JP2015055088A - Building construction method - Google Patents

Building construction method Download PDF

Info

Publication number
JP2015055088A
JP2015055088A JP2013188586A JP2013188586A JP2015055088A JP 2015055088 A JP2015055088 A JP 2015055088A JP 2013188586 A JP2013188586 A JP 2013188586A JP 2013188586 A JP2013188586 A JP 2013188586A JP 2015055088 A JP2015055088 A JP 2015055088A
Authority
JP
Japan
Prior art keywords
cement liquid
construction
building
liquid
pile hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2013188586A
Other languages
Japanese (ja)
Other versions
JP6226123B2 (en
Inventor
清水 健司
Kenji Shimizu
健司 清水
修 中元
Osamu Nakamoto
修 中元
憲一 森口
Kenichi Moriguchi
憲一 森口
敏典 大野
Toshinori Ono
敏典 大野
淳史 花岡
Junji Hanaoka
淳史 花岡
憲弘 大槻
Norihiro Otsuki
憲弘 大槻
謙一 三幸
Kenichi Miyuki
謙一 三幸
久郎 春川
Hisao Harukawa
久郎 春川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP2013188586A priority Critical patent/JP6226123B2/en
Publication of JP2015055088A publication Critical patent/JP2015055088A/en
Application granted granted Critical
Publication of JP6226123B2 publication Critical patent/JP6226123B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Piles And Underground Anchors (AREA)
  • Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To economically progress building construction while employing an inverted construction method.SOLUTION: In a building construction method using an inverted construction method, a pile hole 8 is excavated by a pile hole excavation method that does not use a stable liquid; a cement liquid 12 is injected in a depth range H set for a permanent steel base column 7 in the pile hole 8; and a lower end of a permanent steel column 6 is inserted into an upper end of an injection range of the cement liquid 12 and integrated therewith for construction of a building skeleton.

Description

本発明は、逆打ち工法を用いた建物構築方法に関する。   The present invention relates to a building construction method using a reverse driving method.

従来、この種の建物構築方法としては、地下掘削に先立って、構真台柱の施工、及び、その構真台柱に構真柱を支持させる施工を実施した後、それら構真台柱と構真柱とに荷重を支持させながら建物の地下部分と地上部分とを並行して構築するものである。
そして、構真台柱は、本設の支持杭として使用されることが多いから、所定の孔径や強度を確保できるようにする為に、掘削においては、安定液を使用して孔壁安定を図ることで杭径の確保を行い、掘削後は、安定液で満たされた掘削穴内にトレミー管を使用してコンクリートを充填し、強度の確保を行っている。また、構真柱は、構真台柱のコンクリートが固まる前にその下端部をコンクリート中に挿入して一体化が図られている(例えば、特許文献1参照)。
Conventionally, this kind of building construction method has been the construction of a construction pillar and construction work supporting the construction pillar before the underground excavation, and then the construction pillar and construction pillar. The basement part and the ground part of the building are constructed in parallel while supporting the load.
And since the construction stand pillar is often used as a support pile for the main construction, in order to ensure a predetermined hole diameter and strength, in the excavation, a stabilizing liquid is used to stabilize the hole wall. The diameter of the pile is secured by this, and after excavation, the concrete is filled in the excavation hole filled with the stabilizing liquid using the treme tube to ensure the strength. In addition, the structural pillar is integrated by inserting its lower end into the concrete before the concrete of the structural support pillar is hardened (see, for example, Patent Document 1).

特開平5−5312号公報(段落番号〔0008〕、〔0009〕)JP-A-5-5312 (paragraph numbers [0008], [0009])

上述した従来の建物構築方法によれば、構真台柱の施工において、掘削工程で安定液を杭穴内に満たしながら実施されるが、使用済みの安定液は、産業廃棄物としての適切な処理を施す必要があり、その廃棄物処理に、多額の費用がかかる。
更には、安定液は、使用に伴って、掘削土や地下水が混入することによって物性が劣化するから、物性を維持する為に、ベントナイト濃度の管理及び調整処理、液中に混入するスライムの除去処理等を行う必要があり、それらの処理を実施する為の安定液維持装置が必要となる他、安定液を杭穴から回収して安定液維持装置に送液したり、安定液維持装置から杭穴に送液する循環装置も必要となり、設備費用が高額となる。
また、支持杭としての品質を確保するために、充分な強度を発揮できるコンクリートを充填材に使用するから、材料費も高額となる。
その結果、建物構築にかかる全体費用が嵩むことになり、その低減が望まれるところである。
According to the conventional building construction method described above, in the construction of the pedestal column, it is carried out while filling the pile hole with the stabilizing liquid in the excavation process, but the used stabilizing liquid is appropriately treated as industrial waste. It must be applied, and the waste disposal costs a lot of money.
Furthermore, the stability of the stable liquid deteriorates due to the mixing of excavated soil and groundwater with use. Therefore, in order to maintain the physical properties, the bentonite concentration is controlled and adjusted, and slime mixed in the liquid is removed. It is necessary to carry out processing etc., and in addition to the need for a stabilizing liquid maintenance device for carrying out such processing, the stabilizing liquid is collected from the pile hole and fed to the stabilizing liquid maintenance device, or from the stabilizing liquid maintenance device A circulation device for feeding liquid into the pile hole is also required, resulting in high equipment costs.
Moreover, in order to ensure the quality as a support pile, since the concrete which can exhibit sufficient intensity | strength is used for a filler, material cost also becomes expensive.
As a result, the overall cost for building construction increases, and a reduction is desired.

従って、本発明の目的は、上記問題点を解消し、逆打ち工法を用いながらも、経済的に建物建設を進めることができる建物構築方法を提供するところにある。   Accordingly, an object of the present invention is to provide a building construction method capable of solving the above-described problems and economically proceeding with the construction of a building while using a reverse driving method.

本発明の第1の特徴構成は、逆打ち工法を用いた建物構築方法であって、安定液を使用しない杭穴掘削方法によって杭穴を掘削し、前記杭穴において構真台柱とする深さ範囲にセメント液を注入して、前記セメント液の注入範囲(構真台柱の深さ範囲)の上端部に、構真柱の下端部を挿入して一体化を図り、建物躯体を構築するところにある。   A first characteristic configuration of the present invention is a building construction method using a reverse driving method, in which a pile hole is excavated by a pile hole excavation method that does not use a stabilizing liquid, and the depth of the pile hole used as a built-up pillar. Injecting cement liquid into the area, and inserting the lower end of the construction column into the upper end of the cement liquid injection range (depth range of the construction column) to build a building frame It is in.

本発明の第1の特徴構成によれば、安定液を使用しない杭穴掘削方法によって杭穴を掘削するから、安定液維持装置や循環装置を用いなくてもよくなり、シンプルな施工設備で効率的に杭穴掘削を実施できるようになるから、工期短縮や設備費の削減が可能となる。。
また、使用済みの安定液を廃棄物処理する必要がないから、廃棄物処理費用の削減が可能となる。
更には、構真台柱にセメント液を使用するから、コンクリートを使用するのに比べて、施工面・材料面の両面でのコストダウンを叶えられる。
以上の結果、建物構築にかかる全体費用の低減化を図ることができるようになる。
According to the first characteristic configuration of the present invention, since the pile hole is excavated by the pile hole excavation method that does not use the stabilizing liquid, it is not necessary to use the stabilizing liquid maintaining device and the circulation device, and the efficiency is improved with simple construction equipment. As a result, it is possible to carry out excavation of pile holes, and it is possible to shorten the construction period and reduce equipment costs. .
In addition, since it is not necessary to dispose of the used stabilizing solution, it is possible to reduce the waste treatment cost.
Furthermore, since cement liquid is used for the construction stand pillar, cost reduction in both construction and material aspects can be achieved compared to using concrete.
As a result, the overall cost for building construction can be reduced.

本発明の第2の特徴構成は、前記建物躯体の構築に伴って、柱と梁との構築を先行させて行い、基礎部が完成した後に、床スラブの構築を開始するところにある。   According to the second characteristic configuration of the present invention, the construction of the column slab is started after the foundation is completed after the construction of the column and the beam is performed in advance with the construction of the building frame.

本発明の第2の特徴構成によれば、基礎部が完成するまでの躯体重量を、極力抑えることで、構真柱・構真台柱への荷重負担を減らすことができ、杭穴掘削の小径化や、杭強度の低減化を図ることが可能となる。
その結果、建物全体とした経済性の向上を図れるようになる。
According to the second characteristic configuration of the present invention, it is possible to reduce the load burden on the structural pillar and the structural base column by suppressing the weight of the frame until the foundation is completed as much as possible. It is possible to reduce the pile strength.
As a result, the economy of the entire building can be improved.

本発明の第3の特徴構成は、前記基礎部は、直接基礎であり、前記構真台柱は、仮設杭であるところにある。   According to a third characteristic configuration of the present invention, the foundation portion is a direct foundation, and the stem frame is a temporary pile.

本発明の第3の特徴構成によれば、直接基礎である基礎部によって建物全体を支持できるから、建物完成後は、構真台柱は荷重負担する必要がない。即ち、構真台柱は、建物の最終的な荷重のすべてを支持するものではなく、あくまでも施工段階での建物荷重を一時的に支持するだけでよいから、構真台柱の更なる低強度化を図れ、コストダウンを叶えることができる。   According to the 3rd characteristic structure of this invention, since the whole building can be supported by the foundation part which is a direct foundation, after completion of a building, it is not necessary to bear a load for a construction pillar. In other words, the pedestal column does not support all of the final load of the building, but it only needs to temporarily support the building load at the construction stage. You can achieve cost reduction.

本発明の第4の特徴構成は、前記杭穴への前記セメント液の注入の後、その注入範囲(構真台柱の深さ範囲)の上方範囲に、前記セメント液より貧配合の貧配合セメント液を注入して前記杭穴の孔壁安定を図るところにある。   According to a fourth feature of the present invention, after the injection of the cement liquid into the pile hole, a poorly mixed cement that is poorer than the cement liquid in an upper range of the injection range (depth range of the stem column). The liquid is injected to stabilize the hole wall of the pile hole.

本発明の第4の特徴構成によれば、安定液を使用しない掘削方法によって杭穴を掘削しているから、孔壁崩れの可能性はあるものの、少なくとも、構真台柱の上方範囲に対しては、注入した貧配合セメント液によって孔壁安定が図られ、通常のセメント液が注入された構真台柱の範囲に余分な土が脱落して混入することを防止でき、杭品質の維持を図れる。
更には、貧配合セメント液そのものは、通常のセメント液に比べて硬化後の強度が低いから、簡単に除去することができる。従って、例えば、逆打ち工法での建物の地下部分の掘削の際に、構真柱の周りに貧配合セメント硬化物が付着していたとしても簡単に除去することができ、建物地下部分における施工性を向上させることができる。
According to the fourth characteristic configuration of the present invention, since the pile hole is excavated by an excavation method that does not use a stabilizing liquid, there is a possibility that the hole wall collapses, but at least with respect to the upper range of the stem frame Can stabilize the hole wall by the injected poorly mixed cement liquid, and can prevent the soil from falling off and mixing in the range of the construction column where the normal cement liquid has been injected, and can maintain the pile quality. .
Furthermore, the poorly blended cement liquid itself has a lower strength after curing than a normal cement liquid, and therefore can be easily removed. Therefore, for example, when excavating the underground part of a building by the reverse driving method, even if poor cementitious cemented material adheres around the structural pillar, it can be easily removed, and construction in the underground part of the building Can be improved.

本発明の第5の特徴構成は、前記構真台柱の形成においては、前記セメント液の注入範囲(構真台柱の深さ範囲)の上方近傍に下端部が位置する状態にガイドケーシングを設置しておき、前記ガイドケーシングの下端部と、前記セメント液の注入範囲の上端部との間にわたって、前記セメント液より貧配合の貧配合セメント液を注入して前記杭穴の孔壁安定を図るところにある。   According to a fifth characteristic configuration of the present invention, in the formation of the stem frame, a guide casing is installed in a state where a lower end portion is positioned in the vicinity of the upper portion of the cement liquid injection range (depth range of the stem column). In addition, between the lower end portion of the guide casing and the upper end portion of the cement liquid injection range, the poorly mixed cement liquid that is poorer than the cement liquid is injected to stabilize the hole wall of the pile hole. It is in.

本発明の第5の特徴構成によれば、ガイドケーシングと貧配合セメント液とによって、構真台柱の上方の孔壁安定を図れ、孔周囲の土の脱落をより確実に防止できる。
また、貧配合セメント液とガイドケーシングとの付着力は、通常のセメント液とガイドケーシングとの付着力に比べて低いから、ガイドケーシングの引き抜きの際に抵抗になりにくく、スムーズに作業を進行させることができる。
また、貧配合セメント液は、ガイドケーシングの設置範囲には注入する必要がないから、上方まで注入するのに比べて注入量を低減でき、より材料コストの低減を図ることができる。
従って、構真台柱の品質面、施工面、経済面それぞれで、好ましい結果が得られる。
According to the fifth feature of the present invention, the guide casing and the poorly mixed cement liquid can stabilize the hole wall above the stem frame and can more reliably prevent the soil around the hole from falling off.
In addition, since the adhesion between the poorly mixed cement liquid and the guide casing is lower than the adhesion between the normal cement liquid and the guide casing, it is difficult to resist when pulling out the guide casing, and the work proceeds smoothly. be able to.
Moreover, since it is not necessary to inject | pouring the poor mixing | blending cement liquid into the installation range of a guide casing, compared with inject | pouring upwards, the injection quantity can be reduced and the reduction of material cost can be aimed at more.
Therefore, preferable results can be obtained in terms of quality, construction, and economy of the construction stand pillar.

建物の正面視断面図Front sectional view of the building 建物構築手順を示す説明図Explanatory drawing showing the building construction procedure 建物構築手順を示す説明図Explanatory drawing showing the building construction procedure 建物構築手順を示す説明図Explanatory drawing showing the building construction procedure 建物構築手順を示す説明図Explanatory drawing showing the building construction procedure 建物構築手順を示す説明図Explanatory drawing showing the building construction procedure 構真台柱と構真柱との設置手順を示す説明図Explanatory diagram showing the installation procedure of the structural stem and structural pillar

以下に本発明の実施の形態を図面に基づいて説明する。   Embodiments of the present invention will be described below with reference to the drawings.

図1は、本発明の建物構築方法の一実施形態を採用して構築された建物Bを示している。
建物Bは、地下部B0と地上部B1とを備えた複数階層の構造に形成してあり、逆打ち工法を用いて構築されている。
最下層には、直接基礎を構成する基礎部Kが設けてあり、その基礎部K上に、各階層の柱1、梁2、床スラブ3、壁4等が設けてある。
FIG. 1 shows a building B constructed by adopting an embodiment of the building construction method of the present invention.
The building B is formed in a multi-level structure including an underground portion B0 and an above-ground portion B1, and is constructed by using a reverse driving method.
In the lowermost layer, a foundation part K that directly constitutes the foundation is provided, and on the foundation part K, pillars 1, beams 2, floor slabs 3, walls 4, etc. of each layer are provided.

また、建物Bの構築に当たっては、地下部B0の形成に先立って、土留め壁5の設置、及び、逆打ち工法実施時の先行地中柱となる構真柱6と、その構真柱6の支持杭となる構真台柱7との設置を行うものである。   In building B, prior to the formation of the basement B0, the structural pillar 6 which becomes the leading underground column during the installation of the retaining wall 5 and the reverse driving method, and the structural pillar 6 It installs with the construction stand pillar 7 used as a support pile of.

建物Bの構築方法を説明する。
[1]地下部B0の外周側の位置に土留め壁5を設置すると共に、柱1の予定位置の下方に、構真台柱7を形成する為の杭穴8を掘削する(図2参照)。
尚、構真台柱7、構真柱6の詳細な設置方法については後述する。
A construction method of the building B will be described.
[1] The retaining wall 5 is installed at a position on the outer peripheral side of the basement B0, and a pile hole 8 for excavating the frame stand 7 is excavated below the planned position of the column 1 (see FIG. 2). .
In addition, the detailed installation method of the construction stem pillar 7 and the construction stem pillar 6 will be described later.

[2]杭穴8内の構真台柱7に対応する深さ範囲Hに、セメント液12を注入すると共に、その注入範囲の上端部に、構真柱6の下端部を挿入し、位置保持させた状態で一体化を図る(図3参照)。 [2] The cement liquid 12 is injected into the depth range H corresponding to the framing pillar 7 in the pile hole 8, and the lower end portion of the framing column 6 is inserted into the upper end portion of the injection range to maintain the position. In this state, integration is attempted (see FIG. 3).

[3]該当する構真台柱7、及び、構真柱6の設置が完了し、それぞれが支持力を確保できる状態になったら、一階の梁2や床スラブ3を形成して、構真柱6の頭部と一体化を図り、荷重を構真柱6に支持させる。
また、一階の梁2は、両端部を、対向する土留め壁5にそれぞれ当接させてあり、切梁としての機能をも果たすように設置されている(図4参照)。
[3] When the installation of the corresponding structural support pillars 7 and the structural support pillars 6 is completed and each of them can secure a supporting force, the first floor beam 2 and the floor slab 3 are formed, and the structural support Integration with the head of the column 6 is performed, and the load is supported on the construction column 6.
Further, the beam 2 on the first floor has both ends abutted against the opposing earth retaining wall 5 and is installed so as to function as a cut beam (see FIG. 4).

[4]続いて、地上部B1と地下部B0との施工を並行して進める。
地上部B1においては、設置した構真柱6に荷重をかける状態で、柱1と梁2とを順次形成し、上層階へ施工を進めていく。
地下部B0においては、所定の深さ範囲の地盤掘削を行い、該当地下階の梁2を形成すると共に、構真柱6と一体化を図る。この該当地下階の梁2についても、一階の場合と同様に、端部を土留め壁5に当接させて、切梁としての機能を果たすように構成する(図4参照)。
尚、柱1と梁2とを先行させて形成し、床スラブ3の構築は後回しにすることで、構真柱6や構真台柱7に作用する施工途中での荷重を、床スラブ3の荷重相当分、減じることができる。
[4] Subsequently, the construction of the ground part B1 and the underground part B0 is performed in parallel.
In the above-ground part B1, the column 1 and the beam 2 are sequentially formed in a state where a load is applied to the installed true pillar 6, and the construction is advanced to the upper floor.
In the underground part B0, ground excavation in a predetermined depth range is performed to form the beam 2 of the corresponding underground floor and to be integrated with the structural pillar 6. Similarly to the case of the first floor, the beam 2 of the corresponding underground floor is configured so that the end portion is brought into contact with the earth retaining wall 5 and functions as a cut beam (see FIG. 4).
It is to be noted that the column 1 and the beam 2 are formed in advance, and the construction of the floor slab 3 is postponed, so that the load on the middle of the construction column 6 and the construction platform column 7 can be applied to the floor slab 3. It can be reduced by the amount corresponding to the load.

[5]更に、下階側の掘削を進行させると共に、直上階の構真柱6の補強を図って本設の柱1として更新する(図5参照)。以下、地下掘削と構真柱6の本設柱への更新を繰り返して実施する。 [5] Further, the excavation on the lower floor side is advanced, and the construction pillar 6 on the immediately upper floor is reinforced and updated as the main pillar 1 (see FIG. 5). Thereafter, the underground excavation and the renewal of the structural pillar 6 to the main pillar are repeated.

[6]最下層まで掘削を行って、荷重支持が可能な状態に基礎部Kを形成する。この時点で、設計の全荷重を、基礎部Kで支持できるようになり、仮設として荷重支持を行ってきた構真台柱7から基礎部Kに支持構造としての役割が移される。
従って、それまで形成していなかった地下部B0、地上部B1の各床スラブ3の構築を、柱1や梁2の施工と共に開始する(図6参照)。
尚、各階層の壁4に関しては、外周部に関しては、外部との遮断の目的が先行する為、柱1や梁2の構築と共に形成するのが好ましいが、内壁に関しては、仮設の構真台柱7への荷重負担の低減を図る為に、床スラブ3の施工時期まで遅らせるのが好ましい。
以上、地上部B1の最上階までの構築を済ませることで、建物Bのすべてが完成する。
[6] Excavation is performed up to the lowest layer, and the base portion K is formed in a state where the load can be supported. At this point, the entire design load can be supported by the foundation portion K, and the role as a support structure is transferred from the structural stand column 7 which has supported the load as a temporary structure to the foundation portion K.
Therefore, construction of each floor slab 3 of the underground part B0 and the above-ground part B1 which has not been formed is started with the construction of the pillar 1 and the beam 2 (see FIG. 6).
As for the wall 4 of each level, the outer peripheral part is preferably formed together with the construction of the pillar 1 and the beam 2 because the purpose of shielding from the outside is preceded, but the inner wall is a temporary construction stand pillar. In order to reduce the load on 7, it is preferable to delay until the construction time of the floor slab 3.
As described above, the building B is completed by completing the construction up to the top floor of the ground portion B1.

次に、構真台柱7、構真柱6の詳細な設置方法について説明する。
[a]掘削深度の途中深度まで、ガイドケーシング10を設置し、その内空部を、オーガー11を回転駆動させて掘削する形式の掘削装置(不図示)によって掘削する(図7(a)参照)。
掘削には、安定液は使用せず、例えば、オーガー11の回転のみによる素堀や、水を先端から吐出しながら掘り進む方法で実施することが、産業廃棄物を発生させない上で好ましい。
Next, the detailed installation method of the construction stem pillar 7 and the construction pillar 6 will be described.
[A] The guide casing 10 is installed up to an intermediate depth of excavation depth, and the inner space thereof is excavated by an excavator (not shown) of the type that excavates by rotating the auger 11 (see FIG. 7A). ).
For the excavation, it is preferable not to use industrial liquids, for example, it is preferable to carry out the excavation by using a moat only by rotating the auger 11 or a method of digging while discharging water from the tip.

[b]構真台柱7の下端深度まで掘削が終了したら、オーガー11を回転させながら先端からセメント液12を吐出しつつ上昇させる。セメント液12を吐出させる範囲は、構真台柱7に対応する深さ範囲Hとする(図7(b)参照)。 [B] When excavation is completed up to the lower end depth of the structural support column 7, the auger 11 is rotated and the cement liquid 12 is discharged from the tip while being raised. A range in which the cement liquid 12 is discharged is set to a depth range H corresponding to the stem column 7 (see FIG. 7B).

[c]構真台柱7に対応する深さ範囲Hにおけるセメント液12の吐出が完了したら、セメント液12を、貧配合セメント液13に切り替えて、ガイドケーシング10の下端部までの深さ範囲Jにおいて杭穴8内に注入を行う(図7(c)参照)。
この工程によって、ガイドケーシング10とセメント液12の注入範囲との間の深さ範囲Jに対して、貧配合セメント液13による孔壁安定効果を発揮することができる。
因みに、セメント液12は、例えば、水セメント比が60%程度の配合で調合され、貧配合セメント液13は、例えば、水セメント比が800%程度の配合で調合される。
[C] When the discharge of the cement liquid 12 in the depth range H corresponding to the structural stand column 7 is completed, the cement liquid 12 is switched to the poorly mixed cement liquid 13 and the depth range J to the lower end of the guide casing 10 is changed. Is injected into the pile hole 8 (see FIG. 7C).
By this step, the hole wall stabilizing effect by the poorly blended cement liquid 13 can be exhibited with respect to the depth range J between the guide casing 10 and the cement liquid 12 injection range.
Incidentally, the cement liquid 12 is prepared, for example, with a mixture having a water cement ratio of about 60%, and the poorly mixed cement liquid 13 is prepared, for example, with a composition having a water cement ratio of about 800%.

[d]掘削装置を撤去した後、杭穴8内のセメント液12と貧配合セメント液13とが流動可能な状態を保っている間に、杭穴8内に構真柱6を挿入し、下端部をセメント液12の中に挿入し、その位置を保持した状態で一体に硬化させる(図7(d)参照)。
因みに、構真柱6は、例えば、H形鋼等の鋼材が使用されるのが一般的である。また、説明は割愛しているが、構真柱6の立て込みにあたっては、設置角度(鉛直)や設置深度を、適宜、計測しながら実施される。
[D] After removing the excavator, while the cement liquid 12 and the poorly mixed cement liquid 13 in the pile hole 8 are maintained in a flowable state, the frame column 6 is inserted into the pile hole 8; The lower end portion is inserted into the cement liquid 12 and cured integrally with the position maintained (see FIG. 7D).
Incidentally, for the structural pillar 6, for example, a steel material such as H-shaped steel is generally used. In addition, although explanation is omitted, the installation angle (vertical) and the installation depth are appropriately measured while the construction column 6 is set up.

[e]ガイドケーシング10を引き抜くと共に、杭穴8を土で埋め戻す(図7(e)参照)。
以上の工程で、構真台柱7、及び、構真柱6を設置することができる。
[E] The guide casing 10 is pulled out and the pile hole 8 is backfilled with soil (see FIG. 7E).
Through the above steps, the pedestal column 7 and the structuring column 6 can be installed.

当該実施形態による建物構築方法によれば、シンプルな施工設備で効率的に杭穴掘削を実施できると共に、杭穴8の掘削に伴う安定液等の産業廃棄物処理が発生しないから、廃棄物処理費用の削減が可能となり、更には、コストメリットの高いセメント液12を構真台柱7に使用できるから、建物構築にかかる全体費用の低減化を図ることができるようになる。
つまり、施工手順の工夫により、構真台柱7に作用する荷重の低減を図りながら逆打ち工法を進めることが可能となり、杭穴掘削の簡素化や小径化、及び、杭強度の低減化を推進することで、建物全体とした経済性の向上を図れるようになった。
According to the building construction method according to this embodiment, pile hole excavation can be carried out efficiently with simple construction equipment, and industrial waste treatment such as stable liquid accompanying excavation of the pile hole 8 does not occur. Costs can be reduced, and furthermore, since the cement liquid 12 with high cost merit can be used for the gantry column 7, the overall cost for building construction can be reduced.
In other words, by devising the construction procedure, it is possible to proceed with the reverse driving method while reducing the load acting on the structural stand column 7, and promoting simplification and small diameter drilling of pile holes and reduction of pile strength By doing so, it became possible to improve the economic efficiency of the entire building.

〔別実施形態〕
以下に他の実施の形態を説明する。
[Another embodiment]
Other embodiments will be described below.

〈1〉 前記建物Bは、先の実施形態で説明したものは、一例にすぎず、その構造形式や、規模等は、適宜、設定することができる。 <1> The building B described in the previous embodiment is merely an example, and the structure type, scale, and the like can be set as appropriate.

〈2〉 前記杭穴8の掘削は、先の実施形態で説明したオーガーを使用した掘削装置によって実施することに限るものではなく、異なる方式の掘削装置によって実施するものであってもよい。
また、杭穴8の掘削にあたって、素堀によって実施することの他に、水を吐出しながら実施する方法を採用することも可能である。
要するに、安定液を使用しない杭穴掘削方法によるものであればよい。
<2> The excavation of the pile hole 8 is not limited to being performed by the excavator using the auger described in the previous embodiment, and may be performed by an excavator of a different type.
Moreover, when excavating the pile hole 8, it is also possible to employ a method in which water is ejected in addition to performing by excavation.
In short, what is necessary is just by the pile hole excavation method which does not use a stabilizer.

〈3〉 前記セメント液12や、貧配合セメント液13は、先の実施形態で説明した配合のものに限るものではなく、適宜、変更することが可能である。
また、貧配合セメント液13を使用せずに、構真台柱7の深さ範囲Hへのセメント液12の注入の後、その上方の杭穴8内に、土を埋め戻す方法であってもよい。
また、貧配合セメント液13を使用する場合でも、ガイドケーシング10の下端部と構真台柱7の深さ範囲Hの上端部との間に注入することに限らず、杭穴8の孔壁安定を図れる最小限の深さ範囲のみの注入に減縮することも可能である。
また、貧配合セメント液を構真台柱7の上方に注入するのに替えて、ガイドケーシング10の下端部が、構真台柱7の上端近傍にまで達するように深く設置する方法をとってもよい。この場合、貧配合セメント液の注入手間や材料そのものを省略できるから、より経済性を向上させることができる。
<3> The cement liquid 12 and the poorly mixed cement liquid 13 are not limited to those described in the previous embodiment, and can be appropriately changed.
Moreover, even if it is the method of backfilling the soil in the pile hole 8 above it after inject | pouring the cement liquid 12 to the depth range H of the construction stand pillar 7 without using the poor mixing | blending cement liquid 13. Good.
Further, even when the poorly mixed cement liquid 13 is used, the hole wall stability of the pile hole 8 is not limited to being injected between the lower end portion of the guide casing 10 and the upper end portion of the depth range H of the frame column 7. It is also possible to reduce the injection to a minimum depth range that can be achieved.
Further, instead of injecting the poorly blended cement liquid above the gantry column 7, a method may be adopted in which the lower end portion of the guide casing 10 is installed deeply so as to reach the vicinity of the upper end of the gantry column 7. In this case, since the trouble of injecting the poorly blended cement liquid and the material itself can be omitted, the economy can be further improved.

〈4〉 前記構真台柱7は、先の実施形態では、基礎部Kが完成するまでの仮設杭として説明したが、仮設に限るものではなく、例えば、基礎部Kと構真台柱7とで建物荷重を支持するように設計するものであってもよい。 <4> In the previous embodiment, the structural stand pillar 7 has been described as a temporary pile until the foundation K is completed, but is not limited to temporary construction. For example, the foundation pillar 7 includes the foundation K and the construction stand pillar 7. It may be designed to support building loads.

尚、上述のように、図面との対照を便利にするために符号を記したが、該記入により本発明は添付図面の構成に限定されるものではない。また、本発明の要旨を逸脱しない範囲において、種々なる態様で実施し得ることは勿論である。   In addition, as mentioned above, although the code | symbol was written in order to make contrast with drawing convenient, this invention is not limited to the structure of an accompanying drawing by this entry. In addition, it goes without saying that the present invention can be carried out in various modes without departing from the gist of the present invention.

1 柱
2 梁
3 床スラブ
6 構真柱
7 構真台柱
8 杭穴
10 ガイドケーシング
12 セメント液
13 貧配合セメント液
H 深さ範囲
K 基礎部
1 pillar 2 beam 3 floor slab 6 construction column 7 construction platform pillar 8 pile hole 10 guide casing 12 cement liquid 13 poor blending cement liquid H depth range K foundation

Claims (5)

逆打ち工法を用いた建物構築方法であって、
安定液を使用しない杭穴掘削方法によって杭穴を掘削し、
前記杭穴において構真台柱とする深さ範囲にセメント液を注入して、前記セメント液の注入範囲の上端部に、構真柱の下端部を挿入して一体化を図り、
建物躯体を構築する建物構築方法。
It is a building construction method that uses the reverse hammering method,
Drilling pile holes by a pile hole drilling method that does not use a stabilizing liquid,
Cement liquid is injected into the depth range to be the pedestal column in the pile hole, and the lower end portion of the pedestal column is inserted into the upper end portion of the cement liquid injection range to achieve integration,
A building construction method for building a building frame.
前記建物躯体の構築に伴って、柱と梁との構築を先行させて行い、
基礎部が完成した後に、床スラブの構築を開始する請求項1に記載の建物構築方法。
Along with the construction of the building frame, the construction of columns and beams is performed in advance,
The building construction method according to claim 1, wherein construction of the floor slab is started after the foundation is completed.
前記基礎部は、直接基礎であり、
前記構真台柱は、仮設杭である請求項2に記載の建物構築方法。
The foundation is a direct foundation;
The building construction method according to claim 2, wherein the structural stem pillar is a temporary pile.
前記杭穴への前記セメント液の注入の後、
その注入範囲の上方範囲に、前記セメント液より貧配合の貧配合セメント液を注入して前記杭穴の孔壁安定を図る請求項1〜3の何れか一項に記載の建物構築方法。
After injection of the cement liquid into the pile hole,
The building construction method according to any one of claims 1 to 3, wherein a poorly blended cement liquid that is poorer than the cement liquid is poured into an upper range of the pouring range to stabilize the hole wall of the pile hole.
前記構真台柱の形成においては、前記セメント液の注入範囲の上方近傍に下端部が位置する状態にガイドケーシングを設置しておき、
前記ガイドケーシングの下端部と、前記セメント液の注入範囲の上端部との間にわたって、前記セメント液より貧配合の貧配合セメント液を注入して前記杭穴の孔壁安定を図る請求項1〜3の何れか一項に記載の建物構築方法。
In the formation of the stem frame, a guide casing is installed in a state where the lower end is located near the upper part of the cement liquid injection range,
Between the lower end part of the said guide casing and the upper end part of the injection | pouring range of the said cement liquid, the poor mixing | blending poor cement liquid is injected from the said cement liquid, and the hole wall stability of the said pile hole is aimed at. 4. The building construction method according to any one of 3 above.
JP2013188586A 2013-09-11 2013-09-11 Building construction method Active JP6226123B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2013188586A JP6226123B2 (en) 2013-09-11 2013-09-11 Building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2013188586A JP6226123B2 (en) 2013-09-11 2013-09-11 Building construction method

Publications (2)

Publication Number Publication Date
JP2015055088A true JP2015055088A (en) 2015-03-23
JP6226123B2 JP6226123B2 (en) 2017-11-08

Family

ID=52819690

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2013188586A Active JP6226123B2 (en) 2013-09-11 2013-09-11 Building construction method

Country Status (1)

Country Link
JP (1) JP6226123B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049461A (en) * 2016-05-31 2016-10-26 中铁二十二局集团电气化工程有限公司 Construction method for filling piles
JP2018001427A (en) * 2016-06-27 2018-01-11 株式会社竹中工務店 Method for confirming the strength at the initial stage of the hardening of concrete structure, and method for determining the removal time of support or framework
JP2018100508A (en) * 2016-12-20 2018-06-28 大成建設株式会社 Building construction method
JP2020084685A (en) * 2018-11-29 2020-06-04 鹿島建設株式会社 Support column construction method
CN116290079A (en) * 2023-02-15 2023-06-23 中铁二院工程集团有限责任公司 Prefabricated retaining wall, side prefabricated block, middle prefabricated block and hole-opening construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61109827A (en) * 1984-10-31 1986-05-28 Takenaka Komuten Co Ltd Construction of basement
JPH02266014A (en) * 1989-04-04 1990-10-30 Takenaka Komuten Co Ltd Constructing underground structure eliminating use of temporary material
JPH0485419A (en) * 1990-07-26 1992-03-18 Kajima Corp Method for constructing underground structure
JPH04149321A (en) * 1990-10-12 1992-05-22 Mitsui Constr Co Ltd Underground structure by reverse placing method
JPH04185814A (en) * 1990-11-19 1992-07-02 Mitani Sekisan Co Ltd Construction of structural core column
JPH05156654A (en) * 1991-12-10 1993-06-22 Takenaka Komuten Co Ltd Top-down construction method
JPH08184067A (en) * 1994-12-28 1996-07-16 Ohbayashi Corp Method for constructing underground structure
JPH10317374A (en) * 1997-05-19 1998-12-02 Ohbayashi Corp Method for constructing underground column made of reinforced concrete

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61109827A (en) * 1984-10-31 1986-05-28 Takenaka Komuten Co Ltd Construction of basement
JPH02266014A (en) * 1989-04-04 1990-10-30 Takenaka Komuten Co Ltd Constructing underground structure eliminating use of temporary material
JPH0485419A (en) * 1990-07-26 1992-03-18 Kajima Corp Method for constructing underground structure
JPH04149321A (en) * 1990-10-12 1992-05-22 Mitsui Constr Co Ltd Underground structure by reverse placing method
JPH04185814A (en) * 1990-11-19 1992-07-02 Mitani Sekisan Co Ltd Construction of structural core column
JPH05156654A (en) * 1991-12-10 1993-06-22 Takenaka Komuten Co Ltd Top-down construction method
JPH08184067A (en) * 1994-12-28 1996-07-16 Ohbayashi Corp Method for constructing underground structure
JPH10317374A (en) * 1997-05-19 1998-12-02 Ohbayashi Corp Method for constructing underground column made of reinforced concrete

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106049461A (en) * 2016-05-31 2016-10-26 中铁二十二局集团电气化工程有限公司 Construction method for filling piles
JP2018001427A (en) * 2016-06-27 2018-01-11 株式会社竹中工務店 Method for confirming the strength at the initial stage of the hardening of concrete structure, and method for determining the removal time of support or framework
JP2018100508A (en) * 2016-12-20 2018-06-28 大成建設株式会社 Building construction method
JP2020084685A (en) * 2018-11-29 2020-06-04 鹿島建設株式会社 Support column construction method
JP7193994B2 (en) 2018-11-29 2022-12-21 鹿島建設株式会社 Strut construction method
CN116290079A (en) * 2023-02-15 2023-06-23 中铁二院工程集团有限责任公司 Prefabricated retaining wall, side prefabricated block, middle prefabricated block and hole-opening construction method thereof
CN116290079B (en) * 2023-02-15 2024-06-11 中铁二院工程集团有限责任公司 Prefabricated retaining wall, side prefabricated block, middle prefabricated block and hole-opening construction method thereof

Also Published As

Publication number Publication date
JP6226123B2 (en) 2017-11-08

Similar Documents

Publication Publication Date Title
JP6226123B2 (en) Building construction method
CN103510540B (en) Mortar flag stone retaining wall reinforcement construction method and structure thereof
JP2006328716A (en) Structure and method for underpinning of existing structure and method of constructing new structure near existing structure
JP5202708B2 (en) Steel pipe pile and pile foundation method using the steel pipe pile
KR101021915B1 (en) A method for constructing cut-off temporary structure for sheathing work
KR101746654B1 (en) Method for constructing pile for reinforce of mine hole
JP5690864B2 (en) Construction method of mountain retaining wall, construction method of cast-in-place pile
KR100992597B1 (en) The support material for a tunnel and tunnel support
CN207211158U (en) Assembled pile board wall foundation pit supporting construction
CN109440779A (en) Active X-shaped foundation pit supporting method with double rows of piles
JP6645098B2 (en) Removal method of existing pile
KR20100030241A (en) Compaction grouting method
JP2007308951A (en) Method of constructing outer peripheral column by inverted construction method
JP2008031772A (en) Construction method of precast pile, and cover for use in the construction method
JP5648085B2 (en) How to build a pile
JP2007046343A (en) Liquefaction preventive construction method of ground just under existing building
KR101021913B1 (en) A method for constructing cut-off temporary structure for sheathing work
JP2010275708A (en) Method for forming building
JP5634036B2 (en) Method for constructing retaining wall, method for constructing pile, retaining wall, pile
JP5378066B2 (en) Mountain fastening method
KR20190043709A (en) Construction Method Soft Surface Treatment And Strength of Reinforced Soil Using Waste Aggregates
KR20180062669A (en) Micropile and micropile molding method for earthquake-proof and strengthening ground
JP2004003306A (en) Sludge treatment method in prefabricated pile construction, and ground reinforcing structure obtained by method
JP2011157719A (en) Earth retaining method
JP2009203690A (en) Earth anchor and method of removing the same

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20160627

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20170213

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20170221

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20170420

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20170912

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20170926

R150 Certificate of patent or registration of utility model

Ref document number: 6226123

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150