JPH02266014A - Constructing underground structure eliminating use of temporary material - Google Patents

Constructing underground structure eliminating use of temporary material

Info

Publication number
JPH02266014A
JPH02266014A JP1084989A JP8498989A JPH02266014A JP H02266014 A JPH02266014 A JP H02266014A JP 1084989 A JP1084989 A JP 1084989A JP 8498989 A JP8498989 A JP 8498989A JP H02266014 A JPH02266014 A JP H02266014A
Authority
JP
Japan
Prior art keywords
retaining wall
floor
ground
construction
underground structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP1084989A
Other languages
Japanese (ja)
Other versions
JP2736542B2 (en
Inventor
Kiyoshi Oshima
基義 大島
Koichi Sano
佐野 紘一
Kenji Takahashi
賢司 高橋
Masaaki Kakurai
正昭 加倉井
Masanobu Hoshi
星 正信
Hirotsune Terada
寺田 尋恒
Fuminobu Tanifuji
谷藤 文信
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP1084989A priority Critical patent/JP2736542B2/en
Publication of JPH02266014A publication Critical patent/JPH02266014A/en
Application granted granted Critical
Publication of JP2736542B2 publication Critical patent/JP2736542B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Abstract

PURPOSE:To construct an underground structure using almost no temporary materials and to contrive to reduce term of works and cost by constructing the structure with SC beams, PC boards or the like installed using landslide protection walls made of soil cement with H shape core materials dropped therein and frame center columns. CONSTITUTION:Landslide protection walls 1 made of soil cement 2 and 5 with H shape steel core materials 3 dropped therein and with the lower ends of the required core materials 3 reached bearing subsoil 4 and frame center columns 7 that are positioned at common centers C of an underground structure are installed. Then the ground 8 is excavated to a depth bearable for construction of floor framing for an aboveground story, and SC beams 10 incorporating steels are installed between the wall 1 and the columns 7 and between each of the columns 7, and PC boards 11 are installed thereon. Slab concrete 12 is then placed thereon and beams 13 and columns 14, doubling as wales, are further placed. By repeating the above-mentioned processes, the underground structure is constructed by advancing works in series toward the lower stories with employment of reverse casting method. Normal casting method in which works are advanced in series toward the upper stories may be employed.

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、ソイル柱列による山留め壁を施工して建物
の地下構造物などを順打ち工法又は逆打ぢ工法で構築す
る場合の施工法に係り、ざらに云えは、山留め用の切梁
や腹起し相なとの仮設材はほとんど必要としない地下構
造物の施工法に関する。
[Detailed Description of the Invention] Industrial Field of Application This invention relates to a construction method for constructing an underground structure of a building by constructing a retaining wall using a series of soil pillars using the forward pouring method or the reverse pouring method. , Zara-Ni-e relates to a construction method for underground structures that requires almost no temporary materials such as sills for retaining the piles and sills.

従来の技術 ■ 従来、建物の地下構造物を施工する場合は、当ρ(
のように地下構造物の外周に山留め壁を仮設し、地盤の
l掘削の進捗に合わせて腹起し材や切梁を糾み入れてI
llff1次に山留め壁の補剛を行なう山留め工法が実
施されている。従って、かなり大量の仮設祠を必要とし
、仮設工事に相当な工門を消費しているのが実情である
Conventional technology ■ Conventionally, when constructing an underground structure for a building, the
A retaining wall is temporarily installed around the outer periphery of the underground structure, and as the ground excavation progresses, upholstery materials and struts are added.
llff1 Next, the mountain retaining construction method is being implemented to stiffen the retaining wall. Therefore, the reality is that a considerable amount of temporary shrines are required, and a considerable amount of construction time is consumed for temporary construction.

■  この点、山留め工事用の仮設イ」費の節減を目的
とした、例えば特開昭6 3 − 2 4− 7 4 
2 3号公報に記載された地下構造物の施工法の場合は
、高価な地下連続壁を地下構造物の基S<一部分)とし
て利用する手段が開示されている。
■ In this regard, for example, Japanese Patent Application Laid-Open No. 1983-3-2 4-7 4 aimed at reducing the cost of temporary construction for mountain retaining work.
In the case of the method for constructing an underground structure described in Publication No. 2-3, a method is disclosed in which an expensive underground continuous wall is used as the base S<part of the underground structure.

■ その他、■]鋼を芯材とするソイル柱列を地下外壁
の一部として利用する工法も従来公知に属する。
■In addition, ■] A method of using soil columns with steel as a core material as part of the underground outer wall is also conventionally known.

本発明か解決しようとする課題 (1)l述したように、建設工事費に占める山留め工事
費、例えばH鋼を芯材とするソイル柱列の施工や切梁、
腹起し祠などを仮設し又は撤去するための所謂仮設祠費
の割合はかなり大きい。然るにこうした仮設材は、地下
構造物の施工時にのみ必要で、山留め工事の終了時(必
要性がなくなったとぎ)には、ソイル柱列にあっては埋
め殺され、切梁や腹起し材は全部撤去しかりればならな
い。要するに、仮設材の無駄は計りしれず、そして、切
梁や腹起し祠の解体時には危険作業を余儀なくされると
云う二重、三重の不都合があり、大きな問題点になって
いる。
Problems to be solved by the present invention (1) As mentioned above, the cost of retaining the piles in the construction cost, for example, the construction of soil columns with H steel as the core material, the construction of struts, etc.
The cost of so-called temporary shrines for temporarily erecting or removing Haraoki-shrines is quite large. However, these temporary materials are only needed when constructing the underground structure, and when the heap retaining work is completed (no longer needed), the soil column rows are buried, and the struts and upholstery materials are replaced. must be completely removed. In short, the waste of temporary construction materials is immeasurable, and dangerous work is forced when dismantling the beams and haragorishi shrines, creating a double or triple inconvenience that has become a major problem.

(2) この点、」1記■に述べた特開昭63−2 4
、 7 4. 2 3号公報に記載された施工法のよう
に、地下連続壁を地下構造物の基礎に利用し、あるいは
また、」1記■て述べたようにソイル柱列を地下外壁の
一部に利用する施工法は、仮設材積の無駄を削減する改
良案という点てかなり評価できる。
(2) On this point, JP-A-63-2-4 mentioned in 1.
, 7 4. 2 As in the construction method described in Publication No. 3, an underground continuous wall can be used as the foundation of an underground structure, or as described in 1. This construction method can be highly evaluated as an improved proposal for reducing wasted temporary construction materials.

しか腰 前者は大規模な高層ないし超高層建物の建設の
ときに限って採用される高価な地下連続壁を前提とした
施工法であり、中小規模の中低層建物への適用の可能性
はないに等しい。後考は、逆に中低層建物に実施される
施工法ではあるが、前者の場合も含めて、いまだ切梁や
腹起し祠なとの必要性まで解消するには至らず、切梁や
腹起し14に関する無駄の解決ができていないから、依
然として解決するべき課題が残されているのである。
However, the former is a construction method that assumes an expensive underground continuous wall that is only used when constructing large-scale high-rise or super-high-rise buildings, and there is no possibility of its application to small- to medium-sized and low-rise buildings. be equivalent to. In hindsight, this is a construction method that is used for medium- and low-rise buildings, but even in the former case, the need for sills and harakori shrines has not yet been eliminated; Since the waste related to the tummy tuck 14 has not been resolved, there are still issues to be solved.

課題を解決するための手段 (第1の発明) 」1記従来技術の課題を解決するための手段として、第
1の発明に係る仮設材を省略した地下構造物の施工法は
、云わば逆打ち工法に属するものてあって、それは図面
の第1図から第7図に好適な実施例を示した通り、 山留め壁を施工し、地盤を掘削してそこに地下構造物を
構築する施工法において、 イ) 山留め壁1は、ソイルセメント2の中に11鋼芯
材3を落し込み、かつ要所位置のIJ鋼芯材の下端は支
持層4に到達せしめたソイル柱列によって形成する。ま
た、地下構造物の通心Cにおける柱の位置には、やはり
ソイルセメント5の中に1(銅芯祠6を落し込み、かつ
その下端を支持層4に到達せしめた構真柱7を設置する
段階ど、 口〉 地盤8を地上階の床組の構築に支障ない程度の深
さまで掘削する段階と、 ハ) 山留め壁1及び構真柱7の■1鋼芯材3と6を露
出させ、構真柱相互のH鋼芯材6,6の間、及び構真柱
7と山留め壁1それぞれのH銅芯祠3.60間に本設1
9ζ骨9を内蔵したプレキャストコンクU −1−梁1
0を架けて接合し、こうして架設されたプレキャストコ
ンクリート梁1010の上にプレキャストコンクリ−1
・版11を架設して敷き詰め、その上に現場打ちのスラ
ブコンクリート12を打設し、かつ山留め壁1に沿って
は腹起し材兼用の梁】3を、そして、構真柱7の位置に
は本設の柱14をそれぞれ現場打ちコンクリートで打設
する段階と、 二) さらに地盤8の掘削を地下1階の床組を構築可能
な深ざまで進め、前記ハ)の工程を行ない、以下同様の
工程を繰り返す段階と、から成ることを特徴とする。
Means for Solving the Problems (First Invention) As a means for solving the problems of the prior art described in 1., the construction method of underground structures omitting temporary materials according to the first invention is, so to speak, the opposite. This method belongs to the pouring construction method, and as the preferred embodiments are shown in Figures 1 to 7 of the drawings, it is a construction method in which a retaining wall is constructed, the ground is excavated, and an underground structure is constructed there. A) The retaining wall 1 is formed by dropping the 11 steel core material 3 into the soil cement 2, and the lower ends of the IJ steel core materials at key positions are formed by rows of soil columns that reach the support layer 4. In addition, at the position of the pillar in the center C of the underground structure, a structural pillar 7 is also installed in which the copper core shrine 6 is dropped into the soil cement 5 and its lower end reaches the support layer 4. The step of excavating the ground 8 to a depth that does not interfere with the construction of the ground floor floor structure, and c) exposing the retaining walls 1 and ■1 steel core materials 3 and 6 of the structural pillars 7. , permanent installation 1 between the H steel core members 6 and 6 between the structural pillars, and between the H copper cores 3.60 of the structural pillars 7 and the retaining walls 1, respectively.
Precast conch U-1-beam 1 with built-in 9ζ bone 9
The precast concrete beams 1010 are placed on top of the precast concrete beams 1010 constructed in this way.
・Erect and lay the slabs 11, place the cast-in-place slab concrete 12 on top of it, and install the beams] 3 which also serve as raising materials along the retaining wall 1, and set the position of the structural pillars 7. 2) Further, the excavation of the ground 8 is continued to a depth that allows the construction of the first basement floor, and the step 3) is carried out. It is characterized by comprising the following steps of repeating the same steps.

作   用 ソイル柱列による山留め壁1は、地盤8を地」二階の床
組の構築に支障ない程度の深ざ(およそ2〜3n]<ら
い)まて掘削する間は、地盤8の崩壊を防くたけの強度
、剛性を発揮する。
Function: The retaining wall 1 formed by the row of soil pillars prevents the collapse of the ground 8 while excavating the ground 8 to a depth (approximately 2 to 3 nm) that does not interfere with the construction of the second floor floor. Demonstrates strength and rigidity to prevent damage.

山留め壁1及び構真柱7は、各々のソイルセメント2,
5を借壊することにより、中のH&li1.E:祠3.
6を簡単に必要なたけ(叉は必要な部分たり〉露出させ
ることかできる。
The retaining wall 1 and the structure pillar 7 are made of soil cement 2,
By renting out 5, the inside H&li1. E: Shrine 3.
6 can be easily exposed as much as necessary (or as much as necessary).

かくして露出された■]鋼芯材3.6の間及び6゜60
間にそれぞれ本設用鉄骨(H鋼)9を内蔵したブレギヤ
ストコンクリート ず)10を架けて接合することにより、このSCClO
2山留め壁1を内側から支持する切梁の働きをする他、
そのまま本設の梁とされる。
■] steel core material 3.6 and 6°60 thus exposed
This SCClO
In addition to functioning as a strut to support the double retaining wall 1 from the inside,
It is considered to be the permanent beam.

前記SC梁10.10の上に架設したブレキャス)・コ
ンクリ−1・版(以下20版と略す)11がスラブコン
クリート120床型枠の代用ともなる。
The slab concrete 120 (hereinafter abbreviated as 20th edition) 11 can also be used as a substitute for the slab concrete 120 floor formwork.

山留め壁1に沿ってその内側に打設された梁13は、山
留め壁1を内側から補則する腹起し材の働きを兼ねる。
The beam 13 cast along the inside of the retaining wall 1 also serves as a raised member that supports the retaining wall 1 from the inside.

また、構真柱7の位置には、H鋼芯材6を補強鉄骨とす
る本設の鉄骨鉄筋コンクリ−1・柱14か打設される。
In addition, at the position of the structural pillar 7, a permanent steel-reinforced concrete column 14 having the H steel core material 6 as a reinforcing steel frame is cast.

上述のようにして完成された地上階の床組の鉛直荷重は
、山留め壁1及び構真柱7のH鋼芯材3。
The vertical load of the ground floor floor assembly completed as described above is the H steel core material 3 of the retaining wall 1 and the structural pillar 7.

6を通して支持層4へ伝達して支持される。6 and is transmitted to the support layer 4 and supported.

かくして地上階の床組が完成した後は、SCClO2補
強された出留め壁1は、地盤8をざらに深く掘削するこ
とが可能となり、地下1階の床組を構築可能な深さまで
掘削を進め、地下1階の床キ■の構築に進むことができ
る。
In this way, after the floor assembly for the ground floor is completed, it becomes possible to excavate the ground 8 roughly and deeply for the retaining wall 1 reinforced with SCClO2, and the excavation is continued to a depth where the floor assembly for the first basement floor can be constructed. , you can proceed with the construction of the first basement floor.

(第2の発明) 同じく」二記1に来技術の課題を解決するだめの手段と
して、第2の発明に係る仮設材を省略した地下構造物の
施工法は、云わは順打ち工法に属するものであって、 山留め壁を施工腰 地盤を掘削してそこに地下構造物を
構築する施工法において、 イ) 山留め壁1は、ソイルセメント2の中に11鋼芯
材3を落し込み、かつ要所位置のIJ鋼芯材の下端は支
持層4に到達せしめたソイル柱列によって形成する。ま
た、地下構造物の通心Cにおける柱の位置には、やはり
ソイルセメント5の中に1(鋼芯材6を落し込み、かつ
その下端を支持N4に到達せ−しめた構真柱7を設置す
る段階と、 口) 地盤8を地上階の床組の構築に支障ない程度の深
さまで1届削する段階と、 ハ) 山留め壁1及び構真柱7のH構芯材3,6を必要
なたけ露出させ、構真柱7相互のH鋼芯材6,6の間、
及び構真柱7と山留め壁1それぞれのIJ鋼銅芯3.6
の間に本設鉄骨9を内蔵したSCCl2O架けて接合す
ると共に山留め壁1に沿って腹起し材兼用の梁13を構
築する段階と、 二) さらに地盤の掘削を地下1階の床組な構築可能な
深さまで進め、前記ハ)の工程を行ない、以下同様の工
程を繰り返して最下層まて地盤の掘削を完成する段階と
、 ボ) 最下層階から順次上層階に向かって、前記工程に
より架設されたSC梁】0の上にPC版11を架設梁の
上に現場打ちのスラブコンクリ−1・12を打設し、出
留め壁1の部位には構造物外壁】5を、そして、構真柱
7の位置には本設柱J4をそれぞれ現場打ちコンクリー
トて打設する工程をくり返す段階と、 から成ることを特徴とする。
(Second invention) Similarly, as a means of solving the problem of the technology mentioned in Section 2, 1, the method of constructing an underground structure omitting temporary materials according to the second invention belongs to the so-called sequential construction method. In the construction method of excavating the ground and constructing an underground structure there, a) The retaining wall 1 is constructed by dropping 11 steel core material 3 into soil cement 2, and The lower ends of the IJ steel cores at strategic locations are formed by rows of soil columns that reach the support layer 4. In addition, at the position of the column in the center C of the underground structure, there is also a structure column 7 with a steel core 6 dropped into the soil cement 5 and its lower end reaching the support N4. (1) Excavation of the ground 8 to a depth that does not interfere with the construction of the ground floor floor structure, and (3) The step of installing the H-framework members 3 and 6 of the retaining walls 1 and the structural pillars 7. Between the H steel core members 6 and 6 of the structural pillars 7,
And IJ steel copper core 3.6 of each of structural pillar 7 and retaining wall 1
2) A step of constructing a beam 13 which also serves as an upright material along the retaining wall 1, and 2) further excavating the ground to assemble the floor of the first basement floor. Proceed to a depth that allows for construction, perform the process in c) above, repeat the same process to complete the excavation of the ground until the lowest level; PC board 11 was erected on top of the SC beam] 0. Cast-in-place slab concrete 1 and 12 were placed on the beam, and the structure exterior wall 5 was placed on the retaining wall 1, and , repeating the process of placing the main pillar J4 at the position of the structural pillar 7 by pouring concrete on site, respectively.

作   用 山留め壁1、構真柱7、及びそれらのIJ鋼芯桐3.6
の間に架設されたSCCl2O働きは、夫々上記第1の
発明と同しである。
Function retaining wall 1, structural pillar 7, and their IJ steel core paulownia 3.6
The functions of SCCl2O installed between the two are the same as those in the first invention.

本発明の場合は、SCCl2O切梁として働かせたまま
、とりあえず地盤8の掘削を最下層まで先行して行い、
その後に最下層階から順次上層階に向かってスラブコン
クリート12の打設、本設柱14及び構造物外壁15の
打設などを遂行する順打ち工法に特徴を有する。
In the case of the present invention, excavation of the ground 8 is carried out in advance to the lowest layer while the SCCl2O strut is working,
It is characterized by a sequential pouring method in which the concrete slabs 12 are poured, the main pillars 14 and the outer walls 15 of the structure are poured, etc., from the lowest floor to the upper floors.

実  施  例 次に、図示した本発明の詳細な説明する。Example The illustrated invention will now be described in detail.

まず第1図は、構築しようとする地下構造物の地下外壁
の部位には、オーカーによりクラウドを注入しつつ穿孔
撹拌して形成したソイルセメン!・2の中に本設用のH
鋼芯材3を落し込んたソイル柱列による山留め壁1を設
置し、また、当該地下構造物に於ける柱梁の逆心Cの位
置にもソイルセメント5の中に本設用のH1芯+A6を
落し込んて成る構真柱7を設置した段階の平面配置を示
している。山留め壁1及び構真柱7のH鋼芯材3,6の
うち要所位置のものは、夫々第3図に示したように、下
端を支持層4にまで到達せしめると共に該IJ鋼芯材3
,6の下端部には耐圧用鋼板16を溶接又はボルト接合
により取り伺けて先端支持力の増強が行なわれている。
First of all, Figure 1 shows soil cement formed by drilling and stirring while injecting cloud with ocher into the underground outer wall of the underground structure to be constructed.・H for permanent installation in 2
A retaining wall 1 is installed with a row of soil columns into which the steel core material 3 is dropped, and a H1 core for permanent installation is installed in the soil cement 5 at the opposite center C of the column and beam in the underground structure. It shows the planar arrangement at the stage where the structural pillar 7 formed by dropping +A6 is installed. As shown in FIG. 3, the H steel core materials 3 and 6 of the retaining wall 1 and the structural pillar 7 are located at key positions, and their lower ends reach the support layer 4, and the IJ steel core materials 3
, 6, a pressure-resistant steel plate 16 is attached by welding or bolting to the lower end portions to increase the supporting force at the tip.

この)」銅芯祠3,6は、打撃をしない埋め込み杭とさ
れている。そのため山留め壁1及び構真柱7のソイルセ
メント2,5の支持層近傍部分は、水セメント比を50
〜70%くらいの冨調合とした根固め液を使用して根固
め部分17を形成し、もってH鋼芯材3.6が負担する
鉛直荷重(支持力)を支持層4へ伝達可能に構成されて
いる。
The copper core shrines 3 and 6 are embedded piles that do not need to be struck. Therefore, in the vicinity of the support layer of the soil cement 2 and 5 of the retaining wall 1 and the structure pillar 7, the water-cement ratio is 50.
The foot hardening part 17 is formed using a root hardening solution with a concentration of ~70%, thereby making it possible to transmit the vertical load (supporting force) borne by the H steel core material 3.6 to the support layer 4. has been done.

第3図は、前記山留め壁1に囲まれた地盤8を、地」二
階(グラントレヘル階)の床組の構築に支障ない程度の
深さ(およそ2〜3 rnぐらい)まで掘削し、山留め
壁1及び構真柱7のH銅芯祠3,6を必要なだけ露出さ
せ、これらのHfll芯材3,6の間及び6,6間に本
設鉄骨(H形鋼)9を内蔵したSCCl2O架けて接合
した段階を示している。第2図は第3図の平面配置を示
している。
Figure 3 shows that the ground 8 surrounded by the retaining wall 1 is excavated to a depth (approximately 2 to 3 rn) that does not interfere with the construction of the floor structure for the second floor (ground floor), and the retaining wall 1 is The H copper cores 3 and 6 of the walls 1 and structural pillars 7 were exposed as necessary, and a permanent steel frame (H-shaped steel) 9 was built in between these Hfll cores 3 and 6 and between 6 and 6. This shows the stage where SCCl2O is bridged and bonded. FIG. 2 shows the planar arrangement of FIG.

SCCl2O、H鋼芯材3,6に現場溶接で取り付けた
カセッ!・ブレーI・18へ本設鉄骨9のウェブを高力
ボルトによって接合されている。このため、カセットプ
レート 設けられている。なお、SCCl2O架設、接合の他の
手段としては、図示することは省略したが、1−T I
N芯材3,6とSCCl2Oれぞれのフランジ部を1゛
型金具を介して高力ボルトにより引っ張り接合すること
もてきる。
SCCl2O, cassette attached to H steel core materials 3 and 6 by on-site welding! - The web of the permanent steel frame 9 is connected to the brake I-18 using high-strength bolts. For this reason, a cassette plate is provided. Note that as other means for constructing and joining SCCl2O, although not shown, 1-T I
The flange portions of the N core members 3 and 6 and the SCCl2O can also be tension-joined with high-strength bolts via 1-inch metal fittings.

次に、第5図は、」二記のようにして架設されたSCC
l2O10の上にI) C版11を架設梁の上に現場打
ちのスラブコンク’J − 1・12を打設し、同時に
出留め壁1に沿っては腹起し材兼用の鉄筋コンクリート
梁13を、そして、構真柱7の位置には本設の柱14−
を打設するための鉄筋及び型枠をそれぞれ親み立て、前
記スラブコンクリート】2と一体の梁13尺ひ柱14が
現場打ちコンクリ−I・て打設されている。その結果、
この地上階部外の床組の自重量及びこれに載荷された鉛
直荷重は、山留め壁1及び構真柱7のH鋼芯材3゜6に
伝達して支持されている。こうした荷重の伝達を安全、
確実ならしめるため、H鋼芯材3,6にシャーコネクタ
を取り付けて実施する場合もある。
Next, Figure 5 shows the SCC constructed as described in ``2''.
I) Erection C version 11 on top of l2O10 Cast-in-place slab concrete 'J-1.12 is placed on the beam, and at the same time, along the retaining wall 1, a reinforced concrete beam 13 that also serves as a raised material is installed. At the position of the structure pillar 7, there is a permanent pillar 14-
The reinforcing bars and formwork for pouring the slab concrete 2 are assembled, and the beams 13 and pillars 14 integrated with the slab concrete 2 are poured using cast-in-place concrete I. the result,
The weight of the floor assembly outside the ground floor and the vertical load loaded thereon are transmitted to and supported by the H steel core material 3.6 of the retaining wall 1 and the structural pillar 7. Transferring these loads safely and
In order to ensure reliability, shear connectors may be attached to the H steel core materials 3 and 6 in some cases.

第4図はSCCl2O上にPC版11を架設した状態の
平面配置図を示している。
FIG. 4 shows a plan layout of the PC plate 11 installed on SCCl2O.

第6図は、地盤8の掘削を地下1階の床組を構築可能な
深さまで進め、やはり出留め壁1及び構真柱7の11鋼
芯祠3,6を露出さぜ、そのIJ鋼芯材3.6の間及び
6,6間に本設鉄骨9を内蔵したSCCl2O架けて接
合した段階を示している。
Figure 6 shows that the excavation of the ground 8 has been carried out to a depth that allows the construction of the floor assembly on the first basement floor, and the retaining walls 1 and the 11 steel cores 3 and 6 of the structural pillars 7 have been exposed, and the IJ steel This shows the stage in which the main steel frame 9 is built between the core members 3 and 6 and between the core members 6 and 6, and the SCCl2O structure is installed and joined.

こうして架設されたSC梁io、ioの上にPC版11
を架設梁の上に現場打ちのスラブコンクリート12を打
設し、同時に山留め壁1に沿っては腹起し材兼用の梁1
3を、そして、構真柱7の位置には本設の柱14−を打
ち継ぎ打設するための型枠をそれぞれ組み立て、前記ス
ラブコンクリート12ど一体の梁13及び柱14が現場
打ちコンクリートで打設される。また、この段階では、
山留め壁1を外型枠とする補強鉄骨とする地下構造物の
外壁型枠も組み立てられ、地下外壁15か現場打ちコン
クリ−1・により地下1階分が打ち継き施工される。
The PC version 11 is placed on top of the SC beam io and io constructed in this way.
A concrete slab 12 cast in the field is placed on the construction beam, and at the same time, a beam 1 is placed along the retaining wall 1, which also serves as an upright material.
3, and a formwork for pouring and pouring the main pillar 14- is assembled at the position of the structural pillar 7, and the beam 13 and the pillar 14, which are integral with the slab concrete 12, are made of cast-in-place concrete. It will be poured. Also, at this stage,
The outer wall formwork of the underground structure with the retaining wall 1 as the outer formwork and the reinforcing steel frame is also assembled, and the underground one floor is poured and constructed using the underground outer wall 15 or cast-in-place concrete 1.

第7図は、かくして地下1階分の施工により構築された
梁13、地下構造物外壁15及び本設柱14の平面配置
図を示している。こうして地下構造物は順次下向き;こ
所謂逆打ぢ工法で施工されてゆくのである。
FIG. 7 shows a plan layout of the beam 13, the outer wall 15 of the underground structure, and the main column 14 constructed by constructing one underground floor in this manner. In this way, the underground structures are constructed one after another, facing downwards, using the so-called reverse construction method.

その他の実施例 ところで、本発明の異なる実施例として、所謂順打ち工
法の施工も可能である。図示して説明することは省略し
たが、順打ち工法を実施する場合は、各階ことに山留め
壁1及び構真柱7のH41芯材3,6にSCCl2O架
設し、山留め壁1の内側に沿って腹起し材兼用の梁13
を構築したたけの架構て地盤8の掘削をどんとん進めて
ゆく。そして、最下層までの回前を達成した段階で、最
下段階から順次上層階に向かって地下構造物の構築施工
が進められる。即ち、上記のように既に架設されている
SC梁1帆 10の上にPC版11を架設梁の上に現場
打ちのスラブコンクリ−1・12を打設し、同時に構真
柱7の位置には本設の柱14を打ち継ぎ打設するための
鉄筋や型枠をそれぞれ組み立て、前記スラブコンクリ−
1・12と一体の柱14が現場打ちコンクリートで打設
される。
Other Embodiments By the way, as a different embodiment of the present invention, a so-called pour-in construction method is also possible. Although it has been omitted from illustration and explanation, when implementing the sequential casting method, SCCl2O is installed on the H41 core materials 3 and 6 of the retaining wall 1 and the structural pillar 7 on each floor, and along the inside of the retaining wall 1. Beam 13 that also serves as a material for raising the stomach
The excavation of ground 8 for the newly constructed frame is proceeding steadily. Then, at the stage when the construction to the lowest level is achieved, the construction of the underground structure proceeds from the lowest level to the upper floors. That is, as mentioned above, the PC plate 11 is placed on top of the SC beam 1 sail 10 that has already been erected, and the cast-in-place slab concrete 1 and 12 are placed on the erected beam, and at the same time, the slab concrete 1 and 12 are placed at the position of the structure pillar 7. Assemble the reinforcing bars and formwork for pouring and pouring the main pillars 14, and install the slab concrete.
Column 14, which is integral with 1 and 12, is cast with cast-in-place concrete.

さらにこの段階て山留め壁1の内側に地下構造物の外壁
鉄筋と型枠が組み立てられ、地下外壁15が現場打ちコ
ンクリートにより1階分ずつ打ち継ぎ施工され、順次上
層階へと施工が進められるのである。
Furthermore, at this stage, the reinforcing bars and formwork for the underground structure's outer wall are assembled inside the retaining wall 1, and the underground outer wall 15 is poured one floor at a time using cast-in-place concrete, and construction progresses sequentially to the upper floors. be.

本発明が奏する効果 以」二に実施例と(tlぜて詳述したとおりてあって、
この発明に係る仮設材を省略した地下構造物の施工法は
、仮設材としての切梁や腹起し材なとは使用されないか
ら、そうした仮設材積、仮設工事の工Illを全て削減
でき、もって大幅なコスI・ダウンと玉量の短縮を達成
できるのである。
The effects of the present invention are described in detail in the following examples and examples.
The construction method of underground structures that omit temporary materials according to the present invention does not use stubs or raised materials as temporary materials, so it is possible to completely reduce the volume of temporary materials and construction work required for temporary construction. It is possible to achieve a significant reduction in cost I and the amount of balls.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はソイル柱列による山留め壁及び構真柱の施工状
況を示した平面図、第2図は第3図の平面図、第3図は
地上階部分のSC梁を架設した状態の立面図、第4図は
I) C版の架設状態を示した平面図、第5図は地上階
部分のスラブコンクリートの施工を完成した状態を示し
た立面図、第6図は地下1階部分のSC梁を架設した状
態の立面図、第7図は地下構造物の平面図である。 1・・・山留め壁 3.6・・・H鋼芯材 4・・支持層 8・・・地盤 10・・・SC梁 12・・・スラブコンク 13・・・梁 15・・・外壁 2.5・・・ソイルセメント C・・・逆心 7・・・構真柱 9・・・鉄骨 11・・PC版 ノート 14・・・柱
Figure 1 is a plan view showing the construction status of retaining walls and structural pillars using soil column rows, Figure 2 is a plan view of Figure 3, and Figure 3 is a diagram showing the construction status of the SC beams on the ground floor. Figure 4 is a plan view showing the construction status of I)C version, Figure 5 is an elevation view showing the completed slab concrete construction of the ground floor, and Figure 6 is the basement floor. FIG. 7 is an elevational view of a portion of the underground structure with the SC beams installed, and a plan view of the underground structure. 1... Mountain retaining wall 3.6... H steel core material 4... Support layer 8... Ground 10... SC beam 12... Slab concrete 13... Beam 15... Outer wall 2.5 ... Soil cement C ... Reverse core 7 ... Structural pillar 9 ... Steel frame 11 ... PC version note 14 ... Column

Claims (1)

【特許請求の範囲】 【1】山留め壁を施工し、地盤を掘削してそこに地下構
造物を構築する施工法において、 イ)山留め壁は、ソイルセメントの中にH鋼芯材を落し
込み、かつ要所位置のH鋼芯材の下端は支持層に到達せ
しめたソイル柱列によって形成し、また、地下構造物の
通心における柱の位置には、ソイルセメントの中にH鋼
芯材を落し込み、かつその下端を支持層に到達せしめた
構真柱を設置する段階と、 ロ)地盤を地上階の床組の構築に支障ない程度の深さま
で掘削する段階と、 ハ)山留め壁及び構真柱のH鋼芯材を露出させ、構真柱
相互のH鋼芯材の間、及び構真柱と山留め壁それぞれの
H鋼芯材の間に本設鉄骨内蔵プレキャストコンクリート
梁を架けて接合し、こうして架設されたプレキャストコ
ンクリート梁の上にプレキャストコンクリート版を架設
し、その上に現場打ちのスラブコンクリートを打設し、
かつ山留め壁に沿って腹起し材兼用の梁を、そして、構
真柱の位置には本設の柱をそれぞれ現場打ちコンクリー
トで打設する段階と、 ニ)地盤の掘削を地下1階の床組を構築可能な深さまで
進め、前記ハ)の工程を行ない、以下同様の工程を繰り
返す段階と、 から成ることを特徴とする、仮設材を省略した地下構造
物の施工法。 【2】山留め壁を施工し、地盤を掘削してそこに地下構
造物を構築する施工法において、 イ)山留め壁は、ソイルセメントの中にH鋼芯材を落し
込み、かつ要所位置のH鋼芯材の下端は支持層に到達せ
しめたソイル柱列によって形成し、また、地下構造物の
通心における柱の位置には、ソイルセメントの中にH鋼
芯材を落し込み、かつその下端を支持層に到達せしめた
構真柱を設置する段階と、 ロ)地盤を地上階の床組の構築に支障ない程度の深さま
で掘削する段階と、 ハ)山留め壁及び構真柱のH鋼芯材を露出させ、構真柱
相互のH鋼芯材の間、及び構真柱と山留め壁それぞれの
H鋼芯材の間に本設鉄骨内蔵プレキャストコンクリート
梁を架けて接合すると共に山留め壁に沿って腹起し材兼
用の梁を構築する段階と、 ニ)地盤の掘削を地下1階の床組を構築可能な深さまで
進め、前記ハ)の工程を行ない、以下同様の工程を繰り
返して最下層まで地盤の掘削を完成する段階と、 ホ)最下層階から順次上層階に向かって、前記工程によ
り架設されたプレキャストコンクリート梁の上にプレキ
ャストコンクリート版を架設し、その上に現場打ちのス
ラブコンクリートを打設し、山留め壁の部位に構造物外
壁を、そして、構真柱の位置には本設の柱をそれぞれ現
場打ちコンクリートで打設する段階と、 から成ることを特徴とする、仮設材を省略した地下構造
物の施工法。
[Claims] [1] A construction method in which a retaining wall is constructed, the ground is excavated, and an underground structure is constructed there: (a) The retaining wall is constructed by dropping an H steel core material into soil cement. , and the lower ends of the H-steel cores at strategic locations are formed by rows of soil columns that reach the support layer, and the H-steel cores are placed in the soil cement at the locations of the columns in the center of the underground structure. (b) excavating the ground to a depth that does not interfere with the construction of the ground floor floor; and (c) retaining wall. The H steel core materials of the structural pillars are exposed, and precast concrete beams with built-in steel frames are installed between the H steel core materials of the structural pillars and between the H steel core materials of the structural pillars and the retaining walls. A precast concrete slab was then erected on top of the precast concrete beams, and cast-in-place slab concrete was placed on top of the precast concrete beams.
In addition, a beam that also serves as a raising material will be placed along the retaining wall, and a permanent pillar will be placed at the position of the main pillar using cast-in-place concrete. A method for constructing an underground structure omitting temporary materials, characterized by the following steps: advancing the floor assembly to a depth that allows construction, performing the process of c) above, and repeating the same process thereafter. [2] In the construction method in which a retaining wall is constructed, the ground is excavated, and an underground structure is constructed there. The lower end of the H-steel core material is formed by a row of soil columns that reach the support layer, and the H-steel core material is dropped into soil cement at the position of the column in the center of the underground structure. The stage of installing the structural pillars with their lower ends reaching the supporting layer; b) The stage of excavating the ground to a depth that does not interfere with the construction of the ground floor floor; and c) The H of the retaining walls and structural pillars. The steel core material is exposed, and precast concrete beams with a built-in steel frame are installed between the H steel core materials of each structure pillar and between the structure pillars and the retaining wall to connect them, and the retaining wall is installed. d) Excavation of the ground is carried out to a depth that allows construction of the floor structure for the first basement floor, and step 3) is carried out, and the same process is repeated thereafter. (e) Erection of a precast concrete slab on top of the precast concrete beams erected in the above process, starting from the lowest floor and working its way up to the upper floors; The method is characterized by the following steps: pouring slab concrete, placing the outer wall of the structure in the retaining wall area, and placing permanent columns in the positions of the structural pillars with cast-in-place concrete. , a construction method for underground structures that eliminates temporary materials.
JP1084989A 1989-04-04 1989-04-04 Construction method of underground structure omitting temporary materials Expired - Fee Related JP2736542B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1084989A JP2736542B2 (en) 1989-04-04 1989-04-04 Construction method of underground structure omitting temporary materials

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1084989A JP2736542B2 (en) 1989-04-04 1989-04-04 Construction method of underground structure omitting temporary materials

Publications (2)

Publication Number Publication Date
JPH02266014A true JPH02266014A (en) 1990-10-30
JP2736542B2 JP2736542B2 (en) 1998-04-02

Family

ID=13846035

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1084989A Expired - Fee Related JP2736542B2 (en) 1989-04-04 1989-04-04 Construction method of underground structure omitting temporary materials

Country Status (1)

Country Link
JP (1) JP2736542B2 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10121500A (en) * 1996-10-16 1998-05-12 Ohbayashi Corp Construction method of outer peripheral beam of basement floor
JP2015055088A (en) * 2013-09-11 2015-03-23 株式会社竹中工務店 Building construction method
JP2016199957A (en) * 2015-04-14 2016-12-01 戸田建設株式会社 Floor preceding method
JP2017172248A (en) * 2016-03-24 2017-09-28 鹿島建設株式会社 Subsurface structure skeleton construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10121500A (en) * 1996-10-16 1998-05-12 Ohbayashi Corp Construction method of outer peripheral beam of basement floor
JP2015055088A (en) * 2013-09-11 2015-03-23 株式会社竹中工務店 Building construction method
JP2016199957A (en) * 2015-04-14 2016-12-01 戸田建設株式会社 Floor preceding method
JP2017172248A (en) * 2016-03-24 2017-09-28 鹿島建設株式会社 Subsurface structure skeleton construction method

Also Published As

Publication number Publication date
JP2736542B2 (en) 1998-04-02

Similar Documents

Publication Publication Date Title
JPH1150480A (en) Rebuilding method of building
KR100313720B1 (en) Composite Underground Structure Construction Method
RU2220258C1 (en) Process of erection of multilevel underground structure ( variants )
JP2004263467A (en) Reconstruction method using existing underground skeleton
JPH0220767A (en) Earthquake-proofing method for existing building
JPH02266014A (en) Constructing underground structure eliminating use of temporary material
KR0179708B1 (en) Working method for underground structure of a building
JPH0684690B2 (en) Building basement extension method
JPS6137692Y2 (en)
JPS5829922A (en) Constructing method for underground outer wall
JP3033538B2 (en) Construction method of building frame using existing foundation slab
JP2003003690A (en) Base isolation building and method for base isolation of exisiting building
JP3016215B2 (en) Underground multi-story parking lot and its construction method
JPH1130053A (en) Construction method of base isolation building
JP2763488B2 (en) Prefabricated pillar and inverted ramen prefabricated construction method
JP2894217B2 (en) Building structural frame
JPH07103583B2 (en) Construction method for large span underground structure
JP2565457B2 (en) Structure pillar construction method
JPH0657769A (en) Underground concrete structure and working method thereof
JP3238510B2 (en) Construction method of preceding slab floor
JPS6217233A (en) Foundation base column
JPH08291529A (en) Underground floor construction method
JPH03147926A (en) construction method for basement
JP2023108327A (en) Reconstruction method of building having underground structure
JPH03253613A (en) Construction of earth retaining in excavated ground

Legal Events

Date Code Title Description
FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090116

Year of fee payment: 11

LAPS Cancellation because of no payment of annual fees