Prior art keywords
lifter
crane
seat
work
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2008040830A
Other languages
Japanese (ja)
Other versions
JP5138413B2 (en
Inventor
Osamu Yokoyama
治 横山
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nippon Steel Nisshin Co Ltd
Original Assignee
Nisshin Steel Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nisshin Steel Co Ltd filed Critical Nisshin Steel Co Ltd
Priority to JP2008040830A priority Critical patent/JP5138413B2/en
Publication of JP2009196675A publication Critical patent/JP2009196675A/en
Application granted granted Critical
Publication of JP5138413B2 publication Critical patent/JP5138413B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pallets (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a crane lifter transport trestle for safely and efficiently removing or transporting a crane lifter which hangs and transports an item (steel plate coil or the like) from a crane hook for checking, repairing, or the like. <P>SOLUTION: This crane lifter transport trestle includes a lifter seat 2 and a horizontal base stand 4. The seat 2 has a seat part 22 and a backrest part 23 and is supported on the stand 4 able to tilt and move between a vertical position VP and a horizontal position HP. The bottom of a body frame 61 of the crane lifter 6 suspended by a crane hook is seated on the seat part 22 of the seat 2 fixed at the position VP and the seat 2 is tilted to be in a supine attitude roughly in parallel with the stand 4. The trestle is transported to a predetermined position for checking, repairing, or the like by an appropriate transport unit (rail car, truck, or the like) after the crane lifter is placed in the supine attitude. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は、クレーンリフターを、点検・修理等のために、クレーンフックから外して所定の場所へ搬送するクレーンリフター搬送作業を、安全かつ効率よく遂行し得るようにしたクレーンリフター搬送用架台に関する。   The present invention relates to a crane lifter transportation stand that can perform a crane lifter transportation work for removing a crane lifter from a crane hook and transporting the crane lifter to a predetermined place for inspection and repair.

鋼帯コイル等の物品を取扱う製造ラインでは、該物品を懸吊・運搬する手段としてクレーンリフター(トングとも称される)が広く使用されている。
クレーンリフターは、図10(側面図)及び図11(正面図)に示すように、本体フレーム(61)の左右に、リンク機構(62)に連結された物品保持アーム(63,63)を備えている。本体フレーム(61)には、モーター(65)とこれに連結されたねじ棒(66)が配置され、リンク機構(62)の基端部は連結部材(67)を介してねじ棒(66)に係合されている。物品保持アーム(63,63)は、図12のように、モータ(65)によるねじ棒(66)の回転(正/逆回転)に伴うリンク機構(62)の相対動作により、物品(W)(鋼帯コイルを例示)の幅サイズより広い開状態(実線表示)と、該物品(W)を両側から挟んで保持する閉状態(鎖線表示)との開閉動作を行う。該クレーンリフター(6)は、本体フレーム(61)の頂部に連結されるクレーンフック係合部(7)を介してクレーンフック(CH)に懸吊され昇降及び水平方向の移動を行う。
In production lines that handle articles such as steel strip coils, crane lifters (also called tongs) are widely used as means for suspending and transporting the articles.
As shown in FIG. 10 (side view) and FIG. 11 (front view), the crane lifter includes article holding arms (63, 63) connected to the link mechanism (62) on the left and right sides of the main body frame (61). ing. The body frame (61) is provided with a motor (65) and a screw rod (66) connected to the motor (65), and the base end portion of the link mechanism (62) is connected to the screw rod (66) via the connecting member (67). Is engaged. As shown in FIG. 12, the article holding arms (63, 63) are moved by the relative movement of the link mechanism (62) accompanying the rotation (forward / reverse rotation) of the screw rod (66) by the motor (65). An opening / closing operation is performed between an open state (shown by a solid line) wider than the width size (illustrated by a steel strip coil) and a closed state (shown by a chain line) holding the article (W) from both sides. The crane lifter (6) is suspended from the crane hook (CH) via a crane hook engaging portion (7) connected to the top of the main body frame (61), and moves up and down and moves in the horizontal direction.

クレーンリフター(6)による物品の運搬作業[物品(W)を保持アーム(63,63)で吊り上げ所定場所まで移行し荷下しする]が安全・確実に遂行されるように、クレーンリフター(6)の本体フレーム(61)及び物品保持アーム(63,63)には、各種のセンサー・制御機器類が多数組み込まれている。
クレーンリフター(6)のサイズ・重量はさまざまであるが、鋼帯コイル運搬用のリフターの具体例を挙げれば、高さ[物品保持アーム(63,63)の下端縁から本体フレーム(61)の上端縁(頂部のクレーンフック係合部7を除く)までの高さ]は約4〜5m、重さ[頂部のクレーンフック係合具7を除いた重量]は約2〜3ton、という比較的大型サイズの重量物である。
The crane lifter (6) is used so that the work of transporting the article by the crane lifter (6) [the article (W) is lifted by the holding arms (63, 63) and unloaded to a predetermined place and unloaded] is performed safely and reliably. A large number of various sensors and control devices are incorporated in the main body frame (61) and the article holding arms (63, 63).
There are various sizes and weights of the crane lifter (6). To give specific examples of lifters for carrying steel strip coils, the height [from the lower edge of the article holding arm (63, 63) to the main body frame (61) The height to the upper edge (excluding the crane hook engaging portion 7 at the top) is about 4 to 5 m, and the weight (weight excluding the crane hook engaging tool 7 at the top) is about 2 to 3 tons. It is a large-sized heavy object.

特開2000−355482号公報JP 2000-355482 A 実開昭57−116681号公報Japanese Utility Model Publication No. 57-116682

クレーンリフター(6)は、定期点検の実施、あるいは突発的に発生した不具合の修理等に際して、クレーンフック(CH)から外され、その作業ヤードから、搬送車(軌道台車,トラック等)で点検修理工場等に送られる。前記の鋼帯コイル運搬用リフターのように、丈が高く重量の大きいリフター(6)は、搬送作業の安全性のために搬送車に水平姿勢に載置して搬送される。
クレーンフック(CH)に懸吊された鉛直姿勢のリフター(6)を、搬送車の荷台の上に水平姿勢に載置するクレーン運転操作には高度の熟練を要する。またクレーンリフター(6)には前記のように各種センサー・制御機器類が多数取り付けられているので、それらの機器類に衝撃によるダメージを生じさせないように、より慎重なクレーン操作と玉掛け作業が要求される。
The crane lifter (6) is removed from the crane hook (CH) when carrying out periodic inspections or repairing problems that occur suddenly, and is inspected and repaired from the work yard with a transport vehicle (track carriage, truck, etc.). Sent to factories. Like the steel strip coil transporter, the lifter 6 having a high height and a large weight is placed on a transport vehicle in a horizontal position and transported for safety of transport work.
High skill is required for the crane operation for placing the vertical lifter (6) suspended on the crane hook (CH) in a horizontal posture on the carrier bed. The crane lifter (6) is equipped with many sensors and control devices as described above, so more careful crane operation and slinging work are required to prevent damage to these devices due to impact. Is done.

クレーンリフター(6)を搬送車に載置する作業は、上記のようにクレーン作業の安全確保及びリフター(6)に内装された各種機器類の保護のために、慎重かつ緩徐の取り扱いを必要とし、そのために作業所要時間(クレーン拘束時間)が比較的長く、結果としてクレーン運転効率を阻害する大きな要因となっている。また、その作業は慎重かつ緩徐の操作のもとに行われるとはいえ、リフター(6)に加わる衝撃(リフターに内装された各種機器類のダメージの原因となる)を確実に回避することは容易でない。
本発明は、クレーンリフター(6)の搬送に関する上記問題を解消することを目的としてなされたものである。
The work of placing the crane lifter (6) on the transport vehicle requires careful and slow handling in order to ensure the safety of the crane work and to protect the various devices installed in the lifter (6) as described above. For this reason, the work required time (crane restraint time) is relatively long, and as a result, this is a major factor that impedes crane operation efficiency. In addition, although the work is carried out under careful and slow operation, it is not possible to reliably avoid the impact applied to the lifter (6) (which may cause damage to various devices installed in the lifter). Not easy.
The present invention has been made for the purpose of solving the above-mentioned problems relating to the conveyance of the crane lifter (6).

本発明のクレーンリフター搬送用架台は、
本体フレームに左右一対の物品保持アームが開閉可能に連結されているクレーンリフターを点検修理作業場に搬送する際に使用されるクレーンリフター搬送用架台であって、
リフター着座台(2)と水平基台(4)とからなり、リフター着座台(2)は、座部(22)と背もたれ部(23)とを有する共に、水平基台(4)に対する垂直位置(VP)と水平位置(HP)との間の傾動動作が可能なように水平基台(4)に支承されており、垂直位置(VP)に固定したリフター着座台(2)の座部(22)に、クレーンフックに懸吊されたクレーンリフター(6)の本体フレーム(61)の底部を着座させたうえ、リフター着座台(2)を傾動して水平基台(4)に略平行な仰臥姿勢となすように構成されていることを特徴としている。
搬送用架台は、クレーンリフターが仰臥姿勢に載置されたうえ、適宜の搬送手段(軌道車,トラック等)により点検・修理等のための所定場所に搬送される。
The crane lifter carrier of the present invention is
A crane lifter transportation stand used when transporting a crane lifter in which a pair of left and right article holding arms are connected to a main body frame so as to be openable and closable to an inspection and repair work place,
The lifter seat (2) and the horizontal base (4) consist of a lifter seat (2) having a seat (22) and a backrest (23), and a vertical position relative to the horizontal base (4). The seat of the lifter seat (2), which is supported on the horizontal base (4) and can be tilted between the horizontal position (HP) and the vertical position (VP) 22), the bottom of the main frame (61) of the crane lifter (6) suspended from the crane hook is seated, and the lifter seat (2) is tilted to be substantially parallel to the horizontal base (4). It is configured to be in a supine posture.
The transportation platform is transported to a predetermined place for inspection / repair by an appropriate transportation means (railway vehicle, truck, etc.) after the crane lifter is placed in a supine posture.

上記構成を有する本発明において、クレーンフック(CH)に懸吊された鉛直姿勢のクレーンリフター(6)を、垂直位置(VP)のリフター着座台(2)に着座させるクレーン運転操作は容易であり、その垂直位置(VP)から水平位置(HP)に傾動させることによりクレーンリフター(6)を、搬送に適した安定な仰臥姿勢とすることができる。
上記クレーンリフター(6)の着座の操作、およびリフター着座台(2)の傾動操作のいずれも容易に行うことができるので、クレーンリフター(6)の搬出作業に要求されるクレーン運転の拘束時間が短縮され、クレーンの運転効率が高められる。
また、クレーンリフター(6)を、リフター着座台(2)に着座させて水平位置(HP)まで傾動する作業工程は円滑に遂行されるので、その作業過程においてクレーンリフター(6)に対する衝撃(それに因る各種センサー・機器類のダメージ)も効果的に回避される。
In the present invention having the above-described configuration, the crane operation for allowing the crane lifter (6) in the vertical posture suspended from the crane hook (CH) to be seated on the lifter seat (2) in the vertical position (VP) is easy. By tilting from the vertical position (VP) to the horizontal position (HP), the crane lifter (6) can be in a stable supine posture suitable for conveyance.
Since both the operation of sitting the crane lifter (6) and the tilting operation of the lifter seating base (2) can be easily performed, the restraint time of crane operation required for the crane lifter (6) unloading work is required. This shortens the crane operation efficiency.
In addition, since the work process in which the crane lifter (6) is seated on the lifter seat (2) and tilted to the horizontal position (HP) is smoothly performed, the impact on the crane lifter (6) (and to it) (The damage of various sensors and devices) is effectively avoided.

図1及び図2は、クレーンリフター(以下「リフター」とも称する)の搬送用架台(1)の具体例(図1:正面図、図2:側面図)を示している。リフター搬送用架台(1)は、リフター着座台(2)とそれを支持する水平基台(4)とからなる。
リフター着座台(2)は、左右に向かい合う一対のフレーム(21,21)を支柱とする、座部(22)及び背もたれ部(23)を有している。水平基台(4)は、床フレーム(41)とリフター着座台(2)を支承するフレーム(43,43)、フレーム(45,45)等からなり、該支承フレーム(43,43)及びフレーム(45,45)のそれぞれは、床フレーム(41)の一端側に位置して床フレーム(41)の左右両側に立設されている。
FIG. 1 and FIG. 2 show specific examples (FIG. 1: front view, FIG. 2: side view) of a transportation platform (1) of a crane lifter (hereinafter also referred to as “lifter”). The lifter carrier (1) includes a lifter seat (2) and a horizontal base (4) that supports the lifter seat (2).
The lifter seat (2) has a seat part (22) and a backrest part (23) using a pair of frames (21, 21) facing left and right as columns. The horizontal base (4) includes a frame (43, 43), a frame (45, 45), and the like that support the floor frame (41) and the lifter seat (2). Each of (45, 45) is located on one end side of the floor frame (41) and is erected on both the left and right sides of the floor frame (41).

水平基台(4)に立設された一方の支承フレーム(43,43)の上端側には、リフター着座台(2)の傾動支点となる軸ピン(44,44)が設けられている。他方の支承フレーム(45,45)の上端側には、リフター着座台(2)を一時的に垂直位置(VP)に固定するための固定ピン(46,46)が着脱可能に取付けられている。
支承フレーム(43,43)の軸ピン(44,44)は、リフター着座台(2)の脚部フレーム(24,24)に係合され、その係合構造によりリフター着座台(2)は軸ピン(44,44)を傾動支点として支承フレーム(43,43)に枢支されている。
A shaft pin (44, 44) serving as a tilting fulcrum of the lifter seating base (2) is provided on the upper end side of one support frame (43, 43) erected on the horizontal base (4). Fixing pins (46, 46) for temporarily fixing the lifter seat (2) to the vertical position (VP) are detachably attached to the upper end side of the other support frame (45, 45). .
The shaft pins (44, 44) of the support frame (43, 43) are engaged with the leg frames (24, 24) of the lifter seat (2), and the lifter seat (2) is pivoted by the engagement structure. The pins (44, 44) are pivotally supported on the support frame (43, 43) with the tilting fulcrum as a tilting fulcrum.

図3及び図4は、リフター搬送用架台(1)にリフター(6)が載置された状態を示している[図3:正面図,図4:側面図、各図ともリフター(6)からクレーンフック係合具(7)が取り外された状態を示す]。リフター着座台(2)は、水平基台(4)に対する垂直位置(VP)と、水平基台(2)に平行な向きの水平位置(HP)との間を、軸ピン(44,44)を支点として傾動する。
リフター(6)をリフター着座台(2)に着座させる操作は、リフター着座台(2)を垂直位置(VP)に保持した状態で行われる。リフター(6)は、本体フレーム(61)の底面(611)を着座面として、リフター着座台(2)の座部(22)に着座される。このときリフター着座台(2)の垂直位置(VP)は固定ピン(46,46)で固定されている。リフター(6)を着座させた後、固定ピン(46,46)を抜き取り、リフター着座台(2)を水平位置(HP)に傾動させる。
3 and 4 show a state in which the lifter (6) is placed on the lifter transporting base (1) [FIG. 3: front view, FIG. 4: side view, both drawings from the lifter (6)] The crane hook engaging tool (7) is shown in a removed state]. The lifter seat (2) has a shaft pin (44, 44) between a vertical position (VP) relative to the horizontal base (4) and a horizontal position (HP) oriented parallel to the horizontal base (2). Tilt around the fulcrum.
The operation of seating the lifter (6) on the lifter seat (2) is performed with the lifter seat (2) held in the vertical position (VP). The lifter (6) is seated on the seat (22) of the lifter seating base (2) with the bottom surface (611) of the main body frame (61) as a seating surface. At this time, the vertical position (VP) of the lifter seat (2) is fixed by the fixing pins (46, 46). After the lifter (6) is seated, the fixing pins (46, 46) are removed, and the lifter seat (2) is tilted to the horizontal position (HP).

クレーンフック(CH)に懸吊されたリフター(6)をリフター着座台(2)の座部(22)に着座させ、ついでリフター着座台(2)を水平位置(HP)に傾動させる一連の動作は、クレーン運転操作と地上作業者の玉掛け作業との連携作業により行われる。この一連の作業操作が円滑に遂行されるように、リフター着座台(2)には、アーム(25,25)、作業デッキ(31,31)及びその他付属部品が設けられている。   A series of operations in which the lifter (6) suspended from the crane hook (CH) is seated on the seat (22) of the lifter seat (2), and then the lifter seat (2) is tilted to the horizontal position (HP). Is performed by a cooperative operation between the crane operation and the ground worker's slinging operation. The lifter seat (2) is provided with arms (25, 25), work decks (31, 31) and other accessory parts so that this series of work operations can be performed smoothly.

アーム(25,25)は、リフター着座台(2)の背もたれ部(23)の上端側に位置し、その左右の支柱フレーム(21,21)に対をなして取付けられ、該アーム(25,25)の先端にチエン掛け具(26,26)が設けられている。リフター着座台(2)にリフター(6)を着座させた後、チエン掛け具(26,26)(26)にチェン(27)を掛ければ、リフター(6)の上部は背もたれ部(23)とアーム(25,25)及びチエン(27)で包囲される。これにより、クレーン運転の作業過程[クレーンフック(CH)やフック係合部(7)の取り外し等の作業過程]において、何らかのはずみでリフター(6)の着座姿勢のバランスが損なわれるようなことがあっても、リフターの横転等のトラブルを防止することができる。なおアーム(25,25)の側部に取付けられた箱状体(30)(図1,図2)はリフター(6)に付属するケーブル類(電源用ケーブルや通信用ケーブル等,図示省略)の先端部を収納するボックスである。   The arms (25, 25) are positioned on the upper end side of the backrest portion (23) of the lifter seat (2), and are attached to the left and right column frames (21, 21) in pairs. A chain hook (26, 26) is provided at the tip of 25). After the lifter (6) is seated on the lifter seat (2), the chain (27) is hung on the chain hooks (26, 26) and (26), and the upper part of the lifter (6) is connected to the backrest part (23). Surrounded by arms (25, 25) and chain (27). As a result, the balance of the sitting posture of the lifter (6) may be lost due to some sort of slack in the crane operation process [work process of removing the crane hook (CH) and the hook engaging portion (7), etc.]. Even if it exists, troubles such as a rollover of the lifter can be prevented. The box-like body (30) (FIGS. 1 and 2) attached to the side of the arm (25, 25) is a cable attached to the lifter (6) (power cable, communication cable, etc., not shown) It is a box which accommodates the front-end | tip part.

またアーム(25,25)には、吊り具掛け金具(28,28)が取り付けられている。リフター(6)を垂直位置(VP)のリフター着座台(2)に着座させた後、リフター着座台(2)をクレーンで水平位置(HP)に傾動させるに際して、該掛け金具(28,28)にワイヤ、チエン等の吊り具(81)が掛けられる(後記)。
更に、リフター着座台(2)の上端側の左右両側には、作業デッキ(31,31)が設けられている。リフター着座台(2)に着座したリフター(6)からクレーンフック(CH)を離脱する作業、アーム(25,25)にチエン(27)を掛ける作業、リフター着座台(2)を垂直位置(VP)から水平位置(HP)に傾動させるためのクレーン玉掛け作業など(後記)は、地上作業者の介添え作業(クレーンの誘導合図・玉掛け等)が必要である。鋼帯コイル運搬用リフターのように丈の高いリフター(6)(例えば高さ約3〜4m)の搬送用架台では、作業の安全・円滑性が確保されるように、作業デッキ(31)に上がって所要の介添え作業を行う。
Further, hanging arms (28, 28) are attached to the arms (25, 25). After the lifter (6) is seated on the lifter seat (2) in the vertical position (VP), when the lifter seat (2) is tilted to the horizontal position (HP) with a crane, the hooks (28, 28) A hanger (81) such as a wire or a chain is hung on (see below).
Furthermore, work decks (31, 31) are provided on the left and right sides of the upper end side of the lifter seat (2). Lifting the crane hook (CH) from the lifter (6) seated on the lifter seat (2), hanging the chain (27) on the arms (25, 25), lifting the lifter seat (2) to the vertical position (VP ) From the ground to the horizontal position (HP), etc. (described later) requires the assistance of ground workers (guide guidance of the crane, sling, etc.). In the case of a high-lifter (6) (for example, about 3 to 4 m in height), such as a steel band coil carrier lifter, the work deck (31) can be used to ensure the safety and smoothness of work. Go up and do the necessary care.

上記作業デッキ(31)の作業者の昇降には梯子(L)(図3中、鎖線表示)が使用される。作業デッキ(31)は、リフター着座台(2)の片側だけでもよいが、図は作業者が左右のどちら側からもアクセスできるように支柱フレーム(21,21)の両側に取り付けている。 作業デッキ(31)の手すりの昇降口側には、作業者の転落事故防止のために開閉バー(32)が設けられている。開閉バー(32)は、片側端を支点として作業者の手で回動され(図2中,矢符R)、作業者が昇降する際に開け(鎖線表示)、作業中は閉じておく(実線表示)。
また、リフター着座台(2)の背もたれ部(23)には、リフター受け部材(29)が設けられている。受け部材(29)は、リフター着座台(2)が水平位置(HP)に傾動されたときに、リフター(6)をその背面側から担持し、リフター(6)の安定な仰臥姿勢を保持する枕木である。受け部材(29)は左右の支柱フレーム(21,21)に掛け渡されて固定される。図では、背もたれ部(23)の2個所に受け部材(29,29)を取り付けているが、取り付け位置及び個数はリフター(6)の形状・サイズに応じて適宜設定される。
A ladder (L) (shown by a chain line in FIG. 3) is used for raising and lowering the worker on the work deck (31). The work deck (31) may be only on one side of the lifter seat (2), but the figure is attached to both sides of the support frame (21, 21) so that the operator can access from either the left or right side. An open / close bar (32) is provided on the handrail side of the work deck (31) to prevent the operator from falling. The open / close bar (32) is rotated by an operator's hand with one end as a fulcrum (arrow R in FIG. 2), opened when the operator moves up and down (indicated by a chain line), and closed during the operation ( Solid line display).
A lifter receiving member (29) is provided on the backrest (23) of the lifter seat (2). The receiving member (29) carries the lifter (6) from the back side when the lifter seat (2) is tilted to the horizontal position (HP), and maintains a stable supine posture of the lifter (6). It is a sleeper. The receiving member (29) is stretched over the left and right support frames (21, 21) and fixed. In the figure, the receiving members (29 1 , 29 2 ) are attached to two positions of the backrest portion (23), but the attachment position and number are appropriately set according to the shape and size of the lifter (6).

水平基台(4)には、床フレーム(41)の一端側[前記支柱フレーム(43)(45)の設置位置の反対側]に、堰フレーム(42)が立設されている。リフター着座台(2)に着座したリフター(6)は、リフター着座台(2)の傾動により、堰フレーム(42)と座部(22)との間に納められ、水平基台(4)に平行な仰臥姿勢となる(図4,図9)。これによりリフター(6)の搬送用架台(1)からのずれ落ち等の万一のトラブルが防止される。   On the horizontal base (4), a weir frame (42) is erected on one end side of the floor frame (41) [on the opposite side to the installation position of the support frame (43), 45). The lifter (6) seated on the lifter seat (2) is placed between the weir frame (42) and the seat (22) by the tilt of the lifter seat (2), and is placed on the horizontal base (4). Parallel supine postures (FIGS. 4 and 9). As a result, it is possible to prevent troubles such as a slippage of the lifter (6) from the carrier (1).

また水平基台(4)の床フレーム(41)には、バンド掛け金具(47)及び吊り具の掛け金具(49)が設けられている。バンド掛け金具(47)及び吊り具掛け金具(49)のいずれも、床フレーム(41)の左右両側に取り付けられている。
バンド掛け金具(47)には、仰臥姿勢のリフター(6)を水平基台(4)に括りつけて仰臥姿勢を固定するためのバンドが係着される(後記)。他方、吊り具掛け金具(49)には、搬送用架台(1)をクレーンで吊り上げるための吊り具(ワイヤ等)が係着される(後記)。
The floor frame (41) of the horizontal base (4) is provided with a band hanging bracket (47) and a hanging bracket (49). Both the band hanging bracket (47) and the hanging bracket hanging bracket (49) are attached to the left and right sides of the floor frame (41).
A band for securing the supine posture by tying the lifter 6 in the supine posture to the horizontal base 4 is attached to the band hanging bracket 47 (described later). On the other hand, a hanging tool (wire or the like) for lifting the transportation platform (1) with a crane is attached to the hanging tool hanging bracket (49) (described later).

次にクレーンリフターの搬送用架台への載置および搬送操作について、図5〜図9を参照して説明する。
まずリフター(6)をリフター搬送用架台(1)に載置するにあたり、図5のように、リフター着座台(2)を垂直位置(VP)に回動し、支承フレーム(45)の固定ピン(46)で垂直姿勢位置(VP)に固定しておく。そして、クレーンフック(CH)に懸吊したリフター(6)を、リフター着座台(2)に向けて移行(矢符A)させ、図6に示すように、本体フレーム(61)の底面(611)を着座面として座部(22)に着座させる。
Next, placement and transportation operation of the crane lifter on the transportation platform will be described with reference to FIGS.
First, when placing the lifter (6) on the lifter carrier (1), as shown in FIG. 5, the lifter seat (2) is rotated to the vertical position (VP), and the fixing pin of the support frame (45) is fixed. The vertical posture position (VP) is fixed at (46). Then, the lifter (6) suspended from the crane hook (CH) is moved (arrow A) toward the lifter seat (2), and as shown in FIG. ) Is seated on the seat portion (22) as a seating surface.

リフター(6)を座部(22)に着座させたうえ、背もたれ部(23)のアーム(25,25)にチエン(27)を掛け渡し、ついでクレーンフック(CH)を外す。図6では、クレーンフック(CH)と共にリフター頂部のクレーンフック係合部(7)をも取り外した例を示している。しかるのち、図7(I:側面図、II:正面図)に示すように、アーム(25,25)の吊り具掛け金具(28,28)に傾動用吊り具(81)(ワイヤ,チエンなど)を掛け、クレーンフック(CH)に係合する。これらの作業は作業者が作業デッキ(31)に搭乗して行なう。   The lifter (6) is seated on the seat (22), the chain (27) is passed over the arms (25, 25) of the backrest (23), and then the crane hook (CH) is removed. FIG. 6 shows an example in which the crane hook engaging portion (7) at the top of the lifter is also removed together with the crane hook (CH). After that, as shown in FIG. 7 (I: side view, II: front view), the tilting hanger (81) (wire, chain, etc.) is attached to the hanger hanger (28, 28) of the arm (25, 25). ) And engage the crane hook (CH). These operations are carried out by the operator on the work deck (31).

クレーンフック(CH)に係合した傾動用吊り具(81)を、クレーン操作で適度の緊張状態に保持し、支承フレーム(45,45)の固定ピン(46,46)を抜き取ってリフター着座台(2)を傾動自在の状態となす。ついで、クレーン操作により、軸ピン(44,44)を支点としてリフター着座台(2)を水平位置(HP)に傾動させる。水平位置(HP)に移行したリフター着座台(2)上のリフター(6)は、リフター着座台の座部(22)と水平基台の堰フレーム(42)との間に納置され、受け部材(枕木)(29)(29,29)に担持された安定な仰臥姿勢に保たれる(図8)。 The tilting suspension (81) engaged with the crane hook (CH) is held in an appropriate tension state by the crane operation, and the fixing pins (46, 46) of the support frame (45, 45) are pulled out to lift the lifter seat. Make (2) tiltable. Next, the lifter seat (2) is tilted to the horizontal position (HP) with the shaft pins (44, 44) as fulcrums by crane operation. The lifter (6) on the lifter seat (2) that has been moved to the horizontal position (HP) is placed between the seat (22) of the lifter seat and the weir frame (42) of the horizontal base and received. A stable supine posture held on the members (sleepers) (29) (29 1 , 29 2 ) is maintained (FIG. 8).

リフター着座台(2)を水平位置(HP)に移行させた後、傾動用吊り具(81)を外し、図9のように、水平基台の床フレーム(41)のバンド掛け具(47)にバンド(48)を掛け、該バンド(48)で、リフター(6)をリフター着座台(2)と共に水平基台(4)に括りつける。これによりリフター(6)の仰臥姿勢が固定される。
ついで、床フレーム(41)の吊り具掛け金具(49)(49,49)に吊り具(チエンやワイヤ等)(82)を掛け、クレーンフック(CH)でリフター搬送用架台(1)を吊り上げて搬送車(図示省略)の荷台に載せる。搬送用架台(1)を予め搬送車の荷台に載せている場合は、そのまま点検修理工場へ搬出する。なお、点検修理工場が、同じ作業ヤード(建屋)のクレーン走行範囲内にある場合は、搬送用架台(1)をクレーンフック(CH)に吊り上げてクレーン走行により点検修理工場へ搬送すればよく、搬送車は不要である。
After the lifter seating base (2) is moved to the horizontal position (HP), the lifting device for tilting (81) is removed, and the band hanging tool (47) of the floor frame (41) of the horizontal base as shown in FIG. A band (48) is hung on and the lifter (6) is fastened to the horizontal base (4) together with the lifter seat (2). Thereby, the supine posture of the lifter (6) is fixed.
Next, suspenders (chain, wire, etc.) (82) are hung on the hanging brackets (49) (49 1 , 49 2 ) of the floor frame (41), and the lifter transport platform (1) is secured with a crane hook (CH). Is lifted and placed on the carrier of the transport vehicle (not shown). If the transport platform (1) is previously placed on the platform of the transport vehicle, it is transported to the inspection and repair factory. If the inspection / repair factory is within the crane travel range of the same work yard (building), the transport platform (1) can be lifted on the crane hook (CH) and transported to the inspection / repair factory by crane travel. A transport vehicle is not required.

点検修理工場に送り込まれたリフターの点検修理は、リフター(6)を搬送用架台(1)から荷下しすることなく、搬送用架台(1)上の水平な仰臥姿勢の状態で実施することができる。そのままの状態で、本体フレーム(61)や物品保持アーム(63,63)に対する作業者等のアクセスが容易であるからである。   Inspection and repair of the lifter sent to the inspection / repair factory should be carried out in a horizontal supine posture on the transportation platform (1) without unloading the lifter (6) from the transportation platform (1). Can do. This is because it is easy for an operator or the like to access the main body frame (61) and the article holding arms (63, 63) in this state.

点検修理を終えたリフター(6)は送り込まれたときと同じように、リフター(6)をバンド(48)で水平基台(4)に括り付けてもとの作業ヤードへ返送する。もとの作業ヤードに返送された搬送用架台(1)のリフター(6)を、クレーンフック(CH)に掛け戻す作業は、リフター(6)を搬送用架台(1)に載置する前記の作業手順(図5〜図9)と逆の手順で行えばよい。まず吊り具(82),バンド(48)を外し、リフター着座台(2)のアーム(25,25)に傾動用吊り具(81)を掛けて、クレーンフック(CH)に係合する(図8)。   The lifter (6) that has been inspected and repaired is returned to the original work yard even if the lifter (6) is tied to the horizontal base (4) with the band (48) in the same manner as when it was sent. The work of returning the lifter (6) of the transportation platform (1) returned to the original work yard to the crane hook (CH) is performed by placing the lifter (6) on the transportation platform (1). The work procedure (FIGS. 5 to 9) may be reversed. First, the lifting device (82) and the band (48) are removed, and the lifting device (81) is hung on the arm (25, 25) of the lifter seat (2) and engaged with the crane hook (CH) (see FIG. 8).

ついで、クレーン操作でリフター着座台(2)を水平位置(HP)から垂直位置(VP)に傾動し、固定ピン(46)で垂直位置(VP)に固定する(図7,図6)。つぎにアーム(25,25)の先端にチエン(27)を掛けたうえ、傾動用吊り具(81)を外す。更に、リフター(6)の本体フレーム(61)の頂部にクレーンリフター係合部(7)を連結し、これにクレーンフック(CH)を掛けてリフター着座台(2)から吊り上げる(図5)。これら一連の作業は地上作業者の介添えとクレーン運転操作により効率よく遂行することができる。こうしてクレーンフック(CH)に懸吊されたリフター(6)は鋼帯コイル等の物品の運搬作業に投入される。   Next, the lifter seat (2) is tilted from the horizontal position (HP) to the vertical position (VP) by crane operation, and fixed to the vertical position (VP) by the fixing pin (46) (FIGS. 7 and 6). Next, the chain (27) is hung on the tip of the arm (25, 25), and the tilting hanger (81) is removed. Further, a crane lifter engaging portion (7) is connected to the top of the main body frame (61) of the lifter (6), and a crane hook (CH) is hooked on the crane lifter engaging portion (7) and lifted from the lifter seat (2) (FIG. 5). These series of operations can be efficiently performed by the assistance of ground workers and crane operation. Thus, the lifter (6) suspended from the crane hook (CH) is put into the work of transporting articles such as steel strip coils.

本発明によれば、クレーンリフターを、点検修理等のためにクレーンフックから外して作業ヤードから搬出する作業を安全かつ効率よく短時間で行うことができる。
クレーンリフターは、安定した仰臥姿勢で搬送されるので、搬送作業も容易である。また、クレーンリフターの点検修理等の施工も、搬送用架台に載置された仰臥姿勢のもとで実施することができる。更に、クレーンリフターを、もとの作業ヤードへ返送して本来の物品運搬作業に復帰させる際の作業操作も効率よく短時間で遂行することができ、従ってクレーンリフターの搬出・搬入作業のためのクレーン運転時間(クレーン拘束時間)が減少し、作業ヤードにおけるクレーン運転効率が向上する。
本発明は各種製造工場において、クレーンリフターを、点検修理等のためにクレーンフックから外して搬出及び搬入する手段として極めて有用であり、その搬出・搬入作業に要するクレーン運転時間を削減してクレーン運転効率を高めると共に、クレーンリフターに付帯する各種センサー・機器類の保護の観点から、工業的に大きな実用価値を有するものである。
ADVANTAGE OF THE INVENTION According to this invention, the operation | work which removes a crane lifter from a crane hook for inspection repair etc., and can carry out from a work yard can be performed safely and efficiently.
Since the crane lifter is transported in a stable supine posture, transport work is also easy. Construction such as inspection and repair of the crane lifter can also be carried out under the supine posture placed on the transportation platform. Furthermore, the work operation when returning the crane lifter to the original work yard and returning it to the original material transportation work can be carried out efficiently and in a short time. The crane operation time (crane restraint time) is reduced, and the crane operation efficiency in the work yard is improved.
The present invention is extremely useful as means for removing and lifting a crane lifter from a crane hook for inspection and repair in various manufacturing factories. From the viewpoint of enhancing the efficiency and protecting various sensors and devices attached to the crane lifter, it has a great industrial value.

搬送用架台の正面図Front view of transfer platform 搬送用架台の側面図Side view of transport platform リフターの載置状態を示す正面説明図Front explanatory view showing the lifter mounting state リフターの載置状態を示す側面説明図Side surface explanatory view showing the state of placement of the lifter 搬送用架台へのリフター載置操作の説明図Explanatory drawing of lifter placement operation on transfer platform 搬送用架台へのリフター載置操作の説明図Explanatory drawing of lifter placement operation on transfer platform 搬送用架台へのリフター載置操作の説明図(I:側面図、II:正面図)Explanatory drawing of lifter placement operation on transfer platform (I: side view, II: front view) 搬送用架台へのリフター載置操作の説明図Explanatory drawing of lifter placement operation on transfer platform 搬送用架台へのリフター載置/搬送操作の説明図Explanatory drawing of lifter placement / transport operation on transport platform リフターの側面図Side view of lifter リフターの正面図Front view of lifter リフターの物品保持アーム開閉動作の模式的説明図Schematic explanatory diagram of opening and closing operation of lifter article holding arm

符号の説明Explanation of symbols

1:リフター搬送用架台
2:リフター着座台
21:支柱フレーム
22 :座部
23 :背もたれ部
24:脚部フレーム
25:アーム
26:チエン掛け金具
27 :チェン
28:傾動用吊り具の掛け金具
29(29,29):受け部材(枕木)
30:ケーブル先端部収納ボックス
31:作業デッキ
32:開閉バー(転落防止用)
1: Lifter transport base 2: Lifter seat 21: Post frame 22: Seat 23: Backrest 24: Leg frame 25: Arm 26: Chain hanging bracket 27: Chain 28: Hanging bracket 29 for tilting 29 1 , 29 2 ): Receiving member (sleeper)
30: Cable tip storage box 31: Work deck 32: Opening / closing bar (for fall prevention)

4:水平基台
41:床フレーム
42:堰フレーム
43:支承フレーム
44:軸ピン(リフター着座台の傾動支軸)
45:支承フレーム
46:固定ピン
47:バンド掛け金具
48:バンド
49(491,492):搬送用架台の吊り具掛け金具
4: Horizontal base 41: Floor frame 42: Weir frame 43: Support frame 44: Shaft pin (tilting support shaft of lifter seat)
45: Support frame 46: Fixing pin 47: Band hanging bracket 48: Band 49 (49 1 , 49 2 ): Suspension bracket hanging bracket for the carrier

6:クレーンリフター
61:本体フレーム
611:本体フレームの底面
62:リンク機構
63:物品保持アーム
64:リフター制御盤
65:駆動モーター
66:ねじ棒
67:連結部材
7:クレーンフック係合部
81:傾動用吊り具
82:搬送用架台吊り具
6: Crane lifter 61: Main body frame 611: Bottom surface of main body frame
62: Link mechanism 63: Article holding arm 64: Lifter control panel 65: Drive motor 66: Screw rod 67: Connecting member
7: Crane hook engaging part 81: Tilt lifting device 82: Transfer platform lifting device

W :被運搬物品(鋼帯コイル等)
CH:クレーンフック
L :はしご
VP:垂直位置
HP:水平位置
W: Article to be transported (steel strip coil, etc.)
CH: Crane hook L: Ladder VP: Vertical position HP: Horizontal position

Claims (1)

本体フレームに左右一対の物品保持アームが開閉可能に連結されているクレーンリフターを点検修理作業場に搬送する際に使用されるクレーンリフター搬送用架台であって、
リフター着座台(2)および水平基台(4)からなり、リフター着座台(2)は、座部(22)と背もたれ部(23)とを有する共に、水平基台(4)に対する垂直位置(VP)と水平位置(HP)との間の傾動動作が可能なように水平基台(4)に支承されており、垂直位置(VP)に固定したリフター着座台(2)の座部(22)に、クレーンフックに懸吊されたクレーンリフター(6)の本体フレーム(61)の底部を着座させたうえ、リフター着座台(2)を傾動して水平基台(4)に略平行な仰臥姿勢となすように構成されていることを特徴とするクレーンリフター搬送用架台。
A crane lifter transportation stand used when transporting a crane lifter in which a pair of left and right article holding arms are connected to a main body frame so as to be openable and closable to an inspection and repair work place,
The lifter seat (2) and the horizontal base (4) have a seat portion (22) and a backrest portion (23), and a vertical position relative to the horizontal base (4) ( VP) and the horizontal position (HP) are supported by the horizontal base (4) so as to be able to tilt, and the seat (22) of the lifter base (2) fixed at the vertical position (VP) ), The bottom of the main frame (61) of the crane lifter (6) suspended from the crane hook is seated, and the lifter seat (2) is tilted so that it is substantially parallel to the horizontal base (4). A crane lifter transportation stand configured to be in a posture.
JP2008040830A 2008-02-22 2008-02-22 Crane lifter carrier Expired - Fee Related JP5138413B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2008040830A JP5138413B2 (en) 2008-02-22 2008-02-22 Crane lifter carrier

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2008040830A JP5138413B2 (en) 2008-02-22 2008-02-22 Crane lifter carrier

Publications (2)

Publication Number Publication Date
JP2009196675A true JP2009196675A (en) 2009-09-03
JP5138413B2 JP5138413B2 (en) 2013-02-06

Family

ID=41140653

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2008040830A Expired - Fee Related JP5138413B2 (en) 2008-02-22 2008-02-22 Crane lifter carrier

Country Status (1)

Country Link
JP (1) JP5138413B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012240818A (en) * 2011-05-23 2012-12-10 Sankyu Inc Lifting magnet type carrying device
CN111874790A (en) * 2020-06-22 2020-11-03 海洋石油工程股份有限公司 A stand up wet structure of depositing for vertical dredging pipe ware under water

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5777348U (en) * 1980-10-24 1982-05-13
JPS57116681U (en) * 1981-01-12 1982-07-20
JPH0562432U (en) * 1992-02-03 1993-08-20 村田機械株式会社 Tall luggage pallet
JPH0941667A (en) * 1995-08-04 1997-02-10 Fujita Corp Truck equipped with derrick for conveying building member and method for conveying building member on the truck

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5777348U (en) * 1980-10-24 1982-05-13
JPS57116681U (en) * 1981-01-12 1982-07-20
JPH0562432U (en) * 1992-02-03 1993-08-20 村田機械株式会社 Tall luggage pallet
JPH0941667A (en) * 1995-08-04 1997-02-10 Fujita Corp Truck equipped with derrick for conveying building member and method for conveying building member on the truck

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012240818A (en) * 2011-05-23 2012-12-10 Sankyu Inc Lifting magnet type carrying device
CN111874790A (en) * 2020-06-22 2020-11-03 海洋石油工程股份有限公司 A stand up wet structure of depositing for vertical dredging pipe ware under water

Also Published As

Publication number Publication date
JP5138413B2 (en) 2013-02-06

Similar Documents

Publication Publication Date Title
JP3039445B2 (en) Container crane
US5232192A (en) Suspender arm for machinery
JP3375330B2 (en) Container handling equipment
JP5138413B2 (en) Crane lifter carrier
JP3116107U (en) Left-right switchable rail loader
JPH11301966A (en) Load lifting device for carrying-in/shipping
JP2005324930A (en) Sling
JPH03186510A (en) Transport facility using self-running device
JP2007090186A (en) Apparatus for transporting material to be coated
JP2001097662A (en) Hoisting device for ship cargo handling
JP4461161B2 (en) Equipment for suspending radioactive material transport and storage containers
JP2019123614A (en) Container crane and cargo handling method by container crane
JP3234536B2 (en) Multipurpose crane
JP2009023811A (en) Tilting type truck frame conveying device
JP4514277B2 (en) Product coil shipping method
KR102560294B1 (en) Construction Material Lifting Device with Improved Structure Capable of Rope Binding
JP3298488B2 (en) Container crane
JPH11157777A (en) Container crane
RU22921U1 (en) 9 TON LOAD
RU2029839C1 (en) Mounted platform
JPH0650111Y2 (en) Reversing device
JP2510485Y2 (en) Heavy goods transportation and installation machine
JPH07270578A (en) Acceptance inspection method for new fuel
JPH0688755B2 (en) Carrier
JP2002327536A (en) Slinging frame

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20110221

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20121105

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20121108

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20121114

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20151122

Year of fee payment: 3

LAPS Cancellation because of no payment of annual fees