JP2013538952A - 根かせ補強 - Google Patents
根かせ補強 Download PDFInfo
- Publication number
- JP2013538952A JP2013538952A JP2013518382A JP2013518382A JP2013538952A JP 2013538952 A JP2013538952 A JP 2013538952A JP 2013518382 A JP2013518382 A JP 2013518382A JP 2013518382 A JP2013518382 A JP 2013518382A JP 2013538952 A JP2013538952 A JP 2013538952A
- Authority
- JP
- Japan
- Prior art keywords
- solid structure
- anchor shaft
- anchor
- anchor head
- wall portion
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/20—Side-supporting means therefor, e.g. using guy ropes or struts
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
- E02D5/808—Ground anchors anchored by using exclusively a bonding material
Abstract
【選択図】図8
Description
1.アンカーシャフトの点検。この技術には、アンカーシャフトの状態を目視で確認するための既存のアンカーシャフトの掘削が含まれる。通常、アンカーシャフト全体を点検する必要があるため、デッドマン118まで掘削することになる。デッドマン上の土を取り除くことにより根かせが一時的に弱体化するため、点検を進めるにあたって根かせを地中に維持するための対策をとる必要がある。
2.新しいデッドマンアンカーを腐食したアンカーの前に設置する。この手法では、腐食したアンカーシャフトから新しいアンカーシャフトに既存の支線を移すことが必要となる。
3.新しいアンカーを腐食したアンカーの後ろに設置する。一般に、この手法では、塔マストまでの距離が広がり、新しい根かせを再取り付けするためには支線が短すぎるため、全ての支線を交換することが必要となる。変更後の塔にさらにスペースが必要とされるため、塔所有者には新たに土地を所有または使用権を得る必要が出てくるおそれがある。
4.新しくドリルで穴を開けたピアアンカーを腐食したアンカーの一方にオフセットして設置する。この手法では、腐食したアンカーシャフトから新しいアンカーシャフトに既存の支線を移すことが必要になる。ピン止めされた基部を有する塔は、新しいアンカーと再配列できるように、回転させられてもよい。塔の回転は危険を伴うことがあり、一般に、塔のアンテナは全て再配列する必要が出る。また、固定された基部を有する塔は自在に回転することができない場合があり、この場合には、支線を新しいアンカーヘッドへ移すことによって塔にさらにストレスが加わる可能性があり、別の問題が発生するおそれがある。
Claims (32)
- 支線式塔または追加支線式塔の根かせ(100)用の補強システムであって、前記根かせ(100)はアンカーヘッド(114)と前記アンカーヘッド(114)から地中に延びるアンカーシャフト(116)とを備え、前記補強システムは、
前記アンカーシャフト(116)の部分の周囲に設けられたソリッド構造体(210)と、
前記アンカーヘッド(114)に取り付けられて前記ソリッド構造体(210)の内部に延びる補助アンカーシャフト(220)と、
前記ソリッド構造体(210)の内部の前記補助アンカーシャフト(220)に取り付けられたまたは一体的に設けられた維持構造体とを備え、
前記ソリッド構造体(210)が、
地表より上に配された上表面(210f)と、
前記塔に面し、前記上表面(210f)より地中へと延びる前壁部(210b)と、
前記上表面(210f)より地中へと延びる後壁部(210c)と、
前記前壁部(210b)と前記後壁部(210c)との間に設けられ地中へと延びる中間部とを含み、
前記前壁部(210b)および前記後壁部(210c)が前記中間部よりも深く地中に延びる、根かせ用の補強システム。 - 前記前壁部(210b)および前記後壁部(210c)が、前記中間部よりも少なくとも2倍深く地中に延びる、請求項1に記載の補強システム。
- 前記前壁部(210b)および前記後壁部(210c)が、それぞれ、土壌に接触し前記塔に面する表面を有する、請求項1に記載の補強システム。
- 前記ソリッド構造体(210)は、前記前壁部(210b)と前記後壁部(210c)との間に配された中間壁部(1110d)をさらに備え、前記中間壁部(1110d)が前記中間部よりも深く地中に延びる、請求項1に記載の補強システム。
- 前記ソリッド構造体(210)は、前記前壁部(210b)と前記後壁部(210c)との間に配された第1の中間壁部と第2の中間壁部とをさらに備え、前記第1の中間壁部および前記第2の中間壁部がいずれも前記中間部よりも深く地中に延びる、請求項1に記載の補強システム。
- 前記ソリッド構造体(210)は、前記ソリッド構造体(210)の質量が前記アンカーヘッド(114)の前よりも後ろで多くなるよう、前記根かせ(100)に対して配置される、請求項1に記載の補強システム。
- 前記ソリッド構造体(210)は硬化性材料を備える、請求項1に記載の補強システム。
- 前記ソリッド構造体(210)は鉄筋コンクリートを備える、請求項1に記載の補強システム。
- 前記補助アンカーシャフト(220)は、いずれも前記アンカーヘッド(114)に取り付けられて前記アンカーシャフト(116)に平行に前記ソリッド構造体(210)の内部に延びる第1および第2の延長部材(310、312)を含む、請求項1に記載の補強システム。
- 前記維持構造体は、各延長部材に取り付けられたまたはこれと一体的に構成されてこの延長部材を前記ソリッド構造体(210)の内部にしっかりと維持する遠位構造体(314、316)を備える、請求項9に記載の補強システム。
- 各延長部材(310、312)は金属製の山形材を備え、各遠位構造体(314、316)は対応する延長部材(310、312)に取り付けられてこれに垂直な方向におかれた金属製の山形材を備える、請求項10に記載の補強システム。
- 構造体を支持する根かせ(100)用の補強システムであって、前記根かせ(100)はアンカーヘッド(114)と前記アンカーヘッド(114)から地中に延びるアンカーシャフト(116)とを有し、前記補強システムは、
前記アンカーシャフト(116)の周囲に設けられたソリッド構造体(210)であって、基部(210a)と、前記基部から下方向に延びて被支持構造体に面した表面を有する少なくとも1つの壁とを含むソリッド構造体(210)と、
前記アンカーヘッド(114)に取り付けられて前記ソリッド構造体(210)の内部に延びる補助アンカーシャフト(220)と、
前記補助アンカーシャフト(220)に取り付けられまたは一体的に設けられ、前記ソリッド構造体(210)の内部に包まれた維持構造体とを備える、根かせ用の補強システム。 - 前記ソリッド構造体(210)は硬化性材料を備える、請求項12に記載の補強システム。
- 前記ソリッド構造体(210)は鉄筋コンクリートを備える、請求項12に記載の補強システム。
- 前記ソリッド構造体(210)は、前記ソリッド構造体(210)の質量が被支持構造体に相対的に前記アンカーヘッド(114)の前よりも後ろで多くなるよう、前記根かせ(100)に対して配置される、請求項12に記載の補強システム。
- 前記ソリッド構造体(210)の前記基部(210a)は、地表より上に配された上表面(210f)を有する、請求項12に記載の補強システム。
- 前記ソリッド構造体(210)の前記少なくとも1つの壁は、前記ソリッド構造体(210)の対向する端部に配された2つの壁(210b、210c)を備える、請求項12に記載の補強システム。
- 前記ソリッド構造体(210)の前記少なくとも1つの壁は、前記ソリッド構造体(210)の対向する端部に配された2つの壁(210b、210c)と、実質的に前記ソリッド構造体(210)の中心に配された第3の壁(1110d)とを備える、請求項12に記載の補強システム。
- 塔であって、
マストと、
前記マスト周囲に配置され、それぞれアンカーヘッド(114)と前記アンカーヘッド(114)から地中に延びるアンカーシャフト(116)とを有する複数の根かせ(100)と、
前記マストと前記複数の根かせ(100)との間に取り付けられた複数の支線(110)とを備え、
前記複数の根かせ(100)の少なくとも1つが補強によって補強されており、
前記補強は、
前記アンカーシャフト(116)の周囲に設けられたソリッド構造体(210)であって、基部(210a)と、前記基部(210a)から下方向に延びて前記マストに面した表面を有する少なくとも1つの壁とを含むソリッド構造体(210)と、
前記アンカーヘッド(114)に取り付けられて前記ソリッド構造体(210)の内部に延びる補助アンカーシャフト(220)と、
前記補助アンカーシャフト(220)に取り付けられまたは一体的に設けられ、前記ソリッド構造体(210)の内部に包まれた維持構造体とを備える、塔。 - 前記ソリッド構造体(210)の前記少なくとも1つの壁は、前記ソリッド構造体(210)の対向する端部に配された2つの壁(210b、210c)を備え、前記ソリッド構造体(210)は鉄筋コンクリートを備える、請求項19に記載の塔。
- 前記ソリッド構造体(210)は、前記ソリッド構造体(210)の質量が前記アンカーヘッド(114)の前よりも後ろで多くなるよう、前記根かせ(100)に対して配置される、請求項20に記載の塔。
- アンカーヘッド(114)と前記アンカーヘッド(114)から地中に延びるアンカーシャフト(116)とを含む根かせ(100)を補強する方法であって、
前記根かせ(100)の周囲の領域を掘削して掘削領域を形成し、
前記掘削領域の内部に延びる補助アンカーシャフト(220)を前記アンカーヘッド(114)に取り付け、
前記掘削領域の内部に硬化性材料を導入し、
前記硬化性材料が硬化してソリッド構造体(210)を形成するよう硬化させる、根かせ(100)を補強する方法。 - 前記導入ステップは、前記硬化性材料が地表よりも上に広がるまでこれを導入する、請求項22に記載の方法。
- 前記硬化性材料の導入ステップに先立つ任意のタイミングで、遠位維持構造体を前記補助アンカーシャフト(220)の遠位端に取り付ける、請求項22に記載の方法。
- 前記掘削ステップは、順不同で、
前記アンカーヘッドの前後のそれぞれに、第1および第2領域を掘削し、
前記第1および第2領域の間に第3領域を掘削し、
第1および第2領域は、前記第3領域よりも深く掘削される、請求項22に記載の方法。 - 第1および第2領域は、前記第3領域よりも少なくとも2倍深く掘削される、請求項25に記載の方法。
- 前記掘削ステップは、さらに、第1および第2領域の間に少なくとも第4領域を掘削し、前記第4領域は前記第3領域よりも深い、請求項25に記載の方法。
- さらに、前記硬化性材料をスチールで補強する、請求項22に記載の方法。
- 前記掘削ステップは、前記アンカーヘッド(114)の前よりも後ろの領域をより多く掘削する、請求項25に記載の方法。
- 前記ソリッド構造体(210)は質量中心(826)を有し、
さらに
前記ソリッド構造体(210)の質量中心(826)から下方向の力(822)、
これに同等の、前記ソリッド構造体(210)に押し付けられる土壌からの横力(824)、
前記アンカーヘッドに取り付けられた支線からの合力(820)、
の3つの力が実質的に交差するように、前記アンカーヘッド(114)に相対的な前記掘削領域の位置決めを行う、請求項25に記載の方法。 - 構造体を支持する支線を固定するシステムであって、
1以上の支線(110)を取り付けるアンカーヘッド(114)と、
前記アンカーヘッド(114)から延びるアンカーシャフト(116)と、
前記アンカーシャフトの遠位端で前記アンカーシャフト(116)に取り付けられたまたはこれと一体的に構成された維持構造体と、
前記維持構造体を包むソリッド構造体(210)であって、基部(210a)と、前記基部(210a)から下方向に延びて支持される構造体に面した土壌に接触する表面を有する少なくとも1つの壁を含むソリッド構造体(210)とを備える、システム。 - 前記ソリッド構造体(210)は鉄筋コンクリートを備える、請求項31に記載のシステム。
Applications Claiming Priority (7)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US36190010P | 2010-07-06 | 2010-07-06 | |
US61/361,900 | 2010-07-06 | ||
US36362010P | 2010-07-12 | 2010-07-12 | |
US61/363,620 | 2010-07-12 | ||
US12/890,565 US8250817B2 (en) | 2010-07-06 | 2010-09-24 | Guy anchor reinforcement |
US12/890,565 | 2010-09-24 | ||
PCT/US2011/033283 WO2012005792A1 (en) | 2010-07-06 | 2011-04-20 | Guy anchor reinforcement |
Publications (3)
Publication Number | Publication Date |
---|---|
JP2013538952A true JP2013538952A (ja) | 2013-10-17 |
JP2013538952A5 JP2013538952A5 (ja) | 2015-04-30 |
JP5785258B2 JP5785258B2 (ja) | 2015-09-24 |
Family
ID=45437551
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2013518382A Active JP5785258B2 (ja) | 2010-07-06 | 2011-04-20 | 根かせ補強 |
Country Status (15)
Country | Link |
---|---|
US (3) | US8250817B2 (ja) |
EP (1) | EP2596187B1 (ja) |
JP (1) | JP5785258B2 (ja) |
AP (1) | AP3075A (ja) |
AU (1) | AU2011277062B2 (ja) |
BR (1) | BR112012033713B1 (ja) |
CA (1) | CA2803832C (ja) |
CL (1) | CL2012003735A1 (ja) |
CO (1) | CO6650352A2 (ja) |
MX (1) | MX2012015136A (ja) |
NZ (1) | NZ603723A (ja) |
PE (1) | PE20130992A1 (ja) |
PT (1) | PT2596187T (ja) |
WO (1) | WO2012005792A1 (ja) |
ZA (1) | ZA201209159B (ja) |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9587363B2 (en) * | 2011-11-07 | 2017-03-07 | Oscar PEDRAZA | Stationary, pre-fabricated anchor having an anchor block and an anchor rod |
WO2014056113A1 (en) * | 2012-10-11 | 2014-04-17 | Lafarge Canada Inc. | Unitized precast grillage foundation and method for manufacturing the same |
US8863455B2 (en) | 2012-10-11 | 2014-10-21 | Lafarge Canada Inc. | Unitized precast grillage foundation and method for manufacturing the same |
US9359739B2 (en) | 2013-12-03 | 2016-06-07 | Glaus, Pyle, Schomer, Burns & Delhaven, Inc. | Guy anchor remediation apparatus |
IT201600098221A1 (it) * | 2016-09-30 | 2018-03-30 | Vodafone Italia S P A | Dispositivo di tensionamento per stralli |
US10132098B1 (en) | 2017-05-16 | 2018-11-20 | Atc Ip Llc | Non-disruptive reinforcement of telecommunications towers |
US10538935B2 (en) * | 2017-08-04 | 2020-01-21 | Tower Engineering Solutions, Llc | Guy wire anchor securement system |
CN108222021A (zh) * | 2018-02-28 | 2018-06-29 | 中国五冶集团有限公司 | 一种用于深基坑支护的土钉装置及其制备方法 |
CN108374596A (zh) * | 2018-03-20 | 2018-08-07 | 国网宁夏电力有限公司中卫供电公司 | 调整带护套拉线辅助工具 |
WO2019194821A1 (en) * | 2018-04-06 | 2019-10-10 | Tower Engineering Solutions, Llc | Apparatus and methods for reinforcing telecommunications towers |
CN111980021A (zh) * | 2020-08-21 | 2020-11-24 | 兰州理工大学 | 一种可自动集排风通风锚杆及施工方法 |
CN112431198B (zh) * | 2020-11-28 | 2021-12-14 | 中铁十七局集团第五工程有限公司 | 一种保持锚杆位于钻孔中心的施工方法 |
DE102020131687A1 (de) * | 2020-11-30 | 2022-06-02 | Trumer Schutzbauten Ges.M.B.H | Schutzverbauung sowie Verfahren zur Dissipation von in ein Tragseil einer Tragseilanordnung der Schutzverbauung eingebrachten Zuglast |
CN113431053B (zh) * | 2021-07-28 | 2023-05-30 | 广东珠江工程总承包有限公司 | 一种土木工程基坑支护用安全防护结构 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3368319A (en) * | 1965-08-16 | 1968-02-13 | Granger Associates | Tall column structure of connected sections with warren cross-bracing and legs of channel section |
JPS63217005A (ja) * | 1987-03-04 | 1988-09-09 | 三菱重工業株式会社 | ケ−ブル架設工法 |
JPH04153478A (ja) * | 1990-10-17 | 1992-05-26 | Nippon Steel Corp | 支線式タワーにおける支線の支持構造 |
JP2001254318A (ja) * | 2000-03-14 | 2001-09-21 | Kajima Corp | ケーブルのアンカレッジへの定着構造 |
JP2002339316A (ja) * | 2001-05-16 | 2002-11-27 | Ishikawajima Harima Heavy Ind Co Ltd | 既設つり橋のケーブルアンカー部の補強構造およびその補強方法 |
JP2007205139A (ja) * | 2006-02-06 | 2007-08-16 | Sumitomo Mitsui Construction Co Ltd | アーチ橋の構築方法 |
Family Cites Families (28)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1777469A (en) * | 1926-11-19 | 1930-10-07 | Robert W Luippold | Tower anchorage |
US3256694A (en) * | 1962-10-29 | 1966-06-21 | Bremische Spannbetonwerke Hill | Structural piles and methods of preparing pipe foundations |
US3402518A (en) * | 1966-03-10 | 1968-09-24 | Peter B. Lettunich | Guy cable with means for adjusting tension |
US3541798A (en) * | 1969-04-18 | 1970-11-24 | Harry Schnabel Jr | Method and structure for shoring a lateral face of an excavation |
US3744192A (en) * | 1972-02-15 | 1973-07-10 | G Burnett | House trailer ground anchor |
US3936924A (en) * | 1973-09-21 | 1976-02-10 | Yoshio Ichise | Releaseable steel cable anchor and method for withdrawing the same |
US4103618A (en) * | 1974-06-19 | 1978-08-01 | Losinger Ag | Means for extracting a soil anchor consisting of a prestressed steel tendon |
CH583340A5 (ja) * | 1974-06-19 | 1976-12-31 | Losinger Ag | |
US4126972A (en) * | 1976-06-28 | 1978-11-28 | Almer Silen | Tornado protection building |
US4180952A (en) | 1978-03-02 | 1980-01-01 | Donald Vanderlyn | Anchoring system |
US4435931A (en) * | 1981-01-29 | 1984-03-13 | Newbanks James A | Guy wire protector device |
DE3434620A1 (de) * | 1984-09-21 | 1986-04-03 | Dyckerhoff & Widmann AG, 8000 München | Abstuetzung eines freien zugglieds, vorzugsweise eines schraegseils einer schraegseilbruecke |
US4882891A (en) * | 1986-06-26 | 1989-11-28 | S.A.F.E. | Anchoring and foundation support apparatus having moment resisting vanes and method |
US4776140A (en) * | 1986-08-06 | 1988-10-11 | San Diego Gas And Electric | Modular block anchor |
US4725168A (en) * | 1986-10-24 | 1988-02-16 | Fagundes Charles P | Retaining wall anchoring system and method |
US5243795A (en) * | 1991-09-20 | 1993-09-14 | Bruce Roberts | Tie down stake |
US5586417A (en) * | 1994-11-23 | 1996-12-24 | Henderson; Allan P. | Tensionless pier foundation |
US5819483A (en) * | 1996-09-27 | 1998-10-13 | Wells; Raymond | Inverted ground anchor |
US6311319B1 (en) * | 1998-05-22 | 2001-10-30 | Taiwan Semiconductor Manufacturing Company | Solving line-end shortening and corner rounding problems by using a simple checking rule |
US6311565B1 (en) | 1999-01-11 | 2001-11-06 | Westinghouse Savannah River Company | Techniques and equipment for assessing the structural integrity of subterranean tower anchor rods |
US6256942B1 (en) * | 1999-07-14 | 2001-07-10 | Michael A. Schatz | Stake system |
AU2001296896A1 (en) * | 2000-09-27 | 2002-04-08 | Allan P. Henderson | Perimeter weighted foundation for wind turbines and the like |
US6474028B2 (en) * | 2001-01-05 | 2002-11-05 | Matt Cusimano | Deadman ground-anchor |
US20030121219A1 (en) * | 2001-12-27 | 2003-07-03 | Dietel William R. | Apparatus for installing a workpiece below a surface |
US7470093B2 (en) * | 2005-06-28 | 2008-12-30 | Mansfield Peter W | Interlocking seawall construction and installation apparatus |
KR100760213B1 (ko) * | 2006-12-28 | 2007-09-20 | (주) 신기술산업 | 톱니가 형성된 곡선부를 가지는 어스 앵커 브라켓 |
US7827741B2 (en) * | 2007-02-13 | 2010-11-09 | Electronics Research, Inc. | Guy anchor equalizer plate with ultrasound port |
US8151528B2 (en) * | 2008-05-28 | 2012-04-10 | Building Technologies Incorporated | System and method for anchoring a modular building |
-
2010
- 2010-09-24 US US12/890,565 patent/US8250817B2/en active Active
-
2011
- 2011-04-20 EP EP11803956.9A patent/EP2596187B1/en active Active
- 2011-04-20 BR BR112012033713-0A patent/BR112012033713B1/pt active IP Right Grant
- 2011-04-20 PE PE2012002448A patent/PE20130992A1/es active IP Right Grant
- 2011-04-20 AU AU2011277062A patent/AU2011277062B2/en active Active
- 2011-04-20 CA CA2803832A patent/CA2803832C/en active Active
- 2011-04-20 NZ NZ603723A patent/NZ603723A/en unknown
- 2011-04-20 WO PCT/US2011/033283 patent/WO2012005792A1/en active Application Filing
- 2011-04-20 JP JP2013518382A patent/JP5785258B2/ja active Active
- 2011-04-20 MX MX2012015136A patent/MX2012015136A/es active IP Right Grant
- 2011-04-20 AP AP2012006608A patent/AP3075A/xx active
- 2011-04-20 PT PT11803956T patent/PT2596187T/pt unknown
-
2012
- 2012-08-23 US US13/592,475 patent/US8458986B2/en active Active
- 2012-12-05 ZA ZA2012/09159A patent/ZA201209159B/en unknown
- 2012-12-19 CO CO12230439A patent/CO6650352A2/es active IP Right Grant
- 2012-12-28 CL CL2012003735A patent/CL2012003735A1/es unknown
-
2013
- 2013-06-10 US US13/914,167 patent/US8745933B2/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3368319A (en) * | 1965-08-16 | 1968-02-13 | Granger Associates | Tall column structure of connected sections with warren cross-bracing and legs of channel section |
JPS63217005A (ja) * | 1987-03-04 | 1988-09-09 | 三菱重工業株式会社 | ケ−ブル架設工法 |
JPH04153478A (ja) * | 1990-10-17 | 1992-05-26 | Nippon Steel Corp | 支線式タワーにおける支線の支持構造 |
JP2001254318A (ja) * | 2000-03-14 | 2001-09-21 | Kajima Corp | ケーブルのアンカレッジへの定着構造 |
JP2002339316A (ja) * | 2001-05-16 | 2002-11-27 | Ishikawajima Harima Heavy Ind Co Ltd | 既設つり橋のケーブルアンカー部の補強構造およびその補強方法 |
JP2007205139A (ja) * | 2006-02-06 | 2007-08-16 | Sumitomo Mitsui Construction Co Ltd | アーチ橋の構築方法 |
Also Published As
Publication number | Publication date |
---|---|
PT2596187T (pt) | 2019-03-01 |
AU2011277062B2 (en) | 2014-05-15 |
MX2012015136A (es) | 2013-05-14 |
US8250817B2 (en) | 2012-08-28 |
EP2596187A1 (en) | 2013-05-29 |
US20130276387A1 (en) | 2013-10-24 |
CA2803832C (en) | 2015-09-15 |
BR112012033713A2 (pt) | 2020-01-28 |
US8458986B2 (en) | 2013-06-11 |
NZ603723A (en) | 2014-05-30 |
PE20130992A1 (es) | 2013-10-04 |
CL2012003735A1 (es) | 2013-07-26 |
JP5785258B2 (ja) | 2015-09-24 |
CO6650352A2 (es) | 2013-04-15 |
EP2596187B1 (en) | 2018-11-28 |
US8745933B2 (en) | 2014-06-10 |
AP3075A (en) | 2014-12-31 |
AU2011277062A1 (en) | 2012-12-06 |
US20130000244A1 (en) | 2013-01-03 |
CA2803832A1 (en) | 2012-01-12 |
WO2012005792A1 (en) | 2012-01-12 |
ZA201209159B (en) | 2013-07-31 |
US20120005970A1 (en) | 2012-01-12 |
AP2012006608A0 (en) | 2012-12-31 |
BR112012033713B1 (pt) | 2021-04-20 |
EP2596187A4 (en) | 2016-01-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5785258B2 (ja) | 根かせ補強 | |
CN100564700C (zh) | 格构式钢柱塔吊基础座的施工方法 | |
CN102418345A (zh) | 横撑钢丝固定装置 | |
US10443207B2 (en) | Pile foundations for supporting power transmission towers | |
CN111236299B (zh) | 市政道路管线加固保护系统及其施工方法 | |
US10100486B2 (en) | Method for installing overhead transmission line supports on permafrost soils | |
WO2016187615A1 (en) | Foundation anchor | |
KR20130124266A (ko) | 탑 구조물의 기초 구조물 시공 구조 및 시공 방법 | |
KR101253410B1 (ko) | 벽강관말뚝의 연결구조체 | |
JP6865518B1 (ja) | 山留壁及びその形成方法 | |
CN113914333A (zh) | 边坡防护单体构件、边坡防护结构及边坡防护施工方法 | |
KR101188694B1 (ko) | 통신용 강관주의 근가장치 | |
KR100983633B1 (ko) | Phc 복합말뚝 | |
CN113006010B (zh) | 混凝土导墙基础加固的方法 | |
CN214303706U (zh) | 混凝土导墙基础扩桩成墙的定位导向器 | |
KR102400508B1 (ko) | 흙막이벽 설치 구조물의 시공방법 | |
CN220927778U (zh) | 一种用于深水岩溶地质的大直径桩基作业平台 | |
CN219586772U (zh) | 承台群锚基础 | |
CN220581845U (zh) | 一种大跨度压力管线临时架空保护结构 | |
KR20210095335A (ko) | 태양광발전용 스크류파일 | |
CN115652917A (zh) | 一种螺锁式预应力异形预制混凝土实心方桩施工工法 | |
KR101253427B1 (ko) | 벽강관말뚝의 결속보강재가 구비된 연결구조체 | |
JP2021088884A (ja) | 杭の打設方法 | |
CN113026688A (zh) | 混凝土导墙基础底部基岩扩桩成墙的系统 | |
WO2007117065A1 (en) | Mechanized construction method of earth wire under-bracing using backhoe |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A521 | Request for written amendment filed |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20140203 |
|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20140203 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20141114 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20141202 |
|
A601 | Written request for extension of time |
Free format text: JAPANESE INTERMEDIATE CODE: A601 Effective date: 20150225 |
|
A524 | Written submission of copy of amendment under article 19 pct |
Free format text: JAPANESE INTERMEDIATE CODE: A524 Effective date: 20150312 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20150707 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20150723 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5785258 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |