JP2011247064A - Reinforcement method for bridge abutment and back fill - Google Patents
Reinforcement method for bridge abutment and back fill Download PDFInfo
- Publication number
- JP2011247064A JP2011247064A JP2010124438A JP2010124438A JP2011247064A JP 2011247064 A JP2011247064 A JP 2011247064A JP 2010124438 A JP2010124438 A JP 2010124438A JP 2010124438 A JP2010124438 A JP 2010124438A JP 2011247064 A JP2011247064 A JP 2011247064A
- Authority
- JP
- Japan
- Prior art keywords
- abutment
- embankment
- rod
- back embankment
- bridge girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
本発明は、橋台と背面盛土の補強方法に関するものである。
さらに具体的には、背面を背面盛土構造として構築してある、鉄道橋台、道路橋台を背面盛土とともに補強する方法に関するものである。
The present invention relates to a method for reinforcing an abutment and a backfill.
More specifically, the present invention relates to a method of reinforcing a railway abutment and a road abutment together with a back embankment, the back of which is constructed as a back embankment structure.
背面部を背面盛土構造とする鉄道橋台、道路橋台が多数存在する。
これらの橋台の中には現在の設計基準でみると耐震性について問題のある構造物も存在する。
そうでなくとも、橋台、橋桁の老朽化によって安全性が低下している可能性も考えられる。
そのような橋台、橋桁を補強する工法としては、従来から次のような工法が採用されている。
<1> 鉄道や道路の供用を確保するために仮線を、補修対象の橋台とは別に構築し、老朽化した橋台、橋桁を撤去して新たに構造物を構築する方法。
<2> 仮線を別途構築し、老朽化した橋台を補強する方法。
<3> 橋台に鋼板の巻き立てや増壁の新設を行って橋台補修する方法。
<4> 橋台の背面の沈下を抑制するために、図7に示すように支持地盤d上の橋台aと、背面の盛土bとの間にアプローチブロックcを設置する方法。
There are many railway abutments and road abutments with back embankment on the back.
Among these abutments, there are also structures that have problems with seismic resistance according to the current design standards.
Even if this is not the case, it is possible that the safety of the abutment and the bridge girder has deteriorated.
As a method for reinforcing such abutments and bridge girders, the following methods have been conventionally employed.
<1> A method of constructing a new structure by constructing a temporary line separately from the abutment to be repaired and removing the aged abutment and bridge girder in order to secure the use of railways and roads.
<2> A method of reinforcing aged abutments by constructing a temporary line separately.
<3> A method of repairing the abutment by winding a steel plate or installing a new wall on the abutment.
<4> A method of installing an approach block c between the abutment a on the support ground d and the backfill b as shown in FIG.
前記した従来の橋台と背面盛土の補強方法にあっては、次のような問題点がある。
<1> いずれの工法でも鉄道や車両の交通が不可能となってしまう時期が発生して周囲の経済活動に影響を与える。
<2> 仮線を構築するだけで大規模な工事となり、余分な膨大な費用が発生する。
<3> 鉄道の場合には夜間に使用しない状態が生じるが、その時間を利用して補強工事を行う場合にも、工事を短時間に分割して進めなければならず、不経済なものである。
<4> 地震時の振動で橋台が背面の背面盛土から瞬間的に離れると、その間隙に背面盛土が押し出し、橋台は元の姿勢に戻れない場合がある。この現象が繰り返すことで、橋台背面の背面盛土が1メートル近くも沈下した例が報告されている。
<5> したがって橋台だけを補強しても、背面盛土が大きく沈下したケースのように、橋台と背面盛土との一体化がなければ大きな事故につながる可能性がある。
<6> 新設の橋台であれば、図7に示すようにはじめからアプローチブロックcを設置できるが、それでも背面の盛土bの沈下は避けられず、沈下が生じると鉄道の軌道ではバラストの補給を、道路では再舗装を行っている。
The above-described conventional abutment and back embankment reinforcement methods have the following problems.
<1> Regardless of the method of construction, there will be times when rail and vehicle traffic will be impossible, affecting the surrounding economic activities.
<2> Construction of a temporary line is a large-scale construction, resulting in an extra huge cost.
<3> In the case of railroads, there is a situation where it is not used at night, but even when reinforcement work is performed using that time, the work must be divided into short periods of time, which is uneconomical. is there.
<4> If the abutment is momentarily separated from the back embankment due to vibration during an earthquake, the back embankment may be pushed out into the gap and the abutment may not return to its original position. It has been reported that when this phenomenon is repeated, the back embankment on the back of the abutment has subsided nearly 1 meter.
<5> Therefore, even if only the abutment is reinforced, there is a possibility that it will lead to a major accident if the abutment and the back embankment are not integrated, as in the case where the back embankment sinks greatly.
<6> If it is a new abutment, the approach block c can be installed from the beginning as shown in FIG. 7, but the settlement of the embankment b on the back is still unavoidable. The road is re-paved.
上記のような課題を解決するために本発明の橋台と背面盛土の補強方法は、背面に背面盛土を有し、橋桁を支持する橋台において、背面盛土に向けて、橋台の前面から橋桁の軸方向とほぼ平行に棒状補強材を打設して行う、橋台と背面盛土の補強方法を特徴としたものである。
さらに本発明は、前記の橋台において、橋台の背面盛土に向けて、盛土の法面から、橋桁の軸方向と直交する方向に、棒状補強材を打設して行う橋台と背面盛土の補強方法を特徴としたものである。
さらに本発明は、前記の橋台において、橋台の背面盛土に向けて、橋台の前面から橋桁の軸方向とほぼ平行に棒状補強材を打設し、さらに橋台の背面盛土に向けて、背面盛土の法面から橋桁の軸方向と直交する方向に、棒状補強材を打設して行う橋台と背面盛土の補強方法を特徴としたものである。
In order to solve the problems as described above, the abutment and back embankment reinforcement method of the present invention has a back embankment on the back and supports the bridge girder. It is characterized by a method of reinforcing an abutment and a back embankment, which is performed by placing a rod-shaped reinforcing material substantially parallel to the direction.
Further, the present invention provides a method for reinforcing an abutment and a back embankment in the above-mentioned abutment by placing a rod-shaped reinforcing material in a direction orthogonal to the axial direction of the bridge girder from the slope of the embankment toward the back embankment of the abutment. It is characterized by.
Furthermore, in the abutment described above, the present invention provides the above-mentioned abutment with a rod-shaped reinforcing material placed almost in parallel with the axial direction of the bridge girder from the front of the abutment toward the back embankment, and further toward the back embankment of the abutment. It is characterized by a method of reinforcing the abutment and back embankment by placing a rod-shaped reinforcing material in a direction perpendicular to the axial direction of the bridge girder from the slope.
本発明の橋台と背面盛土の補強方法は以上説明したようになるから次のような効果のいずれかを得ることができる。
<1> 鉄道や道路の通行を確保したまま、仮線を設置することなく橋台と背面盛土を補強することができるから、仮線を設置したり、橋台を解体して新設するような工法と比較してきわめて経済的である。
<2> 背面盛土内に打設した棒状補強材を介して、背面盛土と橋台とが一体化しているので、地震時にも橋台の背面盛土が一体化して挙動し、背面盛土の沈下が発生しにくい。
Since the abutment and back embankment reinforcement method of the present invention is as described above, one of the following effects can be obtained.
<1> While securing rail and road traffic, the abutment and backfill can be reinforced without installing temporary lines. It is extremely economical in comparison.
<2> Since the back embankment and the abutment are integrated via a bar-shaped reinforcement placed in the back embankment, the back embankment of the abutment behaves in an integrated manner even during an earthquake, causing subsidence of the back embankment. Hateful.
以下図面を参照にしながら本発明の好適な実施の形態を詳細に説明する。 DESCRIPTION OF EMBODIMENTS Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings.
<1>前提条件。(図1)
前記したように、本発明の補強方法の対象は、背面に背面盛土3を有する橋台1と背面盛土3の補強方法である。
橋台1はコンクリート製であり、道路などを挟んで対面する2基の橋台1の上に、道路、鉄道などの橋桁2をかけ渡してある。
橋台1の両側には背面には背面盛土3が存在し、背面盛土3は法面を備え、その裾部分は石積やコンクリート製の既設盛土擁壁4で包囲してある。
なお本明細書では説明の便宜上から、平面視がほぼ矩形の橋台1について、背面盛土3側を「背面」、通路側を「前面」、橋桁2に平行の両側の面を「側面」と称することにする。
<1> Precondition. (Figure 1)
As described above, the object of the reinforcing method of the present invention is a method for reinforcing the abutment 1 having the
The abutment 1 is made of concrete, and
On both sides of the abutment 1, there is a
In the present specification, for the convenience of explanation, regarding the abutment 1 having a substantially rectangular plan view, the
<2>棒状補強材の打設。(図2)
橋台1の前面から、その支承部11より下の位置において、背面盛土3に向けて複数本の棒状補強材5を打設する。
棒状補強材5の打設方向は、橋桁2の軸方向とほぼ平行であり、橋台1の背面の盛土3内に平行に複数本を打設し、その前面側の端部を橋台1と一体化する。
この棒状補強材4として、たとえば特許第2575329号に記載されたような公知の工法を採用することができる。
この特許工法は、中空回転軸の周囲に掘削翼と攪拌翼とを設けた掘削攪拌ロッドを使用する工法である。
そしてこの掘削攪拌ロッドによって地中に筒状の攪拌土とセメントミルクとの混合体を形成する。
この混合体の中心にはセメントミルクよりなる中央補強体を位置させる。
この中央補強柱の中央には、尾端を孔外に露出させた芯材を位置させてこの芯材を引張り補強体とするものである。
しかしこの工法は一例であり、その他の各種の公知の棒状補強材5を採用することができる。
棒状補強材5の橋台1側の端は、橋台1の前面に露出する。
そこで棒状補強材5の露出端を、コンクリートブロックで包囲して、頭部ブロック6として形成することもできる。
この頭部ブロック6は、橋台1の前面に形成されるから、橋台1と棒状補強材5との一体化がさらに確実となる。
<2> Placing a rod-shaped reinforcing material. (Figure 2)
A plurality of bar-shaped reinforcing
The direction in which the rod-shaped reinforcing
As this rod-shaped reinforcing
This patent method is a method using an excavation stirring rod provided with an excavation blade and a stirring blade around a hollow rotating shaft.
The excavation stirring rod forms a mixture of cylindrical stirring soil and cement milk in the ground.
A central reinforcing body made of cement milk is located at the center of the mixture.
In the center of the central reinforcing column, a core material with the tail end exposed outside the hole is positioned, and this core material is used as a tension reinforcing body.
However, this construction method is an example, and various other known bar-shaped reinforcing
The end of the rod-shaped reinforcing
Therefore, the exposed end of the rod-shaped reinforcing
Since the
<3>橋台と背面盛土の一体化。
上記したように、橋台1と背面盛土3とは、棒状補強材5を介して強固に連結している。
そのために、橋台1だけの補強とは異なり橋台1と背面盛土3は一体化しているから、地震時にも橋台1は背面盛土3と一体となって挙動する。
そのために従来のように橋台1と背面盛土3の縁が切れて、背面盛土3が大きく沈下する、といった現象を生じることがなく、安定した構造を提供することができる。
<3> Integration of abutment and backfill.
As described above, the abutment 1 and the
Therefore, unlike the reinforcement of only the abutment 1, the abutment 1 and the
Therefore, a stable structure can be provided without causing the phenomenon that the edge of the abutment 1 and the
<4>他の実施例1。(図6)
上記の実施例では棒状補強材5を橋桁2の方向と平行に打設した。
しかし橋台1の背面盛土3に向けて、盛土3の法面から、橋桁2の軸方向と直交する方向に、棒状補強材5を打設することもできる。
この方法によっても、橋台1と背面盛土3を、棒状補強材を介して一体化して補強することができる。
<4> Other Embodiment 1. (Fig. 6)
In the above embodiment, the rod-shaped reinforcing
However, the rod-shaped reinforcing
Also by this method, the abutment 1 and the
<5>他の実施例2。
前記のような、橋台1の背面盛土3に向けて、橋台1の前面から橋桁2の軸方向とほぼ平行に棒状補強材5を打設する方法と、橋台1の背面盛土3に向けて、背面盛土3の法面から橋桁2の軸方向と直交する方向に棒状補強材5を打設して行う方法とを組み合わせて橋台1と背面盛土3を補強することもできる。
<5>
For the back embankment 1 of the abutment 1 as described above, the method of placing the rod-shaped reinforcing
1:橋台
2:橋桁
3:盛土
4:既設擁壁
5:棒状補強材
6:頭部ブロック
1: Abutment 2: Bridge girder 3: Embankment 4: Existing retaining wall 5: Bar-shaped reinforcement 6: Head block
Claims (3)
背面盛土に向けて、橋台の前面から橋桁の軸方向とほぼ平行に棒状補強材を打設して行う、
橋台と背面盛土の補強方法。
In the abutment that has the back embankment on the back and supports the bridge girder,
For the back embankment, a rod-shaped reinforcing material is placed from the front of the abutment almost parallel to the axial direction of the bridge girder.
Reinforcement method of abutment and back embankment.
橋台の背面盛土に向けて、
盛土の法面から、橋桁の軸方向と直交する方向に、棒状補強材を打設して行う、
請求項1記載の橋台と背面盛土の補強方法。
In the abutment,
For the back embankment of the abutment,
From the slope of the embankment, in the direction orthogonal to the axial direction of the bridge girder, perform by placing a rod-shaped reinforcing material,
The abutment and back embankment reinforcing method according to claim 1.
橋台の背面盛土に向けて、橋台の前面から橋桁の軸方向とほぼ平行に棒状補強材を打設し、
さらに橋台の背面盛土に向けて、背面盛土の法面から橋桁の軸方向と直交する方向に、棒状補強材を打設して行う、
請求項1記載の橋台と背面盛土の補強方法。 In the abutment,
For the back embankment of the abutment, a bar-shaped reinforcing material is placed from the front of the abutment almost parallel to the axial direction of the bridge girder,
Furthermore, toward the back embankment of the abutment, a rod-shaped reinforcing material is placed in the direction perpendicular to the axial direction of the bridge girder from the slope of the back embankment.
The abutment and back embankment reinforcing method according to claim 1.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010124438A JP2011247064A (en) | 2010-05-31 | 2010-05-31 | Reinforcement method for bridge abutment and back fill |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010124438A JP2011247064A (en) | 2010-05-31 | 2010-05-31 | Reinforcement method for bridge abutment and back fill |
Publications (1)
Publication Number | Publication Date |
---|---|
JP2011247064A true JP2011247064A (en) | 2011-12-08 |
Family
ID=45412656
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2010124438A Pending JP2011247064A (en) | 2010-05-31 | 2010-05-31 | Reinforcement method for bridge abutment and back fill |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2011247064A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018178401A (en) * | 2017-04-05 | 2018-11-15 | 公益財団法人鉄道総合技術研究所 | Structure and method for reinforcing abutment |
CN111535161A (en) * | 2020-05-22 | 2020-08-14 | 中铁二院工程集团有限责任公司 | Slope terrain pier deformation repairing structure and method |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2575329B2 (en) * | 1992-02-10 | 1997-01-22 | 財団法人鉄道総合技術研究所 | Tensile reinforcement |
JP2010053644A (en) * | 2008-08-29 | 2010-03-11 | Railway Technical Res Inst | Abutment and method for reinforcing fill provided on backside of the same |
-
2010
- 2010-05-31 JP JP2010124438A patent/JP2011247064A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2575329B2 (en) * | 1992-02-10 | 1997-01-22 | 財団法人鉄道総合技術研究所 | Tensile reinforcement |
JP2010053644A (en) * | 2008-08-29 | 2010-03-11 | Railway Technical Res Inst | Abutment and method for reinforcing fill provided on backside of the same |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2018178401A (en) * | 2017-04-05 | 2018-11-15 | 公益財団法人鉄道総合技術研究所 | Structure and method for reinforcing abutment |
CN111535161A (en) * | 2020-05-22 | 2020-08-14 | 中铁二院工程集团有限责任公司 | Slope terrain pier deformation repairing structure and method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5266291B2 (en) | Construction method of bridge deck and joint structure of precast deck | |
JP6316665B2 (en) | Composite structure of steel girder and precast slab and its construction method | |
JP5584520B2 (en) | Reinforcement method of abutment and back embankment | |
JP6375195B2 (en) | Widened PC slab structure and widening method of existing PC slab | |
JP6180376B2 (en) | Main girder provision method in composite girder floor slab replacement method, composite girder floor slab replacement method, and main girder provision structure in composite girder floor slab replacement method | |
JP5718133B2 (en) | Precast floor slab and its joint structure | |
JP2008196162A (en) | Bridge fall prevention structure | |
CN102943431B (en) | Cast-in-place reinforced concrete plate and fabricated reinforced concrete plate splicing bridge and method | |
JP6046479B2 (en) | Articulated track block and construction method for connecting track block supporting girder | |
JP2007327255A (en) | Fatigue-resistant steel floor slab | |
JP5265471B2 (en) | Abutment and bridge girder reinforcement method | |
JP2006214269A (en) | Erected girder | |
JP2011247064A (en) | Reinforcement method for bridge abutment and back fill | |
JP6182402B2 (en) | Seismic reinforcement method for bridges to prevent falling bridges | |
JP2005016106A (en) | Method for preventing settlement of viaduct | |
JP6838808B2 (en) | Reinforcement structure and method of abutment | |
JP5265470B2 (en) | Abutment and bridge girder reinforcement method | |
JP5457942B2 (en) | Reinforcement method of abutment and back embankment | |
JP5043879B2 (en) | How to install width expansion materials for road bridges | |
JP2021042610A (en) | Culvert structure and construction method therefor | |
KR100987948B1 (en) | Construction method for underground structure using prestressed beam and development structure, saddle used in the same | |
JP6969909B2 (en) | How to reinforce steel synthetic girders | |
JP2021031864A (en) | Slab reinforcement method of side fastening pc bridge | |
JP6673132B2 (en) | Paved steel slab unit and slab structure | |
JP2006112086A (en) | Structure of bridge and method for rebuilding bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20130517 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20131224 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20140107 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20140220 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20140325 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20140514 |
|
A02 | Decision of refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A02 Effective date: 20140603 |