JP2018178658A - Method for constructing structure - Google Patents

Method for constructing structure Download PDF

Info

Publication number
JP2018178658A
JP2018178658A JP2017084038A JP2017084038A JP2018178658A JP 2018178658 A JP2018178658 A JP 2018178658A JP 2017084038 A JP2017084038 A JP 2017084038A JP 2017084038 A JP2017084038 A JP 2017084038A JP 2018178658 A JP2018178658 A JP 2018178658A
Authority
JP
Japan
Prior art keywords
construction
post
pile
pillar
frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2017084038A
Other languages
Japanese (ja)
Other versions
JP7003376B2 (en
Inventor
鈴木 庸介
Yasusuke Suzuki
庸介 鈴木
秀幸 成田
Hideyuki Narita
秀幸 成田
杉内 章浩
Akihiro Sugiuchi
章浩 杉内
夏輝 飯野
Natsuki Iino
夏輝 飯野
純平 瀬戸
Jumpei Seto
純平 瀬戸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2017084038A priority Critical patent/JP7003376B2/en
Publication of JP2018178658A publication Critical patent/JP2018178658A/en
Application granted granted Critical
Publication of JP7003376B2 publication Critical patent/JP7003376B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

PROBLEM TO BE SOLVED: To shorten a construction period of a structure.SOLUTION: A method for constructing a structure includes: a frame construction step of constructing a frame 50 having a pair of preceding columns 52 and a beam 58 supported by the pair of preceding columns 52; and a post-construction column construction step of constructing a post-construction column 54 supporting the beam 58 adjacent to the preceding column 52.SELECTED DRAWING: Figure 4

Description

本発明は、構造物の施工方法に関する。   The present invention relates to a construction method of a structure.

ハーフプレキャストフーチング上に、上部構造体を支持する柱を立てる構造物の施工方法が知られている(例えば、特許文献1参照)。   There is known a construction method of a structure in which a pillar supporting an upper structure is placed on a half precast footing (see, for example, Patent Document 1).

また、トラスで補強された人工地盤の作業穴から、地盤に杭孔を掘削する人工地盤の施工方法を知られている(例えば、特許文献2参照)。   Moreover, the construction method of the artificial ground which excavates a pile hole in the ground is known from the working hole of the artificial ground reinforced with the truss (for example, refer patent document 2).

特開2001−355246号公報JP 2001-355246 A 特開2006−083673号公報Japanese Patent Application Publication No. 2006-083673

特許文献1に開示された施工方法では、ハーフプレキャストフーチング上に打設する現場打ちコンクリートと、柱に支持される上部構造体との同時施工が可能になるため、構造物の工期を短縮することができる。   According to the construction method disclosed in Patent Document 1, simultaneous construction of cast-in-place concrete to be placed on a half precast footing and an upper structure supported by a column becomes possible, thereby shortening the construction period of the structure. Can.

しかしながら、構造物の工期の短縮するためには、さらなる改善の余地がある。   However, there is room for further improvement to shorten the construction period of the structure.

本発明は、上記の事実を考慮し、構造物の工期を短縮することを目的とする。   The present invention aims to shorten the construction period of a structure in consideration of the above facts.

請求項1に記載の構造物の施工方法は、一対の先行柱と、前記一対の先行柱に支持される水平部材と、を有する架構を施工する架構施工工程と、前記先行柱の隣に、前記水平部材を支持する後施工柱を施工する後施工柱施工工程と、を備える。   In the construction method of a structure according to claim 1, a frame construction step of constructing a frame having a pair of leading columns and a horizontal member supported by the pair of leading columns, and next to the leading columns, The post-construction pillar construction process of constructing a post-construction pillar supporting the horizontal member.

請求項1に係る構造物の施工方法によれば、架構施工工程において、一対の先行柱と、一対の先行柱に支持される水平部材とを有する架構を施工する。次に、後施工柱施工工程において、先行柱の隣に、水平部材を支持する後施工柱を施工する。   According to the construction method of a structure in accordance with the first aspect, in the construction processing step, a construction having a pair of leading columns and a horizontal member supported by the pair of leading columns is constructed. Next, in the post-construction pillar construction process, a post-construction pillar supporting the horizontal member is constructed next to the leading pillar.

このように本発明では、後施工柱を間引いた架構を先行して施工することにより、例えば、架構の上に施工される上部構造体と、後施工柱とを並行して施工することができる。したがって、構造物の工期を短縮することができる。   As described above, in the present invention, for example, the upper structure to be constructed on the frame and the post-construction column can be constructed in parallel by constructing the frame in which the post-construction column is thinned in advance. . Therefore, the construction period of the structure can be shortened.

請求項2に記載の構造物の施工方法は、請求項1に記載の構造物の施工方法において、前記架構施工工程の後に、前記後施工柱を支持する後施工杭を施工する後施工杭施工工程を備える。   The construction method for a structure according to claim 2 is the construction method for a structure according to claim 1, wherein a post-construction pile is carried out to construct a post-construction pile for supporting the post-construction column after the frame construction process. It has a process.

請求項2に係る構造物の施工方法によれば、架構施工工程の後の後施工杭施工工程において、後施工柱を支持する後施工杭を施工する。これにより、架構の上に施工される上部構造体と、後施工杭及び後施工柱とを並行して施工することができる。したがって、構造物の工期をさらに短縮することができる。   According to the construction method of a structure according to claim 2, in the post-construction pile construction step after the frame construction step, the post-construction pile supporting the post-construction column is constructed. Thereby, the upper structure to be constructed on the frame, and the post-construction pile and the post-construction column can be constructed in parallel. Therefore, the construction period of the structure can be further shortened.

請求項3に記載の構造物の施工方法は、請求項2に記載の構造物の施工方法において、前記後施工杭施工工程において、前記後施工杭の少なくとも一部を前記水平部材の上から施工する。   In the construction method of a structure according to claim 3, in the construction method of a structure according to claim 2, in the post-construction pile construction step, at least a part of the post-construction pile is constructed from above the horizontal member Do.

請求項3に係る構造物の施工方法によれば、後施工杭施工工程において、後施工杭の少なくとも一部を水平部材の上から施工する。   According to the construction method of a structure according to claim 3, in the post-construction pile construction step, at least a part of the post-construction pile is constructed from above the horizontal member.

ここで、例えば、後施工杭が場所打ち杭の場合、水平部材の上からであれば、架構の階高よりも全長が長い鉄筋ユニットを地盤の杭孔に挿入することができる。そのため、鉄筋ユニットの分割数を減らすことができる。したがって、鉄筋ユニットの連結箇所が少なくなるため、後施工杭の施工性が向上する。   Here, for example, when the post-construction pile is a cast-in-place pile, from above the horizontal member, it is possible to insert a reinforcing bar unit whose total length is longer than the floor height of the frame into the ground hole. Therefore, the number of divisions of the reinforcing bar unit can be reduced. Therefore, since the connection location of a reinforcement unit decreases, the construction property of a post-construction pile improves.

以上説明したように、本発明に係る構造物の施工方法によれば、構造物の工期を短縮することができる。   As explained above, according to the construction method of a structure according to the present invention, the construction period of the structure can be shortened.

本実施形態に係る構造物の施工方法によって施工された構造物を示す立面図である。It is an elevation view which shows the structure constructed by the construction method of the structure concerning this embodiment. (A)及び(B)は、先行杭施工工程を説明する立面図である。(A) and (B) are elevations explaining a prior pile construction process. (A)は架構施工工程を説明する立面図であり、(B)は、上部構造体施工工程を説明する立面図である。(A) is an elevation view explaining a frame construction process, (B) is an elevation view explaining an upper structure construction process. 上部構造体施工工程と、後施工杭施工工程及び後施工柱施工工程とを説明する立面図である。It is an elevation view explaining an upper structure construction process, a post-construction pile construction process, and a post-construction pillar construction process. 後施工杭施工工程を説明する立面図である。It is an elevation view explaining a post-construction pile construction process. 後施工柱施工工程を説明する立面図である。It is an elevation view explaining a post-construction pillar construction process. (A)〜(C)は、スラブの作業開口を示す平面図である。(A)-(C) are top views which show the work opening of a slab. 後施工杭施工工程の変形例を説明する立面図である。It is an elevation view explaining the modification of a post-construction pile construction process. 後施工柱施工工程の変形例を説明する立面図である。It is an elevation view explaining the modification of a post-construction pillar construction process. 後施工杭及び後施工柱の配置の変形例を示す立面図である。It is an elevation view which shows the modification of arrangement | positioning of a post-construction pile and a post-construction pillar. スラブの作業開口の変形例を示す平面図である。It is a top view which shows the modification of the work opening of a slab. 後施工杭及び後施工柱の配置の変形例を示す平面図である。It is a top view which shows the modification of arrangement | positioning of a post-construction pile and a post-construction pillar.

以下、図面を参照しながら、一実施形態に係る構造物の施工方法について説明する。   Hereinafter, the construction method of a structure according to an embodiment will be described with reference to the drawings.

(構造物の構成)
先ず、本実施形態に係る構造物の施工方法(以下、単に「施工方法」という)によって施工される構造物の構成について説明する。
(Structure configuration)
First, the structure of the structure constructed by the construction method of the structure according to the present embodiment (hereinafter simply referred to as "construction method") will be described.

図1には、本実施形態に係る施工方法によって施工される構造物10が示されている。構造物10は、既存施設20の下又は周囲に設けられる基礎40と、基礎40に支持される架構50と、架構50の上に施工される上部構造体60とを備えている。   The structure 10 constructed by the construction method which concerns on this embodiment is shown by FIG. The structure 10 includes a base 40 provided under or around the existing facility 20, a frame 50 supported by the base 40, and an upper structure 60 installed on the frame 50.

(既存施設)
既存施設20は、一例として、鉄道の駅22を含んでいる。駅22は、鉄道車両24が走行する複数の線路26と、鉄道車両24が停車する複数のプラットホーム28とを有している。複数の線路26は、地盤G上に敷設されている。また、複数の線路26は、並走されており、平面視にて構造物10を横切っている。さらに、各線路26の脇には、プラットホーム28が配置されている。
(Existing facility)
The existing facility 20 includes a railway station 22 as an example. The station 22 has a plurality of tracks 26 on which the railcars 24 travel and a plurality of platforms 28 on which the railcars 24 stop. The plurality of tracks 26 are laid on the ground G. Further, the plurality of lines 26 run in parallel, and cross the structure 10 in plan view. Furthermore, a platform 28 is disposed beside each track 26.

複数のプラットホーム28は、線路26に沿って配置されている。これらの線路26及びプラットホーム28の上に、後述する上部構造体60が配置されている。なお、線路26は、一本でも良いし、プラットホーム28も1つでも良い。   A plurality of platforms 28 are disposed along the track 26. An upper structure 60 described later is disposed on the line 26 and the platform 28. The line 26 may be one, and the platform 28 may be one.

(基礎)
基礎40は、杭基礎とされており、複数の先行杭42及び後施工杭44を有している。先行杭42及び後施工杭44は、線路26の脇で、かつ、プラットホーム28の下の地盤Gに設けられている。また、先行杭42及び後施工杭44は、例えば、場所打ち杭とされている。
(Basic)
The foundation 40 is a pile foundation and has a plurality of preceding piles 42 and post-construction piles 44. The leading pile 42 and the post-construction pile 44 are provided on the ground G below the platform 28 at the side of the track 26. The preceding pile 42 and the post-construction pile 44 are, for example, cast-in-place piles.

なお、先行杭42及び後施工杭44の構造や配置、本数は、適宜変更可能である。したがって、先行杭42及び後施工杭44は、例えば、プラットホーム28の下ではなく、プラットホーム28の脇に配置されても良い。   In addition, the structure and arrangement of the leading pile 42 and the post-construction pile 44, and the number thereof can be changed as appropriate. Thus, the leading piles 42 and the post-construction piles 44 may, for example, be disposed beside the platform 28 rather than below the platform 28.

(架構)
架構50は、複数の先行柱52及び後施工柱54と、複数の梁56,58A,58Bとを有し、既存施設20の少なくとも一部を跨ぐように配置されている。先行柱52は、先行杭42の上に立てられている。また、後施工柱54は、後施工杭44の上に立てられている。つまり、構造物10では、一柱一杭構造が採用されている。これらの先行柱52及び後施工柱54は、線路26の上方(上空)に配置された上部構造体60を支持しており、上部構造体60の下に鉄道車両24が走行可能な走行空間(既存施設用空間)30を形成している。
(Structure)
The frame 50 has a plurality of leading columns 52 and post-construction columns 54, and a plurality of beams 56, 58A, 58B, and is arranged to straddle at least a part of the existing facility 20. The leading post 52 is erected on the leading pile 42. Also, the post-construction pillar 54 is erected on the post-construction pile 44. That is, in the structure 10, the one pillar one pile structure is adopted. The leading pillars 52 and the post-construction pillars 54 support the upper structural body 60 disposed above (above) the track 26, and a traveling space in which the railway vehicle 24 can travel under the upper structural body 60 ( Space for existing facilities) 30 is formed.

梁56は、隣り合う一対の先行柱52に架設されており、梁58A,58Bは、隣り合う先行柱52と後施工柱54とにそれぞれ架設されている。これらの先行柱52、後施工柱54、及び梁56,58A,58Bによって、架構50が構成されている。また、梁56,58A,58Bの上には、スラブ62(図5参照)が設けられている。さらに、架構50の上には、上部構造体60が設けられている。   The beam 56 is bridged by a pair of adjacent leading columns 52, and the beams 58A and 58B are bridged respectively by adjacent leading columns 52 and post-construction columns 54. A frame 50 is configured by the leading post 52, the post-construction post 54, and the beams 56, 58A, 58B. Further, a slab 62 (see FIG. 5) is provided on the beams 56, 58A, 58B. Furthermore, an upper structure 60 is provided on the frame 50.

(上部構造体)
上部構造体60は、線路26の上空に設けられる線路上空構造体(既存施設上空構造体)とされている。この上部構造体60は、例えば、複数階(複数層)からなり、複数の柱64と、隣り合う柱64に架設される梁66と、梁66に支持される図示しないスラブとを有している。また、上部構造体60は、例えば、複数のプラットホーム28間の移動経路等を有している。
(Superstructure)
The upper structure 60 is an over-track structure provided above the track 26 (an over-the-air facility existing structure). The upper structural body 60 includes, for example, a plurality of floors (a plurality of layers), and includes a plurality of columns 64, beams 66 bridged by the adjacent columns 64, and a slab (not shown) supported by the beams 66. There is. In addition, the upper structure 60 has, for example, a movement path between the plurality of platforms 28 and the like.

(構造物の施工方法)
次に、本実施形態に係る構造物の施工方法について説明する。
(Construction method of structure)
Next, the construction method of the structure according to the present embodiment will be described.

(先行杭施工工程)
先ず、先行杭施工工程について説明する。図2(A)には、地盤Gに設けられた既存施設20が示されている。この状態から、図2(B)に示されるように、プラットホーム28の下に先行杭42を施工する。この先行杭42の施工では、例えば、図示しない掘削機によって地盤Gに杭孔を掘削するとともに、掘削した杭孔に図示しない鉄筋かごを挿入し、コンクリートを打設する。これにより、鉄筋コンクリート造の先行杭42が施工される。
(Preceding pile construction process)
First, the preceding pile construction process will be described. The existing facility 20 provided in the ground G is shown by FIG. 2 (A). From this state, as shown in FIG. 2 (B), the leading pile 42 is applied under the platform 28. In the construction of the leading pile 42, for example, a pile hole is excavated in the ground G by an unillustrated excavating machine, and a rebar cage (not illustrated) is inserted into the excavated pile hole, and concrete is cast. Thereby, the leading pile 42 of reinforced concrete is constructed.

なお、本実施形態では、先行杭42の準備工事として、図2(A)に示されるように、例えば、線路26及びプラットホーム28の下の地盤Gに、排泥管やコンクリート供給管等の配管32を敷設している。この配管32の大きさや形状、配置、本数は、適宜変更可能である。   In the present embodiment, for example, as shown in FIG. 2A, the ground G below the track 26 and the platform 28 is a pipe such as a sludge pipe or a concrete supply pipe as a preparation work for the leading pile 42. 32 are laid. The size, shape, arrangement, and number of the pipes 32 can be changed as appropriate.

(架構施工工程)
次に、架構施工工程について説明する。架構施工工程では、図3(A)に示されるように、先行杭42の上に、後施工柱54を間引いた架構(先行架構)50を施工する。具体的には、複数の先行杭42の上に先行柱52をそれぞれ立てるとともに、隣り合う先行柱52に、水平部材としての梁56,58をそれぞれ架設する。
(Frame construction process)
Next, the frame construction process will be described. In the frame construction process, as shown in FIG. 3A, a frame (preceding frame) 50 in which the post construction column 54 is thinned is constructed on the leading pile 42. Specifically, the leading pillars 52 are respectively erected on the plurality of leading piles 42, and beams 56, 58 as horizontal members are constructed on the adjacent leading pillars 52, respectively.

なお、水平部材としては、梁56,58に限らず、スラブであっても良いし、梁及びスラブの両方であっても良い。また、架構(先行架構)は、複数の先行柱、すなわち少なくとも2本以上の先行柱と、これらの先行柱に架設される水平部材とで構成することができる。   The horizontal member is not limited to the beams 56 and 58, and may be a slab or both beams and slabs. In addition, the frame (preceding frame) can be configured by a plurality of leading columns, that is, at least two or more leading columns, and a horizontal member installed on the leading columns.

ここで、架構(先行架構)50には、前述したように、後施工柱54が存在していない。そのため、後施工柱54が後施工されるまでの間、梁58の支持スパンLが長くなっている。   Here, as described above, the post-construction pillar 54 does not exist in the frame (preceding frame) 50. Therefore, the support span L of the beam 58 is long until the post-construction pillar 54 is post-construction.

(上部構造体施工工程)
次に、上部構造体施工工程について説明する。上部構造体施工工程では、図3(B)に示されるように、架構50の上に上部構造体60を施工する。具体的には、架構50の梁56,58の上に、例えば、鉄筋コンクリート造のスラブ62(図5参照)を施工する。また、先行柱52の上に柱64をそれぞれ立てるとともに、隣り合う柱64に梁66をそれぞれ架設する。これにより、図4に示されるように、複数階からなる上部構造体60を施工する。
(Superstructure construction process)
Next, the upper structure installation process will be described. In the upper structure installation step, the upper structure 60 is installed on the frame 50, as shown in FIG. 3 (B). Specifically, for example, a reinforced concrete slab 62 (see FIG. 5) is constructed on the beams 56 and 58 of the frame 50. Further, the pillars 64 are respectively erected on the leading pillars 52, and the beams 66 are constructed on the adjacent pillars 64, respectively. Thereby, as shown in FIG. 4, the upper structural body 60 consisting of a plurality of floors is constructed.

ここで、後施工柱54を施工する前の架構50では、前述したように、梁58の支持スパンL(図3(A)参照)が長くなっており、梁58がたわみ易くなっている。この対策として本実施形態では、梁58を補強部材によって補強している。なお、補強部材は、必要に応じて設ければ良く、適宜省略可能である。   Here, in the structure 50 before the post-construction column 54 is constructed, as described above, the support span L (see FIG. 3A) of the beam 58 is long, and the beam 58 is easily bent. As a countermeasure, in the present embodiment, the beam 58 is reinforced by a reinforcing member. In addition, what is necessary is just to provide a reinforcement member as needed, and can be abbreviate | omitted suitably.

補強部材としては、例えば、梁58における後施工柱54との接合部を吊り上げるワイヤー等の吊り材70やブレース等が挙げられる。また、梁58の断面積を大きくしても良いし、架構50の直上階を、梁56,58を下弦材としたトラス構造としても良い。   As a reinforcement member, for example, a suspending material 70 such as a wire for lifting a joint of the beam 58 with the post-construction pillar 54 or a brace may be mentioned. Further, the cross-sectional area of the beam 58 may be increased, or the immediately upper floor of the frame 50 may be a truss structure in which the beams 56 and 58 are lower chord members.

また、吊り材70には、例えば、梁58のレベルを調整するためのレベル調整機構を設けても良い。レベル調整機構としては、吊り材70を緊張させるチェーンブロック72や、ブレースに内蔵され、ブレースの全長を短くするジャッキ等が挙げられる。   In addition, the hanging material 70 may be provided with a level adjustment mechanism for adjusting the level of the beam 58, for example. Examples of the level adjustment mechanism include a chain block 72 for tensioning the hanging member 70, and a jack or the like incorporated in the brace to shorten the overall length of the brace.

なお、吊り材70等の補強部材は、本設でも良いし、仮設であっても良い。つまり、吊り材70は、後施工柱54の施工後に撤去しても良いし、撤去しなくても良い。また、補強部材は、必要に応じて設ければ良く、適宜省略可能である。   In addition, reinforcement members, such as suspension material 70, may be permanent installation, and may be temporary installation. That is, the hanging material 70 may or may not be removed after the post-construction column 54 is installed. Further, the reinforcing member may be provided as necessary, and can be omitted as appropriate.

また、図5に示されるように、スラブ62には、後述する後施工杭44及び後施工柱54を施工するための作業開口62Aを形成しておく。作業開口62Aは、後施工杭44及び後施工柱54の上方に配置される。また、作業開口62Aは、後施工柱54と梁58との柱梁仕口部の上方に配置される。この作業開口62Aは、例えば、後施工杭44及び後施工柱54の平断面よりも大きな開口とされる。   Further, as shown in FIG. 5, the slab 62 is provided with a work opening 62A for constructing a post-construction pile 44 and a post-construction column 54 described later. The work opening 62A is disposed above the post-construction pile 44 and the post-construction column 54. In addition, the work opening 62A is disposed above the beam-to-beam connection between the post-construction column 54 and the beam 58. The work opening 62A is, for example, an opening larger than the flat cross section of the post-construction pile 44 and the post-construction column 54.

図7(A)に示されるように、作業開口62Aの周辺部は、仮設又は本設の補強梁68によって補強される。これにより、作業開口62Aの周辺部の強度が確保される。なお、補強梁68は、必要に応じて設ければ良く、適宜省略可能である。   As shown in FIG. 7A, the periphery of the work opening 62A is reinforced by a temporary or permanent reinforcement beam 68. Thereby, the strength of the periphery of the work opening 62A is secured. The reinforcing beams 68 may be provided as necessary and can be omitted as appropriate.

(後施工杭施工工程)
次に、後施工杭施工工程について説明する。図4に示されるように、後施工杭施工工程は、前述した上部構造体施工工程と並行して行う。この後施工杭施工工程では、架構50の梁56,58上に敷設されたスラブ62の上から、地盤Gに後施工杭44を施工する。つまり、後施工杭施工工程では、スラブ62を作業台として、地盤Gに後施工杭44を施工する。
(Post-construction pile construction process)
Next, the post-construction pile construction process will be described. As shown in FIG. 4, the post-construction pile construction process is performed in parallel with the above-described upper structure construction process. In the post-construction pile construction process, a post-construction pile 44 is constructed on the ground G from above the slab 62 laid on the beams 56, 58 of the structure 50. That is, in the post-construction pile construction process, the post-construction pile 44 is constructed on the ground G using the slab 62 as a workbench.

具体的には、先ず、スラブ62の作業開口62A(図5参照)の周辺部に掘削機(図示省略)を設置し、作業開口62Aを介して地盤Gを掘削する。これにより、地盤Gに、後施工杭44用の杭孔46を形成する。なお、本実施形態では、プラットホーム28の下に後施工杭44を施工するため、プラットホーム28にも後施工杭44を施工するための貫通孔28A(図5参照)が形成されている。   Specifically, first, an excavator (not shown) is installed around the work opening 62A (see FIG. 5) of the slab 62, and the ground G is excavated through the work opening 62A. Thereby, a pile hole 46 for the post-construction pile 44 is formed in the ground G. In addition, in this embodiment, in order to construct the post-construction pile 44 under the platform 28, the through-hole 28A (refer FIG. 5) for constructing the post-construction pile 44 also in the platform 28 is formed.

次に、図5に示されるように、複数に分割された鉄筋かご48を図示しないクレーン等によって吊り上げ、当該鉄筋かご48をスラブ62の上から作業開口62Aを介して杭孔46に挿入する。この際、杭孔46には、複数の鉄筋かご48が接合された状態で挿入される。なお、鉄筋かご48は、鉄筋ユニットの一例である。   Next, as shown in FIG. 5, the rebar cage 48 divided into a plurality of pieces is lifted by a crane or the like (not shown), and the rebar cage 48 is inserted from above the slab 62 into the pile hole 46 through the work opening 62A. At this time, a plurality of reinforcing steel cages 48 are inserted into the pile holes 46 in a joined state. The reinforcing bar cage 48 is an example of a reinforcing bar unit.

次に、スラブ62の上に図示しないコンクリート打設機を設置し、スラブ62の上から作業開口62Aを介して杭孔46にコンクリートを打設する。これにより、後施工杭44が施工される。なお、後施工杭44の杭頭部には、後述する後施工柱54の柱脚部が接合される。   Next, a concrete casting machine (not shown) is installed on the slab 62, and concrete is cast from above the slab 62 into the pile hole 46 through the work opening 62A. Thereby, the post-construction pile 44 is constructed. In addition, the column base part of the post-construction pillar 54 mentioned later is joined to the pile head of the post-construction pile 44. As shown in FIG.

(後施工柱施工工程)
次に、後施工柱施工工程について説明する。後施工柱施工工程は、前述した上部構造体施工工程と並行して行う。この後施工柱施工工程では、スラブ62の上から、後施工杭44の上に、梁58を支持する後施工柱54を施工する。換言すると、スラブ62を作業台として、隣り合う一対の先行柱52の間に、梁58を支持する後施工柱54を施工する。
(Post-construction column construction process)
Next, the post-construction column construction process will be described. The post-construction pillar construction process is performed in parallel with the above-described upper structure construction process. In the post-construction pillar construction process, a post-construction pillar 54 supporting the beam 58 is constructed on the post-construction pile 44 from above the slab 62. In other words, the post-construction pillar 54 supporting the beam 58 is constructed between the pair of adjacent leading pillars 52 by using the slab 62 as a workbench.

具体的には、図6に示されるように、図示しないクレーン等によって後施工柱54を吊り上げ、当該後施工柱54をスラブ62の上から作業開口62Aを介して後施工杭44の上に設置する。この際、後施工柱54の柱脚部は、プラットホーム28の貫通孔28Aを介して杭孔46に挿入する。この状態で、杭孔46及びプラットホーム28の貫通孔28Aにコンクリートを打設し、後施工柱54の柱脚部を後施工杭44の柱頭部に固定する。   Specifically, as shown in FIG. 6, the post-construction pillar 54 is lifted by a crane or the like (not shown), and the post-construction pillar 54 is installed from above the slab 62 through the work opening 62A. Do. At this time, the column base portion of the post-construction pillar 54 is inserted into the pile hole 46 through the through hole 28A of the platform 28. In this state, concrete is placed in the pile holes 46 and the through holes 28 A of the platform 28, and the column base portion of the post-construction pillar 54 is fixed to the column head of the post-construction pile 44.

次に、後施工柱54の柱梁仕口部に、梁58を接合する。これにより、先行柱52、後施工柱54、及び梁56,58によって、架構50(図1参照)が施工される。また、後施工柱54によって梁58(梁58A,58B)が支持されるため、梁58A,58Bの支持スパンが短くなる。その後、作業開口62Aにコンクリートを打設し、作業開口62Aを塞ぐ。   Next, the beam 58 is joined to the beam connection of the post-construction pillar 54. Thereby, the frame 50 (see FIG. 1) is constructed by the leading pillar 52, the post construction pillar 54, and the beams 56, 58. Further, since the beams 58 (the beams 58A and 58B) are supported by the post-construction pillar 54, the support span of the beams 58A and 58B is shortened. Thereafter, concrete is cast in the work opening 62A to close the work opening 62A.

(作用及び効果)
次に、本実施形態の作用及び効果について説明する。
(Action and effect)
Next, the operation and effects of the present embodiment will be described.

図1に示されるように、本実施形態に係る施工方法によれば、構造物10の上部構造体60は、既存施設20の上方(上空)に施工される。ここで、既存施設20の上方に上部構造体60を施工する場合、例えば、既存施設20の稼働時間、すなわち駅22の営業時間等によって、一日の基礎40(先行杭42及び後施工杭44)の施工時間(工事時間)が制限される。そのため、構造物10の工期が長期化する可能性がある。   As shown in FIG. 1, according to the construction method according to the present embodiment, the upper structural body 60 of the structure 10 is constructed above (over the sky) the existing facility 20. Here, when constructing the upper structural body 60 above the existing facility 20, for example, the foundation 40 (previous pile 42 and post-construction pile 44 of one day depending on the operating time of the existing facility 20, ie, the operating time of the station 22). The construction time (construction time) is limited. Therefore, the construction period of the structure 10 may be prolonged.

この対策として本実施形態では、先ず、架構施工工程において、後施工杭44及び後施工柱54を間引いた架構50を施工する。次に、上部構造体施工工程と、後施工杭施工工程及び後施工柱施工工程とを並行して行う。つまり、上部構造体60と、後施工杭44及び後施工柱54とを並行して施工する。これにより、後施工杭44及び後施工柱54を施工してから、上部構造体60を施工する場合と比較して、構造物10の工期を短縮することができる。   As a countermeasure for this, in the present embodiment, first, in the frame construction process, the frame 50 in which the post-construction pile 44 and the post-construction column 54 are thinned out is constructed. Next, the upper structure construction process and the post-construction pile construction process and the post-construction column construction process are performed in parallel. That is, the upper structural body 60, and the post-construction pile 44 and the post-construction pillar 54 are constructed in parallel. Thereby, after construction of the post-construction pile 44 and the post-construction pillar 54, the construction period of the structure 10 can be shortened as compared with the case of constructing the upper structural body 60.

また、後施工杭44は、架構50の梁58上に敷設されたスラブ62の上から地盤Gに施工される。ここで、スラブ62の上からではなく、例えば、プラットホーム28上から地盤Gに後施工杭44を施工する場合、既存施設20の稼動時間終了後に、後施工杭44を施工するための掘削機やコンクリート打設機等をプラットホーム28の上に設置するとともに、既存施設20の稼働開始時間に合わせて、掘削機等をプラットホーム28の上からサイトヤード等に退避させる必要があるため、工期が長期化する可能性がある。   Further, the post-construction pile 44 is constructed on the ground G from above the slab 62 laid on the beam 58 of the frame 50. Here, when constructing the post-construction pile 44 from above the platform 62 to the ground G from above the slab 62, for example, an excavator or the like for constructing the post-construction pile 44 after the operation time of the existing facility 20 ends. Since it is necessary to evacuate the excavating machine etc. from above the platform 28 to the site yard etc. according to the operation start time of the existing facility 20 while installing a concrete placing machine etc. on the platform 28, the construction period is extended there's a possibility that.

これに対して本実施形態では、スラブ62の上に掘削機等を設置し、スラブ62の上から作業開口62Aを介して地盤Gに後施工杭44を施工する。そのため、既存施設20の稼働開始時間に合わせて、掘削機等をスラブ62の上からサイトヤード等に退避する必要がない。したがって、工期を短縮することができる。   On the other hand, in the present embodiment, an excavator or the like is installed on the slab 62, and the post-construction pile 44 is constructed on the ground G from above the slab 62 via the work opening 62A. Therefore, it is not necessary to withdraw the excavator or the like from the top of the slab 62 to the site yard or the like according to the operation start time of the existing facility 20. Therefore, the construction period can be shortened.

また、例えば、プラットホーム28の上から杭孔46に鉄筋かご48を挿入する場合、鉄筋かご48が梁58やスラブ62と干渉しないように、鉄筋かご48の全長を架構50の階高よりも短くする必要がある。   Also, for example, when the reinforcing bar cage 48 is inserted into the pile hole 46 from above the platform 28, the total length of the reinforcing bar cage 48 is shorter than the floor height of the structure 50 so that the reinforcing bar cage 48 does not interfere with the beam 58 or the slab 62. There is a need to.

これに対して本実施形態では、図5に示されるように、スラブ62の上から作業開口62Aを介して、杭孔46に鉄筋かご48を挿入する。これにより、鉄筋かご48が梁58やスラブ62と干渉しないため、鉄筋かご48の全長を架構50の階高よりも長くすることができる。この結果、鉄筋かご48の分割数を減らすことができる。したがって、鉄筋かご48の継手箇所や揚重回数が低減されるため、施工性が向上する。   On the other hand, in the present embodiment, as shown in FIG. 5, the reinforcing steel cage 48 is inserted into the pile hole 46 from above the slab 62 via the work opening 62A. As a result, since the reinforcing bar cage 48 does not interfere with the beams 58 and the slab 62, the total length of the reinforcing bar cage 48 can be made longer than the floor height of the frame 50. As a result, the number of divisions of the reinforcing bar cage 48 can be reduced. Therefore, since the number of joints and the number of liftings of the reinforcing bar cage 48 are reduced, the workability is improved.

これと同様に、本実施形態では、スラブ62の上から作業開口62Aを介して、後施工柱54を後施工杭44の上に設置する。これにより、後施工柱54が梁58やスラブ62と干渉しないため、後施工柱54を分割せずに、後施工杭44の上に設置することができる。したがって、後施工柱54の施工性が向上する。   Similarly to this, in the present embodiment, the post-construction pillar 54 is installed on the post-construction pile 44 from above the slab 62 via the work opening 62A. Thereby, since the post-construction pillar 54 does not interfere with the beam 58 or the slab 62, the post-construction pillar 54 can be installed on the post-construction pile 44 without being divided. Therefore, the workability of the post-construction pillar 54 is improved.

さらに、本実施形態では、スラブ62の上から作業開口62Aを介して、地盤Gに後施工杭44用の杭孔46を掘削し、掘削した杭孔46にコンクリートを打設する。そのため、後施工杭44の施工には、排泥管やコンクリート供給管等の配管32(図2(A)参照)を既存施設20内に設ける必要がない。したがって、配管32の敷設コスト等を削減することができる。   Furthermore, in the present embodiment, the pile hole 46 for the post-construction pile 44 is excavated in the ground G from above the slab 62 through the work opening 62A, and concrete is cast in the excavated pile hole 46. Therefore, for the construction of the post-construction pile 44, it is not necessary to provide the piping 32 (see FIG. 2A) such as a mud pipe or a concrete supply pipe in the existing facility 20. Therefore, the laying cost of the piping 32 can be reduced.

(変形例)
次に、上記実施形態の変形例について説明する。
(Modification)
Next, modifications of the above embodiment will be described.

スラブ62に形成する作業開口62Aの大きさや形状、配置は、適宜可能である。また、作業開口62Aの周辺部の補強構造も適宜変更可能である。例えば、図7(B)に示される変形例では、略平行する一対の梁58の間に作業開口62Aが形成されている。この一対の梁58には、作業開口62Aの両側の周辺部に沿った補強梁80がそれぞれ架設されており、これらの補強梁80によって作業開口62Aの周辺部が補強されている。   The size, shape, and arrangement of the work openings 62A formed in the slab 62 can be appropriately determined. Further, the reinforcing structure of the peripheral portion of the work opening 62A can also be changed as appropriate. For example, in the modification shown in FIG. 7B, the work opening 62A is formed between the pair of substantially parallel beams 58. In the pair of beams 58, reinforcing beams 80 are installed along the peripheral portions on both sides of the work opening 62A, and the peripheral portions of the work opening 62A are reinforced by the reinforcing beams 80.

また、図7(C)に示される変形例では、後施工柱54に支持される梁58A,58Bの端部が、作業開口62A内へ突出している。一方、後施工柱54の柱梁仕口部には、各梁58A,58Bに対応する複数のブラケット82が設けられている。これらのブラケット82には、各梁58A,58Bの端部が接合される。これにより、後施工柱54の柱梁仕口部に各梁58A,58Bを容易に接合することができる。   Further, in the modification shown in FIG. 7C, the end portions of the beams 58A, 58B supported by the post-construction pillar 54 project into the work opening 62A. On the other hand, a plurality of brackets 82 corresponding to the beams 58A and 58B are provided at the beam-to-beam connection of the post-construction column 54. The ends of the beams 58A and 58B are joined to these brackets 82. Thereby, each beam 58A, 58B can be easily joined to the beam-to-beam connection part of the post-construction pillar 54.

次に、上記実施形態では、架構50の梁58上に敷設されたスラブ62の上から後施工杭44及び後施工柱54を施工したが、上記実施形態はこれに限らない。例えば、図8に示されるように、プラットホーム28の上から、後施工杭44を施工しても良い。なお、図8に示される例では、プラットホーム28の上に、コンクリート打設機84が設置されている。   Next, although the post-construction pile 44 and the post-construction pillar 54 are constructed from the top of the slab 62 laid on the beam 58 of the structure 50 in the above embodiment, the above embodiment is not limited thereto. For example, as shown in FIG. 8, a post-construction pile 44 may be installed on the platform 28. In the example shown in FIG. 8, a concrete casting machine 84 is installed on the platform 28.

ここで、図8に示される変形例では、スラブ62の上から後施工杭44を施工しないため、後施工杭44の上方から外れた位置に作業開口62Aが配置されている。また、架構50には、架構施工工程において、後施工柱54の上部54Aが予め施工されている。   Here, in the modification shown in FIG. 8, since the post-construction pile 44 is not constructed from above the slab 62, the work opening 62A is disposed at a position deviated from above the post-construction pile 44. In the frame construction process, the upper part 54A of the post-construction post 54 is pre-applied to the frame 50.

この場合は、例えば、図9に示されるように、図示しないクレーンによって、後施工柱54の柱ユニット54Bを吊り上げ、当該柱ユニット54Bを作業開口62Aを介して後施工杭44と後施工柱54の上部54Aとの間に設置するとともに、柱ユニット54Bの柱脚部を後施工杭44に接合する。また、後施工柱54の上部54Aと柱ユニット54Bとの隙間を間詰め材86によって埋め、間詰め材86を介して後施工柱54の上部54Aと柱ユニット54Bとを接合する。   In this case, for example, as shown in FIG. 9, the crane unit (not shown) lifts the post unit 54B of the post-construction post 54, and the post unit 54B and the post-construction post 54 via the work opening 62A. And the column base of the column unit 54B is joined to the post-construction pile 44. Further, the gap between the upper portion 54A of the post-construction pillar 54 and the pillar unit 54B is filled with the padding 86, and the upper portion 54A of the post-construction pillar 54 and the pillar unit 54B are joined via the padding 86.

このように架構施工工程において、後施工柱54の一部を施工し、後施工柱施工工程において、後施工柱54の残りの部分を施工することも可能である。   As described above, it is also possible to construct a part of the post-construction column 54 in the frame construction process, and to construct the remaining part of the post-construction column 54 in the post-construction column construction process.

また、上記実施形態では、スラブ62の上から全ての後施工杭44を施工したが、上記実施形態はこれに限らない。例えば、スラブ62の上から後施工杭44の一部のみを施工し、後施工杭44の他の部分は、プラットホーム28の上から施工しても良い。つまり、スラブ62の上からは、後施工杭44の少なくとも一部を施工することができる。   Moreover, in the said embodiment, although all the post construction piles 44 were constructed from the top of the slab 62, the said embodiment is not restricted to this. For example, only a part of the post-construction pile 44 may be constructed from above the slab 62, and the other part of the post-construction pile 44 may be constructed from above the platform 28. That is, from above the slab 62, at least a part of the post-construction pile 44 can be constructed.

なお、後施工柱54の鉄筋かご48は、スラブ62の上から作業開口62Aを介して杭孔46に挿入することが好ましい。前述したように、鉄筋かご48の全長を架構50の階高よりも長くし、鉄筋かご48の分割数等を減らすことができるためである。また、プラットホーム28上や地盤G上から、後施工杭44の少なくとも一部を施工することも可能である。   Preferably, the reinforcing steel cage 48 of the post-construction post 54 is inserted into the pile hole 46 from above the slab 62 through the work opening 62A. As described above, the total length of the reinforcing bar cage 48 can be made longer than the floor height of the frame 50, and the number of divisions of the reinforcing bar cage 48 can be reduced. Moreover, it is also possible to construct at least one part of the post-construction pile 44 from the platform 28 and the ground G.

また、上記実施形態では、スラブ62の上から全ての後施工柱54を施工したが、上記実施形態はこれに限らない。例えば、スラブ62の上から後施工柱54の一部のみを施工し、後施工柱54の他の部分は、プラットホーム28の上から施工しても良い。また、プラットホーム28上や地盤G上から、後施工柱54の少なくとも一部を施工することも可能である。   Moreover, in the said embodiment, although all the post-construction pillars 54 were constructed from the top of the slab 62, the said embodiment is not restricted to this. For example, only a part of the post-construction pillar 54 may be constructed from above the slab 62, and the other part of the post-construction pillar 54 may be constructed from above the platform 28. Moreover, it is also possible to construct at least one part of the post-construction pillar 54 from the platform 28 and the ground G.

次に、上記実施形態では、一対の先行柱52の間に後施工柱54を施工したが、上記実施形態はこれに限らない。例えば、図10に示されるように、構造物10の外周杭及び外周柱を、後施工杭44及び後施工柱54としても良い。   Next, although the post-construction pillar 54 was constructed between a pair of leading pillars 52 in the above-mentioned embodiment, the above-mentioned embodiment is not restricted to this. For example, as shown in FIG. 10, the outer periphery pile and the outer periphery pillar of the structure 10 may be used as the post-construction pile 44 and the post-construction pillar 54.

具体的には、架構施工工程において、一対の先行柱52に梁56を架設して架構50を施工するとともに、架構50から跳ね出す跳出し梁90を施工する。この架構50では、跳出し梁90の先端側(自由端側)を支持する後施工柱54が間引かれており、跳出し梁90が架構50に片持ち状態で支持されている。   Specifically, in the frame construction process, the beam 56 is erected on the pair of leading columns 52 to construct the frame 50, and the jump beam 90 splashing from the frame 50 is constructed. In this structure 50, the post construction post 54 supporting the tip end side (free end side) of the jump-out beam 90 is thinned out, and the jump-out beam 90 is supported by the structure 50 in a cantilever state.

この場合、後施工杭施工工程では、例えば、図11に示されるように、跳出し梁90上に施工されたスラブ62の作業開口62Bから、後施工杭44を施工する。この作業開口62Bは、孔ではなく、切り欠き状に形成されている。   In this case, in the post-construction pile construction step, for example, as shown in FIG. 11, the post-construction pile 44 is constructed from the work opening 62B of the slab 62 constructed on the jump beam 90. The working opening 62B is formed not like a hole but like a notch.

なお、図10に示されるように、跳出し梁90は、前述した吊り材70等やブレース92の補強部材によって適宜補強されている。また、跳出し梁90に対する補強としては、跳出し梁90の断面積を大きくしても良い。なお、跳出し梁90は、水平部材の一例である。   As shown in FIG. 10, the jump-out beam 90 is appropriately reinforced by the above-described suspension members 70 and the like and a reinforcing member of the brace 92. In addition, as a reinforcement for the jumping beam 90, the cross-sectional area of the jumping beam 90 may be increased. In addition, the jump-out beam 90 is an example of a horizontal member.

次に、図12(A)及び図12(B)に示されるように、先行杭42(先行柱52)及び後施工杭44(後施工柱54)の配置は、適宜変更可能である。   Next, as FIG. 12 (A) and FIG. 12 (B) show, arrangement | positioning of the precedent pile 42 (preceding pillar 52) and the post-construction pile 44 (post-construction pillar 54) is changeable suitably.

また、上記実施形態では、先行杭42及び後施工杭44が場所打ち杭とされるが、上記実施形態はこれに限らない。先行杭及び後施工杭は、例えば、既製杭であっても良い。また、後施工杭44、適宜省略可能であり、例えば、架構50を施工する前に、全ての杭を施工しても良い。また、上記実施形態では、基礎40は、杭基礎に限らず、直接基礎であっても良い。   Moreover, although the preceding pile 42 and the post-construction pile 44 are made into cast-in-place piles in the said embodiment, the said embodiment is not restricted to this. The preceding pile and the post-construction pile may be, for example, prefabricated piles. Also, the post-construction pile 44 can be omitted as appropriate, and, for example, all the piles may be constructed before the construction of the frame 50. Moreover, in the said embodiment, the foundation 40 may be not only a pile foundation but a direct foundation.

また、先行柱52及び後施工柱54の構造は適宜変更であり、例えば、鉄骨造やCFT造、鉄筋コンクリート造、鉄骨鉄筋コンクリート造であっても良い。   Further, the structures of the leading column 52 and the post-construction column 54 are appropriately changed, and may be, for example, a steel frame, a CFT, a reinforced concrete, or a steel-framed reinforced concrete.

また、上記実施形態では、既存施設20が駅22を含むが、上記実施形態はこれに限らない。既存施設としては、例えば、道路や設備、構造物等であって良い。また、架構50の上に施工される上部構造体は、人工地盤等であっても良い。   Moreover, in the said embodiment, although the existing installation 20 contains the station 22, the said embodiment is not restricted to this. The existing facilities may be, for example, roads, facilities, structures and the like. In addition, the upper structure constructed on the frame 50 may be artificial ground or the like.

以上、本発明の一実施形態について説明したが、本発明はこうした実施形態に限定されるものでなく、一実施形態及び各種の変形例を適宜組み合わせて用いても良いし、本発明の要旨を逸脱しない範囲において、種々なる態様で実施し得ることは勿論である。   As mentioned above, although one Embodiment of this invention was described, this invention is not limited to such Embodiment, You may use it combining suitably one Embodiment and various modifications, The summary of this invention Of course, various modifications can be made without departing from the scope of the invention.

10 構造物
44 後施工杭
50 架構
52 先行柱
54 後施工柱
58 梁(水平部材)
10 Structure 44 Post-Construction Pile 50 Structure 52 Leading Column 54 Post-Construction Column 58 Beam (Horizontal Member)

Claims (3)

一対の先行柱と、前記一対の先行柱に支持される水平部材と、を有する架構を施工する架構施工工程と、
前記先行柱の隣に、前記水平部材を支持する後施工柱を施工する後施工柱施工工程と、
を備える構造物の施工方法。
A frame construction step of constructing a frame having a pair of leading columns and a horizontal member supported by the pair of leading columns;
A post-construction pillar construction step of constructing a post-construction pillar supporting the horizontal member next to the leading pillar;
Construction method of the structure provided with
前記架構施工工程の後に、前記後施工柱を支持する後施工杭を施工する後施工杭施工工程を備える、
請求項1に記載の構造物の施工方法。
After the frame construction process, comprising a post-construction pile construction process of constructing a post-construction pile for supporting the post-construction column,
The construction method of the structure of Claim 1.
前記後施工杭施工工程において、前記後施工杭の少なくとも一部を前記水平部材の上から施工する、
請求項2に記載の構造物の施工方法。

In the post-construction pile construction step, at least a part of the post-construction pile is constructed from above the horizontal member,
The construction method of the structure of Claim 2.

JP2017084038A 2017-04-20 2017-04-20 Construction method of structure Active JP7003376B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2017084038A JP7003376B2 (en) 2017-04-20 2017-04-20 Construction method of structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2017084038A JP7003376B2 (en) 2017-04-20 2017-04-20 Construction method of structure

Publications (2)

Publication Number Publication Date
JP2018178658A true JP2018178658A (en) 2018-11-15
JP7003376B2 JP7003376B2 (en) 2022-01-20

Family

ID=64282910

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2017084038A Active JP7003376B2 (en) 2017-04-20 2017-04-20 Construction method of structure

Country Status (1)

Country Link
JP (1) JP7003376B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020186520A (en) * 2019-05-09 2020-11-19 株式会社サクシス Construction method, building, construction method of main structure of skeleton of building, main structure of skeleton of building, and method of building extension to upward floor

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05230891A (en) * 1992-02-21 1993-09-07 Takenaka Komuten Co Ltd Construction method of super-multistoried building
JP2004156207A (en) * 2002-11-01 2004-06-03 Kajima Corp Construction method for building and beam member used for the same
JP2007321399A (en) * 2006-05-31 2007-12-13 Tekken Constr Co Ltd Construction method and device for structure over railroad track
CN103866700A (en) * 2014-03-14 2014-06-18 中冶建筑研究总院有限公司 Double-hanging-rod hanging widening structure for transforming platform coming into use
US20150211205A1 (en) * 2014-01-29 2015-07-30 Guangzhou Jishi Construction Group Co., Ltd. Construction system for subway station

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05230891A (en) * 1992-02-21 1993-09-07 Takenaka Komuten Co Ltd Construction method of super-multistoried building
JP2004156207A (en) * 2002-11-01 2004-06-03 Kajima Corp Construction method for building and beam member used for the same
JP2007321399A (en) * 2006-05-31 2007-12-13 Tekken Constr Co Ltd Construction method and device for structure over railroad track
US20150211205A1 (en) * 2014-01-29 2015-07-30 Guangzhou Jishi Construction Group Co., Ltd. Construction system for subway station
CN103866700A (en) * 2014-03-14 2014-06-18 中冶建筑研究总院有限公司 Double-hanging-rod hanging widening structure for transforming platform coming into use

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020186520A (en) * 2019-05-09 2020-11-19 株式会社サクシス Construction method, building, construction method of main structure of skeleton of building, main structure of skeleton of building, and method of building extension to upward floor

Also Published As

Publication number Publication date
JP7003376B2 (en) 2022-01-20

Similar Documents

Publication Publication Date Title
CN106758841B (en) A kind of whole construction process of the double rope face low-pylon cable-stayed bridges of double tower
KR101111594B1 (en) Method for constructing underground structure
JP4853429B2 (en) Support structure of lining board, method of supporting lining board
JP6349339B2 (en) Floor slab, bearing, inner wall, joint formwork and floor slab erection crane
KR102105230B1 (en) Railroad bridge construction method for keeping preexistence railroad track and rail service
JP2004263467A (en) Reconstruction method using existing underground skeleton
JP2010031607A (en) Construction method for grade separation
JP2006214269A (en) Erected girder
JP2018178658A (en) Method for constructing structure
JP6889010B2 (en) Bridge construction method
JP2005146695A (en) Viaduct structure and method of constructing the same
JP3910135B2 (en) Building construction method and beam member used therefor
JP3380301B2 (en) Viaduct construction method
JP4479229B2 (en) Basic structure of the structure
KR101047943B1 (en) A extension footpath with reinforcement equipment and it's construction method
JP6720761B2 (en) How to build a ramen structure
JP5073960B2 (en) Construction method of underground structure and underground structure
JP3940587B2 (en) Construction method of divided bridge type traffic route
JP2020186516A (en) Method of constructing bridge railing
JP2000129633A (en) Erection method for bridge floor slab
CN204960366U (en) Tunnel passes through device that underpins of existing large diameter pile building
JP4128887B2 (en) How to install a three-dimensional crossover viaduct
JP2009203750A (en) Excavating machine and excavation method
JP6401833B2 (en) Pca wall
JP2587029B2 (en) Viaduct construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20200326

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20210216

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210309

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210415

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20210831

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20210910

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20211130

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20211210

R150 Certificate of patent or registration of utility model

Ref document number: 7003376

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150