JP2010037727A - Equipment and method for erecting precast pc plate for floor slab - Google Patents
Equipment and method for erecting precast pc plate for floor slab Download PDFInfo
- Publication number
- JP2010037727A JP2010037727A JP2008198331A JP2008198331A JP2010037727A JP 2010037727 A JP2010037727 A JP 2010037727A JP 2008198331 A JP2008198331 A JP 2008198331A JP 2008198331 A JP2008198331 A JP 2008198331A JP 2010037727 A JP2010037727 A JP 2010037727A
- Authority
- JP
- Japan
- Prior art keywords
- precast
- plate
- floor slab
- floor
- erection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
本発明は、床版用プレキャストPC板を橋桁上の所望の架設位置まで橋軸方向に向けて搬送し、架設位置手前で所望の架設角度に旋回させ、然る後架設位置へ移動させて架設するための床版用プレキャストPC板架設装置及びその方法に関する。 The present invention conveys the precast PC board for floor slabs to the desired erection position on the bridge girder in the direction of the bridge axis, turns it to the desired erection angle before the erection position, and then moves it to the erection position and installs it. The present invention relates to a precast PC plate erection device for floor slab and a method thereof.
近年、鋼桁を使用した橋梁の床版では、耐久性を考慮してPC(プレストレストコンクリート)床版が使用される事が多く、特に急速施工が望まれる場所では床版用プレキャストPC板を並べて架設することにより床版を構築する方法が採用されている。 In recent years, PC (prestressed concrete) floor slabs are often used for bridge slabs using steel girders, and precast PC plates for floor slabs are arranged side by side, especially in places where rapid construction is desired. A method of building a floor slab by erection is adopted.
一般に、床版用プレキャストPC板の架設は、桁下からトラッククレーンを使用して架設する場合が多いが、桁下にトラッククレーンが近づけない河川や交差道路のような場所では、橋上より専用の架設装置を使用して架設されている。 Generally, precast PC boards for floor slabs are often installed from under the girder using a truck crane. However, in places such as rivers and crossing roads where the truck crane cannot be approached under the girder, it is more dedicated than the bridge. It is erected using an erection device.
従来の架設装置は、図8〜図10に示すように、桁上に設置した既設の床版1上にレール3を敷設し、その上に搬送台車4及び架設機5を移動可能に載せ、搬送台車4は新たに架設しようとする床版用プレキャストPC板2を橋軸方向に対して直交する向きにして搭載して架設機5の手前位置まで搬送するようにしている。
As shown in FIGS. 8 to 10, the conventional erection apparatus lays a
架設機5は、走行台車6上に旋回架台7が設置され、その旋回架台7から突出させた吊り持ち用の片持式水平梁8を有しており、その水平梁8の先端に吊り装置9を備えた構造となっている。
The
床版用プレキャストPC板の架設に際しては、図8に示すように、架設機5を既設床版1の先端部分に移動させておき、搬送台車4上に床版用プレキャストPC板2を載せて架設機5の手前位置まで搬送し、この床版用プレキャストPC板2上に吊り装置9が来るように走行台車6及び旋回架台7を操作し、図9に示すように、搬送台車4上の床版用プレキャストPC板2を吊り装置9によって吊り上げる。この状態で旋回架台7を旋回させて床版用プレキャストPC板2を架設機5の後方側から前方側、即ち架設位置側に旋回移動させ、図10に示すように、走行架台6を移動させて床版用プレキャストPC板2を架設位置上に移動させて吊り降ろすようにしている。
When laying the precast PC plate for floor slab, as shown in FIG. 8, the
上記従来装置では、床版用プレキャストPC板2を旋回架台7に支持させて旋回する際に、床版用プレキャストPC板2が既設の床版1の側部にはみ出すため、安定性を保つ為の工夫が必要であり、また、既設床版1の近くに建物等の障害物があって旋回の為のスペースが十分に無い場合がある。この問題を解決しようとするものとして、図11、図12に示す架設機10のように、走行台車11の片側に立設した支柱部材12の上端に走行台車11の中央部分上に張り出した上部フレーム12を設け、その下面に橋軸方向に向けた懸垂用レール13を設置し、この懸垂用レール13に支持させたトロリー15に吊り装置16を支持させたものを使用し、搬送台車5によって搬送されてきた床版用プレキャストPC板2を、吊り装置16により吊り上げ、その位置で吊り上げた床版用プレキャストPC板2を橋軸方向に向くように旋回させ、この状態で上部フレーム12下を架設機10の反対側まで移動させ、然る後橋軸方向と直交する方向に旋回させた後、架設位置に吊り降ろす装置が開発されている(特許文献1)。
上述した従来の装置では、架設機の手前側位置からか架設位置側までの移動を、床版用プレキャストPC板を吊り上げた状態で架設機を旋回するか、吊り上げた状態で旋回させ、架設機の上部フレーム下を架設機の架設位置側まで移動させて再度旋回させるものであるため、架設機の構造が複雑となり、製造コストが高い。また、安定性確保のためには重量も大きくする必要があり既設床版に大きな負荷がかかり、移動も困難である。更には、架設機による床版用プレキャストPC板の吊り上げ(荷取り)、旋回、移動、架設の作業中にも台車反力が不均一となり、安定性が悪くなる状況があるなどの問題があった。 In the above-mentioned conventional apparatus, the construction machine is swung with the precast PC board for floor slab being lifted or swung in the state of being lifted, and moved from the near side position of the construction machine to the construction position side. Is moved to the erection position side of the erection machine and swiveled again, so that the structure of the erection machine becomes complicated and the manufacturing cost is high. Moreover, in order to ensure stability, it is necessary to increase the weight, a large load is applied to the existing floor slab, and movement is difficult. Furthermore, there is a problem that the reaction force of the carriage becomes non-uniform and the stability is deteriorated even during the lifting (loading), turning, moving, and erection work of the precast PC board for floor slab by the erection machine. It was.
本発明はこのような従来の問題に鑑み、架設のための装置が簡略化されるとともに、装置全体が軽量となり、床版用プレキャストPC板の移動、旋回、架設の作業が常に安定した状態でなされる床版用プレキャストPC板架設装置及びその架設方法の提供を目的としてなされたものである。 In view of such a conventional problem, the present invention simplifies the apparatus for erection, makes the entire apparatus lighter, and keeps the work of moving, turning, and erection of the precast PC plate for floor slabs constantly. It is made for the purpose of providing the precast PC board erection apparatus for floor slabs made, and its erection method.
上述の如き従来の問題を解決し、所期の目的を達成するための請求項1に記載の発明の特徴は、橋桁上に架設された既設床版上に橋軸方向に向けて設置した搬送台車用レールと、該搬送台車用レールの外側にこれと並行に設置した架設機用レールと、前記搬送台車用レール上を移動できる床版用プレキャストPC板搬送用台車と、前記架設機用レール上を移動できる架設機とを有し、前記床版用プレキャストPC板搬送用台車は、床版用プレキャストPC板の中央部分を支持し、これを水平方向に旋回できる旋回台を備えた旋回台付台車と、前記橋軸方向に向けた床版用プレキャストPC板の両端部を支持する一対の端部支持用台車とをもって構成され、前記架設機は、前記搬送台車用レールの上方を跨いで前記架設機用レール上を移動でき、且つ内部を前記床版用プレキャストPC板を橋軸方向に向けて搭載した前記床版用プレキャストPC板搬送台車が通過できる門型架台と、該門型架台の頂部より床版用プレキャストPC板架設部側に向けて橋軸方向に突出させた片持式水平梁と、該片持式水平梁の突出部分に支持され、床版用プレキャストPC板を吊り持ちして昇降させる吊り装置とから構成され、前記旋回台付台車上で橋軸と交差する向きに旋回された状態の床版用プレキャストPC板を前記吊り装置で吊り上げ、門型架台を移動させて架設位置まで搬送できるようにしてなる床版用プレキャストPC板架設装置にある。
The feature of the invention described in
請求項2に記載の発明の特徴は、請求項1に記載の床版用プレキャストPC板架設装置 を使用し、前記3台の台車からなる床版用プレキャストPC板搬送台車上に床版用プレキャストPC板を橋軸方向に向けて搭載し、これを前記門型架台内を通過させて架設機より床版用プレキャストPC板架設位置側まで移動させ、然る後、床版用プレキャストPC板を旋回台付台車の旋回台上のみに支持させ、該旋回台により床版用プレキャストPC板を橋軸方向に交差する所望の角度まで旋回させ、然る後前記架設機の門型架台を移動させて床版用プレキャストPC板上にまで前記吊り装置を移動させ、該吊り装置によって床版用プレキャストPC板を吊り上げ、該床版用プレキャストPC板が所望の架設位置上に至るまで門型架台を移動させ、該架設位置にて床版用プレキャストPC板を吊り降ろす床版用プレキャストPC板架設方法にある。
A feature of the invention described in
請求項3に記載の発明の特徴は、請求項2の構成に加え、床版用プレキャストPC板の上面又は下面に該床版用プレキャストPC板の自重による発生する断面力に対抗する仮補強鋼材を添わせて固定した状態で、前記床版用プレキャストPC板搬送台車への搭載から架設までの工程を行なうことにある。
The invention according to
本発明においては、床版用プレキャストPC板搬送台車として、床版用プレキャストPC板の中央部分を支持する旋回台付台車と両端を支持する一対の端部支持用台車とをもって構成させ、床版用プレキャストPC板をこれらの台車によって縦向きにして既設床版上を搬送させるようにし、床版用プレキャストPC板の旋回は、レール上の旋回台付台車上に支持させた状態で行なうこととなり、既設床版上で、その外側にはみ出すことなく、安定した状態で安全に行なう事ができる。 In the present invention, the floor slab precast PC board conveying carriage is constituted by a car with a swivel base that supports the central portion of the floor cast precast PC board and a pair of end support carriages that support both ends, The precast PC board for the slab is transported on the existing floor slab vertically by these carts, and the precast PC board for the floor slab is swung while being supported on the carriage with the swivel platform on the rail. On the existing floor slab, it can be safely performed in a stable state without protruding to the outside.
また、架設機は、台車に搭載された床版用プレキャストPC板が内部を通過できる門型に形成され、前記床版用プレキャストPC板搬送台車用のレールの外側に設置したレール上を移動できるようにしたことにより、床版用プレキャストPC板搬送用台車の移動作業と並行してとは別個に作業ができることとなり、施工性が向上する。 Further, the erection machine is formed in a gate shape through which the precast PC board for floor slab mounted on the carriage can pass through, and can be moved on the rail installed outside the rail for the precast PC board conveying carriage for floor slab. By doing in this way, work can be performed separately from the movement work of the precast PC board conveying carriage for floor slabs, and workability is improved.
また、床版用プレキャストPC板搬送台車はとして3台の台車を使用し、床版用プレキャストPC板を橋軸方向に向けて搬送するものであるため、既設床版上を搬送するために必要なスペースが少なくなり、他の作業機器類を床版上に残し、他の作業を進行させつつ床版用プレキャストPC板の架設作業ができることとなり、作業効率が良いものとなる。 In addition, the precast PC board transportation cart for floor slabs is used for transporting the precast PC board for floor slabs in the direction of the bridge axis because it uses three carts. Therefore, the work space is reduced, and other work equipments are left on the floor slab, and the precast PC board for floor slab can be installed while the other work is progressed, so that the work efficiency is improved.
更に、3台の台車を使用して床版用プレキャストPC板を搬送するものであるため、特に端部支持用台車は簡易な構造のものでよく、また、架設機はそれ自体の移動と床版用プレキャストPC板の昇降操作ができればよいため、必要とする個々の装置の構成が単純化されるとともに軽量化されて全体としてコストが削減されるとともに、仮置き状態の既設床版に与える負荷も小さくなる。 Furthermore, since the three trolleys are used to transport the precast PC board for floor slabs, the end support trolleys in particular may have a simple structure, and the erection machine can move and floor itself. Since it is only necessary to be able to lift and lower the precast PC plate for the plate, the configuration of each required device is simplified and the weight is reduced, and the cost is reduced as a whole, and the load applied to the temporarily placed existing floor slab Becomes smaller.
また、架設される床版用プレキャストPC板の上面又は下面に該床版用プレキャストPC板の自重により発生する断面力に対抗する仮補強鋼材を添わせて固定した状態で、前記床版用プレキャストPC板搬送台車への搭載から架設までの工程を行なうようにしたことにより、作業中に発生する床版用プレキャストPC板の断面力に対しても安全な状態で作業ができる。 In addition, the precast floor slab precast is fixed in a state in which a temporary reinforcing steel material that resists the cross-sectional force generated by the weight of the precast PC plate for floor slab is attached to the upper or lower surface of the precast PC plate for floor slab. By performing the steps from mounting on the PC board conveying cart to erection, the work can be performed in a safe state against the cross-sectional force of the precast PC board for floor slab generated during the work.
次に本発明の実施の形態を図1〜図7に示した実施例に基づいて説明する。図1〜図3は、本発明に係る装置の全体の構成を簡略化して示している。図において符号20は鋼桁であり、21は床版用プレキャストPC板22を仮置きして架設された既設床版である。この既設床版21上に、橋軸方向に向けて搬送台車用レール23,23が敷設され、その外側にこれと並行配置に架設機用レール24,24が敷設されている。
Next, embodiments of the present invention will be described based on the examples shown in FIGS. 1 to 3 show a simplified overall configuration of an apparatus according to the present invention. In the figure,
搬送台車用レール23,23上には、3台を一組とした床版用プレキャストPC板搬送用台車25,26,26が走行可能に載せられている。この各台車は、床版用プレキャストPC板22を橋軸方向に向けた状態で搭載して移動できるようにしているものであり、3台の内の中央には旋回台付台車25、その前後側に端部支持用台車26,26が配置されている。
On the
旋回台付台車25は、下部に車輪を有する走行台27の上に水平方向に旋回できる旋回台28が載せられており、その上面に枕材29を介して床版用プレキャストPC板22の中央部分下面が支持されるようになっている。
In the
端部支持用台車26,26は旋回台付台車25の前後に配置されていて、その上面の載荷台30上に枕材31を介して床版用プレキャストPC板22の両端部下面が支持されるようになっている。尚、図には示してないが、この枕材31には、上向きのジャッキが備えられ、このジャッキを介して床版用プレキャストPC板22の端部下が載荷されるようになっている。
The
架設機用レール24,24上には架設機35が移動可能に載せられている。この架設機35は、レール24,24上を移動できる門型架台36を有している。この門型架台36は、天井横梁37aとその両端下に一体化させた脚37b,37bとによって門型に形成された一対の門型構37,37と、それらの天井横梁37a,37aの上に跨らせて固定した一対の縦梁38、38とによって構成されており、各脚37bの下端にはレール上に載荷される走行用車輪39それぞれ備えられている。
A
この門型架台35は、その門型内を前述した台車25,26,26上の床版用プレキャストPC板22を搭載した状態で通過できる大きさに形成されている。
The
門型架台35には、床版用プレキャストPC板新規架設部側に向けて片持式水平梁40、40が突設されている。この水平梁40は、前述した縦梁38を天井横梁37a,37a間の間隔より長く形成しておき、その先端を新規架設部側に突出させて構成させている。
Cantilever type
水平梁40、40の先端部には、吊り装置45,45が支持されている。この吊り装置45,45は、それらから下向きに垂下した吊り材46を昇降させるものであり、例えば、電動のワイヤー巻き上げ機やチェンブロック、更には油圧シリンダーが使用できる。吊り材46の下端には吊り金具47が連結されている。
次に上述した床版用プレキャストPC板架設装置を使用した床版用プレキャストPC板22の架設方法を、図1、図4〜図7について説明する。
Next, a method of laying the
図1に示すように、新規に架設しようとする床版用プレキャストPC板22は、その上面にH型鋼からなる仮補強材50を固定した状態で中央部分を旋回台付台車25に、両端部を端部支持用台車26,26上に支持させ、搬送台車用レール23,23上を橋軸方向に向けた状態で、床版21上を該床版端部の架設位置側に搬送する。このとき、架設機35は、架設位置より床版用プレキャストPC板22の長さ分以上手前位置に待機させておく。
As shown in FIG. 1, the
台車25,26,26に搭載した状態で搬送されてくる床版用プレキャストPC板22を、図4に示すように、待機している架設機35の門型内を通過させて架設位置側に移動させる。然る後、両端部支持用台車26,26による床版用プレキャストPC板22の支持を解く。この操作は、例えば、枕材31と床版用プレキャストPC板22間のジャッキを縮めて床版用プレキャストPC板の載荷状態を解くことにより行なう。
As shown in FIG. 4, the
次いで図5に示すように、旋回台付台車25の旋回台28を旋回させて床版用プレキャストPC板22を橋軸方向と交差する架設向きに至るまで旋回させる。この旋回は旋回台25に電動の旋回駆動機構を設置しておき、電動によって行なっても良く、旋回駆動機構を備えていない場合には人力により床版用プレキャストPC板22を旋回させる。
Next, as shown in FIG. 5, the
次いで図6に示すように、架設機35を床版用プレキャストPC板22の手前位置まで前進させることにより水平梁40の吊り装置45を床版用プレキャストPC板22上位置に移動させる。次いで、吊り材46を降下させ、吊り金具47によって床版用プレキャストPC板22上に添わせてある仮補強材50に固定して吊り上げ、床版用プレキャストPC板22を旋回台付台車25上から架設機35に荷取りする。
Next, as shown in FIG. 6, the suspending
然る後図7に示すように、架設機35を架設位置側に移動させて床版用プレキャストPC板22を架設位置上に移動させる。次いで吊り装置45により床版用プレキャストPC板22を吊り降ろし、指定の位置に架設する。この架設機35の移動は、台車25,26,26を跨いでなされ、床版用プレキャストPC板22の架設機35による移動及び架設の間に、各台車25,26を、図6に示すように、搬送台車用レール23,23上を戻り方向に移動させ、次の床版用プレキャストPC板搬送作業に備える。架設機35は、床版用プレキャストPC板22の架設作業完了後、その位置より次に搬送されてくる床版用プレキャストPC板の長さ分以上の距離を戻り方向に移動させ、次の架設作業に備える。
Thereafter, as shown in FIG. 7, the laying
尚、上述した実施例では、端部支持用台車26による床版用プレキャストPC板端部支持を解除し、旋回台付台車25のみに支持させる方式として、枕材にジャッキを付設した場合を示しているが、旋回台付台車25の旋回台をジャッキによって昇降できるようにしておき、該ジャッキにより床版用プレキャストPC板を上昇させることによって端部支持台車26に対する載荷状態を解除しても良い。
In addition, in the Example mentioned above, the case where the jack was attached to the pillow material as a system which cancels | releases the precast PC board edge part support for floor slabs by the edge
20 鋼桁
21 既設床版
22 床版用プレキャストPC板
23 搬送台車用レール
24 架設機用レール
25 旋回台付台車
26 端部支持用台車
27 走行台
28 旋回台
29 枕材
30 載荷台
31 枕材
35 架設機
36 門型架台
37 門型構
37a 天井横梁
37b 脚
38 縦梁
39 走行用車輪
40 片持式水平梁
45 吊り装置
46 吊り材
47 吊り金具
50 仮補強材
20
Claims (3)
前記床版用プレキャストPC板搬送用台車は、床版用プレキャストPC板の中央部分を支持し、これを水平方向に旋回できる旋回台を備えた旋回台付台車と、前記橋軸方向に向けた床版用プレキャストPC板の両端部を支持する一対の端部支持用台車とをもって構成され、
前記架設機は、前記搬送台車用レールの上方を跨いで前記架設機用レール上を移動でき、且つ内部を前記床版用プレキャストPC板を橋軸方向に向けて搭載した前記床版用プレキャストPC板搬送台車が通過できる門型架台と、該門型架台の頂部より床版用プレキャストPC板架設部側に向けて橋軸方向に突出させた片持式水平梁と、該片持式水平梁の突出部分に支持され、床版用プレキャストPC板を吊り持ちして昇降させる吊り装置とから構成され、
前記旋回台付台車上で橋軸と交差する向きに旋回された状態の床版用プレキャストPC板を前記吊り装置で吊り上げ、門型架台を移動させて架設位置まで搬送できるようにしてなる床版用プレキャストPC板架設装置。 A rail for a transport carriage installed on an existing floor slab installed on a bridge girder in the direction of the bridge axis, a rail for a construction machine installed in parallel to the outside of the rail for the transport carriage, and the rail for the transport carriage It has a precast PC board carriage for floor slab that can move on, and an erection machine that can move on the erection rail.
The floor slab precast PC board transporting carriage supports the central part of the floor slab precast PC board, and is provided with a car with a swivel that has a swivel that can be turned in a horizontal direction, and is directed in the bridge axis direction. It is composed of a pair of end support carts that support both ends of the precast PC plate for floor slabs,
The precast PC for floor slab, which can move on the rail for the construction machine across the rail for the carriage, and has the precast PC plate for floor slab mounted in the direction of the bridge axis. A gate-type pedestal through which a plate carriage can pass, a cantilevered horizontal beam projecting in the direction of the bridge axis from the top of the gate-type pedestal toward the precast PC plate erection side of the floor slab, Is supported by the projecting portion of, and is composed of a lifting device that lifts and lowers a precast PC board for floor slab,
A floor slab that allows a precast PC plate for a floor slab in a state of being swung in a direction intersecting with a bridge axis on the carriage with a swivel to be lifted by the suspension device and moved to a laying position by moving a gate-type frame. Precast PC board erection device.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008198331A JP5051591B2 (en) | 2008-07-31 | 2008-07-31 | Precast PC plate erection device for floor slab and its erection method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2008198331A JP5051591B2 (en) | 2008-07-31 | 2008-07-31 | Precast PC plate erection device for floor slab and its erection method |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2010037727A true JP2010037727A (en) | 2010-02-18 |
JP5051591B2 JP5051591B2 (en) | 2012-10-17 |
Family
ID=42010559
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2008198331A Active JP5051591B2 (en) | 2008-07-31 | 2008-07-31 | Precast PC plate erection device for floor slab and its erection method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP5051591B2 (en) |
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102433844A (en) * | 2011-09-26 | 2012-05-02 | 中交四航局第一工程有限公司 | Cantilever beam hoisting system of trestle and construction system and method for erecting prefabricated beam of bridge deck |
CN102979040A (en) * | 2012-12-13 | 2013-03-20 | 中铁二局股份有限公司 | Assembly method of bridge-building machine at exit of tunnel connected with bridge |
RU2479687C1 (en) * | 2011-10-20 | 2013-04-20 | Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" | Device to lift and install span blocks |
CN103981814A (en) * | 2014-06-04 | 2014-08-13 | 郑州新大方重工科技有限公司 | Overhead crane operating rail gauge change adjusting mechanism |
KR101441332B1 (en) | 2013-09-27 | 2014-09-17 | 주식회사 에스비테크 | A method for supplying materials for access floor of clean room and an apparatus therefor |
JP2017053117A (en) * | 2015-09-08 | 2017-03-16 | 新日鉄住金エンジニアリング株式会社 | Renewal method for existing road, and renewed road |
CN106638325A (en) * | 2016-12-31 | 2017-05-10 | 中铁十八局集团第五工程有限公司 | Construction method applicable to steel member gliding assembling in narrow spaces |
CN107059629A (en) * | 2017-03-22 | 2017-08-18 | 河南省黄河防爆起重机有限公司 | Sightseeing trajectory bridge lifting bridging equipment |
CN107697837A (en) * | 2017-08-24 | 2018-02-16 | 柳州欧维姆机械股份有限公司 | A kind of integrally rotated slide device of achievable large-scale component and installation method |
CN108130864A (en) * | 2018-04-23 | 2018-06-08 | 重庆交通大学 | The whole bridge transport of overall assembled bridge sets up equipment and construction method |
JP2018104972A (en) * | 2016-12-26 | 2018-07-05 | 株式会社Ihiインフラシステム | Floor slab erection method and floor slab erection device |
CN108342991A (en) * | 2018-05-11 | 2018-07-31 | 山东铁正工程试验检测中心有限公司 | Bridge hauling construction system |
CN108867383A (en) * | 2018-06-25 | 2018-11-23 | 中铁三局集团有限公司 | A kind of across the steel case trusses cable-stayed bridge rapid constructing method of double tower five |
CN110273364A (en) * | 2018-03-17 | 2019-09-24 | 中铁第五勘察设计院集团有限公司 | In the method set a roof beam in place on station of setting a roof beam in place |
JP2020122359A (en) * | 2019-01-31 | 2020-08-13 | 鹿島建設株式会社 | Floor slab erection system, additional floor slab installation method, and floor slab removing method |
WO2023214438A1 (en) * | 2022-05-05 | 2023-11-09 | Deal S.R.L. | Plant for the construction of engineering works |
JP7421434B2 (en) | 2020-07-13 | 2024-01-24 | 株式会社ピーエス三菱 | PCa board erection equipment and method for floor slabs |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105780667B (en) * | 2016-05-16 | 2017-08-25 | 贵州路桥集团有限公司 | The special light-duty Bridge Erector of cored slab |
CN106087768B (en) * | 2016-08-12 | 2017-12-26 | 中铁二十五局集团第三工程有限公司 | A kind of method of the assembled mobile formwork in the narrow short transition time section of bridge tunnel |
JP7299103B2 (en) * | 2019-08-20 | 2023-06-27 | Jr東日本コンサルタンツ株式会社 | Elevated structure construction system and construction method |
-
2008
- 2008-07-31 JP JP2008198331A patent/JP5051591B2/en active Active
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102433844A (en) * | 2011-09-26 | 2012-05-02 | 中交四航局第一工程有限公司 | Cantilever beam hoisting system of trestle and construction system and method for erecting prefabricated beam of bridge deck |
CN102433844B (en) * | 2011-09-26 | 2014-08-06 | 中交四航局第一工程有限公司 | Method for erecting prefabricated beam of bridge deck |
RU2479687C1 (en) * | 2011-10-20 | 2013-04-20 | Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" | Device to lift and install span blocks |
CN102979040A (en) * | 2012-12-13 | 2013-03-20 | 中铁二局股份有限公司 | Assembly method of bridge-building machine at exit of tunnel connected with bridge |
KR101441332B1 (en) | 2013-09-27 | 2014-09-17 | 주식회사 에스비테크 | A method for supplying materials for access floor of clean room and an apparatus therefor |
CN103981814A (en) * | 2014-06-04 | 2014-08-13 | 郑州新大方重工科技有限公司 | Overhead crane operating rail gauge change adjusting mechanism |
JP2017053117A (en) * | 2015-09-08 | 2017-03-16 | 新日鉄住金エンジニアリング株式会社 | Renewal method for existing road, and renewed road |
JP2018104972A (en) * | 2016-12-26 | 2018-07-05 | 株式会社Ihiインフラシステム | Floor slab erection method and floor slab erection device |
CN106638325A (en) * | 2016-12-31 | 2017-05-10 | 中铁十八局集团第五工程有限公司 | Construction method applicable to steel member gliding assembling in narrow spaces |
CN106638325B (en) * | 2016-12-31 | 2018-06-08 | 中铁十八局集团第五工程有限公司 | Suitable for the construction method of steel member liding assembling under narrow space |
CN107059629A (en) * | 2017-03-22 | 2017-08-18 | 河南省黄河防爆起重机有限公司 | Sightseeing trajectory bridge lifting bridging equipment |
CN107059629B (en) * | 2017-03-22 | 2022-08-23 | 河南省黄河防爆起重机有限公司 | Sightseeing line track bridge hoisting bridge equipment |
CN107697837A (en) * | 2017-08-24 | 2018-02-16 | 柳州欧维姆机械股份有限公司 | A kind of integrally rotated slide device of achievable large-scale component and installation method |
CN107697837B (en) * | 2017-08-24 | 2023-12-15 | 柳州欧维姆机械股份有限公司 | Sliding device capable of realizing integral rotation of large-scale component and installation method |
CN110273364A (en) * | 2018-03-17 | 2019-09-24 | 中铁第五勘察设计院集团有限公司 | In the method set a roof beam in place on station of setting a roof beam in place |
CN110273364B (en) * | 2018-03-17 | 2021-06-25 | 中铁第五勘察设计院集团有限公司 | Method for erecting beam at beam erecting station |
CN108130864A (en) * | 2018-04-23 | 2018-06-08 | 重庆交通大学 | The whole bridge transport of overall assembled bridge sets up equipment and construction method |
CN108342991B (en) * | 2018-05-11 | 2019-09-06 | 铁正检测科技有限公司 | Bridge hauling construction system |
CN108342991A (en) * | 2018-05-11 | 2018-07-31 | 山东铁正工程试验检测中心有限公司 | Bridge hauling construction system |
CN108867383A (en) * | 2018-06-25 | 2018-11-23 | 中铁三局集团有限公司 | A kind of across the steel case trusses cable-stayed bridge rapid constructing method of double tower five |
JP2020122359A (en) * | 2019-01-31 | 2020-08-13 | 鹿島建設株式会社 | Floor slab erection system, additional floor slab installation method, and floor slab removing method |
JP7421434B2 (en) | 2020-07-13 | 2024-01-24 | 株式会社ピーエス三菱 | PCa board erection equipment and method for floor slabs |
WO2023214438A1 (en) * | 2022-05-05 | 2023-11-09 | Deal S.R.L. | Plant for the construction of engineering works |
Also Published As
Publication number | Publication date |
---|---|
JP5051591B2 (en) | 2012-10-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5051591B2 (en) | Precast PC plate erection device for floor slab and its erection method | |
JP3721166B2 (en) | Floor slab erection device | |
JP5507383B2 (en) | Heavy load erection machine and heavy load erection method | |
JP6476426B2 (en) | Member renewal method using lifting device | |
JP2015169029A (en) | Laying method of bridge floor plate and its device | |
JPH0841828A (en) | Bridge girder erection equipment | |
CN110562856B (en) | Hoisting device for heavy object and hoisting and carrying method | |
JP5769961B2 (en) | Construction method and removal method of structure | |
KR101160273B1 (en) | Straddle carrier for bridge construction | |
JP2008248664A (en) | Hoisting method of curtain wall | |
JP5473294B2 (en) | Overhead crane installation method and installation system | |
JP2019157441A (en) | Demolition system and demolition method for existing structure | |
JP2013002143A (en) | Installation device and installation method | |
JP2016142097A (en) | Portable hoist unit and horizontal member dismantling method | |
JP5027015B2 (en) | Cable conveyor | |
JPH06272389A (en) | Temporary unloading stage | |
JP2001213584A (en) | Large-scale elevation stage and lifting method and reversely driving technique using the same | |
JP2000302389A (en) | Working cage elevator | |
JP2020122359A (en) | Floor slab erection system, additional floor slab installation method, and floor slab removing method | |
JP4961268B2 (en) | Precast floor slab transport method and transport mechanism | |
JP6718392B2 (en) | How to suspend and remove concrete slabs | |
JP4888737B2 (en) | Under-orbit transport mechanism | |
JP2019015150A (en) | Demolition method of existing structure | |
CN215798013U (en) | Reinforced concrete roof truss beam conveyor in hole | |
JP7479885B2 (en) | Transport device and method for assembling new structure within existing structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20110425 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20120612 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20120620 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20120713 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 5051591 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150803 Year of fee payment: 3 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |