JP2000144907A - Joint structure between inverted construction post and beam - Google Patents

Joint structure between inverted construction post and beam

Info

Publication number
JP2000144907A
JP2000144907A JP10325024A JP32502498A JP2000144907A JP 2000144907 A JP2000144907 A JP 2000144907A JP 10325024 A JP10325024 A JP 10325024A JP 32502498 A JP32502498 A JP 32502498A JP 2000144907 A JP2000144907 A JP 2000144907A
Authority
JP
Japan
Prior art keywords
steel
strut
reverse
inverted construction
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP10325024A
Other languages
Japanese (ja)
Inventor
Minoru Kanazawa
稔 金沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP10325024A priority Critical patent/JP2000144907A/en
Publication of JP2000144907A publication Critical patent/JP2000144907A/en
Pending legal-status Critical Current

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide joint structure between an inverted construction post and a beam capable of connecting the beam with high degree of accuracy of a position and simply to the inverted construction post with allowableness and, at the same time, rationalizing inverted construction skeleton work. SOLUTION: A beam 2 consisting of steel frame or precast concrete is set between inverted construction posts 1 consisting of precast concrete or concrete filled steel pipe or steel pipe. A void between the end of the beam 2 and inverted construction post is filled with shrinkage-compensating mortar 11 and, at the same time, PS steel materials 8 passing through the inverted construction post 1 are fastened with nuts 9 to fix.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、地下部分に逆打支
柱を打設した後、地面を掘削しつつこの逆打支柱に梁部
材を順次接続するようにした逆打支柱と梁との接続構造
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a connection between a back strut and a beam in which, after a back strut is cast in an underground portion, a beam member is sequentially connected to the back strut while excavating the ground. Regarding the structure.

【0002】[0002]

【従来の技術】近年、地下構造物を構築するにあたっ
て、地下部分に逆打支柱を打設した後に地面を掘削して
この逆打支柱を露出し、露出した逆打支柱に順次梁を接
続して地下架構を構築するようにした逆打工法がある。
この逆打工法における地下躯体工事は、具体的には、S
RC(鉄骨鉄筋コンクリート)柱のコアとなる鉄骨柱に
工事中の上部荷重を支持させながら、下方に向かって掘
削工事し、SRC梁のコアとなる鉄骨梁を建て込み、柱
・壁・梁・床の鉄筋コンクリート工事を繰り返し行う方
式である。
2. Description of the Related Art In recent years, when constructing an underground structure, a reverse strut is installed in an underground portion, and then the ground is excavated to expose the reverse strut, and a beam is sequentially connected to the exposed reverse strut. There is a reverse striking method that builds an underground frame.
The underground framing work in this reverse construction method is, specifically,
Excavation work is carried out downward while supporting the upper load during construction on the steel column as the core of the RC (steel reinforced concrete) column, and the steel beam as the core of the SRC beam is built, and the column, wall, beam, floor It is a method to repeat the reinforced concrete work.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、かかる
従来の逆打工法にあっては、逆打支柱を設置する際に
は、逆打支柱の上端部を保持して吊下げ状態で打設する
ようになっているため、この逆打支柱に微妙な傾きが発
生し、当該逆打支柱の建込み精度を確保することが困難
になる。
However, in such a conventional reverse striking method, when installing the reverse strut, it is necessary to hold the upper end of the reverse strut and hang it in a suspended state. Therefore, a slight inclination is generated in the reverse strut, and it is difficult to secure the installation accuracy of the reverse strut.

【0004】建込み精度が十分に確保されていない逆打
支柱の柱芯に梁を接合することは、梁位置をも位置ずれ
させることになる。しかし、逆打工法における鉄骨梁の
建て込みは、上階の躯体工事が完了しており且つ逆打支
柱が周辺地盤に拘束されているために、一般の鉄骨建て
方のように建ち直しが容易には出来ない。
[0004] When a beam is joined to the column core of a reverse strut whose mounting accuracy is not sufficiently ensured, the position of the beam is also shifted. However, steel beams can be easily rebuilt in the reverse-casting method, as in the case of general steel-frame construction, since the upper-floor skeleton construction has been completed and the reverse struts are restrained by the surrounding ground. Can not do.

【0005】このために主として逆打支柱の建て込み精
度に起因する誤差を、掘削後の実測寸法を反映させた鉄
骨梁の製作によって吸収する必要があり、工事消化上厳
しい工程管理を要求される。即ち、逆打支柱の施工精度
が比較的良くないために、溶接により鉄骨梁を建て込む
際には、掘削後の実測寸法に基づき鉄骨梁の部材長さを
切断等して調整することが必要となる。
[0005] For this reason, it is necessary to absorb errors mainly due to the accuracy of the installation of the back strut by the manufacture of a steel beam reflecting the measured dimensions after excavation, and strict process control is required in the construction. . That is, since the construction accuracy of the back strut is relatively poor, when building a steel beam by welding, it is necessary to adjust the length of the steel beam by cutting the length of the steel beam based on the measured dimensions after excavation. Becomes

【0006】一方、鉄筋コンクリート工事を伴う柱・梁
工事には、煩雑な鉄筋・型枠工事の発生、掘削敷に打設
した土間コンクリート上に型枠支保工を組み立てる煩雑
な工事の発生、コンクリート強度発現までこれを存置さ
せることによる工程短縮を阻害する養生の発生等の問題
点がある。
On the other hand, column and beam construction accompanied with reinforced concrete construction involves complicated rebar and formwork construction, complicated construction of assembling a formwork support on soil concrete placed on an excavation floor, and concrete strength. There is a problem such as the occurrence of curing which inhibits the shortening of the process due to the presence of this until expression.

【0007】そこで、本発明の目的は、上記課題を解決
し、逆打支柱に対して許容性をもって、位置精度良好に
かつ簡単に梁を結合することができると共に、逆打ち躯
体工事の合理化を図ることが可能な逆打支柱と梁との接
続構造を提供することにある。
Accordingly, an object of the present invention is to solve the above-mentioned problems, to allow easy connection of beams with good positional accuracy, with tolerance to a back-strut support, and to rationalize the construction of a back-stroke frame. It is an object of the present invention to provide a connection structure between a reverse strut and a beam that can be achieved.

【0008】[0008]

【課題を解決するための手段】上記目的を達成するた
め、本発明による逆打支柱と梁との接続構造は、プレキ
ャストコンクリートもしくはコンクリート充填鋼管又は
鋼管のいずれかから成る逆打支柱の間に、鉄骨又はプレ
キャストコンクリートから成る梁をセットし、この梁の
端部と逆打支柱との間の間隙にグラウト材を充填すると
ともに、逆打支柱に、これに貫通させた鋼材を介して梁
の端部を締結部材により締め付けたことを特徴とする。
In order to achieve the above object, a connection structure between a back strut and a beam according to the present invention is provided between a back strut made of either precast concrete or concrete-filled steel pipe or steel pipe. A beam made of steel frame or precast concrete is set, and the gap between the end of the beam and the striking strut is filled with grout material, and the striking strut is inserted into the end of the beam through a steel material penetrated therethrough. The part is fastened by a fastening member.

【0009】締め付け力が導入される鋼材を用いて梁を
逆打支柱にグラウト材を介して圧着接合する構造であ
り、グラウト材の充填される隙間により施工誤差が容易
に吸収できるため、梁寸法や逆打支柱の建て込みに高い
精度を要求する必要がなくなる。また、逆打支柱を貫通
する鋼材を利用して梁を締結する構造であるため、鉄骨
溶接の作業がなくなる。
A structure in which a beam is press-bonded to a counter strut using a steel material to which a tightening force is introduced through a grout material, and a construction error can be easily absorbed by a gap filled with the grout material. There is no need to require high accuracy for the installation of the struts and the back struts. In addition, since the beam is fastened using a steel material penetrating the reverse strut, the work of welding the steel frame is eliminated.

【0010】従って、逆打支柱にPC(プレキャストコ
ンクリート)柱もしくはCFT(コンクリート充填鋼
管)柱又は鋼管柱のいずれかを用い、更に、梁に鉄骨梁
又はPC(プレキャストコンクリート)梁を用いること
ができて、労働生産性の低い労務集約的な鉄筋・型枠工
事の殆どを削減できる。このため、大幅な生産性の向上
に期待できる。
Therefore, it is possible to use either a PC (precast concrete) column, a CFT (concrete-filled steel pipe) column or a steel pipe column as the back strut and further use a steel beam or a PC (precast concrete) beam as the beam. As a result, most labor-intensive rebar and formwork work with low labor productivity can be reduced. For this reason, a significant improvement in productivity can be expected.

【0011】[0011]

【発明の実施の形態】以下、本発明を図示の実施形態に
基づいて説明する。図1,図2は本発明にかかる逆打支
柱と梁との接続構造の一実施形態を示し、図1は逆打支
柱1と梁2との接続部分の縦断面図、図2は逆打支柱1
と梁2との接続部分の平面図である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described below based on the illustrated embodiment. 1 and 2 show an embodiment of a connection structure between a back strut and a beam according to the present invention. FIG. 1 is a longitudinal sectional view of a connection portion between a back strut 1 and a beam 2, and FIG. Prop 1
FIG. 3 is a plan view of a connection portion between the beam and a beam 2.

【0012】図3に示すように、地下部分に所定間隔で
打設された逆打支柱1間に、梁2が掘削敷3上の梁建て
込みクレーン4によりセットされる。図中、5は逆打支
柱1の下部に設けた場所打コンクリート杭、6は土留壁
を示す。
As shown in FIG. 3, a beam 2 is set by a crane 4 on a digging floor 3 between a striking column 1 installed at a predetermined interval in an underground portion. In the figure, 5 is a cast-in-place concrete pile provided at the lower part of the reverse strut 1, and 6 is a retaining wall.

【0013】この実施形態の場合、図1,図2に示すよ
うに、逆打支柱1は長方形断面の角形鋼管1a中にコン
クリート1bを充填したCFT(コンクリート充填鋼
管)柱から成り、一方、梁2はH形鋼から成る鉄骨梁で
構成されている。これは鉄筋・型枠工事が不要となるか
らである。従って、同じ観点から、逆打支柱1としては
CFT柱の代わりにPC(プレキャストコンクリート)
柱又は鋼管柱を用いることができ、また、梁2として鉄
骨梁の代わりにPC梁を用いることもできる。
In the case of this embodiment, as shown in FIGS. 1 and 2, the back strut 1 is made of a CFT (concrete-filled steel pipe) column in which concrete 1b is filled in a rectangular steel pipe 1a having a rectangular cross section. Reference numeral 2 is a steel beam made of H-section steel. This is because rebar and formwork work is not required. Therefore, from the same viewpoint, PC (precast concrete) is used as the back strut 1 instead of the CFT column.
A column or a steel tube column can be used, and a PC beam can be used as the beam 2 instead of a steel beam.

【0014】逆打支柱1の間に鉄骨梁2をセットした場
合、その鉄骨梁2端部の長方形のエンドプレート7が逆
打支柱1の側面に四方向から対向することになる。
When the steel beam 2 is set between the reverse struts 1, the rectangular end plate 7 at the end of the steel beam 2 faces the side surface of the reverse strut 1 from four directions.

【0015】この後、鉄骨梁2の端部のエンドプレート
7と逆打支柱1の側面との間の間隙にグラウト材として
無収縮モルタル11が充填される。
Thereafter, the gap between the end plate 7 at the end of the steel beam 2 and the side surface of the back strut 1 is filled with a non-shrink mortar 11 as a grout material.

【0016】さらに、この鉄骨梁2のエンドプレート7
には、逆打支柱1に貫通させた棒状のPS鋼材8の端部
が挿通され、このPS鋼材8はその突出端部に螺着され
た締結部材としてのナット9より締め付けられて締め付
け力が導入される。
Further, the end plate 7 of the steel beam 2
The end of a rod-shaped PS steel material 8 penetrated through the reverse strut 1 is inserted through the back strut 1, and the PS steel material 8 is tightened by a nut 9 as a fastening member screwed to the protruding end thereof, and a tightening force is applied. be introduced.

【0017】即ち、逆打支柱1には、通常PS(プレス
トレス)入力用としてPS鋼材8と共に用いられている
シース10が、上記PS鋼材8を通すべき位置に対応さ
せて貫通状態で予め設けられており、このシース10中
に、PS鋼材8が通される。そして、このPS鋼材8の
両端部がそれぞれ鉄骨梁2のエンドプレート7の小孔を
通して他側に突出され、その突出端部のネジ部に締結部
材としてのナット9が螺着され、締め付けられる。これ
により、鉄骨梁2が逆打支柱1にしっかりと接合され
る。特に、逆打支柱1を貫通するPS鋼材8を利用して
鉄骨梁2を締結する構造であるため、鉄骨溶接の作業が
必要なくなる。
That is, a sheath 10 usually used together with a PS steel material 8 for inputting PS (prestress) is provided in advance in the reverse strut 1 in a penetrating state corresponding to a position where the PS steel material 8 is to be passed. The PS steel material 8 is passed through the sheath 10. Then, both ends of the PS steel material 8 are projected to the other side through small holes of the end plate 7 of the steel beam 2, and a nut 9 as a fastening member is screwed into a threaded portion of the projected end and tightened. Thereby, the steel beam 2 is firmly joined to the reverse strut 1. In particular, since the structure is such that the steel beam 2 is fastened using the PS steel material 8 penetrating the reverse strut 1, the work of welding the steel frame is unnecessary.

【0018】以上述べたように、本実施形態は、逆打工
事の合理化のために次のように改善したものである。 (1) 逆打支柱1の工事合理化のために、鉄筋・型枠工事
が要らないCFT柱を逆打支柱1として採用する。 (2) 梁2の工事合理化のために、梁2の構造を鉄筋・型
枠工事の要らない純鉄骨造とする。 (3) 逆打支柱1の建て込みの施工誤差に対する対応を簡
単にするために、この施工誤差が容易に吸収できる圧着
接合法により、つまり締め付け力が導入されるPS鋼材
8を用いて鉄骨梁2を逆打支柱1に無収縮モルタル11
を介して接合する構造によって柱・梁接合部を構成す
る。
As described above, the present embodiment is improved as described below in order to rationalize the reverse hitting work. (1) In order to rationalize the construction of the back strut 1, a CFT column that does not require rebar and formwork will be adopted as the back strut 1. (2) In order to rationalize the construction of the beam 2, the structure of the beam 2 will be a pure steel frame that does not require rebar and formwork. (3) In order to make it easy to cope with the construction error of the installation of the reverse strut 1, a steel beam using the PS steel material 8 into which the tightening force is introduced, that is, by the crimping method which can easily absorb the construction error. Non-shrink mortar 11
The column / beam joint is constituted by a structure that is joined through the joint.

【0019】この改善により、次の効果が期待できる。With this improvement, the following effects can be expected.

【0020】(a) 労働生産性の低い労務集約的な鉄筋・
型枠工事の殆どを削減できるために大幅な生産性の向上
に期待できる。即ち、逆打工法の地下躯体工事におい
て、従来のSRC柱とSRC梁を用いて建て込み、柱・
壁・梁・床の鉄筋コンクリート工事を繰り返し行う場合
に比べ、柱及び梁の鉄筋・型枠・コンクリートの各工事
に代表される煩雑な作業が不要となって、生産性を向上
させることができる。
(A) Labor-intensive steel bars with low labor productivity
Since most of the formwork work can be reduced, significant productivity improvement can be expected. In other words, in the underground construction of the reverse driving method, the existing SRC columns and SRC beams are used to build
Compared with the case where the reinforced concrete work of the wall, the beam and the floor is repeatedly performed, complicated work typified by the work of the reinforced concrete, the formwork and the concrete of the column and the beam is not required, and the productivity can be improved.

【0021】(b) 逆打支柱1に用いるCFT柱は柱・梁
接合部の応力伝達性状が鉄筋コンクリートのそれと同じ
であり、従って鉄骨加工手間を多く必要とするダイヤフ
ラムを梁支持のために設ける必要がなく、鉄骨製作コス
トの低減が可能である。
(B) The CFT column used for the back strut 1 has the same stress transmission characteristics at the column-beam joint as that of the reinforced concrete. Therefore, it is necessary to provide a diaphragm for supporting the beam which requires much time and labor for steel frame processing. Therefore, the cost of manufacturing a steel frame can be reduced.

【0022】(c) PS鋼材8により逆打支柱1の側面に
無収縮モルタル11を介して鉄骨梁2を圧着接合する構
造であって、逆打支柱1の施工誤差が鉄骨梁2端部のモ
ルタル充填代で吸収できるため、実測値に基づく鉄骨寸
法の調整が不要であり、鉄骨製作コストの低減や円滑な
工程消化ができる。
(C) A structure in which the steel beam 2 is pressure-bonded to the side surface of the back strut 1 by the PS steel material 8 via the non-shrink mortar 11, and the construction error of the back strut 1 is Since it can be absorbed by the mortar filling allowance, it is not necessary to adjust the steel frame dimensions based on the actually measured values, and it is possible to reduce the steel frame manufacturing cost and smoothly complete the process.

【0023】(d) 以上のメリットの相乗効果により、大
幅な工期短縮と現場労務コストの低減が可能である。
(D) By the synergistic effect of the above advantages, it is possible to greatly shorten the construction period and reduce the on-site labor cost.

【0024】上記実施形態では、鉄骨梁2を逆打支柱1
の間にセットして、鉄骨梁2の端部と逆打支柱1間の間
隙を無収縮モルタル11でグラウトした後、強度発現を
待ち、逆打支柱1に貫通させたPS鋼材8で締め付ける
ことにより、鉄骨梁2を逆打支柱1に対して接合するよ
うにしたが、鉄骨梁2の端部を逆打支柱1に対してPS
鋼材8で締め付けて接合した後に、鉄骨梁2端部と逆打
支柱1間の間隙を無収縮モルタルでグラウトすることも
できる。
In the above embodiment, the steel beam 2 is connected to the back strut 1
After grouting the gap between the end of the steel beam 2 and the back strut 1 with the non-shrink mortar 11, wait for the strength to develop and tighten with the PS steel material 8 penetrated through the back strut 1. To join the steel beam 2 to the reverse strut 1, but the end of the steel beam 2 is
After tightening and joining with the steel material 8, the gap between the end of the steel beam 2 and the back strut 1 can be grouted with non-shrink mortar.

【0025】この形態も、PS鋼材8への導入締め付け
力を利用しつつ、鉄骨梁2を逆打支柱1の側面に無収縮
モルタル11を介して圧着接合した構造であり、無収縮
モルタル11の充填される隙間により施工誤差が容易に
吸収できるため、逆打支柱1に高い精度を要求する必要
がなくなる。
This embodiment also has a structure in which the steel beam 2 is pressure-bonded to the side surface of the reverse strut 1 via the non-shrinkable mortar 11 while utilizing the tightening force introduced into the PS steel material 8. Since the construction error can be easily absorbed by the gap to be filled, it is not necessary to request the back strut 1 to have high accuracy.

【0026】[0026]

【発明の効果】以上説明したように本発明によれば、締
め付け力が導入される鋼材を用いて梁を逆打支柱にグラ
ウト材を介して圧着接合する構造であり、グラウト材の
充填される隙間により施工誤差が容易に吸収できるた
め、梁寸法や逆打支柱の建て込みに高い精度を要求する
必要がなくなる。また、逆打支柱を貫通する棒状の鋼材
を利用して梁を締結する構造であるため、鉄骨溶接の作
業がなくなる。
As described above, according to the present invention, there is provided a structure in which a beam is press-bonded to a counter strut using a steel material to which a tightening force is introduced via a grout material, and the grout material is filled. Since gaps can easily absorb construction errors, there is no need to require high accuracy in beam dimensions and in building back struts. Further, since the beam is fastened by using a bar-shaped steel material penetrating the reverse strut, the work of welding the steel frame is eliminated.

【0027】従って、逆打支柱にPC柱もしくはCFT
柱又は鋼管柱のいずれかを用い、更に、梁に鉄骨梁又は
PC梁を用いることができて、労働生産性の低い労務集
約的な鉄筋・型枠工事の殆どを削減できる。このため、
大幅な生産性の向上に期待できる。
Therefore, the PC column or CFT is used as the reverse strut.
Either a column or a steel pipe column can be used, and further, a steel beam or a PC beam can be used for the beam, so that most labor-intensive rebar and formwork work with low labor productivity can be reduced. For this reason,
It can be expected to greatly improve productivity.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の一実施形態に係る逆打支柱と梁との接
続構造の縦断面図である。
FIG. 1 is a longitudinal sectional view of a connection structure between a reverse strut and a beam according to an embodiment of the present invention.

【図2】本発明の一実施形態に係る逆打支柱と梁との接
続構造の平面図である。
FIG. 2 is a plan view of a connection structure between a reverse strut and a beam according to an embodiment of the present invention.

【図3】本発明の一実施形態に係る逆打工法による地下
躯体工事の様子を示した図である。
FIG. 3 is a view showing a state of underground skeleton construction by a reverse striking method according to an embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 逆打支柱 1a 角形鋼管 1b コンクリート 2 梁 3 掘削敷 4 梁建て込みクレーン 5 場所打コンクリート杭 6 土留壁 7 エンドプレート 8 棒状の鋼材 9 ナット(締結部材) 10 シース 11 無収縮モルタル(グラウト材) DESCRIPTION OF SYMBOLS 1 Reverse strut 1a Square steel pipe 1b Concrete 2 Beam 3 Excavation floor 4 Beam crane 5 Cast-in-place concrete pile 6 Retaining wall 7 End plate 8 Bar-shaped steel material 9 Nut (fastening member) 10 Sheath 11 Non-shrink mortar (grout material)

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 プレキャストコンクリートもしくはコン
クリート充填鋼管又は鋼管のいずれかから成る逆打支柱
の間に、鉄骨又はプレキャストコンクリートから成る梁
をセットし、この梁の端部と逆打支柱との間の間隙にグ
ラウト材を充填するとともに、逆打支柱に、これに貫通
させた鋼材を介して梁の端部を締結部材により締め付け
たことを特徴とする逆打支柱と梁との接続構造。
1. A beam made of steel frame or precast concrete is set between a striking strut made of either precast concrete or concrete-filled steel pipe or steel pipe, and a gap between an end of the beam and the striking strut is set. Characterized in that the grouting material is filled into the backing strut and the end of the beam is fastened to the striking strut by a fastening member via a steel material penetrating the grouting strut.
JP10325024A 1998-11-16 1998-11-16 Joint structure between inverted construction post and beam Pending JP2000144907A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10325024A JP2000144907A (en) 1998-11-16 1998-11-16 Joint structure between inverted construction post and beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10325024A JP2000144907A (en) 1998-11-16 1998-11-16 Joint structure between inverted construction post and beam

Publications (1)

Publication Number Publication Date
JP2000144907A true JP2000144907A (en) 2000-05-26

Family

ID=18172301

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10325024A Pending JP2000144907A (en) 1998-11-16 1998-11-16 Joint structure between inverted construction post and beam

Country Status (1)

Country Link
JP (1) JP2000144907A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100767926B1 (en) * 2005-05-13 2007-10-18 이창남 Error absorbing fixing device of compression or flexural compression horizontal members with eccentrically arranged vertical members
KR100773410B1 (en) * 2001-12-21 2007-11-05 재단법인 포항산업과학연구원 I-shape steel girder with reinforcement
KR101124446B1 (en) 2011-06-13 2012-03-26 주식회사 포스코건설 Combining apparatus and guiding bracket for joint portion of concrete filled tube and combining method using the same
CN109577653A (en) * 2017-09-29 2019-04-05 青岛理工大学 Mounting method of flange bolt welding hybrid connection assembly type beam-column joint
TWI743549B (en) * 2019-08-30 2021-10-21 林培元 Pillar-in-pillar construction method of supporting pillars in reverse driving engineering
CN113605442A (en) * 2021-06-30 2021-11-05 广东省建筑设计研究院有限公司 Sand tank connecting node structure for empty face of basement

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100773410B1 (en) * 2001-12-21 2007-11-05 재단법인 포항산업과학연구원 I-shape steel girder with reinforcement
KR100767926B1 (en) * 2005-05-13 2007-10-18 이창남 Error absorbing fixing device of compression or flexural compression horizontal members with eccentrically arranged vertical members
KR101124446B1 (en) 2011-06-13 2012-03-26 주식회사 포스코건설 Combining apparatus and guiding bracket for joint portion of concrete filled tube and combining method using the same
CN109577653A (en) * 2017-09-29 2019-04-05 青岛理工大学 Mounting method of flange bolt welding hybrid connection assembly type beam-column joint
TWI743549B (en) * 2019-08-30 2021-10-21 林培元 Pillar-in-pillar construction method of supporting pillars in reverse driving engineering
CN113605442A (en) * 2021-06-30 2021-11-05 广东省建筑设计研究院有限公司 Sand tank connecting node structure for empty face of basement

Similar Documents

Publication Publication Date Title
JP2006291575A (en) Retaining wall and method of constructing the same
JP2006132303A (en) Fixing structure of steel frame stud to reinforced concrete beam
JP2831909B2 (en) Connection structure of steel columns, piles and foundation beams
JP3700102B2 (en) Building basic structure
JP2000144907A (en) Joint structure between inverted construction post and beam
JP2007277913A (en) Joining structure of column base part and its construction method
JP2004011203A (en) Precast src-column joining section structure
JP2002242302A (en) Beam-column connection structure of building steel frame and its connecting method
JP3929006B2 (en) Construction method for expanded seismic walls
JPH11343667A (en) Structure for fixing column base with underground beam made of reinforced concrete
JP2880027B2 (en) Joint structure between steel pipe column and reinforced concrete slab
KR20210026900A (en) Joining method of precast concrete pillar and girderin concrete structure
JP2002021096A (en) Building and constructing method therefor
JPH09151463A (en) Column-integrated column base anchoring foundation structire and work execution method therefor
JP3319709B2 (en) Construction method of prestressed concrete steel beam
KR20130051183A (en) Seismic resistant reinforcement structures and the reinforcing method using it
JPH101956A (en) Underground construction method for building
JP2907807B1 (en) Tunnel construction method
JPH06173273A (en) Slope stabilizing construction method
JPH06248722A (en) Joining method for precast reinforcement concrete earthquake resisting wall and steel frame beam
JP2001254365A (en) Junction structure between column and pile
JP2003261949A (en) Composite wall formed of earth retaining core and underground exterior wall and its construction method
JPH11181807A (en) Construction method for underground story
JP2000319904A (en) Foundation of structure
JP2002364184A (en) Method of reconstructing existing building