JP2010031607A - Construction method for grade separation - Google Patents

Construction method for grade separation Download PDF

Info

Publication number
JP2010031607A
JP2010031607A JP2008197420A JP2008197420A JP2010031607A JP 2010031607 A JP2010031607 A JP 2010031607A JP 2008197420 A JP2008197420 A JP 2008197420A JP 2008197420 A JP2008197420 A JP 2008197420A JP 2010031607 A JP2010031607 A JP 2010031607A
Authority
JP
Japan
Prior art keywords
floor slab
pair
portal crane
crane
width
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008197420A
Other languages
Japanese (ja)
Other versions
JP5184248B2 (en
Inventor
Nobuyuki Matsui
信行 松井
Yukihiro Nakatani
行博 中谷
Tadahiro Sato
忠宏 佐藤
Munehisa Yamaguchi
統央 山口
Takahiro Arai
崇裕 新井
Seiichiro Takizawa
清一郎 滝沢
Masatoshi Kawada
正敏 川田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2008197420A priority Critical patent/JP5184248B2/en
Publication of JP2010031607A publication Critical patent/JP2010031607A/en
Application granted granted Critical
Publication of JP5184248B2 publication Critical patent/JP5184248B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method for a grade separation, which is a method for constructing a bridge of grade separated crossing or the like, using one and the same portal crane from the installation of a bridge girder to the installation of a floor slab, so as to reduce a space occupied for the construction work as small as possible, while a construction period can be shortened. <P>SOLUTION: The floor slab 19, whose width direction is arranged in parallel to the moving direction of the portal crane 1, is placed temporarily between rails 3. The floor slab 19 is lifted between a pair of support legs 13. Next, the floor slab 19 is placed on a turn table 21. Then, the turn table 21 is rotated by 90° for rotating the floor slab 19. Under such a condition as the width direction of the floor slab 19 is perpendicular to the moving direction of the portal crane 1, the portal crane 1 is advanced. Since a winch 17 is provided on a projecting portion 14, the support leg 13 and the floor slab 19 are not interfered to each other when lifting the floor slab. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

本発明は、道路の工事占有範囲を極力少なくし、工期の短縮が可能な立体交差の施工方法に関する。   The present invention relates to a construction method for a three-dimensional intersection capable of reducing the construction occupation range of a road as much as possible and shortening a construction period.

従来、交差点などの立体交差の工事には、部材の仮置き場や、部材を運搬するクレーン等の動作範囲など、広範囲の工事占有範囲を確保する必要がある。また、工事期間中は、工事車両等の通過や施工時の交通規制の影響で、深刻な渋滞が発生する恐れがある。したがって、短期間かつ交通規制などを最低限に抑えた施工方法が望まれている。   Conventionally, in construction of a three-dimensional intersection such as an intersection, it is necessary to secure a wide occupation occupation range such as a temporary storage place for members and an operation range of a crane for transporting the members. In addition, during the construction period, serious traffic congestion may occur due to the passage of construction vehicles or the like and the influence of traffic restrictions during construction. Therefore, there is a demand for a construction method that minimizes traffic restrictions and the like for a short period of time.

このような短期間かつ交通への悪影響を解消する方法としては、橋梁の両側に設置される左右一対の主桁上に、主桁上を走行可能かつ床版を運搬可能な床版搬送車を設け、床版搬送車によって、床版を設置位置まで運搬し、設置する橋梁床版架設方法がある(特許文献1)。   As a method for eliminating such adverse effects on traffic for a short period of time, on the pair of left and right main girders installed on both sides of the bridge, a floor slab carrier vehicle that can run on the main girder and carry the floor slab is provided. There is a bridge slab erection method in which a floor slab is transported to an installation position by a floor slab conveyance vehicle and installed (Patent Document 1).

また、複数の分割体により構成され、互いに連結して折り畳むことが可能な構造の上部工を用い、折りたたんだ状態の上部工を橋脚上に設置し、橋脚上で上部工の分割体を展開して橋梁を施工する方法がある(特許文献2)。   In addition, a superstructure composed of a plurality of divided bodies, which can be connected to each other and folded, is installed on the pier, and the superstructure divided sections are deployed on the pier. There is a method of constructing a bridge (Patent Document 2).

特開2006−169757号公報JP 2006-169757 A 特開2004−176531号公報JP 2004-176531 A

しかし、特許文献1のような橋梁床版架設方法では、床版の運搬に使用する床版搬送車の幅よりも大きな幅を有する床板を設置することができないという問題がある。このため、設置可能な床版幅は、あらかじめ設置された主桁の間隔までであり、中央に設けられた橋脚に対して、両側方へ床版が張り出したような構造の橋梁を施工することができない。また、主桁等の設置の際には、従来と同様にクレーン等を使用する必要があり、主桁の施工が完了するまでの間は、従来と同様に交通規制等を行う必要があるという問題がある。   However, in the bridge floor slab erection method as in Patent Document 1, there is a problem that a floor plate having a width larger than the width of the floor slab transport vehicle used for transporting the floor slab cannot be installed. For this reason, the width of the slab that can be installed is up to the interval between the main girders installed in advance, and a bridge with a structure in which the slab protrudes to both sides of the bridge pier provided in the center should be constructed. I can't. In addition, when installing the main girder etc., it is necessary to use a crane etc. as before, and until the construction of the main girder is completed, it is necessary to carry out traffic regulation etc. as before There's a problem.

また、特許文献2のような橋梁の施工方法では、上部工を折り畳める構造にするため、橋脚の両側方へ張り出したような形状の橋梁を施工することができるが、上部工を折り畳める構造とすることから、構造が複雑であり、また回転部が金属製であることから、橋梁の耐久性が悪く、工費がかさむという問題がある。また、折り畳まれた上部工を展開する際には、上部工の下方の交通規制を行う必要があり、橋梁の施工に伴う交通規制の緩和の効果は大きくないという問題がある。   Moreover, in the construction method of a bridge like patent document 2, in order to set it as the structure which can fold an upper work, it can construct the bridge of the shape projected on the both sides of a bridge pier, but it is set as the structure which can fold an upper work. Therefore, since the structure is complicated and the rotating part is made of metal, there is a problem that the durability of the bridge is poor and the construction cost is increased. Moreover, when unfolding the superstructure, it is necessary to regulate traffic below the superstructure, and there is a problem that the effect of relaxing traffic regulations associated with the construction of bridges is not great.

本発明は、このような問題に鑑みてなされたもので、立体交差などの橋梁を施工する方法であって、橋桁の設置から床版の設置まで同一の門型クレーンを用い、道路の工事占有範囲を極力少なくするとともに、工期の短縮が可能な立体交差の施工方法を提供することを目的とする。   The present invention has been made in view of such problems, and is a method of constructing a bridge such as a three-dimensional intersection, using the same portal crane from the installation of a bridge girder to the installation of a floor slab, An object is to provide a construction method for a three-dimensional intersection capable of reducing the range as much as possible and shortening the construction period.

前述した目的を達成するため、本発明は、一対の支持脚と、前記支持脚下方に取り付けられ、レールに沿って走行可能な車輪と、一対の前記支持脚を連結するクレーン桁と、前記クレーン桁に設けられ、走行方向へ突出した突出部と、前記クレーン桁に沿って移動可能であり、前記突出部に設けられた第1のウィンチと、を有する門型クレーンを用い、前記第1のウィンチが向かい合うように、一対の前記門型クレーンを、移動方向に対向するようにレール上に設置する工程(a)と、前記レールの間に橋脚を設ける工程(b)と、一対の前記門型クレーンで橋桁を共吊りし、前記橋桁を前記橋脚上に設置する工程(c)と、前記門型クレーンで床版を吊上げ、前記床版を前記橋桁上へ設置する工程(d)と、を具備することを特徴とする立体交差の施工方法である。   In order to achieve the above-described object, the present invention provides a pair of support legs, wheels attached below the support legs and capable of traveling along rails, a crane girder connecting the pair of support legs, and the crane. A portal crane having a projecting portion provided on a girder and projecting in a traveling direction, and a first winch disposed on the projecting portion and movable along the crane girder, A step (a) of installing the pair of portal cranes on the rail so that the winches face each other, a step (b) of providing a bridge pier between the rails, and a pair of the gates A step (c) of suspending a bridge girder with a type crane and installing the bridge girder on the pier; a step of lifting a floor slab with the portal crane and installing the floor slab on the bridge girder (d); Characterized by comprising It is a construction method of the cross.

前記床版の幅が、一対の前記支持脚同士の間隔よりも大きく、前記工程(d)は、前記床板の幅方向が前記門型クレーンの移動方向に向くように、前記床版を一対の前記支持脚の間に、吊上げる工程(e)と、前記床版をターンテーブル上へ設置する工程(f)と、前記床版の幅方向が前記門型クレーンの移動方向に対して略垂直方向へ向くように、前記ターンテーブルを回転させる工程(g)と、前記床版を前記門型クレーンで吊上げる工程(h)と、前記床版を前記橋桁上へ設置する工程(i)と、を具備してもよい。   A width of the floor slab is larger than a distance between the pair of support legs, and the step (d) is performed by placing the floor slab in a pair so that a width direction of the floor board faces a moving direction of the portal crane. A step (e) of lifting between the support legs, a step (f) of installing the floor slab on a turntable, and the width direction of the floor slab is substantially perpendicular to the moving direction of the portal crane. A step (g) of rotating the turntable so as to face in a direction, a step (h) of lifting the floor slab with the portal crane, and a step (i) of installing the floor slab on the bridge girder. , May be included.

前記床版は一対の略L字状部材であり、一対の前記L字状部材は、吊り具の両端に接合されており、前記工程(e)は、一対の前記L字状部材が接合された前記吊り具の幅方向が前記門型クレーンの移動方向に向くように、前記吊り具を一対の前記支持脚の間に吊上げる工程であり、前記工程(i)は、前記L字状部材を前記橋桁の両端近傍へ接合する工程であり、前記工程(i)の後、前記吊り具を前記門型クレーンで撤去する工程(j)をさらに具備してもよい。   The floor slab is a pair of substantially L-shaped members, and the pair of L-shaped members are joined to both ends of a hanging tool. In the step (e), the pair of L-shaped members are joined. The lifting tool is lifted between the pair of support legs so that the width direction of the lifting tool is directed to the moving direction of the portal crane, and the step (i) is the L-shaped member. May be further joined to the vicinity of both ends of the bridge girder, and after the step (i), a step (j) of removing the suspension tool with the portal crane may be further included.

この場合、前記吊り具は幅方向の伸縮が可能であり、前記吊り具を縮めた状態では、前記吊り具に取り付けられた一対の前記L字状部材の幅は、一対の前記支持脚同士の間隔よりも小さく、前記吊り具を伸ばした状態では、前記吊り具に取り付けられた一対の前記L字状部材の幅は、一対の前記支持脚同士の間隔よりも大きく、前記工程(e)に代えて、前記吊り具を縮めた状態で、前記L字状部材の幅方向が前記門型クレーンの移動方向とほぼ垂直方向に向くように、前記L字状部材が接合された前記吊り具を、一対の前記支持脚の間に吊上げる工程(k)を具備し、前記工程(f)に代えて、前記L字状部材が接合された前記吊り具を、前記吊り具の幅を変更可能な伸縮架台へ載せる工程(l)を具備し、前記工程(g)に代えて、前記吊り具の幅を前記伸縮架台により伸ばし、一対の前記L字状部材同士の間隔を大きくする工程(m)を具備してもよい。   In this case, the hanging tool can be expanded and contracted in the width direction. When the hanging tool is contracted, the pair of L-shaped members attached to the hanging tool has a width between the pair of supporting legs. The width of the pair of L-shaped members attached to the hanger is larger than the distance between the pair of support legs when the hanger is extended and smaller than the gap, and the step (e) Instead, in the state where the suspension member is contracted, the suspension member to which the L-shaped member is joined so that the width direction of the L-shaped member is substantially perpendicular to the moving direction of the portal crane. A step (k) of lifting between the pair of support legs, and instead of the step (f), the width of the hanger can be changed for the hanger to which the L-shaped member is joined. A step (l) for placing on a flexible telescopic mount, and instead of the step (g), The width of Ri member stretched by the stretch frame may comprise a step (m) to increase the distance between the pair of the L-shaped member.

前記門型クレーンは、前記第1のウィンチのさらに前方に第2のウィンチが設けられ、前記工程(i)は、前記第1のウィンチにより、設置予定のL字状部材が設けられた第1の吊り具を前記橋桁上へ設置する工程であり、前記工程(j)は、前記第2のウィンチにより、設置終了後のL字状部材が設けられていた第2の吊り具を前記橋桁上から撤去する工程でであってもよい。   The portal crane is provided with a second winch in front of the first winch. In the step (i), the first winch is provided with an L-shaped member to be installed. Is installed on the bridge girder, and the step (j) uses the second winch to place the second hanger provided with the L-shaped member after installation on the bridge girder. It may be a process of removing from.

前記工程(b)は、前記橋脚の型枠および鉄筋が組み立てられたプレファブ型枠を前記門型クレーンにより設置し、前記プレファブ型枠へコンクリートを打設することにより、前記橋脚が設けられてもよい。   In the step (b), even if the pier is provided by installing a prefabricated formwork in which the formwork and reinforcing bars of the pier are assembled with the portal crane and placing concrete into the prefabricated formwork. Good.

本発明によれば、一対の門型クレーンによって、橋脚の設置から床版の架設までの工程をすべて行うことができ、立体交差近傍への他の大型クレーン等の設置や、クレーンの交換作業等が不要であるため、短納期に立体交差を施工することができる。特に、門型クレーンの走行時のみ道路を規制すれば良いため、交通規制を最小限に抑えることができる。   According to the present invention, a pair of portal cranes can perform all steps from installation of piers to installation of floor slabs, installation of other large cranes near a three-dimensional intersection, crane replacement work, etc. Is unnecessary, so it is possible to construct a three-dimensional intersection in a short delivery time. In particular, since it is only necessary to regulate the road only when the portal crane is traveling, traffic regulation can be minimized.

また、門型クレーンは、ウィンチが突出部に設けられるため、門型クレーンよりも幅の大きな構造物を吊上げ、運搬することが可能である。また、門型クレーンの幅は、橋脚を避けることができるだけの幅を有すればよいため、門型クレーンの走行スペースを小さくすることができ、門型クレーンの走行スペース以外の車線の交通規制を行う必要がない。したがって、交通規制の必要な車線を最小限に抑えることができる。   Moreover, since the winch is provided in the protrusion part, the portal crane can lift and convey a structure wider than a portal crane. In addition, the width of the gate crane need only be wide enough to avoid the piers, so the travel space of the gate crane can be reduced, and traffic control of lanes other than the travel space of the gate crane is restricted. There is no need to do it. Therefore, it is possible to minimize lanes that require traffic regulation.

また、ターンテーブルを用いることで、門型クレーンよりも幅の大きな床版を縦方向(門型クレーンの移動方向)に向けて運搬し、ターンテーブル上で床版を横向き(門型クレーンの移動方向に対して垂直方向)に回転させて再度吊り上げることで、床版置き場から容易に床版を運搬することができるとともに、橋桁上へも床版を横向きに設置することができる。   Also, by using a turntable, the floor slab, which is wider than the portal crane, is transported in the vertical direction (moving direction of the portal crane), and the floor slab is turned sideways on the turntable (moving the portal crane). The floor slab can be easily transported from the floor slab yard and can be installed sideways on the bridge girder by rotating it in the direction perpendicular to the direction and lifting it again.

また、床版が一対のL字状部材であり、橋桁端部に設置可能であれば、床版を橋桁上へ設置した際に、床版の床部と橋桁の上面部とが2重構造になることがなく、このため床版のコンクリートを削減することができる。また、L字状部材を接合する吊り具を用いれば、L字状部材の設置が容易であり、また、吊り具は繰り返し使用することができるため経済的である。   In addition, if the floor slab is a pair of L-shaped members and can be installed at the end of the bridge girder, when the floor slab is installed on the bridge girder, the floor part of the floor slab and the upper part of the bridge girder are double structures. Therefore, the concrete of the floor slab can be reduced. Moreover, if the hanging tool which joins an L-shaped member is used, installation of an L-shaped member is easy, and since the hanging tool can be used repeatedly, it is economical.

また、吊り具の幅を伸縮可能とし、吊り具の幅を縮めた状態では、吊り具の幅を門型クレーンの支持脚の間隔よりも小さくできれば、床版が接合された吊り具を回転させる必要がない。また、設置前の床版の置き場の面積を小さくすることができるため、より狭い作業エリアで作業をおこなうことができる。   In addition, if the width of the suspension can be expanded and contracted and the width of the suspension is reduced, the suspension attached to the floor slab can be rotated if the width of the suspension can be made smaller than the distance between the support legs of the gate crane. There is no need. In addition, since the area of the floor slab before installation can be reduced, the work can be performed in a narrower work area.

また、門型クレーンに2段階に突出したウィンチを設けることで、支持脚に近い側のウィンチで設置予定の床版および吊り具を吊上げ、当該床版を設置後、他方のウィンチで前回設置した床版の吊り具を吊上げ、回収することができる。このため、床版を橋桁に設置後、橋桁上では橋桁と床版との接合作業を行いながら、次に設置する床版を門型クレーンで橋桁上へ運搬することができ、作業効率が高い。   In addition, by installing a winch that protrudes in two stages on the portal crane, the floor slab and lifting tool to be installed are lifted by the winch on the side close to the support leg, and after installing the floor slab, it was previously installed by the other winch. It is possible to lift the floor stool and collect it. For this reason, after the floor slab is installed on the bridge girder, while the bridge girder and the floor slab are joined on the bridge girder, the next installed floor slab can be transported to the bridge girder by the portal crane, and the work efficiency is high. .

また、橋脚を設置するための型枠が、あらかじめ鉄筋や足場などと一体化されており、一体化されたプレファブ型枠を門型クレーンで設置することで、橋脚の設置の段階から門型クレーンを使用し手施工を行うことができ、施工時間を短縮することができる。   In addition, the formwork for installing the pier is integrated with rebars and scaffolds in advance, and the integrated prefab formwork is installed with the portal crane, so that the portal crane can be used from the stage of the pier installation. Can be used for manual construction, and construction time can be shortened.

本発明によれば、立体交差などの橋梁を施工する方法であって、橋桁の設置から床版の設置まで同一の門型クレーンを用い、道路の工事占有範囲を極力少なくするとともに、工期の短縮が可能な立体交差の施工方法を提供することができる。   According to the present invention, a method of constructing a bridge such as a three-dimensional intersection, using the same portal crane from the installation of a bridge girder to the installation of a floor slab, reducing the construction occupation range of the road as much as possible and shortening the construction period It is possible to provide a method for constructing a three-dimensional intersection that can be

以下、本発明の実施の形態にかかる立体交差の施工方法について説明する。図1は、立体交差を施工する交差点近傍を示す概略図である、図1(a)は平面図、図1(b)は側面図である。   Hereinafter, the construction method of the three-dimensional intersection concerning embodiment of this invention is demonstrated. 1A and 1B are schematic views showing the vicinity of an intersection where a three-dimensional intersection is constructed. FIG. 1A is a plan view and FIG. 1B is a side view.

道路7と道路8は交差しており、メインである道路8に沿って立体交差が設置される。図1に示すように、立体交差の設置位置である道路8に沿って、2列のレール3が敷設される。   The road 7 and the road 8 intersect each other, and a three-dimensional intersection is installed along the main road 8. As shown in FIG. 1, two rows of rails 3 are laid along a road 8 that is an installation position of a three-dimensional intersection.

レール3上には一対の門型クレーン1が設置される。門型クレーン1a、1bは、互いに対向するように同一レール3上に設置される。門型クレーン1a、1bは、それぞれレール3に沿って移動可能である。   A pair of portal cranes 1 are installed on the rails 3. The portal cranes 1a and 1b are installed on the same rail 3 so as to face each other. The portal cranes 1a and 1b are movable along the rails 3, respectively.

道路8の門型クレーン1の走行部以外の部位(図中レール3の外側)は、門型クレーン1が移動中であっても、車両が通行することができる。したがって、道路8の門型クレーン1の幅よりも外側の車道は交通規制を行う必要がない。また、道路7は、門型クレーン1が交差点を通過する際を除き、車両が通行することができる。したがって、門型クレーン1の移動状況に応じて、多少の交通規制は必要であるが、門型クレーン1が交差点を通過した後にはただちに道路7の通行を再開できるため、交通規制を最小限に抑えることができる。   A part of the road 8 other than the traveling part of the portal crane 1 (outside of the rail 3 in the figure) can pass by the vehicle even when the portal crane 1 is moving. Therefore, it is not necessary to regulate traffic on the roadway outside the width of the portal crane 1 on the road 8. Further, the road 7 can be used by vehicles except when the portal crane 1 passes through the intersection. Therefore, some traffic regulation is necessary depending on the movement situation of the portal crane 1, but the traffic on the road 7 can be resumed immediately after the portal crane 1 passes the intersection, so that traffic regulation is minimized. Can be suppressed.

図2は門型クレーン1を示す図であり、図2(a)は正面図、図2(b)は側面図である。門型クレーン1は、主に支持脚13、車輪11、クレーン桁12、突出部14、横行レール15、ウィンチ17等から構成される。   FIG. 2 is a view showing the portal crane 1, FIG. 2 (a) is a front view, and FIG. 2 (b) is a side view. The portal crane 1 is mainly composed of support legs 13, wheels 11, crane girders 12, protrusions 14, traverse rails 15, winches 17, and the like.

一対の支持脚13が略鉛直に設けられる。支持脚13の下方には、車輪11を有する台車16が設けられる。車輪11が設けられる台車16はレール3上を図2(b)の矢印B方向に走行可能である。なお、以後の説明において、図2(b)における左側を、門型クレーン1の前方とする。支持脚13の上方は、クレーン桁12で接合される。したがって、門型クレーン1を正面から見ると、支持脚13およびクレーン桁12によって、下方が開放したコの字状の形状となる。一対の支持脚13の間隔は、後述する橋脚の幅よりもわずかに大きく、またクレーン桁12の高さが橋脚よりも十分に高いため、門型クレーン1は橋脚と干渉することなく、レール3上を移動することができる。なお、橋脚については詳細は後述する。   A pair of support legs 13 are provided substantially vertically. Below the support leg 13, a carriage 16 having wheels 11 is provided. The carriage 16 provided with the wheels 11 can travel on the rail 3 in the direction of arrow B in FIG. In the following description, the left side in FIG. The upper part of the support leg 13 is joined by a crane girder 12. Therefore, when the portal crane 1 is viewed from the front, the lower side is opened by the support leg 13 and the crane girder 12 to form a U-shape. The distance between the pair of support legs 13 is slightly larger than the width of the bridge pier, which will be described later, and the height of the crane girder 12 is sufficiently higher than the bridge pier, so that the portal crane 1 does not interfere with the pier, and the rail 3 You can move up. Details of the pier will be described later.

クレーン桁12には、門型クレーン1の前方側に突出した突出部14が設けられる。したがって、門型クレーン1を側方から見ると、支持脚13と突出部14を有するクレーン桁12とで逆L字型の形状となる。   The crane girder 12 is provided with a protruding portion 14 that protrudes forward of the portal crane 1. Therefore, when the portal crane 1 is viewed from the side, the support leg 13 and the crane girder 12 having the protruding portion 14 form an inverted L-shape.

突出部14の下方には横行レール15が設けられる。横行レール15にはウィンチ17が設置される。ウィンチ17は横行レール15に沿って、図2(a)の矢印A方向へ移動可能である。また、ウィンチ17はワイヤおよび吊り具によって対象部材を上下へ吊り上げおよび吊り降ろすことができる。この際、ウィンチ17は支持脚13よりも前方へ突出した突出部14へ設けられるため、吊下げる部材が支持脚13と干渉することはない。   A traverse rail 15 is provided below the protrusion 14. A winch 17 is installed on the transverse rail 15. The winch 17 can move in the direction of arrow A in FIG. In addition, the winch 17 can lift and lower the target member up and down with a wire and a lifting tool. At this time, since the winch 17 is provided on the protruding portion 14 protruding forward from the support leg 13, the suspended member does not interfere with the support leg 13.

次に、橋脚の設置方法について説明する。橋脚を施工するためには、橋脚用のプレファブ型枠50を設置する。図3はプレファブ型枠50を示す図であり、図3(a)は正面図、図3(b)は図3(a)のX−X線断面図である。プレファブ型枠50は、型枠51、足場53、鉄筋55等から構成される。   Next, the installation method of a pier is demonstrated. In order to construct the pier, a prefab form 50 for the pier is installed. 3A and 3B are diagrams showing the prefabricated mold 50, FIG. 3A is a front view, and FIG. 3B is a sectional view taken along line XX in FIG. The prefab mold 50 includes a mold 51, a scaffold 53, a reinforcing bar 55, and the like.

型枠51は、コンクリートを打設する際に使用される。型枠51としては、通常の型枠でよく、または埋設型枠であってもよい。型枠51の内部には、あらかじめ鉄筋55が設置されている。また、型枠51の外部には足場53が設けられる。型枠51、鉄筋53、足場55は工場等で一体化されている。なお、詳細は後述するが、鉄筋53の下端よりも型枠51の下端の方が上方に位置し、プレファブ型枠50を地面においた状態では、地面と型枠51との間に隙間54が形成される。隙間54からは型枠51内部の鉄筋55が露出している。   The formwork 51 is used when placing concrete. The formwork 51 may be a normal formwork or an embedded formwork. A reinforcing bar 55 is installed in advance inside the mold 51. A scaffold 53 is provided outside the formwork 51. The mold 51, the reinforcing bar 53, and the scaffold 55 are integrated in a factory or the like. As will be described in detail later, when the lower end of the mold 51 is positioned above the lower end of the reinforcing bar 53 and the prefab mold 50 is placed on the ground, a gap 54 is formed between the ground and the mold 51. It is formed. From the gap 54, the reinforcing bar 55 inside the mold 51 is exposed.

図4はプレファブ型枠50を門型クレーン1で吊上げた状態を示す図であり、図4(a)は正面図、図4(b)は側面図である。一体化されたプレファブ型枠50は、吊り具57を用いて、門型クレーン1のウィンチ17により吊り上げられる。図4(a)に示すように、門型クレーン1はプレファブ型枠50(およびこれにより形成される橋脚)よりも幅(支持脚の間隔)がやや大きい。このため、プレファブ型枠50は支持脚13の間で吊上げられる。   4A and 4B are views showing a state in which the prefabricated formwork 50 is lifted by the portal crane 1, in which FIG. 4A is a front view and FIG. 4B is a side view. The integrated prefabricated formwork 50 is lifted by the winch 17 of the portal crane 1 using a lifting tool 57. As shown in FIG. 4A, the portal crane 1 is slightly larger in width (interval between support legs) than the prefabricated form frame 50 (and the pier formed thereby). For this reason, the prefabricated formwork 50 is lifted between the support legs 13.

図5は、プレファブ桁50の設置状況を示す図であり、図5(a)は交差点近傍の平面図、図5(b)は側面図である。あらかじめレール3の間に設置された部材置き場にはプレファブ型枠50が仮置きされる。プレファブ型枠50は、門型クレーン1で吊上げられて運搬され、所定の場所に設置される。この際、プレファブ型枠50は、門型クレーン1a、1bそれぞれによって、立体交差の中央(道路7との交差部近傍)から端部(立体交差のアプローチ部近傍)に向かって順次設置される。   FIGS. 5A and 5B are diagrams showing an installation state of the prefabricated girder 50, in which FIG. 5A is a plan view near an intersection and FIG. 5B is a side view. The prefabricated formwork 50 is temporarily placed in a member place previously installed between the rails 3. The prefabricated formwork 50 is lifted and transported by the portal crane 1 and installed at a predetermined location. At this time, the prefab form 50 is sequentially installed from the center of the three-dimensional intersection (near the intersection with the road 7) to the end (near the three-dimensional intersection approach) by the gate cranes 1a and 1b.

たとえば、門型クレーン1aは、プレファブ型枠50aを道路7と道路8との交差部近傍に設置する。次に、仮置きされているプレファブ型枠50bを門型クレーン1bで運搬し、プレファブ型枠50aの手前側(図中向かって左側)に設置する。プレファブ型枠50を手前側から設置すると、設置されたプレファブ型枠を超えて、プレファブ型枠を運搬する必要があり、門型クレーンの揚程が足りなくなるためである。   For example, the portal crane 1 a installs the prefabricated formwork 50 a in the vicinity of the intersection between the road 7 and the road 8. Next, the temporarily placed prefabricated formwork 50b is transported by the portal crane 1b and installed on the front side (left side in the figure) of the prefabricated formwork 50a. If the prefabricated formwork 50 is installed from the front side, it is necessary to transport the prefabricated formwork beyond the installed prefabricated formwork, and the lift of the portal crane becomes insufficient.

同様に、門型クレーン1bは、プレファブ型枠50c、50dの順に所定の位置に設置する。なお、プレファブ型枠50の高さは、設置される橋脚の高さに対応するため、立体交差の中央近傍に設置されるプレファブ型枠50a、50cの高さは、立体交差の端部近傍に設けられるプレファブ型枠50b、50dの高さよりも高い。   Similarly, the portal crane 1b is installed at a predetermined position in the order of the prefab formwork 50c, 50d. In addition, since the height of the prefabricated formwork 50 corresponds to the height of the installed pier, the height of the prefabricated formwork 50a, 50c installed near the center of the three-dimensional intersection is near the end of the three-dimensional intersection. It is higher than the height of the prefabricated molds 50b and 50d provided.

プレファブ型枠50の設置位置には、図示を省略したフーチングがあらかじめ設けられる。プレファブ型枠50とフーチングとの接合は、例えば以下のように行われる。前述の通り、鉄筋55は型枠51の下端より突出しており、フーチング上にプレファブ型枠50が設置された状態で、型枠51下端とフーチング表面との間には隙間54が形成される。隙間54には、鉄筋55が露出している。フーチングには鉄筋があらかじめ埋設され、フーチング表面より突出している。   A footing (not shown) is provided in advance at the installation position of the prefabricated formwork 50. For example, the prefabricated mold 50 and the footing are joined as follows. As described above, the reinforcing bar 55 protrudes from the lower end of the mold 51, and a gap 54 is formed between the lower end of the mold 51 and the footing surface in a state where the prefab mold 50 is installed on the footing. A reinforcing bar 55 is exposed in the gap 54. Reinforcing bars are embedded in the footing in advance and protrude from the footing surface.

フーチング表面に突出する鉄筋は、プレファブ型枠50の鉄筋55と接合される。鉄筋同士は、例えばラップ継手、機械式継手、溶接等の公知の方法で接合される。接合作業は、隙間54より行うことができる。鉄筋同士の接合が完了した後、型枠51下端とフーチング表面との隙間54を型枠部材で覆い、隙間54を埋める。鉄筋同士の接合によって、プレファブ型枠50がフーチング上へ固定される。   The reinforcing bars protruding from the footing surface are joined to the reinforcing bars 55 of the prefabricated mold 50. The reinforcing bars are joined by a known method such as a lap joint, a mechanical joint, or welding. The joining operation can be performed from the gap 54. After the joining of the reinforcing bars is completed, the gap 54 between the lower end of the mold 51 and the footing surface is covered with the mold member, and the gap 54 is filled. The prefabricated formwork 50 is fixed onto the footing by joining the reinforcing bars.

プレファブ型枠50の設置が完了した後、それぞれの型枠内へコンクリートを打設する。コンクリートの打設には、門型クレーン1を使用してもよく、または、プレファブ型枠50側方の道路8から別途打設作業を行ってもよい。型枠51下端とフーチング表面との隙間54はあらかじめ埋められているので、型枠51内へ打設されたコンクリートが型枠51下端より漏れだすことはない。   After the installation of the prefabricated formwork 50 is completed, concrete is placed in each formwork. For placing concrete, the portal crane 1 may be used, or a separate placing work may be performed from the road 8 on the side of the prefabricated formwork 50. Since the gap 54 between the lower end of the mold 51 and the footing surface is filled in advance, the concrete cast into the mold 51 does not leak from the lower end of the mold 51.

図6は、プレファブ型枠50を用いて橋脚5が設けられた状態を示す図で、図6(a)は交差点近傍の平面図、図6(b)は側面図である。前述の通り、プレファブ型枠50の幅は門型クレーン1の支持脚間の幅よりも小さい。したがって、プレファブ型枠50によって設けられた橋脚5もまた、門型クレーン1の支持脚間の幅よりも小さい。このため、門型クレーン1は橋脚5をまたいで移動することができる。   FIG. 6 is a view showing a state where the pier 5 is provided using the prefabricated formwork 50, FIG. 6 (a) is a plan view near the intersection, and FIG. 6 (b) is a side view. As described above, the width of the prefabricated formwork 50 is smaller than the width between the support legs of the portal crane 1. Therefore, the pier 5 provided by the prefabricated formwork 50 is also smaller than the width between the support legs of the portal crane 1. For this reason, the portal crane 1 can move across the pier 5.

また、門型クレーン1は橋脚5よりも高さが高く、橋脚5上へ部材を吊下げることができる。なお、レール3の間であって、橋脚5から離れた位置には部材置き場が設けられ、図6に示すように橋桁9等が仮置きされている。橋桁9は例えば繊維補強コンクリート製である。   The portal crane 1 is higher than the pier 5 and can suspend members on the pier 5. In addition, a member place is provided between the rails 3 and away from the pier 5, and a bridge girder 9 and the like are temporarily placed as shown in FIG. The bridge girder 9 is made of, for example, fiber reinforced concrete.

次に、立体交差の施工方法を説明する。まず、図7(a)に示すように門型クレーン1a、1bとで橋桁9を共吊りする。橋桁9を吊上げるには、門型クレーン1a、1bを予め橋桁9が仮置きされた部位近傍へ移動させ、それぞれのウィンチ17を同期させて、橋桁9を吊上げる(図7(a)の矢印C方向)。門型クレーン1a、1bは互いにそれぞれの前方(突出部14が突出する方向)を対向させているため、それぞれのウィンチ17が向かい合うように橋桁9が吊上げられる。なお、橋桁9は橋脚5よりも高い位置に吊り上げられる。   Next, a construction method for a three-dimensional intersection will be described. First, as shown in FIG. 7A, the bridge girder 9 is suspended together with the portal cranes 1a and 1b. In order to lift the bridge girder 9, the gate cranes 1a and 1b are moved to the vicinity of the part where the bridge girder 9 is temporarily placed, and the winch 17 is synchronized to lift the bridge girder 9 (see FIG. 7A). Arrow C direction). Since the portal cranes 1a and 1b face each other forward (in the direction in which the protruding portion 14 protrudes), the bridge girder 9 is lifted so that the winches 17 face each other. The bridge girder 9 is lifted to a position higher than the pier 5.

次に、門型クレーン1a、1bの移動速度を同期させて、図7(a)の矢印D方向へ走行させる。この際、門型クレーン1は橋脚5と干渉することがない。橋桁9が設置位置まで移動したら、門型クレーン1の走行を停止する。次に、図7(b)に示すように、門型クレーン1a、1bそれぞれのウィンチ17を同期させて、橋桁9を橋脚5上に設置する(図中矢印E方向)。   Next, the traveling speeds of the portal cranes 1a and 1b are synchronized to travel in the direction of arrow D in FIG. At this time, the portal crane 1 does not interfere with the pier 5. When the bridge girder 9 moves to the installation position, the traveling of the portal crane 1 is stopped. Next, as shown in FIG. 7B, the bridge girder 9 is installed on the pier 5 (in the direction of arrow E in the figure) by synchronizing the winches 17 of the portal cranes 1a and 1b.

以上の工程を繰り返し、橋脚5上へ橋桁9を設置する。図8は、橋脚5上への橋桁9の設置を終えた状態を示す図であり、図8(a)は平面図、図8(b)は側面図である。橋桁9は横方向に複数本が設置され、互いに接合される。また、橋桁9の長手方向に(複数の橋脚5をまたぐように)複数本が設置され、それぞれの橋桁9が接合される。前述の通り、長さが長い橋桁9を橋脚5上へ設置する際に、一対の門型クレーン1a、1bを用いるため、吊上げおよび設置が容易である。   The above steps are repeated to install the bridge girder 9 on the pier 5. 8A and 8B are views showing a state where the installation of the bridge girder 9 on the pier 5 is finished, FIG. 8A is a plan view, and FIG. 8B is a side view. A plurality of bridge girders 9 are installed in the horizontal direction and joined together. In addition, a plurality of bridge girder 9 are installed in the longitudinal direction of bridge girder 9 (so as to straddle a plurality of bridge piers 5), and each bridge girder 9 is joined. As described above, when the bridge girder 9 having a long length is installed on the pier 5, the pair of portal cranes 1 a and 1 b is used, so that lifting and installation are easy.

次に、床版19を運搬する。図9は床版19を門型クレーン1によって運搬する状態を示す図であり、図9(a)は平面図、図9(b)は側面図である。なお、以後の工程においては、門型クレーン1a、1bは、設置された橋桁9の長手方向の反対側よりそれぞれ単独で同一作業を行う。したがって、一方の側の工程のみを図示する。床版19は、側壁部を有するコの字状の部材で、例えばプレキャスト床版である。設置予定の橋桁9の手前にはターンテーブル21が設置される。   Next, the floor slab 19 is transported. FIG. 9 is a view showing a state in which the floor slab 19 is transported by the portal crane 1, FIG. 9 (a) is a plan view, and FIG. 9 (b) is a side view. In the subsequent steps, the portal cranes 1a and 1b perform the same operation independently from the opposite side of the longitudinal direction of the installed bridge girder 9, respectively. Therefore, only the process on one side is illustrated. The floor slab 19 is a U-shaped member having a side wall, and is, for example, a precast floor slab. A turntable 21 is installed in front of the bridge girder 9 to be installed.

まず、あらかじめ部材置き場等に仮置きされた床版19を門型クレーン1で吊上げ、ターンテーブル21方向(図中矢印F方向)へ運搬する。床版19は門型クレーン1の支持脚13間の間隔よりも長さが長い。このため、床板19の幅方向(長手方向)をレール3に対して垂直に置いておくと、床板19によってレール3が覆われ、門型クレーン1は床板19を超えて移動することができない。したがって、床版19の幅方向(長手方向)を門型クレーン1の移動方向に平行に向け、レール3の間に仮置きしておき、床版19は一対の支持脚13の間で吊上げられる。   First, the floor slab 19 temporarily placed in a member storage place or the like is lifted by the portal crane 1 and transported in the direction of the turntable 21 (in the direction of arrow F in the figure). The floor slab 19 is longer than the distance between the support legs 13 of the portal crane 1. For this reason, when the width direction (longitudinal direction) of the floor board 19 is placed perpendicular to the rail 3, the rail 3 is covered by the floor board 19, and the portal crane 1 cannot move beyond the floor board 19. Therefore, the floor slab 19 is temporarily placed between the rails 3 with the width direction (longitudinal direction) of the floor slab 19 parallel to the moving direction of the portal crane 1, and the floor slab 19 is lifted between the pair of support legs 13. .

次に、図10に示すように床版19をターンテーブル21上へ載置する。図10はターンテーブル21上へ床板19が置かれた状態を示す図で、図10(a)は平面図、図10(b)は側面図、図10(c)は正面図である。   Next, the floor slab 19 is placed on the turntable 21 as shown in FIG. FIG. 10 is a diagram showing a state where the floor board 19 is placed on the turntable 21, FIG. 10 (a) is a plan view, FIG. 10 (b) is a side view, and FIG. 10 (c) is a front view.

図10(c)に示すように、床版19をターンテーブル21上へ置いた状態では、床版19の幅方向が門型クレーン1の移動方向に向いているため、床版19と門型クレーン1とが干渉することはない。門型クレーン1は床版19をターンテーブル21上へ載置した後、やや後方へ退避し、ターンテーブル21上で床版19が回転する際に干渉することを避ける。   As shown in FIG. 10 (c), when the floor slab 19 is placed on the turntable 21, the width direction of the floor slab 19 faces the moving direction of the portal crane 1. There is no interference with the crane 1. After the floor slab 19 is placed on the turntable 21, the portal crane 1 is retracted slightly rearward to avoid interference when the floor slab 19 rotates on the turntable 21.

次に、図11(a)に示すように、ターンテーブル21を90°回転させ、床版19を回転させる(図中矢印G方向)。床版19の幅方向が門型クレーン1の移動方向に対して略垂直となった状態で、門型クレーン1を前進させ(図11(b)中矢印H方向)、ウィンチ17が床版19上に位置し、床版19を吊上げ可能な位置まで移動させる。なお、図11(b)、図11(c)に示すように、門型クレーン1と床版19とは干渉することはない。また、ウィンチ17は突出部14に設けられるため、床版19を吊上げる際にも支持脚13と床版19とが干渉することがない。   Next, as shown to Fig.11 (a), the turntable 21 is rotated 90 degrees and the floor slab 19 is rotated (arrow G direction in the figure). In a state where the width direction of the floor slab 19 is substantially perpendicular to the moving direction of the portal crane 1, the portal crane 1 is advanced (in the direction of arrow H in FIG. 11B), and the winch 17 is moved to the floor slab 19. It is located above and the floor slab 19 is moved to a position where it can be lifted. In addition, as shown in FIG.11 (b) and FIG.11 (c), the portal crane 1 and the floor slab 19 do not interfere. Moreover, since the winch 17 is provided in the protrusion part 14, when the floor slab 19 is lifted, the support leg 13 and the floor slab 19 do not interfere.

次に、図12(a)に示すように、床版19を吊上げた状態で、床版19を設置部位まで移動する(図中矢印I方向)。門型クレーン1が設置部位まで移動したら、門型クレーン1の走行を停止し、図12(b)に示すように、床版19を橋桁9上へ設置する(図中矢印J方向)。   Next, as shown in FIG. 12A, in the state where the floor slab 19 is lifted, the floor slab 19 is moved to the installation site (in the direction of arrow I in the figure). When the portal crane 1 moves to the installation site, the traveling of the portal crane 1 is stopped, and the floor slab 19 is installed on the bridge girder 9 as shown in FIG.

図12(c)は、床版19が橋桁9上へ設置された状態を示す図である。図12(c)に示すように、床版19は幅方向を橋桁9の長手方向に対して垂直な方向に向けて、橋桁9上に設置される。すなわち、床版19の幅方向は橋桁9の幅方向へ張り出して架設される。   FIG. 12C is a diagram showing a state in which the floor slab 19 is installed on the bridge girder 9. As shown in FIG. 12 (c), the floor slab 19 is installed on the bridge girder 9 with its width direction oriented in a direction perpendicular to the longitudinal direction of the bridge girder 9. That is, the width direction of the floor slab 19 extends over the width direction of the bridge girder 9.

以上の工程を繰り返し、床版19を橋桁9上の全面へ設置し、床版19同士を接合する。図13は床版19の設置が完了した状態を示す図である。なお、前述の通り、一対の門型クレーン1により、橋桁9の長手方向両側から同時に床版19を設置する。床版19の設置が完了すれば、残部を盛土等で施工して立体交差の施工が完了する。   The above steps are repeated, the floor slab 19 is installed on the entire surface of the bridge girder 9, and the floor slabs 19 are joined together. FIG. 13 is a diagram showing a state in which the installation of the floor slab 19 is completed. As described above, the floor slab 19 is simultaneously installed from both sides of the bridge girder 9 in the longitudinal direction by the pair of portal cranes 1. When the installation of the floor slab 19 is completed, the remaining part is constructed with embankment or the like, and the construction of the three-dimensional intersection is completed.

以上説明したように、本発明の実施形態にかかる立体交差の施工方法によれば、一対の門型クレーン1によって、橋脚5の設置、橋桁9の架設および床版19の架設を行うことができる。このため、短納期に立体交差を施工することができる。特に、門型クレーン1の走行時のみ道路7等の規制をおこなえば良いため、立体交差に伴う交通規制を最小限に抑えることができる。   As described above, according to the construction method of the three-dimensional intersection according to the embodiment of the present invention, it is possible to install the pier 5, the bridge girder 9, and the floor slab 19 by the pair of portal cranes 1. . For this reason, it is possible to construct a three-dimensional intersection in a short delivery time. In particular, since it is only necessary to regulate the road 7 and the like only when the portal crane 1 is traveling, traffic regulation associated with a three-dimensional intersection can be minimized.

また、門型クレーン1は、ウィンチ17が突出部14に設けられるため、門型クレーン1よりも幅の大きな床版19を吊上げて運搬することが可能である。また、ターンテーブル21を用いることで、門型クレーン1よりも幅の大きな床版19を縦方向に向けて運搬し、ターンテーブル21上で床版19を横向きに回転させて再度吊り上げることで、床版置き場から容易に床版19を運搬することができるとともに、橋桁9上へも床版19を横向きに設置することができる。   Moreover, since the winch 17 is provided in the protrusion part 14, the portal crane 1 can lift and convey the floor slab 19 wider than the portal crane 1. FIG. Further, by using the turntable 21, the floor slab 19 having a width larger than that of the portal crane 1 is transported in the vertical direction, and the floor slab 19 is rotated sideways on the turntable 21 and lifted again. The floor slab 19 can be easily transported from the floor slab storage place, and the floor slab 19 can also be installed sideways on the bridge girder 9.

また、門型クレーン1の支持脚13の間隔は、橋脚5を避けることができるだけの間隔を有すればよいため、門型クレーン1の走行スペースを小さくすることができ、門型クレーン1の走行スペース以外の車線の交通規制を行う必要がない。したがって、交通規制の必要な車線を最小限に抑えることができる。   Moreover, since the space | interval of the support leg 13 of the portal crane 1 should just have the space | interval which can avoid the bridge pier 5, the traveling space of the portal crane 1 can be made small, and traveling of the portal crane 1 is possible. There is no need to regulate traffic in lanes other than space. Therefore, it is possible to minimize lanes that require traffic regulation.

また、プレファブ型枠50を用いれば型枠51、足場53、鉄筋55が一体化されているため、設置が容易であり、また、プレファブ型枠50の設置に門型クレーン1を用いることができるため、施工工期を短縮することができる。   Moreover, if the prefabricated formwork 50 is used, the formwork 51, the scaffold 53, and the reinforcing bar 55 are integrated, so that the installation is easy, and the portal crane 1 can be used to install the prefabricated formwork 50. Therefore, the construction period can be shortened.

次に、本発明の第2の実施の形態について説明する。なお、以下の実施の形態において、図1〜図13に示す構成要素と同一の機能を果たす構成要素には、図1〜図13と同一番号を付し重複した説明を省略する。図14(a)は第2の実施の形態にかかる床版33および吊り具31を示す図である。第2の実施の形態では、第1の実施の形態に対し、床板の形態が異なる。すなわち、床板33は、床板19と形状のみが異なり、一対の略L字状の部材である。   Next, a second embodiment of the present invention will be described. In the following embodiments, components having the same functions as those shown in FIGS. 1 to 13 are assigned the same reference numerals as in FIGS. FIG. 14A is a diagram showing a floor slab 33 and a hanging tool 31 according to the second embodiment. In 2nd Embodiment, the form of a floor board differs from 1st Embodiment. That is, the floor plate 33 is different from the floor plate 19 only in shape and is a pair of substantially L-shaped members.

床版33の形状は、概ね、床版19の両端近傍の形状と同一である。したがって、床版19の床部の一部を切り取り、両端のみを残したような形状である。このため、吊り具31に接合された状態の一対の床版33の幅は、床版19と略同一幅である。床版33の下方端部には、段部34が設けられる。床版33の上方の端部は、ボルト37により吊り具31と接合される。   The shape of the floor slab 33 is generally the same as the shape in the vicinity of both ends of the floor slab 19. Therefore, it is a shape in which a part of the floor portion of the floor slab 19 is cut out and only both ends are left. For this reason, the width of the pair of floor slabs 33 in a state joined to the hanging tool 31 is substantially the same width as the floor slab 19. A step 34 is provided at the lower end of the floor slab 33. The upper end of the floor slab 33 is joined to the hanging tool 31 by a bolt 37.

吊り具31の上方の両側方にはアーム35が設けられる。床版33と吊り具31とはアーム35の先端近傍で接合される。なお、吊り具31の高さは、床版33の高さよりもやや高い。したがって、床版33が接合された状態の吊り具31を地面等に置いた際に、吊り具31によって自立する。この場合、床版33はアーム35によって吊りさげられた状態となる。また、ボルト37を緩めることで、床版33を下方へ移動させることができ、ボルト37を抜き去ると床版33は吊り具31から離脱する。   Arms 35 are provided on both sides above the hanger 31. The floor slab 33 and the hanging tool 31 are joined in the vicinity of the tip of the arm 35. In addition, the height of the hanging tool 31 is slightly higher than the height of the floor slab 33. Therefore, when the hanger 31 with the floor slab 33 joined is placed on the ground or the like, the hanger 31 is self-supporting. In this case, the floor slab 33 is suspended by the arm 35. Further, by loosening the bolt 37, the floor slab 33 can be moved downward. When the bolt 37 is removed, the floor slab 33 is detached from the hanger 31.

図14(b)は、第2の実施の形態に用いられる門型クレーン30を示す図である。門型クレーン30は門型クレーン1に対して、ウィンチ17が2段に設けられる点で異なる。門型クレーン30の突出部14には、さらに前方側へ突出する突出部32が設けられる。突出部14下方にはウィンチ17aが設けられ、突出部32下方へはウィンチ17bが設けられる。したがって、門型クレーン30は、同一方向(前方)に、支持脚13から距離を変えてウィンチ17a、17bが2段に設けられる。   FIG. 14B is a diagram illustrating a portal crane 30 used in the second embodiment. The portal crane 30 differs from the portal crane 1 in that the winches 17 are provided in two stages. The protrusion 14 of the portal crane 30 is provided with a protrusion 32 that protrudes further forward. A winch 17a is provided below the protrusion 14 and a winch 17b is provided below the protrusion 32. Accordingly, the portal crane 30 is provided with two winches 17a and 17b in the same direction (forward) by changing the distance from the support leg 13.

次に、第2の実施の形態にかかる立体交差の施工手順について述べる。図15は施工手順を示す図である。   Next, the construction procedure of the solid intersection according to the second embodiment will be described. FIG. 15 is a diagram showing a construction procedure.

まず、第1の実施の形態と同一の手順で橋桁9を施工後、吊り具31aへ接合された床版33aをターンテーブル21上へ載置する。その後、図15(a)に示すように、門型クレーン30を後方へ退避させ、ターンテーブル21を回転(図中矢印K)させる。   First, after the bridge girder 9 is constructed in the same procedure as in the first embodiment, the floor slab 33a joined to the hanging tool 31a is placed on the turntable 21. Then, as shown to Fig.15 (a), the portal crane 30 is retracted back, and the turntable 21 is rotated (arrow K in the figure).

次に、図15(b)に示すように、床版33の幅方向(長手方向)を門型クレーン30の移動方向に垂直な方向に向けた状態で、支持脚13に近い側のウィンチ17aによって床版33a(吊り具31a)を吊上げる(図中矢印L方向)。   Next, as shown in FIG. 15B, the winch 17 a on the side close to the support leg 13 in the state where the width direction (longitudinal direction) of the floor slab 33 is directed to the direction perpendicular to the moving direction of the portal crane 30. To lift the floor slab 33a (hanging tool 31a) (in the direction of arrow L in the figure).

次に、図15(c)に示すように、門型クレーン30を床版33aの設置場所方向へ移動させ(図中矢印M方向)、設置場所まで移動後、床版33aを橋桁9上へ設置する(図中矢印N方向)。   Next, as shown in FIG. 15 (c), the portal crane 30 is moved in the direction of the installation location of the floor slab 33 a (in the direction of arrow M in the figure), and after moving to the installation location, the floor slab 33 a is moved onto the bridge girder 9. Install (in the direction of arrow N in the figure).

図15(d)は設置された床版33aの正面断面図である。床版33aは併設された橋桁9の端部近傍に接合される。端部に設けられる橋桁9には、あらかじめ床版33aの下方に設けられた段部34に対応する段差が設けられており、段部34が橋桁9の当該段差と組み合わされて接合される。   FIG. 15D is a front sectional view of the installed floor slab 33a. The floor slab 33a is joined in the vicinity of the end of the bridge girder 9 provided. The bridge girder 9 provided at the end is provided with a step corresponding to the step 34 provided in advance below the floor slab 33 a, and the step 34 is combined and joined with the step of the bridge girder 9.

なお、吊り具31aが橋桁9上に設置されたのち、ボルト37を緩めることで床版33aを橋桁9へ接触させることができる。橋桁9と床版33aとが接合されたのち、ボルト37が抜き取られ、床版33aと吊り具31aとが離脱する。床版33aは一対のL字部材であるため、床版33aが取り付けられた状態では、一対の床版33aの間には橋桁9の上面が露出する。   After the hanging tool 31a is installed on the bridge girder 9, the floor slab 33a can be brought into contact with the bridge girder 9 by loosening the bolt 37. After the bridge girder 9 and the floor slab 33a are joined, the bolt 37 is pulled out, and the floor slab 33a and the hanging tool 31a are detached. Since the floor slab 33a is a pair of L-shaped members, the upper surface of the bridge girder 9 is exposed between the pair of floor slabs 33a when the floor slab 33a is attached.

次に、図16(a)に示すように、同様の作業を繰り返し、床版33bが接合された吊り具33bを門型クレーン30で吊上げ(図中矢印O方向)、設置部方向へ走行させる(図中矢印P方向)。   Next, as shown in FIG. 16A, the same operation is repeated, and the lifting tool 33b to which the floor slab 33b is joined is lifted by the portal crane 30 (in the direction of arrow O in the drawing) and travels toward the installation portion. (Arrow P direction in the figure).

次に、図16(b)に示すように、先に設置した床版33aの手前側に床版33bを設置する(図中矢印P方向)。次に、すでに設置が完了し、床版33aから離脱した吊り具31aを、床版33bを吊下げていたウィンチ17aよりもさらに前方に突出した位置に設けられたウィンチ17bによって吊り上げる(図中矢印Q方向)。以上により、吊り具31aの撤去が完了する。なお、床版33bと橋桁9との接合作業の間には、門型クレーン30はさらに次に設置する床版33の運搬を行うことができる。   Next, as shown in FIG. 16B, the floor slab 33b is installed on the front side of the previously installed floor slab 33a (in the direction of arrow P in the figure). Next, the lifting tool 31a that has already been installed and detached from the floor slab 33a is lifted by a winch 17b provided at a position protruding further forward than the winch 17a from which the floor slab 33b is suspended (arrow in the figure). Q direction). Thus, the removal of the hanging tool 31a is completed. In addition, during the joining operation | work of the floor slab 33b and the bridge girder 9, the portal crane 30 can carry the floor slab 33 installed next.

第2の実施形態にかかる立体交差の施工方法によれば、第1の実施の形態にかかる立体交差の施工方法と同様の効果を得ることができる。また、床版33が一対のL字状部材であり、橋桁9の端部に設置可能であるため、床版33を橋桁9上へ設置した際に、床版33間に橋桁9の上面が露出し、橋桁9の上面と床板33とで、コの字状の床板19と同様の形態を得ることができ、このため床版のコンクリートを削減することができる。また、L字状部材を接合する吊り具31を用いるため、L字状部材の設置が容易であり、また、吊り具31は繰り返し使用することができるため経済的である。   According to the construction method of the solid intersection according to the second embodiment, the same effect as the construction method of the solid intersection according to the first embodiment can be obtained. Since the floor slab 33 is a pair of L-shaped members and can be installed at the end of the bridge girder 9, when the floor slab 33 is installed on the bridge girder 9, the upper surface of the bridge girder 9 is between the floor slabs 33. Exposed and the top surface of the bridge girder 9 and the floor board 33 can obtain the same form as the U-shaped floor board 19, and therefore, the concrete of the floor slab can be reduced. Moreover, since the hanging tool 31 which joins an L-shaped member is used, the installation of the L-shaped member is easy, and the hanging tool 31 can be used repeatedly and is economical.

また、門型クレーン30には2段階に突出したウィンチ17a、17bを設けることで、支持脚13に近い側のウィンチ17aで設置予定の床版33bおよび吊り具31bを吊上げ、床版33bを橋桁9へ設置後、ウィンチ17bで前回設置した床版33aの吊り具31aを吊上げ、撤去・回収することができる。このため、床版33を橋桁9に設置後、橋桁9上では橋桁9と床版33との接合作業を行いながら、次に設置する床版33を門型クレーン30で橋桁9上へ運搬することができ、作業効率が高い。   Further, the portal crane 30 is provided with winches 17a and 17b protruding in two stages, so that the floor slab 33b and the lifting tool 31b to be installed are lifted by the winch 17a near the support leg 13, and the floor slab 33b is mounted on the bridge girder 9, the hanging tool 31a of the floor slab 33a previously installed by the winch 17b can be lifted, removed and collected. For this reason, after the floor slab 33 is installed on the bridge girder 9, while the bridge girder 9 and the floor slab 33 are joined on the bridge girder 9, the next installed floor slab 33 is transported onto the bridge girder 9 by the portal crane 30. Can work with high efficiency.

次に、本発明の第3の実施の形態について説明する。図17は第3の実施の形態にかかる吊り具41等を示す図である。第3の実施の形態では、第2の実施の形態に対し、さらに吊り具の構造が異なる。すなわち、吊り具41は上方の両側方にアーム43が設けられ、アーム43の先端にボルト37によって床板33が設けられる。アーム43は伸縮が可能であり、吊り具41の幅を変化させることができる。   Next, a third embodiment of the present invention will be described. FIG. 17 is a diagram illustrating a hanging tool 41 and the like according to the third embodiment. In the third embodiment, the structure of the lifting tool is further different from that of the second embodiment. That is, the hanger 41 is provided with arms 43 on both upper sides, and the floor plate 33 is provided at the tip of the arm 43 with the bolts 37. The arm 43 can be expanded and contracted, and the width of the hanger 41 can be changed.

図17(a)は、門型クレーン30で床版33が両端に接合された吊り具41を運搬している状態を示す正面図である。吊り具41は図中矢印S方向へ伸縮が可能である。門型クレーン30で吊り具41を吊上げる際には、あらかじめ吊り具41の幅を縮めておく。   FIG. 17A is a front view showing a state in which a suspension 41 having a floor slab 33 bonded to both ends is being transported by the portal crane 30. The hanger 41 can be expanded and contracted in the direction of arrow S in the figure. When lifting the lifting tool 41 with the portal crane 30, the width of the lifting tool 41 is reduced in advance.

吊り具41が最も縮められた状態では、両端に接合された床版33の幅は、支持脚13の間隔よりも狭くなる。したがって、吊り具41の幅方向を門型クレーン30の移動方向に対して垂直な方向に向けて吊上げる場合であっても、門型クレーン30はターンテーブル等を用いずに通常の方法で吊上げることができる。   In the state where the hanging tool 41 is most contracted, the width of the floor slab 33 joined to both ends is narrower than the interval between the support legs 13. Therefore, even when the lifting tool 41 is lifted in the direction perpendicular to the moving direction of the portal crane 30, the portal crane 30 is suspended by a normal method without using a turntable or the like. Can be raised.

本実施の形態においては、ターンテーブル21に代えて伸縮架台45を用いる。伸縮架台45は、レール3の間に設けられ、レール3に略垂直な方向に伸縮が可能である。伸縮架台45を縮めた状態では、門型クレーン30の支持脚13間よりも幅が狭くなるため、門型クレーン30は伸縮架台45をまたいで走行することができる。   In the present embodiment, an extendable frame 45 is used instead of the turntable 21. The telescopic mount 45 is provided between the rails 3 and can be expanded and contracted in a direction substantially perpendicular to the rails 3. In a state where the telescopic mount 45 is contracted, the width becomes narrower than between the support legs 13 of the portal crane 30, so that the portal crane 30 can travel across the extendable mount 45.

まず、図17(a)に示すように、吊り具41(床版33)を伸縮架台の上に載せる(図中矢印R方向)。伸縮架台45および吊り具41はいずれも幅が縮められた状態である。伸縮架台45の床版33が置かれる部位にはジャッキ47が設けられる。ジャッキ47は上下方向に伸縮可能である。   First, as shown in FIG. 17A, the hanger 41 (floor slab 33) is placed on the telescopic frame (in the direction of arrow R in the figure). The telescopic mount 45 and the hanging tool 41 are both in a state where the width is reduced. A jack 47 is provided at a portion where the floor slab 33 of the telescopic mount 45 is placed. The jack 47 can extend and contract in the vertical direction.

吊り具41を伸縮架台45に設置後、ジャッキ47上昇させて床版33の重量を受ける。次に、ジャッキ47を上昇させた状態で、図17(b)に示すように、伸縮架台45を伸長する(図中矢印T方向)。伸縮架台45上に載せられた吊り具41は、伸縮架台45の伸長動作に伴い伸長し(図中矢印U方向)、床版33同士の間隔が広げられる。なお、ジャッキ47および伸縮架台45の動作には、例えば油圧シリンダ等が使用できる。   After installing the hanger 41 on the telescopic mount 45, the jack 47 is raised to receive the weight of the floor slab 33. Next, with the jack 47 raised, as shown in FIG. 17B, the telescopic mount 45 is extended (in the direction of arrow T in the figure). The hanger 41 placed on the telescopic gantry 45 extends (in the direction of arrow U in the figure) with the extension operation of the telescopic gantry 45, and the interval between the floor slabs 33 is widened. For example, a hydraulic cylinder or the like can be used for the operation of the jack 47 and the telescopic mount 45.

吊り具41の幅が伸張された状態の床版33同士の間隔は、橋桁9上に設置される際の床版33間隔と一致する。したがって、床版33の幅は支持脚13間隔よりも広くなる。   The interval between the floor slabs 33 in a state where the width of the lifting tool 41 is extended coincides with the interval between the floor slabs 33 when installed on the bridge girder 9. Therefore, the width of the floor slab 33 is wider than the interval between the support legs 13.

次に、図17(c)に示すように、幅が伸張された吊り具41(床版33)を吊上げる(図中矢印V方向)。同時に、ジャッキ47を縮めるとともに伸縮架台45の幅を縮める(図中矢印W方向)。伸縮架台45が縮められると、門型クレーン30は伸縮架台45を超えて走行することができる。したがって、橋桁9へ床版33を設置することができる。   Next, as shown in FIG. 17 (c), the lifting tool 41 (floor slab 33) having an extended width is lifted (in the direction of arrow V in the figure). At the same time, the jack 47 is contracted and the width of the telescopic mount 45 is contracted (in the direction of arrow W in the figure). When the telescopic gantry 45 is contracted, the portal crane 30 can travel beyond the telescopic gantry 45. Therefore, the floor slab 33 can be installed on the bridge girder 9.

第3の実施の形態にかかる立体交差の施工方法によれば、第1の実施の形態にかかる立体交差の施工方法と同様の効果を得ることができる。また、吊り具41の幅が伸縮可能であり、幅を縮めた状態では門型クレーン30の支持脚13の間隔よりも小さいため、床版33が接合された吊り具41を回転等させる必要がない。また、吊り具41を縮めた状態にしておけば、設置前の床版33の置き場の面積を小さくすることができるため、より狭い作業エリアでも作業を行うことができる。   According to the construction method of the three-dimensional intersection according to the third embodiment, the same effect as the construction method of the three-dimensional intersection according to the first embodiment can be obtained. Moreover, since the width | variety of the hanger 41 can be expanded-contracted and it is smaller than the space | interval of the support leg 13 of the portal crane 30 in the state where the width | variety was shrunk, it is necessary to rotate the hanger 41 with which the floor slab 33 was joined. Absent. In addition, if the hanger 41 is in a contracted state, the area of the storage place for the floor slab 33 before installation can be reduced, so that the work can be performed even in a narrower work area.

以上、添付図を参照しながら、本発明の実施の形態を説明したが、本発明の技術的範囲は、前述した実施の形態に左右されない。当業者であれば、特許請求の範囲に記載された技術的思想の範疇内において各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。   As mentioned above, although embodiment of this invention was described referring an accompanying drawing, the technical scope of this invention is not influenced by embodiment mentioned above. It is obvious for those skilled in the art that various modifications or modifications can be conceived within the scope of the technical idea described in the claims, and these are naturally within the technical scope of the present invention. It is understood that it belongs.

立体交差を施工する交差点近傍にレール3を設置し、レール3上に一対の門型クレーン1を設置した状態を示す図。The figure which shows the state which installed the rail 3 in the intersection vicinity which constructs a three-dimensional intersection, and installed a pair of portal crane 1 on the rail 3. FIG. 門型クレーン1を示す図で(a)は正面図、(b)は側面図。It is a figure which shows the portal crane 1, (a) is a front view, (b) is a side view. プレファブ型枠50を示す図で(a)は正面図、(b)は(a)のX−X線断面図。It is a figure which shows the prefabricated formwork 50, (a) is a front view, (b) is XX sectional drawing of (a). プレファブ型枠50を門型クレーン1で吊上げる状態を示す図。The figure which shows the state which lifts the prefabricated formwork 50 with the portal crane. プレファブ型枠50を設置する工程を示す図。The figure which shows the process of installing the prefabricated formwork 50. 橋脚5の設置が完了した状態を示す図。The figure which shows the state which installation of the bridge pier 5 was completed. 門型クレーン1で橋桁9を運搬し、橋脚5上に設置する工程を示す図。The figure which shows the process of conveying the bridge girder 9 with the portal crane 1 and installing on the bridge pier 5. FIG. 橋脚5上に、橋桁9の設置が完了した状態を示す図。The figure which shows the state which installation of the bridge girder 9 was completed on the bridge pier 5. FIG. ターンテーブル21を設置し、門型クレーン1で床版19を運搬する状態を示す図。The figure which shows the state which installs the turntable 21 and conveys the floor slab 19 with the portal crane 1. FIG. 床版19をターンテーブル21上へ載置した状態を示す図。The figure which shows the state which mounted the floor slab 19 on the turntable 21. FIG. ターンテーブル21を回転させ、床版19の幅方向を門型クレーン1の移動方向に対して略垂直方向へ向けた状態を示す図。The figure which shows the state which rotated the turntable 21, and orient | assigned the width direction of the floor slab 19 to the substantially perpendicular direction with respect to the moving direction of the portal crane 1. As shown in FIG. 幅方向を移動方向に対して垂直方向にむけた状態の床版19を、門型クレーン1で運搬し、橋桁9上へ設置した状態を示す図。The figure which shows the state which conveyed the floor slab 19 of the state which faced the width direction perpendicular | vertical to the moving direction with the portal crane 1, and installed on the bridge girder 9. FIG. 橋桁9上へ床版19の設置を完了した状態を示す図。The figure which shows the state which completed installation of the floor slab 19 on the bridge girder 9. FIG. (a)は吊り部31および床版33を示す正面図で、(b)は門型クレーン30を示す側面図。(A) is a front view which shows the hanging part 31 and the floor slab 33, (b) is a side view which shows the portal crane 30. FIG. 門型クレーン30を用いて、吊り具31に取り付けられた床版33を橋桁9上へ設置する工程を示す図。The figure which shows the process of installing the floor slab 33 attached to the hanging tool 31 on the bridge girder 9 using the portal crane 30. FIG. 門型クレーン30を用いて、吊り具31に取り付けられた床版33を橋桁9上へ設置するとともに、使用後の吊り具31を撤去する工程を示す図。The figure which shows the process of removing the used hanging tool 31 while installing the floor slab 33 attached to the hanging tool 31 on the bridge girder 9 using the portal crane 30. FIG. 吊り具41と伸縮架台45を用いて、床版33の幅を伸長し、門型クレーン30で吊上げる工程を示す図。The figure which shows the process of extending the width | variety of the floor slab 33 using the hanging tool 41 and the expansion-contraction mount 45, and lifting with the portal crane 30. FIG.

符号の説明Explanation of symbols

1、30………門型クレーン
3………レール
5………橋脚
7、8………道路
9………橋桁
11………車輪
12………クレーン桁
13………支持脚
14………突出部
15………横行レール
16………台車
17………ウィンチ
19………床版
21………ターンテーブル
31、41………吊り具
32………突出部
33………床版
34………段部
35………アーム
37………ボルト
43………アーム
45………伸縮架台
47………ジャッキ
50………プレファブ型枠
51………型枠
53………足場
55………鉄筋
57………吊り具
1, 30 ......... Gate crane 3 ... Rail 5 ... Piers 7, 8 ... Road 9 ... Bridge girder 11 ... Wheel 12 ... Crane girder 13 ... Support leg 14 ... …… Projection 15 ……… Transverse rail 16 …… Carriage 17 ………… Winch 19 ………… Slab 21 ………… Turntables 31, 41 …… ...... Suspension 32 32 …… Projection 33 ……… Floor slab 34 ......... Step 35 ......... Arms 37 ......... Bolts 43 ......... Arms 45 ...... Extensible mount 47 ...... Jack 50 ...... Prefab form 51 ...... Form 53 ... ... scaffold 55 ...... reinforcing bar 57 ...... hanging tool

Claims (6)

一対の支持脚と、前記支持脚下方に取り付けられ、レールに沿って走行可能な車輪と、一対の前記支持脚を連結するクレーン桁と、前記クレーン桁に設けられ、走行方向へ突出した突出部と、前記クレーン桁に沿って移動可能であり、前記突出部に設けられた第1のウィンチと、を有する門型クレーンを用い、
前記第1のウィンチが向かい合うように、一対の前記門型クレーンを、移動方向に対向するようにレール上に設置する工程(a)と、
前記レールの間に橋脚を設ける工程(b)と、
一対の前記門型クレーンで橋桁を共吊りし、前記橋桁を前記橋脚上に設置する工程(c)と、
前記門型クレーンで床版を吊上げ、前記床版を前記橋桁上へ設置する工程(d)と、
を具備することを特徴とする立体交差の施工方法。
A pair of support legs, wheels attached to the lower side of the support legs and capable of traveling along rails, a crane girder connecting the pair of support legs, and a protrusion provided in the crane girder and projecting in the traveling direction And a portal crane that is movable along the crane girder and has a first winch provided in the protruding portion,
(A) installing the pair of portal cranes on the rail so as to face each other in the moving direction so that the first winches face each other;
Providing a pier between the rails (b);
(C) a step of suspending a bridge girder with a pair of portal cranes and installing the bridge girder on the pier;
A step (d) of lifting the floor slab with the portal crane and installing the floor slab on the bridge girder;
A construction method for a three-dimensional intersection characterized by comprising:
前記床版の幅が、一対の前記支持脚同士の間隔よりも大きく、
前記工程(d)は、
前記床板の幅方向が前記門型クレーンの移動方向に向くように、前記床版を一対の前記支持脚の間に、吊上げる工程(e)と、
前記床版をターンテーブル上へ設置する工程(f)と、
前記床版の幅方向が前記門型クレーンの移動方向に対して略垂直方向へ向くように、前記ターンテーブルを回転させる工程(g)と、
前記床版を前記門型クレーンで吊上げる工程(h)と、
前記床版を前記橋桁上へ設置する工程(i)と、
を具備することを特徴とする請求項1記載の立体交差の施工方法。
The width of the floor slab is larger than the distance between the pair of support legs,
The step (d)
A step (e) of lifting the floor slab between the pair of support legs so that the width direction of the floor board faces the moving direction of the portal crane;
Installing the floor slab on a turntable; and
A step (g) of rotating the turntable so that a width direction of the floor slab is directed in a direction substantially perpendicular to a moving direction of the portal crane;
A step (h) of lifting the floor slab with the portal crane;
Installing the floor slab on the bridge beam (i);
The construction method of the three-dimensional intersection of Claim 1 characterized by comprising.
前記床版は一対の略L字状部材であり、一対の前記L字状部材は、吊り具の両端に接合されており、
前記工程(e)は、一対の前記L字状部材が接合された前記吊り具の幅方向が前記門型クレーンの移動方向に向くように、前記吊り具を一対の前記支持脚の間に吊上げる工程であり、
前記工程(i)は、前記L字状部材を前記橋桁の両端近傍へ接合する工程であり、
前記工程(i)の後、前記吊り具を前記門型クレーンで撤去する工程(j)をさらに具備することを特徴とする請求項2記載の立体交差の施工方法。
The floor slab is a pair of substantially L-shaped members, and the pair of L-shaped members are joined to both ends of the hanger,
In the step (e), the suspension tool is suspended between the pair of support legs so that the width direction of the suspension tool to which the pair of L-shaped members are joined faces the moving direction of the portal crane. Is the process of raising,
The step (i) is a step of joining the L-shaped member to the vicinity of both ends of the bridge beam,
The method of constructing a three-dimensional intersection according to claim 2, further comprising a step (j) of removing the suspension tool with the portal crane after the step (i).
前記吊り具は幅方向の伸縮が可能であり、
前記吊り具を縮めた状態では、前記吊り具に取り付けられた一対の前記L字状部材の幅は、一対の前記支持脚同士の間隔よりも小さく、
前記吊り具を伸ばした状態では、前記吊り具に取り付けられた一対の前記L字状部材の幅は、一対の前記支持脚同士の間隔よりも大きく、
前記工程(e)に代えて、前記吊り具を縮めた状態で、前記L字状部材の幅方向が前記門型クレーンの移動方向とほぼ垂直方向に向くように、前記L字状部材が接合された前記吊り具を、一対の前記支持脚の間に吊上げる工程(k)を具備し、
前記工程(f)に代えて、前記L字状部材が接合された前記吊り具を、前記吊り具の幅を変更可能な伸縮架台へ載せる工程(l)を具備し、
前記工程(g)に代えて、前記吊り具の幅を前記伸縮架台により伸ばし、一対の前記L字状部材同士の間隔を大きくする工程(m)を具備することを特徴とする請求項3記載の立体交差の施工方法。
The lifting device can be expanded and contracted in the width direction,
In a state where the suspension tool is contracted, the width of the pair of L-shaped members attached to the suspension tool is smaller than the distance between the pair of support legs,
In the state in which the suspension is extended, the width of the pair of L-shaped members attached to the suspension is larger than the interval between the pair of support legs,
In place of the step (e), the L-shaped member is joined so that the width direction of the L-shaped member is substantially perpendicular to the moving direction of the portal crane in a state where the suspension tool is contracted. A step (k) of lifting the suspended tool between the pair of support legs,
In place of the step (f), the step (l) of placing the hanging tool, to which the L-shaped member is joined, on an extendable frame that can change the width of the hanging tool,
4. The method according to claim 3, further comprising a step (m), in place of the step (g), by extending the width of the hanger using the telescopic mount and increasing the distance between the pair of L-shaped members. Construction method of three-dimensional intersection.
前記門型クレーンは、前記第1のウィンチのさらに前方に第2のウィンチが設けられ、
前記工程(i)は、前記第1のウィンチにより、設置予定のL字状部材が設けられた第1の吊り具を前記橋桁上へ設置する工程であり、
前記工程(j)は、前記第2のウィンチにより、設置終了後のL字状部材が設けられていた第2の吊り具を前記橋桁上から撤去する工程であることを特徴とする請求項3または請求項4記載の立体交差の施工方法。
The portal crane is provided with a second winch in front of the first winch,
The step (i) is a step of installing the first hanging tool provided with the L-shaped member to be installed on the bridge girder by the first winch,
The step (j) is a step of removing, from the bridge girder, the second suspender provided with the L-shaped member after completion of installation by the second winch. Or the construction method of the three-dimensional intersection of Claim 4.
前記工程(b)は、前記橋脚の型枠および鉄筋が組み立てられたプレファブ型枠を前記門型クレーンにより設置し、前記プレファブ型枠へコンクリートを打設することにより、前記橋脚が設けられることを特徴とする請求項1から請求項5のいずれかに記載の立体交差の施工方法。   In the step (b), the pier is provided by installing the prefab form with the pier formwork and rebar assembled by the portal crane and placing concrete into the prefab form. The construction method of the three-dimensional intersection in any one of Claims 1-5 characterized by the above-mentioned.
JP2008197420A 2008-07-31 2008-07-31 Construction method of level crossing Expired - Fee Related JP5184248B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008197420A JP5184248B2 (en) 2008-07-31 2008-07-31 Construction method of level crossing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008197420A JP5184248B2 (en) 2008-07-31 2008-07-31 Construction method of level crossing

Publications (2)

Publication Number Publication Date
JP2010031607A true JP2010031607A (en) 2010-02-12
JP5184248B2 JP5184248B2 (en) 2013-04-17

Family

ID=41736396

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008197420A Expired - Fee Related JP5184248B2 (en) 2008-07-31 2008-07-31 Construction method of level crossing

Country Status (1)

Country Link
JP (1) JP5184248B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101886369A (en) * 2010-07-06 2010-11-17 中建八局基础设施建设有限公司 Beam erecting method
CN102251483A (en) * 2011-05-23 2011-11-23 海波重型工程科技股份有限公司 Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane
CN103147401A (en) * 2013-03-06 2013-06-12 中交一公局第一工程有限公司 Construction method and structure of self-climbing portal frame
CN110510531A (en) * 2019-08-29 2019-11-29 成都天府轨谷科技有限公司 Wheel track self-propelled gantry tower crane on a kind of bevel edge trestle
CN111675112A (en) * 2020-06-22 2020-09-18 中铁工程机械研究设计院有限公司 Height-adjustable bridge pier hoisting machine, construction method and overpass method

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2007094906A2 (en) 2006-02-14 2007-08-23 Farmer Sarah E Belowground tree anchoring apparatus and method
CN103924527B (en) * 2014-04-29 2016-04-20 中铁四局集团有限公司 A kind of highway arrangement of girder field structure of frame integration processed and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0959930A (en) * 1995-08-18 1997-03-04 P S Co Ltd Bridge girder construction method and device thereof
JPH1181244A (en) * 1997-09-05 1999-03-26 Sumiken Kiko Kk Bridge erecting device
JPH11247109A (en) * 1998-03-05 1999-09-14 Tokyu Constr Co Ltd Constructing method of rigid-framed elevated bridge
JP2003147705A (en) * 2001-11-13 2003-05-21 Taisei Corp Constructing method for divided bridge body type traffic road
JP2004232426A (en) * 2003-02-03 2004-08-19 Kawada Construction Co Ltd Floor panel laying apparatus

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0959930A (en) * 1995-08-18 1997-03-04 P S Co Ltd Bridge girder construction method and device thereof
JPH1181244A (en) * 1997-09-05 1999-03-26 Sumiken Kiko Kk Bridge erecting device
JPH11247109A (en) * 1998-03-05 1999-09-14 Tokyu Constr Co Ltd Constructing method of rigid-framed elevated bridge
JP2003147705A (en) * 2001-11-13 2003-05-21 Taisei Corp Constructing method for divided bridge body type traffic road
JP2004232426A (en) * 2003-02-03 2004-08-19 Kawada Construction Co Ltd Floor panel laying apparatus

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101886369A (en) * 2010-07-06 2010-11-17 中建八局基础设施建设有限公司 Beam erecting method
CN102251483A (en) * 2011-05-23 2011-11-23 海波重型工程科技股份有限公司 Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane
CN102251483B (en) * 2011-05-23 2013-01-09 海波重型工程科技股份有限公司 Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane
CN103147401A (en) * 2013-03-06 2013-06-12 中交一公局第一工程有限公司 Construction method and structure of self-climbing portal frame
CN110510531A (en) * 2019-08-29 2019-11-29 成都天府轨谷科技有限公司 Wheel track self-propelled gantry tower crane on a kind of bevel edge trestle
CN111675112A (en) * 2020-06-22 2020-09-18 中铁工程机械研究设计院有限公司 Height-adjustable bridge pier hoisting machine, construction method and overpass method

Also Published As

Publication number Publication date
JP5184248B2 (en) 2013-04-17

Similar Documents

Publication Publication Date Title
JP6081117B2 (en) How to remove existing bridge and update existing bridge
JP5184248B2 (en) Construction method of level crossing
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
JP5507383B2 (en) Heavy load erection machine and heavy load erection method
JP2008274637A (en) Construction method for continuous viaduct
JP3954869B2 (en) Bridge girder replacement method
CN113957793A (en) Construction method for prefabricating box girder support in complex urban environment
CN217378620U (en) Intelligent bridge erecting system
JP2004316295A (en) Construction method for divided bridge body type traffic route, and divided bridge body type traffic route
JP2006028881A (en) Self-propelled pc floor slab erecting machine and pc floor slab erecting method
CN210561749U (en) Multi-frame juxtaposed double-cantilever bridge girder erection machine
JP2024074895A (en) Deck replacement method
JP4559370B2 (en) Girder erection method by erection gutter from the side of bridge
CN104110002A (en) Method for replacing bridge deck slabs of steel truss girder bridge
JP2011202406A (en) Method of assembling and disassembling movable working device for bridge
CN112211112A (en) Steel box girder installation method adopting double-guide-girder erection machine on existing bridge
JP5187969B2 (en) Overhead viaduct construction equipment and construction method
JP2768282B2 (en) Bridge construction method
CN113882286B (en) Bridge dismantling and building integrated machine, crossing method thereof, bridge dismantling method and newly-built method
KR100627102B1 (en) Upper bridge structure construcion method with precast segment deck or box using a lifting traveller
JP3349463B2 (en) How to install additional girder
JP3238751U (en) Bridge girder erection machine
KR101653559B1 (en) Method of repairing railway
JP3940587B2 (en) Construction method of divided bridge type traffic route
JP2002155501A (en) Construction method for space detour

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110302

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120628

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20121106

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20121213

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130115

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130116

R150 Certificate of patent or registration of utility model

Ref document number: 5184248

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160125

Year of fee payment: 3

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees