JP2010090532A - Method for restricting head of earth retaining wall - Google Patents

Method for restricting head of earth retaining wall Download PDF

Info

Publication number
JP2010090532A
JP2010090532A JP2008258269A JP2008258269A JP2010090532A JP 2010090532 A JP2010090532 A JP 2010090532A JP 2008258269 A JP2008258269 A JP 2008258269A JP 2008258269 A JP2008258269 A JP 2008258269A JP 2010090532 A JP2010090532 A JP 2010090532A
Authority
JP
Japan
Prior art keywords
retaining wall
ground
soil
head
improved
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008258269A
Other languages
Japanese (ja)
Other versions
JP5180022B2 (en
Inventor
Taku Hirai
卓 平井
Mayuka Nishimura
繭果 西村
Tetsuya Ikegawa
哲也 池川
Toshikazu Shiratake
寿和 白武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Doboku Co Ltd
Original Assignee
Takenaka Doboku Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Doboku Co Ltd filed Critical Takenaka Doboku Co Ltd
Priority to JP2008258269A priority Critical patent/JP5180022B2/en
Publication of JP2010090532A publication Critical patent/JP2010090532A/en
Application granted granted Critical
Publication of JP5180022B2 publication Critical patent/JP5180022B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

<P>PROBLEM TO BE SOLVED: To provide a method for restricting or reinforcing the head of an earth retaining wall so as not to be deformed inward. <P>SOLUTION: The surface soil of the rear surface side ground of the head of the earth retaining wall is improved in a soil cement by mixing the original soil with cement or replaced with a soil cement. A plurality of anchor steel members 5 are buried in the surface-improved ground 4 improved in the soil cement generally horizontally in the rear surface direction, and at pitches promoting a reinforcement effect in the longitudinal direction of the earth retaining wall. One ends of the anchor steel members 5 are joined to the head of the earth retaining wall. <P>COPYRIGHT: (C)2010,JPO&INPIT

Description

この発明は、地中に山留め壁を構築して、同山留め壁の内側地盤を掘削する山留め掘削工法において、山留め壁の頭部が内側へ倒れる変形を生じないように拘束し又は補強する工法の技術分野に属する。   The present invention relates to a construction method for constructing a retaining wall in the ground and excavating the inner ground of the retaining wall so as to restrain or reinforce the retaining wall so that the head of the retaining wall does not fall inwardly. It belongs to the technical field.

掘削する地盤の周囲に山留め壁を構築して地盤を掘削する山壁め掘削工法としては、従来、いわゆるシートパイルを連続壁状態に地中へ打設して山留め壁を構築する工法、或いはH形鋼柱を地中へ打設し、そのH形鋼柱の間へ土留め板を建て込んで山留め壁を構築する工法が実施されたほか、軟弱地盤の場合には、原位置地盤土と安定材(セメント)とを攪拌・混合したソイルセメントで造成した地盤改良柱を連続させた山留め壁を構築し、或いは同地盤改良柱の中へ芯材を挿入して補強、補剛した自立山留め壁を構築する工法が広く実施されている(下記の特許文献1〜3を参照)。   As a mountain wall excavation method for excavating the ground by constructing a retaining wall around the ground to be excavated, conventionally, a method of constructing a retaining wall by placing a so-called sheet pile into the ground in a continuous wall state, or H In addition to implementing a method of constructing a retaining wall by placing a steel column into the ground and installing a retaining plate between the H-shaped steel columns, in the case of soft ground, Build a retaining wall made of continuous soil improvement pillars made of soil cement mixed and mixed with stabilizer (cement), or insert a core material into the ground improvement pillars to reinforce and stiffen it. A construction method for constructing a wall is widely implemented (see Patent Documents 1 to 3 below).

その他、下記の特許文献4には、ソイルセメントで造成した地盤改良柱を連続させた山留め壁を構築すると共に、同地盤改良柱の頭部の背面側地盤の表層に捨てコンクリートを打設して前記地盤改良柱の頭部と結合し、もって地盤改良柱へ芯材を建て込むことを無用とし、コストダウンを図った山留め壁工法が開示されている。
更に、下記の特許文献5には、芯材入りソイルセメント柱列山留め壁を内側から支持する切梁が無用となるように、又は切梁の段数を減らせるように、地山側(背面側地盤)にソイルセメント柱列の芯材と平行する弦材を打ち込み、この弦材と芯材とを束材および斜材で連結して、地山側の側圧に対する補強、補剛を行ったソイルセメント柱列山留め壁工法が開示されている。
In addition, in Patent Document 4 below, a retaining wall is constructed in which ground improvement columns made of soil cement are connected, and abandoned concrete is placed on the surface of the ground on the back side of the head of the ground improvement columns. There is disclosed a mountain retaining wall method that is combined with the head of the ground improvement pillar and eliminates the need to build a core material in the ground improvement pillar, thereby reducing the cost.
Furthermore, in Patent Document 5 below, the ground side (back side ground) is used so that the beam supporting the soil cement pillar row retaining wall with core material from the inside becomes unnecessary or the number of steps of the beam can be reduced. ) Soil cement columns that are driven by a string material parallel to the core material of the soil cement column array, and the string material and the core material are connected by a bundle material and a diagonal material to reinforce and stiffen the side pressure on the natural ground side. A row retaining wall method is disclosed.

特開平2−74715号公報Japanese Patent Laid-Open No. 2-74715 特開平4−115016号公報Japanese Patent Laid-Open No. 4-115016 特開平7−197450号公報JP-A-7-197450 特開平11−350491号公報JP-A-11-350491 特開2003−55959号公報JP 2003-55959 A

地盤の掘削工事を目的として構築する山壁め壁は、所詮は仮設物であり、事後には解体し撤去することを前提に構築し使用される。したがって、仮設工事はなるべく安価に短時間で施工できることが望ましい。
その点、上記特許文献1〜3に開示された山壁め壁構築工法は、いわゆる軟弱地盤の特質を活用した施工法として有効的である。しかし、もともと軟弱地盤であるが故に、山留め壁を構築して地盤の掘削を開始すると、地盤の掘削に使用するバックホウ、或いは切梁の架設や掘削土の搬出に使用するクローラクレーン、ダンプトラックなどの重機類が山留め壁頭部の背面側地盤の上に載り、山留め壁に接近して稼働するため、そうした重機類の重量や作業荷重によって山留め壁の頭部に対する側圧が増大し、山留め壁の頭部が掘削側へ倒れる変形を生じ、ひいては周辺地山の変形や沈下が大きくなること、および山留め壁にその耐力以上の荷重が作用するといった重大な問題点が起きる。
The wall of the mountain wall built for the purpose of excavating the ground is a temporary structure, and is constructed and used on the assumption that it will be demolished and removed after the fact. Therefore, it is desirable that the temporary construction can be performed in as short a time as possible.
In that respect, the mountain wall wall construction method disclosed in Patent Documents 1 to 3 is effective as a construction method utilizing the characteristics of so-called soft ground. However, because it is originally soft ground, when a ground retaining wall is constructed and excavation of the ground begins, backhoes used for excavating the ground, crawler cranes used for erection of cut beams and excavation soil, dump trucks, etc. Heavy machinery rests on the back ground of the head of the retaining wall and operates close to the retaining wall, so that the side pressure against the head of the retaining wall increases due to the weight and work load of such heavy machinery. The head will be deformed to fall to the excavation side, resulting in significant deformations and subsidence of the surrounding ground, and serious problems such as the load exceeding the proof stress acting on the retaining wall.

その点、上記特許文献4に開示された発明は、地盤改良柱頭部の背面側地盤の表層に捨てコンクリートを打設して前記地盤改良柱の頭部と結合するので、一見、山留め壁頭部の変形を抑止する作用効果を期待できると誤解しやすい。しかし、捨てコンクリートは厚さにして5〜30cm程度のコンクリート構造物にすぎないから、上記の重機類が山留め壁頭部の捨てコンクリート上に載ると、そうした重機類の重量や作業荷重によって簡単に亀裂を生じ破損してしまうから、山留め壁の頭部に対する側圧の増大を抑制する効果は期待することは難しい。また、捨てコンクリートは事後の解体、撤去が困難で、例えばバックホウでザクザクと解体することは望み得ない。   In that respect, the invention disclosed in the above-mentioned Patent Document 4 is abandoned concrete placed on the surface layer of the ground on the back side of the ground improvement column head and joined with the head of the ground improvement column. It is easy to misunderstand that it can be expected to have the effect of suppressing the deformation of. However, since the discarded concrete is only a concrete structure having a thickness of about 5 to 30 cm, when the above heavy machinery is placed on the discarded concrete on the head of the retaining wall, it is easily determined by the weight and work load of such heavy machinery. Since it cracks and breaks, it is difficult to expect the effect of suppressing an increase in lateral pressure on the head of the retaining wall. In addition, it is difficult to disassemble and remove post-mortem concrete. For example, it is impossible to expect to dismantle with a backhoe.

上記捨てコンクリートの代わりに、山留め壁頭部の背面側地盤が軟弱である場合の対策として、その表層地盤を事後の解体、撤去が容易なソイルセメントに改良処理した場合も同様で、重機類の重量や作業荷重によって崩壊し、山留め壁に対する側圧荷重の軽減効果は期待できない。
一旦山留め壁が内側へ倒れる変形をし始めると、上記捨てコンクリートやソイルセメントによる表層改良体は簡単に崩壊を始め、載荷重(側圧)の分散効果は消滅する。
Instead of the above-mentioned discarded concrete, as a countermeasure when the back side ground of the head of the retaining wall is soft, the same applies to the case where the surface ground is modified to soil cement that can be easily disassembled and removed. It will collapse due to weight and work load, and it cannot be expected to reduce the lateral pressure load on the retaining wall.
Once the mountain retaining wall starts to be deformed to fall inward, the surface improvement body by the above-mentioned discarded concrete or soil cement starts to collapse easily, and the effect of dispersing the loading load (side pressure) disappears.

また、上記特許文献5に開示された発明のように、芯材入りソイルセメント柱列山留め壁よりも地山側(背面側地盤)に芯材と平行する弦材を打ち込み、この弦材と芯材とを束材および斜材で連結した構成のソイルセメント柱列山留め壁も、山留め壁の補強、補剛効果を注目できる。しかし、地盤改良柱の頭部の変形を抑止する拘束、補強にはさほど有効とはいえない。また、弦材を打ち込み、この弦材と芯材とを束材および斜材で連結して補強する作業が面倒で、工費が嵩み、工期が長引く上に、事後の解体、撤去にも手数が掛かるという問題点がある。   Further, as in the invention disclosed in the above-mentioned Patent Document 5, a chord material parallel to the core material is driven into the ground mountain side (back side ground) from the soil cement pillar row retaining wall containing the core material, and the chord material and the core material The soil cement pillar row retaining wall constructed by connecting the two with a bundle material and an oblique member can also pay attention to the reinforcement and stiffening effect of the retaining wall. However, it cannot be said to be very effective for restraint and reinforcement that suppresses deformation of the head of the ground improvement pillar. In addition, it is cumbersome to drive and reinforce the string material and connect the string material and the core material with a bundle material and a diagonal material, which increases the construction cost, prolongs the work period, and requires time for disassembly and removal after the fact. There is a problem that it takes.

本発明の目的は、重機類が山留め壁頭部の背面側地盤の上に載り、山留め壁に接近して稼働しても、そうした重機類の重量や作業荷重によってひび割れたり崩壊しないだけに補強されて山留め壁頭部への側圧が増大することを防止でき、且つ山留め壁頭部が掘削側へ倒れる変形は積極的に抑止することができ、もって周辺地山に変形や沈下を生じさせず、また、山留め壁にその耐力以上の荷重が作用することを有効に防止できる山留め壁頭部の拘束工法を提供することである。
本発明の次の目的は、施工が容易で安価に短工期で実施でき、事後の解体、撤去の作業が容易で、産業廃棄物を発生しない山留め壁頭部の拘束工法を提供することである。
The object of the present invention is to reinforce the heavy machinery so that it does not crack or collapse due to the weight or work load of heavy machinery even if the heavy machinery rests on the backside ground of the retaining wall head and operates close to the retaining wall. It is possible to prevent the lateral pressure on the head of the retaining wall from increasing, and the deformation that the retaining wall head falls to the excavation side can be positively suppressed, so that the surrounding ground is not deformed or subsidized, Another object of the present invention is to provide a restraining method for a head of a retaining wall that can effectively prevent a load exceeding its proof stress from acting on the retaining wall.
The next object of the present invention is to provide a restraining method for the head of a retaining wall that is easy to construct and can be carried out in a short construction period, is easy to be disassembled and removed afterwards, and does not generate industrial waste. .

上述した従来技術の課題を解決するための手段として、請求項1に記載した発明に係る山留め壁頭部の拘束工法は、
地中に山留め壁1を構築して、同山留め壁1の内側地盤を掘削する山留め掘削工法において山留め壁1の頭部が変形しないように拘束する工法であって、
山留め壁頭部の背面側地盤の表層土を、原位置土とセメントを混合したソイルセメントに改良し又はソイルセメントに置換する工事を行い、
ソイルセメントに改良した表層改良地盤4中に、複数のアンカー用鋼材5を背面方向へほぼ水平な配置で、且つ山留め壁の長手方向には補強効果を奏するピッチで複数本埋設して、同アンカー用鋼材5の一端を前記山留め壁の頭部と結合することを特徴とする。
As means for solving the above-described problems of the prior art, the restraint method for the head of the retaining wall according to the invention described in claim 1 is:
A construction method for constructing a retaining wall 1 in the ground and restraining the head of the retaining wall 1 from being deformed in a retaining mechanism for excavating the inner ground of the retaining wall 1.
The surface soil of the back side ground of the mountain retaining wall head is improved to soil cement mixed with in situ soil and cement, or replaced with soil cement.
In the surface improvement ground 4 improved to soil cement, a plurality of anchoring steel materials 5 are embedded in a substantially horizontal arrangement in the back direction and in the longitudinal direction of the retaining wall at a pitch that provides a reinforcing effect. One end of the steel material 5 is connected to the head of the retaining wall.

請求項2に記載した発明は、請求項1に記載した山留め壁頭部の拘束工法において、
山留め壁頭部の背面側地盤の表層土をソイルセメントに改良し又はソイルセメントに置換する工事は、原位置で表層土を攪拌してセメントと混合する施工法、又は表層土を掘削して改良施設へ運搬し、若しくは他所で掘削して改良施設へ運搬した土を改良施設においてセメントと混合してソイルセメントに改良処理し、そのソイルセメントを前記表層土の位置へ埋め戻す施工法により行うことを特徴とする。
請求項3に記載した発明は、請求項1に記載した山留め壁頭部の拘束工法において、
アンカー用鋼材5として鉄筋又はPC鋼材を使用し、同アンカー用鋼材5はソイルセメントに改良した表層改良地盤4の補強に適するピッチで複数本を表層改良地盤4中に埋設し、その中で山留め壁1の芯材6と相対峙する鋼材5の一端を同芯材6の頭部と結合することを特徴とする。
請求項4に記載した発明は、請求項1に記載した山留め壁頭部の拘束工法において、
アンカー用鋼材5として鉄筋又はPC鋼材を使用し、同アンカー用鋼材5はソイルセメントに改良した表層改良地盤4の補強に適するピッチで複数本を表層改良地盤4中に埋設し、その中の一部の鋼材5の端部を山留め壁1の頭部と反力受け具10、11を介して結合することを特徴とする。
The invention described in claim 2 is a method for restraining a mountain retaining wall head according to claim 1,
The construction of the surface soil on the back side of the mountain retaining wall head with soil cement is improved or replaced with soil cement. The construction method is to stir the surface soil in situ and mix with cement, or excavate the surface soil to improve. The soil transported to the facility, or excavated elsewhere and transported to the improved facility is mixed with cement in the improved facility and improved to soil cement, and the soil cement is refilled to the position of the surface soil. It is characterized by.
The invention described in claim 3 is the restraint method for the head of the retaining wall described in claim 1,
Reinforcing steel or PC steel material is used as the anchoring steel material 5, and the anchoring steel material 5 is embedded in the surface improvement ground 4 at a pitch suitable for reinforcement of the surface improvement ground 4 improved to soil cement, and is fastened therein. One end of the steel material 5 facing the core material 6 of the wall 1 is connected to the head of the core material 6.
The invention described in claim 4 is the restraint method of the head of the retaining wall described in claim 1,
Reinforcing steel or PC steel material is used as the anchoring steel material 5, and a plurality of anchoring steel materials 5 are embedded in the surface improvement ground 4 at a pitch suitable for reinforcement of the surface improvement ground 4 improved to soil cement. The end of the steel material 5 is connected to the head of the retaining wall 1 via the reaction force receivers 10 and 11.

本発明に係る山留め壁頭部の拘束工法は、山留め壁頭部の背面側地盤の表層土を、原位置土とセメントを混合したソイルセメントに改良し、又はソイルセメントに置換し、ソイルセメントに改良した表層改良地盤4中に、複数本のアンカー用鋼材5を背面方向へほぼ水平に、且つ山留め壁の長手方向に補強効果を奏するピッチで複数本埋設して、同アンカー用鋼材5の一端を前記山留め壁1の頭部と結合するから、第一に、アンカー用鋼材5が表層改良地盤4の補強材として働き、載荷重に対して強い剪断補強効果を発揮する。そのため重機類が山留め壁頭部の背面側地盤の上に載り、山留め壁1に接近して稼働しても、表層改良地盤4はそうした重機類の重量や作業荷重に耐える強度と剛性を発揮し、或いは荷重分散の効果を発揮するので、重機類の載荷重を受けても、山留め壁1の頭部を掘削側へ倒す側圧作用が軽減され、且つ山留め壁1にその耐力以上の荷重が作用することを有効に抑止できる。   The method of restraining the head of the retaining wall according to the present invention is to improve the surface soil of the back side ground of the retaining wall head to a soil cement mixed with in-situ soil and cement, or to replace the soil cement with the soil cement. A plurality of anchor steel materials 5 are embedded in the improved surface layer improved ground 4 at a pitch that exerts a reinforcing effect substantially horizontally in the back direction and in the longitudinal direction of the retaining wall, and one end of the anchor steel material 5 is embedded. Is coupled to the head of the retaining wall 1, firstly, the anchoring steel material 5 works as a reinforcing material for the surface-improved ground 4 and exhibits a strong shear reinforcement effect against the load. Therefore, even if heavy machinery rests on the back side ground of the retaining wall head and operates close to the retaining wall 1, the surface improvement ground 4 exhibits strength and rigidity that can withstand the weight and work load of such heavy machinery. In addition, since the load distribution effect is exhibited, even if the load of heavy machinery is received, the side pressure action of depressing the head of the retaining wall 1 to the excavation side is reduced, and a load exceeding the proof stress acts on the retaining wall 1. Can be effectively suppressed.

第二に、アンカー用鋼材5は、表層改良地盤4と強く付着、密着してアンカー用鋼材5の引き抜きに大きな抵抗力を生じ、アンカー機能を発揮するので、このアンカー用鋼材5の一端を前記山留め壁1の頭部と結合した効果として、やはり山留め壁1の頭部が掘削側へ倒れる変形に抵抗して山留め壁頭部の拘束効果を発揮する。
こうして山留め壁頭部の変形が効果的に拘束される結果、相対的に周辺地山に変形や沈下が発生することも効果的に防止でき、安全性の高い地盤掘削工事を可能にする。
Secondly, the anchoring steel material 5 strongly adheres and closely adheres to the surface improvement ground 4 and generates a large resistance to pulling out the anchoring steel material 5 and exerts an anchor function. As an effect combined with the head of the retaining wall 1, the restraining effect of the retaining wall head is exhibited by resisting the deformation that the head of the retaining wall 1 falls to the excavation side.
As a result of effectively restraining the deformation of the head of the retaining wall, it is possible to effectively prevent deformation and subsidence in the surrounding natural ground, and to enable highly safe ground excavation work.

その上、本発明の拘束工法は、山留め壁頭部の背面側地盤の表層土を、原位置土とセメントを混合したソイルセメントに改良し、又はソイルセメントに置換して、複数のアンカー用鋼材5を背面方向へほぼ水平に埋設する既往技術の工程で実施できるから、施工が容易であり、安価に短工期に実施できる。
しかも、ソイルセメントに改良した表層改良地盤4は、アンカー用鋼材5を埋設していても、事後の解体、撤去の作業は、例えばバックホウでザクザクと掘削する方法で容易に解体でき、アンカー用鋼材5との分別も容易である。
Moreover, in the restraint method of the present invention, the surface soil of the back side ground of the retaining wall head is improved to soil cement mixed with in-situ soil and cement, or replaced with soil cement, and a plurality of steel materials for anchors are used. Since it can be carried out in the process of the existing technique of burying 5 almost horizontally in the back direction, construction is easy and can be carried out at a low cost and in a short construction period.
Moreover, even if the surface improvement ground 4 improved to soil cement is embedded with the anchor steel material 5, the subsequent dismantling and removal work can be easily dismantled by a method of excavating with a backhoe, for example, and the anchor steel material. Separation from 5 is easy.

地中に山留め壁1を構築して、同山留め壁1の内側地盤を掘削する山留め掘削工法において山留め壁1の頭部が変形しないように拘束するための施工法である。
山留め壁頭部の背面側地盤の表層土を、原位置土とセメントを混合したソイルセメントに改良し、又はソイルセメントに置換する工事を行う。
ソイルセメントに改良した表層改良地盤4中に、複数本のアンカー用鋼材5を背面方向へほぼ水平に、且つ山留め壁1の長手方向へは補強効果を発揮するピッチで埋設して、同アンカー用鋼材5の一端を前記山留め壁1の頭部と結合する。
山留め壁頭部の背面側地盤の表層土をソイルセメントに改良し、又はソイルセメントに置換する工事は、原位置で表層土を攪拌してセメントと混合する施工法により、又は表層土を掘削して改良施設へ運搬し、若しくは他所で掘削して改良施設へ運搬した土を改良施設においてセメントと混合してソイルセメントに改良処理し、そのソイルセメントを前記表層土の位置へ埋め戻す施工法により行う。
アンカー用鋼材5としては鉄筋又はPC鋼材を使用し、同アンカー用鋼材5はソイルセメントに改良した表層改良地盤4の補強に適するピッチで複数本を表層改良地盤4中に埋設し、その中で山留め壁1の芯材6と対応する鋼材の一端を山留め壁1の同芯材6の頭部と結合する。
或いは前記のように埋設したアンカー用鋼材5中の一部の鋼材5の端部を山留め壁1の頭部と反力受け具10、11を介して結合する。
This is a construction method for constraining the head of the retaining wall 1 from being deformed in the retaining retaining excavation method in which the retaining wall 1 is constructed in the ground and the inner ground of the retaining wall 1 is excavated.
The surface soil on the back side ground of the head of the retaining wall will be improved with soil cement mixed with in-situ soil and cement, or replaced with soil cement.
A plurality of anchoring steel materials 5 are embedded in the surface improvement ground 4 improved to soil cement substantially horizontally in the back direction and in the longitudinal direction of the retaining wall 1 at a pitch that exhibits a reinforcing effect. One end of the steel material 5 is coupled to the head of the retaining wall 1.
The surface soil on the back side of the head of the retaining wall is modified with soil cement or replaced with soil cement. The surface soil is stirred in place and mixed with cement, or the surface soil is excavated. The soil that has been transported to the improved facility, or excavated elsewhere and transported to the improved facility is mixed with cement at the improved facility to improve the soil cement, and then the soil cement is refilled to the surface soil location. Do.
Reinforcing steel or PC steel is used as the anchoring steel 5, and the anchoring steel 5 is embedded in the surface improvement ground 4 at a pitch suitable for reinforcement of the surface improvement ground 4 improved by soil cement. One end of the steel material corresponding to the core material 6 of the retaining wall 1 is coupled to the head of the concentric material 6 of the retaining wall 1.
Or the edge part of some steel materials 5 in the steel materials 5 for anchors embed | buried as mentioned above is couple | bonded with the head part of the retaining wall 1 via the reaction force receptacles 10 and 11. FIG.

次に、本発明に係る山留め壁頭部の拘束工法を、図示した実施例に基づいて説明する。 先ず図1は、掘削するべき地盤の外周位置の地中に山留め壁1を構築し、同山留め壁1の内側地盤を掘削する山留め掘削工法の実施状況を平面図として示している。図中の符号2、3は前記山留め壁1の内側へ組み入れて架設した切梁と腹起こしを示す。
また、図中の符号4は、前記山留め壁1の外周の軟弱地盤について、山留め壁頭部の背面側地盤の表層土を、原位置土とセメントを混合したソイルセメントに改良し、又はサイト等に用意した改良施設で改良処理したソイルセメントを再び埋め戻して置換する工事を行った表層改良地盤を示している。
Next, the method of restraining the head of the retaining wall according to the present invention will be described based on the illustrated embodiment. First, FIG. 1 is a plan view showing the state of implementation of a mountain retaining excavation method in which a retaining wall 1 is constructed in the ground at the outer peripheral position of the ground to be excavated and the inner ground of the retaining wall 1 is excavated. Reference numerals 2 and 3 in the figure indicate a cut beam and an upset erected in the inside of the retaining wall 1.
Further, reference numeral 4 in the figure indicates that the soft soil on the outer periphery of the retaining wall 1 is modified with a soil cement in which the soil on the back side of the retaining wall head is mixed with in situ soil and cement, or a site, etc. Fig. 1 shows the surface improved ground where the soil cement improved at the improved facility prepared in 1 is refilled and replaced.

上記した山留め壁頭部の背面側地盤の表層土を、原位置土とセメントを混合したソイルセメントに改良し、又はソイルセメントに置換する工事は、既往の技術として次のように実施される。
具体的には、図示を省略したスタピライザの如き地盤改良処理機を搬入し、原位置の表層土を直接、深さ70cm〜150cmぐらいまでをセメントと攪拌、混合する地盤改良工法を実施する。
或いは山留め壁頭部の背面側地盤の表層土を、バックホウやブルドーザー、ユンボ等の重機により、やはり地下70cm〜150cmぐらいまで掘削し、その掘削土は一旦サイトに用意した改良施設へ運搬する。又は他所で掘削した土砂をサイトの改良施設へ運び込み、そうした掘削土を改良施設においてセメントと均一に攪拌、混合してソイルセメントに改良処理し、出来上がったソイルセメントを再び前記山留め壁頭部の背面側地盤の表層土上へ運搬して埋め戻す施工法を実施する。
いずれの施工法を採用して実施するかは、現場の施工条件や環境条件などに応じて適宜に選択することになる。かくして形成する表層改良地盤4の幅員Wは4mないし6mぐらいとし、その深さH(層厚)はおよそ70cmないし150cmを目安に施工する。
The above-described construction in which the surface soil on the back side ground of the retaining wall head is replaced with soil cement mixed with in-situ soil and cement, or replaced with soil cement is performed as follows.
Specifically, a ground improvement processing machine such as a stabilizer (not shown) is carried in, and a ground improvement method is carried out in which the surface soil in the original position is directly stirred and mixed with cement to a depth of about 70 cm to 150 cm.
Alternatively, the surface soil on the back side ground of the retaining wall head is excavated to about 70 cm to 150 cm underground by heavy machinery such as a backhoe, bulldozer, and yumbo, and the excavated soil is once transported to an improved facility prepared at the site. Or, the soil excavated elsewhere is carried to the site improvement facility, and the excavated soil is uniformly stirred and mixed with the cement in the improvement facility to improve the soil cement. Carry out the construction method of transporting back to the surface soil of the side ground.
Which construction method is employed is selected as appropriate according to the construction conditions and environmental conditions at the site. The surface improvement ground 4 thus formed has a width W of about 4 m to 6 m and a depth H (layer thickness) of about 70 cm to 150 cm.

本発明の特徴は、上記のように原位置土を直接改良処理し、又は表層土をソイルセメントと置換して形成した表層改良地盤4の中に、複数のアンカー用鋼材5を、図1〜図3に示したように、背面方向へほぼ水平に、且つ山止め壁1の長手方向には当該表層改良地盤4の補強効果を奏するピッチで埋設することにある。アンカー用鋼材5としては、外径が32mm程度の鉄筋又はPC鋼材を好適に使用することができる。アンカー用鋼材5の長さは、図2に見るとおり、表層改良地盤4の幅員Wよりも少し短い程度とする。
アンカー用鋼材5の平面配置のうち、上記表層改良地盤4の補強効果を奏するピッチで埋設するとは、具体的には上記の鉄筋又はPC鋼材を山止め壁1の長手方向に45cmピッチ程度に配置して埋設することを指す(図3を参照)。アンカー用鋼材5は、表層改良地盤4の層厚のおよそ中程の位置に埋設する。
そして、山留め壁1が芯材入り地盤改良柱であるときは、前記アンカー用鋼材5の中で、山留め壁1中に挿入した芯材6と相対峙する位置のアンカー用鋼材5の内端を、山留め壁頭部の芯材6と接点7において溶接等の方法で結合する。もっともアンカー用鋼材5の平面配置や本数、長さについては、山留め壁1を構成する資材に応じて太さ、材質、ピッチと共に決定して実施する。
A feature of the present invention is that a plurality of anchoring steel materials 5 are placed in the surface improvement ground 4 formed by directly improving the in-situ soil as described above or replacing the surface soil with soil cement. As shown in FIG. 3, the surface of the mountain retaining wall 1 is embedded at a pitch that exhibits the reinforcing effect of the surface improvement ground 4 substantially horizontally in the rear direction and in the longitudinal direction of the mountain retaining wall 1. As the steel material 5 for anchors, a rebar or PC steel material having an outer diameter of about 32 mm can be suitably used. As shown in FIG. 2, the length of the steel for anchor 5 is set to be slightly shorter than the width W of the surface improved ground 4.
Of the planar arrangement of the anchoring steel material 5, embedding at a pitch that exerts the reinforcing effect of the surface improvement ground 4 is specifically arranged at a pitch of about 45 cm in the longitudinal direction of the mountain retaining wall 1 with the above-mentioned reinforcing steel or PC steel material. To be buried (see FIG. 3). The anchoring steel material 5 is embedded at a position approximately in the middle of the layer thickness of the surface improved ground 4.
And when the mountain retaining wall 1 is a ground improvement pillar containing a core material, the inner end of the anchor steel material 5 at a position facing the core material 6 inserted into the mountain retaining wall 1 in the anchor steel material 5 is The core member 6 and the contact 7 of the head of the retaining wall are joined by a method such as welding. However, the planar arrangement, number, and length of the steel materials 5 for anchors are determined and implemented together with the thickness, material, and pitch according to the material constituting the retaining wall 1.

アンカー用鋼材5を、改良処理した表層改良地盤4の中程へ埋設する手法としては、次のように実施できる。
表層改良地盤4の形成を、山留め壁頭部の背面側地盤の表層土を掘削して一旦運び出し改良施設においてソイルセメントに改良処理して再度埋め戻す置換を行う施工法を実施する場合には、図3に例示したように、ソイルセメントを表層改良地盤4の層厚の約1/2程度に敷き均した時点で、同ソイルセメントの面上へアンカー用鋼材5を上記した配置に並べて置き、その一部の鋼材5は、内端を山留め壁頭部の芯材6と溶接等の方法で結合する。しかる後に、ソイルセメントの埋め戻しを残る1/2の層厚分だけ行い、締め固めて一体化させる。
As a method of burying the anchor steel material 5 in the middle of the improved surface layer improved ground 4, it can be carried out as follows.
When the surface layer improved ground 4 is formed, the surface soil of the back side ground of the retaining wall head is excavated, and once carried out, the soil cement is improved at the improved facility, and the construction method for refilling back is performed. As illustrated in FIG. 3, when the soil cement is spread to about ½ of the layer thickness of the surface improved ground 4, the anchor steel materials 5 are placed in the above arrangement on the surface of the soil cement, A part of the steel material 5 is joined at its inner end to the core material 6 of the mountain retaining wall head by a method such as welding. After that, backfilling of the soil cement is performed for the remaining 1/2 layer thickness, and compacted and integrated.

山留め壁頭部の背面側地盤の表層土を、スタピライザの如き地盤改良処理機で直接掘削しセメントと攪拌混合して改良処理する施工法を実施する場合には、同施工法の進捗にしたがい、施工直後の表層改良地盤4にアンカー用鋼材5の埋設用溝を掘り、その溝底へアンカー用鋼材5を置いて山留め壁頭部の芯材6と溶接等の方法で結合する。その後に前記溝を埋め戻し、強く締め固めて一体化を図る作業を繰り返す施工法を好適に実施することができる。
かくしてアンカー用鋼材5を表層改良地盤4の層厚の中程へ埋設すると、各アンカー用鋼材5は、表層改良地盤4と強く接着ないし付着して一体化し、同表層改良地盤4の補強材として働き、表層改良地盤4への載荷重に対して有効な剪断補強材としての作用効果を奏する。
When the construction method of excavating the surface soil of the back side ground of the mountain retaining wall head directly with a ground improvement processing machine such as a stabilizer and mixing with cement is improved, according to the progress of the construction method, A groove for embedding an anchor steel material 5 is dug in the surface improved ground 4 immediately after the construction, and the anchor steel material 5 is placed on the bottom of the groove and joined to the core material 6 of the retaining wall head by welding or the like. After that, it is possible to suitably carry out a construction method in which the groove is backfilled, and the work of reinforce and compacting is repeated.
Thus, when the anchoring steel material 5 is buried in the middle of the layer thickness of the surface improvement ground 4, each anchoring steel material 5 is strongly bonded or adhered to and integrated with the surface improvement ground 4 and is used as a reinforcing material for the surface improvement ground 4. Work and effect as an effective shear reinforcement for the load on the surface improvement ground 4 is achieved.

ここで、上記アンカー用鋼材5が表層改良地盤4と強く接着ないし付着して一体化した場合のアンカー効果を、強度設計の手法で示すと以下の通りである。
先ず、ソイルセメントに改良処理された表層改良地盤4の強度quは、過去の実績に基づいて、qu=0.1N/mmと仮定することができる。
この条件下で、アンカー用鋼材5の接着強度τuは、上記表層改良地盤4の強度quの約1/6と仮定すると、τu=qu/6=0.017N/mm程度を確保できるものと考えられる。
アンカー用鋼材5の太さがD32、長さL=6mの鉄筋で、その全長が図2に示したように表層改良地盤4の層厚の中程に深く埋設され一体化している場合に、この鉄筋1本当たりの接着強度Fuは、上記の事例によると、Fu=π・D・L×τu=10.2KNと算出される。つまり、この接着強度Fuにより、山留め壁頭部の芯材6を拘束して、その変形を抑制できることになる。
Here, the anchor effect when the anchor steel material 5 is strongly bonded to or adhered to the surface-improved ground 4 and integrated is shown by the following strength design method.
First, the strength qu of the surface improved ground 4 improved by soil cement can be assumed to be qu = 0.1 N / mm 2 based on the past results.
Under this condition, assuming that the adhesive strength τu of the anchoring steel material 5 is about 1/6 of the strength qu of the surface improved ground 4, it is possible to secure about τu = qu / 6 = 0.177 N / mm 2. Conceivable.
When the thickness of the anchoring steel material 5 is D32 and the length L = 6 m, and the entire length is deeply buried in the middle of the layer thickness of the surface improvement ground 4 as shown in FIG. According to the above example, the adhesive strength Fu per reinforcing bar is calculated as Fu = π · D · L × τu = 10.2 KN. That is, by this adhesive strength Fu, the core material 6 of the head of the retaining wall can be constrained and its deformation can be suppressed.

次に、上記山留め壁頭部の背面側地盤の表層土を表層改良地盤4で形成した場合に、この表層改良地盤4が載った表層土との摩擦抵抗を算定する。
表層改良地盤4の下に存在する表層土が緩い砂地盤で、その安息角φ=25°程度で、表層改良地盤4の単位体積重量γがγ=17KN/m程度、 表層改良地盤4の層厚hが70cmであると、表層改良地盤4が載った表層土との摩擦応力τrは、
τr=γ・h・tanφ=17×0.7×tan25°=5.5KN/m
と求めることができる。
山留め壁頭部が内側へ倒れる変位は、初期の掘削による影響が大きいと考えられる。そこで地下5mまでの掘削による変位を、本発明の拘束工法で抑制するものとし、45°の主動崩壊を仮定すると、表層改良地盤4の幅員Wが6mのうち、実質は幅員W1=4mのみが抵抗すると仮定する。すると上記アンカー用鋼材5の接着強度τuに相当する表層改良地盤4の底面に必要な分担幅Lは、次のように求めることができる。
L=Fu/(W1・τr)=10.2/4.0×5.5=0.46m。
したがって、山留め壁1が芯材入り地盤改良柱で構築され、芯材6のピッチが45cm程度であるときは、全芯材に1本づつ相対峙する配置のアンカー用鋼材5をそれぞれ表層改良地盤4の中に埋設すると、最大の山留め壁頭部の拘束効果が得られることがわかる。
Next, when the surface soil of the back side ground of the mountain retaining wall head is formed by the surface improved ground 4, the frictional resistance with the surface soil on which the surface improved ground 4 is placed is calculated.
The surface soil existing under the surface improvement ground 4 is a loose sand ground, the angle of repose φ is about 25 °, and the unit volume weight γ of the surface improvement ground 4 is about γ = 17 KN / m 2 . When the layer thickness h is 70 cm, the friction stress τr with the surface soil on which the surface improved ground 4 is placed is
τr = γ · h · tanφ = 17 × 0.7 × tan25 ° = 5.5 KN / m 2
It can be asked.
It is considered that the displacement of the head of the retaining wall falling inward is greatly affected by the initial excavation. Therefore, assuming that the displacement due to excavation up to 5m underground is restrained by the restraint method of the present invention and assuming 45 ° main dynamic collapse, the width W1 of the surface improvement ground 4 is only 6m out of the width W. Assume resistance. Then, the sharing width L required for the bottom surface of the surface improved ground 4 corresponding to the adhesive strength τu of the anchor steel material 5 can be obtained as follows.
L = Fu / (W1 · τr) = 10.2 / 4.0 × 5.5 = 0.46 m.
Therefore, when the mountain retaining wall 1 is constructed of a ground improvement column with a core material and the pitch of the core material 6 is about 45 cm, the anchor steel materials 5 arranged so as to face each other one by one with respect to the entire core material are respectively improved in the surface layer improvement ground. 4 shows that the maximum restraint effect of the retaining wall head can be obtained.

次に、図4は、アンカー用鋼材5と山留め壁1の頭部との結合の異なる実施例を示す。
即ち、山留め壁1の長手方向へ表層改良地盤4の補強に適するピッチで複数本配置し、同表層改良地盤4の層厚の中程へ埋設したアンカー用鋼材5のうちから、山留め壁頭部の拘束効果を考慮して選択した一部のアンカー用鋼材5の内端を、それぞれ山留め壁1の頭部を水平方向に内側まで貫通させる。そして、山留め壁1の頭部の内側面に腹起こしの如き反力受け10と受け台11を設置し、アンカー用鋼材5の内端を、いわゆる地盤アンカーの緊結に使用する結合具12により結合して固定した例である。
Next, FIG. 4 shows the Example from which the coupling | bonding of the steel material 5 for anchors and the head of the retaining wall 1 differs.
That is, a plurality of anchor steel members 5 are arranged in the longitudinal direction of the retaining wall 1 at a pitch suitable for reinforcement of the surface improvement ground 4 and embedded in the middle of the surface thickness of the surface improvement ground 4. The inner ends of some of the anchor steel materials 5 selected in consideration of the restraining effect are respectively penetrated through the heads of the retaining walls 1 inward in the horizontal direction. Then, a reaction force receiver 10 and a cradle 11 are installed on the inner side surface of the head of the retaining wall 1 and the inner end of the anchoring steel member 5 is coupled by a coupling tool 12 used for binding a so-called ground anchor. This is an example fixed.

以上に本発明を図示した実施例に基づいて説明したが、本発明は図示した実施例に限定されない。本発明の目的、要旨を逸脱することなく、いわゆる当業者が必要に応じて行う設計変更や変形、応用のバリエーションにも及ぶことを、念のために申し添える。   Although the present invention has been described above based on the illustrated embodiment, the present invention is not limited to the illustrated embodiment. It should be noted that the present invention extends to design changes, modifications, and application variations as required by those skilled in the art without departing from the scope and spirit of the present invention.

本発明による山留め壁頭部の拘束工法を実施した地盤掘削工事全景を概念的に示した平面図である。It is the top view which showed notionally the ground excavation construction whole view which implemented the restraint method of the retaining wall head by this invention. 図1のII−II線矢視の断面図である。It is sectional drawing of the II-II line | wire arrow of FIG. 表層改良地盤へアンカー用鋼材を埋設する要領を示す斜視図である。It is a perspective view which shows the point which embeds the steel material for anchors to a surface improvement ground. 図2とは異なる構成の実施例2を示した断面図である。FIG. 5 is a cross-sectional view illustrating a second embodiment having a configuration different from that of FIG. 2.

符号の説明Explanation of symbols

1 山留め壁
4 表層改良地盤(ソイルセメント)
5 アンカー用鋼材
10、11 反力受け具
1 Mountain retaining wall 4 Surface improved ground (soil cement)
5 Steel materials 10 and 11 for anchors

Claims (4)

地中に山留め壁を構築して、同山留め壁の内側地盤を掘削する山留め掘削工法において山留め壁の頭部が変形しないように拘束する工法であって、
山留め壁頭部の背面側地盤の表層土を、原位置土とセメントを混合したソイルセメントに改良し又はソイルセメントに置換する工事を行い、
ソイルセメントに改良した表層改良地盤中に、複数のアンカー用鋼材を背面方向へほぼ水平な配置で、且つ山留め壁の長手方向にか補強効果を奏するピッチで複数本埋設し、同アンカー用鋼材の一端を前記山留め壁の頭部と結合することを特徴とする、山留め壁頭部の拘束工法。
It is a construction method that constructs a retaining wall in the ground and restrains the head of the retaining wall from being deformed in the retaining mechanism for excavating the inner ground of the retaining wall,
The surface soil of the back side ground of the mountain retaining wall head is improved to soil cement mixed with in situ soil and cement, or replaced with soil cement.
In the surface improvement ground improved to soil cement, a plurality of anchoring steel materials are embedded in a horizontal direction in the back direction and at a pitch that exerts a reinforcing effect in the longitudinal direction of the retaining wall. A constraining method for a mountain retaining wall head, wherein one end is coupled to the head of the mountain retaining wall.
山留め壁頭部の背面側地盤の表層土をソイルセメントに改良し又はソイルセメントに置換する工事は、原位置で表層土を攪拌してセメントと混合する施工法、又は表層土を掘削して改良施設へ運搬し、若しくは他所で掘削して改良施設へ運搬した土を改良施設においてセメントと混合してソイルセメントに改良処理し、そのソイルセメントを前記表層土の位置へ埋め戻す施工法により行うことを特徴とする、請求項1に記載した山留め壁頭部の拘束工法。   The construction of the surface soil on the back side of the mountain retaining wall head with soil cement is improved or replaced with soil cement. The construction method is to stir the surface soil in situ and mix with cement, or excavate the surface soil to improve. The soil transported to the facility, or excavated elsewhere and transported to the improved facility is mixed with cement in the improved facility and improved to soil cement, and the soil cement is refilled to the position of the surface soil. The method for restraining a mountain retaining wall head according to claim 1, wherein: アンカー用鋼材として鉄筋又はPC鋼材を使用し、該アンカー用鋼材はソイルセメントに改良した表層改良地盤の補強に適するピッチで複数本を表層改良地盤中に埋設し、その中で山留め壁の芯材と相対峙する鋼材の一端を芯材の頭部と結合することを特徴とする、請求項1に記載した山留め壁頭部の拘束工法。   Reinforcing steel or PC steel is used as the anchoring steel, and the anchoring steel is embedded in the surface improvement ground at a pitch suitable for reinforcement of the surface improvement ground improved to soil cement, and the core material of the retaining wall therein 2. The method of restraining a mountain retaining wall head according to claim 1, wherein one end of a steel material facing the surface is coupled to the head of the core. アンカー用鋼材として鉄筋又はPC鋼材を使用し、該アンカー用鋼材はソイルセメントに改良した表層改良地盤の補強に適するピッチで複数本を表層改良地盤中に埋設し、その中の一部の鋼材の端部を山留め壁の頭部と反力受け具を介して結合することを特徴とする、請求項1に記載した山留め壁頭部の拘束工法。

Reinforcing steel or PC steel is used as the anchoring steel, and the anchoring steel is embedded in the surface improvement ground at a pitch suitable for reinforcement of the surface improvement ground improved to soil cement. The restraint method for a mountain retaining wall head according to claim 1, wherein the end portion is coupled to the head of the mountain retaining wall via a reaction force receiver.

JP2008258269A 2008-10-03 2008-10-03 Constraining method for mountain retaining wall head Active JP5180022B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008258269A JP5180022B2 (en) 2008-10-03 2008-10-03 Constraining method for mountain retaining wall head

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008258269A JP5180022B2 (en) 2008-10-03 2008-10-03 Constraining method for mountain retaining wall head

Publications (2)

Publication Number Publication Date
JP2010090532A true JP2010090532A (en) 2010-04-22
JP5180022B2 JP5180022B2 (en) 2013-04-10

Family

ID=42253509

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008258269A Active JP5180022B2 (en) 2008-10-03 2008-10-03 Constraining method for mountain retaining wall head

Country Status (1)

Country Link
JP (1) JP5180022B2 (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102505696A (en) * 2011-10-28 2012-06-20 上海建瓴工程咨询有限公司 Support system of rear support removing type section steel-concrete double-enclosing-purlin foundation pit and construction method
JP2014181487A (en) * 2013-03-19 2014-09-29 Kajima Corp Earth retaining structure and earth retaining method
JP2014224456A (en) * 2010-07-16 2014-12-04 鹿島建設株式会社 Shaft construction method and shaft structure on sloped ground
CN105297740A (en) * 2015-09-30 2016-02-03 常州大学怀德学院 FRP plate strip type foundation pit support structure and construction method
JP2017031727A (en) * 2015-08-04 2017-02-09 株式会社大林組 Deformation suppressing structure for earth retaining wall and deformation suppressing method for earth retaining wall
CN106978810A (en) * 2016-01-18 2017-07-25 浙江国泰建设集团有限公司 A kind of concrete inner support end uses the construction method of shaped steel tectonic system
CN112695767A (en) * 2020-12-22 2021-04-23 四汇建设集团有限公司 Water lowering structure and water lowering method for micro-expansive soil foundation pit soaked by underground water

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089061B (en) * 2015-08-11 2017-01-18 泰兴市第一建筑安装工程有限公司 Ultra-deep foundation pit supporting method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4891703U (en) * 1972-02-05 1973-11-05
JPS55148820A (en) * 1979-05-10 1980-11-19 Sanwa Kizai Co Ltd Method and device for improving soft ground
JPH06248650A (en) * 1993-03-02 1994-09-06 Kajima Corp Landslide protection method
JPH07259080A (en) * 1994-03-22 1995-10-09 Shimizu Corp Self-supported sheath wall structure
JP2001207451A (en) * 2000-01-25 2001-08-03 Yachiyo Engineering Co Ltd Earth retaining wall and construction method thereof

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS4891703U (en) * 1972-02-05 1973-11-05
JPS55148820A (en) * 1979-05-10 1980-11-19 Sanwa Kizai Co Ltd Method and device for improving soft ground
JPH06248650A (en) * 1993-03-02 1994-09-06 Kajima Corp Landslide protection method
JPH07259080A (en) * 1994-03-22 1995-10-09 Shimizu Corp Self-supported sheath wall structure
JP2001207451A (en) * 2000-01-25 2001-08-03 Yachiyo Engineering Co Ltd Earth retaining wall and construction method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2014224456A (en) * 2010-07-16 2014-12-04 鹿島建設株式会社 Shaft construction method and shaft structure on sloped ground
CN102505696A (en) * 2011-10-28 2012-06-20 上海建瓴工程咨询有限公司 Support system of rear support removing type section steel-concrete double-enclosing-purlin foundation pit and construction method
CN102505696B (en) * 2011-10-28 2014-06-11 上海建瓴工程咨询有限公司 Support system of rear support removing type section steel-concrete double-enclosing-purlin foundation pit and construction method
JP2014181487A (en) * 2013-03-19 2014-09-29 Kajima Corp Earth retaining structure and earth retaining method
JP2017031727A (en) * 2015-08-04 2017-02-09 株式会社大林組 Deformation suppressing structure for earth retaining wall and deformation suppressing method for earth retaining wall
CN105297740A (en) * 2015-09-30 2016-02-03 常州大学怀德学院 FRP plate strip type foundation pit support structure and construction method
CN106978810A (en) * 2016-01-18 2017-07-25 浙江国泰建设集团有限公司 A kind of concrete inner support end uses the construction method of shaped steel tectonic system
CN112695767A (en) * 2020-12-22 2021-04-23 四汇建设集团有限公司 Water lowering structure and water lowering method for micro-expansive soil foundation pit soaked by underground water

Also Published As

Publication number Publication date
JP5180022B2 (en) 2013-04-10

Similar Documents

Publication Publication Date Title
JP5180022B2 (en) Constraining method for mountain retaining wall head
JP5654641B2 (en) Reinforcement method of existing harbor quay
JP2010090608A (en) Method for constructing underground space and structure of the underground space
JP2007051486A (en) Sheet pile-combined spread foundation and its construction method
KR101006963B1 (en) Assembly retaining wall system using ground reinforcement and pile, and its construction method
JP2011094443A (en) Method for constructing wall surface work by using bag body
JP5683286B2 (en) Embankment structure and construction method thereof
KR100313721B1 (en) Method for designing synthetic underground retaining wall by temporary soil protection structure and working process of underground retaining wall of structure
JP6621243B2 (en) Yamadome frame and its construction method
JP3899094B2 (en) Foundation reinforcement method for existing structures by press-fitting steel pipe piles
JP2022171931A (en) Joint structure for pile and superstructure, and structural body
JP4524451B2 (en) Starting method of shield excavator
JP5777435B2 (en) Reinforcement method for foundations for small buildings
JP5423134B2 (en) Foundation structure
JP4466418B2 (en) Soil cement wall pile, soil cement structure
JP6357366B2 (en) Horizontal movement restraint method
JP7115923B2 (en) Foundation structure reinforcement method and foundation structure reinforcement structure
JP2013002077A (en) Ground improvement body, and piled raft foundation equipped therewith
JP5551943B2 (en) Foundation structure using ground improvement body
JP5036775B2 (en) Construction method of cast-in-place concrete pile or cylindrical ground improvement body
JP2008196255A (en) Pile foundation reinforcing structure and pile foundation reinforcing method
JP2016199915A (en) Foundation structure and foundation construction method
JPH07259080A (en) Self-supported sheath wall structure
JP5267242B2 (en) Pier foundation structure and bridge pier foundation construction method
JP3678290B2 (en) High earthquake resistance foundation

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110930

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20120815

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120828

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20121002

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20121218

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130110

R150 Certificate of patent or registration of utility model

Ref document number: 5180022

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250