JPH0485419A - Method for constructing underground structure - Google Patents

Method for constructing underground structure

Info

Publication number
JPH0485419A
JPH0485419A JP2199696A JP19969690A JPH0485419A JP H0485419 A JPH0485419 A JP H0485419A JP 2199696 A JP2199696 A JP 2199696A JP 19969690 A JP19969690 A JP 19969690A JP H0485419 A JPH0485419 A JP H0485419A
Authority
JP
Japan
Prior art keywords
column
steel
erection
pile core
pillar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2199696A
Other languages
Japanese (ja)
Other versions
JPH0737726B2 (en
Inventor
Shoei Ito
伊藤 昭栄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2199696A priority Critical patent/JPH0737726B2/en
Publication of JPH0485419A publication Critical patent/JPH0485419A/en
Publication of JPH0737726B2 publication Critical patent/JPH0737726B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE:To improve the accuracy in erection dimensions of a column and improve economic efficiency, productivity and general applicability by the arrangement such that a column and beam made up of ordinary steel framed column or beam for use as a temporary column or beam can be used as permanent ones. CONSTITUTION:A steel framed column 3 is erected, as a core column for pile, in each of a plurality of bores 2 formed inside an earth pressure wall 1 formed in the soil, while jacks 4 provided on the side of the bores are properly extended by remote control. After adjusting the preciseness in erection dimensions of the column 3 by regulating the pressure on the bore wall, foot protection concrete 5 is placed in the lower section of the bore. Thereafter, a steel framed beam 6, which becomes a first stage strut, is connected to the upper part of the column 3, while correcting error in dimensions by means of a connection member 8 and adjustment nut, and excavation is performed to connect a second beam 7 to the column 3. In the similar manner, a third beam 7 and the following beams are connected, while steel frames for floors above ground are erected and after completion of erection of steel frames, underground concrete body is constructed.

Description

【発明の詳細な説明】 [産業上の利用分野] 本発明は、建物の地下躯体や、地下駐車場などの地下構
造物の構築法に関する。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method of constructing an underground structure such as an underground frame of a building or an underground parking lot.

〔従来の技術〕[Conventional technology]

地下構造物を施工するには、従来、仮設としての柱を建
込んだ後で、同じく仮設としての山留め用の切梁や腹起
を架設し、根切りの進行とともにこの切梁を2段、3段
と順次増やしていく。
To construct an underground structure, conventionally, after erecting temporary pillars, a temporary sill or sill is erected, and as the root cutting progresses, this sill is erected in two stages. Gradually increase the number to three stages.

該地下構造物が地下5,6層にもおよぶ大型のものにな
ると、当然この切梁の段数も増加し、仮設材の量も多く
なる。
When the underground structure becomes large, reaching five or six levels underground, the number of struts and the amount of temporary materials will naturally increase.

ところで、本設の柱・梁を前記山留め用の仮設として兼
用できれば著しく経済性が向上し、また地上部工事も一
階のスラブ等を除いて同時進行することが可能となるの
で工期の短縮等生産性も著しく向上する。
By the way, if the permanent pillars and beams could be used as temporary structures for the above-mentioned mountain retaining, the economic efficiency would be significantly improved, and above ground construction could also be done at the same time, except for the first floor slab, etc., which would shorten the construction period, etc. Productivity also improves significantly.

このような本設切梁工法の一つとして、次のような工法
がある。
The following construction method is one of such permanent beam construction methods.

先ず本設の構芯柱(鋼管柱)を抗工事時に建込み、続い
て従来の切梁に当たる鉄骨ボックス梁を取付ける。
First, the main pillars (steel pipe columns) will be erected during the construction work, and then the steel box beams, which will serve as conventional struts, will be installed.

このあと、その内部にコンクリートを打設して山留め壁
の支持架橋を横築し、次の掘削工事に移行する。
After this, concrete will be poured inside and a support bridge for the retaining wall will be built horizontally, before moving on to the next excavation work.

さらに直下階の鉄骨ボックス粱を取り付け、内部コンク
リート打設、掘削を繰り返して順次地下の躯体工事を進
めていく。
Furthermore, we will install the steel frame box on the floor immediately below, and proceed with the construction of the underground frame by repeating internal concrete pouring and excavation.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

このような従来の本設切梁工法では、コンクリートを充
填する鋼管柱と鉄骨ボックス梁を使用する特殊なもので
あり、通常の鉄骨柱や鉄骨梁を使用するものではない。
This conventional permanent beam construction method is a special method that uses concrete-filled steel pipe columns and steel box beams, and does not use regular steel columns or steel beams.

仮に、通常の鉄骨柱や鉄骨梁を使用するとすると、まず
、構芯柱(杭芯柱)の造成は、施工の困難さもあり、ど
うしても建入れ寸法精度が悪イ(垂直度が斜めになる)
ため、本設の鉄骨柱として使用できないことが多い。
If normal steel columns and beams were to be used, first of all, constructing the core columns (pile core columns) would be difficult to construct, and the precision of construction dimensions would be poor (verticality would be slanted).
Therefore, they often cannot be used as permanent steel columns.

また、それに取付く梁(切梁)の長さも現場合わせの寸
法になるため、本設の梁として使用することができない
In addition, the length of the beam (strut) attached to it will be adjusted at the site, so it cannot be used as a permanent beam.

本発明の目的は前記従来例−の不都合を解消し、通常の
鉄骨柱や鉄骨梁を使用して山留め用の切梁を構築しても
、これを充分本設用の柱・梁として利用することができ
、本設切梁工法の特質を充分生かせる地下構造物の構築
法を提供することにある。
The purpose of the present invention is to eliminate the disadvantages of the conventional example, and to make it possible to use ordinary steel columns and beams as pillars and beams for permanent installation even when constructing sills for retaining the piles. The object of the present invention is to provide a method for constructing an underground structure that can fully utilize the characteristics of the permanent beam construction method.

〔課題を解決するための手段〕[Means to solve the problem]

本発明は前記目的を達成するため、地下に柱を建込み、
この柱の上部に梁を架設して構築する柱・梁架構を山留
め用の切梁として使用し、根切りの深さに応して順次該
柱の下部に2段目以下の梁を架設して地下構造物を施工
する構築法において、柱は外方への押圧手段を側部に設
けた杭芯柱で、二〇杭芯柱を本設用の鉄骨柱として整孔
した孔内へ建込み、該押圧手段の孔壁への押圧調整によ
り建入れ精度を修正し、杭芯柱下部に根固めコンクリー
トを施し、この杭芯柱と切梁ともなる本設鉄骨梁との接
合は、一端に雄ネジのボルト部を形成し、他端にボルト
挿通孔を形成した平板部を有する接合金物を使用し、こ
の接合金物のボルト部に調整ナツトを螺合し、そのボル
ト部を鉄骨柱フランジに挿通して締付けるとともに該接
合金物の平板部は鉄骨梁フランジに重ねてボルト・ナッ
トで緊締し、かつ柱フランジと梁ウェブをガセットプレ
ートで連結することにより行うことを要旨とするもので
ある。
In order to achieve the above object, the present invention erects pillars underground,
The column/beam frame constructed by erecting a beam at the top of this column is used as a sill beam for retaining the pile, and the second and subsequent beams are erected at the bottom of the column in sequence according to the depth of the root cut. In the construction method of constructing an underground structure, the pillar is a pile core column with an outward pressing means on the side. The construction accuracy was corrected by adjusting the pressure of the means on the hole wall, and concrete was applied to the bottom of the pile core column, and the connection between this pile core column and the main steel beam, which also served as the cut beam, was formed using a male-threaded bolt at one end. Then, use a joining hardware that has a flat plate part with a bolt insertion hole formed at the other end, screw an adjustment nut into the bolt part of this joining hardware, insert the bolt part into the steel column flange, tighten it, and complete the connection. The main idea is that the flat plate part of the hardware is placed over the steel beam flange and tightened with bolts and nuts, and the column flange and beam web are connected with a gusset plate.

〔作用] 従来、仮設として構築されている柱や切梁を本設として
使用するには、柱の建入れ寸法精度を良くすることであ
り、また梁も本設としての長さ寸法のものが柱に接合で
きることである。
[Function] In order to use columns and struts that were conventionally constructed as temporary structures as permanent structures, it is necessary to improve the dimensional accuracy of the pillar construction, and the length of the beams as well as those for permanent structures must be improved. It can be joined to pillars.

本発明によれば、杭芯柱の建入れ寸法精度は、該杭芯柱
の側部に設けた押圧手段の孔壁への押圧調整により反作
用としてこの杭芯柱の孔内での傾きを簡単に修正して高
い精度のものとすることができる。
According to the present invention, the erecting dimensional accuracy of the pile core column is achieved by easily correcting the inclination of the pile core column in the hole as a reaction by adjusting the pressure of the pressing means provided on the side of the pile core column against the hole wall. It can be made into

また、鉄骨梁の前記杭芯柱への接合は、接合金物の一端
に形成するボルト部に螺合する調整ナツトの回転で該ボ
ルト部の鉄骨柱フランジへの挿通程度を変更することに
より位置調整できる。
Furthermore, the position of the connection of the steel beam to the pile core column can be adjusted by changing the degree of insertion of the bolt into the steel column flange by rotating an adjustment nut that is screwed into a bolt formed at one end of the joining hardware.

さらに、この接合金物は杭芯柱へ後付けできるので、該
杭芯柱は建入れの際には鉄骨梁との接合用のブラケット
等の突起物を設ける必要がなく、孔径を大きくする必要
もない。
Furthermore, since this joining hardware can be attached to the pile core column later, there is no need to provide a protrusion such as a bracket for connecting the pile core column to the steel beam during erection, and there is no need to increase the diameter of the hole.

〔実施例〕〔Example〕

以下、図面について本発明の実施例を詳細に説明する。 Embodiments of the present invention will be described in detail below with reference to the drawings.

第1図〜第4図は本発明の地下構造物の構築法の各工程
を示す側面図で、まず、第1図に示すように土圧壁1を
地盤中に形成し、この上圧壁1で囲繞した内側に掘削機
で孔2を必要本鑿孔する。
Figures 1 to 4 are side views showing each step of the method for constructing an underground structure according to the present invention. First, as shown in Figure 1, an earth pressure wall 1 is formed in the ground, and this upper pressure wall is Drill hole 2 as necessary inside the area surrounded by 1 using an excavator.

なお、この孔2の造成は鋼管ケーシングを配置して行う
ものでもよい。
Note that the hole 2 may be created by arranging a steel pipe casing.

次いで、この孔1内に杭芯柱としての鉄骨柱3を建込む
が、該鉄骨柱3は第3図に示すようにその側部、すなわ
ちフランジ3a(ウェブテモ可)の面に外方への押圧手
段としてのジャ・7キ4を設けた。
Next, a steel column 3 as a pile core column is erected in this hole 1, and as shown in FIG. We have set up JA 7 Ki 4 as a standard.

このジヤツキ4はネジ構造の手動式のものでもよいが、
油圧ジヤツキ、エアジヤツキでもよく、少なくとも鉄骨
柱3の上端部近くから遠隔操作可能なものとする。
This jack 4 may be a manual type with a screw structure, but
A hydraulic jack or an air jack may be used, and it should be possible to remotely control the jack from at least near the upper end of the steel column 3.

鉄骨柱3の建込み前にはこのジヤツキ4は縮めて出っ張
らないようにしておき、鉄骨柱3を孔1内に建込んだ後
で、前記遠隔操作により該ジヤツキ4を適宜伸長し、孔
壁への押圧調整によりその反作用としてこの鉄骨柱3の
孔1内での傾きを修正する。
Before erecting the steel column 3, this jack 4 is shortened so that it does not protrude, and after the steel column 3 is erected in the hole 1, the jack 4 is extended as appropriate by the remote control and the hole wall is tightened. By adjusting the pressure, the inclination of the steel column 3 within the hole 1 is corrected as a reaction.

このようにして鉄骨柱3の建入れ精度を修正したならば
、第2図に示すように鉄骨柱3の下部に根固めコンクリ
ート5を打設する。
After correcting the erection accuracy of the steel column 3 in this way, foot protection concrete 5 is placed at the bottom of the steel column 3 as shown in FIG.

そして、鉄骨柱3の上端に継ぎ足しを行うなどして、鉄
骨梁6を接合するがこの鉄骨梁6は第1段目の切梁とな
るものである。
Then, a steel beam 6 is joined by adding a joint to the upper end of the steel column 3, and this steel beam 6 becomes a first-stage strut.

なお、この鉄骨梁6は地上階建物のIF階階床色なるも
ので、地上からすくの場所で掘削深さもきわめて浅いも
のであるから、前記鉄骨柱3とはブラケットを設けると
か継手部を形成するとかして接合する通常の接合方法を
使用する。
Note that this steel beam 6 is the IF floor of a ground-floor building, and the excavation depth is extremely shallow at a location below the ground level, so it is difficult to connect it to the steel column 3 by providing a bracket or forming a joint part. A normal joining method of combing is used.

次いで、第3図に示すように該鉄骨梁6を山留め用の切
梁として使用して根切りを行い、その深さに応して第2
段目の切梁として1.鉄骨梁7を鉄骨柱3に接合する。
Next, as shown in FIG. 3, root cutting is performed using the steel beam 6 as a strut for retaining the pile, and a second cut is made according to the depth of the root cutting.
1. As a strut for each step. The steel beam 7 is joined to the steel column 3.

また、地上階への鉄骨建方も同時進行を始める。At the same time, construction of the steel frame on the ground floor will also begin.

該鉄骨梁7と鉄骨柱3との接合は、第3図、第4図に示
すような接合金物8を使用して行うもので、第5図、第
6図に示すようにこの接合金物8は、一端に雄ネジのボ
ルト部8aを形成し、他端にボルト挿通孔8Cを形成し
た平板部8bを有する。
The steel beam 7 and the steel column 3 are joined using a joining hardware 8 as shown in FIGS. 3 and 4, and as shown in FIGS. The flat plate part 8b has a male threaded bolt part 8a formed at one end and a bolt insertion hole 8C formed at the other end.

鉄骨柱3のフランジ3aには前記ボルト部8aが挿通す
る挿通孔が形成してあり、この挿通孔にボルト部8aを
該挿通孔に差し入れ、かつ接合骨は金物9を介在させて
調整ナラ1−10.10’を螺合する。
The flange 3a of the steel column 3 is formed with an insertion hole through which the bolt portion 8a is inserted. -10. Screw together 10'.

一方、鉄骨梁7のフランジ7aにも挿通孔が形成してあ
り、接合金物8の平板部8bはこの鉄骨梁7のフランジ
7aに重ねてボルト・ナット11で緊締する。
On the other hand, an insertion hole is also formed in the flange 7a of the steel beam 7, and the flat plate portion 8b of the joining hardware 8 is placed over the flange 7a of the steel beam 7 and tightened with bolts and nuts 11.

そしてこのような接合に際し、鉄骨柱3の建入れ寸法誤
差がまだ残っており、これを修正するには、調整ナツト
10の回転で接合金物8のボルト部8aの鉄骨柱フラン
ジ3aへの挿通程度を変更することにより行う。
When such a connection is made, there is still an error in the construction dimensions of the steel column 3, and in order to correct this, it is necessary to rotate the adjustment nut 10 to insert the bolt part 8a of the joint hardware 8 into the steel column flange 3a. This is done by changing the .

このとき、鉄骨梁7のウェブ7bと鉄骨柱3のフランジ
3aに予め形成した接合用ガゼツトプレート13とはス
プライスプレート12により接合するが、この鉄骨梁7
のウェブ7bのスプライスプレート12のボルト止め用
の穴14を長穴としておく。
At this time, the web 7b of the steel beam 7 and the joining gusset plate 13 formed in advance on the flange 3a of the steel column 3 are joined by the splice plate 12.
The holes 14 for bolting the splice plate 12 of the web 7b are elongated holes.

また、ガセットプレートに設けるボルト止め用の穴を長
大としてもよい。
Further, the holes for bolting provided in the gusset plate may be made long.

第4図に示すように、このようにして、2段目の切梁と
しての鉄骨梁7を架設したならば、同様に根切りを行い
、その掘削深さに応じて3段目以下の切梁としての鉄骨
梁7を同じく接合金物8を使用して架設して行く。
As shown in Fig. 4, once the steel beam 7 as the second stage strut has been erected in this way, the roots are cut in the same way, and the third and subsequent stages are cut according to the excavation depth. A steel beam 7 as a beam is similarly erected using joining hardware 8.

このような鉄骨柱3と鉄骨梁7の接合で、土圧壁より作
用する土圧力による梁軸力と梁から柱に伝達する剪断力
は鉄骨柱3と鉄骨梁7との間のガセットプレート12を
介して伝えられ、また鉄骨梁7の曲げモーメントは該梁
7端部において一対の偶力として柱3に伝えられ、この
偶力中、引張力は接合金物8を介してそのボルト部8a
に螺合した一方のナツトを反力点として柱3に、また圧
縮力は他方のナツトを反力点としてそれぞれ柱3に伝達
される。
In such a connection between the steel column 3 and the steel beam 7, the beam axial force due to the earth pressure acting from the earth pressure wall and the shear force transmitted from the beam to the column are generated by the gusset plate 12 between the steel column 3 and the steel beam 7. In addition, the bending moment of the steel beam 7 is transmitted to the column 3 as a pair of couples at the ends of the beam 7, and in this couple, the tensile force is transmitted via the metal fitting 8 to the bolt portion 8a.
The compressive force is transmitted to the column 3 using one of the nuts screwed together as a reaction force point, and the compressive force is transmitted to the column 3 using the other nut as a reaction force point.

そして、地下鉄骨の建方が完了したならば、地下コンク
リ−+−i体15の施工を行う。
After the erection of the subway frame is completed, the construction of the underground concrete body 15 is carried out.

〔発明の効果〕〔Effect of the invention〕

以上述べたように本発明の地下構造物の構築法は、山留
め用の仮設として使用したものをそのまま本設用の柱・
梁として兼用できるので、経済性が向上し、また地上部
工事も同時進行することが可能となるので工期の短縮等
生産性も向上するものである。
As described above, the method of constructing an underground structure of the present invention is to use the structure that is used as a temporary structure for retaining a mountain as it is to be used as a pillar for permanent construction.
Since it can also be used as a beam, economic efficiency is improved, and above-ground construction can be carried out at the same time, which improves productivity by shortening the construction period.

そして、このように仮設として構築されている柱や切梁
を本設として使用するのに、汎用性の多い鉄骨柱、鉄骨
梁を使用することができるものであり、従来、出来なか
った柱の建入れ寸法精度の向上と、柱と梁の接合の調整
が簡単かつ確実にできるものである。
In addition, it is possible to use steel columns and beams, which are highly versatile, to use these temporary columns and struts as permanent structures, and it is possible to use columns and beams that were previously not possible. This improves the accuracy of construction dimensions and makes it possible to easily and reliably adjust the connection between columns and beams.

【図面の簡単な説明】[Brief explanation of drawings]

第1図〜第4図は本発明の地下構造物の構築法の1実施
例を示すもので、各工程の示す側面図、第5図は要部の
側面図、第6図は同上平面図である。 1・・・土圧壁 3・・・鉄骨柱 4・・・ジヤツキ 6.7・・・鉄骨梁 7b・・・ウェブ 8・・・接合金物 8b・・・平板部 9・・−接合受は金物 11・・・ボルト・ナット 13・・・ガゼツトブレー 15・・・地下コンクリ− 2・・・孔 3a・・・フランジ 5・・・根固めコンクリート 7a・・・フランジ 8a・・・ボルト部 8C・・・ボルト挿通孔 10.10  ’・・・調整ナツト 12・・・スプライスプレート ド14・・・長大 ト躯体 第 2図 第1 3図 第4 図 第 図
Figures 1 to 4 show one embodiment of the method for constructing an underground structure according to the present invention, and are side views showing each step, Figure 5 is a side view of the main part, and Figure 6 is a plan view of the same. It is. 1...Earth pressure wall 3...Steel frame column 4...Judge 6.7...Steel beam 7b...Web 8...Joint hardware 8b...Flat plate part 9...-Joint receiver is Hardware 11... Bolt/Nut 13... Gazette Brake 15... Underground Concrete 2... Hole 3a... Flange 5... Foot protection concrete 7a... Flange 8a... Bolt part 8C. ...Bolt insertion hole 10.10'...Adjusting nut 12...Splice plate 14...Long frame Figure 2 Figure 1 3 Figure 4 Figure

Claims (1)

【特許請求の範囲】[Claims] 地下に柱を建込み、この柱の上部に梁を架設して構築す
る柱・梁架構を山留め用の切梁として使用し、根切りの
深さに応じて順次該柱の下部に2段目以下の梁を架設し
て地下構造物を施工する構築法において、柱は外方への
押圧手段を側部に設けた杭芯柱で、この杭芯柱を本設用
の鉄骨柱として鑿孔した孔内へ建込み、該押圧手段の孔
壁への押圧調整により建入れ精度を修正し、杭芯柱下部
に根固めコンクリートを施し、この杭芯柱と切梁ともな
る本設鉄骨梁との接合は、一端に雄ネジのボルト部を形
成し、他端にボルト挿通孔を形成した平板部を有する接
合金物を使用し、この接合金物のボルト部に調整ナット
を螺合し、そのボルト部を鉄骨柱フランジに挿通して締
付けるとともに該接合金物の平板部は鉄骨梁フランジに
重ねてボルト・ナットで緊締し、かつ柱フランジと梁ウ
ェブをガセットプレートで連結することにより行うこと
を特徴とする地下構造物の構築法。
The pillar-beam frame is constructed by building pillars underground and installing beams on top of these pillars.The pillar-beam frame is used as a strut for retaining the mountain, and the second stage is installed at the bottom of the pillar depending on the depth of the root cut. In the construction method of constructing an underground structure by erecting the following beams, the pillar is a pile core column with outward pressing means on the side, and this pile core column is used as a steel frame column for permanent installation into the drilled hole. During erection, the accuracy of erection is corrected by adjusting the pressure of the pressing means against the hole wall, and concrete is applied to the lower part of the pile core column, and the connection between this pile core column and the main steel beam, which also serves as the strut, is made using a male screw at one end. Use a joining hardware that has a flat plate part with a bolt hole formed at the other end, screw an adjustment nut onto the bolt part of this joining hardware, and insert the bolt part into the steel column flange. A method for constructing an underground structure, characterized in that the flat plate part of the joining metal is overlaid on a steel beam flange and tightened with bolts and nuts, and the column flange and beam web are connected with a gusset plate.
JP2199696A 1990-07-26 1990-07-26 Construction method of underground structure Expired - Fee Related JPH0737726B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2199696A JPH0737726B2 (en) 1990-07-26 1990-07-26 Construction method of underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2199696A JPH0737726B2 (en) 1990-07-26 1990-07-26 Construction method of underground structure

Publications (2)

Publication Number Publication Date
JPH0485419A true JPH0485419A (en) 1992-03-18
JPH0737726B2 JPH0737726B2 (en) 1995-04-26

Family

ID=16412096

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2199696A Expired - Fee Related JPH0737726B2 (en) 1990-07-26 1990-07-26 Construction method of underground structure

Country Status (1)

Country Link
JP (1) JPH0737726B2 (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015055088A (en) * 2013-09-11 2015-03-23 株式会社竹中工務店 Building construction method
JP2020172817A (en) * 2019-04-12 2020-10-22 株式会社大林組 Position adjustment device, and position adjustment method of underground piled column
CN112727107A (en) * 2020-12-25 2021-04-30 上海二十冶建设有限公司 Construction method for quickly adjusting position of axis in steel column installation and in-place

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2015055088A (en) * 2013-09-11 2015-03-23 株式会社竹中工務店 Building construction method
JP2020172817A (en) * 2019-04-12 2020-10-22 株式会社大林組 Position adjustment device, and position adjustment method of underground piled column
JP2023078235A (en) * 2019-04-12 2023-06-06 株式会社大林組 Position adjustment device, and position adjustment method of underground piled column
CN112727107A (en) * 2020-12-25 2021-04-30 上海二十冶建设有限公司 Construction method for quickly adjusting position of axis in steel column installation and in-place

Also Published As

Publication number Publication date
JPH0737726B2 (en) 1995-04-26

Similar Documents

Publication Publication Date Title
US5469684A (en) Concrete building frame construction method
JPH07252835A (en) Construction method for diagonal shore strut
JP2001349065A (en) Underground base isolating construction method for existing building
JPH11100854A (en) Building and foundation structure therefor
JPH10152998A (en) Earthquake-resistant reinforcing structure of existing building
JP2700811B2 (en) Construction method of structure including super frame
JPH0485419A (en) Method for constructing underground structure
JP2757026B2 (en) Reverse construction method of basement structure
JP3436104B2 (en) Steel pipe construction method
JP3185129B2 (en) Column-integrated column base fixed foundation structure and its construction method
JPH05179647A (en) Supporting structure for earth retaining wall
JP2002309591A (en) Structure for joining pile head to steel footing beam
JP2000144907A (en) Joint structure between inverted construction post and beam
JP3156025B2 (en) Independent open cut method for large scale and large depth
JPH09228398A (en) Construction method for pile support type multistoried building
JPS63280153A (en) Underground inverted lining method
JPH0232417B2 (en)
JPH05112985A (en) Joint structure of steel column legs
JP3246321B2 (en) Column and pile joint structure
JPH0748847A (en) Steel frame column base section structure for building with underground floor and underground skeleton construction method
JPS6026724A (en) Integration work of steel-framed building structure and composite underground beam
JPH1130053A (en) Construction method of base isolation building
JPH04366229A (en) Temporary corresponding standard used for method of reverse driving construction
JPH0892959A (en) Head-section structure of earth retaining wall
JPH04185822A (en) Constructing method for underground structure

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees