JP2015203204A - Method and device for estimating amount of time available for concrete leveling work - Google Patents

Method and device for estimating amount of time available for concrete leveling work Download PDF

Info

Publication number
JP2015203204A
JP2015203204A JP2014082283A JP2014082283A JP2015203204A JP 2015203204 A JP2015203204 A JP 2015203204A JP 2014082283 A JP2014082283 A JP 2014082283A JP 2014082283 A JP2014082283 A JP 2014082283A JP 2015203204 A JP2015203204 A JP 2015203204A
Authority
JP
Japan
Prior art keywords
time
leveling
concrete
bleeding water
generation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2014082283A
Other languages
Japanese (ja)
Other versions
JP6252856B2 (en
Inventor
喜昭 竹本
Yoshiaki Takemoto
喜昭 竹本
俊文 菊地
Toshibumi Kikuchi
俊文 菊地
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP2014082283A priority Critical patent/JP6252856B2/en
Publication of JP2015203204A publication Critical patent/JP2015203204A/en
Application granted granted Critical
Publication of JP6252856B2 publication Critical patent/JP6252856B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method and device for estimating the amount of time available for concrete leveling work, before starting leveling work on a concrete surface.SOLUTION: In a method for estimating the amount of work time available for leveling a concrete surface, the amount of time available for leveling work is derived by measuring the amount of bleeding water generated from concrete immediately after casting and the conductivity of the concrete, estimating the halting time when generation of bleeding water terminates based on the amount of bleeding water generated, before the fall starting time when the conductivity starts falling, and applying the estimated halting time of bleeding water generation and the measured fall starting time of conductivity into a predetermined relationship among the amount of time available for leveling work, the fall starting time of conductivity, and the halting time of bleeding water generation.

Description

本発明は、例えばコンクリート製の床スラブなどの表面の均し作業を伴うコンクリートの均し施工可能時間の予測方法および予測装置に関するものである。   The present invention relates to a prediction method and a prediction device for a concrete leveling time that can be used for leveling work of a surface such as a concrete floor slab.

従来、建設現場においてコンクリート製の床スラブを施工する場合は、打設したコンクリートのレベルを出し、床スラブとしての表面の平滑性を確保するべく、熟練技術者が木ゴテや金ゴテでコンクリート表面を数回ずつ押える均し作業を行うことで、コンクリート表面を平滑に仕上げている。この均し作業の時期は、コンクリート表面の硬化速度とコンクリート表面に浮き上がってくるブリーディング水の量を目安にして、熟練技術者の経験によって判断していた。   Conventionally, when constructing a concrete floor slab at a construction site, a skilled engineer uses a wooden iron or a gold iron to obtain the level of the concrete placed and to ensure the smoothness of the surface as the floor slab. The surface of the concrete is smoothed by performing a leveling operation that can be pressed several times. The timing of the leveling work was determined by the experience of skilled technicians, using the hardening speed of the concrete surface and the amount of bleeding water floating on the concrete surface as a guide.

このコンクリートの硬化速度やブリーディング水の発生速度および発生量は、コンクリートの配合や施工環境によって変化する。例えば、夏季のように施工環境温度が高い場合は、一般的にコンクリートの硬化速度は速く、ブリーディング水の発生速度も速い。そのため、均し作業は早く取り掛かり、早く終える必要がある。一方、冬季のように施工環境温度が低い場合は、コンクリートの硬化速度は遅く、ブリーディング水の発生速度も遅い。そのため、均し作業の時期は遅くなり、作業完了時刻がコンクリート打設日の深夜となることも多い。また、コンクリートの配合において砕砂の割合が多い場合は、ブリーディング水の発生量が多い傾向となる。   The concrete curing rate and bleeding water generation rate and amount vary depending on the concrete mix and construction environment. For example, when the construction environment temperature is high as in summer, the concrete is generally hardened at a high rate, and the generation rate of bleeding water is also high. Therefore, it is necessary to start the leveling work quickly and finish it quickly. On the other hand, when the construction environment temperature is low, such as in winter, the curing rate of concrete is slow and the generation rate of bleeding water is also slow. For this reason, the leveling work is delayed and the work completion time is often late at night on the concrete placement day. Moreover, when the ratio of crushed sand is large in the blending of concrete, the amount of bleeding water tends to be large.

このように、熟練技術者は、コンクリートの配合や施工環境に合わせ、均し作業の時期を調節する必要がある。ところが、上述したように均し作業の時期は熟練技術者の経験に頼っており、熟練技術者各人で判断基準が異なることから、熟練技術者が変わると、同じコンクリートの配合、施工環境でも均し作業の時期がずれるケースがある。均し作業の時期がずれると、以下の(1)、(2)のような問題が発生する。   In this way, the skilled engineer needs to adjust the level of the leveling work according to the concrete composition and construction environment. However, as described above, the leveling work depends on the experience of skilled engineers, and the judgment criteria differ for each skilled engineer. There is a case where the time of leveling work shifts. When the leveling operation is shifted, the following problems (1) and (2) occur.

(1)コンクリートの硬化やブリーディング水の発生速度が速く、均し作業の時期が遅れると、コンクリートの硬化が進み、表面の水分が失われることから、表面を平滑に均すことが難しくなり、凹凸が多い、平滑度の悪い仕上がりとなる。 (1) If the rate of concrete hardening and bleeding water is fast and the leveling operation is delayed, the concrete will harden and the surface will lose moisture, making it difficult to level the surface smoothly. There are many irregularities and the finish is poor in smoothness.

(2)コンクリートの硬化やブリーディング水の発生速度が遅く、均し作業の時期が速すぎる場合は、コンクリート表面の強度不足となったり、コンクリート表層が剥がれやすくなったりする。 (2) If the rate of hardening of concrete or bleeding water is slow and the leveling operation is too fast, the concrete surface will be insufficient in strength or the concrete surface layer will be easily peeled off.

コンクリートの均し作業の時期を把握する方法については、過去にもいくつか検討されている。従来の方法としては、例えば特許文献1に記載のものが知られている。この方法は、硬化前のコンクリート躯体中に電極を設置し、コンクリートの硬化が進むにつれて変化する電気抵抗値を測定するものである。ここで、あらかじめ対象としているコンクリートの試験体によって表面の剥離強度および貫入抵抗値と、電気抵抗値との関係を求めるとともにデータとして蓄積し、これに基づいて最適均し時期を把握しておく。この方法によれば、測定した電気抵抗値が最適均し時期に対応する判定基準値に到達した時点を、最適な均し時期として判定する。   Several methods have been examined in the past for grasping the timing of concrete leveling. As a conventional method, for example, a method described in Patent Document 1 is known. In this method, an electrode is installed in a concrete frame before hardening, and an electric resistance value that changes as the concrete hardens is measured. Here, the relationship between the peel strength and penetration resistance value of the surface and the electrical resistance value is obtained in advance by using a concrete specimen as a target and accumulated as data, and the optimum leveling time is grasped based on this. According to this method, the time when the measured electric resistance value reaches the determination reference value corresponding to the optimum leveling time is determined as the optimum leveling time.

ところが、コンクリートの電気抵抗値は、コンクリートと電極の接触の仕方によって大きく変動する欠点があり、電気抵抗値の微妙な変化を的確に捉えることは難しい。また、あらかじめ対象とするコンクリートの試験体を用いたデータを蓄積しておくことは、膨大なデータベースを構築しておく必要があるため現実的でない。   However, the electrical resistance value of concrete has a drawback that it fluctuates greatly depending on how the concrete contacts with the electrodes, and it is difficult to accurately capture the subtle changes in the electrical resistance value. In addition, it is not realistic to store data using a concrete specimen as a target in advance because it is necessary to construct a huge database.

なお、本発明に関連する従来の技術として、コンクリート打設直後の締固め作業のタイミングを判定する方法が知られている(例えば、特許文献2〜4を参照)。   As a conventional technique related to the present invention, there is known a method for determining the timing of compaction work immediately after placing concrete (see, for example, Patent Documents 2 to 4).

特開平5−340938号公報JP-A-5-340938 特開2013−53492号公報JP 2013-53492 A 特開2002−242435号公報JP 2002-242435 A 特開2013−101070号公報JP 2013-101070 A

ところで、上記の従来の特許文献1に記載の方法では、コンクリート表面の均し作業を始める前に、均し作業を適正に行うことが可能な時間(均し施工可能時間)を把握することはできなかった。   By the way, in the method of the above-mentioned conventional patent document 1, before starting the leveling work of the concrete surface, it is possible to grasp the time during which the leveling work can be performed properly (the leveling work possible time). could not.

本発明は、上記に鑑みてなされたものであって、コンクリート表面の均し作業を始める前に、均し施工可能時間を把握することができるコンクリートの均し施工可能時間の予測方法および予測装置を提供することを目的とする。   The present invention has been made in view of the above, and a concrete leveling workable time prediction method and a prediction device capable of grasping the leveling workable time before starting the concrete surface leveling work The purpose is to provide.

上記した課題を解決し、目的を達成するために、本発明に係るコンクリートの均し施工可能時間の予測方法は、コンクリートの表面を均すことができる均し施工可能時間を予測する方法であって、打設直後の前記コンクリートから発生するブリーディング水の発生量と、前記コンクリートの導電率とを測定し、前記導電率が降下を開始する降下開始時間の前に、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生が終了する発生終了時間を予測し、予測した前記ブリーディング水の発生終了時間および測定した前記導電率の降下開始時間を、あらかじめ把握してある均し施工可能時間と導電率の降下開始時間とブリーディング水の発生終了時間との関係に当てはめることで、均し施工可能時間を求めることを特徴とする。   In order to solve the above-described problems and achieve the object, the method for predicting the leveling time of concrete according to the present invention is a method for predicting the leveling time that can level the concrete surface. Measuring the amount of bleeding water generated from the concrete immediately after placing and the conductivity of the concrete, and before the descent start time when the conductivity starts to drop, the amount of bleeding water generated Based on this, the occurrence end time at which the generation of the bleeding water ends is predicted, the predicted generation end time of the bleeding water and the measured descent start time of the conductivity are grasped in advance and the leveling work possible time By applying the relationship between the conductivity start time and the bleeding water finish time, the leveling time can be calculated.

また、本発明に係る他のコンクリートの均し施工可能時間の予測方法は、上述した発明において、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生速度の単位時間当たりの変化量を一次方程式で近似し、前記一次方程式を1回または2回積分して得られる二次方程式または三次方程式の特性値を求めることで、前記ブリーディング水の発生終了時間を予測することを特徴とする。   In addition, in the above-described invention, the method for predicting the leveling time of concrete according to the present invention is based on the amount of bleeding water generated, and the amount of change per unit time in the generation speed of the bleeding water is firstly calculated. The generation end time of the bleeding water is predicted by obtaining a characteristic value of a quadratic equation or a cubic equation obtained by approximating with an equation and integrating the linear equation once or twice.

また、本発明に係る他のコンクリートの均し施工可能時間の予測方法は、上述した発明において、前記関係は、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係であることを特徴とする。   In addition, in the above-described invention, the method for predicting the leveling time of other concrete according to the present invention is based on the above-described relationship between the leveling time that can be leveled and the start time of decrease in electrical conductivity by the generation end time of bleeding water. It is characterized by the relationship with the divided value.

また、本発明に係る他のコンクリートの均し施工可能時間の予測方法は、上述した発明において、求めた均し施工可能時間が、所定の施工条件で決まる均し施工可能時間の範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を上回り、前記コンクリートの硬化を促進するための促進剤を前記コンクリートの表面に散布するべき範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を下回り、前記コンクリートの硬化を遅延するための遅延剤を前記コンクリートの表面に散布するべき範囲にあるかを予測することを特徴とする。   In addition, in the above-described invention, the method for predicting the leveling workable time of other concrete according to the present invention is, in the above-described invention, whether the obtained leveling workable time is within the range of the leveling workable time determined by predetermined construction conditions. Exceeds the range of the leveling time that can be determined according to the predetermined construction conditions, and is within the range in which the accelerator for promoting the hardening of the concrete is to be sprayed on the surface of the concrete, or is determined according to the predetermined level. It is less than the range of possible construction time, and it is predicted whether it exists in the range which should spread the retarder for delaying the hardening of the concrete to the surface of the concrete.

また、本発明に係るコンクリートの均し施工可能時間の予測装置は、コンクリートの表面を均すことができる均し施工可能時間を予測する装置であって、打設直後の前記コンクリートから発生するブリーディング水の発生量を測定するブリーディング水の発生量測定手段と、前記コンクリートの導電率を測定する導電率測定手段と、前記導電率が降下を開始する降下開始時間の前に、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生が終了する発生終了時間を予測するブリーディング水発生終了時間予測手段と、予測した前記ブリーディング水の発生終了時間および測定した前記導電率の降下開始時間を、あらかじめ把握してある均し施工可能時間と導電率の降下開始時間とブリーディング水の発生終了時間との関係に当てはめることで、均し施工可能時間を求める均し施工可能時間予測手段とを備えることを特徴とする。   The concrete leveling time predicting device according to the present invention is a device for predicting the leveling time that can level the surface of the concrete, and is a bleeding generated from the concrete immediately after placing. Bleeding water generation amount measuring means for measuring the generation amount of water, conductivity measuring means for measuring the conductivity of the concrete, and generation of the bleeding water before the descent start time when the conductivity starts to decrease Based on the amount, the bleeding water generation end time predicting means for predicting the generation end time at which the generation of bleeding water ends, the predicted generation end time of the bleeding water and the measured decrease start time of the conductivity are determined in advance. The relationship between the known leveling time, the start time of decrease in electrical conductivity, and the generation end time of bleeding water By fitting, characterized in that it comprises a leveling construction available time prediction means for determining a leveling construction possible time.

また、本発明に係る他のコンクリートの均し施工可能時間の予測装置は、上述した発明において、ブリーディング水発生終了時間予測手段は、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生速度の単位時間当たりの変化量を一次方程式で近似し、前記一次方程式を1回または2回積分して得られる二次方程式または三次方程式の特性値を求めることで、前記ブリーディング水の発生終了時間を予測することを特徴とする。   Further, the predicting device for the leveling time of other concrete according to the present invention is the invention described above, wherein the bleeding water generation end time predicting means is based on the amount of bleeding water generated, By approximating the amount of change per unit time with a linear equation, and determining the characteristic value of a quadratic equation or a cubic equation obtained by integrating the linear equation once or twice, the generation end time of the bleeding water is determined. It is characterized by prediction.

また、本発明に係る他のコンクリートの均し施工可能時間の予測装置は、上述した発明において、均し施工可能時間予測手段における前記関係は、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係であることを特徴とする。   In addition, in the above-described invention, the above-described relationship in the leveling workable time predicting means includes the leveling workable time and the decrease start time of the conductivity. It is a relationship with the value which remove | divided by the generation | occurrence | production completion time of bleeding water.

また、本発明に係る他のコンクリートの均し施工可能時間の予測装置は、上述した発明において、求めた均し施工可能時間が、所定の施工条件で決まる均し施工可能時間の範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を上回り、前記コンクリートの硬化を促進するための促進剤を前記コンクリートの表面に散布するべき範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を下回り、前記コンクリートの硬化を遅延するための遅延剤を前記コンクリートの表面に散布するべき範囲にあるかを予測する均し施工可能時間の範囲予測手段をさらに備えることを特徴とする。   In addition, in the above-described invention, the prediction apparatus for the leveling workable time of other concrete according to the present invention is in the range of the leveling time available for the leveling determined by predetermined construction conditions. Exceeds the range of the leveling time that can be determined according to the predetermined construction conditions, and is within the range in which the accelerator for promoting the hardening of the concrete is to be sprayed on the surface of the concrete, or is determined according to the predetermined level. It further comprises a range predicting means for leveling workable time that predicts whether a retarder for delaying hardening of the concrete is within a range to be sprayed on the surface of the concrete that is below the workable time range. And

本発明に係るコンクリートの均し施工可能時間の予測方法によれば、コンクリートの表面を均すことができる均し施工可能時間を予測する方法であって、打設直後の前記コンクリートから発生するブリーディング水の発生量と、前記コンクリートの導電率とを測定し、前記導電率が降下を開始する降下開始時間の前に、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生が終了する発生終了時間を予測し、予測した前記ブリーディング水の発生終了時間および測定した前記導電率の降下開始時間を、あらかじめ把握してある均し施工可能時間と導電率の降下開始時間とブリーディング水の発生終了時間との関係に当てはめることで、均し施工可能時間を求めるので、導電率が降下を開始する降下開始時間の前、つまりコンクリート表面の均し作業を始める前に、均し施工可能時間を把握することができるという効果を奏する。   According to the method for predicting the leveling time of concrete according to the present invention, it is a method for predicting the leveling time capable of leveling the concrete, which is generated from the concrete immediately after placing. The amount of water generation and the conductivity of the concrete are measured, and the generation of the bleeding water is terminated based on the amount of generation of the bleeding water before the descent start time when the conductivity starts to decrease. Predict the end time, predict the generation time of the bleeding water and the measured start time of the decrease in conductivity, knowing beforehand the leveling work possible time, the start time of decrease in conductivity, and the end of occurrence of bleeding water By applying to the relationship with the time, the leveling work possible time is obtained, so the conductivity starts before the descent start time, i.e. Before you begin leveling work cleat surface, an effect that it is possible to grasp the leveling construction possible time.

また、本発明に係る他のコンクリートの均し施工可能時間の予測方法によれば、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生速度の単位時間当たりの変化量を一次方程式で近似し、前記一次方程式を1回または2回積分して得られる二次方程式または三次方程式の特性値を求めることで、前記ブリーディング水の発生終了時間を予測するので、ブリーディング水の発生終了時間を簡便な統計的な手法によって精度よく予測することができるという効果を奏する。   Further, according to the method for predicting the leveling time of other concrete according to the present invention, based on the generation amount of the bleeding water, the amount of change per unit time of the generation speed of the bleeding water is approximated by a linear equation. The generation end time of the bleeding water is predicted by obtaining the characteristic value of the quadratic equation or the cubic equation obtained by integrating the linear equation once or twice, so that the generation end time of the bleeding water can be simplified. The effect is that it can be accurately predicted by a statistical method.

また、本発明に係る他のコンクリートの均し施工可能時間の予測方法によれば、前記関係は、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係であるので、一般に比例関係にあると考えられるこの関係に当てはめることで、均し施工可能時間を簡便に求めることができるという効果を奏する。   Further, according to the method of predicting the leveling workable time of other concrete according to the present invention, the relationship is a value obtained by dividing the leveling time and the decrease start time of conductivity by the generation end time of bleeding water. Therefore, by applying this relationship, which is generally considered to be in a proportional relationship, it is possible to easily obtain the leveling workable time.

また、本発明に係る他のコンクリートの均し施工可能時間の予測方法によれば、求めた均し施工可能時間が、所定の施工条件で決まる均し施工可能時間の範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を上回り、前記コンクリートの硬化を促進するための促進剤を前記コンクリートの表面に散布するべき範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を下回り、前記コンクリートの硬化を遅延するための遅延剤を前記コンクリートの表面に散布するべき範囲にあるかを予測するので、予測した均し施工可能時間の範囲に基づいて、その後の施工上の対応をより適正に行うことができるという効果を奏する。例えば、予測された範囲が、遅延剤を散布するべき範囲の場合には、コンクリート表面に遅延剤を散布する対応を行うことで、その後の均し施工可能時間を長くすることができる。また、予測された範囲が、促進剤を散布するべき範囲の場合には、コンクリート表面に促進剤を散布する対応を行うことで、その後の均し施工可能時間を短くすることができる。   Further, according to the method for predicting the leveling workable time of other concrete according to the present invention, the obtained leveling workable time is within the range of the leveling workable time determined by the predetermined construction conditions, The leveling time that exceeds the range of the leveling time that is determined by the work conditions and that is within the range in which the accelerator for accelerating the hardening of the concrete is to be sprayed on the surface of the concrete, or that is determined by the predetermined leveling conditions. Therefore, it is predicted that the retarder for delaying the hardening of the concrete is within the range to be sprayed on the surface of the concrete. There exists an effect that the above correspondence can be performed more appropriately. For example, when the predicted range is a range in which the retarder is to be sprayed, it is possible to lengthen the subsequent leveling time by performing a countermeasure to spray the retarder on the concrete surface. In addition, when the predicted range is a range in which the accelerator is to be sprayed, it is possible to shorten the subsequent leveling time by performing a countermeasure to spray the accelerator on the concrete surface.

また、本発明に係るコンクリートの均し施工可能時間の予測装置によれば、コンクリートの表面を均すことができる均し施工可能時間を予測する装置であって、打設直後の前記コンクリートから発生するブリーディング水の発生量を測定するブリーディング水の発生量測定手段と、前記コンクリートの導電率を測定する導電率測定手段と、前記導電率が降下を開始する降下開始時間の前に、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生が終了する発生終了時間を予測するブリーディング水発生終了時間予測手段と、予測した前記ブリーディング水の発生終了時間および測定した前記導電率の降下開始時間を、あらかじめ把握してある均し施工可能時間と導電率の降下開始時間とブリーディング水の発生終了時間との関係に当てはめることで、均し施工可能時間を求める均し施工可能時間予測手段とを備えるので、導電率が降下を開始する降下開始時間の前、つまりコンクリート表面の均し作業を始める前に、均し施工可能時間を把握することができるという効果を奏する。   Further, according to the predicting device of the concrete leveling workable time according to the present invention, it is a device for predicting the leveling workable time that can level the surface of the concrete, and is generated from the concrete immediately after placing. Generating amount measuring means for measuring the amount of bleeding water to be measured, conductivity measuring means for measuring the conductivity of the concrete, and before the descent start time at which the conductivity starts decreasing, the bleeding water A bleeding water generation end time predicting means for predicting the generation end time at which the generation of bleeding water ends based on the generation amount of the bleeding water, and the predicted generation end time of the bleeding water and the measured decrease start time of the conductivity. The leveling work time, conductivity lowering start time, and bleeding water generation end time By applying to the relationship, it is equipped with a leveling workable time predicting means for obtaining the leveling workable time, so before the descent start time when the conductivity starts to drop, that is, before starting the leveling work of the concrete surface, There is an effect that it is possible to grasp the leveling work possible time.

また、本発明に係る他のコンクリートの均し施工可能時間の予測装置によれば、ブリーディング水発生終了時間予測手段は、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生速度の単位時間当たりの変化量を一次方程式で近似し、前記一次方程式を1回または2回積分して得られる二次方程式または三次方程式の特性値を求めることで、前記ブリーディング水の発生終了時間を予測するので、ブリーディング水の発生終了時間を簡便な統計的な手法によって精度よく予測することができるという効果を奏する。   Further, according to the predicting apparatus for the other concrete leveling time according to the present invention, the bleeding water generation end time predicting means is based on the amount of bleeding water generated, and the unit time of the generation speed of the bleeding water. Since the amount of change per hit is approximated by a linear equation and the characteristic value of a quadratic or cubic equation obtained by integrating the linear equation once or twice is obtained, the generation end time of the bleeding water is predicted. In addition, there is an effect that the occurrence end time of bleeding water can be accurately predicted by a simple statistical method.

また、本発明に係る他のコンクリートの均し施工可能時間の予測装置によれば、均し施工可能時間予測手段における前記関係は、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係であるので、一般に比例関係にあると考えられるこの関係に当てはめることで、均し施工可能時間を簡便に求めることができるという効果を奏する。   Further, according to the predicting apparatus for the leveling workable time of other concrete according to the present invention, the relationship in the leveling workable time predicting means is that the leveling workable time and the decrease start time of the conductivity are set as a bleeding water. Therefore, by applying this relationship, which is generally considered to be in a proportional relationship, it is possible to easily obtain the leveling workable time.

また、本発明に係る他のコンクリートの均し施工可能時間の予測装置によれば、求めた均し施工可能時間が、所定の施工条件で決まる均し施工可能時間の範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を上回り、前記コンクリートの硬化を促進するための促進剤を前記コンクリートの表面に散布するべき範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を下回り、前記コンクリートの硬化を遅延するための遅延剤を前記コンクリートの表面に散布するべき範囲にあるかを予測する均し施工可能時間の範囲予測手段をさらに備えるので、予測した均し施工可能時間の範囲に基づいて、その後の施工上の対応をより適正に行うことができるという効果を奏する。例えば、予測された範囲が、遅延剤を散布するべき範囲の場合には、コンクリート表面に遅延剤を散布する対応を行うことで、その後の均し施工可能時間を長くすることができる。また、予測された範囲が、促進剤を散布するべき範囲の場合には、コンクリート表面に促進剤を散布する対応を行うことで、その後の均し施工可能時間を短くすることができる。   Further, according to the predicting device for the leveling workable time of other concrete according to the present invention, whether the determined leveling workable time is within the range of the leveling workable time determined by the predetermined construction conditions, The leveling time that exceeds the range of the leveling time that is determined by the work conditions and that is within the range in which the accelerator for accelerating the hardening of the concrete is to be sprayed on the surface of the concrete, or that is determined by the predetermined leveling conditions. Is further provided with means for predicting the range of possible workable time for predicting whether the retarder for retarding the hardening of the concrete is within the range to be sprayed on the surface of the concrete. Based on the range of possible construction time, there is an effect that it is possible to more appropriately cope with the subsequent construction. For example, when the predicted range is a range in which the retarder is to be sprayed, it is possible to lengthen the subsequent leveling time by performing a countermeasure to spray the retarder on the concrete surface. In addition, when the predicted range is a range in which the accelerator is to be sprayed, it is possible to shorten the subsequent leveling time by performing a countermeasure to spray the accelerator on the concrete surface.

図1は、本発明に係るコンクリートの均し施工可能時間の予測方法および予測装置の実施例を示す概略フローチャート図である。FIG. 1 is a schematic flowchart showing an embodiment of a predicting method and a predicting apparatus for concrete leveling workable time according to the present invention. 図2は、ブリーディング水の発生量と導電率の時間変化の一例を示す図である。FIG. 2 is a diagram showing an example of the time variation of the amount of bleeding water generated and conductivity. 図3は、単位時間当たりのブリーディング水の発生速度の時間変化量から求めた一次近似方程式を示す図である。FIG. 3 is a diagram showing a first-order approximation equation obtained from the amount of time change in the generation rate of bleeding water per unit time. 図4は、単位時間当たりのブリーディング水の発生速度から求めた二次方程式を示す図である。FIG. 4 is a diagram showing a quadratic equation obtained from the generation rate of bleeding water per unit time. 図5は、ブリーディング水の発生量から求めた三次方程式を示す図である。FIG. 5 is a diagram showing a cubic equation obtained from the amount of bleeding water generated. 図6は、導電率の測定結果の一例を示す図である。FIG. 6 is a diagram illustrating an example of a measurement result of conductivity. 図7は、導電率の降下開始時間とブリーディング水の発生終了時間および均し施工可能時間の関係の一例を示す図である。FIG. 7 is a diagram showing an example of the relationship between the decrease start time of electrical conductivity, the generation end time of bleeding water, and the leveling work possible time. 図8は、均し施工可能時間範囲の調整例を示すイメージ図である。FIG. 8 is an image diagram showing an example of adjusting the leveling work possible time range. 図9は、本発明に係るコンクリートの均し施工可能時間の予測装置の実施例を示す概略ブロック図である。FIG. 9: is a schematic block diagram which shows the Example of the prediction apparatus of the leveling construction possible time of the concrete based on this invention.

以下に、本発明に係るコンクリートの均し施工可能時間の予測方法および予測装置の実施の形態を図面に基づいて詳細に説明する。ここで、本発明の対象とするコンクリートは、モルタル、セメントペーストなどのセメントを含有するセメント系材料を含む広義のコンクリートを意味するものである。また、以下の説明では、本発明の対象とするコンクリートの一例としてコンクリート製の床スラブを例にとり説明するが、この実施の形態によりこの発明が限定されるものではない。   DESCRIPTION OF EMBODIMENTS Embodiments of a method and apparatus for predicting a concrete leveling time that can be applied to concrete according to the present invention will be described below in detail with reference to the drawings. Here, the concrete which is the subject of the present invention means concrete in a broad sense including a cement-based material containing cement such as mortar and cement paste. Further, in the following description, a concrete floor slab will be described as an example of concrete targeted by the present invention. However, the present invention is not limited to this embodiment.

[コンクリートの均し施工可能時間の予測方法]
まず、本発明に係るコンクリートの均し施工可能時間の予測方法の実施の形態について図1〜図8を参照しながら説明する。
[Prediction method of concrete leveling time]
First, an embodiment of a method for predicting the leveling time of concrete according to the present invention will be described with reference to FIGS.

本発明に係るコンクリートの均し施工可能時間の予測方法は、コンクリートから発生するブリーディング水の発生終了時間と、コンクリートの導電率の降下開始時間の2つの時間を基にして、コンクリート(例えば床スラブ)の表面を均すことができる均し施工可能時間の長さを予測するものである。
次に、本発明の概略的手順について図1を参照しながら説明する。
The method of predicting the leveling time of concrete according to the present invention is based on two times, the generation end time of bleeding water generated from concrete and the start time of decrease in the electrical conductivity of the concrete (for example, floor slabs). ) To predict the length of time that can be leveled.
Next, a schematic procedure of the present invention will be described with reference to FIG.

[本発明の概略的手順]
図1に示すように、まず、コンクリートを打設し(ステップS1)、打設直後のコンクリートから発生するブリーディング水の発生量の測定を開始する(ステップS2)。この測定と同時に、打設直後のコンクリートの導電率の測定を開始する(ステップS5)。そして導電率の上昇を監視しておき(ステップS6)、導電率が降下を開始する降下開始時間を測定するようにする(ステップS7)。
[Schematic Procedure of the Present Invention]
As shown in FIG. 1, first, concrete is placed (step S1), and measurement of the amount of bleeding water generated from the concrete immediately after placement is started (step S2). Simultaneously with this measurement, measurement of the electrical conductivity of the concrete immediately after placing is started (step S5). Then, the increase in conductivity is monitored (step S6), and the decrease start time at which the conductivity starts decreasing is measured (step S7).

一方、測定されたブリーディング水の発生量、発生速度に基づいて、ブリーディング水の発生量を近似する三次方程式を求める(ステップS3)。求めた三次方程式より、ブリーディング水の発生が終了する発生終了時間を求める(ステップS4)。ここで、ブリーディング水の発生終了時間は、導電率が降下開始する前(ステップS7)に求めるようにする。   On the other hand, a cubic equation that approximates the generation amount of bleeding water is obtained based on the generation amount and generation speed of the measured bleeding water (step S3). From the calculated cubic equation, the generation end time at which the generation of bleeding water ends is determined (step S4). Here, the generation end time of bleeding water is obtained before the start of decrease in the conductivity (step S7).

求めたブリーディング水の発生終了時間と、導電率の降下開始時間とに基づいて、コンクリートの表面を均すことができる均し施工可能時間を求める(ステップS8)。必要に応じて均し施工可能時間に合わせた対応、対策を講じる(ステップS9)。   Based on the determined bleeding water generation end time and the electrical conductivity lowering start time, the leveling work possible time for leveling the concrete surface is determined (step S8). If necessary, measures and measures are taken in accordance with the leveling work available time (step S9).

このように、本発明によれば、導電率が降下開始する前に、ブリーディング水の発生終了時間を予測し、導電率が降下を始めた時点で均し施工可能時間が分かるため、コンクリート表面の均し作業を始める前に、均し施工可能時間を把握することができる。このため、均し施工可能時間の長さに合わせた対応、対策が可能である。したがって、的確な均し作業が可能となり、良好な施工品質のコンクリートを得ることができるという効果を奏する。   As described above, according to the present invention, the occurrence time of bleeding water is predicted before the electric conductivity starts to decrease, and when the electric conductivity starts to decrease, the leveling work possible time is known. Before starting the leveling work, it is possible to grasp the leveling time available for leveling. For this reason, it is possible to take measures and countermeasures according to the length of time during which leveling can be performed. Therefore, it is possible to perform an appropriate leveling operation and to obtain an effect that a concrete having a good construction quality can be obtained.

[本発明の具体的手順]
次に、本発明の具体的手順について図2〜図8を参照しながら説明する。
[Specific Procedures of the Present Invention]
Next, specific procedures of the present invention will be described with reference to FIGS.

まず、図2に示すように、打設直後のコンクリートから時間の経過とともに発生するブリーディング水の発生量を測定する。これと同時に、コンクリートに設置した導電率計より導電率を測定する。導電率計は、メーカーによって形状が異なるが、コンクリート表面に突き刺して安定して設置できるものであればよい。導電率計のセンサー部分は、コンクリート表面に近く、かつコンクリートに安定して設置ができる深さであればよく、コンクリート表面からの深さが例えば10mm〜50mmであれば導電率の傾向に違いはない。   First, as shown in FIG. 2, the amount of bleeding water generated from the concrete immediately after pouring is measured with time. At the same time, the conductivity is measured by a conductivity meter installed on the concrete. The conductivity meter has a different shape depending on the manufacturer, but any conductivity meter can be used as long as it can be stabbed into the concrete surface and stably installed. The sensor part of the conductivity meter may be a depth that is close to the concrete surface and can be stably installed on the concrete, and if the depth from the concrete surface is, for example, 10 mm to 50 mm, the difference in conductivity tends to be different. Absent.

ここで、ブリーディング水の発生量の測定値に基づいて、ブリーディング水の発生速度の単位時間当たりの時間変化量を求める。そして、所定の期間における時間変化量のデータを用いて回帰分析を行い、図3に示すように、時間変化量の回帰直線(一次方程式)を求める。図3においては、時間変化量をY、経過時間をXとした場合の一次近似方程式が、Y=−0.000078X+0.005694で表される例を示している。   Here, the amount of time change per unit time of the generation rate of bleeding water is obtained based on the measured value of the generation amount of bleeding water. Then, regression analysis is performed using the data of the amount of change over time in a predetermined period, and a regression line (primary equation) of the amount of change in time is obtained as shown in FIG. FIG. 3 shows an example in which a linear approximation equation is expressed as Y = −0.000078X + 0.005694, where Y is the amount of time change and X is the elapsed time.

なお、上記の回帰分析の対象期間に用いた所定の期間としては、本実施例では、ブリーディング水の発生量の測定開始時間から、後述する導電率が降下を開始する降下開始時間までの期間としている。この期間については、これ以外の期間を選択してもよく、例えば施工条件等に応じて定めた期間を設定してもよい。   In addition, as a predetermined period used for the target period of the above-described regression analysis, in this embodiment, a period from the measurement start time of the generation amount of bleeding water to a decrease start time at which the conductivity described later starts decreasing. Yes. About this period, you may select a period other than this, for example, you may set the period defined according to construction conditions etc.

次に、この一次近似方程式を時間積分して、図4に示すように、単位時間当たりのブリーディング水の発生速度の近似方程式(二次方程式)を求める。図4においては、ブリーディング水の発生速度をY、経過時間をXとした場合の二次方程式が、Y=−0.000039X+0.00569X+αで表される例を示している。この二次方程式の積分定数αは、実測したデータにより、X=0における値を得ることで決定することができる。本実施例では、α=0.775としている。 Next, this primary approximation equation is integrated over time to obtain an approximation equation (secondary equation) of the generation rate of bleeding water per unit time as shown in FIG. FIG. 4 shows an example in which the quadratic equation where Y is the generation rate of bleeding water and X is the elapsed time is represented by Y = −0.000039X 2 + 0.00569X + α. The integral constant α of this quadratic equation can be determined by obtaining a value at X = 0 from actually measured data. In this embodiment, α = 0.775.

次に、この二次方程式を時間積分して、図5に示すように、ブリーディング水の発生量の近似方程式(三次方程式)を求める。図5においては、ブリーディング水の発生量をY、経過時間をXとした場合の三次方程式がY=−0.000013X+0.00285X+0.775Xで表される例を示している。 Next, this quadratic equation is integrated over time to obtain an approximate equation (tertiary equation) for the amount of bleeding water generated, as shown in FIG. FIG. 5 shows an example in which the cubic equation is expressed as Y = −0.000013X 3 + 0.00285X 2 + 0.775X where Y is the amount of bleeding water generated and X is the elapsed time.

次に、この三次方程式により、ブリーディング水の発生が終了する発生終了時間を予測する。ブリーディング水の発生終了時間は、図5の三次方程式のグラフにおける頂点に対応する時間X1(=250分)と予測できる。なお、この時間は、図4の二次方程式のグラフにおいては、単位時間当たりのブリーディング水の発生速度が0となる時間X1に対応する。また、三次方程式において、時間X1を代入して得られる値(頂点の値:142mL)が、発生するブリーディング水の総量として予測できる。   Next, the generation end time at which the generation of bleeding water ends is predicted by this cubic equation. The generation time of bleeding water can be predicted as the time X1 (= 250 minutes) corresponding to the vertex in the graph of the cubic equation of FIG. This time corresponds to the time X1 when the generation rate of bleeding water per unit time becomes 0 in the graph of the quadratic equation of FIG. In the cubic equation, a value obtained by substituting the time X1 (vertex value: 142 mL) can be predicted as the total amount of bleeding water to be generated.

一方、導電率計の測定により、コンクリートの導電率が上昇から降下に変化する時間を求める。図6に例示するように、導電率が上昇から降下に転じる時間X0(=210分)は、一般的に、ブリーディング水の発生が終了する予測時間X1(=250分)より前となる。   On the other hand, the time required for the electrical conductivity of the concrete to change from rising to falling is determined by measuring with a conductivity meter. As illustrated in FIG. 6, the time X0 (= 210 minutes) when the conductivity changes from rising to lowering is generally before the predicted time X1 (= 250 minutes) when the generation of bleeding water ends.

ここで、コンクリート表面を均すことができる均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係をあらかじめ把握しておく。図7は、施工環境温度が20℃である条件下において、あらかじめ把握した均し施工可能時間と(導電率の降下開始時間/ブリーディング水の発生終了時間)との関係の一例であり、プロットとその回帰直線を示している。この図に示すように、均し施工可能時間と(導電率の降下開始時間/ブリーディング水の発生終了時間)との間には、一定の比例関係が成り立つことが分かる。   Here, the relationship between the leveling time during which the concrete surface can be leveled and the value obtained by dividing the decrease start time of the conductivity by the generation end time of bleeding water is grasped in advance. FIG. 7 is an example of the relationship between the leveling time that can be grasped in advance and the (conductivity drop start time / bleeding water generation end time) under the condition that the construction environment temperature is 20 ° C. The regression line is shown. As shown in this figure, it can be seen that a certain proportional relationship is established between the leveling work possible time and (conductivity drop start time / bleeding water generation end time).

図6で求めた導電率の降下開始時間X0と、図5で求めたブリーディング水の発生終了時間X1より、その比率(X0/X1)を求める。本実施例では、X0/X1=210/250=0.84となる。このX0/X1を図7の回帰直線に当てはめることで、均し施工可能時間が求められる。本実施例の場合には、均し施工可能時間は75分程度と求められる。   The ratio (X0 / X1) is obtained from the conductivity decrease start time X0 obtained in FIG. 6 and the bleeding water generation end time X1 obtained in FIG. In this embodiment, X0 / X1 = 210/250 = 0.84. By applying this X0 / X1 to the regression line of FIG. 7, the leveling work possible time is obtained. In the case of the present embodiment, the leveling work possible time is determined to be about 75 minutes.

このように、本発明によれば、ブリーディング水の発生が終了する時間より前に、均し施工可能時間を把握することができる。均し作業を始める前に均し施工可能時間を把握できるので、均し施工可能時間の長さに合わせた施工への事前対応・対策を採ることが可能である。したがって、的確な均し作業が可能となり、良好な施工品質のコンクリートを得ることができるという効果を奏する。   As described above, according to the present invention, it is possible to grasp the time when the leveling work can be performed before the time when generation of bleeding water ends. Since the leveling work time can be grasped before starting the leveling work, it is possible to take prior measures and measures for the construction according to the length of the leveling time. Therefore, it is possible to perform an appropriate leveling operation and to obtain an effect that a concrete having a good construction quality can be obtained.

例えば、施工面積や施工者数などの施工条件に対して均し施工可能時間が短い場合(例えば、夏の高温時やコンクリートの配合による影響)は、コンクリート表面に遅延剤を散布することで均し施工可能時間を長くすることができ、良好な施工品質を確保することができる。図8の例では、当てはめて得られる均し施工可能時間が短く、施工面積や施工者数などの施工条件により決まる施工可能時間範囲(均し施工可能時間の範囲)より下側にある場合には、コンクリート表面に遅延剤を散布することで均し施工可能時間を長くし、上記の施工可能時間範囲に収まるようにすればよい。   For example, if the workable time is short with respect to the construction conditions such as the construction area and the number of installers (for example, the effect of high temperatures in summer or the mixing of concrete), spraying a retarder on the concrete surface The workable time can be extended, and good construction quality can be ensured. In the example of FIG. 8, when the leveling workable time obtained by fitting is short, and is below the workable time range (range of the leveling workable time) determined by the construction conditions such as the construction area and the number of builders. Is to spread the retarding agent on the concrete surface to lengthen the leveling workable time so that it falls within the above workable time range.

例えば、施工面積や施工者数などの施工条件に対して均し施工可能時間が長い場合(例えば、冬の低温時やコンクリートの配合による影響)は、コンクリート表面に促進剤を散布することで均し施工可能時間を短くすることができ、良好な施工品質を確保することができる。図8の例では、当てはめて得られる均し施工可能時間が長く、施工面積や施工者数などの施工条件により決まる施工可能時間範囲(均し施工可能時間の範囲)より上側にある場合には、コンクリート表面に促進剤を散布することで均し施工可能時間を短くし、上記の施工可能時間範囲に収まるようにすればよい。   For example, if the leveling work time is long with respect to the construction conditions such as construction area and number of installers (for example, due to low temperatures in winter or the effect of concrete mix), spraying an accelerator on the concrete surface The workable time can be shortened, and good construction quality can be ensured. In the example of FIG. 8, when the leveling workable time obtained by fitting is long and is above the workable time range (range of the leveling workable time) determined by the construction conditions such as the construction area and the number of builders, By spreading the accelerator on the concrete surface, the leveling work time can be shortened so that it falls within the above work time range.

[コンクリートの均し施工可能時間の予測装置]
次に、本発明に係るコンクリートの均し施工可能時間の予測装置の実施の形態について図9を参照しながら説明する。
[Prediction device for concrete leveling time]
Next, an embodiment of a predicting apparatus for concrete leveling workable time according to the present invention will be described with reference to FIG.

図9に示すように、本発明に係るコンクリートの均し施工可能時間の予測装置10は、コンクリートの表面を均すことができる均し施工可能時間を予測する装置であって、ブリーディング水の発生量測定手段12と、導電率測定手段14と、ブリーディング水発生終了時間予測手段16と、均し施工可能時間予測手段18と、均し施工可能時間の範囲予測手段20とを備える。   As shown in FIG. 9, the concrete leveling workable time predicting device 10 according to the present invention is a device for predicting the leveling time that can level the concrete surface, and generates bleeding water. A quantity measuring means 12, a conductivity measuring means 14, a bleeding water generation end time predicting means 16, a leveling work possible time predicting means 18, and a leveling work possible time range predicting means 20 are provided.

ブリーディング水の発生量測定手段12は、打設直後のコンクリートから発生するブリーディング水の発生量を測定するものであり、例えばJIS A 1123:2012「コンクリートのブリーディング試験方法」などに記載された方法により測定することができ、例えばブリーディングによってコンクリート表面に浸み出した水を吸い取るピペットまたはスポイトと、吸い取った水の量を測定するメスシリンダーなどにより構成することができる。   Bleeding water generation amount measuring means 12 measures the generation amount of bleeding water generated from concrete immediately after pouring, for example, by a method described in JIS A 1123: 2012 “Concrete Bleeding Test Method”. For example, it can be constituted by a pipette or a syringe that sucks out water that has oozed out on the concrete surface by bleeding and a graduated cylinder that measures the amount of sucked water.

導電率測定手段14は、コンクリートの導電率を測定するものであり、例えば上記の導電率計で構成することができる。   The electrical conductivity measuring means 14 measures the electrical conductivity of concrete, and can be constituted by the above electrical conductivity meter, for example.

ブリーディング水発生終了時間予測手段16は、導電率が降下を開始する降下開始時間の前に、ブリーディング水の発生量に基づいて、ブリーディング水の発生が終了する発生終了時間を予測するものである。ここで、ブリーディング水発生終了時間予測手段16は、上述したように、ブリーディング水の発生量に基づいて、ブリーディング水の発生速度の単位時間当たりの変化量を一次方程式で近似し、一次方程式を1回または2回積分して得られる二次方程式または三次方程式の極値や切片の値等の特性値を求めることで、ブリーディング水の発生終了時間を予測してもよい。このようにすることで、ブリーディング水の発生終了時間を簡便な統計的な手法によって精度よく予測することができる。   The bleeding water generation end time predicting means 16 predicts the generation end time at which the generation of bleeding water ends based on the generation amount of bleeding water before the descent start time at which the conductivity starts to decrease. Here, as described above, the bleeding water generation end time predicting means 16 approximates the amount of change per unit time of the generation speed of the bleeding water by a linear equation based on the generation amount of the bleeding water. The generation end time of bleeding water may be predicted by obtaining characteristic values such as extreme values and intercept values of a quadratic equation or a cubic equation obtained by integrating twice or twice. By doing in this way, generation | occurrence | production completion time of bleeding water can be accurately estimated with a simple statistical method.

このブリーディング水発生終了時間予測手段16としては、ブリーディング水の発生量の測定値を表す情報、導電率の測定値を表す情報があらかじめ格納されたデータベースまたはメモリと、このデータベースまたはメモリに格納された上記情報を読み出して、所定の演算処理を行う演算処理部を有するコンピュータとにより構成することができる。   The bleeding water generation end time predicting means 16 includes a database or memory in which information representing the measured value of the amount of bleeding water generated and information representing the measured value of conductivity are stored in advance, and this database or memory. The information can be read out and configured by a computer having an arithmetic processing unit that performs predetermined arithmetic processing.

均し施工可能時間予測手段18は、予測したブリーディング水の発生終了時間および測定した導電率の降下開始時間を、あらかじめ把握してある均し施工可能時間と導電率の降下開始時間とブリーディング水の発生終了時間との関係に当てはめることで、均し施工可能時間を求めるものである。ここで、上記の関係は、上述したように、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係を用いてもよい。この関係は、一般に比例関係にあると考えられるため、この関係に当てはめることで、均し施工可能時間を簡便に求めることができる。   The leveling workable time predicting means 18 is configured to grasp the predicted bleeding generation end time and the measured conductivity lowering start time in advance, the leveling workable time, the conductivity lowering start time, and the bleeding water. By applying to the relationship with the occurrence end time, the leveling work possible time is obtained. Here, as described above, the above relationship may be a relationship between the leveling work possible time and the value obtained by dividing the decrease start time of conductivity by the generation end time of bleeding water. Since this relationship is generally considered to be proportional, it is possible to easily obtain the leveling workable time by applying this relationship.

この均し施工可能時間予測手段18としては、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係を表す情報、および、予測したブリーディング水の発生終了時間および測定した導電率の降下開始時間を表す情報があらかじめ格納されたデータベースまたはメモリと、このデータベースまたはメモリに格納された上記情報を読み出して、所定の演算処理を行う演算処理部を有するコンピュータとにより構成することができる。   The leveling construction possible time prediction means 18 includes information representing the relationship between the leveling construction possible time and the value obtained by dividing the decrease start time of conductivity by the generation end time of bleeding water, and the predicted bleeding water. A database or memory in which information representing the generation end time and the measured conductivity start time is stored in advance, and an arithmetic processing unit that reads out the information stored in the database or memory and performs predetermined arithmetic processing And a computer.

均し施工可能時間の範囲予測手段20は、求めた均し施工可能時間が、所定の施工条件で決まる均し施工可能時間の範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を上回り、コンクリートの硬化を促進するための促進剤をコンクリートの表面に散布するべき範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を下回り、コンクリートの硬化を遅延するための遅延剤をコンクリートの表面に散布するべき範囲にあるかを予測するものである。このようにすれば、予測した均し施工可能時間の範囲に基づいて、その後の施工上の対応をより適正に行うことができる。   The average construction possible time range predicting means 20 determines whether the obtained leveling construction possible time is within the range of the leveling construction possible time determined by the predetermined construction conditions or the leveling construction possible time determined by the predetermined construction conditions. To delay the hardening of concrete by exceeding the range and within the range where the accelerator for promoting the hardening of the concrete is to be sprayed on the concrete surface, or below the range of the average workable time determined by the predetermined construction conditions It is predicted that the retarder is within the range to be sprayed on the concrete surface. If it does in this way, based on the range of the estimated leveling construction possible time, the correspondence on subsequent construction can be performed more appropriately.

この均し施工可能時間の範囲予測手段20としては、施工条件を表す情報、施工条件と均し施工可能時間との関係を表す情報、均し施工可能時間予測手段18で求めた均し施工可能時間を表す情報があらかじめ格納されたデータベースまたはメモリと、このデータベースまたはメモリに格納された上記情報を読み出して、所定の演算処理を行う演算処理部を有するコンピュータとにより構成することができる。   As the range predicting means 20 of the leveling workable time, information indicating construction conditions, information indicating the relationship between the work conditions and the leveling time available for leveling, leveling work possible by the leveling workable time predicting means 18 is possible. A database or memory in which information representing time is stored in advance, and a computer having an arithmetic processing unit that reads out the information stored in the database or memory and performs predetermined arithmetic processing.

上記の構成によれば、導電率が降下開始する前に、ブリーディング水の発生終了時間を予測し、導電率が降下を始めた時点で均し施工可能時間が分かるため、コンクリート表面の均し作業を始める前に、均し施工可能時間を把握することができる。このため、均し施工可能時間の長さに合わせた対応、対策が可能である。したがって、的確な均し作業が可能となり、良好な施工品質のコンクリートを得ることができるという効果を奏する。   According to the above configuration, since the occurrence time of bleeding water is predicted before the electric conductivity starts to decrease, and the time when the electric conductivity starts to decrease can be understood, the leveling work can be performed. Before starting, you can grasp the leveling time. For this reason, it is possible to take measures and countermeasures according to the length of time during which leveling can be performed. Therefore, it is possible to perform an appropriate leveling operation and to obtain an effect that a concrete having a good construction quality can be obtained.

以上説明したように、本発明に係るコンクリートの均し施工可能時間の予測方法によれば、コンクリートの表面を均すことができる均し施工可能時間を予測する方法であって、打設直後の前記コンクリートから発生するブリーディング水の発生量と、前記コンクリートの導電率とを測定し、前記導電率が降下を開始する降下開始時間の前に、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生が終了する発生終了時間を予測し、予測した前記ブリーディング水の発生終了時間および測定した前記導電率の降下開始時間を、あらかじめ把握してある均し施工可能時間と導電率の降下開始時間とブリーディング水の発生終了時間との関係に当てはめることで、均し施工可能時間を求めるので、導電率が降下を開始する降下開始時間の前、つまりコンクリート表面の均し作業を始める前に、均し施工可能時間を把握することができる。   As described above, according to the method for predicting the leveling time of concrete according to the present invention, it is a method for predicting the leveling time capable of leveling the concrete surface, The amount of bleeding water generated from the concrete and the conductivity of the concrete are measured, and the bleeding water is determined based on the amount of bleeding water before the descent start time when the conductivity starts to decrease. The occurrence end time is predicted, and the predicted bleeding generation end time and the measured decrease start time of the conductivity are grasped in advance and the average workable time and the decrease start time of the conductivity are known. Is applied to the relationship between the occurrence time of bleeding water and the end time of bleeding water. Before the time, that is, before you begin the leveling work of the concrete surface, it is possible to grasp the leveling construction possible time.

また、本発明に係る他のコンクリートの均し施工可能時間の予測方法によれば、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生速度の単位時間当たりの変化量を一次方程式で近似し、前記一次方程式を1回または2回積分して得られる二次方程式または三次方程式の特性値を求めることで、前記ブリーディング水の発生終了時間を予測するので、ブリーディング水の発生終了時間を簡便な統計的な手法によって精度よく予測することができる。   Further, according to the method for predicting the leveling time of other concrete according to the present invention, based on the generation amount of the bleeding water, the amount of change per unit time of the generation speed of the bleeding water is approximated by a linear equation. The generation end time of the bleeding water is predicted by obtaining the characteristic value of the quadratic equation or the cubic equation obtained by integrating the linear equation once or twice, so that the generation end time of the bleeding water can be simplified. It is possible to accurately predict by a simple statistical method.

また、本発明に係る他のコンクリートの均し施工可能時間の予測方法によれば、前記関係は、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係であるので、一般に比例関係にあると考えられるこの関係に当てはめることで、均し施工可能時間を簡便に求めることができる。   Further, according to the method of predicting the leveling workable time of other concrete according to the present invention, the relationship is a value obtained by dividing the leveling time and the decrease start time of conductivity by the generation end time of bleeding water. Therefore, by applying this relationship, which is generally considered to be in a proportional relationship, the leveling workable time can be easily obtained.

また、本発明に係る他のコンクリートの均し施工可能時間の予測方法によれば、求めた均し施工可能時間が、所定の施工条件で決まる均し施工可能時間の範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を上回り、前記コンクリートの硬化を促進するための促進剤を前記コンクリートの表面に散布するべき範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を下回り、前記コンクリートの硬化を遅延するための遅延剤を前記コンクリートの表面に散布するべき範囲にあるかを予測するので、予測した均し施工可能時間の範囲に基づいて、その後の施工上の対応をより適正に行うことができる。例えば、予測された範囲が、遅延剤を散布するべき範囲の場合には、コンクリート表面に遅延剤を散布する対応を行うことで、その後の均し施工可能時間を長くすることができる。また、予測された範囲が、促進剤を散布するべき範囲の場合には、コンクリート表面に促進剤を散布する対応を行うことで、その後の均し施工可能時間を短くすることができる。   Further, according to the method for predicting the leveling workable time of other concrete according to the present invention, the obtained leveling workable time is within the range of the leveling workable time determined by the predetermined construction conditions, The leveling time that exceeds the range of the leveling time that is determined by the work conditions and that is within the range in which the accelerator for accelerating the hardening of the concrete is to be sprayed on the surface of the concrete, or that is determined by the predetermined leveling conditions. Therefore, it is predicted that the retarder for delaying the hardening of the concrete is within the range to be sprayed on the surface of the concrete. The above response can be performed more appropriately. For example, when the predicted range is a range in which the retarder is to be sprayed, it is possible to lengthen the subsequent leveling time by performing a countermeasure to spray the retarder on the concrete surface. In addition, when the predicted range is a range in which the accelerator is to be sprayed, it is possible to shorten the subsequent leveling time by performing a countermeasure to spray the accelerator on the concrete surface.

また、本発明に係るコンクリートの均し施工可能時間の予測装置によれば、コンクリートの表面を均すことができる均し施工可能時間を予測する装置であって、打設直後の前記コンクリートから発生するブリーディング水の発生量を測定するブリーディング水の発生量測定手段と、前記コンクリートの導電率を測定する導電率測定手段と、前記導電率が降下を開始する降下開始時間の前に、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生が終了する発生終了時間を予測するブリーディング水発生終了時間予測手段と、予測した前記ブリーディング水の発生終了時間および測定した前記導電率の降下開始時間を、あらかじめ把握してある均し施工可能時間と導電率の降下開始時間とブリーディング水の発生終了時間との関係に当てはめることで、均し施工可能時間を求める均し施工可能時間予測手段とを備えるので、導電率が降下を開始する降下開始時間の前、つまりコンクリート表面の均し作業を始める前に、均し施工可能時間を把握することができる。   Further, according to the predicting device of the concrete leveling workable time according to the present invention, it is a device for predicting the leveling workable time that can level the surface of the concrete, and is generated from the concrete immediately after placing. Generating amount measuring means for measuring the amount of bleeding water to be measured, conductivity measuring means for measuring the conductivity of the concrete, and before the descent start time at which the conductivity starts decreasing, the bleeding water A bleeding water generation end time predicting means for predicting the generation end time at which the generation of bleeding water ends based on the generation amount of the bleeding water, and the predicted generation end time of the bleeding water and the measured decrease start time of the conductivity. The leveling work time, conductivity lowering start time, and bleeding water generation end time By applying to the relationship, it is equipped with a leveling workable time predicting means for obtaining the leveling workable time, so before the descent start time when the conductivity starts to drop, that is, before starting the leveling work of the concrete surface, It is possible to grasp the leveling work possible time.

また、本発明に係る他のコンクリートの均し施工可能時間の予測装置によれば、ブリーディング水発生終了時間予測手段は、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生速度の単位時間当たりの変化量を一次方程式で近似し、前記一次方程式を1回または2回積分して得られる二次方程式または三次方程式の特性値を求めることで、前記ブリーディング水の発生終了時間を予測するので、ブリーディング水の発生終了時間を簡便な統計的な手法によって精度よく予測することができる。   Further, according to the predicting apparatus for the other concrete leveling time according to the present invention, the bleeding water generation end time predicting means is based on the amount of bleeding water generated, and the unit time of the generation speed of the bleeding water. Since the amount of change per hit is approximated by a linear equation and the characteristic value of a quadratic or cubic equation obtained by integrating the linear equation once or twice is obtained, the generation end time of the bleeding water is predicted. The generation end time of bleeding water can be accurately predicted by a simple statistical method.

また、本発明に係る他のコンクリートの均し施工可能時間の予測装置によれば、均し施工可能時間予測手段における前記関係は、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係であるので、一般に比例関係にあると考えられるこの関係に当てはめることで、均し施工可能時間を簡便に求めることができる。   Further, according to the predicting apparatus for the leveling workable time of other concrete according to the present invention, the relationship in the leveling workable time predicting means is that the leveling workable time and the decrease start time of the conductivity are set as a bleeding water. Therefore, by applying this relationship, which is generally considered to be proportional, it is possible to easily obtain the leveling workable time.

また、本発明に係る他のコンクリートの均し施工可能時間の予測装置によれば、求めた均し施工可能時間が、所定の施工条件で決まる均し施工可能時間の範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を上回り、前記コンクリートの硬化を促進するための促進剤を前記コンクリートの表面に散布するべき範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を下回り、前記コンクリートの硬化を遅延するための遅延剤を前記コンクリートの表面に散布するべき範囲にあるかを予測する均し施工可能時間の範囲予測手段をさらに備えるので、予測した均し施工可能時間の範囲に基づいて、その後の施工上の対応をより適正に行うことができる。例えば、予測された範囲が、遅延剤を散布するべき範囲の場合には、コンクリート表面に遅延剤を散布する対応を行うことで、その後の均し施工可能時間を長くすることができる。また、予測された範囲が、促進剤を散布するべき範囲の場合には、コンクリート表面に促進剤を散布する対応を行うことで、その後の均し施工可能時間を短くすることができる。   Further, according to the predicting device for the leveling workable time of other concrete according to the present invention, whether the determined leveling workable time is within the range of the leveling workable time determined by the predetermined construction conditions, The leveling time that exceeds the range of the leveling time that is determined by the work conditions and that is within the range in which the accelerator for accelerating the hardening of the concrete is to be sprayed on the surface of the concrete, or that is determined by the predetermined leveling conditions. Is further provided with means for predicting the range of possible workable time for predicting whether the retarder for retarding the hardening of the concrete is within the range to be sprayed on the surface of the concrete. Based on the range of possible construction time, it is possible to more appropriately deal with the subsequent construction. For example, when the predicted range is a range in which the retarder is to be sprayed, it is possible to lengthen the subsequent leveling time by performing a countermeasure to spray the retarder on the concrete surface. In addition, when the predicted range is a range in which the accelerator is to be sprayed, it is possible to shorten the subsequent leveling time by performing a countermeasure to spray the accelerator on the concrete surface.

以上のように、本発明に係るコンクリートの均し施工可能時間の予測方法および予測装置は、例えばコンクリート製の床スラブなどの表面の均し作業を伴うコンクリートに有用であり、特に、均し施工可能時間を予測するのに適している。   As described above, the method and apparatus for predicting the leveling time of concrete according to the present invention are useful for concrete involving surface leveling work such as a concrete floor slab, and in particular, leveling work. Suitable for predicting possible time.

10 コンクリートの均し施工可能時間の予測装置
12 ブリーディング水の発生量測定手段
14 導電率測定手段
16 ブリーディング水発生終了時間予測手段
18 均し施工可能時間予測手段
20 均し施工可能時間の範囲予測手段
DESCRIPTION OF SYMBOLS 10 Prediction device of concrete equalizing construction possible time 12 Generation | occurrence | production measuring means of bleeding water 14 Conductivity measuring means 16 Bleeding water generation | occurrence | production completion time prediction means 18 Leveling construction possible time prediction means 20 Range prediction means of leveling construction possible time

Claims (8)

コンクリートの表面を均すことができる均し施工可能時間を予測する方法であって、
打設直後の前記コンクリートから発生するブリーディング水の発生量と、前記コンクリートの導電率とを測定し、
前記導電率が降下を開始する降下開始時間の前に、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生が終了する発生終了時間を予測し、
予測した前記ブリーディング水の発生終了時間および測定した前記導電率の降下開始時間を、あらかじめ把握してある均し施工可能時間と導電率の降下開始時間とブリーディング水の発生終了時間との関係に当てはめることで、均し施工可能時間を求めることを特徴とするコンクリートの均し施工可能時間の予測方法。
A method of predicting the leveling time that can level the surface of concrete,
Measure the amount of bleeding water generated from the concrete immediately after placing and the electrical conductivity of the concrete,
Before the descent start time when the conductivity starts to drop, based on the amount of generation of the bleeding water, predict the occurrence end time at which the generation of the bleeding water ends,
The predicted generation time of the bleeding water and the measured decrease start time of the conductivity are applied to the relationship between the known leveling time, the decrease start time of the conductivity, and the generation end time of the bleeding water. Therefore, the method for predicting the leveling time of concrete, characterized by obtaining the leveling time.
前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生速度の単位時間当たりの変化量を一次方程式で近似し、前記一次方程式を1回または2回積分して得られる二次方程式または三次方程式の特性値を求めることで、前記ブリーディング水の発生終了時間を予測することを特徴とする請求項1に記載のコンクリートの均し施工可能時間の予測方法。   Based on the amount of bleeding water generated, the amount of change in the generation speed of the bleeding water per unit time is approximated by a linear equation, and the linear equation or the cubic equation obtained by integrating the linear equation once or twice. The method for predicting the leveling time of concrete leveling according to claim 1, wherein the generation end time of the bleeding water is predicted by obtaining the characteristic value of the concrete. 前記関係は、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係であることを特徴とする請求項1または2に記載のコンクリートの均し施工可能時間の予測方法。   3. The concrete leveling according to claim 1, wherein the relationship is a relationship between a leveling time that can be leveled and a value obtained by dividing a time when conductivity starts decreasing by a generation time of bleeding water. Prediction method of possible construction time. 求めた均し施工可能時間が、所定の施工条件で決まる均し施工可能時間の範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を上回り、前記コンクリートの硬化を促進するための促進剤を前記コンクリートの表面に散布するべき範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を下回り、前記コンクリートの硬化を遅延するための遅延剤を前記コンクリートの表面に散布するべき範囲にあるかを予測することを特徴とする請求項1〜3のいずれか一つに記載のコンクリートの均し施工可能時間の予測方法。   In order to promote the hardening of the concrete, the calculated leveling workable time is within the range of the leveling workable time determined by the predetermined construction conditions or exceeds the range of the leveling workable time determined by the predetermined construction conditions Is not within the range to be sprayed on the surface of the concrete, or is below the range of the leveling time that can be determined by predetermined construction conditions, and a retarder for delaying the hardening of the concrete is applied to the surface of the concrete. It is estimated whether it exists in the range which should be spread | dispersed, The prediction method of the leveling construction possible time of the concrete as described in any one of Claims 1-3 characterized by the above-mentioned. コンクリートの表面を均すことができる均し施工可能時間を予測する装置であって、
打設直後の前記コンクリートから発生するブリーディング水の発生量を測定するブリーディング水の発生量測定手段と、
前記コンクリートの導電率を測定する導電率測定手段と、
前記導電率が降下を開始する降下開始時間の前に、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生が終了する発生終了時間を予測するブリーディング水発生終了時間予測手段と、
予測した前記ブリーディング水の発生終了時間および測定した前記導電率の降下開始時間を、あらかじめ把握してある均し施工可能時間と導電率の降下開始時間とブリーディング水の発生終了時間との関係に当てはめることで、均し施工可能時間を求める均し施工可能時間予測手段とを備えることを特徴とするコンクリートの均し施工可能時間の予測装置。
A device that predicts the leveling time that can level the surface of concrete,
Means for measuring the amount of bleeding water generated to measure the amount of bleeding water generated from the concrete immediately after placing;
A conductivity measuring means for measuring the conductivity of the concrete;
Bleeding water generation end time predicting means for predicting the generation end time at which the generation of bleeding water ends based on the generation amount of the bleeding water before the descent start time at which the conductivity starts to decrease;
The predicted generation time of the bleeding water and the measured decrease start time of the conductivity are applied to the relationship between the known leveling time, the decrease start time of the conductivity, and the generation end time of the bleeding water. A concrete leveling workable time predicting device comprising: a leveling workable time predicting means for obtaining a leveling workable time.
ブリーディング水発生終了時間予測手段は、前記ブリーディング水の発生量に基づいて、前記ブリーディング水の発生速度の単位時間当たりの変化量を一次方程式で近似し、前記一次方程式を1回または2回積分して得られる二次方程式または三次方程式の特性値を求めることで、前記ブリーディング水の発生終了時間を予測することを特徴とする請求項5に記載のコンクリートの均し施工可能時間の予測装置。   The bleeding water generation end time predicting means approximates the amount of change per unit time of the generation speed of the bleeding water by a linear equation based on the generation amount of the bleeding water, and integrates the linear equation once or twice. 6. The predicting apparatus for concrete leveling time according to claim 5, wherein the generation time of the bleeding water is predicted by obtaining a characteristic value of a quadratic equation or a cubic equation obtained in this way. 均し施工可能時間予測手段における前記関係は、均し施工可能時間と、導電率の降下開始時間をブリーディング水の発生終了時間で除した値との関係であることを特徴とする請求項5または6に記載のコンクリートの均し施工可能時間の予測装置。   The relationship in the leveling construction possible time prediction means is a relationship between the leveling construction possible time and a value obtained by dividing the decrease start time of conductivity by the generation end time of bleeding water. 6. The predicting device of the concrete leveling time possible for concrete according to 6. 求めた均し施工可能時間が、所定の施工条件で決まる均し施工可能時間の範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を上回り、前記コンクリートの硬化を促進するための促進剤を前記コンクリートの表面に散布するべき範囲にあるか、所定の施工条件で決まる均し施工可能時間の範囲を下回り、前記コンクリートの硬化を遅延するための遅延剤を前記コンクリートの表面に散布するべき範囲にあるかを予測する均し施工可能時間の範囲予測手段をさらに備えることを特徴とする請求項5〜7のいずれか一つに記載のコンクリートの均し施工可能時間の予測装置。   In order to promote the hardening of the concrete, the calculated leveling workable time is within the range of the leveling workable time determined by the predetermined construction conditions or exceeds the range of the leveling workable time determined by the predetermined construction conditions Is not within the range to be sprayed on the surface of the concrete, or is below the range of the leveling time that can be determined by predetermined construction conditions, and a retarder for delaying the hardening of the concrete is applied to the surface of the concrete. The apparatus for predicting the leveling time for leveling of concrete according to any one of claims 5 to 7, further comprising means for predicting the range of leveling time for leveling construction that predicts whether the range is to be spread. .
JP2014082283A 2014-04-11 2014-04-11 Prediction method and prediction device for concrete leveling time Active JP6252856B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2014082283A JP6252856B2 (en) 2014-04-11 2014-04-11 Prediction method and prediction device for concrete leveling time

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2014082283A JP6252856B2 (en) 2014-04-11 2014-04-11 Prediction method and prediction device for concrete leveling time

Publications (2)

Publication Number Publication Date
JP2015203204A true JP2015203204A (en) 2015-11-16
JP6252856B2 JP6252856B2 (en) 2017-12-27

Family

ID=54596830

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2014082283A Active JP6252856B2 (en) 2014-04-11 2014-04-11 Prediction method and prediction device for concrete leveling time

Country Status (1)

Country Link
JP (1) JP6252856B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017179821A (en) * 2016-03-30 2017-10-05 前田建設工業株式会社 Automatic finishing device of concrete surface
JP2019073962A (en) * 2017-10-16 2019-05-16 清水建設株式会社 Method and device for predicting leveling work enabling period of concrete and method for constructing concrete
JP2019073898A (en) * 2017-10-16 2019-05-16 清水建設株式会社 Method and device for predicting leveling work enabling period of concrete and method for constructing concrete
JP2019098707A (en) * 2017-12-07 2019-06-24 清水建設株式会社 Method for controlling curing time of concrete, control device and method for constructing concrete
JP2020176483A (en) * 2019-04-22 2020-10-29 清水建設株式会社 Concrete construction management method and construction management system
JP2022024180A (en) * 2020-03-27 2022-02-08 株式会社フロアエージェント Method of constructing concrete floor surface

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05340938A (en) * 1992-06-09 1993-12-24 Mitsui Constr Co Ltd Method and device for judging leveling timing of concrete
JPH07229297A (en) * 1994-02-17 1995-08-29 Kajima Corp Detecting method of surface water of concrete in form
JPH08332626A (en) * 1995-06-07 1996-12-17 Nikko Co Ltd Ready mixed concrete manufacturing device

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05340938A (en) * 1992-06-09 1993-12-24 Mitsui Constr Co Ltd Method and device for judging leveling timing of concrete
JPH07229297A (en) * 1994-02-17 1995-08-29 Kajima Corp Detecting method of surface water of concrete in form
JPH08332626A (en) * 1995-06-07 1996-12-17 Nikko Co Ltd Ready mixed concrete manufacturing device

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017179821A (en) * 2016-03-30 2017-10-05 前田建設工業株式会社 Automatic finishing device of concrete surface
JP2019073962A (en) * 2017-10-16 2019-05-16 清水建設株式会社 Method and device for predicting leveling work enabling period of concrete and method for constructing concrete
JP2019073898A (en) * 2017-10-16 2019-05-16 清水建設株式会社 Method and device for predicting leveling work enabling period of concrete and method for constructing concrete
JP7000107B2 (en) 2017-10-16 2022-01-19 清水建設株式会社 Prediction method of concrete leveling workable time, prediction device and concrete construction method
JP2019098707A (en) * 2017-12-07 2019-06-24 清水建設株式会社 Method for controlling curing time of concrete, control device and method for constructing concrete
JP7042602B2 (en) 2017-12-07 2022-03-28 清水建設株式会社 How to control the hardening time of concrete, control device and concrete construction method
JP2020176483A (en) * 2019-04-22 2020-10-29 清水建設株式会社 Concrete construction management method and construction management system
JP2022024180A (en) * 2020-03-27 2022-02-08 株式会社フロアエージェント Method of constructing concrete floor surface
JP7072955B2 (en) 2020-03-27 2022-05-23 株式会社フロアエージェント Construction method of concrete floor
WO2022210682A1 (en) * 2020-03-27 2022-10-06 株式会社フロアエージェント Method for constructing concrete floor

Also Published As

Publication number Publication date
JP6252856B2 (en) 2017-12-27

Similar Documents

Publication Publication Date Title
JP6252856B2 (en) Prediction method and prediction device for concrete leveling time
Attari et al. A combined SEM–Calorimetric approach for assessing hydration and porosity development in GGBS concrete
JP2016183526A (en) Adjustment method of possible time for concrete leveling work
JP2012026734A (en) Lined concrete demolding time determination method and demolding time determination system
Zach et al. Technology of concrete with low generation of hydration heat
JP2009002721A (en) Method for determining time of demolding concrete
JP6936718B2 (en) Prediction method of concrete leveling work time, prediction device and concrete construction method
JP5246113B2 (en) Early estimation method of concrete drying shrinkage strain
JP7042602B2 (en) How to control the hardening time of concrete, control device and concrete construction method
Caballero et al. Chloride penetration into cementitious mortar at early age
JP2013195186A (en) Method and apparatus for evaluating water content of cement-based material during hardening process
Goh et al. Determination of flow number in asphalt mixtures from deformation rate during secondary state
Ahmed et al. A new approach in fatigue testing and evaluation of hot mix asphalt using a dynamic shear rheometer
JP6497707B2 (en) Strength estimation system for concrete demolding
JP6548953B2 (en) Concrete workability judgment method
Liu et al. Quantification of the actual expansion and deposition of rust in reinforced concrete
JP5713640B2 (en) Method for determining the amount of shrinkage reducing agent
JP5391457B2 (en) Concrete stacking management method
JP2022080719A (en) Prediction method of construction timing, prediction device and concrete construction method
JP7000107B2 (en) Prediction method of concrete leveling workable time, prediction device and concrete construction method
JPH11271301A (en) Estimation method for compressive strength of on-the-spot placed concrete and shield driving method
JP4374519B2 (en) Strength evaluation method for structural concrete
JPH05340938A (en) Method and device for judging leveling timing of concrete
JP7257797B2 (en) Concrete setting time determination device, determination method and concrete construction method
JP2023144835A (en) Method for estimating strength development of hydraulic composition and program of estimation processing of strength development of hydraulic composition

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20161207

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170911

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20171017

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20171115

R150 Certificate of patent or registration of utility model

Ref document number: 6252856

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150