20が代入され、傾きAとして56.9が算出される。
(How to calculate the slope A)
Next, a method of calculating the inclination A by the calculation unit will be described.
The calculation unit obtains the slope A from the approximate expression shown in FIG. 2 using the input predicted air temperature on the day of construction. However, it is premised that the concrete temperature T does not differ from the predicted air temperature extremely. For example, when the predicted air temperature is 20 ° C., T = 20 is substituted into the approximate expression of FIG. 2, and 56.9 is calculated as the slope A.

(注水時間から導電率低下時刻までの時間の算出方法)
次に、演算部による注水時刻から導電率低下時刻までの時間の算出方法について説明する。
演算部は、入力された注水予定時刻を注水時刻として設定し、設定した注水時刻から導電率低下時刻までの時間を、図4に示す近似式から求める。例えば、上記のように傾きAとして56.9が算出された場合、図2の近似式にA=56.9が代入され、注水時刻から導電率低下時刻までの時間tとして、188分が算出される。
(How to calculate the time from water injection time to conductivity decrease time)
Next, a method of calculating the time from the water injection time to the conductivity decrease time by the calculation unit will be described.
The calculation unit sets the input scheduled water injection time as the water injection time, and obtains the time from the set water injection time to the conductivity decrease time from the approximate expression shown in FIG. 4. For example, when 56.9 is calculated as the slope A as described above, A = 56.9 is substituted in the approximate expression of FIG. 2, and 188 minutes is calculated as the time t from the water injection time to the conductivity decrease time. Be done.

(各作業時刻の算出方法)
次に、演算部による各作業時刻の算出方法について説明する。
演算部は、各作業時刻を、貫入抵抗値Pと経過時間tの関係を表す近似式(t=A×Ln(P)+B)から求める。ここで、上述したように、貫入抵抗値P=0.1(N/mm)は導電率低下時刻の貫入抵抗値に一致することから、この時刻を0分とするため、切片Bについては、P=0.1のときt=0となる値を採用する。この場合、上記の近似式は、t=A×(Ln(P)−log(0.1))=A×(Ln(P)+2.3)のように表すことができる。
(How to calculate each work time)
Next, a method of calculating each work time by the calculation unit will be described.
The calculation unit obtains each operation time from an approximate expression (t = A × Ln (P) + B) representing the relationship between the penetration resistance value P and the elapsed time t. Here, as described above, since the penetration resistance value P = 0.1 (N / mm 2 ) matches the penetration resistance value at the conductivity lowering time, in order to make this time 0 minutes, , P = 0.1 and a value of t = 0 is adopted. In this case, the above approximate expression can be expressed as t = A × (Ln (P) −log (0.1)) = A × (Ln (P) +2.3).

演算部は、上記の近似式を使用して貫入抵抗値Pにおける経過時間tおよびそれぞれの時刻を算出し、例えば図8に示すようなテーブルを作成する。例えば傾きA=56.9の場合には、近似式はt=56.9×(Ln(P)+2.3)となる。図8に示すように、この近似式に貫入抵抗値P=x(例えば、x=0.1,0.2,・・・,30.0)を代入して、各貫入抵抗値xに対応する経過時間tを算出する。   The calculation unit calculates an elapsed time t and each time of the penetration resistance value P using the above-mentioned approximate expression, and creates a table as shown in FIG. 8, for example. For example, in the case of the slope A = 56.9, the approximate expression is t = 56.9 × (Ln (P) +2.3). As shown in FIG. 8, the penetration resistance value P = x (for example, x = 0.1, 0.2,..., 30.0) is substituted into this approximate expression to correspond to each penetration resistance value x. Calculate the elapsed time t.

そして、既に算出した注水時刻から導電率低下時刻までの時間t=188分を注水時刻9:00に加算することで、導電率低下時刻12:08を算出する。この導電率低下時刻が経過時間0分に相当する。算出した導電率低下時刻に、近似式から算出した経過時間tを加算することで、各貫入抵抗値xに対応する時刻を算出する。このようにすることで、図8のようなテーブルを作成することができる。   Then, the conductivity decrease time 12: 08 is calculated by adding the time t = 188 minutes from the water injection time already calculated to the conductivity decrease time to the water injection time 9:00. This conductivity decrease time corresponds to an elapsed time of 0 minutes. The time corresponding to each penetration resistance value x is calculated by adding the elapsed time t calculated from the approximate expression to the calculated conductivity decrease time. By doing this, a table as shown in FIG. 8 can be created.

この図より、導電率低下時刻(経過時間0分)が12:08であるから、貫入抵抗値が0.5(N/mm)に達するのは91分後の13:40であり、始発時間の貫入抵抗値3.4(N/mm)に達するのは201分後の15:29、終結時間の貫入抵抗値28.0(N/mm)に達するのは321分後の17:29であることがわかる。演算部は、こうした時刻を算出値として出力部に出力する。また、演算部は、それぞれの対象となる時刻の差から作業開始までの時間、押え作業可能時間を算出して出力部に出力する。 From this figure, since the conductivity decrease time (elapsed time 0 minutes) is 12:08, the penetration resistance value reaches 0.5 (N / mm 2 ) at 13:40 after 91 minutes, which is the first occurrence. The penetration resistance value of time 3.4 (N / mm 2 ) is reached at 15:29 after 201 minutes, the penetration time of termination time 28.0 (N / mm 2 ) is reached after 17 minutes 321 minutes : It turns out that it is 29. The arithmetic unit outputs such time as a calculated value to the output unit. In addition, the calculation unit calculates the time until the start of the work and the pressable work available time from the difference between the respective target times, and outputs the time to the output unit.

上記の構成によれば、「予想気温」と「注水予定時刻」の2つの項目を入力するだけで、コンクリートスラブの施工前に、「人が乗れる時刻」、「押え作業開始時刻」、「押え作業終了時刻」、「作業開始までの時間」、「押え作業可能時間」を瞬時に得ることができる。   According to the above configuration, only by inputting the two items of "expected temperature" and "scheduled water injection time", "time when people can get on", "time for starting pressing work", "pressing time" before construction of a concrete slab It is possible to instantly obtain the work end time, the time until the work start, and the pressing workable time.

また、コンクリートスラブ施工日より前に、施工準備や押え作業が可能な時間を把握することができる。これにより、作業者や施工機械の数や配置準備を具体的に計画でき、作業終了時刻を把握することができる。また、これを施工管理に活かすことで、安定した品質のコンクリートスラブを施工することが可能となる。   In addition, before the concrete slab construction day, it is possible to grasp the time when construction preparation and pressing work are possible. As a result, the number of workers and construction machines and preparation for arrangement can be specifically planned, and the work end time can be grasped. In addition, by utilizing this for construction management, it becomes possible to construct a concrete slab of stable quality.

(予測装置の変形例1)
次に、本発明に係るコンクリートの均し作業可能時期の予測装置の実施の形態の変形例について説明する。
(Modification 1 of prediction device)
Next, a modification of the embodiment of the prediction device of the leveling operation possible time of concrete according to the present invention will be described.

上記の実施の形態に係るコンクリートの均し作業可能時期の予測装置は、図7の入出力画面に示したように「予想気温」と「注水予定時刻」を基にして、均し作業に関する時刻および時間を施工日よりも前に予測することができる。   The prediction device of the leveling operation possible time of concrete according to the above-mentioned embodiment is, as shown in the input / output screen of FIG. 7, a time related to the leveling operation based on the "expected temperature" and the "scheduled water injection time". And time can be predicted before the date of construction.

ところが、この画面表示では、多くのミキサー車がコンクリートを搬入し、スラブとして打設していく施工現場においては、スラブのどの位置のコンクリートについての時刻なのかを把握しにくくなるおそれがある。   However, in this screen display, at a construction site where many mixer cars carry in concrete and cast it as a slab, it may be difficult to grasp at which position of the slab the time for the concrete is.

そこで、本変形例1では、こうした問題を解決し、予測装置を現場管理ツールとして活用するために、図7のように得られる均し作業に関する時刻を、視覚的に分かりやすく表示する。この本変形例1について以下に説明する。   Therefore, in the first modification, in order to solve such a problem and to utilize the prediction device as a field management tool, the time related to the leveling operation obtained as shown in FIG. 7 is visually displayed in an easily understandable manner. The present modification 1 will be described below.

本変形例1では、図9の入出力画面に示すように、コンクリートを打設する現場の施工範囲に対してミキサー車1台ごとにNo.1、No.2、・・・のように番号を割り当ててメッシュを区切り、各メッシュについて「予想気温」と「注水予定時刻(図では注水時刻と表示)」を入力可能なようにする。メッシュの数は、例えば以下の手順で設定することができる。   In the first modification, as shown in the input / output screen of FIG. 9, the number of No. 1, No. 2,... Is assigned to separate meshes, so that it is possible to input "expected temperature" and "scheduled water injection time (displayed as water injection time in the figure)" for each mesh. The number of meshes can be set, for example, by the following procedure.

(1)ミキサー車1台に積むコンクリートの体積を、計画しているコンクリートの厚さで割ることで、1台のミキサー車で打設可能な面積を求める。
(2)上記(1)で求めた打設可能な面積をコンクリートの打設幅で割ることで、ミキサー車1台における打設長さを求める。コンクリートの打設幅は作業者の施工と管理のしやすさの観点からおおよそ2mであり、ミキサー車1台の積載量は通常4.25mであるので、例えばコンクリートの厚さが0.25mの場合は、打設長さは8.5mとなる。
(3)コンクリートを打設する現場の1辺長さを、ミキサー車1台における打設長さで割ることで、メッシュの数を設定する。図10の例では、平面視で矩形状の施工範囲を横方向に4個のメッシュに分割した場合を示している。
(1) The volume of concrete loaded on one mixer vehicle is divided by the thickness of the planned concrete to obtain the area which can be cast by one mixer vehicle.
(2) The castable length of one mixer car is obtained by dividing the castable area obtained in the above (1) by the casted width of concrete. The placement width of concrete is approximately 2 m from the viewpoint of the operator's ease of construction and management, and the loading capacity of one mixer truck is usually 4.25 m 3 , so for example, the thickness of concrete is 0.25 m In the case of, the casting length is 8.5m.
(3) The number of meshes is set by dividing the length of one side of the site where concrete is to be placed by the placement length of one mixer vehicle. In the example of FIG. 10, the case where the construction range of a rectangular shape is divided | segmented into four meshes in the horizontal direction by planar view is shown.

さて、各メッシュに「予想気温」と「注水予定時刻」を入力すると、演算部の演算処理と出力部の出力表示処理により、そのメッシュの「押え作業開始時刻」、「押え作業終了時刻」および「押え作業可能時間」が出力表示される。なお、図9の例では、「注水予定時刻」を「注水時刻」と表示し、「押え作業開始時刻」、「押え作業終了時刻」および「押え作業可能時間」をそれぞれ「開始時刻」、「終了時刻」および「作業時間」として表示する場合を示している。また、画面上部には、左から順に「INPUT」キー1、「+10min」キー2、「OUTPUT」キー3、「OUTPUT」キー4が配置されている。「INPUT」キー1は各メッシュの「予想気温」、「注水時刻」を入力する際の操作キー、「+10min」キー2は後続メッシュの注水時刻を自動的に10分加算する際の操作キー、「OUTPUT」キー3は各メッシュの「開始時刻」、「終了時刻」を出力表示する際の操作キー、「OUTPUT」キー4は各メッシュの「作業時間」を出力表示する際の操作キーである。   Now, when "expected temperature" and "water injection scheduled time" are input to each mesh, the "pressing start time", "pressing end time", and the pressing end time of the mesh are calculated by the calculation processing of the calculation unit and the output display processing of the output unit “Pressing available time” is displayed. In the example of FIG. 9, “water injection scheduled time” is displayed as “water injection time”, “pressing work start time”, “pressing work end time” and “pressing work possible time” are respectively “start time” and “start time” It shows a case where it is displayed as "end time" and "working time". In the upper part of the screen, an "INPUT" key 1, a "+10 min" key 2, a "OUTPUT" key 3 and an "OUTPUT" key 4 are disposed in order from the left. “INPUT” key 1 is an operation key for inputting “expected temperature” and “water injection time” of each mesh, and “+10 min” key 2 is an operation key for automatically adding water injection time of the following mesh for 10 minutes, "OUTPUT" key 3 is an operation key for outputting and displaying "start time" and "end time" of each mesh, and "OUTPUT" key 4 is an operation key for outputting and displaying "working time" of each mesh .

また、時間の経過とともに気温の変化(例えば25℃→28℃)が考えられる場合は、該当するメッシュ番号(例えば途中のメッシュNo.12)において予想気温(28℃)を入力する。これにより、最新の予想気温に応じた各時刻と作業時間が表示される。   Further, when a change in air temperature (for example, 25 ° C. → 28 ° C.) can be considered with the passage of time, an expected air temperature (28 ° C.) is input in the corresponding mesh number (for example, mesh No. 12 in the middle). Thereby, each time and working time according to the latest predicted air temperature are displayed.

また、注水時刻を用いれば、コンクリートの打設計画に応じて時間あたりのミキサー車の台数を決めることができる。例えば、図9において時間あたり6台のミキサー車を現場に入れる計画とした場合、No.1の注水時刻を8:30とすれば、No.2〜No.11までは自動的に注水時刻に10分間隔が加算されて各メッシュに各時刻および作業時間が表示される。   Also, if the water injection time is used, the number of mixers per hour can be determined according to the concrete design plan. For example, assuming that six mixer cars per hour are planned to be put on site in FIG. 9, if the water injection time of No. 1 is 8:30, No. 2 to No. 11 are automatically injected at the water injection time. The 10-minute interval is added and each time and working time are displayed on each mesh.

このように、本変形例1によれば、図9に示すような入出力画面で「予想気温」と「注水時刻(注水予定時刻)」を入力することで、各時刻と作業時間をメッシュごとに予測することができる。このため、多くのミキサー車がコンクリートを搬入し、スラブとして打設していく施工現場において、スラブのどの位置のコンクリートについての「押え作業開始時刻」、「押え作業終了時刻」、「押え作業可能時間」であるのかを視覚的に分かりやすく把握できるようになるので、現場の施工管理を容易に行うことができる。   As described above, according to the first modification, by inputting “expected temperature” and “water injection time (water injection scheduled time)” on the input / output screen as shown in FIG. Can be predicted. For this reason, at the construction site where many mixer cars carry in concrete and place them as slabs, the "pressing start time", "pressing end time", and "pressing work possible" for concrete at any position of the slab Since it becomes possible to visually grasp whether it is "time" in an easy-to-understand manner, construction management on site can be easily performed.

(予測装置の変形例2)
上記の変形例1は、類似の入出力画面の予測装置を視覚的に分かりやすく表示する場合にも適用可能である。
(Modification 2 of prediction device)
The above-mentioned modification 1 is applicable also to the case where the prediction device of the similar input / output screen is displayed in an easily understandable manner.

類似の入出力画面の予測装置としては、例えば、本発明に関連して本特許出願人が特願2017−200254号(現時点で未公開)で提案した「コンクリートの均し作業可能時期の予測装置」が挙げられる。この予測装置は、施工中のコンクリートの導電率を測定し、コンクリートの導電率が低下する導電率低下時刻を求める手段と、求めた導電率低下時刻を、予め把握されたフレッシュコンクリートを作製する際のセメントと水を混ぜる注水時刻からコンクリートの導電率低下時刻までの時間と、所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報の関係に当てはめることで、求めた導電率低下時刻に対応する傾き情報を求める手段と、求めた傾き情報に対応する貫入抵抗値と経過時間の関係を推定する手段と、推定した貫入抵抗値と経過時間の関係と、求めた導電率低下時刻から、コンクリートの均し作業可能時期を予測する手段とを備えるものである。   As a prediction device of a similar input / output screen, for example, a prediction device of “concrete leveling operation possible time period” proposed by the present patent applicant in the context of the present invention in Japanese Patent Application No. 2017-200254 (currently undisclosed) "Is mentioned. This prediction device measures the conductivity of the concrete under construction, and obtains the conductivity decrease time when the conductivity of the concrete decreases, and when preparing the fresh concrete in which the conductivity decrease time obtained is grasped in advance. The time from the water injection time of mixing cement and water to the conductivity decrease time of concrete, and the relationship of the inclination information of the approximate expression representing the relationship between the penetration resistance value obtained by the predetermined penetration resistance test and the elapsed time, A means for obtaining inclination information corresponding to the determined conductivity lowering time, a means for estimating the relationship between the penetration resistance value and the elapsed time corresponding to the obtained inclination information, a relationship between the estimated penetration resistance value and the elapsed time, and And a means for predicting the leveling time of concrete leveling operation from the conductivity lowering time.

より具体的な予測手順としては、コンクリートサンプルを採取して注水時刻を記録するとともに、導電率の測定を開始する。その後、注水時刻から導電率低下時刻までの時間を算出し、所定の近似式から傾きAを算出して、傾きAを用いて貫入抵抗値と経過時間の関係を算出する。算出した貫入抵抗値と経過時間の関係を用いて、導電率低下時刻に経過時間を加算することで、各貫入抵抗値における時刻を算出する。これにより、「押え作業開始時刻」、「押え作業終了時刻」、「押え作業可能時間」を施工前に予測することが可能となる。   As a more concrete prediction procedure, while taking a concrete sample and recording water injection time, measurement of conductivity is started. Thereafter, the time from the water injection time to the conductivity decrease time is calculated, the slope A is calculated from a predetermined approximate expression, and the relation between the penetration resistance value and the elapsed time is calculated using the slope A. The time at each penetration resistance value is calculated by adding the elapsed time to the conductivity lowering time using the relationship between the calculated penetration resistance value and the elapsed time. As a result, it becomes possible to predict "pressing start time", "pressing end time", and "time available for pressing" before construction.

図10は、この予測装置の入出力画面の例である。図7とよく似た表示形態である。図10に示すように、この予測装置では、「注水時刻」と「導電率低下時刻」を基にして、均し作業に関する時刻と作業時間を均し作業の開始前に予測する。この画面表示の場合も、多くのミキサー車がコンクリートを搬入する施工現場では、スラブのどの位置のコンクリートについての時刻なのかを把握しにくくなるおそれがある。そこで、本変形例2では、上記の変形例1と同様に、均し作業に関する時刻を、視覚的に分かりやすく表示する。   FIG. 10 is an example of an input / output screen of this prediction device. It is a display form similar to FIG. As shown in FIG. 10, this prediction device predicts the time and work time related to the leveling operation before the start of the leveling operation based on the “water injection time” and the “conductivity decrease time”. Also in the case of this screen display, at a construction site where many mixer vehicles carry in concrete, it may be difficult to grasp at which position of the slab the concrete is at the time of concrete. Therefore, in the second modification, as in the first modification, the time relating to the leveling operation is displayed in an easily understandable manner.

本変形例2では、図11の入出力画面に示すように、コンクリートを打設する現場の施工範囲に対してミキサー車1台ごとにNo.1、No.2、・・・のように番号を割り当ててメッシュを区切る。そして、ミキサー車からコンクリートサンプルを採取したメッシュに「注水時刻」と「導電率低下時刻」を入力可能なようにする。メッシュの数は、上記の変形例1と同様の方法で設定することができる。   In the second modification, as shown in the input / output screen of FIG. 11, the number of No. 1, No. 2,... Assign to divide the mesh. Then, “water injection time” and “conductivity decrease time” can be input to the mesh obtained by collecting concrete samples from the mixer vehicle. The number of meshes can be set by the same method as that of the first modification described above.

サンプルを採取するミキサー車は任意であるが、通常は1台目(図11のNo.1)から採取する方が分かりやすい。No.2以降は、ミキサー車の時間あたりの台数に応じて、開始時刻(押え作業開始時刻)と終了時刻(押え作業終了時刻)に自動的に加算する。図11には、注水時刻を10分ずつ自動的に加算した結果をNo.2〜No.4まで表示している。一方、例えば途中のNo.3からサンプルを採取する場合は、No.1とNo.2の各作業時間から10分引いて表示することができる。   Although a mixer truck for collecting samples is optional, it is usually easier to understand if it is collected from the first unit (No. 1 in FIG. 11). In No. 2 and later, the start time (pressing start time) and the end time (pressing end time) are automatically added according to the number of mixer cars per hour. In FIG. 11, the results of automatically adding the water injection time by 10 minutes are displayed from No. 2 to No. 4. On the other hand, for example, when collecting a sample from No. 3 on the way, it can be displayed by subtracting 10 minutes from each working time of No. 1 and No. 2.

また、打設途中でサンプルを再度採取して導電率低下時刻を測定することができる場合(例えばNo.5からサンプル採取)は、図11のNo.6以降は改めて10分加算した各作業時刻を表示することができる。   In addition, when it is possible to collect the sample again during the placement and measure the conductivity decrease time (for example, sample collection from No. 5), each operation time added 10 minutes again with No. 6 and later in FIG. Can be displayed.

なお、図11の例では、画面上部に左から順に「INPUT」キー1、「+10min」キー2、「OUTPUT」キー3、「OUTPUT」キー4が配置されている。「INPUT」キー1は各メッシュの「注水時刻」、「導電率低下時刻」を入力する際の操作キー、「+10min」キー2は後続メッシュの注水時刻を自動的に10分加算する際の操作キー、「OUTPUT」キー3は各メッシュの「開始時刻」、「終了時刻」を出力表示する際の操作キー、「OUTPUT」キー4は各メッシュの「作業時間」を出力表示する際の操作キーである。   In the example of FIG. 11, the "INPUT" key 1, the "+10 min" key 2, the "OUTPUT" key 3 and the "OUTPUT" key 4 are arranged in order from the left at the top of the screen. "INPUT" key 1 is an operation key for inputting "water injection time" and "conductivity decrease time" of each mesh, and "+10 min" key 2 is an operation for automatically adding water injection time of the subsequent mesh for 10 minutes The key, "OUTPUT" key 3 are operation keys for outputting and displaying the "start time" and "end time" of each mesh, and the "OUTPUT" key 4 is an operation key for outputting and displaying the "working time" of each mesh It is.

このように、本変形例2によれば、図11に示すような入出力画面で「注水時刻」と「導電率低下時刻」を入力することで、各時刻と作業時間をメッシュごとに予測することができる。このため、多くのミキサー車がコンクリートを搬入し、スラブとして打設していく施工現場において、スラブのどの位置のコンクリートについての「押え作業開始時刻」、「押え作業終了時刻」、「押え作業可能時間」であるのかを視覚的に分かりやすく把握できるようになるので、現場の施工管理を容易に行うことができる。   As described above, according to the second modification, each time and the operation time are predicted for each mesh by inputting “water injection time” and “conductivity decrease time” on the input / output screen as shown in FIG. be able to. For this reason, at the construction site where many mixer cars carry in concrete and place them as slabs, the "pressing start time", "pressing end time", and "pressing work possible" for concrete at any position of the slab Since it becomes possible to visually grasp whether it is "time" in an easy-to-understand manner, construction management on site can be easily performed.

[コンクリートの施工方法]
次に、本発明に係るコンクリートの施工方法の実施の形態について、コンクリートスラブを施工する場合を例にとり説明する。
[Concrete construction method]
Next, an embodiment of a method of constructing concrete according to the present invention will be described by taking a case of constructing a concrete slab as an example.

まず、コンクリートスラブを施工する前に、上述したコンクリートの均し作業可能時期の予測方法を用いて均し作業可能時期を予測する。これにより、施工前に「人が乗れる時刻」、「押え作業開始時刻」、「押え作業終了時刻」、「作業開始までの時間」、「押え作業可能時間」を把握することが可能となる。   First, before constructing a concrete slab, the leveling operation possible time is predicted using the above-described prediction method of the leveling operation possible time of concrete. Thereby, it becomes possible to grasp "time when a person can get on", "pressing start time", "pressing end time", "time until start of work", and "time available for holding work" before construction.

次に、フレッシュコンクリートを型枠上に打設してコンクリートスラブを施工する。そして、「人が乗れる時刻」になったら、作業員が硬化中のコンクリートスラブ上に乗り、ブリーディング水や端部の処理などの作業を行う。この作業は、「作業開始までの時間」内に終えるように計画的に実施する。その後、「押え作業開始時刻」になったら、手押しトロウェルや鏝などで表面を繰返し押えていく。この作業は「押え作業可能時間」内に終えるように計画的に実施し、「押え作業終了時刻」で作業を終了する。   Next, fresh concrete is cast on a form and a concrete slab is constructed. Then, when it is "time when people can get on", a worker gets on the hardened concrete slab and carries out work such as treatment of bleeding water and ends. This work is planned to be completed within the "time to work start". After that, when the “pressing start time” is reached, the surface is repeatedly pressed with a hand-held trowell or a hook. This work is performed in a planned manner so as to finish within the “pressing work possible time”, and the work is finished at “the pressing work end time”.

このように、本実施の形態によれば、施工前に予測した均し作業可能時期に基づいて、コンクリートスラブの表面に対する均し作業を適正に行うことが可能となる。これにより、安定した品質のコンクリートスラブを施工することができる。   As described above, according to the present embodiment, it is possible to properly perform the leveling operation on the surface of the concrete slab based on the leveling possible time predicted before the construction. Thereby, a concrete slab of stable quality can be constructed.

以上説明したように、本発明に係るコンクリートの均し作業可能時期の予測方法によれば、施工中のコンクリートの表面に対する均し作業を実施する前に、均し作業を行うのに好適な均し作業可能時期を予測するための方法であって、施工時間帯の気温とコンクリートの温度が相関関係にあるとみなして、施工時間帯に予想される予想気温を、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、コンクリートの温度の関係に当てはめることで、予想気温に対応する傾き情報を求めるステップと、求めた傾き情報を、予め把握されたフレッシュコンクリートを作製する際の注水時刻からコンクリートの導電率低下時刻までの時間と、傾き情報の関係に当てはめることで、求めた傾き情報に対応する導電率低下時刻を推定するステップと、求めた傾き情報に対応する貫入抵抗値と経過時間の関係を推定するステップと、推定した貫入抵抗値と経過時間の関係と、推定した導電率低下時刻から、コンクリートの均し作業可能時期を予測するステップとを備えるので、コンクリート表面の均し作業を始める前に、均し作業可能時期を容易に把握することができる。   As explained above, according to the prediction method of the leveling operation possible time of concrete according to the present invention, the leveling suitable for performing the leveling operation before performing the leveling operation on the surface of the concrete under construction It is a method to predict the workable period, and it is considered that the air temperature in the construction time zone and the temperature of the concrete are in a correlation, and the predicted air temperature expected in the construction time zone is a predetermined penetration previously grasped A step of obtaining inclination information corresponding to the predicted air temperature by applying to the relation of inclination temperature of an approximate expression representing the relation between penetration resistance value and elapsed time obtained by resistance test and the temperature of concrete, and the obtained inclination information Inclination information obtained by applying the relationship between the time from water injection time when producing fresh concrete that was grasped in advance to the conductivity decrease time of concrete and the inclination information The step of estimating the corresponding conductivity decrease time, the step of estimating the relationship between the penetration resistance value and the elapsed time corresponding to the obtained inclination information, the relationship between the estimated penetration resistance value and the elapsed time, and the estimated conductivity decrease Since the step of predicting the leveling time of concrete can be predicted from the time, it is possible to easily grasp the leveling possible time before starting the leveling operation of the concrete surface.

また、本発明に係るコンクリートの均し作業可能時期の予測装置によれば、施工中のコンクリートの表面に対する均し作業を実施する前に、均し作業を行うのに好適な均し作業可能時期を予測するための装置であって、施工時間帯の気温とコンクリートの温度が相関関係にあるとみなして、施工時間帯に予想される予想気温を、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、コンクリートの温度の関係に当てはめることで、予想気温に対応する傾き情報を求める手段と、求めた傾き情報を、予め把握されたフレッシュコンクリートを作製する際の注水時刻からコンクリートの導電率低下時刻までの時間と、傾き情報の関係に当てはめることで、求めた傾き情報に対応する導電率低下時刻を推定する手段と、求めた傾き情報に対応する貫入抵抗値と経過時間の関係を推定する手段と、推定した貫入抵抗値と経過時間の関係と、推定した導電率低下時刻から、コンクリートの均し作業可能時期を予測する手段とを備えるので、コンクリート表面の均し作業を始める前に、均し作業可能時期を容易に把握することができる。   Moreover, according to the prediction device of the leveling operation possible time of concrete according to the present invention, the leveling operation possible time suitable for performing the leveling operation before performing the leveling operation on the surface of the concrete under construction It is an apparatus for predicting the temperature of the construction time zone, and the temperature of the construction time zone is considered to be correlated with the temperature of concrete, and the predicted air temperature expected during the construction time zone is obtained by a predetermined penetration resistance test grasped beforehand. The slope information corresponding to the predicted air temperature is obtained in advance by grasping the slope information corresponding to the predicted air temperature by applying it to the slope information of the approximate expression representing the relation between the penetration resistance value and the elapsed time and the temperature of the concrete. The conductivity low corresponding to the inclination information obtained by applying the relationship between the time from the water injection time when producing fresh concrete to the conductivity decrease time of the concrete and the inclination information From the means for estimating time, the means for estimating the relationship between penetration resistance value and elapsed time corresponding to the obtained inclination information, the relationship between estimated penetration resistance value and elapsed time, and from the estimated conductivity decrease time, concrete Since it is equipped with means for predicting the leveling possible time, it is possible to easily grasp the leveling possible time before starting the leveling operation of the concrete surface.

また、本発明に係るコンクリートの施工方法によれば、上述したコンクリートの均し作業可能時期の予測方法を用いて均し作業可能時期を予測するステップと、コンクリートを打設するステップと、予測した均し作業可能時期に基づいて、コンクリートの表面に対する均し作業を実施するステップとを備えるので、予測した均し作業可能時期に基づいて均し作業を適正に行うことが可能となり、安定した品質のコンクリートを施工することができる。   Further, according to the method of constructing concrete according to the present invention, the step of predicting the leveling possible period of time using the above-described method of predicting the leveling possible period of concrete, the step of placing concrete, and the prediction Since the step of performing the leveling operation on the surface of the concrete based on the leveling possible time is provided, it is possible to properly perform the leveling operation based on the predicted leveling possible time, and stable quality Concrete can be constructed.

以上のように、本発明に係るコンクリートの均し作業可能時期の予測方法、予測装置およびコンクリートの施工方法は、コンクリートスラブの施工に有用であり、特に、コンクリートスラブの均し作業の開始タイミングを予測するのに適している。   As described above, the method for predicting the leveling time of concrete leveling operation according to the present invention, the prediction device and the method for constructing concrete are useful for the construction of a concrete slab, and in particular, the start timing of leveling operation for concrete slab Suitable for prediction.

Claims (3)

施工中のコンクリートの表面に対する均し作業を実施する前に、均し作業を行うのに好適な均し作業可能時期を予測するための方法であって、
施工時間帯の気温とコンクリートの温度が相関関係にあるとみなして、施工時間帯に予想される予想気温を、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、コンクリートの温度の関係に当てはめることで、予想気温に対応する傾き情報を求めるステップと、
求めた傾き情報を、予め把握されたフレッシュコンクリートを作製する際の注水時刻からコンクリートの導電率低下時刻までの時間と、傾き情報の関係に当てはめることで、求めた傾き情報に対応する導電率低下時刻を推定するステップと、
求めた傾き情報に対応する貫入抵抗値と経過時間の関係を推定するステップと、
推定した貫入抵抗値と経過時間の関係と、推定した導電率低下時刻から、コンクリートの均し作業可能時期を予測するステップとを備えることを特徴とするコンクリートの均し作業可能時期の予測方法。
It is a method for predicting a time suitable for performing a leveling operation before performing the leveling operation on the surface of concrete under construction.
Assuming that the air temperature in the construction time zone and the temperature of the concrete are correlated, the predicted air temperature predicted in the construction time zone is the relationship between the penetration resistance value obtained by a predetermined penetration resistance test grasped beforehand and the elapsed time Obtaining inclination information corresponding to the predicted air temperature by applying the relation between the inclination information of the approximate expression to be expressed and the temperature of the concrete;
Conductivity decrease corresponding to the obtained inclination information by applying the obtained inclination information to the relationship between the time from the time of water injection at the time of preparing fresh concrete to the time when conductivity of the concrete decreases and the inclination information Estimating the time,
Estimating a relationship between penetration resistance value and elapsed time corresponding to the obtained inclination information;
And a step of predicting the leveling time of the concrete from the relationship between the estimated penetration resistance value and the elapsed time and the estimated conductivity decrease time, and a method of predicting the leveling time of the leveling operation of concrete.
施工中のコンクリートの表面に対する均し作業を実施する前に、均し作業を行うのに好適な均し作業可能時期を予測するための装置であって、
施工時間帯の気温とコンクリートの温度が相関関係にあるとみなして、施工時間帯に予想される予想気温を、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、コンクリートの温度の関係に当てはめることで、予想気温に対応する傾き情報を求める手段と、
求めた傾き情報を、予め把握されたフレッシュコンクリートを作製する際の注水時刻からコンクリートの導電率低下時刻までの時間と、傾き情報の関係に当てはめることで、求めた傾き情報に対応する導電率低下時刻を推定する手段と、
求めた傾き情報に対応する貫入抵抗値と経過時間の関係を推定する手段と、
推定した貫入抵抗値と経過時間の関係と、推定した導電率低下時刻から、コンクリートの均し作業可能時期を予測する手段とを備えることを特徴とするコンクリートの均し作業可能時期の予測装置。
An apparatus for predicting a time suitable for performing a leveling operation before performing a leveling operation on the surface of concrete under construction,
Assuming that the air temperature in the construction time zone and the temperature of the concrete are correlated, the predicted air temperature predicted in the construction time zone is the relationship between the penetration resistance value obtained by a predetermined penetration resistance test grasped beforehand and the elapsed time A means for obtaining inclination information corresponding to the predicted air temperature by applying the relation between the inclination information of the approximate expression to be expressed and the temperature of the concrete;
Conductivity decrease corresponding to the obtained inclination information by applying the obtained inclination information to the relationship between the time from the time of water injection at the time of preparing fresh concrete to the time when conductivity of the concrete decreases and the inclination information A means for estimating the time of day;
A means for estimating the relationship between penetration resistance value and elapsed time corresponding to the obtained inclination information;
A device for predicting the leveling operation possible time of concrete, comprising: means for predicting the leveling operation possible time of concrete from the estimated relationship between penetration resistance value and elapsed time and estimated conductivity decreasing time.
請求項1に記載のコンクリートの均し作業可能時期の予測方法を用いて均し作業可能時期を予測するステップと、
コンクリートを打設するステップと、
予測した均し作業可能時期に基づいて、コンクリートの表面に対する均し作業を実施するステップとを備えることを特徴とするコンクリートの施工方法。
Predicting the possible workable period using the method of predicting the possible workable time of concrete according to claim 1;
Step of placing concrete,
And performing a leveling operation on the surface of the concrete on the basis of the predicted leveling time.
JP2017235501A 2017-10-16 2017-12-07 Prediction method of concrete leveling work time, prediction device and concrete construction method Active JP6936718B2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2017200255 2017-10-16
JP2017200255 2017-10-16

Publications (2)

Publication Number Publication Date
JP2019073962A true JP2019073962A (en) 2019-05-16
JP6936718B2 JP6936718B2 (en) 2021-09-22

Family

ID=66543892

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017235501A Active JP6936718B2 (en) 2017-10-16 2017-12-07 Prediction method of concrete leveling work time, prediction device and concrete construction method

Country Status (1)

Country Link
JP (1) JP6936718B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020059979A (en) * 2018-10-05 2020-04-16 株式会社奥村組 Finish management method for concrete floor surface
JP2020117950A (en) * 2019-01-24 2020-08-06 清水建設株式会社 Concrete setting time determination device, determination method, and concrete construction method
JP7352912B2 (en) 2020-03-24 2023-09-29 鹿島建設株式会社 Fresh concrete determination method and fresh concrete determination device
JP7461704B2 (en) 2020-02-03 2024-04-04 株式会社安藤・間 Concrete floor mirror finishing device and method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05340938A (en) * 1992-06-09 1993-12-24 Mitsui Constr Co Ltd Method and device for judging leveling timing of concrete
JP2013209801A (en) * 2012-03-30 2013-10-10 Kajima Corp System for supporting concrete placing and program
JP2014102204A (en) * 2012-11-21 2014-06-05 Fujita Corp Penetration resistance test machine for concrete
JP2015017379A (en) * 2013-07-09 2015-01-29 株式会社Ihiインフラシステム Re-vibration device and re-vibration method
JP2015142964A (en) * 2014-01-31 2015-08-06 宇部興産株式会社 Surface finish method of ultrahigh strength fiber-reinforced concrete
JP2015203204A (en) * 2014-04-11 2015-11-16 清水建設株式会社 Method and device for estimating amount of time available for concrete leveling work
JP2016183526A (en) * 2015-03-26 2016-10-20 清水建設株式会社 Adjustment method of possible time for concrete leveling work

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05340938A (en) * 1992-06-09 1993-12-24 Mitsui Constr Co Ltd Method and device for judging leveling timing of concrete
JP2013209801A (en) * 2012-03-30 2013-10-10 Kajima Corp System for supporting concrete placing and program
JP2014102204A (en) * 2012-11-21 2014-06-05 Fujita Corp Penetration resistance test machine for concrete
JP2015017379A (en) * 2013-07-09 2015-01-29 株式会社Ihiインフラシステム Re-vibration device and re-vibration method
JP2015142964A (en) * 2014-01-31 2015-08-06 宇部興産株式会社 Surface finish method of ultrahigh strength fiber-reinforced concrete
JP2015203204A (en) * 2014-04-11 2015-11-16 清水建設株式会社 Method and device for estimating amount of time available for concrete leveling work
JP2016183526A (en) * 2015-03-26 2016-10-20 清水建設株式会社 Adjustment method of possible time for concrete leveling work

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020059979A (en) * 2018-10-05 2020-04-16 株式会社奥村組 Finish management method for concrete floor surface
JP7149040B2 (en) 2018-10-05 2022-10-06 株式会社奥村組 Concrete floor finish control method
JP2020117950A (en) * 2019-01-24 2020-08-06 清水建設株式会社 Concrete setting time determination device, determination method, and concrete construction method
JP7257797B2 (en) 2019-01-24 2023-04-14 清水建設株式会社 Concrete setting time determination device, determination method and concrete construction method
JP7461704B2 (en) 2020-02-03 2024-04-04 株式会社安藤・間 Concrete floor mirror finishing device and method
JP7352912B2 (en) 2020-03-24 2023-09-29 鹿島建設株式会社 Fresh concrete determination method and fresh concrete determination device

Also Published As

Publication number Publication date
JP6936718B2 (en) 2021-09-22

Similar Documents

Publication Publication Date Title
JP2019073962A (en) Method and device for predicting leveling work enabling period of concrete and method for constructing concrete
Cioni et al. Assessing fire damage to rc elements
Attari et al. A combined SEM–Calorimetric approach for assessing hydration and porosity development in GGBS concrete
Drougkas et al. The confinement of mortar in masonry under compression: experimental data and micro-mechanical analysis
Zach et al. Technology of concrete with low generation of hydration heat
Azenha et al. Continuous monitoring of concrete E-modulus since casting based on modal identification: A case study for in situ application
JP6252856B2 (en) Prediction method and prediction device for concrete leveling time
JP7042602B2 (en) How to control the hardening time of concrete, control device and concrete construction method
Bushmanova et al. The thermo-stressed state in massive concrete structures
Rodríguez-Mariscal et al. Evaluating the performance of sonic and ultrasonic tests for the inspection of rammed earth constructions
Czernuschka et al. Investigation of fracture based on sequentially linear analysis
Santilli et al. Influence of temperature and concrete reinforcement on vertical formwork design
Bensalem et al. Analysis of thermal-induced spalling tests on high to ultra-high performance concrete subjected to standard fire
Shi et al. Numerical investigations on the influence of ITZ and its width on the carbonation depth of concrete with stress damage
Lim et al. Structural behavior prediction of SFRC beams by a novel integrated approach of X-ray imaging and finite element method
JP7000107B2 (en) Prediction method of concrete leveling workable time, prediction device and concrete construction method
Dabarera et al. Experimental assessment and modelling of effective tensile elastic modulus in high performance concrete at early age
Jabbour et al. New experimental approach to accelerate the development of internal swelling reactions (ISR) in massive concrete structures
Gamil et al. Experimental based assessment of formwork pressure theoretical design models for self-compacting concrete
Drougkas et al. Material characterization and micro-modeling of a historic brick masonry pillar
Khan et al. 3D effects on crack front core regions, stress intensity factors and crack initiation angles
Deysel et al. Implementing capillary pressure control measures to prevent plastic shrinkage cracking in concrete
JP2013036162A (en) Re-vibration period determination method for ready-mixed concrete and re-vibration period determination device for ready-mixed concrete
JP6265787B2 (en) Device for calculating compaction characteristics of fresh concrete
JP2022080719A (en) Prediction method of construction timing, prediction device and concrete construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20201104

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210811

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20210824

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20210827

R150 Certificate of patent or registration of utility model

Ref document number: 6936718

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150