JP2011241608A - Construction method of basement in existing house - Google Patents

Construction method of basement in existing house Download PDF

Info

Publication number
JP2011241608A
JP2011241608A JP2010114920A JP2010114920A JP2011241608A JP 2011241608 A JP2011241608 A JP 2011241608A JP 2010114920 A JP2010114920 A JP 2010114920A JP 2010114920 A JP2010114920 A JP 2010114920A JP 2011241608 A JP2011241608 A JP 2011241608A
Authority
JP
Japan
Prior art keywords
basement
caisson
existing
existing house
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2010114920A
Other languages
Japanese (ja)
Inventor
Keiichi Kato
圭一 加藤
Hiroshi Saito
浩 斉藤
Toshiyuki Hoshino
利幸 星野
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to JP2010114920A priority Critical patent/JP2011241608A/en
Publication of JP2011241608A publication Critical patent/JP2011241608A/en
Pending legal-status Critical Current

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide a method for constructing a basement in an existing house inexpensively and efficiently.SOLUTION: Excavating means and surplus soil discharge means are provided in an existing house, existing base concrete is chipped and removed, a skeleton caisson with a leading blade is formed inside the existing house, and the undersurface inside the skeleton caisson is excavated so that the skeleton caisson with a leading blade is made to sink by its own weight to a predetermined place. A basement is constructed by leveling the bottom surface of the place after the caisson has sunk and forming a pressure-proof board concrete and bars in the upper part of the basement.

Description

本発明は、既存住宅内で構築される地下室を構築する方法に関し、さらにはケーソン(周壁)を、地下室用ケーソン(周壁)で囲まれた地面を掘削して地下に自重で沈設させる際の地下室自重沈下ケーソンの工法に関する。 The present invention relates to a method for constructing a basement constructed in an existing house, and further, a caisson (circumferential wall) is excavated from the ground surrounded by the basement caisson (peripheral wall) and is submerged under its own weight in the basement. It relates to the construction method of self-weight subsidence caisson.

従来より地下室,地下貯水槽などからなる地下構造物を地下に構築する施工に、いわゆる潜函工法といわれる工法がある。潜函工法は、地上で構築した地下構造物用ケーソン(周壁)を地下に沈設する工法であり、水中に地下構造物を沈めて行なう工法と、地下構造物用ケーソン(周壁)で囲まれた内側の地面を掘削しながら地下構造物用ケーソン(周壁)をその自重によって徐々に地下までに沈下させて行なう方法とがある。後者の方法においては、下部に先行刃が設けられたケーソン躯体構造(内側に底を有していない周枠形状)のオープン型によって行なわれる。 Conventionally, there is a so-called submersible construction method for constructing an underground structure consisting of a basement, an underground water tank, etc. in the basement. The submersible construction method is a method in which the caisson (surrounding wall) for underground structures built on the ground is submerged in the underground. The construction method involves submerging the underground structure in water and the inside surrounded by the caisson for the underground structure (surrounding wall). There is a method in which the caisson (surrounding wall) for underground structures is gradually submerged to the underground by its own weight while excavating the ground. The latter method is performed by an open type of caisson housing structure (peripheral frame shape having no bottom on the inside) in which a leading blade is provided at the lower part.

多くのオープン型のケーソンは、地下構造物用ケーソン(周壁)が設けられその後、ケーソンを地下に沈設させる、いわゆる潜函工法が行なわれる。このため、地下構造物の基盤は、地下構造物用ケーソン(周壁)を地下に沈設させた後に、施工される。オープン型のケーソンを潜函工法によって地下に沈設させる施工では、こういったケーソンの製作が地上で行なわれるため、地下で地下構造物そのものを構築する場合と比較して、土壌壁面の崩壊が無く、作業の負担が大幅に軽減され、期間が短縮され、コストが抑えられるなど、様々な利点がある。 Many open-type caissons are provided with a caisson (surrounding wall) for an underground structure, and then a so-called submersible construction method in which the caisson is sunk underground. For this reason, the basement of an underground structure is constructed after the caisson (surrounding wall) for underground structures is sunk in the basement. In the construction where an open caisson is submerged by the submerged method, the caisson is produced on the ground. There are various advantages such as the burden of work is greatly reduced, the period is shortened, and the cost is reduced.

例えば特許文献1では「この発明にかかる地下構造物の構築方法は、地盤面でコンクリート型枠にコンクリートを打設してコンクリート周壁を構築したあと、コンクリート周壁からコンクリート型枠を撤去した状態で、コンクリート周壁の内側空間における地盤の掘削を行ってコンクリート周壁を沈下させる。コンクリート型枠が存在しない状態のコンクリート周壁を沈下させるので、コンクリート周壁の取り扱いが容易である。」と書かれている。
特開2001−323435
For example, in Patent Document 1, “The construction method of an underground structure according to the present invention is to place concrete on a concrete formwork on the ground surface to construct a concrete peripheral wall, and then remove the concrete formwork from the concrete peripheral wall. The excavation of the ground in the inner space of the concrete peripheral wall causes the concrete peripheral wall to sink, and the concrete peripheral wall without the concrete formwork sinks, so that the concrete peripheral wall is easy to handle. "
JP 2001-323435 A

しかしながら特許文献1の方法は狭い土地面積等では有効であるがあくまで外での施工法である。本発明は従来難しかった既にある既存住宅内での地下室を安価にかつ容易に構築すると時の問題を解消し既存住宅内に地下室を安価でかつ容易に構築する方法を提供することである。 However, although the method of patent document 1 is effective in a small land area etc., it is a construction method outside. An object of the present invention is to provide a method for easily and inexpensively constructing a basement in an existing house by solving a problem when constructing a basement in an existing house that has been difficult in the past at low cost and easily.

本発明者らは上記の課題を解決するため鋭意研究を行い次のような手法をとった。すなわち既存住宅内に地下室を作る際既存住宅内に地下室の外周壁躯体を構成するケーソンを配置しこのケーソンの内側下部を掘削してケーソンを自重で所定の設置深さまで沈下させて地下室を構築する工法を取る場合に以下の3つの工程から行う。
第1工程は
A)小型掘削機または掘削道具の既存住宅内の地下室構築場所への搬入、すなわち既存住宅内で地面を掘削するためのミニユンボなどの小型掘削機またはスコップ、つるはし等の掘削道具を搬入する。
B)既存ベースコンクリートのはつり撤去、既存住宅内の既存ベースコンクリートのはつり撤去を行う。
C)先行刃設置、鋼製フレーム、型枠組み立てコンクリートミルク充填、すなわち自重沈下式ケーソンを構成するための準備で先行刃を設置し、鋼製フレーム、型枠組み立ててコンクリートミルクを充填し先行刃付きケーソン壁形成の準備を行う。
In order to solve the above-mentioned problems, the present inventors have conducted intensive research and adopted the following method. In other words, when creating a basement in an existing house, a caisson that constitutes the outer wall of the basement is placed in the existing house, and the caisson is submerged to a predetermined installation depth by its own weight to construct the basement. When taking a construction method, it is performed from the following three steps.
The first step is A) Carrying a small excavator or excavator into the basement construction site in the existing house, that is, a mini excavator such as a mini-yumbo or excavator such as a scoop or a pickaxe for excavating the ground in the existing house Carry in.
B) Remove existing base concrete and remove existing base concrete in existing houses.
C) Leading blade installation, steel frame, formwork assembled concrete milk filling, that is, setting the leading blade in preparation for constructing self-weight sinking caisson, steel frame, mold assembling, filling concrete milk and leading blade Prepare for caisson wall formation.

第2工程は
D)先行刃付きケーソン壁形成、すなわち第1工程D)で準備した先行刃付きケーソン壁形成する。
E)排残土手段設置、ケーソン壁内部から下部を掘削する際の残土を排出する手段を設ける。
F)掘削にてケーソン所定位置まで自重沈下、すなわち掘削機または掘削道具で掘削することにより先行刃を介してケーソンが自重沈下していくがこの沈下を所定の位置まで行う
G)底面整地、所定位置までケーソンが沈下した時底地の整地を行う
H)小型掘削機または掘削道具搬出、ケーゾン自重沈下させるために掘削してきた小型掘削機または掘削道具搬出を行う。
第3工程は
I)底面コンクリート施工、所定の位置までケーソンを自重沈下させた後底地にコンクリート施工を行う。C)の既存ベースコンクリートのはつり撤去の際に既存の鉄筋を鉄筋の径の40倍以上残した鉄筋を利用し地下室壁上部梁形成、第1工程C)で既存ベースコンクリートのはつり撤去の際に残した既存の鉄筋を鉄筋の径の40倍以上残した鉄筋を利用し地下室壁上部梁を形成する
The second step D) forms a caisson wall with a leading blade, that is, a caisson wall with a leading blade prepared in the first step D).
E) Installation of means for discharging residual soil and means for discharging residual soil when excavating the lower part from the inside of the caisson wall.
F) The caisson sinks to a predetermined position by excavation, that is, the caisson sinks through the leading blade by excavating with an excavator or a drilling tool. This subsidence is performed to a predetermined position. G) Bottom leveling, predetermined When the caisson sinks to the position, the land is leveled. H) Carry out the small excavator or excavator and carry out the excavator or excavator that has been excavated to sink the caisson.
In the third step, I) bottom concrete construction, the caisson is submerged to a predetermined position, and then concrete construction is performed on the bottom. C) When removing the existing base concrete, use the rebar that left over 40 times the diameter of the reinforcing bar to form the upper basement wall beam. In the first step C), remove the existing base concrete. Form the basement wall upper beam by using the rebar that left over 40 times the diameter of the rebar.

第3工程において必要に応じて鉄筋コンクリート地下室壁上部梁を形成する。この際第1工程のB)の既存ベースコンクリートのはつり撤去の際、既存の鉄筋を鉄筋径の40倍以上残し前述の鉄筋コンクリート地下室壁上部梁形成の際この既存の鉄筋径の40倍以上残した鉄筋を利用することにより既存住宅のベース部と強力に接合された地下室上部梁となる。 In the third step, a reinforced concrete basement wall upper beam is formed as necessary. At this time, at the time of removing the existing base concrete in the first step B), the existing rebar is left over 40 times the diameter of the rebar, and when the above-mentioned reinforced concrete basement wall upper beam is formed, it is left over 40 times the existing rebar diameter. By using reinforcing bars, it becomes a basement upper beam that is strongly joined to the base of the existing house.

現場の状態によって必要に応じての第1工程C)の既存ベースコンクリートはつり撤去後地面を地下室面積より40%から150%の範囲の面積で先行堀を行えばよい。地下室面積の150%以上だと既設の基礎の撤去が大変であり、40%以下であると掘削機の作業範囲が狭いので掘削作業に不都合が生じる。また先行堀をしない場合もあるが施工条件によって作業容易にするため先行堀が必要な場合もある。 The existing base concrete in the first step C) as necessary according to the state of the site may be preceded by excavating the ground with an area in the range of 40% to 150% of the basement area after removing the suspension. If it is 150% or more of the basement area, it is difficult to remove the existing foundation, and if it is 40% or less, the work range of the excavator is narrow, which causes inconvenience in excavation work. In some cases, a leading moat is not used, but a leading moat may be necessary to facilitate work depending on the construction conditions.

先行堀を行う場合の深さは300〜1000mmの範囲で現場の状況によって行えばよい。先行堀をしない場合もあるが施工条件によって作業容易にするため先行堀をすることがある。ここで崩れやすい地盤では300mm、崩れにくい地盤では1000mmが適当である。さらに先行堀は第1段階と第2段階に分かれており第1段階は第2段階より広く先行堀をおこなえばよく、第1段階の先行掘りの部分に先行刃等を設置すればよい。 What is necessary is just to perform the depth in the case of performing a preceding moat in the range of 300-1000 mm according to the condition of a field. There is a case where the leading moat is not used, but there is a case where the leading moat is made to facilitate work depending on the construction conditions. Here, 300 mm is appropriate for the ground that is easily collapsed, and 1000 mm is appropriate for the ground that is not easily collapsed. Furthermore, the preceding moat is divided into a first stage and a second stage, and the first stage may be performed broader than the second stage, and a leading blade or the like may be installed in the portion of the first stage.

ケーソン壁形成後該ケーソン壁外周部保護層形成すればよい。ここでの保護層は必要に応じて、防水層の吹き付け、あるいは貼り付け、あるいは発泡スチロール層であったりする。F)の排残土手段設置は必要に応じてベルトコンベアを設置すればよい。 What is necessary is just to form this caisson wall outer peripheral part protective layer after caisson wall formation. The protective layer here may be sprayed or pasted with a waterproof layer or a styrene foam layer as required. F) The residual soil means may be installed as necessary by installing a belt conveyor.

H)の底面整地は必要に応じてランマ等で底地転圧すればよい。特に地盤面の地耐力が弱い場合には栗石等を並べ転圧すればよい。H)の底面整地後に掘削した底面に必要に応じて外周部近傍も含めて捨てコンクリート打ちをすればよい。H)の底面整地後あるいは底面コンクリート打ち後に床面の防水加工処理を行えばよい。 The bottom leveling of H) may be crushed by a ramp or the like as necessary. In particular, if the ground surface is weak in ground strength, it is sufficient to arrange and roll chestnut stones. If necessary, the bottom surface excavated after the bottom surface preparation of H) may be disposed of, including the vicinity of the outer peripheral portion, if necessary. The floor surface may be waterproofed after the bottom surface preparation of H) or after the bottom surface concrete is cast.

第2工程において必要に応じて外周部骨材盛り上げ、ケーソンの外周部に骨材の盛り上げを行い、ケーソンが自重沈下していく際に先行刃際外周部が形成していく地面の壁面とケーソン外周部の間に骨材が流れ込み摩擦を減じるようする。 In the second step, the aggregate of the outer peripheral part is raised as necessary, the aggregate is raised on the outer peripheral part of the caisson, and the wall surface and caisson of the ground that the outer peripheral part of the leading edge forms when the caisson sinks under its own weight Aggregate flows between the outer peripheries to reduce friction.

第3工程I)底面にコンクリート施工は鉄筋コンクリート耐圧盤施工、すなわち底部に耐圧盤鉄筋コンクリート施工を行う。また既存住宅内地下室接地場所の床面が存在する場合には第1工程でこの床面を撤去する。 Third step I) Concrete construction on the bottom surface is reinforced concrete pressure board construction, that is, pressure board reinforced concrete construction is performed on the bottom. Also, if there is a floor surface in the basement grounding area in the existing house, this floor surface is removed in the first step.

本発明によれば既存住宅内に地下室を作る際既存住宅内に地下室の外周壁躯体を構成するケーソンを配置しこのケーソンの内側下部を掘削してケーソンを自重で所定の設置深さまで沈下させて地下室を構築する際に従来容易にできなかった既存住宅内に地下室を構築することが容易にかつ安価に可能となる。 According to the present invention, when a basement is created in an existing house, a caisson constituting the outer peripheral wall of the basement is placed in the existing house, and the caisson is submerged to a predetermined installation depth by its own weight by excavating the lower part inside the caisson. When building a basement, it becomes easy and inexpensive to build a basement in an existing house that could not be easily done before.

以下に本発明を実施するための最良の形態例について図に基づいて詳細に説明していく。 The best mode for carrying out the present invention will be described below in detail with reference to the drawings.

図1に既存住宅内に地下室を作る際のフローを示し、第2図は地下室構築のためのケーソン構築の準備の断面図、図3は既存住宅の1階部分と地下室構築用ケーソンを説明する図で、第5図は既存住宅の1階部分とケーソン工法で構築した地下室を示している。第1工程S11は床面がある場合に既存住宅内の地下室設置場所の床を撤去であり、図2の3で示した。S12はA)小型ユンボ等の掘削機あるいは掘削道具の既存住宅内地下室設置場所への搬入である。S13はB)既存ベースコンクリートのはつり撤去であり、図2の4で表しており、残っている既存ベースコンクリートは8である。ここで必要に応じて既存ベースコンクリートの中の鉄筋を鉄筋の径の40倍以上残しておくと後の地下室上部梁に強度の点で有利となるがその様子を図2の5で示した。S14はC)先行刃、鋼製フレーム、型枠を組み立ててコンクリートミルクを充填しケーソンの準備をする皇帝である。図2の1は先行刃を示している。 Fig. 1 shows the flow when creating a basement in an existing house, Fig. 2 is a cross-sectional view of preparation for caisson construction for basement construction, and Fig. 3 explains the first floor part of the existing house and basement construction caisson. In the figure, FIG. 5 shows the first floor of an existing house and the basement constructed by the caisson method. The first step S11 is to remove the floor of the basement installation place in the existing house when there is a floor, and is shown by 3 in FIG. S12 is A) carrying an excavator such as a small yumbo or a drilling tool into a basement installation location in an existing house. S13 is B) Lifting of the existing base concrete, which is represented by 4 in FIG. Here, if necessary, leaving the reinforcing bars in the existing base concrete at least 40 times the diameter of the reinforcing bars is advantageous in terms of strength for the upper basement beam later, as shown in FIG. S14 is an emperor who prepares a caisson by assembling a leading blade, a steel frame, and a formwork and filling concrete milk with S14. 2 in FIG. 2 indicates a leading blade.

ここで現場の状況によって先行堀をすることがあるが本実施例では2段階の先行堀りの場合を示している。図2の6が第1段階の先行堀りでありこの部分に1の先行刃を設置し鋼製フレーム、型枠を組み立てればよい。図2の7が第2段階の先行堀りでありこのそこの部分に搬入した小型ユンボ等の掘削機あるいは掘削道具を設置し掘削をしていけばよい。言うまでも無いが先行堀りも小型ユンボ等の掘削機あるいは掘削道具を用いればよい。 Here, a prior digging may be carried out depending on the situation at the site, but in this embodiment, a case of a two-stage digging is shown. 2 in FIG. 2 is the first stage leading excavation, and it is only necessary to assemble a steel frame and formwork by installing one leading blade in this portion. Reference numeral 7 in FIG. 2 is the second stage leading excavation, and it is only necessary to excavate by installing an excavating machine such as a small yumbo or an excavating tool carried there. Needless to say, an excavator such as a small Yumbo or an excavating tool may be used for the preceding excavation.

次に第2工程について説明するがS21はD)先行刃付ケーソン壁形成であり第1工程S14で準備したコンクリートミルクが固まりケーソン壁となっている。その様子を図3の10で示した。ここで必要に応じて防水などを目的としたケーソン壁外周保護層を設ければよいがその様子は図3の11に示した。S22はE)の排残土手段を設ければよい。小型ユンボ等の掘削機あるいは掘削道具を使って掘削するわけであるがここで残土が出る。これを外に排出する必要があるがベルトコンベアを設置して残土を排出してもよい。その様子を図4の12に示した。 Next, the second step will be described. S21 is D) formation of a caisson wall with a leading blade, and the concrete milk prepared in the first step S14 is solidified to form a caisson wall. This is indicated by 10 in FIG. Here, a caisson wall outer peripheral protective layer for the purpose of waterproofing or the like may be provided as necessary, and this state is shown in 11 of FIG. S22 may be provided with the waste soil removal means of E). The excavator or excavator such as a small Yumbo is used for excavation, but the remaining soil comes out here. Although it is necessary to discharge this outside, a belt conveyor may be installed to discharge the remaining soil. This is shown in FIG.

S23はF)掘削にて先行刃付ケーソンを所定位置まで沈下させる。その状態が図5である。S24はG)底地整地である。図5の15が底地であり必要に応じて栗石等を敷き詰めランマ等を使い転圧を行えばよい。その後図5の13の部分に捨てコンクリート施工を行い、同じく図5の14に示すようにエンビシートで防水処理すれば効果的である。S25はH)掘削が終了しているので小型ユンボ等の掘削機あるいは掘削道具は必要なくなったため搬出すればよい。 S23: F) The caisson with a leading blade is sunk to a predetermined position by excavation. This state is shown in FIG. S24 is G) Landslide leveling. Reference numeral 15 in FIG. 5 denotes the land, and rolling may be performed by spreading a chestnut or the like as needed and using a ramma or the like. After that, it is effective if a concrete construction is carried out at a portion 13 in FIG. 5 and waterproofed with an envi sheet as indicated by 14 in FIG. S25 is H) Since excavation has been completed, an excavator such as a small yumbo or an excavating tool is no longer necessary, and it may be carried out.

次に第3工程について説明するがS31はI)底面コンクリート施工でありここでは鉄筋コンクリート耐圧盤施工を行なっている。同時に地下室上部梁を施工してもよく、前述の既存ベースコンクリートの中の鉄筋を鉄筋の径の40倍以上残した部分を活用し地下室上部梁を施工すれば既存の住宅の既存ベースコンクリートとの接合強度があがり住宅としての強度があがる。 Next, the third step will be described. S31 is I) bottom concrete construction. Here, reinforced concrete pressure board construction is performed. At the same time, the basement upper beam may be constructed. If the basement upper beam is constructed by using the part of the above-mentioned existing base concrete where the rebar is left at least 40 times the diameter of the reinforcing bar, Bonding strength is increased and the strength of the house is increased.

次に第2工程において掘削によりケーソンがスムーズに自重沈下するためにケーソン外周部に骨材(砂等)を盛り上げると摩擦が減り目的が達成されるがその様子を図6に示した。図6では沈下していく時の様子を示しており17の位置にあった先行刃は1の位置まで沈下する。ここで2は地盤、10はケーソン壁、11はケーソン外周部保護層、19は先行刃最外周部による掘削面であり20は骨材層である。この20の骨材層の存在により摩擦が低減しスムーズにケーソンが自重沈下する。21は先行刃最外周部を通る鉛直線である。22の位置にあった先行刃は1の位置まで沈下する動きを23で表しており沈下によって先行刃外周部が作る掘削面とケーソン外周部保護層の間に24で示すように新たな骨材が流れ込み沈下しても摩擦が特に大きくなることは無くスムーズに先行刃付ケーソンが自重沈下していく。 Next, since the caisson smoothly settles due to excavation in the second step, when aggregate (sand, etc.) is raised on the outer periphery of the caisson, the friction is reduced and the purpose is achieved, as shown in FIG. FIG. 6 shows the state of the sinking, and the leading blade at position 17 sinks to position 1. Here, 2 is the ground, 10 is the caisson wall, 11 is the caisson outer periphery protective layer, 19 is the excavation surface by the outermost periphery of the leading blade, and 20 is the aggregate layer. The presence of these 20 aggregate layers reduces friction and allows the caisson to settle down by its own weight. Reference numeral 21 denotes a vertical line passing through the outermost peripheral portion of the leading blade. The leading blade which was at position 22 represents the movement of sinking to the position of 1 by 23, and a new aggregate as indicated by 24 between the excavation surface formed by the leading edge outer periphery and the caisson outer periphery protective layer by the sinking. Even if it flows in and sinks, the friction is not particularly increased, and the caisson with the leading blade smoothly sinks by its own weight.

既存住宅内に地下室を作る際のフローFlow when creating a basement in an existing house 地下室構築のためのケーソン構築の準備の断面図Cross section of preparation of caisson construction for basement construction 既存住宅の1階部分と地下室構築用ケーソン1st floor part of existing house and caisson for basement construction ベルトコンベアー設置Belt conveyor installation 既存住宅の1階部分とケーソン工法で構築した地下室Basement constructed with the first floor of the existing house and the caisson method ケーソン外周部に骨材(砂等)を盛り上げの効果Effect of raising aggregate (sand, etc.) on caisson outer periphery

S11 既存住宅地下室設置場所床面撤去
S12 小型掘削機、掘削道具の既存住宅内への搬入
S13 既存ベースコンクリートのはつり撤去
S14 先行刃、鋼製フレーム、型枠組立コンクリートミルク充填
S21 先行刃付ケーソン壁形成
S22 排残土手段設置
S23 掘削にてケーソン所定位置まで自重沈下
S24 底地整地
S25 小型掘削機、掘削道具搬出
S31 底面コンクリート施工
1 先行刃
2 地盤
3 床撤去したところ
4 既存ベースコンクリートはつり
5 既存の鉄筋を残してある様子 (鉄筋径の40倍以上の長さ)
6 先行堀(1) 第1段階
7 先行堀(2) 第2段階
8 既存ベースコンクリート残した部分
9 既存住宅壁
10 ケーソン壁
11 ケーソン壁外周部保護層
12 ベルトコンベアー
13 捨てコンクリート
14 防水処理(エンビシート)
15 底面 必要に応じて栗石等を敷く
16 鉄筋コンクリート耐圧盤
17 地下室上部梁
18 既存の鉄筋を活かした地下室上部梁鉄筋
19 掘削面
20 骨材(砂等)
21 先行刃最外周部を通る鉛直線
22 先行刃の一定沈下の前の位置
23 ケーソンと先行刃の動き
24 骨材の動き
S11 Existing house basement installation floor floor removal S12 Small excavator and excavation tool into existing house S13 Existing base concrete suspension removal S14 Lead blade, steel frame, formwork assembly concrete milk filling S21 Caisson wall with lead blade Formation S22 Waste soil removal means installation S23 Sedimentation down to caisson predetermined position by excavation S24 Soil leveling S25 Small excavator, excavation tool removal S31 Bottom concrete construction 1 Leading edge
2 ground
3 When the floor is removed
4 Existing base concrete is hanging 5 Existing rebar is left (length 40 times longer than rebar diameter)
6 Leading moat (1) First stage 7 Leading moat (2) Second stage 8 Existing base concrete remaining part 9 Existing housing wall 10 Caisson wall
11 Caisson wall outer peripheral protective layer 12 Belt conveyor 13 Abandoned concrete
14 Waterproof treatment (enbi sheet)
15 Bottom surface Place Kuriishi etc. if necessary
16 Reinforced concrete pressure board
17 Basement Upper Beam 18 Basement Upper Beam Reinforcement 19 Utilizing Existing Reinforcement 19 Drilling Surface 20 Aggregate (Sand, etc.)
21 Vertical line passing through the outermost periphery of the leading blade
22 Position before the settling of the leading blade 23 Movement of caisson and leading blade
24 Aggregate movement

Claims (13)

既存住宅内に地下室を作る際該既存住宅内に地下室の外周壁躯体を構成するケーソンを配置し該ケーソンの内側下部を掘削して該ケーソンを自重で所定の設置深さまで沈下させて地下室を構築する工法であって
A)乃至C)から構成される第1工程
A)小型掘削機または掘削道具の既存住宅内の地下室構築場所への搬入
B)既存ベースコンクリートのはつり撤去
C)先行刃設置、鋼製フレーム、型枠組み立てコンクリートミルク充填
D)乃至H)から構成される第2工程
D)先行刃付きケーソン壁形成
E)排残土手段設置
F)掘削にてケーソン所定位置まで自重沈下
G)底面整地
H)小型掘削機または掘削道具搬出
I)から構成される第3工程
I)底面にコンクリート施工
の3工程から構成された既存住宅内地下室構築方法
When creating a basement in an existing house, a caisson that constitutes the outer wall of the basement is placed in the existing house, and the lower part of the caisson is excavated to sink the caisson to a predetermined installation depth by its own weight. 1) A) A small excavator or excavator is brought into the basement construction site in the existing house B) The existing base concrete is lifted C) The leading blade is installed, Second step composed of steel frame, formwork assembled concrete milk filling D) to H) D) Formation of caisson wall with leading blade E) Installation of waste soil removal means F) Excavation of self-weight to caisson predetermined position by excavation G) Bottom surface Leveling H) Third step consisting of small excavator or excavation tool I) I) Method of constructing underground house in existing house consisting of three steps of concrete construction on the bottom
前記第3工程において鉄筋コンクリート地下室壁上部梁を形成することを特徴とする特許請求範囲第1項記載の既存住宅内地下室構築方法 The method for constructing a basement in an existing house according to claim 1, wherein an upper beam of a reinforced concrete basement wall is formed in the third step. 前記第2工程の前記B)の既存ベースコンクリートのはつり撤去の際、既存の鉄筋を鉄筋径40倍以上残し前記鉄筋コンクリート地下室壁上部梁形成の際前記既存鉄筋径の40倍以上残した鉄筋を利用することを特徴とする特許請求範囲第2項記載の既存住宅内地下室構築方法 When removing the existing base concrete in step B) of the second step, the existing rebar is left over 40 times the diameter of the rebar, and the rebar left over 40 times the diameter of the existing rebar is used when forming the upper beam of the reinforced concrete basement wall. A method for constructing a basement in an existing house according to claim 2, characterized in that: 現場の状態によって必要に応じて前記C)のはつり撤去後地面を地下室面積より40%から150%の範囲の面積で深さ300〜1000mm先行堀を行うことを特徴とする特許請求範囲第1項乃至3記載の既存住宅内地下室構築方法 According to the condition of the site, after removing the suspension of C), the ground is subjected to a 300-1000 mm depth moat with an area in the range of 40% to 150% from the basement area. Thru 3 existing basement construction method 前記先行堀は2段階になっていることを特徴する特許請求範囲第1項乃至4記載の既存住宅内地下室構築方法 The method for constructing a basement in an existing house according to claims 1 to 4, wherein the preceding moat has two stages. 前記ケーソン壁形成後該ケーソン壁外周部保護層形成することを特徴とする特許請求範囲第1項乃至5項記載の既存住宅内地下室構築方法 6. The method for constructing a basement in an existing house according to claim 1, wherein the caisson wall outer periphery protective layer is formed after the caisson wall is formed. 前記排残土手段設置はベルトコンベアであることを特徴とする特許請求範囲第1項乃至65項記載の既存住宅内地下室構築方法 The method for constructing a basement in an existing house according to any one of claims 1 to 65, wherein the waste soil disposal means is a belt conveyor. 前記底地整地は底地転圧であることを特徴とする特許請求範囲第1項乃至7項記載の既存住宅内地下室構築方法 The method for constructing a basement in an existing house according to claims 1 to 7, wherein the land leveling is a land rolling pressure. 外周部近傍及び底部に捨てコンクリート打ちすることを特徴とする特許請求範囲第1項乃至8項記載の既存住宅内地下室構築方法 9. A method for constructing a basement in an existing house according to claims 1 to 8, wherein the concrete is disposed in the vicinity of the outer periphery and the bottom. 底地整地後あるいは底面コンクリート打ち後床面防水加工を行うことを特徴とする特許請求範囲第1項乃至9項記載の既存住宅内地下室構築方法 10. A method for constructing a basement in an existing house according to claims 1 to 9, wherein the floor is waterproofed after bottoming or after bottom concrete is cast. 第2工程において必要に応じてケーソン外周部に骨材盛り上げたことを特徴とする特許請求範囲第1項乃至10項記載の既存住宅内地下室構築方法 The method for constructing a basement in an existing house according to any one of claims 1 to 10, wherein the aggregate is raised on the outer periphery of the caisson as necessary in the second step. 前記第3工程I)底面にコンクリート施工は鉄筋コンクリート耐圧盤施工であることを特徴とする特許請求範囲第1項乃至11項記載の既存住宅内地下室構築方法 The method for constructing a basement in an existing house according to claims 1 to 11, characterized in that the concrete construction on the bottom of the third step I) is a reinforced concrete pressure panel construction. 床面が存在する場合第1工程においてまず床面撤去を行うことを特徴とする特許請求範囲第1項乃至12項記載の既存住宅内地下室構築方法 The method for constructing a basement in an existing house according to claims 1 to 12, wherein the floor surface is first removed in the first step when the floor surface exists.
JP2010114920A 2010-05-19 2010-05-19 Construction method of basement in existing house Pending JP2011241608A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2010114920A JP2011241608A (en) 2010-05-19 2010-05-19 Construction method of basement in existing house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2010114920A JP2011241608A (en) 2010-05-19 2010-05-19 Construction method of basement in existing house

Publications (1)

Publication Number Publication Date
JP2011241608A true JP2011241608A (en) 2011-12-01

Family

ID=45408547

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2010114920A Pending JP2011241608A (en) 2010-05-19 2010-05-19 Construction method of basement in existing house

Country Status (1)

Country Link
JP (1) JP2011241608A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6423045B1 (en) * 2017-06-05 2018-11-14 Jfe建材株式会社 Caisson blade
CN110453722A (en) * 2019-08-27 2019-11-15 天津大学 A kind of mechanical auxiliary sink device reducing the resistance that breaks ground
CN111501829A (en) * 2020-04-29 2020-08-07 中国建筑第八工程局有限公司 Construction method of backfill type basement

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6423045B1 (en) * 2017-06-05 2018-11-14 Jfe建材株式会社 Caisson blade
CN110453722A (en) * 2019-08-27 2019-11-15 天津大学 A kind of mechanical auxiliary sink device reducing the resistance that breaks ground
CN111501829A (en) * 2020-04-29 2020-08-07 中国建筑第八工程局有限公司 Construction method of backfill type basement
CN111501829B (en) * 2020-04-29 2021-08-10 中国建筑第八工程局有限公司 Construction method of backfill type basement

Similar Documents

Publication Publication Date Title
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
KR100722665B1 (en) Steel guide wall for construction of underground diaphragm wall and construction method of underground diaphragm wall using the same
CN106013053A (en) Steel sheet pile support construction method for building underground garage open caisson
CN110159294A (en) A kind of high steep landform tunnel immediately adjacent to bridge section spreading open cut tunnel construction method
CN102888847B (en) Construction method free from lowering water level for local deep foundation pit of elevator shaft
CN106164380B (en) Wind-driven generator fabricated base
CN203160254U (en) Pit support structure
CN104032767A (en) Tower crane foundation in deep foundation pit and construction method of tower crane foundation
JP2011241608A (en) Construction method of basement in existing house
JP2010133206A (en) Structure and construction method for newly-built structure using existing pile
CN106988337B (en) It is a kind of for reducing the reinforcement means of bar shaped shallow foundation house differential settlement
CN102605801A (en) Suspension semi-reverse-construction method for underground circular water tank
JP6806465B2 (en) Construction method of foundation structure
CN206368375U (en) A kind of electric power pylon basis
JP6475554B2 (en) Construction method of shaft and construction method of underground storage tank
JP6220659B2 (en) Position adjustment method of reaction force receiving member and top of column
JP2017206882A (en) Method of constructing underground structure
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
JP5432814B2 (en) Construction method of concrete body for septic tank protection
JP4475116B2 (en) Vertical shaft structure and its construction method
CN205557573U (en) Underground structure
CN205224091U (en) Small -size basement of wherein of wholly being under construction
JP6402056B2 (en) Vertical shaft, underground storage tank, vertical shaft construction method and underground storage tank construction method
KR100981061B1 (en) Method for backfill gap of structure