JP2022080719A - Prediction method of construction timing, prediction device and concrete construction method - Google Patents

Prediction method of construction timing, prediction device and concrete construction method Download PDF

Info

Publication number
JP2022080719A
JP2022080719A JP2020191936A JP2020191936A JP2022080719A JP 2022080719 A JP2022080719 A JP 2022080719A JP 2020191936 A JP2020191936 A JP 2020191936A JP 2020191936 A JP2020191936 A JP 2020191936A JP 2022080719 A JP2022080719 A JP 2022080719A
Authority
JP
Japan
Prior art keywords
concrete
time
resistance value
elapsed time
penetration resistance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2020191936A
Other languages
Japanese (ja)
Inventor
喜昭 竹本
Yoshiaki Takemoto
亮介 齊藤
Ryosuke Saito
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2020191936A priority Critical patent/JP2022080719A/en
Publication of JP2022080719A publication Critical patent/JP2022080719A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

To provide a method for predicting concrete construction timing, a prediction device, and a concrete construction method that can easily predict construction timing.SOLUTION: There provided steps of determining intercept information corresponding to measured initial temperature, estimating elapsed time from the determined intercept information and time of water pouring until a predetermined penetration resistance value is reached, measuring temperature of the concrete at time obtained by adding time obtained by subtracting predetermined subtraction time from the estimated elapsed time to the time of water pouring to the concrete, obtaining slope information corresponding to the measured temperature of the concrete, and determining an approximate equation representing the relationship between the penetration resistance and the elapsed time by using the obtained slope information and the intercept information to predict construction timing of the pushing operation.SELECTED DRAWING: Figure 5

Description

本発明は、例えばコンクリートスラブなどのコンクリートの施工タイミングの予測方法、予測装置およびコンクリートの施工方法に関するものである。 The present invention relates to a method for predicting the construction timing of concrete such as a concrete slab, a prediction device, and a method for constructing concrete.

従来、コンクリートスラブは、打設作業→均し作業→あま出し作業→押え作業という手順により施工されている。より具体的には、プラントからミキサー(アジテータ車)で運ばれたコンクリートを型枠上に打設し、全体を決められた高さになる様に均してゆく。コンクリートは時間の経過とともに硬化が進み、作業者が上に乗ることができる硬さになってから、ブリーディング水や端部の処理などを行い、鏝で表面を繰返し押えてゆく。 Conventionally, concrete slabs are constructed by the procedure of placing work → leveling work → shaving work → pressing work. More specifically, concrete carried from the plant by a mixer (agitator truck) is placed on the formwork and leveled so that the whole height is determined. As the concrete hardens over time and becomes hard enough for the operator to ride on, bleeding water and edge treatment are performed, and the surface is repeatedly pressed with a trowel.

あま出しから押えに至る作業は、コンクリート表面の平滑性、緻密化に必要な作業であり、スラブの良し悪しに大きな影響を与える。この押え作業は、熟練作業者がコンクリート表面を触った硬さ、見た目の色、ブリーディング水の発生具合などの感覚で判断している。近年の作業者不足により、この感覚による施工は成り立たなくなりつつあり、コンクリートスラブの施工品質の低下につながるおそれがある。特に、近年は建設業の労働者不足を補う目的で施工の機械化が求められており、人による作業と比較して重量やパワーが大きくなり、施工タイミングの管理は極めて重要となっている。 The work from shaving to pressing is necessary for the smoothness and densification of the concrete surface, and has a great influence on the quality of the slab. This pressing work is judged based on the hardness of the concrete surface touched by a skilled worker, the color of appearance, and the degree of generation of bleeding water. Due to the shortage of workers in recent years, construction based on this feeling is becoming impossible, which may lead to deterioration of the construction quality of concrete slabs. In particular, in recent years, mechanization of construction has been required for the purpose of compensating for the labor shortage in the construction industry, and the weight and power are heavier than the work by humans, and the management of construction timing is extremely important.

コンクリートの硬化具合を把握する従来の方法としては、例えば特許文献1、2に記載の方法が知られている。特許文献1の方法は、コンクリートサンプルから粗骨材を除去したモルタルを試験体とし、規定の侵入針を垂直に刺した際の貫入抵抗値を求めるJISの貫入抵抗試験(JIS A 1147:2007)データを基として、試験体に設置した導電率計(抵抗値計でもよい)から得られる時間と導電率の関係を記録しつつ、その波形の変曲点となる時刻とコンクリートの注水時刻から、コンクリートの硬化速度の係数Aを求めることで、以降のコンクリートの貫入抵抗値における時刻を算出する方法である。 As a conventional method for grasping the degree of hardening of concrete, for example, the methods described in Patent Documents 1 and 2 are known. In the method of Patent Document 1, a mortar obtained by removing coarse aggregate from a concrete sample is used as a test piece, and a JIS penetration resistance test (JIS A 1147: 2007) for obtaining a penetration resistance value when a specified penetration needle is vertically pierced. Based on the data, while recording the relationship between the conductivity and the time obtained from the conductivity meter (may be a resistance value meter) installed on the test piece, from the time when the waveform changes and the concrete water injection time, This is a method of calculating the time in the subsequent penetration resistance value of concrete by obtaining the coefficient A of the hardening rate of concrete.

特開2019-73898号公報Japanese Unexamined Patent Publication No. 2019-73898 特開2019-73962号公報Japanese Unexamined Patent Publication No. 2019-73962

しかしながら、上記の従来の特許文献1の方法は、導電率が変化するタイミングを待つ必要があり、見落としがないようにするためには、変化を見極めるまで測定者が拘束されるか、自動化する必要がある。また、コンクリートの導電率と硬化程度の関係は、コンクリートの作業者や施工現場ではイメージが湧きにくく取り組みにくい傾向がある。また、実際の施工現場で貫入抵抗値を測定しながら施工タイミングを管理する方法は、確実ではあるが粗骨材を除去する作業や使用した器具を洗浄する作業、時間ごとに貫入抵抗値を測定する手間がかかる。このため、手間をかけずにコンクリートの施工タイミングを容易に予測することができる方法が求められていた。 However, in the above-mentioned conventional method of Patent Document 1, it is necessary to wait for the timing at which the conductivity changes, and in order to prevent oversight, the measurer must be restrained or automated until the change is discerned. There is. In addition, the relationship between the conductivity of concrete and the degree of hardening tends to be difficult for concrete workers and construction sites to get an image of. In addition, the method of managing the construction timing while measuring the penetration resistance value at the actual construction site is reliable, but the work of removing coarse aggregate, the work of cleaning the used equipment, and the penetration resistance value are measured every hour. It takes time and effort to do. Therefore, there has been a demand for a method that can easily predict the concrete construction timing without any trouble.

本発明は、上記に鑑みてなされたものであって、施工タイミングを容易に予測することができるコンクリートの施工タイミングの予測方法、予測装置およびコンクリートの施工方法を提供することを目的とする。 The present invention has been made in view of the above, and an object of the present invention is to provide a concrete construction timing prediction method, a prediction device, and a concrete construction method capable of easily predicting the construction timing.

上記した課題を解決し、目的を達成するために、本発明に係るコンクリートの施工タイミングの予測方法は、施工中のコンクリートの表面に対する押え作業を実施する前に、押え作業を行うのに好適な施工タイミングを予測するための方法であって、コンクリートの注水時刻を取得するステップと、コンクリートの初期温度を測定するステップと、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の切片情報と、コンクリートの初期温度の関係に対して、測定した初期温度を当てはめることで、測定した初期温度に対応する切片情報を求めるステップと、求めた切片情報を、貫入抵抗値と経過時間の関係を表す近似式に当てはめることで、所定の貫入抵抗値に達するまでの経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算することで、注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定するステップと、推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定するステップと、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、所定の貫入抵抗値に達するまでの経過時間から所定の減算時間を減算した時点におけるコンクリートの温度の関係に対して、測定したコンクリートの温度を当てはめることで、測定したコンクリートの温度に対応する傾き情報を求めるステップと、求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、決定した近似式に対して、押え作業の施工タイミングに対応する貫入抵抗値を当てはめることで、経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算して得られる時刻を押え作業の施工タイミングとして予測するステップとを有することを特徴とする。 In order to solve the above-mentioned problems and achieve the object, the method for predicting the construction timing of concrete according to the present invention is suitable for performing the pressing work before performing the pressing work on the surface of the concrete under construction. It is a method for predicting the construction timing, that is, the step of acquiring the water injection time of concrete, the step of measuring the initial temperature of concrete, and the penetration resistance value and elapsed time obtained by a predetermined penetration resistance test grasped in advance. By applying the measured initial temperature to the relationship between the section information of the approximate expression representing the relationship between the above and the initial temperature of the concrete, the step of obtaining the section information corresponding to the measured initial temperature and the obtained section information are obtained. By applying to the approximate formula that expresses the relationship between the penetration resistance value and the elapsed time, the elapsed time until reaching the predetermined penetration resistance value is obtained, and by adding the obtained elapsed time to the water injection time of the concrete, it is specified from the water injection time. The temperature of the concrete at the step of estimating the elapsed time until the penetration resistance value is reached and the time obtained by subtracting the predetermined subtraction time from the estimated elapsed time and adding it to the water injection time of the concrete. The inclination information of the approximate expression showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test grasped in advance, and the predetermined subtraction from the elapsed time until the predetermined penetration resistance value is reached. By applying the measured concrete temperature to the relationship of the concrete temperature at the time when the time is subtracted, the step of obtaining the inclination information corresponding to the measured concrete temperature, and the obtained inclination information and the section information are used. , Determine the approximate expression that expresses the relationship between the penetration resistance value and the elapsed time, and apply the penetration resistance value corresponding to the construction timing of the presser work to the determined approximate expression to obtain the elapsed time and obtain the elapsed time. It is characterized by having a step of predicting the time obtained by adding the water injection time of the concrete to the water injection time of the concrete as the construction timing of the pressing work.

また、本発明に係る他のコンクリートの施工タイミングの予測方法は、上述した発明において、所定の貫入抵抗値は1(N/mm)であり、所定の減算時間は60分であることを特徴とする。 Further, another method for predicting the construction timing of concrete according to the present invention is characterized in that, in the above-mentioned invention, the predetermined penetration resistance value is 1 (N / mm 2 ) and the predetermined subtraction time is 60 minutes. And.

また、本発明に係るコンクリートの施工タイミングの予測装置は、施工中のコンクリートの表面に対する押え作業を実施する前に、押え作業を行うのに好適な施工タイミングを予測するための装置であって、コンクリートの注水時刻を取得する手段と、コンクリートの初期温度を測定する手段と、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の切片情報と、コンクリートの初期温度の関係に対して、測定した初期温度を当てはめることで、測定した初期温度に対応する切片情報を求める手段と、求めた切片情報を、貫入抵抗値と経過時間の関係を表す近似式に当てはめることで、所定の貫入抵抗値に達するまでの経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算することで、注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定する手段と、推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定する手段と、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、所定の貫入抵抗値に達するまでの経過時間から所定の減算時間を減算した時点におけるコンクリートの温度の関係に対して、測定したコンクリートの温度を当てはめることで、測定したコンクリートの温度に対応する傾き情報を求める手段と、求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、決定した近似式に対して、押え作業の施工タイミングに対応する貫入抵抗値を当てはめることで、経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算して得られる時刻を押え作業の施工タイミングとして予測する手段とを備えることを特徴とする。 Further, the concrete construction timing predicting device according to the present invention is a device for predicting a suitable construction timing for performing the pressing work before performing the pressing work on the surface of the concrete during construction. A means for acquiring the water injection time of the concrete, a means for measuring the initial temperature of the concrete, an approximate section information showing the relationship between the penetration resistance value and the elapsed time obtained by a predetermined penetration resistance test grasped in advance, and concrete. By applying the measured initial temperature to the relationship of the initial temperature of, the means for obtaining the section information corresponding to the measured initial temperature and the obtained section information are approximate expressions expressing the relationship between the penetration resistance value and the elapsed time. By applying to, the elapsed time until reaching the predetermined penetration resistance value is obtained, and by adding the obtained elapsed time to the water injection time of the concrete, the elapsed time from the water injection time to reaching the predetermined penetration resistance value is estimated. A predetermined means for measuring the temperature of the concrete at a time obtained by adding a predetermined subtraction time from the estimated elapsed time to the water injection time of the concrete. The relationship between the inclination information of the approximate formula showing the relationship between the penetration resistance value and the elapsed time obtained by the penetration resistance test and the temperature of the concrete at the time when the predetermined subtraction time is subtracted from the elapsed time until the predetermined penetration resistance value is reached. On the other hand, by applying the measured temperature of the concrete, a means for obtaining the inclination information corresponding to the measured temperature of the concrete, and an approximation representing the relationship between the penetration resistance value and the elapsed time using the obtained inclination information and the section information. The elapsed time is obtained by determining the formula and applying the penetration resistance value corresponding to the construction timing of the presser work to the determined approximate formula, and the time obtained by adding the obtained elapsed time to the water injection time of the concrete. It is characterized by being provided with a means for predicting the construction timing of the pressing work.

また、本発明に係る他のコンクリートの施工タイミングの予測装置は、上述した発明において、所定の貫入抵抗値は1(N/mm)であり、所定の減算時間は60分であることを特徴とする。 Further, another concrete construction timing predictor according to the present invention is characterized in that, in the above-mentioned invention, the predetermined penetration resistance value is 1 (N / mm 2 ) and the predetermined subtraction time is 60 minutes. And.

また、本発明に係るコンクリートの施工方法は、上述したコンクリートの施工タイミングの予測方法を用いて施工タイミングを予測するステップと、コンクリートを打設するステップと、予測した施工タイミングに基づいて、コンクリートの表面に対する押え作業を実施するステップとを有することを特徴とする。 Further, the concrete construction method according to the present invention is based on the step of predicting the construction timing by using the above-mentioned method of predicting the construction timing of concrete, the step of placing concrete, and the predicted construction timing. It is characterized by having a step of performing a pressing operation against the surface.

本発明に係るコンクリートの施工タイミングの予測方法によれば、施工中のコンクリートの表面に対する押え作業を実施する前に、押え作業を行うのに好適な施工タイミングを予測するための方法であって、コンクリートの注水時刻を取得するステップと、コンクリートの初期温度を測定するステップと、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の切片情報と、コンクリートの初期温度の関係に対して、測定した初期温度を当てはめることで、測定した初期温度に対応する切片情報を求めるステップと、求めた切片情報を、貫入抵抗値と経過時間の関係を表す近似式に当てはめることで、所定の貫入抵抗値に達するまでの経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算することで、注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定するステップと、推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定するステップと、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、所定の貫入抵抗値に達するまでの経過時間から所定の減算時間を減算した時点におけるコンクリートの温度の関係に対して、測定したコンクリートの温度を当てはめることで、測定したコンクリートの温度に対応する傾き情報を求めるステップと、求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、決定した近似式に対して、押え作業の施工タイミングに対応する貫入抵抗値を当てはめることで、経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算して得られる時刻を押え作業の施工タイミングとして予測するステップとを有するので、コンクリートの注水時刻、初期温度、所定時刻におけるコンクリートの温度を測定することにより、その後の押え作業の施工タイミングを容易に予測することができるという効果を奏する。 According to the method for predicting the construction timing of concrete according to the present invention, it is a method for predicting a suitable construction timing for performing the pressing work before performing the pressing work on the surface of the concrete under construction. The step of acquiring the water injection time of the concrete, the step of measuring the initial temperature of the concrete, the section information of the approximate formula showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test grasped in advance, and the concrete. By applying the measured initial temperature to the relationship of the initial temperature of, the step of obtaining the section information corresponding to the measured initial temperature and the obtained section information are approximate expressions expressing the relationship between the penetration resistance value and the elapsed time. By applying to, the elapsed time until reaching the predetermined penetration resistance value is obtained, and by adding the obtained elapsed time to the water injection time of the concrete, the elapsed time from the water injection time to reaching the predetermined penetration resistance value is estimated. Step to measure the temperature of the concrete at the time obtained by adding the time obtained by subtracting the predetermined subtraction time from the estimated elapsed time to the water injection time of the concrete, and the predetermined predetermined time grasped in advance. The relationship between the inclination information of the approximate formula showing the relationship between the penetration resistance value and the elapsed time obtained by the penetration resistance test and the temperature of the concrete at the time when the predetermined subtraction time is subtracted from the elapsed time until the predetermined penetration resistance value is reached. On the other hand, by applying the measured temperature of the concrete, the step of obtaining the inclination information corresponding to the measured temperature of the concrete, and the approximation showing the relationship between the penetration resistance value and the elapsed time using the obtained inclination information and the section information. The elapsed time is obtained by determining the formula and applying the penetration resistance value corresponding to the construction timing of the presser work to the determined approximate formula, and the time obtained by adding the obtained elapsed time to the water injection time of the concrete. Since it has a step of predicting the construction timing of the pressing work, it is possible to easily predict the construction timing of the subsequent pressing work by measuring the water injection time of the concrete, the initial temperature, and the temperature of the concrete at a predetermined time. It plays the effect.

また、本発明に係る他のコンクリートの施工タイミングの予測方法によれば、所定の貫入抵抗値は1(N/mm)であり、所定の減算時間は60分であるので、貫入抵抗値と経過時間の関係を表す近似式を容易に精度よく決定することができるという効果を奏する。 Further, according to another method for predicting the construction timing of concrete according to the present invention, the predetermined penetration resistance value is 1 (N / mm 2 ) and the predetermined subtraction time is 60 minutes. It has the effect that the approximate expression expressing the relationship of elapsed time can be easily and accurately determined.

また、本発明に係るコンクリートの施工タイミングの予測装置によれば、施工中のコンクリートの表面に対する押え作業を実施する前に、押え作業を行うのに好適な施工タイミングを予測するための装置であって、コンクリートの注水時刻を取得する手段と、コンクリートの初期温度を測定する手段と、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の切片情報と、コンクリートの初期温度の関係に対して、測定した初期温度を当てはめることで、測定した初期温度に対応する切片情報を求める手段と、求めた切片情報を、貫入抵抗値と経過時間の関係を表す近似式に当てはめることで、所定の貫入抵抗値に達するまでの経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算することで、注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定する手段と、推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定する手段と、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、所定の貫入抵抗値に達するまでの経過時間から所定の減算時間を減算した時点におけるコンクリートの温度の関係に対して、測定したコンクリートの温度を当てはめることで、測定したコンクリートの温度に対応する傾き情報を求める手段と、求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、決定した近似式に対して、押え作業の施工タイミングに対応する貫入抵抗値を当てはめることで、経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算して得られる時刻を押え作業の施工タイミングとして予測する手段とを備えるので、コンクリートの注水時刻、初期温度、所定時刻におけるコンクリートの温度を測定することにより、その後の押え作業の施工タイミングを容易に予測することができるという効果を奏する。 Further, according to the device for predicting the construction timing of concrete according to the present invention, it is a device for predicting the suitable construction timing for performing the pressing work before performing the pressing work on the surface of the concrete under construction. The means for acquiring the water injection time of the concrete, the means for measuring the initial temperature of the concrete, and the section information of the approximate formula showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test grasped in advance. By applying the measured initial temperature to the relationship between the initial temperature of concrete, the means for obtaining the section information corresponding to the measured initial temperature and the obtained section information represent the relationship between the penetration resistance value and the elapsed time. By applying to the approximate formula, the elapsed time until reaching the predetermined penetration resistance value is obtained, and by adding the obtained elapsed time to the water injection time of the concrete, the elapsed time from the water injection time to reaching the predetermined penetration resistance value is obtained. And a means for measuring the temperature of the concrete at a time obtained by adding a predetermined subtraction time from the estimated elapsed time to the water injection time of the concrete. Approximate tilt information showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test, and the temperature of the concrete at the time when the predetermined subtraction time is subtracted from the elapsed time until the predetermined penetration resistance value is reached. By applying the measured concrete temperature to the relationship, the means for obtaining the tilt information corresponding to the measured concrete temperature and the relationship between the penetration resistance value and the elapsed time can be obtained by using the obtained tilt information and the section information. The elapsed time is obtained by determining the approximate expression to be expressed and applying the penetration resistance value corresponding to the construction timing of the presser work to the determined approximate expression, and the obtained elapsed time is added to the water injection time of the concrete. Since it is equipped with a means to predict the time to be pressed as the construction timing of the pressing work, it is possible to easily predict the construction timing of the subsequent pressing work by measuring the water injection time of the concrete, the initial temperature, and the temperature of the concrete at a predetermined time. It has the effect of being able to.

また、本発明に係る他のコンクリートの施工タイミングの予測装置によれば、所定の貫入抵抗値は1(N/mm)であり、所定の減算時間は60分であるので、貫入抵抗値と経過時間の関係を表す近似式を容易に精度よく決定することができるという効果を奏する。 Further, according to another concrete construction timing prediction device according to the present invention, the predetermined penetration resistance value is 1 (N / mm 2 ) and the predetermined subtraction time is 60 minutes. It has the effect that the approximate expression expressing the relationship of elapsed time can be easily and accurately determined.

また、本発明に係るコンクリートの施工方法によれば、上述したコンクリートの施工タイミングの予測方法を用いて施工タイミングを予測するステップと、コンクリートを打設するステップと、予測した施工タイミングに基づいて、コンクリートの表面に対する押え作業を実施するステップとを有するので、施工前に予測した施工タイミングに基づいて、コンクリートの表面に対する押え作業を適正に行うことが可能となる。これにより、安定した品質のコンクリートを施工することができるという効果を奏する。 Further, according to the concrete construction method according to the present invention, the step of predicting the construction timing by using the above-mentioned method of predicting the construction timing of concrete, the step of placing concrete, and the predicted construction timing are used. Since it has a step of performing the pressing work on the concrete surface, it is possible to properly perform the pressing work on the concrete surface based on the construction timing predicted before the construction. This has the effect of being able to construct concrete of stable quality.

図1は、経過時間と貫入抵抗値の関係例を示す図であり、(1)は経過時間と貫入抵抗値の関係、(2)は(1)を対数値に変換した場合である。FIG. 1 is a diagram showing an example of the relationship between the elapsed time and the intrusive resistance value, (1) is the relationship between the elapsed time and the intrusive resistance value, and (2) is the case where (1) is converted into a logarithmic value. 図2は、コンクリート初期温度との関係例を示す図であり、(1)はコンクリート初期温度と傾きAの関係、(2)はコンクリート初期温度と切片Bの関係である。FIG. 2 is a diagram showing an example of the relationship with the initial concrete temperature, (1) is the relationship between the initial concrete temperature and the inclination A, and (2) is the relationship between the initial concrete temperature and the intercept B. 図3(1)は、全試験サンプルの貫入抵抗値1(N/mm)における切片Bから算出した経過時間の内訳を示す図、図3(2)は、作業内容と貫入抵抗値の関係である。FIG. 3 (1) is a diagram showing the breakdown of the elapsed time calculated from the intercept B in the penetration resistance value 1 (N / mm 2 ) of all the test samples, and FIG. 3 (2) is the relationship between the work content and the penetration resistance value. Is. 図4は、貫入抵抗値1(N/mm)におけるコンクリート予測温度と傾きAとの関係例を示す図である。FIG. 4 is a diagram showing an example of the relationship between the predicted concrete temperature and the inclination A at a penetration resistance value of 1 (N / mm 2 ). 図5は、本発明に係るコンクリートの施工タイミングの予測方法の実施の形態を示すフローチャート図である。FIG. 5 is a flowchart showing an embodiment of the method for predicting the construction timing of concrete according to the present invention. 図6は、本発明に係るコンクリートの施工タイミングの予測装置の実施の形態を示す画面図である。FIG. 6 is a screen view showing an embodiment of the concrete construction timing prediction device according to the present invention. 図7は、本発明に係るコンクリートの施工タイミングの予測装置の実施の形態を示す画面図である。FIG. 7 is a screen view showing an embodiment of the concrete construction timing prediction device according to the present invention.

以下に、本発明に係るコンクリートの施工タイミングの予測方法、予測装置およびコンクリートの施工方法の実施の形態を図面に基づいて詳細に説明する。なお、この実施の形態によりこの発明が限定されるものではない。 Hereinafter, embodiments of a concrete construction timing prediction method, a prediction device, and a concrete construction method according to the present invention will be described in detail with reference to the drawings. The present invention is not limited to this embodiment.

[コンクリートの施工タイミングの予測方法]
まず、本発明に係るコンクリートの施工タイミングの予測方法の実施の形態について説明する。
[Method of predicting concrete construction timing]
First, an embodiment of the method for predicting the construction timing of concrete according to the present invention will be described.

(基本原理)
まず、本発明の基本原理について説明する。
図1(1)は、夏期、中間期(春)、冬期における打設後のコンクリートの経過時間と貫入抵抗値の測定結果の一例を示したものである。図中のRは相関係数である。この図によると、それぞれが高い相関関係で得ることができ、夏期は短時間で硬化が進み、冬期は長い時間をかけて硬化してゆくことが分かる。この波形について、X軸とY軸を対数値に変換し、分かりやすくなるようにX軸とY軸を入れ替えると図1(2)になる。この図に示すように、貫入抵抗値(X軸)と経過時間(Y軸)は以下に示すような1次関数式で表すことができ、傾きA(傾き情報)と切片B(切片情報)が得られれば、貫入抵抗値から経過時間を算出できる。
(Basic principle)
First, the basic principle of the present invention will be described.
FIG. 1 (1) shows an example of the measurement results of the elapsed time and the penetration resistance value of the concrete after placing in the summer, the middle period (spring), and the winter. R in the figure is a correlation coefficient. According to this figure, each can be obtained with a high correlation, and it can be seen that the curing progresses in a short time in the summer and the curing takes a long time in the winter. For this waveform, the X-axis and the Y-axis are converted into logarithmic values, and the X-axis and the Y-axis are exchanged for easy understanding, so that FIG. 1 (2) is obtained. As shown in this figure, the penetration resistance value (X-axis) and elapsed time (Y-axis) can be expressed by linear function equations as shown below, and slope A (slope information) and intercept B (intercept information). If is obtained, the elapsed time can be calculated from the penetration resistance value.

経過時間の対数値=A×(貫入抵抗値の対数値)+B ・・・式(1) Log of elapsed time = A × (log of intrusive resistance) + B ・ ・ ・ Equation (1)

図に示されるように、傾きAが大きいほど経過時間の対数値が大きくなるため、コンクリートの硬化速度が遅くなることになる。つまり、気温の高い夏期はAが小さく、気温の低い冬期はAが大きくなる傾向がある。また、切片Bは、図1(2)に示すように、貫入抵抗値の対数値が0.0(ゼロ)の値であり、これは貫入抵抗値が1(N/mm)であることを意味する。 As shown in the figure, the larger the slope A, the larger the logarithmic value of the elapsed time, and the slower the hardening rate of concrete. That is, A tends to be small in the summer when the temperature is high, and large in the winter when the temperature is low. Further, in the intercept B, as shown in FIG. 1 (2), the logarithmic value of the penetration resistance value is 0.0 (zero), which means that the penetration resistance value is 1 (N / mm 2 ). Means.

図2は、アジテータ車(コンクリートミキサー)からサンプルを採取し、貫入抵抗値を実際に測定して得たコンクリート初期温度と傾きAおよび切片Bの関係を示したものである。コンクリートは、施工時期、測定場所、出荷プラントなどが異なるが、コンクリートの種類は、特殊な配合を除いた一般的なスラブ用コンクリートである。また、この図におけるコンクリート初期温度は、打設現場に到着したアジテータ車から採取したコンクリート温度である。 FIG. 2 shows the relationship between the initial concrete temperature obtained by taking a sample from an agitator truck (concrete mixer) and actually measuring the penetration resistance value, and the inclination A and the intercept B. Concrete differs in construction time, measurement location, shipping plant, etc., but the type of concrete is general slab concrete excluding special formulations. The initial concrete temperature in this figure is the concrete temperature collected from the agitator truck arriving at the casting site.

この図によると、コンクリート初期温度(X軸)と傾きA(Y軸)との相関はあまりよくないが、コンクリート初期温度(X軸)と切片B(Y軸)とはよい相関であることが分かる。切片Bは、上記のように貫入抵抗値の対数値が0.0、つまり貫入抵抗値が1(N/mm)の値であるため、上記の式(1)に当てはめることで傾きAに関係なく経過時間の対数値を算出することができ、この値の指数値を求めることで経過時間を得ることができる。すなわち、コンクリート初期温度を測定することで、貫入抵抗値1(N/mm)までの経過時間を算出できる。算出した経過時間を、アジテータ車のミルシートなどに記載されているコンクリートの注水時刻に加算することで、貫入抵抗値1(N/mm)に対応する時刻を算出することができる。なお、切片Bは、対数による回帰曲線で相関を求めているが、直線による回帰曲線でも相関係数に違いはほとんどない。そのため、どちらを選定してもよいが、現時点では対数による回帰曲線を採用し、その後、データが揃ってきて直線による回帰曲線の相関がよくなった場合はその時点でそれに変更してもよい。 According to this figure, the correlation between the initial concrete temperature (X-axis) and the slope A (Y-axis) is not very good, but the initial concrete temperature (X-axis) and the intercept B (Y-axis) are well correlated. I understand. Since the logarithmic value of the penetration resistance value of section B is 0.0, that is, the penetration resistance value is 1 (N / mm 2 ) as described above, the slope A can be obtained by applying the above equation (1). The logarithmic value of the elapsed time can be calculated regardless, and the elapsed time can be obtained by obtaining the exponential value of this value. That is, by measuring the initial concrete temperature, the elapsed time up to the penetration resistance value 1 (N / mm 2 ) can be calculated. By adding the calculated elapsed time to the water injection time of the concrete described on the mill sheet of the agitator truck or the like, the time corresponding to the penetration resistance value 1 (N / mm 2 ) can be calculated. In the intercept B, the correlation is obtained by the regression curve by the logarithm, but there is almost no difference in the correlation coefficient even by the regression curve by the straight line. Therefore, either one may be selected, but at present, a logarithmic regression curve may be adopted, and then if the data are collected and the correlation of the linear regression curve is improved, it may be changed at that point.

貫入抵抗値は、コンクリートがまだ十分に柔らかい段階(例えば測定値が得られる程度の0.01~0.1(N/mm)程度)では測定値にばらつきがあるため、傾きAは安定しない傾向がある。また、コンクリート温度は、周囲の気温や日射から影響を受け、夏期や中間期は時間経過とともに徐々に温度が上昇する。一方で、冬期のコンクリート温度は、初期から徐々に低下することもある。したがって傾きAの決定は、できるだけ多くのデータが得られた時点が望ましい。 The penetration resistance value is not stable at the stage where the concrete is still sufficiently soft (for example, about 0.01 to 0.1 (N / mm 2 ) where the measured value can be obtained) because the measured value varies. Tend. In addition, the concrete temperature is affected by the ambient temperature and solar radiation, and the temperature gradually rises over time in the summer and intermediate seasons. On the other hand, the concrete temperature in winter may gradually decrease from the beginning. Therefore, it is desirable to determine the slope A when as much data as possible is obtained.

図3(1)は、切片Bの値から算出した全試験サンプルの貫入抵抗値1(N/mm)における経過時間の内訳を示したものである。最も短い時間で129分、最も長いのは545分である。押え作業の開始が、例えば図3(2)に示すように貫入抵抗値0.5(N/mm)に対応する時刻からに計画している場合は、作業タイミングの時刻予測はそれよりも前に算出する必要がある。一方、あまりにも早い段階での時刻予測は、精度が悪くなる可能性がある。そこで、本発明では貫入抵抗値1(N/mm)におけるコンクリート温度を以下の(1)~(4)の方法で予測する。 FIG. 3 (1) shows the breakdown of the elapsed time in the penetration resistance value 1 (N / mm 2 ) of all the test samples calculated from the value of the intercept B. The shortest time is 129 minutes and the longest is 545 minutes. If the start of the presser work is planned from the time corresponding to the penetration resistance value of 0.5 (N / mm 2 ) as shown in FIG. 3 (2), the time prediction of the work timing is more than that. Must be calculated before. On the other hand, time prediction at an early stage may be inaccurate. Therefore, in the present invention, the concrete temperature at the penetration resistance value of 1 (N / mm 2 ) is predicted by the following methods (1) to (4).

(1)傾きBから算出した貫入抵抗値1(N/mm)における経過時間から所定の減算時間(例えば60分)を引く。
(2)(1)の経過時間における、コンクリート温度の実測値とコンクリート初期温度の差を求める。
(3)(1)の経過時間で、(2)で求めた温度が変化したことになるため、温度変化の割合を算出する。
(4)(3)で求めた温度変化の割合を用いて貫入抵抗値1(N/mm)におけるコンクリート予測温度を求める。
(1) A predetermined subtraction time (for example, 60 minutes) is subtracted from the elapsed time at the penetration resistance value 1 (N / mm 2 ) calculated from the slope B.
(2) Obtain the difference between the measured value of the concrete temperature and the initial concrete temperature during the elapsed time of (1).
(3) Since the temperature obtained in (2) has changed with the elapsed time of (1), the rate of temperature change is calculated.
(4) The predicted concrete temperature at a penetration resistance value of 1 (N / mm 2 ) is obtained by using the rate of temperature change obtained in (3).

図4は、上記の方法で算出した貫入抵抗値1(N/mm)におけるコンクリート予測温度と傾きAとの関係を示したものである。この図と、図2(1)で示した傾きAとコンクリート初期温度の関係とを比較すると、相関が大幅に改善することが分かる。貫入抵抗値1(N/mm)の経過時間から60分を引いた時間のコンクリート温度測定値は、矢印で示される20℃台の2点が他の測定値よりも近似直線から外れていることが分かるが、これは、中間期のデータであり実測値において温度を予測した時刻以降に、温度があまり上がらなかったものと、予想よりも大幅に上がったものである。これは、測定した際の気象変化によるものである。特に中間期のような気温の変動幅が大きい時期においては、貫入抵抗値1(N/mm)や最終的なコンクリート温度を予測することは困難である。したがって、現時点における傾きAの算出では、貫入抵抗値1(N/mm)の経過時間から60分を引いた時間のコンクリート温度測定値である図4の関係を採用することが望ましい。また、気温の変動幅が大きい時期は温度変化が大きいため、減算時間は60分よりも30分、20分などできるだけ短い方が望ましい。 FIG. 4 shows the relationship between the predicted concrete temperature and the inclination A at the penetration resistance value 1 (N / mm 2 ) calculated by the above method. Comparing this figure with the relationship between the slope A shown in FIG. 2 (1) and the initial temperature of concrete, it can be seen that the correlation is significantly improved. The concrete temperature measurement value for the time obtained by subtracting 60 minutes from the elapsed time of penetration resistance value 1 (N / mm 2 ) shows that the two points in the 20 ° C range indicated by the arrows are out of the approximate straight line compared to the other measurement values. It can be seen that this is the data for the interim period, and the temperature did not rise much after the time when the temperature was predicted in the measured value, and it was significantly higher than expected. This is due to changes in the weather when measured. It is difficult to predict the intrusive resistance value 1 (N / mm 2 ) and the final concrete temperature, especially in the middle period when the temperature fluctuation range is large. Therefore, in the calculation of the slope A at the present time, it is desirable to adopt the relationship of FIG. 4, which is the concrete temperature measurement value of the time obtained by subtracting 60 minutes from the elapsed time of the penetration resistance value 1 (N / mm 2 ). Further, since the temperature change is large when the temperature fluctuation range is large, it is desirable that the subtraction time is as short as possible, such as 30 minutes or 20 minutes, rather than 60 minutes.

(具体的な予測手順)
次に、本実施の形態に係る予測方法により、コンクリートスラブ施工時の押えタイミングを予測する場合の手順について説明する。
(Specific prediction procedure)
Next, a procedure for predicting the pressing timing at the time of concrete slab construction by the prediction method according to the present embodiment will be described.

図5に示すように、まず、打設現場に到着したアジテータ車からコンクリート初期温度を測定するとともに、アジテータ車のミルシートなどを参照してコンクリートの注水時刻を記録する(ステップS1)。 As shown in FIG. 5, first, the initial temperature of the concrete is measured from the agitator truck arriving at the casting site, and the water injection time of the concrete is recorded with reference to the mill sheet of the agitator truck (step S1).

次に、図2(2)の関係より切片Bを算出し、算出した切片Bを上記の式(1)に代入して経過時間の対数値を求める。そして、この値の指数値をコンクリートの注水時刻に加算することで注水時刻から貫入抵抗値1(N/mm)までの経過時間を算出する(ステップS2)。 Next, the intercept B is calculated from the relationship of FIG. 2 (2), and the calculated intercept B is substituted into the above equation (1) to obtain the logarithmic value of the elapsed time. Then, by adding the exponential value of this value to the water injection time of the concrete, the elapsed time from the water injection time to the penetration resistance value 1 (N / mm 2 ) is calculated (step S2).

次に、注水時刻に対して、算出した貫入抵抗値1(N/mm)の経過時間から60分を引いた時間を加算した時刻を算出し、その時刻におけるコンクリート温度を測定する(ステップS3)。 Next, the time obtained by adding the time obtained by subtracting 60 minutes from the elapsed time of the calculated penetration resistance value 1 (N / mm 2 ) to the water injection time is calculated, and the concrete temperature at that time is measured (step S3). ).

次に、図4の関係から傾きAを算出する(ステップS4)。 Next, the slope A is calculated from the relationship shown in FIG. 4 (step S4).

次に、図3(2)に示すような各押え作業における開始時刻を算出し、コンクリートスラブ施工の押えタイミングを管理する(ステップS5)。これにより、各作業時刻(施工タイミング)および時間を施工前に予測することが可能となる。 Next, the start time in each pressing operation as shown in FIG. 3 (2) is calculated, and the pressing timing of the concrete slab construction is managed (step S5). This makes it possible to predict each work time (construction timing) and time before construction.

このように、本実施の形態の予測方法によれば、コンクリートの温度を測定するだけで、コンクリートスラブの押えタイミングを施工前に容易に予測することができる。このため、施工準備や押え作業が可能な時間を容易に把握することができる。コンクリートの硬化は、夏の暑い時期は早く、冬の寒い時期は遅いことは作業者や施工管理者にも経験的に知られており、温度を使った施工タイミングの管理は誰もがイメージしやすい利点がある。 As described above, according to the prediction method of the present embodiment, the pressing timing of the concrete slab can be easily predicted before the construction only by measuring the temperature of the concrete. Therefore, it is possible to easily grasp the time during which the construction preparation and the pressing work can be performed. It is empirically known to workers and construction managers that the hardening of concrete is early in the hot summer and late in the cold winter, and everyone imagines the management of construction timing using temperature. There is an easy advantage.

また、事前に押えタイミングを把握できるため、作業者や施工機械の配置準備、施工管理に活かすことが可能となる。このため、安定した品質のコンクリートスラブを施工することができる。また、作業終了時刻を明確にすることで、余計な作業がなくなり、時間短縮につながる。 In addition, since the presser timing can be grasped in advance, it can be utilized for placement preparation and construction management of workers and construction machines. Therefore, it is possible to construct a concrete slab of stable quality. In addition, by clarifying the work end time, unnecessary work is eliminated and the time is shortened.

なお、本発明で対象とするコンクリートは、特殊なケースを除いた通常のスラブに用いるものであれば種類を限定しない。 The type of concrete targeted in the present invention is not limited as long as it is used for ordinary slabs except for special cases.

[コンクリートの施工タイミングの予測装置]
次に、本発明に係るコンクリートの施工タイミングの予測装置の実施の形態について説明する。
[Concrete construction timing prediction device]
Next, an embodiment of the concrete construction timing prediction device according to the present invention will be described.

本実施の形態に係るコンクリートの施工タイミングの予測装置は、上述したコンクリートの施工タイミングの予測方法を装置として具現化したものであり、例えば入力部、出力部、演算部、表示部、温度計測部からなる。入力部、出力部、演算部、表示部は、例えばCPUを有するコンピュータ、メモリ、ディスプレイ等のハードウェア、これらハードウェア上で稼働するコンピュータプログラム等のソフトウェアを用いて構成することができる。温度測定部は、コンクリート温度を測定する温度計などで構成することができる。 The concrete construction timing prediction device according to the present embodiment embodies the above-mentioned concrete construction timing prediction method as a device, for example, an input unit, an output unit, a calculation unit, a display unit, and a temperature measurement unit. Consists of. The input unit, output unit, calculation unit, and display unit can be configured by using, for example, a computer having a CPU, hardware such as a memory and a display, and software such as a computer program running on these hardware. The temperature measuring unit can be configured by a thermometer or the like that measures the concrete temperature.

図6は、本実施の形態に係るコンクリートの施工タイミングの予測装置の入出力画面の一例である。この図のような画面がディスプレイ等の表示部に表示される。 FIG. 6 is an example of an input / output screen of the concrete construction timing prediction device according to the present embodiment. A screen like this figure is displayed on a display unit such as a display.

入力部は、この画面の左側に設けられた4つの項目からなる入力セルである。各セルは、ミルシートからコンクリートの「注水時刻」を入力するためのセル(1)と、現場のコンクリートからコンクリート初期温度の「測定時刻」を入力するためのセル(2)と、「コンクリート初期温度」を入力するためのセル(3)と、現場のコンクリートから貫入抵抗値1(N/mm)の60分前の時刻における「コンクリート温度」を入力するためのセル(4)である。各セルに対する入力データは、演算部の演算処理に使用される。入力するデータは、上記の4つのデータであり、その他の項目は後述の出力部において自動的に算出され、傾きAと切片Bを得ることができる。 The input unit is an input cell composed of four items provided on the left side of this screen. Each cell has a cell (1) for inputting the "water injection time" of concrete from the mill sheet, a cell (2) for inputting the "measurement time" of the concrete initial temperature from the concrete at the site, and "concrete initial temperature". The cell (3) for inputting "concrete temperature" at the time 60 minutes before the penetration resistance value 1 (N / mm 2 ) from the concrete at the site. The input data for each cell is used for the arithmetic processing of the arithmetic unit. The data to be input are the above four data, and the other items are automatically calculated in the output unit described later, and the slope A and the intercept B can be obtained.

出力部は、この画面の右側に設けられた複数の項目からなる出力セルである。各セルは、「切片B」、「貫入抵抗値1(N/mm)までの経過時間」、「貫入抵抗値1(N/mm)から60分前の時刻」、「貫入抵抗値1(N/mm)のコンクリート予測温度」、「傾きA」を出力するためのセルからなる。各セルには、演算部の演算処理によって算出された算出値が出力される。 The output unit is an output cell composed of a plurality of items provided on the right side of this screen. Each cell has "section B", "elapsed time to penetration resistance value 1 (N / mm 2 )", "time 60 minutes before penetration resistance value 1 (N / mm 2 )", and "penetration resistance value 1". It consists of cells for outputting "predicted concrete temperature of (N / mm 2 )" and "inclination A". The calculated value calculated by the arithmetic processing of the arithmetic unit is output to each cell.

上記の構成の動作について説明する。入力部の「注水時刻」、「測定時刻」、「コンクリート初期温度」の3つの項目を入力すると、演算部の演算処理により、「切片B」が算出されるとともに、「貫入抵抗値1(N/mm)までの経過時間」、「貫入抵抗値1(N/mm)から60分前の時刻」が算出される。これらの算出値は出力部の各セルに瞬時に出力表示される。その後、貫入抵抗値1(N/mm)から60分前の時刻においてコンクリート温度を測定し、この測定値を入力部の「コンクリート温度」に入力すると、演算部の演算処理により、「貫入抵抗値1(N/mm)のコンクリート予測温度」、「傾きA」が算出される。これらの算出値は出力部の各セルに瞬時に出力表示される。なお、図の例では、注水時刻8:00、測定時刻9:31、コンクリート初期温度15.0℃、コンクリート温度29.2℃を入力して、切片B=5.82、傾きA=0.10が算出された場合を示している。 The operation of the above configuration will be described. When the three items of "water injection time", "measurement time", and "concrete initial temperature" of the input section are input, "section B" is calculated by the calculation process of the calculation section, and "penetration resistance value 1 (N). The elapsed time until / mm 2 ) and the time 60 minutes before the penetration resistance value 1 (N / mm 2 ) are calculated. These calculated values are instantly output and displayed in each cell of the output unit. After that, the concrete temperature is measured 60 minutes before the penetration resistance value 1 (N / mm 2 ), and when this measured value is input to the "concrete temperature" of the input unit, the "penetration resistance" is calculated by the calculation process of the calculation unit. "Predicted concrete temperature with a value of 1 (N / mm 2 )" and "inclination A" are calculated. These calculated values are instantly output and displayed in each cell of the output unit. In the example of the figure, the water injection time is 8:00, the measurement time is 9:31, the concrete initial temperature is 15.0 ° C., and the concrete temperature is 29.2 ° C., the intercept B = 5.82, and the inclination A = 0. The case where 10 is calculated is shown.

図7は、図6で算出した傾きAと切片Bを用いて各作業における施工タイミングを算出した画面の一例である。上記の傾きAと切片Bが算出されると、演算部の演算処理により、図7に示すように各作業ごとの開始時刻が自動的に算出される。したがって、この予測装置の利用者は、この画面を通じて、各作業の時刻を容易に把握することができる。この例の場合は、コンクリート初期温度を9:31に測定し、12:37にその時のコンクリート温度を測定した時点で、人が上に乗れる時刻13:14以降の時刻が算出される。作業終了は14:43であり、押え過ぎによる剥がれやひび割れ、色むらなどの不具合が発生しにくくなり、これ以降の作業がなくなることで時間短縮にもつながる。 FIG. 7 is an example of a screen in which the construction timing in each work is calculated using the slope A and the intercept B calculated in FIG. When the slope A and the intercept B are calculated, the start time for each operation is automatically calculated by the arithmetic processing of the arithmetic unit as shown in FIG. 7. Therefore, the user of this prediction device can easily grasp the time of each work through this screen. In the case of this example, the initial concrete temperature is measured at 9:31, and when the concrete temperature at that time is measured at 12:37, the time after 13:14 when a person can get on the concrete is calculated. The work is completed at 14:43, and problems such as peeling, cracking, and color unevenness due to excessive pressing are less likely to occur, and the subsequent work is eliminated, which leads to a reduction in time.

このように、本実施の形態の予測装置によれば、コンクリートの温度を測定するだけで、コンクリートスラブの押えタイミングを施工前に容易に予測することができる。また、データの入力は4項目のみであることから作業が容易であり、誰でも押えタイミングの時刻を容易に得ることが可能である。 As described above, according to the prediction device of the present embodiment, the pressing timing of the concrete slab can be easily predicted before the construction only by measuring the temperature of the concrete. Further, since the data can be input only by four items, the work is easy, and anyone can easily obtain the presser timing.

[コンクリートの施工方法]
次に、本発明に係るコンクリートの施工方法の実施の形態について、コンクリートスラブを施工する場合を例にとり説明する。
[Concrete construction method]
Next, an embodiment of the concrete construction method according to the present invention will be described by taking the case of constructing a concrete slab as an example.

まず、コンクリートスラブを施工する前に、上述したコンクリートの施工タイミングの予測方法を用いて施工タイミングを予測する。これにより、施工前に各押え作業の施工タイミングを把握することが可能となる。この結果、例えば図7に示すような施工タイミングの情報を得たものとする。 First, before constructing the concrete slab, the construction timing is predicted by using the above-mentioned concrete construction timing prediction method. This makes it possible to grasp the construction timing of each presser work before construction. As a result, for example, it is assumed that the construction timing information as shown in FIG. 7 is obtained.

次に、フレッシュコンクリートを型枠上に打設してコンクリートスラブを施工する。そして、図7を参照して施工タイミングを確認し、人が上に乗れる時刻(13時14分)になったら、作業員が硬化中のコンクリートスラブ上に乗り、ブリーディング水や端部の処理などの作業を行う。この作業は、円盤・あま出しの開始時刻(14時01分)までに終えるように計画的に実施する。その後、円盤・あま出しを行い、金鏝1回目の開始時刻(14時21分)になったら、金鏝で表面を繰返し押えていく。その後、金鏝2回目の開始時刻(14時43分)になったら、金鏝で表面を仕上げていく。 Next, fresh concrete is placed on the formwork to construct a concrete slab. Then, the construction timing is confirmed with reference to FIG. 7, and when it is time for a person to get on (13:14), the worker gets on the concrete slab being hardened and treats the bleeding water and the edge. Do the work of. This work will be carried out systematically so that it will be completed by the start time (14:01) of the disk and shaving. After that, the disk and trowel are put out, and when the first start time of the gold trowel (14:21) is reached, the surface is repeatedly pressed with the gold trowel. After that, when the second start time of the gold trowel (14:43) comes, the surface is finished with the gold trowel.

このように、本実施の形態によれば、施工前に予測した施工タイミングに基づいて、コンクリートスラブの表面に対する押え作業を適正に行うことが可能となる。これにより、安定した品質のコンクリートスラブを施工することができる。 As described above, according to the present embodiment, it is possible to properly perform the pressing work on the surface of the concrete slab based on the construction timing predicted before the construction. This makes it possible to construct a concrete slab of stable quality.

以上説明したように、本発明に係るコンクリートの施工タイミングの予測方法によれば、施工中のコンクリートの表面に対する押え作業を実施する前に、押え作業を行うのに好適な施工タイミングを予測するための方法であって、コンクリートの注水時刻を取得するステップと、コンクリートの初期温度を測定するステップと、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の切片情報と、コンクリートの初期温度の関係に対して、測定した初期温度を当てはめることで、測定した初期温度に対応する切片情報を求めるステップと、求めた切片情報を、貫入抵抗値と経過時間の関係を表す近似式に当てはめることで、所定の貫入抵抗値に達するまでの経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算することで、注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定するステップと、推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定するステップと、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、所定の貫入抵抗値に達するまでの経過時間から所定の減算時間を減算した時点におけるコンクリートの温度の関係に対して、測定したコンクリートの温度を当てはめることで、測定したコンクリートの温度に対応する傾き情報を求めるステップと、求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、決定した近似式に対して、押え作業の施工タイミングに対応する貫入抵抗値を当てはめることで、経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算して得られる時刻を押え作業の施工タイミングとして予測するステップとを有するので、コンクリートの注水時刻、初期温度、所定時刻におけるコンクリートの温度を測定することにより、その後の押え作業の施工タイミングを容易に予測することができる。 As described above, according to the method for predicting the construction timing of concrete according to the present invention, in order to predict the suitable construction timing for performing the pressing work before performing the pressing work on the surface of the concrete under construction. This is an approximate expression that expresses the relationship between the step of acquiring the water injection time of concrete, the step of measuring the initial temperature of concrete, and the penetration resistance value and the elapsed time obtained by a predetermined penetration resistance test grasped in advance. By applying the measured initial temperature to the relationship between the section information and the initial temperature of the concrete, the step of obtaining the section information corresponding to the measured initial temperature and the obtained section information are obtained by the penetration resistance value and the elapsed time. By applying the approximate formula that expresses the relationship between, the elapsed time until reaching the predetermined penetration resistance value is obtained, and by adding the obtained elapsed time to the water injection time of the concrete, the predetermined penetration resistance value is reached from the water injection time. A step of estimating the elapsed time up to, and a step of measuring the temperature of the concrete at a time obtained by adding a predetermined subtraction time from the estimated elapsed time to the water injection time of the concrete. At the time when the predetermined subtraction time is subtracted from the inclination information of the approximate expression showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test grasped in advance and the elapsed time until the predetermined penetration resistance value is reached. By applying the measured concrete temperature to the relationship of the concrete temperature, the step of obtaining the inclination information corresponding to the measured concrete temperature, and the penetration resistance value and the progress using the obtained inclination information and the section information. The elapsed time is obtained by determining the approximate expression that expresses the time relationship and applying the penetration resistance value corresponding to the construction timing of the presser work to the determined approximate expression, and the calculated elapsed time is used as the water injection time of the concrete. Since it has a step of predicting the time obtained by adding up as the work timing of the presser work, it is easy to set the work timing of the presser work thereafter by measuring the water injection time of the concrete, the initial temperature, and the temperature of the concrete at a predetermined time. Can be predicted.

また、本発明に係る他のコンクリートの施工タイミングの予測方法によれば、所定の貫入抵抗値は1(N/mm)であり、所定の減算時間は60分であるので、貫入抵抗値と経過時間の関係を表す近似式を容易に精度よく決定することができる。 Further, according to another method for predicting the construction timing of concrete according to the present invention, the predetermined penetration resistance value is 1 (N / mm 2 ) and the predetermined subtraction time is 60 minutes. An approximate expression expressing the relationship of elapsed time can be easily and accurately determined.

また、本発明に係るコンクリートの施工タイミングの予測装置によれば、施工中のコンクリートの表面に対する押え作業を実施する前に、押え作業を行うのに好適な施工タイミングを予測するための装置であって、コンクリートの注水時刻を取得する手段と、コンクリートの初期温度を測定する手段と、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の切片情報と、コンクリートの初期温度の関係に対して、測定した初期温度を当てはめることで、測定した初期温度に対応する切片情報を求める手段と、求めた切片情報を、貫入抵抗値と経過時間の関係を表す近似式に当てはめることで、所定の貫入抵抗値に達するまでの経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算することで、注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定する手段と、推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定する手段と、予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、所定の貫入抵抗値に達するまでの経過時間から所定の減算時間を減算した時点におけるコンクリートの温度の関係に対して、測定したコンクリートの温度を当てはめることで、測定したコンクリートの温度に対応する傾き情報を求める手段と、求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、決定した近似式に対して、押え作業の施工タイミングに対応する貫入抵抗値を当てはめることで、経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算して得られる時刻を押え作業の施工タイミングとして予測する手段とを備えるので、コンクリートの注水時刻、初期温度、所定時刻におけるコンクリートの温度を測定することにより、その後の押え作業の施工タイミングを容易に予測することができる。 Further, according to the concrete construction timing predicting device according to the present invention, it is a device for predicting a suitable construction timing for performing the pressing work before performing the pressing work on the concrete surface during construction. The means for acquiring the water injection time of concrete, the means for measuring the initial temperature of concrete, and the section information of the approximate formula showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test grasped in advance. By applying the measured initial temperature to the relationship between the initial temperature of concrete, the means for obtaining the section information corresponding to the measured initial temperature and the obtained section information represent the relationship between the penetration resistance value and the elapsed time. By applying to the approximate formula, the elapsed time until reaching the predetermined penetration resistance value is obtained, and by adding the obtained elapsed time to the concrete water injection time, the elapsed time from the water injection time to reaching the predetermined penetration resistance value is obtained. And a means for measuring the temperature of concrete at a time obtained by adding a predetermined subtraction time from the estimated elapsed time to the water injection time of the concrete. The inclination information of the approximate formula showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test, and the temperature of the concrete at the time when the predetermined subtraction time is subtracted from the elapsed time until the predetermined penetration resistance value is reached. By applying the measured concrete temperature to the relationship, the means for obtaining the inclination information corresponding to the measured concrete temperature and the relationship between the penetration resistance value and the elapsed time can be obtained by using the obtained inclination information and the section information. The elapsed time is obtained by determining the approximate expression to be expressed and applying the penetration resistance value corresponding to the construction timing of the presser work to the determined approximate expression, and the obtained elapsed time is added to the water injection time of the concrete. Since it is equipped with a means to predict the time to be pressed as the construction timing of the pressing work, it is possible to easily predict the construction timing of the subsequent pressing work by measuring the water injection time of the concrete, the initial temperature, and the temperature of the concrete at a predetermined time. Can be done.

また、本発明に係る他のコンクリートの施工タイミングの予測装置によれば、所定の貫入抵抗値は1(N/mm)であり、所定の減算時間は60分であるので、貫入抵抗値と経過時間の関係を表す近似式を容易に精度よく決定することができる。 Further, according to another concrete construction timing prediction device according to the present invention, the predetermined penetration resistance value is 1 (N / mm 2 ) and the predetermined subtraction time is 60 minutes. An approximate expression expressing the relationship of elapsed time can be easily and accurately determined.

また、本発明に係るコンクリートの施工方法によれば、上述したコンクリートの施工タイミングの予測方法を用いて施工タイミングを予測するステップと、コンクリートを打設するステップと、予測した施工タイミングに基づいて、コンクリートの表面に対する押え作業を実施するステップとを有するので、施工前に予測した施工タイミングに基づいて、コンクリートの表面に対する押え作業を適正に行うことが可能となる。これにより、安定した品質のコンクリートを施工することができる。 Further, according to the concrete construction method according to the present invention, the step of predicting the construction timing by using the above-mentioned method of predicting the construction timing of concrete, the step of placing concrete, and the predicted construction timing are used. Since it has a step of performing the pressing work on the concrete surface, it is possible to properly perform the pressing work on the concrete surface based on the construction timing predicted before the construction. This makes it possible to construct concrete of stable quality.

以上のように、本発明に係るコンクリートの施工タイミングの予測方法、予測装置およびコンクリートの施工方法は、コンクリートスラブの施工に有用であり、特に、コンクリートスラブの押え作業の施工タイミングを予測するのに適している。 As described above, the concrete construction timing prediction method, the prediction device, and the concrete construction method according to the present invention are useful for concrete slab construction, and in particular, for predicting the construction timing of the concrete slab pressing work. Are suitable.

Claims (5)

施工中のコンクリートの表面に対する押え作業を実施する前に、押え作業を行うのに好適な施工タイミングを予測するための方法であって、
コンクリートの注水時刻を取得するステップと、
コンクリートの初期温度を測定するステップと、
予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の切片情報と、コンクリートの初期温度の関係に対して、測定した初期温度を当てはめることで、測定した初期温度に対応する切片情報を求めるステップと、
求めた切片情報を、貫入抵抗値と経過時間の関係を表す近似式に当てはめることで、所定の貫入抵抗値に達するまでの経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算することで、注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定するステップと、
推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定するステップと、
予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、所定の貫入抵抗値に達するまでの経過時間から所定の減算時間を減算した時点におけるコンクリートの温度の関係に対して、測定したコンクリートの温度を当てはめることで、測定したコンクリートの温度に対応する傾き情報を求めるステップと、
求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、決定した近似式に対して、押え作業の施工タイミングに対応する貫入抵抗値を当てはめることで、経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算して得られる時刻を押え作業の施工タイミングとして予測するステップとを有することを特徴とするコンクリートの施工タイミングの予測方法。
It is a method for predicting a suitable construction timing for performing the pressing work before performing the pressing work on the concrete surface during construction.
Steps to get the water injection time of concrete and
Steps to measure the initial temperature of concrete,
It was measured by applying the measured initial temperature to the relationship between the initial temperature of concrete and the section information of the approximate formula showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test grasped in advance. Steps to obtain section information corresponding to the initial temperature,
By applying the obtained section information to an approximate formula that expresses the relationship between the penetration resistance value and the elapsed time, the elapsed time until the predetermined penetration resistance value is reached is obtained, and the obtained elapsed time is added to the water injection time of the concrete. Then, the step of estimating the elapsed time from the water injection time to reaching the predetermined penetration resistance value, and
A step of measuring the temperature of concrete at a time obtained by adding a predetermined subtraction time from an estimated elapsed time to the water injection time of concrete.
At the time when the predetermined subtraction time is subtracted from the inclination information of the approximate expression showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test grasped in advance and the elapsed time until the predetermined penetration resistance value is reached. A step to obtain tilt information corresponding to the measured concrete temperature by applying the measured concrete temperature to the relationship of the concrete temperature, and
By using the obtained inclination information and section information, an approximate expression expressing the relationship between the intrusion resistance value and the elapsed time is determined, and the intrusion resistance value corresponding to the construction timing of the presser work is applied to the determined approximate expression. , A method for predicting the construction timing of concrete, which comprises a step of obtaining an elapsed time, adding the obtained elapsed time to the water injection time of the concrete, and predicting the time obtained as the construction timing of the pressing work.
所定の貫入抵抗値は1(N/mm)であり、所定の減算時間は60分であることを特徴とする請求項1に記載のコンクリートの施工タイミングの予測方法。 The method for predicting concrete construction timing according to claim 1, wherein the predetermined penetration resistance value is 1 (N / mm 2 ), and the predetermined subtraction time is 60 minutes. 施工中のコンクリートの表面に対する押え作業を実施する前に、押え作業を行うのに好適な施工タイミングを予測するための装置であって、
コンクリートの注水時刻を取得する手段と、
コンクリートの初期温度を測定する手段と、
予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の切片情報と、コンクリートの初期温度の関係に対して、測定した初期温度を当てはめることで、測定した初期温度に対応する切片情報を求める手段と、
求めた切片情報を、貫入抵抗値と経過時間の関係を表す近似式に当てはめることで、所定の貫入抵抗値に達するまでの経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算することで、注水時刻から所定の貫入抵抗値に達するまでの経過時間を推定する手段と、
推定した経過時間から所定の減算時間を減算して得られる時間を、コンクリートの注水時刻に加算して得られる時刻において、コンクリートの温度を測定する手段と、
予め把握された所定の貫入抵抗試験により得られる貫入抵抗値と経過時間の関係を表す近似式の傾き情報と、所定の貫入抵抗値に達するまでの経過時間から所定の減算時間を減算した時点におけるコンクリートの温度の関係に対して、測定したコンクリートの温度を当てはめることで、測定したコンクリートの温度に対応する傾き情報を求める手段と、
求めた傾き情報と切片情報を用いて、貫入抵抗値と経過時間の関係を表す近似式を決定し、決定した近似式に対して、押え作業の施工タイミングに対応する貫入抵抗値を当てはめることで、経過時間を求め、求めた経過時間をコンクリートの注水時刻に加算して得られる時刻を押え作業の施工タイミングとして予測する手段とを備えることを特徴とするコンクリートの施工タイミングの予測装置。
It is a device for predicting the suitable construction timing for performing the pressing work before performing the pressing work on the concrete surface during construction.
By means of obtaining the water injection time of concrete,
A means of measuring the initial temperature of concrete,
It was measured by applying the measured initial temperature to the relationship between the initial temperature of concrete and the section information of the approximate formula showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test grasped in advance. A means for obtaining section information corresponding to the initial temperature,
By applying the obtained section information to an approximate formula that expresses the relationship between the penetration resistance value and the elapsed time, the elapsed time until the predetermined penetration resistance value is reached is obtained, and the obtained elapsed time is added to the water injection time of the concrete. Then, as a means to estimate the elapsed time from the water injection time to reach the predetermined penetration resistance value,
A means for measuring the temperature of concrete at a time obtained by adding a predetermined subtraction time from the estimated elapsed time to the water injection time of the concrete.
At the time when the predetermined subtraction time is subtracted from the inclination information of the approximate expression showing the relationship between the penetration resistance value and the elapsed time obtained by the predetermined penetration resistance test grasped in advance and the elapsed time until the predetermined penetration resistance value is reached. A means to obtain tilt information corresponding to the measured temperature of the concrete by applying the measured temperature of the concrete to the relationship of the temperature of the concrete.
By using the obtained inclination information and section information, an approximate expression expressing the relationship between the intrusion resistance value and the elapsed time is determined, and the intrusion resistance value corresponding to the construction timing of the presser work is applied to the determined approximate expression. , A device for predicting the construction timing of concrete, which is provided with a means for obtaining an elapsed time and predicting the time obtained by adding the obtained elapsed time to the water injection time of the concrete as the construction timing of the pressing work.
所定の貫入抵抗値は1(N/mm)であり、所定の減算時間は60分であることを特徴とする請求項3に記載のコンクリートの施工タイミングの予測装置。 The concrete construction timing prediction device according to claim 3, wherein the predetermined penetration resistance value is 1 (N / mm 2 ), and the predetermined subtraction time is 60 minutes. 請求項1または2に記載のコンクリートの施工タイミングの予測方法を用いて施工タイミングを予測するステップと、コンクリートを打設するステップと、予測した施工タイミングに基づいて、コンクリートの表面に対する押え作業を実施するステップとを有することを特徴とするコンクリートの施工方法。 A step of predicting the construction timing using the method for predicting the construction timing of concrete according to claim 1 or 2, a step of placing concrete, and a pressing operation against the surface of concrete are carried out based on the predicted construction timing. A concrete construction method characterized by having steps to be made.
JP2020191936A 2020-11-18 2020-11-18 Prediction method of construction timing, prediction device and concrete construction method Pending JP2022080719A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2020191936A JP2022080719A (en) 2020-11-18 2020-11-18 Prediction method of construction timing, prediction device and concrete construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2020191936A JP2022080719A (en) 2020-11-18 2020-11-18 Prediction method of construction timing, prediction device and concrete construction method

Publications (1)

Publication Number Publication Date
JP2022080719A true JP2022080719A (en) 2022-05-30

Family

ID=81756870

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2020191936A Pending JP2022080719A (en) 2020-11-18 2020-11-18 Prediction method of construction timing, prediction device and concrete construction method

Country Status (1)

Country Link
JP (1) JP2022080719A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116754459A (en) * 2023-08-22 2023-09-15 武汉理工大学 Detection method for impervious grade of existing concrete

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116754459A (en) * 2023-08-22 2023-09-15 武汉理工大学 Detection method for impervious grade of existing concrete
CN116754459B (en) * 2023-08-22 2023-11-07 武汉理工大学 Detection method for impervious grade of existing concrete

Similar Documents

Publication Publication Date Title
US8032244B2 (en) Method and system for concrete quality control based on the concrete's maturity
JP6252856B2 (en) Prediction method and prediction device for concrete leveling time
US20060058904A1 (en) Method and system for concrete quality control based on the concrete's maturity
Lin et al. Nondestructive quality assessment of asphalt pavements based on dynamic modulus
JP2013242163A (en) Corrosion progress prediction method and corrosion progress prediction apparatus
JP6936718B2 (en) Prediction method of concrete leveling work time, prediction device and concrete construction method
JP5246113B2 (en) Early estimation method of concrete drying shrinkage strain
JP2022080719A (en) Prediction method of construction timing, prediction device and concrete construction method
CN103954557A (en) Image analysis method for comprehensively assessing concrete carbonation rate coefficient
Debailleux Schmidt hammer rebound hardness tests for the characterization of ancient fired clay bricks
JP7042602B2 (en) How to control the hardening time of concrete, control device and concrete construction method
Liao et al. A humidity-adjusted maturity function for the early age strength prediction of concrete
JP4924557B2 (en) Concrete frost damage deterioration prediction device and its program
JP5755550B2 (en) Calculation method, calculation device and calculation program for evaluation index of concrete surface quality, and evaluation method, evaluation device and evaluation program for concrete surface quality
JP2011257245A (en) Corrosion amount estimation method, corrosion amount estimation device, and management method for reinforced concrete
Teshale Low-temperature fracture behavior of asphalt concrete in semi-circular bend test
KR101791878B1 (en) System and method for monitoring durability and predicting life time about chloride penetration of concrete structure
Kwak et al. Plastic shrinkage cracking in concrete slabs. Part I: a numerical model
JP7000107B2 (en) Prediction method of concrete leveling workable time, prediction device and concrete construction method
JP4182941B2 (en) Concrete frost damage deterioration prediction device and its program
JP2018009821A (en) Concrete demold time strength estimation system
JP2022079221A (en) Prediction method, prediction device of construction timing of concrete, and construction method of concrete
Bauset-Tortonda et al. Effect of single and twin notches in prestressed concrete beams
JPH05340938A (en) Method and device for judging leveling timing of concrete
JP2023144835A (en) Method for estimating strength development of hydraulic composition and program of estimation processing of strength development of hydraulic composition

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20231025