JP2011247059A - Reinforcement method for bridge abutment and back fill - Google Patents
Reinforcement method for bridge abutment and back fill Download PDFInfo
- Publication number
- JP2011247059A JP2011247059A JP2010124372A JP2010124372A JP2011247059A JP 2011247059 A JP2011247059 A JP 2011247059A JP 2010124372 A JP2010124372 A JP 2010124372A JP 2010124372 A JP2010124372 A JP 2010124372A JP 2011247059 A JP2011247059 A JP 2011247059A
- Authority
- JP
- Japan
- Prior art keywords
- abutment
- embankment
- reinforcement
- rod
- bridge girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000002787 reinforcement Effects 0.000 title claims abstract description 36
- 238000000034 method Methods 0.000 title claims abstract description 20
- 230000003014 reinforcing effect Effects 0.000 claims description 25
- 239000012779 reinforcing material Substances 0.000 claims description 16
- 238000009412 basement excavation Methods 0.000 claims description 10
- 238000010276 construction Methods 0.000 claims description 10
- 238000005553 drilling Methods 0.000 claims description 2
- 238000003756 stirring Methods 0.000 description 4
- 239000011162 core material Substances 0.000 description 3
- 239000004568 cement Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 239000008267 milk Substances 0.000 description 2
- 210000004080 milk Anatomy 0.000 description 2
- 235000013336 milk Nutrition 0.000 description 2
- 239000000203 mixture Substances 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 229910000831 Steel Inorganic materials 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
- 239000010959 steel Substances 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Images
Landscapes
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Bridges Or Land Bridges (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
本発明は、橋台と背面盛土の補強方法に関するものである。
さらに具体的には、背面を背面盛土構造として構築してある、鉄道橋台、道路橋台を補強する方法に関するものである。
The present invention relates to a method for reinforcing an abutment and a backfill.
More specifically, the present invention relates to a method for reinforcing a railroad abutment and a road abutment constructed with a backside embankment structure.
背面部を背面盛土構造とする鉄道橋台、道路橋台が多数存在する。
これらの橋台の中には現在の設計基準でみると耐震性について問題のある構造物も存在する。
そうでなくとも、橋台、橋桁の老朽化によって安全性が低下している可能性も考えられる。
そのような橋台、橋桁を補強する工法としては、従来から次のような工法が採用されている。
<1> 鉄道や道路の供用を確保するために仮線を、補修対象の橋台とは別に構築し、老朽化した橋台、橋桁を撤去して新たに構造物を構築する方法。
<2> 仮線を別途構築し、老朽化した橋台を補強する方法。
<3> 橋台に鋼板の巻き立てや増壁の新設を行って橋台補修する方法。
There are many railway abutments and road abutments with back embankment on the back.
Among these abutments, there are also structures that have problems with seismic resistance according to the current design standards.
Even if this is not the case, it is possible that the safety of the abutment and the bridge girder has deteriorated.
As a method for reinforcing such abutments and bridge girders, the following methods have been conventionally employed.
<1> A method of constructing a new structure by constructing a temporary line separately from the abutment to be repaired and removing the aged abutment and bridge girder in order to secure the use of railways and roads.
<2> A method of reinforcing aged abutments by constructing a temporary line separately.
<3> A method of repairing the abutment by winding a steel plate or installing a new wall on the abutment.
前記した従来の橋台と背面盛土の補強方法にあっては、次のような問題点がある。
<1> いずれの工法でも鉄道や車両の交通が不可能となってしまう時期が発生して周囲の経済活動に影響を与える。
<2> 仮線を構築するだけで大規模な工事となり、余分な膨大な費用が発生する。
<3> 鉄道の場合には夜間に使用しない状態が生じるが、その時間を利用して補強工事を行う場合にも、工事を短時間に分割して進めなければならず、不経済なものである。
<4> 地震時の振動で橋台が背面の背面盛土から瞬間的に離れると、その間隙に背面盛土が押し出し、橋台は元の姿勢に戻れない場合がある。この現象が繰り返すことで、橋台背面の背面盛土が1メートル近くも沈下した例が報告されている。
<5> したがって橋台だけを補強しても、背面盛土が大きく沈下したケースのように、橋台と背面盛土との一体化がなければ大きな事故につながる可能性がある。
The above-described conventional abutment and back embankment reinforcement methods have the following problems.
<1> Regardless of the method of construction, there will be times when rail and vehicle traffic will be impossible, affecting the surrounding economic activities.
<2> Construction of a temporary line is a large-scale construction, resulting in an extra huge cost.
<3> In the case of railroads, there is a situation where it is not used at night, but even when reinforcement work is performed using that time, the work must be divided into short periods of time, which is uneconomical. is there.
<4> If the abutment is momentarily separated from the back embankment due to vibration during an earthquake, the back embankment may be pushed out into the gap and the abutment may not return to its original position. It has been reported that when this phenomenon is repeated, the back embankment on the back of the abutment has subsided nearly 1 meter.
<5> Therefore, even if only the abutment is reinforced, there is a possibility that it will lead to a major accident if the abutment and the back embankment are not integrated, as in the case where the back embankment sinks greatly.
上記のような課題を解決するために、本発明の橋台と背面盛土の補強方法は、背面に背面盛土を有し橋桁を支持する橋台の側面の背面盛土を、橋台の両側面に沿って橋桁の軸方向と平行方向に掘削し、掘削して形成した橋桁の軸方向と直交する方向の新設掘削面に、橋桁の軸方向と平行に棒状補強材を打設し、この棒状補強材に反力を取れる状態で、橋台の両側面に側面補強ブロックを打設し、橋台から突設した、あと施工アンカーを介して、側面補強ブロックと橋台を一体化し、さらに背面盛土の周囲を囲む石積などの既設盛土擁壁にも、その表面から棒状補強材を打設し、この棒状補強材に反力を取れる状態で、既設盛土擁壁の外側に、盛土補強壁を構築して構成する、橋台と背面盛土の補強方法を特徴としたものである。
In order to solve the above-described problems, the abutment and back embankment reinforcement method of the present invention includes a back embankment on the side of an abutment that has a back embankment on the back and supports the abutment, and a bridge girder along both sides of the abutment. Drilled in a direction parallel to the axial direction of the bridge girder, a bar-shaped reinforcing material was placed in parallel to the axial direction of the bridge girder on the newly excavated surface in a direction perpendicular to the axial direction of the bridge girder formed by drilling. Side reinforcement blocks are placed on both sides of the abutment in a state where force can be taken, and the side reinforcement blocks and the abutment are integrated via post-installed anchors, and stone masonry surrounding the back embankment, etc. An abutment constructed by constructing a bank reinforcing wall outside the existing bank retaining wall in a state where a bar reinforcing material is placed on the existing bank retaining wall from the surface and a reaction force can be applied to the bar reinforcing material. And the back embankment reinforcement method.
本発明の橋台と背面盛土の補強方法は以上説明したようになるから次のような効果のいずれかを得ることができる。
<1> 鉄道や道路の通行を確保したまま、仮線を設置することなく橋台と背面盛土を補強することができる。
<2> 棒状補強材を設置し、側面補強ブロックを介して橋台を支持するために、その抵抗力によって橋台の地震時の安定性が大幅に向上する。
<3> 背面盛土内に打設した棒状補強材を介して、橋台と側面補強ブロックと背面盛土が一体化しているので、地震時にも橋台の背面の背面盛土が一体化して挙動し、背面盛土の沈下が発生しにくい。
Since the abutment and back embankment reinforcement method of the present invention is as described above, one of the following effects can be obtained.
<1> The abutment and back embankment can be reinforced without installing temporary lines while ensuring the passage of railways and roads.
<2> Since the rod-shaped reinforcing material is installed and the abutment is supported via the side reinforcing blocks, the resistance of the abutment during earthquake is greatly improved.
<3> Since the abutment, the side reinforcement block, and the back embankment are integrated via a bar-shaped reinforcement placed in the back embankment, the back embankment on the back of the abutment behaves in an integrated manner even during an earthquake. Sinking is unlikely to occur.
以下図面を参照にしながら本発明の好適な実施の形態を詳細に説明する。 DESCRIPTION OF EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.
<1>前提条件。(図1)
前記したように、本発明の補強方法の対象は、背面に背面盛土3を有する橋台1と背面盛土3の補強方法である。
橋台1はコンクリート製であり、道路などを挟んで対面する2基の橋台1の上に、道路、鉄道などの橋桁2をかけ渡してある。
橋台1の両側の背面には背面盛土3が存在し、背面盛土3の裾部分は石積やコンクリート製造の既設盛土擁壁で包囲してある。
なお本明細書では、説明の便宜上から、平面視がほぼ矩形の橋台1について、背面盛土3側を「背面」、通路側を「前面」、橋桁2に平行の両側の面を「側面」と称することにする。
<1> Precondition. (Figure 1)
As described above, the object of the reinforcing method of the present invention is a method for reinforcing the abutment 1 having the back embankment 3 on the back surface and the back embankment 3.
The abutment 1 is made of concrete, and
On the back of both sides of the abutment 1, there is a back embankment 3, and the bottom of the back embankment 3 is surrounded by existing embankment retaining walls made of masonry or concrete.
In this specification, for the convenience of explanation, for the abutment 1 having a substantially rectangular plan view, the back embankment 3 side is referred to as “rear surface”, the passage side is referred to as “front surface”, and both sides parallel to the
<2>背面盛土の掘削。(図2)
橋台1の側面の背面盛土3、およびそれよりも奥の背面盛土3の一部を掘削する。
この掘削位置は、平面的に見て、鉄道や道路の路盤の外側である。
そのために、列車や車両の通行には影響を与えることはない。
掘削位置は、橋台1の脇の背面盛土3の状態によって異なるが、橋台1の両側面に沿って橋桁2の軸方向と平行方向に掘削する。(図2)
<2> Excavation of backfill. (Figure 2)
The back embankment 3 on the side surface of the abutment 1 and a part of the back embankment 3 behind it are excavated.
This excavation position is outside the roadbed of the railway or the road in a plan view.
Therefore, it does not affect the traffic of trains and vehicles.
The excavation position varies depending on the state of the back embankment 3 on the side of the abutment 1, but the excavation position is excavated along the both side surfaces of the abutment 1 in a direction parallel to the axial direction of the
<3>棒状補強材の打設。(図3)
その新設掘削面5に対して、橋桁2の軸方向と平行に棒状補強材4を打設する。
この棒状補強材4として、たとえば特許第2575329号に記載されたような公知の工法を採用することができる。
この特許工法は、中空回転軸の周囲に掘削翼と攪拌翼とを設けた掘削攪拌ロッドを使用する工法である。
そしてこの掘削攪拌ロッドによって地中に筒状の攪拌土とセメントミルクとの混合体を形成する。
この混合体の中心にはセメントミルクよりなる中央補強体を位置させる。
この中央補強柱の中央には、尾端を孔外に露出させた芯材を位置させてこの芯材を引張り補強体とするものである。
しかしこの工法は一例であり、その他の各種の公知の棒状補強材4を採用することができる。
この棒状補強材4の複数本を、図3に示すように新設掘削面5から橋桁2の軸方向とほぼ平行に背面盛土3内に打設する。
あるいは新設掘削面5から軌道センター方向に角度をつけて背面盛土3内に打設することもできる。
<3> Placing a rod-shaped reinforcing material. (Figure 3)
A rod-shaped reinforcing
As this rod-shaped reinforcing
This patent method is a method using an excavation stirring rod provided with an excavation blade and a stirring blade around a hollow rotating shaft.
The excavation stirring rod forms a mixture of cylindrical stirring soil and cement milk in the ground.
A central reinforcing body made of cement milk is located at the center of the mixture.
In the center of the central reinforcing column, a core material with the tail end exposed outside the hole is positioned, and this core material is used as a tension reinforcing body.
However, this construction method is an example, and various other known rod-shaped reinforcing
As shown in FIG. 3, a plurality of the rod-shaped reinforcing
Alternatively, it can be placed in the back embankment 3 at an angle from the newly excavated
<4>側面補強ブロックの構築。(図4)
棒状補強材4の打設が終わったら、掘削した空間の周囲に型枠を設置してコンクリートを打設して側面補強ブロック6を構築する。
その場合に側面補強ブロック6は、棒状補強材4に反力を取った状態で構築し、側面補強ブロックと背面盛土3の一体化を図る。
さらに側面補強ブロック6を橋台1と一体化する状態で構築する。
そのために橋台1から、あと施工アンカーを突設し、それを包囲する状態でコンクリートを打設して橋台1と側面補強ブロック6との一体化を図る。
この側面補強ブロック6を、両側の橋台1について同様の工程で構築する。
<4> Construction of side reinforcing blocks. (Fig. 4)
After the placement of the rod-shaped reinforcing
In that case, the
Further, the
For this purpose, a post-construction anchor is protruded from the abutment 1 and concrete is cast in a state surrounding the anchor, thereby integrating the abutment 1 and the
This
<5>既設盛土擁壁への棒状補強材の打設。(図5)
背面盛土3の裾部分を包囲した状態の既設盛土擁壁に棒状補強材を打設する。
既設盛土擁壁が石積で、個別の石塊が不安定な場合には、裏面にモルタルなどを注入して一体化した後に、既設盛土擁壁とその裏側の背面盛土に削孔して棒状補強材を打設する。
<5> Placing a rod-shaped reinforcing material on the existing embankment retaining wall. (Fig. 5)
A bar-shaped reinforcing material is placed on the existing embankment retaining wall in a state of surrounding the bottom portion of the back embankment 3.
If the existing embankment retaining wall is masonry and individual stone blocks are unstable, mortar is injected into the back and integrated, then drilled into the existing embankment retaining wall and the back embankment on the back side to reinforce the rod Placing material.
<6>盛土補強壁の構築。(図6)
既設盛土擁壁の外周に型枠を設置し、間隔に鉄筋を配筋してコンクリートを打設して盛土補強壁を構築する。
棒状補強材4の芯材などを打設するコンクリート内部に位置させることにより、盛土補強壁と棒状補強材4とは一体化しておく。
こうして既設盛土擁壁の外周に、背面盛土の内部の棒状補強材4と一体化した新たなコンクリート製の盛土補強壁を構築する。
<6> Construction of embankment reinforcement walls. (Fig. 6)
Formwork is installed on the outer periphery of the existing embankment retaining wall, reinforcing bars are placed at intervals, and concrete is placed to construct a embankment reinforcement wall.
The embankment reinforcing wall and the bar-shaped reinforcing
In this way, a new concrete embankment reinforcement wall integrated with the rod-shaped
<7>橋台と背面盛土の一体化。
上記したように橋台1は側面の、あと施工アンカーを介して側面補強ブロック6と一体化しており、側面補強ブロック6は背面盛土3内に打設した棒状補強材4と一体化している。
したがって橋台1は、側面補強ブロック6を介して背面盛土3と一体化していることになる。
さらに背面盛土3の裾部分は、既設盛土擁壁の外側に新たに構築する盛土補強壁で包囲し、この盛土補強壁は背面盛土3内に打設した棒状補強材4と一体化しているから、背面盛土3も全体として一体化して安定した形態を確保することができる。
<7> Integration of abutment and back embankment.
As described above, the abutment 1 is integrated with the
Accordingly, the abutment 1 is integrated with the back embankment 3 via the
Furthermore, the bottom portion of the back embankment 3 is surrounded by a newly constructed embankment reinforcement wall on the outside of the existing embankment retaining wall, and this embankment reinforcement wall is integrated with the bar-shaped
1:橋台
2:橋桁
3:背面盛土
4:棒状補強材
5:新設掘削面
6:側面補強ブロック
1: Abutment 2: Bridge girder 3: Back embankment 4: Bar-shaped reinforcement 5: New excavation surface 6: Side reinforcement block
Claims (1)
橋台の両側面に沿って橋桁の軸方向と平行方向に掘削し、
掘削して形成した橋桁の軸方向と直交する方向の新設掘削面に、橋桁の軸方向と平行に棒状補強材を打設し、
この棒状補強材に反力を取れる状態で、橋台の両側面に側面補強ブロックを打設し、
橋台から突設した、あと施工アンカーを介して、側面補強ブロックと橋台を一体化し、
さらに背面盛土の周囲を囲む石積などの既設盛土擁壁にも、その表面から棒状補強材を打設し、
この棒状補強材に反力を取れる状態で、既設盛土擁壁の外側に、盛土補強壁を構築して構成する、
橋台と背面盛土の補強方法。 The back embankment on the side of the abutment that has the back embankment on the back and supports the bridge girder,
Drilling along the sides of the abutment in parallel with the axial direction of the bridge girder,
On the new excavation surface in a direction perpendicular to the axial direction of the bridge girder formed by excavation, a rod-shaped reinforcing material is placed in parallel with the axial direction of the bridge girder,
Side reinforcement blocks are placed on both sides of the abutment in a state where reaction force can be applied to this bar-shaped reinforcement.
The side reinforcement block and the abutment are integrated through a post-construction anchor projecting from the abutment,
Furthermore, rod-shaped reinforcing materials are placed on the existing embankment retaining walls such as masonry surrounding the back embankment from the surface,
In a state where reaction force can be taken on this bar-shaped reinforcing material, on the outside of the existing embankment retaining wall, a embankment reinforcing wall is constructed and configured.
Reinforcement method of abutment and back embankment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010124372A JP5584520B2 (en) | 2010-05-31 | 2010-05-31 | Reinforcement method of abutment and back embankment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010124372A JP5584520B2 (en) | 2010-05-31 | 2010-05-31 | Reinforcement method of abutment and back embankment |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2011247059A true JP2011247059A (en) | 2011-12-08 |
JP5584520B2 JP5584520B2 (en) | 2014-09-03 |
Family
ID=45412651
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2010124372A Active JP5584520B2 (en) | 2010-05-31 | 2010-05-31 | Reinforcement method of abutment and back embankment |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5584520B2 (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102797259A (en) * | 2012-09-01 | 2012-11-28 | 中铁二院工程集团有限责任公司 | Block structure for earth filled in roadbeds at end parts of joints of roads and bridges in steep slope sections |
JP2015021306A (en) * | 2013-07-19 | 2015-02-02 | 藤林コンクリート工業株式会社 | Repair or reinforcement method of retaining wall |
JP2015232241A (en) * | 2014-06-10 | 2015-12-24 | 前田工繊株式会社 | Structure of back fill for existing structure |
JP2017020176A (en) * | 2015-07-07 | 2017-01-26 | 公益財団法人鉄道総合技術研究所 | Abutment reinforcement structure and reinforcing method |
JP2018178401A (en) * | 2017-04-05 | 2018-11-15 | 公益財団法人鉄道総合技術研究所 | Structure and method for reinforcing abutment |
CN113073537A (en) * | 2021-04-25 | 2021-07-06 | 王拴保 | Bridge approach structure of highway engineering and construction method thereof |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005226222A (en) * | 2004-02-10 | 2005-08-25 | Tenox Corp | Reinforced existing retaining wall structure, and reinforcing construction method for existing retaining wall |
JP2009256938A (en) * | 2008-04-15 | 2009-11-05 | Railway Technical Res Inst | Rebuilding method for existing bridge |
JP2011012492A (en) * | 2009-07-03 | 2011-01-20 | Tokyu Construction Co Ltd | Method for reinforcing abutment and bridge girder |
-
2010
- 2010-05-31 JP JP2010124372A patent/JP5584520B2/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005226222A (en) * | 2004-02-10 | 2005-08-25 | Tenox Corp | Reinforced existing retaining wall structure, and reinforcing construction method for existing retaining wall |
JP2009256938A (en) * | 2008-04-15 | 2009-11-05 | Railway Technical Res Inst | Rebuilding method for existing bridge |
JP2011012492A (en) * | 2009-07-03 | 2011-01-20 | Tokyu Construction Co Ltd | Method for reinforcing abutment and bridge girder |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102797259A (en) * | 2012-09-01 | 2012-11-28 | 中铁二院工程集团有限责任公司 | Block structure for earth filled in roadbeds at end parts of joints of roads and bridges in steep slope sections |
JP2015021306A (en) * | 2013-07-19 | 2015-02-02 | 藤林コンクリート工業株式会社 | Repair or reinforcement method of retaining wall |
JP2015232241A (en) * | 2014-06-10 | 2015-12-24 | 前田工繊株式会社 | Structure of back fill for existing structure |
JP2017020176A (en) * | 2015-07-07 | 2017-01-26 | 公益財団法人鉄道総合技術研究所 | Abutment reinforcement structure and reinforcing method |
JP2018178401A (en) * | 2017-04-05 | 2018-11-15 | 公益財団法人鉄道総合技術研究所 | Structure and method for reinforcing abutment |
CN113073537A (en) * | 2021-04-25 | 2021-07-06 | 王拴保 | Bridge approach structure of highway engineering and construction method thereof |
CN113073537B (en) * | 2021-04-25 | 2022-03-01 | 王拴保 | Bridge approach structure of highway engineering and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JP5584520B2 (en) | 2014-09-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5584520B2 (en) | Reinforcement method of abutment and back embankment | |
KR101258807B1 (en) | Tunnel installation method and tunnel installation structure of crossing railroad | |
CN110847041A (en) | Temporary anchoring structure and anchoring method for segmental prefabricated assembled concrete box girder | |
JP2004092078A (en) | Structure and construction method for bridge | |
CN105113434A (en) | Framing demounting supporting structure of spandrelless arch bridge of over crossing operation highway and construction method | |
KR100510092B1 (en) | A one-piece type arch-shaped structure with the precast concrete pannel and the steel frame under the earth, and method for manufacturing it | |
JP2004285738A (en) | Box girder bridge structure and method of constructing the same | |
JP5265471B2 (en) | Abutment and bridge girder reinforcement method | |
JP2021042610A (en) | Culvert structure and construction method therefor | |
CN110552706A (en) | Permanent-temporary combined shield hoisting hole sealing structure and method | |
JP2006214269A (en) | Erected girder | |
JP3893056B2 (en) | Construction method of underground structure | |
KR100784201B1 (en) | Method for construction of tunnel | |
JP5265470B2 (en) | Abutment and bridge girder reinforcement method | |
JP5457942B2 (en) | Reinforcement method of abutment and back embankment | |
JP6838808B2 (en) | Reinforcement structure and method of abutment | |
KR100987948B1 (en) | Construction method for underground structure using prestressed beam and development structure, saddle used in the same | |
JP4162291B2 (en) | Railway work girder cradle and rail work girder cradle construction method | |
JP2011247064A (en) | Reinforcement method for bridge abutment and back fill | |
JP2004092075A (en) | Structure and construction method for cut-and-cover tunnel | |
KR20190072213A (en) | Method Of Ground Half-Openning For Tunnel Excavation | |
JP2006112086A (en) | Structure of bridge and method for rebuilding bridge | |
CN211900603U (en) | Face combination shield structure hole of hoist enclosed construction forever | |
JP2017020176A (en) | Abutment reinforcement structure and reinforcing method | |
JP4047660B2 (en) | Elevated traffic road foundation structure and elevated traffic road |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20130517 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20131224 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20140708 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20140718 |
|
R150 | Certificate of patent or registration of utility model |
Ref document number: 5584520 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |