JP2013092011A - Earth retaining jig for repaired portion of reinforced soil wall, earth retaining method using the earth retaining jig, and repair method for reinforced soil wall - Google Patents
Earth retaining jig for repaired portion of reinforced soil wall, earth retaining method using the earth retaining jig, and repair method for reinforced soil wall Download PDFInfo
- Publication number
- JP2013092011A JP2013092011A JP2011235883A JP2011235883A JP2013092011A JP 2013092011 A JP2013092011 A JP 2013092011A JP 2011235883 A JP2011235883 A JP 2011235883A JP 2011235883 A JP2011235883 A JP 2011235883A JP 2013092011 A JP2013092011 A JP 2013092011A
- Authority
- JP
- Japan
- Prior art keywords
- wall
- earth retaining
- earth
- retaining
- jig
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
Description
本発明は、補強土壁の変状による壁面材の脱落等が発生した箇所を補修するために用いる土留治具、並びに該土留治具を用いた土留方法及び補強土壁の補修方法に関する技術である。 The present invention relates to a earth retaining jig used for repairing a place where a wall surface material has fallen off due to deformation of a reinforcing earth wall, a technique for retaining earth using the earth retaining jig, and a method for repairing a reinforcing earth wall. is there.
補強土壁は、壁面材と、該壁面材の背面に設けた盛土と、前記壁面材と連結し、且つ前記盛土の内部に配する補強材と、を少なくとも含んで構成する土留構造物である。
補強土壁は、壁面材に作用する土圧力に対し、前記補強材の引き抜き抵抗力でもって釣り合いを保つことにより土留効果を発揮することができる。
The reinforcing earth wall is a soil retaining structure that includes at least a wall material, a fill provided on the back surface of the wall material, and a reinforcing material connected to the wall material and arranged inside the bank. .
The reinforced earth wall can exert a soil retaining effect by maintaining a balance with the pulling resistance force of the reinforcing material against the earth pressure acting on the wall surface material.
地震等の様々な要因によって補強土壁が変状し、補強土壁を構成する壁面材が脱落するような大変形を受けた場合には、大規模な補修が必要となる。
補強土壁の大規模な補修が必要とされる場合の従来方法を、図5を参照しながら説明する。
When the reinforced earth wall is deformed due to various factors such as an earthquake and the wall material constituting the reinforced earth wall is dropped, a large-scale repair is required.
A conventional method when a large-scale repair of a reinforced earth wall is required will be described with reference to FIG.
(1)山留め工(図5(a))
始めに壁面材aの脱落部分の背面に、山留め工を施す。
山留め工には、鋼矢板若しくは親杭横矢板等の山留材dを用いた公知の工法を採用することができる。
山留材dの打設作業は、補強土壁の天端に搬入した打設装置でもって行う。
(2)掘削工(図5(b)(c))
前記山留め工によって構築した山留壁dの前面側の盛土bを掘削しつつ、該当箇所の壁面材aを撤去して、掘削空間fを構築する。
前記の盛土bの掘削作業は、補強土壁の天端に搬入した重機e(ロングアームバックホウなど)でもって行うことが一般的である。
(3)壁面の再構築(図5(d))
掘削空間fに、新たな壁面材g及び補強材hを下から順に配置しつつ、新たな盛土iを行って、新たな補強土壁を構築する。
(1) Mountain fastener (Fig. 5 (a))
First, a mountain fixing work is applied to the back surface of the falling part of the wall surface material a.
A known method using a mountain retaining material d such as a steel sheet pile or a main pile transverse sheet pile can be employed for the mountain fastening.
The placing work of the mountain retaining material d is performed with a placing apparatus carried into the top end of the reinforced earth wall.
(2) Excavator (Fig. 5 (b) (c))
While excavating the embankment b on the front side of the mountain retaining wall d constructed by the mountain retaining work, the wall material a at the corresponding location is removed to construct the excavation space f.
The excavation work of the embankment b is generally performed with a heavy machine e (such as a long arm backhoe) carried into the top end of the reinforced earth wall.
(3) Reconstruction of wall surface (Fig. 5 (d))
In the excavation space f, a new embankment i is performed while arranging a new wall material g and a reinforcing material h in order from the bottom, and a new reinforced earth wall is constructed.
しかし、前記した従来の補修方法によれば、以下の様な問題のうち、少なくも一つの問題が生じうる。
(1)山留め工に関する問題
山留め工にあたり、補修対象の壁面材に到達するまでの山留材を必要とするため、資材の節減に限界がある。また、それらの資材の運搬や打設の為に、運搬車や打設装置等を、補強土壁の天端まで手配する必要が生じる。
(2)掘削工に関する問題
土留壁前方の盛土部分を掘削する為に、ロングアームバックホウなどの重機を、補強土壁の天端まで手配する必要が生じる。
However, according to the conventional repair method described above, at least one of the following problems may occur.
(1) Problems related to mountain retaining work There is a limit to the saving of materials because the mountain retaining work requires a mountain retaining material to reach the wall material to be repaired. In addition, it is necessary to arrange a transport vehicle, a driving device, and the like up to the top of the reinforced earth wall for transporting and placing these materials.
(2) Problems related to excavation To excavate the embankment in front of the retaining wall, it is necessary to arrange heavy machinery such as long arm backhoes to the top of the reinforced earth wall.
以上の通り、従来の工法によれば、作業現場が山間部などの険しい場所であった場合に、資材の運搬、重機等の手配、打設、掘削作業に多くの手間を要することとなり、工期・工費の節減に限界があった。 As described above, according to the conventional construction method, when the work site is a steep place such as a mountainous area, a lot of labor is required for transporting materials, arranging heavy machinery, placing, and excavation work. -There was a limit to the cost savings.
したがって、本願発明は、従来工法よりも、工期・工費の節減が可能な補強土壁の補修方法、前記補修方法で用いる土留方法、並びに前記土留方法で用いる土留治具を提供することを目的とするものである。 Therefore, the present invention has an object to provide a method for repairing a reinforced earth wall capable of reducing the construction period and cost compared to the conventional method, a soil retaining method used in the repair method, and a soil retaining jig used in the soil retaining method. To do.
本願の第1発明は、壁面材と、該壁面材の背面に設けた盛土と、前記壁面材と連結し且つ該盛土の内部に配する補強材とを少なくとも含む補強土壁において、前記壁面材の破損或いは脱落等によって露出した盛土を土留するための土留治具であって、前記盛土の露出面に接置する受圧部と、前記盛土から露出した補強材を固定する連結部と、を少なくとも具備することを特徴とする、土留治具を提供するものである。 A first invention of the present application is a reinforced soil wall including at least a wall surface material, a fill provided on a back surface of the wall surface material, and a reinforcing material connected to the wall surface material and disposed inside the fill material. A earth retaining jig for retaining earth exposed due to breakage or falling off, and at least a pressure receiving part placed in contact with the exposed surface of the bank and a connecting part for fixing a reinforcing material exposed from the bank An earth retaining jig is provided.
また、本願の第2発明は、前記第1発明に記載の土留治具を用いた、補強土壁の補修箇所の土留方法であって、(a)補修対象の壁面材を撤去しながら、該壁面材の背面側の盛土の一部を掘削して前記土留治具の設置空間を形成し、(b)前記土留治具を盛土の露出面に設置し、(c)前記土留治具の連結部でもって、前記盛土から露出した補強材を固定し、(d)前記(a)〜(c)の工程を、補修対象の壁面材単位で順次行って、土留面を構築する、ことを特徴とする、補強土壁の補修箇所の土留方法を提供するものである。 Further, the second invention of the present application is a method of retaining the earth of the reinforced earth wall using the earth retaining jig according to the first invention, wherein (a) while removing the wall material to be repaired, A part of the embankment on the back side of the wall material is excavated to form an installation space for the earth retaining jig, (b) the earth retaining jig is installed on the exposed surface of the earth embankment, and (c) connection of the earth retaining jig. The reinforcing material exposed from the embankment is fixed by the part, and (d) the steps (a) to (c) are sequentially performed for each wall material to be repaired to construct the earth retaining surface. And provide a method of retaining soil at the repair site of the reinforced earth wall.
また、本願の第3発明は、前記第2発明に記載の土留方法を用いた、補強土壁の補修方法であって、前記(d)の工程によって土留面を構築した後、(e1)前記土留面を構成する土留治具を下から順に除去しながら、新たな壁面材を構築していくことを特徴とする、補強土壁の補修方法を提供するものである。 A third invention of the present application is a method for repairing a reinforced earth wall using the earth retaining method according to the second invention, wherein after the earth retaining surface is constructed by the step (d), (e1) The present invention provides a repair method for a reinforced earth wall, characterized in that a new wall surface material is constructed while removing the earth retaining jig constituting the earth retaining surface in order from the bottom.
また、本願の第4発明は、前記第2発明に記載の土留方法を用いた、補強土壁の補修方法であって、前記(d)の工程によって土留面を構築した後、(e2)前記土留面を維持したまま、前記土留面の前方に新たな壁面材を構築することを特徴とする、補強土壁の補修方法を提供するものである。 The fourth invention of the present application is a method for repairing a reinforcing earth wall using the earth retaining method according to the second invention, wherein after the earth retaining surface is constructed by the step (d), (e2) The present invention provides a repair method for a reinforced earth wall, characterized in that a new wall surface material is constructed in front of the earth retaining surface while maintaining the earth retaining surface.
本発明によれば、以下に記載する効果のうち、少なくとも何れか一つの効果を得ることができる。
(1)本発明の土留治具によれば、山留め時に鋼矢板、親杭、横矢板等の長尺の山留材の手配が不要となるため、それらの資材をストックしておく大規模な仮設ヤードの確保をする必要が無い。また、資材の確保、運搬、設置作業等も不要であるから、工期・工費の大幅な短縮に寄与しうる。
(2)本発明の土留方法によれば、山留め時に重機の手配が不要となるため、山間部などの険しい現場でも作業が可能となる。また、盛土の掘削量も最低限に留めながら土留することもできる。従って、工期・工費の大幅な短縮に寄与しうる。
(3)本発明の補修方法によれば、土留治具の再利用が可能であるから、工費の短縮に寄与しうる。全体の作業が、壁面材の設置作業と最低限の盛土作業のみで良い為、工期の短縮にも寄与しうる。
(4)本発明の補修方法によれば、壁面材の背面側に、土留治具によって構築した簡易山留め壁が存する状態を維持することができるため、より山留め効果の高い補強土壁の提供が期待できる。
According to the present invention, at least one of the effects described below can be obtained.
(1) According to the earth retaining jig of the present invention, it is not necessary to arrange a long pile retaining material such as a steel sheet pile, a main pile, a lateral sheet pile, etc. at the time of mountain fastening. There is no need to secure a temporary yard. In addition, it is not necessary to secure, transport, or install materials, which can contribute to a significant reduction in work period and cost.
(2) According to the earth retaining method of the present invention, since it is not necessary to arrange heavy machinery at the time of mountain mounting, it is possible to work even in rugged sites such as mountainous areas. It is also possible to retain earth while keeping the amount of excavation of the embankment to a minimum. Therefore, it can contribute to a significant reduction in the construction period and cost.
(3) According to the repairing method of the present invention, the earth retaining jig can be reused, which can contribute to shortening the construction cost. The entire work only needs to be a wall material installation work and a minimum embankment work, which can contribute to shortening the construction period.
(4) According to the repair method of the present invention, a state in which a simple retaining wall constructed by a retaining jig exists on the back side of the wall surface material can be maintained, so that a reinforced soil wall having a higher retaining effect can be provided. I can expect.
以下、各図を参照しながら、本発明の実施例について説明する。
なお、本発明が前提とする補強土壁Aは、壁面材2と、該壁面材2の背面に設けた盛土3と、前記壁面材2と連結し、且つ前記盛土3の内部に配する補強材4と、を少なくとも含んで構成する土留構造物である。
補強土壁Aは、直壁に限られるものでは無く、勾配を設けたものでも良い。
Embodiments of the present invention will be described below with reference to the drawings.
In addition, the reinforcing earth wall A which this invention presupposes is the reinforcement which arrange | positions the
The reinforced earth wall A is not limited to a straight wall, and may be provided with a gradient.
始めに、補強土壁の補修方法に用いる土留治具について説明する。
<1>全体構成
図1(a)は本発明に係る土留治具の平面図であり、図1(b)は本発明に係る土留治具の正面図である。
本発明に係る土留治具1は、盛土3の露出面に接置する受圧部11と、盛土3から露出した補強材4を固定する連結部12と、を少なくとも具備して構成する。
First, the earth retaining jig used for the repair method of the reinforced earth wall will be described.
<1> Overall Configuration FIG. 1A is a plan view of an earth retaining jig according to the present invention, and FIG. 1B is a front view of the earth retaining jig according to the present invention.
The earth retaining jig 1 according to the present invention includes at least a
<2>受圧部
受圧部11は、盛土3からの土圧を受ける為の部材である。
受圧部11は、盛土への接地面111を前面に有する平板部材で構成することができる。
なお、受圧部11の形状は、盛土からの土圧を受けることができれば、如何なる形状でも構わない。
受圧部11には、露出した補強材4を挿通する為の貫通孔112を設けてある。
<2> Pressure receiving part The
The pressure-receiving
In addition, the shape of the
The
<3>連結部
連結部12は、補強材4を連結して固定するための部材である。
連結部12は、露出した補強材4を挿通するための挿通空間121を有する筒状の部材で構成することができる。挿通空間121の断面形状は円形、楕円、多角形などあらゆる形状であってよい。
連結部12は、前記挿通空間121が前記受圧部11の貫通孔112と連通するように、受圧部11の背面側に取り付ける。
連結部12には、適宜連結孔122を設けておき、ボルト等の周知の固定手段(図示せず)によって、挿通空間121に挿通した補強材4を固定自在に構成する。
<3> Connecting part The connecting
The
The connecting
The connecting
<4>使用方法
土留治具1は、補強材4のうち盛土から露出した部分を、受圧部11の貫通孔112、連結部12内部、の順に挿通させて、受圧部11を盛土の露出面31に接地するように配置する。
そして、補強材4を適宜緊張した後、ボルト留めして、土留治具1を盛土表面に固定する。
以上の使用方法によって、土留治具1全体で土留機能を発揮することができる。
<4> Usage Method The earth retaining jig 1 is inserted through the reinforcing
And after tensioning the reinforcing
By the above usage method, the earth retaining function can be exhibited in the entire earth retaining jig 1.
本実施例によれば、山留め時に、鋼矢板、親杭、横矢板等の長尺の山留め材の手配が不要となるため、それらの資材をストックしておく大規模な仮設ヤードの確保を必要としない利点がある。
また、長尺資材の確保、運搬、設置作業等も不要であるから、工期・工費の大幅な短縮に寄与しうる。
According to this embodiment, it is not necessary to arrange long piles such as steel sheet piles, main piles, and horizontal sheet piles at the time of pile mounting, so it is necessary to secure a large temporary yard for stocking those materials. There are advantages to not.
In addition, since it is not necessary to secure, transport, and install long materials, it can contribute to a significant reduction in construction period and cost.
次に、前記土留治具1を用いた補強土壁の補修方法のうち、土留段階までの手順について図2を参照しながら説明する。
<1>初期状態(図2(a))
図2(a)では、補強土壁Aを構成する壁面材2のうち、一部の補強材2が脱落している場合を示す図である。
Next, of the repair method of the reinforced earth wall using the earth retaining jig 1, the procedure up to the earth retaining stage will be described with reference to FIG.
<1> Initial state (FIG. 2 (a))
FIG. 2A is a diagram showing a case where some of the reinforcing
<2>掘削及び土留治具の設置(図2(b)(c))
図2(b)に示すように、補強土壁Aの天端側から、順次壁面材2を撤去しつつ、盛土3から露出した補強材4の一部を、土留治具1に連結していく。
このとき、壁面材2の撤去や、土留治具1の設置作業は、補強土壁Aの前面側に設けた足場(図示せず)から行うことができる。
土留治具1を設置した箇所は、簡易的に山留めされた状態となる。
このステップを順に下方へと進めて順次土留治具(1a,1b,・・・,1e)を設置していくことで、図2(c)のように壁面材の補修が必要な箇所まで山留めした状態を確保していく。これら複数の土留治具によって仮山留面5が形成されることとなる。
<2> Excavation and installation of earth retaining jigs (FIGS. 2B and 2C)
As shown in FIG. 2B, a part of the reinforcing
At this time, removal of the
The place where the earth retaining jig 1 is installed is simply mountain-capped.
By proceeding downward in this order and installing the earth retaining jigs (1a, 1b,..., 1e) in succession, it can be piled up to the point where the wall material needs to be repaired as shown in FIG. We will secure the state. The temporary
本実施例によれば、山留め時に重機の手配が不要となるため、山間部などの険しい現場でも作業が可能となる。また、盛土の掘削量も最低限に留めておくことができる。従って、工期・工費の大幅な短縮に寄与しうる。 According to the present embodiment, since it is not necessary to arrange heavy machinery when mounting on the mountain, it is possible to work even in a rugged site such as a mountainous area. In addition, the amount of excavation of the embankment can be kept to a minimum. Therefore, it can contribute to a significant reduction in the construction period and cost.
次に、前記土留治具1を用いた補強土壁の補修方法のうち、土留段階から補修段階までの手順の一例について図3を参照しながら説明する。
<1>土留治具の撤去・壁面材の設置
本例は、土留治具1a〜1eによって簡易的に山留めした状態から、下方の土留治具1eを撤去し、新たな壁面材2aの構築と再盛土を行っていき、それらを順に繰り返していく方法である。
新たな壁面材2は、プレキャストでも良いし、型枠を設けた現場打ちによる構築でもよい。
土留治具1から外れた補強材4の端部は、新たな壁面材2と再度一体化する。
補強材4と新たな壁面材2とを一体化する方法は、公知の方法を採用することができる。
なお、補強材4の長さが不足する場合には、適宜長さを補充して、壁面材2との一体化を担保すればよい。
Next, an example of a procedure from the earth retaining stage to the repairing stage in the repair method of the reinforced earth wall using the earth retaining jig 1 will be described with reference to FIG.
<1> Removal of retaining jig / Installation of wall surface material In this example, the
The
The end portion of the reinforcing
As a method for integrating the reinforcing
In addition, when the length of the reinforcing
本実施例によれば、土留治具の再利用が可能であるから、工費の短縮に寄与しうる。また、全体の作業が、壁面材の設置作業と最低限の盛土作業のみで良い為、工期の短縮にも寄与しうる。 According to the present embodiment, the earth retaining jig can be reused, which can contribute to shortening the construction cost. Moreover, since the whole work only needs to install the wall surface material and the minimum embankment work, it can contribute to shortening the construction period.
次に、前記土留治具を用いた補強土壁の補修方法のうち、土留段階から補修段階までの手順のその他の例について図4を参照しながら説明する。
本例は、土留治具1をそのまま埋め殺しした状態で、新たな壁面材2の構築と再盛土を行っていく方法である。
新たな壁面材2は、プレキャストでも良いし、現場打ちでもよい。
新たな壁面材2がプレキャストである場合には、土留治具1と、壁面材2とを公知の方法で連結して一体化する。
新たな壁面材2が現場打ちである場合には、壁面材2の内部鉄筋と土留治具1とを公知の方法で連結して一体化しても良いし、土留治具1の一部を、現場打ちしたモルタルで共に埋めることで、壁面材2と強制的に一体化してもよい。
Next, another example of the procedure from the earth retaining stage to the repair stage in the repair method of the reinforced earth wall using the earth retaining jig will be described with reference to FIG.
This example is a method of constructing and refilling a
The
When the new
When the
本実施例によれば、壁面材の背面側に、土留治具によって構築した簡易山留め壁が存する状態を維持することができるため、より山留め効果の高い補強土壁の提供が期待できる。 According to the present embodiment, it is possible to maintain a state in which the simple retaining wall constructed by the earth retaining jig exists on the back side of the wall surface material, and therefore it is possible to provide a reinforced soil wall having a higher retaining effect.
その他、前記した補修方法において、必要に応じて、新たな排水材の配置などの、公知の補強土壁の補修において用いる各種の機能付加作業を施してもよい。 In addition, in the above-described repair method, various function addition operations used in repair of a known reinforced earth wall, such as the arrangement of a new drainage material, may be performed as necessary.
1 土留治具
11 受圧部
111 接地面
112 貫通孔
12 連結部
121 挿通空間
122 連結孔
2 壁面材
3 盛土
31 露出面
4 補強材
5 仮山留面
A 補強土壁
DESCRIPTION OF SYMBOLS 1
Claims (4)
前記盛土の露出面に接置する受圧部と、
前記盛土から露出した補強材を固定する連結部と、
を少なくとも具備することを特徴とする、土留治具。 In a reinforced soil wall including at least a wall surface material, a fill provided on a back surface of the wall surface material, and a reinforcing material connected to the wall surface material and disposed inside the embankment, the wall surface material is exposed due to damage or dropping off. A retaining jig for retaining the embankment
A pressure receiving portion placed on the exposed surface of the embankment;
A connecting portion for fixing the reinforcing material exposed from the embankment;
A earth retaining jig comprising at least
(a)補修対象の壁面材を撤去しながら、該壁面材の背面側の盛土の一部を掘削して前記土留治具の設置空間を形成し、
(b)前記土留治具を盛土の露出面に設置し、
(c)前記土留治具の連結部でもって、前記盛土から露出した補強材を固定し、
(d)前記(a)〜(c)の工程を、補修対象の壁面材単位で順次行って、土留面を構築する、
ことを特徴とする、補強土壁の補修箇所の土留方法。 A method of retaining the reinforced soil wall using the retaining jig according to claim 1,
(A) While removing the wall material to be repaired, excavating a part of the embankment on the back side of the wall material to form an installation space for the earth retaining jig,
(B) installing the earth retaining jig on the exposed surface of the embankment;
(C) fixing the reinforcing material exposed from the embankment with the connecting portion of the earth retaining jig;
(D) The above steps (a) to (c) are sequentially performed for each wall material to be repaired, and a retaining surface is constructed.
An earth retaining method for repairing a reinforced earth wall.
前記(d)の工程によって土留面を構築した後、
(e1)前記土留面を構成する土留治具を下から順に除去しながら、新たな壁面材を構築していくことを特徴とする、補強土壁の補修方法。 A method for repairing a reinforced earth wall using the earth retaining method according to claim 2,
After building the retaining surface by the step (d),
(E1) A method of repairing a reinforced earth wall, wherein a new wall surface material is constructed while removing the earth retaining jig constituting the earth retaining surface in order from the bottom.
前記(d)の工程によって土留面を構築した後、
(e2)前記土留面を維持したまま、前記土留面の前方に新たな壁面材を構築することを特徴とする、補強土壁の補修方法。 A method for repairing a reinforced earth wall using the earth retaining method according to claim 2,
After building the retaining surface by the step (d),
(E2) A method for repairing a reinforced earth wall, wherein a new wall surface material is constructed in front of the earth retaining surface while maintaining the earth retaining surface.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2011235883A JP2013092011A (en) | 2011-10-27 | 2011-10-27 | Earth retaining jig for repaired portion of reinforced soil wall, earth retaining method using the earth retaining jig, and repair method for reinforced soil wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2011235883A JP2013092011A (en) | 2011-10-27 | 2011-10-27 | Earth retaining jig for repaired portion of reinforced soil wall, earth retaining method using the earth retaining jig, and repair method for reinforced soil wall |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2013092011A true JP2013092011A (en) | 2013-05-16 |
Family
ID=48615344
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2011235883A Pending JP2013092011A (en) | 2011-10-27 | 2011-10-27 | Earth retaining jig for repaired portion of reinforced soil wall, earth retaining method using the earth retaining jig, and repair method for reinforced soil wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2013092011A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6002348B1 (en) * | 2016-06-02 | 2016-10-05 | Jfe商事テールワン株式会社 | Retaining method of retaining wall structure |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002021090A (en) * | 2000-07-05 | 2002-01-23 | Kyoei Kogyo Kk | Construction method for anchor and pressing member used therefor |
JP2009299337A (en) * | 2008-06-12 | 2009-12-24 | Nippon Steel & Sumikin Metal Products Co Ltd | Unevenness adjusting mat for slope stabilizing method, and slope stabilizing method |
-
2011
- 2011-10-27 JP JP2011235883A patent/JP2013092011A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2002021090A (en) * | 2000-07-05 | 2002-01-23 | Kyoei Kogyo Kk | Construction method for anchor and pressing member used therefor |
JP2009299337A (en) * | 2008-06-12 | 2009-12-24 | Nippon Steel & Sumikin Metal Products Co Ltd | Unevenness adjusting mat for slope stabilizing method, and slope stabilizing method |
Non-Patent Citations (2)
Title |
---|
JPN6015024595; 補強土(テールアルメ)壁工法 設計・施工マニュアル 第3回改訂版 , 200311, P.1-2,19、写真7-1, JFE商事テールワン株式会社 * |
JPN6015024596; テールアルメの壁面脱落に関する報告書 , 200011, P.3〜9、図1、写真1〜4, JFE商事テールワン株式会社 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP6002348B1 (en) * | 2016-06-02 | 2016-10-05 | Jfe商事テールワン株式会社 | Retaining method of retaining wall structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101205783B1 (en) | The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously | |
KR100722665B1 (en) | Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same | |
KR101070426B1 (en) | Improved Underpinning Method Using the micro pile | |
JP2010090532A (en) | Method for restricting head of earth retaining wall | |
KR101479267B1 (en) | Method for constructing tunnel by using pipe | |
JP5698405B1 (en) | Ground improvement solid foundation method | |
KR100898969B1 (en) | Tunnel Boring Method Using Sheet Pile and Tunnel Structure therof | |
JP2008223390A (en) | Waling material for steel pipe sheet pile, wale, steel pipe sheet pile using wale, and its construction method | |
KR102184900B1 (en) | Temporary retaining wall structure using circular steel pipe and construction method thereof | |
KR101057003B1 (en) | Post Tension Tunnel Method | |
JP2013092011A (en) | Earth retaining jig for repaired portion of reinforced soil wall, earth retaining method using the earth retaining jig, and repair method for reinforced soil wall | |
KR20120128345A (en) | A Prevention Plate of the Ground Subsidence and Construction Method | |
JP5918599B2 (en) | Retaining structure of reinforced earth wall and repair method | |
KR101128955B1 (en) | The Construction Method of Pressing Underground Structure | |
KR102355446B1 (en) | Vertical underground structure and method for constructing the same | |
JP5800765B2 (en) | Rock fall prevention structure | |
JP6429512B2 (en) | Road lining method | |
KR20100118000A (en) | Using reclamation steel perimeter beam and girder which the basement infrastructure construction method | |
KR101025399B1 (en) | Underground Structure and Method for Constructing thereof | |
KR100990430B1 (en) | Construction method for underground structure | |
JP2016037847A (en) | Liquefaction countermeasure structure of ground improvement mat foundation and correction method of occurrence of unequal settlement by liquefaction | |
KR101256311B1 (en) | Structual deepening method | |
KR20140015980A (en) | Method for constructing earth retaining wall using arch pannel | |
JP5116827B2 (en) | Press-in caisson and press-in caisson method using this press-in caisson | |
KR100826573B1 (en) | The construction process of temporary installation for land-side protection wall using freeing method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20141003 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20150612 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20150623 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20151027 |