JP2013070513A - 進相コンデンサ制御装置、及び、力率調整器 - Google Patents
進相コンデンサ制御装置、及び、力率調整器 Download PDFInfo
- Publication number
- JP2013070513A JP2013070513A JP2011207237A JP2011207237A JP2013070513A JP 2013070513 A JP2013070513 A JP 2013070513A JP 2011207237 A JP2011207237 A JP 2011207237A JP 2011207237 A JP2011207237 A JP 2011207237A JP 2013070513 A JP2013070513 A JP 2013070513A
- Authority
- JP
- Japan
- Prior art keywords
- reactive power
- load
- power load
- maximum
- phase advance
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E40/00—Technologies for an efficient electrical power generation, transmission or distribution
- Y02E40/30—Reactive power compensation
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
Abstract
【解決手段】進相コンデンサ制御装置1は、無効電力と、無効電力が得られた際に投入されていた進相コンデンサ4の容量との差分である無効電力負荷の変化実績に対して統計処理を行う変動統計処理部15を備える。また、進相コンデンサ制御装置1は、現在の無効電力負荷と、当該統計処理の結果とに基づいて最大の無効電力負荷たる最大無効電力負荷を予測する最大負荷予測部16と、当該最大無効電力負荷を補償可能な複数の進相コンデンサ4の投入及び開放の組合せを決定する投入決定部17と、当該決定した組合せに基づいて、複数の進相コンデンサ4を投入及び開放する制御を行う制御部18とを備える。
【選択図】図1
Description
図1は、本発明の実施の形態1に係る力率調整器100の構成を示す図である。この図に示すように、力率調整器100は、進相コンデンサ制御装置1と、商用系統の受電点2での無効電力(以下「受電点無効電力」と呼ぶこともある)を計測する無効電力計測器3と、互いに容量が異なる複数(ここでは2つ)の進相コンデンサ4とを備えている。
ただし、この式(1)において、αは1以上の任意の係数である。
図7は、本発明の実施の形態2に係る力率調整器100の構成を示す図である。以下、本実施の形態に係る力率調整器100(進相コンデンサ制御装置1)の説明において、実施の形態1で説明した構成要素と類似するものについては同じ符号を付して説明を省略する。
Claims (5)
- 商用系統の受電点において計測された無効電力に基づいて、互いに容量が異なる複数の進相コンデンサを前記受電点の負荷側において選択的に投入及び開放する制御を行う進相コンデンサ制御装置であって、
前記無効電力と、当該無効電力が得られた際に投入されていた前記進相コンデンサの容量との差分である無効電力負荷の変化実績に対して統計処理を行う変動統計処理部と、
現在の前記無効電力負荷と、前記変動統計処理部での前記統計処理の結果とに基づいて、現在から所定時間経過する将来までの最大の前記無効電力負荷たる最大無効電力負荷を予測する最大負荷予測部と、
前記最大負荷予測部で予測した前記最大無効電力負荷を補償可能な前記複数の進相コンデンサの投入及び開放の組合せを決定する投入決定部と、
前記投入決定部で決定した組合せに基づいて、前記複数の進相コンデンサを投入及び開放する制御を行う制御部と
を備える、進相コンデンサ制御装置。 - 請求項1に記載の進相コンデンサ制御装置であって、
前記無効電力負荷の前記変化実績は、現在から所定期間前の過去時点での前記無効電力負荷と、当該過去時点から現在までの最大の前記無効電力負荷との差として定義される前記所定期間ごとの変動幅を含み、
前記変動統計処理部は、
前記変動幅の平均及び標準偏差を求める統計処理を行い、
前記最大負荷予測部は、前記現在の無効電力負荷、前記平均及び前記標準偏差から、式(1)に基づいて、前記最大無効電力負荷を予測する、進相コンデンサ制御装置。
最大無効電力負荷=(現在の無効電力負荷)+(平均)+α×(標準偏差)…(1)
ただし、αは1以上の任意の係数 - 請求項1または請求項2に記載の進相コンデンサ制御装置であって、
前記変動統計処理部での前記統計処理の結果を、時間帯別及び前記無効電力負荷のレベル別に記憶する負荷変動データベースをさらに備え、
前記最大負荷予測部は、
現在の時間帯及び前記現在の無効電力負荷のレベルに対応する前記負荷変動データベースに記憶された前記統計処理の結果を、最新の統計処理の結果として取得し、当該最新の統計処理の結果と、前記現在の無効電力負荷とから前記最大無効電力負荷を予測する、進相コンデンサ制御装置。 - 請求項1または請求項2に記載の進相コンデンサ制御装置であって、
前記変動統計処理部での前記統計処理の結果を、時間帯別及び前記無効電力負荷のレベル別に記憶する負荷変動データベースをさらに備え、
前記最大負荷予測部は、
現在の時間帯及び前記現在の無効電力負荷のレベルに対応する前記負荷変動データベースに記憶された前記統計処理の結果を、最新の統計処理の結果として取得し、当該最新の統計処理の結果と、前記現在の無効電力負荷とから前記最大無効電力負荷を予測し、
現在の前記無効電力負荷と、現在から前記所定期間前の第1時点の前記無効電力負荷との第1差分が所定値以上であるかを検出するともに、当該第1時点の前記無効電力負荷と、前記第1時点から前記所定期間前の第2時点の前記無効電力負荷との第2差分が前記所定値以上であるかを検出する負荷変動初動検出部をさらに備え、
前記負荷変動初動検出部にて前記第1差分が前記所定値以上でかつ前記第2差分が前記所定値よりも小さいことを検出した場合には、前記最大負荷予測部が前記最新の統計処理の結果と前記現在の無効電力負荷とから前記最大無効電力負荷を予測するとともに、前記投入決定部及び前記制御部が動作し、
前記負荷変動初動検出部にて前記第1差分が前記所定値よりも小さいことを検出した場合には、前記投入決定部が前記現在の無効電力負荷を補償可能な前記複数の進相コンデンサの投入及び開放の組合せを決定するとともに、前記制御部が当該組合せに基づいて、前記複数の進相コンデンサを投入及び開放する、進相コンデンサ制御装置。 - 請求項1乃至請求項4のいずれかに記載の進相コンデンサ制御装置と、
前記受電点での前記無効電力を計測する無効電力計測器と、
前記複数の進相コンデンサと
を備え、
前記進相コンデンサには、
前記制御部の制御に応じて、前記進相コンデンサを投入及び開放するための開閉を行う開閉器が設けられている、力率調整器。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2011207237A JP5583094B2 (ja) | 2011-09-22 | 2011-09-22 | 進相コンデンサ制御装置、及び、力率調整器 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2011207237A JP5583094B2 (ja) | 2011-09-22 | 2011-09-22 | 進相コンデンサ制御装置、及び、力率調整器 |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2013070513A true JP2013070513A (ja) | 2013-04-18 |
JP5583094B2 JP5583094B2 (ja) | 2014-09-03 |
Family
ID=48475574
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2011207237A Expired - Fee Related JP5583094B2 (ja) | 2011-09-22 | 2011-09-22 | 進相コンデンサ制御装置、及び、力率調整器 |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5583094B2 (ja) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20160027710A (ko) * | 2014-09-02 | 2016-03-10 | 한전케이디엔주식회사 | 에너지 관리장치 |
WO2018121075A1 (zh) * | 2016-12-30 | 2018-07-05 | 常熟市五爱电器设备有限公司 | 一种具备串行接口oled显示屏的智能电容综合模块 |
WO2019017373A1 (ja) * | 2017-07-18 | 2019-01-24 | ダイキン工業株式会社 | アクティブフィルタシステム、空気調和装置 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0479727A (ja) * | 1990-07-20 | 1992-03-13 | Fuji Electric Co Ltd | 電圧・無効電力制御装置 |
JPH05328608A (ja) * | 1992-05-22 | 1993-12-10 | Tohoku Electric Power Co Inc | 電圧無効電力制御装置 |
JPH064159A (ja) * | 1992-06-16 | 1994-01-14 | Mitsubishi Electric Corp | 力率自動調整装置 |
JPH08251824A (ja) * | 1995-03-08 | 1996-09-27 | Nisshin Steel Co Ltd | 電力消費設備の力率予測方法および力率管理装置 |
-
2011
- 2011-09-22 JP JP2011207237A patent/JP5583094B2/ja not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0479727A (ja) * | 1990-07-20 | 1992-03-13 | Fuji Electric Co Ltd | 電圧・無効電力制御装置 |
JPH05328608A (ja) * | 1992-05-22 | 1993-12-10 | Tohoku Electric Power Co Inc | 電圧無効電力制御装置 |
JPH064159A (ja) * | 1992-06-16 | 1994-01-14 | Mitsubishi Electric Corp | 力率自動調整装置 |
JPH08251824A (ja) * | 1995-03-08 | 1996-09-27 | Nisshin Steel Co Ltd | 電力消費設備の力率予測方法および力率管理装置 |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20160027710A (ko) * | 2014-09-02 | 2016-03-10 | 한전케이디엔주식회사 | 에너지 관리장치 |
KR101635541B1 (ko) * | 2014-09-02 | 2016-07-01 | 한전케이디엔 주식회사 | 에너지 관리장치 |
WO2018121075A1 (zh) * | 2016-12-30 | 2018-07-05 | 常熟市五爱电器设备有限公司 | 一种具备串行接口oled显示屏的智能电容综合模块 |
WO2019017373A1 (ja) * | 2017-07-18 | 2019-01-24 | ダイキン工業株式会社 | アクティブフィルタシステム、空気調和装置 |
JP2019022439A (ja) * | 2017-07-18 | 2019-02-07 | ダイキン工業株式会社 | アクティブフィルタシステム、空気調和装置 |
US11577186B2 (en) | 2017-07-18 | 2023-02-14 | Daikin Industries, Ltd. | Active filter system and air conditioning device |
Also Published As
Publication number | Publication date |
---|---|
JP5583094B2 (ja) | 2014-09-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10116136B2 (en) | Primary frequency control through simulated droop control with electric loads | |
US20190296552A1 (en) | Energy storage controller with battery life model | |
KR101314075B1 (ko) | 그리드 응답 제어 디바이스 | |
US10345842B2 (en) | Power-distribution-system voltage control system, power-distribution-system voltage control method, and centralized voltage control apparatus | |
AU2016335874A1 (en) | Electrical energy storage system with battery power setpoint optimization based on battery degradation costs and expected frequency response revenue | |
US9733277B2 (en) | Voltage monitoring control device, voltage control device, and voltage monitoring control method | |
US20100094573A1 (en) | Short-Term Load Forecasting Based Capacity Check for Automated Power Restoration of Electric Distribution Networks | |
US20180262003A1 (en) | Power control device, operation plan planning method, and recording medium | |
JP5766364B1 (ja) | 電圧監視制御装置および電圧制御装置 | |
JP2007236038A (ja) | デマンド制御装置 | |
US10283961B2 (en) | Voltage and reactive power control system | |
JP5583094B2 (ja) | 進相コンデンサ制御装置、及び、力率調整器 | |
JP2010032072A (ja) | 消費電力制御装置、冷却システム及び消費電力制御方法 | |
EP1489715A1 (en) | Real-time emergency control in power systems | |
JP6338009B1 (ja) | 電力貯蔵装置を用いた電力安定化システム及び制御装置 | |
US20180159184A1 (en) | Power supply control device, power supply system, power supply control method, and program | |
JPWO2019150586A1 (ja) | 集中電圧制御装置および集中電圧制御システム | |
JP2015177628A (ja) | 蓄電池制御方法、制御装置、および蓄電池制御システム | |
RU2606672C2 (ru) | Способ уменьшения фликера в электродуговых печах и устройство для его осуществления | |
JP6478856B2 (ja) | 集中電圧制御装置および電圧制御システム | |
KR102051192B1 (ko) | 수요전력 예측을 이용한 전력피크 저감시스템 및 방법 | |
JP2015211618A (ja) | 蓄電池制御装置および蓄電池の制御方法 | |
WO2018150461A1 (ja) | 集中電圧制御装置および集中電圧制御システム | |
Widiputra et al. | Development of restoration algorithm under cold load pickup condition using tabu search in distribution system | |
JP2012205454A (ja) | デマンドコントロール装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20131007 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20140606 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20140617 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20140715 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5583094 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|