JP2009019356A - Structure and method for jointing bridge pier and footing - Google Patents
Structure and method for jointing bridge pier and footing Download PDFInfo
- Publication number
- JP2009019356A JP2009019356A JP2007180994A JP2007180994A JP2009019356A JP 2009019356 A JP2009019356 A JP 2009019356A JP 2007180994 A JP2007180994 A JP 2007180994A JP 2007180994 A JP2007180994 A JP 2007180994A JP 2009019356 A JP2009019356 A JP 2009019356A
- Authority
- JP
- Japan
- Prior art keywords
- steel pipe
- footing
- joining
- pier
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
Description
本発明は、鋼製橋脚の下端をRC製フーチングに接合する際に用いられる橋脚とフーチングとの接合構造及び方法に関する。 The present invention relates to a joining structure and method of a pier and a footing used when joining a lower end of a steel pier to an RC footing.
鋼製橋脚の下端を基礎に接合するにあたっては、アンカーフレームと呼ばれる鋼製フレームを予め製作した上、これを鉄筋コンクリート基礎であるフーチング内に埋設し、次いで、アンカーフレームから延びるアンカーボルトを利用して鋼製橋脚の下端をアンカーフレームにボルト接合する方法が従来から広く用いられている。 When joining the lower end of a steel pier to the foundation, a steel frame called an anchor frame is manufactured in advance, and then embedded in a footing, which is a reinforced concrete foundation, and then anchor bolts extending from the anchor frame are used. A method of bolting the lower end of a steel pier to an anchor frame has been widely used.
最近では、かかる方法に加えて、地盤内に構築された基礎にソケット鋼管と呼ばれる太径の鋼管を設置し、次いで、該ソケット鋼管内に鋼製橋脚の下端を挿入した後、鋼製橋脚の外面とソケット鋼管の内面との間にコンクリートを充填することによって、鋼製橋脚の下端、ソケット鋼管及び基礎を一体化する方法も知られており、かかる方法によれば、急速施工が可能であることから、交通量の多い場所で短工期に工事を進めることが可能となる。 Recently, in addition to such a method, a steel pipe with a large diameter called a socket steel pipe is installed on the foundation constructed in the ground, and then the lower end of the steel pier is inserted into the socket steel pipe, and then the steel pier A method of integrating the lower end of the steel pier, the socket steel pipe and the foundation by filling concrete between the outer surface and the inner surface of the socket steel pipe is also known, and according to such a method, rapid construction is possible. Therefore, it is possible to proceed with construction in a short construction period in a place with a lot of traffic.
しかしながら、アンカーフレームを用いた接合工法は、本来的にアンカーフレームの製作費が高いため、橋梁の規模が大きくなると、アンカーフレームの大型化や鋼材の高強度化によって、その製作費用がますます高くなるという問題を生じるとともに、ソケット鋼管を用いたいわゆる二重管工法は、鋼管を二重に用いることから必然的に施工費用が高くなるという問題も生じていた。 However, the joining method using an anchor frame is inherently expensive to produce an anchor frame. Therefore, when the size of a bridge increases, the production cost increases due to the increase in the size of the anchor frame and the strengthening of steel materials. In addition, the so-called double pipe construction method using a socket steel pipe inevitably increases the construction cost because the steel pipe is used twice.
このような状況下、コスト低減可能な工法がさまざまな観点から研究開発されており、例えば橋脚を構成する鋼管の内面にリブを設けるとともに該リブと対向する位置に鉄筋を配筋してコンクリートを打設する工法(特許文献1,2)もあるが、鋼管内面のリブ加工には相応のコストがかかるため、合理的なコストで十分な品質を確保できる接合工法が未だ存在しないのが現状である。
Under these circumstances, cost-reducing construction methods have been researched and developed from various viewpoints.For example, a rib is provided on the inner surface of a steel pipe constituting a bridge pier, and a reinforcing bar is arranged at a position facing the rib to provide concrete. Although there is a construction method (
本発明は、上述した事情を考慮してなされたもので、合理的なコストで十分な品質を確保することが可能な橋脚とフーチングとの接合構造及び方法を提供することを目的とする。 The present invention has been made in consideration of the above-described circumstances, and an object of the present invention is to provide a structure and method for joining a pier and a footing that can ensure sufficient quality at a reasonable cost.
上記目的を達成するため、本発明に係る橋脚とフーチングとの接合構造は請求項1に記載したように、鋼管で構成された橋脚を鉄筋コンクリートで形成されたフーチングに接合してなる橋脚とフーチングとの接合構造において、
In order to achieve the above-mentioned object, the joining structure of a pier and a footing according to the present invention includes a pier and a footing formed by joining a pier composed of a steel pipe to a footing formed of reinforced concrete as described in
前記鋼管の下端と前記フーチングの上面との間に所定の隙間が形成されるように前記鋼管を鉛直姿勢にて前記フーチングの上方に配置するとともに、前記フーチングに一端が埋設定着された鋼管接合用鉄筋と前記鋼管内に充填され前記鋼管接合用鉄筋の他端が埋設定着されるコンクリートとで構成された鉄筋コンクリート体を前記鋼管内に形成してなり、前記鋼管の内面であって該鋼管内に充填されたコンクリートと接触する内面のうち、前記鋼管接合用鉄筋と対向する内面を平滑仕上げとし、前記鋼管接合用鉄筋より上方に位置する内面に突起を設けたものである。 The steel pipe is disposed above the footing in a vertical posture so that a predetermined gap is formed between the lower end of the steel pipe and the upper surface of the footing, and one end of the steel pipe is embedded in the footing. A reinforced concrete body composed of a reinforcing bar and a concrete filled in the steel pipe and the other end of the reinforcing rod for joining the steel pipe is embedded in the steel pipe is formed in the steel pipe, and is an inner surface of the steel pipe and in the steel pipe Of the inner surface in contact with the filled concrete, the inner surface facing the steel pipe joining rebar is made smooth and a protrusion is provided on the inner surface located above the steel pipe joining rebar.
また、本発明に係る橋脚とフーチングとの接合構造は、前記鋼管接合用鉄筋との間で重ね継手を形成する重ね筋を前記突起と対向するようにかつ水平断面位置が前記鋼管接合用鉄筋よりも前記鋼管の中心側となるように前記鋼管内に充填されるコンクリートに埋設したものである。 Moreover, the joining structure of the bridge pier and the footing according to the present invention is such that a lap joint forming a lap joint with the steel pipe joining rebar is opposed to the projection and a horizontal cross-sectional position is more than that of the steel pipe joining rebar. Is embedded in the concrete filled in the steel pipe so as to be on the center side of the steel pipe.
また、本発明に係る橋脚とフーチングとの接合方法は請求項3に記載したように、鋼管で構成された橋脚を鉄筋コンクリートで形成されたフーチングに接合する橋脚とフーチングとの接合方法において、
Further, the method for joining the pier and the footing according to the present invention is as described in
鋼管接合用鉄筋の一端が前記フーチングに埋設定着されるように該フーチングを形成し、前記鋼管の下端と前記フーチングの上面との間に所定の隙間が形成されるようにかつ前記鋼管接合用鉄筋の他端が前記鋼管内に配置されるように該鋼管を鉛直姿勢にて前記フーチングの上方に位置決めし、前記隙間を所定の型枠材で塞ぎ、前記鋼管接合用鉄筋の他端が埋設定着されるように前記鋼管内にコンクリートを充填する各工程からなり、前記鋼管の内面であって該鋼管内に充填されたコンクリートと接触する内面のうち、前記鋼管接合用鉄筋と対向する内面を平滑仕上げとし、前記鋼管接合用鉄筋より上方に位置する内面に突起を設けたものである。 The steel pipe joining rebar is formed so that one end of the steel pipe joining rebar is embedded in the footing, and a predetermined gap is formed between the lower end of the steel pipe and the upper surface of the footing. The steel pipe is positioned above the footing in a vertical posture so that the other end of the steel pipe is disposed in the steel pipe, the gap is closed with a predetermined formwork material, and the other end of the steel pipe joining rebar is embedded. The steel pipe is filled with concrete, and the inner surface of the steel pipe that is in contact with the concrete filled in the steel pipe is smoothed on the inner surface facing the steel pipe joining rebar. A finish is provided, and protrusions are provided on the inner surface located above the steel pipe joining rebar.
また、本発明に係る橋脚とフーチングとの接合方法は、前記鋼管の鉛直荷重を仮受けできるように前記型枠材を構成するとともに、前記鋼管内に充填したコンクリートが硬化した後、前記型枠材を取り外すものである。 The method for joining the pier and the footing according to the present invention is to form the mold material so that the vertical load of the steel pipe can be temporarily received, and after the concrete filled in the steel pipe is hardened, The material is removed.
また、本発明に係る橋脚とフーチングとの接合方法は、前記鋼管接合用鉄筋との間で重ね継手を形成する重ね筋を前記突起と対向するようにかつ水平断面位置が前記鋼管接合用鉄筋よりも前記鋼管の中心側となるように前記鋼管内に充填されるコンクリートに埋設したものである。 Further, the method for joining the pier and the footing according to the present invention is such that a lap joint forming a lap joint between the steel pipe joining rebar is opposed to the projection and a horizontal cross-sectional position is more than that of the steel pipe joining rebar. Is embedded in the concrete filled in the steel pipe so as to be on the center side of the steel pipe.
従来の接合構造(特許文献1,2)は上述したように、フーチングに定着された鉄筋を鋼管内面に形成されたリブと対向するように鋼管内に延設した上、該鋼管内にコンクリートを充填するものである。
As described above, the conventional joint structure (
かかる従来技術によれば、鋼管によるコンクリートの拘束効果を期待できるとともに、コンクリート打設の際の型枠設置や脱型作業を不要とするものであって、それまでのRC橋脚に比べ、きわめて有用な工法であると言える。 According to such conventional technology, the effect of restraining the concrete by the steel pipe can be expected, and the installation of the formwork and the demolding work at the time of placing the concrete are unnecessary, which is extremely useful as compared with the RC piers until then. It can be said that it is a simple construction method.
しかしながら、充填コンクリートによる被りを確保しなければならない関係上、鋼管内面に形成されたリブと対向するように鉄筋を配置するにあたっては、鉄筋の配筋位置を、リブの突設分だけ、鋼管内側に後退させる必要がある。 However, due to the need to ensure covering with filled concrete, when placing reinforcing bars so as to face the ribs formed on the inner surface of the steel pipe, the position of the reinforcing bars should be the same as the rib protrusion. Need to be retreated.
これは、鋼管内の鉄筋及び充填コンクリートを、曲げモーメントに抵抗する鉄筋コンクリート体として考えた場合、水平方向に沿った鉄筋間距離が短くなって曲げ抵抗力が小さくなることを意味する。 This means that when the reinforcing bars and filled concrete in the steel pipe are considered as reinforced concrete bodies that resist bending moments, the distance between the reinforcing bars along the horizontal direction is shortened and the bending resistance is reduced.
本出願人は、かかる点をいかに解決すべきか、研究開発を積み重ねた結果、前記鋼管の下端と前記フーチングの上面との間に所定の隙間が形成されるように前記鋼管を鉛直姿勢にて前記フーチングの上方に配置するとともに、前記フーチングに一端が埋設定着された鋼管接合用鉄筋と前記鋼管内に充填され前記鋼管接合用鉄筋の他端が埋設定着されるコンクリートとで構成された鉄筋コンクリート体を前記鋼管内に形成してなり、前記鋼管の内面であって該鋼管内に充填されたコンクリートと接触する内面のうち、前記鋼管接合用鉄筋と対向する内面を平滑仕上げとし、前記鋼管接合用鉄筋より上方に位置する内面に突起を設けてなる新規な発明をなすに至ったものである。 As a result of accumulating research and development, the present applicant, as a result of accumulating research and development, as described above, the steel pipe in the vertical posture so that a predetermined gap is formed between the lower end of the steel pipe and the upper surface of the footing. A reinforced concrete body, which is arranged above the footing, and which is composed of a steel pipe joining rebar with one end buried in the footing and a concrete filled in the steel pipe and the other end of the steel pipe joining rebar is buried. Of the inner surface of the steel pipe that is formed in the steel pipe and is in contact with the concrete filled in the steel pipe, the inner surface facing the steel pipe joining rebar is made smooth, and the steel pipe joining rebar This has led to a novel invention in which protrusions are provided on the inner surface located further upward.
このようにすれば、鋼管内面に設けられた突起と鉄筋コンクリート体との噛合作用によって、橋脚上方からの圧縮荷重を鉄筋コンクリート体を介してフーチングに伝達させることが可能になるとともに、鋼管接合用鉄筋と対向する内面については突起をなくして平滑仕上げとしたので、鋼管接合用鉄筋を鋼管内面に近づけることが可能となり、水平方向に沿った鉄筋間距離を従来よりも大きくとることが可能となる。 In this way, it is possible to transmit the compressive load from above the pier to the footing through the reinforced concrete body by the meshing action of the protrusion provided on the inner surface of the steel pipe and the reinforced concrete body, and Since the facing inner surfaces are smoothed by eliminating protrusions, the steel pipe joining rebar can be brought closer to the inner surface of the steel pipe, and the distance between the rebars along the horizontal direction can be made larger than before.
本発明が対象とする鋼管は、断面形状を任意とすることが可能であり、例えば円形、角形、多角形等の断面形状が考えられる。また、例えば山間部に橋梁を建設する場合、橋脚が高くなることがあり、その際には、鋼管を溶接等で継ぎ足していくことになる。 The steel pipe targeted by the present invention can have an arbitrary cross-sectional shape, and for example, a cross-sectional shape such as a circle, a square, or a polygon can be considered. For example, when a bridge is constructed in a mountainous area, the pier may become high, and in that case, the steel pipe is added by welding or the like.
橋脚が複数の鋼管で構成される場合、本発明の鋼管を単一の鋼管で構成することができるほか、複数の鋼管で構成することも可能であり、具体的には、内面が平滑仕上げとされた最下段の鋼管と、該最下段の上方に配置され内面に突起が設けられてなる鋼管とで構成することが可能である。また、複数の鋼管で本発明の鋼管を構成する場合、上方に配置された鋼管は、最下段の鋼管の直上に接合された鋼管である必要はなく、いくつかの鋼管が間に介在してもかまわない。 When the pier is composed of a plurality of steel pipes, the steel pipe of the present invention can be composed of a single steel pipe, and can also be composed of a plurality of steel pipes. The lowermost steel pipe and the steel pipe disposed above the lowermost stage and provided with protrusions on the inner surface can be used. In addition, when the steel pipe of the present invention is constituted by a plurality of steel pipes, the steel pipe disposed above does not need to be a steel pipe joined immediately above the lowermost steel pipe, and some steel pipes are interposed therebetween. It doesn't matter.
なお、橋脚を構成する鋼管を鋼殻と称することも多いが、本発明では、便宜上、鋼殻も含める概念として鋼管と呼ぶこととする。 In addition, although the steel pipe which comprises a pier is often called a steel shell, in this invention, it shall call a steel pipe as a concept also including a steel shell for convenience.
フーチングは、鉄筋コンクリートで形成されたものであって、一般的には杭を伴う場合が多いが、本発明においては、フーチングだけで基礎構造が構成されるのか、杭とその頭部に接合されたフーチングとで基礎構造が構成されるのかは問わない。 The footing is made of reinforced concrete and generally accompanied by a pile, but in the present invention, the foundation structure is constituted only by the footing or it is joined to the pile and its head. It does not matter whether the foundation structure is composed of footing.
鋼管接合用鉄筋は、一端がフーチングに埋設定着され、他端が鋼管内に充填形成されたコンクリート内に埋設定着されるものであり、例えば異形鉄筋で構成することができる。 The steel pipe joining rebar is one in which one end is embedded in the footing and the other end is embedded in the concrete filled in the steel pipe, and can be composed of a deformed reinforcing bar, for example.
鋼管内面における平滑仕上げとは、鋼管接合用鉄筋と鋼管内面との離間距離を必要最小限にとどめる、すなわちコンクリートの充填性との関係で必要とされるコンクリート被り厚さだけ鋼管内面から鋼管接合用鉄筋を離間させれば足りるようにすることが目的であって、鋼管接合用鉄筋の断面寸法の例えば1/10程度以下の凹凸まで排除する主旨ではない。 The smooth finish on the inner surface of the steel pipe means that the separation distance between the steel pipe joining rebar and the inner surface of the steel pipe is kept to the minimum necessary. The purpose is to separate the reinforcing bars, and it is not intended to eliminate unevenness of, for example, about 1/10 or less of the cross-sectional dimension of the steel pipe joining reinforcing bars.
一方、鋼管接合用鉄筋より上方に位置する内面に設けられた突起は、鋼管内に充填されたコンクリートとの噛合作用を目的としたものであって、かかる噛合作用によって、橋脚上方からの圧縮荷重をフーチングに伝達させることが可能となるが、鋼管接合用鉄筋は、突起と対面しないため、水平方向に沿った鉄筋間距離が短くなる懸念はない。 On the other hand, the protrusions provided on the inner surface located above the steel pipe joining rebar are for the purpose of meshing with the concrete filled in the steel pipe, and by this meshing action, the compressive load from above the pier However, since the steel pipe joining rebar does not face the protrusion, there is no concern that the distance between the rebars along the horizontal direction will be shortened.
なお、鋼管内面を平滑仕上げとした箇所において充填コンクリートとの間で付着力が発生し、該付着力により、平滑仕上げとした箇所を介して圧縮荷重の一部がフーチングに伝達してもかまわない。 It should be noted that an adhesive force is generated between the steel pipe inner surface and the filled concrete at the location where the finish is smooth, and a part of the compression load may be transmitted to the footing through the location where the finish is smooth. .
鋼管接合用鉄筋は、これを突起と対面させない構成により、最小限の距離まで鋼管内面に近づけることが可能となるものであるが、かかる鋼管接合用鉄筋との間で重ね継手を形成する重ね筋を別途設け、該重ね筋を突起と対向させるようにしてもかまわない。 The steel pipe joining rebar can be brought close to the inner surface of the steel pipe to the minimum distance by a configuration in which the steel pipe joining rebar does not face the protrusion, but a lap joint that forms a lap joint with the steel pipe joining rebar May be provided separately so that the overlapping muscles face the protrusions.
この場合、充填コンクリートによる被りが重ね筋に必要となるため、重ね筋の水平断面位置は、鋼管接合用鉄筋よりも鋼管の中心側となるようにする必要があるが、曲げ抵抗力は、鉄筋間距離が拡がった鋼管接合用鉄筋で十分に確保することが可能であるとともに、重ね筋が鋼管接合用鉄筋及び突起との間で重ね継手を形成することにより、鋼管に作用する引抜き力をフーチングで支持することが可能となる。 In this case, overlaying with filled concrete is required for the lap bars, so the horizontal cross-sectional position of the lap bars must be closer to the center of the steel pipe than the steel pipe joint reinforcing bars. It is possible to sufficiently secure the steel pipe joining rebar with the increased distance between them, and the lap joint forms a lap joint between the steel pipe joining rebar and the protrusion, so that the pulling force acting on the steel pipe is footed. It becomes possible to support with.
本発明に係る橋脚とフーチングとの接合構造を構築するには、まず、鋼管接合用鉄筋の一端がフーチングに埋設定着されるように該フーチングを形成し、次いで、鋼管の下端とフーチングの上面との間に所定の隙間が形成されるようにかつ鋼管接合用鉄筋の他端が鋼管内に配置されるように該鋼管を鉛直姿勢にてフーチングの上方に位置決めし、次いで、隙間を所定の型枠材で塞ぎ、しかる後、鋼管接合用鉄筋の他端が埋設定着されるように、鋼管内にコンクリートを充填すればよい。 In order to construct a joint structure between a pier and a footing according to the present invention, first, the footing is formed so that one end of a steel pipe joining rebar is embedded in the footing, and then the lower end of the steel pipe and the upper surface of the footing The steel pipe is positioned above the footing in a vertical posture so that a predetermined gap is formed between the steel pipe and the other end of the steel pipe joining rebar is disposed in the steel pipe. The steel pipe may be filled with concrete so that the other end of the steel pipe joining rebar is buried and sealed with the frame material.
ここで、鋼管の鉛直荷重を仮受けできるように型枠材を構成すれば、コンクリート充填打設の前における鋼管の仮受けを容易に行うことが可能となる。なお、かかる場合には、鋼管内に充填したコンクリートが硬化した後、型枠材を取り外す。 Here, if the formwork material is configured so that the vertical load of the steel pipe can be temporarily received, it is possible to easily perform the temporary reception of the steel pipe before the concrete filling and placing. In such a case, the mold material is removed after the concrete filled in the steel pipe is cured.
以下、本発明に係る橋脚とフーチングとの接合構造及び方法の実施の形態について、添付図面を参照して説明する。なお、従来技術と実質的に同一の部品等については同一の符号を付してその説明を省略する。 DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of a structure and a method for joining a pier and footing according to the present invention will be described below with reference to the accompanying drawings. Note that components that are substantially the same as those of the prior art are assigned the same reference numerals, and descriptions thereof are omitted.
図1は、本実施形態に係る橋脚とフーチングとの接合構造を示した図である。同図でわかるように、本実施形態に係る橋脚とフーチングとの接合構造1は、鋼管2で構成された橋脚3を鉄筋コンクリートで形成されたフーチング4に接合してなる。
FIG. 1 is a view showing a joint structure between a pier and a footing according to the present embodiment. As can be seen from the figure, the pier and footing
鋼管2の下端とフーチング4の上面との間には、隙間hが形成されるように鋼管2を鉛直姿勢にてフーチング4の上方に配置してある。
Between the lower end of the
フーチング4には、鋼管接合用鉄筋としての異形鉄筋6の一端を埋設定着してあり、該異形鉄筋の他端は、鋼管2内に充填されたコンクリート7に埋設定着してある。
One end of a
異形鉄筋6は、それぞれ直棒状に構成してあり、鋼管2の内面から所定距離dだけ離間した位置にて該内面に沿って複数本配置すればよく、図1(b)に示すように鋼管2が角形鋼管であれば所定ピッチで矩形状に配置すればよいし、円形鋼管であれば円形に配置すればよい。
Each of the deformed reinforcing
ここで、異形鉄筋6は、鋼管2内に充填されたコンクリート7とともに鉄筋コンクリート体8を形成しており、該鉄筋コンクリート体8は後述するように、橋脚3の頭部に水平力が作用したとき、該水平力による鋼管2の回転変形に対して曲げ抵抗し、該水平力をフーチング4に伝達する役目を果たす。
Here, the deformed reinforcing
鋼管2は、その内面のうち、異形鉄筋6と対向する内面9を平滑仕上げとしてあり、異形鉄筋6を最小限距離まで鋼管2の内面に近づけることができるようになっている。
The
一方、鋼管接合用鉄筋6より上方に位置する鋼管2の内面には突起10を設けてあり、充填コンクリート7との噛合作用により、橋脚3からの圧縮荷重を鉄筋コンクリート体8を介してフーチング4に伝達できるようになっている。
On the other hand, a
本実施形態に係る橋脚とフーチングとの接合構造1を構築するには、まず図2に示すように、杭11を地盤(図示せず)に打ち込んだ後、該杭の頭部にフーチング4を形成するが、かかる基礎工事の際には、異形鉄筋6の一端がフーチング4内に埋設定着されるように該フーチングを形成する。
In order to construct the
異形鉄筋6は、上述したように、後工程で立設する鋼管2の内面から所定距離dだけ離間した位置にて該内面に沿って複数本配置されるように、フーチング4内に埋設すればよい。
As described above, if the deformed reinforcing
次に図3に示すように、型枠材12をフーチング4の上面に載置する。型枠材12は、L状断面を有する矩形フレームで構成してあり、内周側に形成された肩部13に鋼管2の下端を載せることにより、該鋼管の下端とフーチング4の上面との間の隙間hを塞ぐとともに、鋼管2の荷重を仮受けすることができるようになっている。
Next, as shown in FIG. 3, the
型枠材12は、次工程で異形鉄筋6の他端が鋼管2内に配置されるよう、異形鉄筋6を取り囲むようにしてフーチング4の上面に取り付けておく。
The
次に、型枠材12の肩部13に鋼管2の下端を載せるようにして、鋼管2をフーチング4の上方に鉛直姿勢で吊り込み、鋼管2を型枠材12で仮受けする。
Next, the lower end of the
次に、鋼管内面に形成された突起10が埋設される高さまで、鋼管2内にコンクリート7を打設充填する。
Next, the
打設したコンクリート7が硬化したならば、最後に型枠材12を撤去する。
When the
このように構築された橋脚とフーチングとの接合構造1においては、図4に示すように、橋脚3上方から圧縮荷重が作用するが、かかる圧縮荷重は、鋼管2内に形成された鉄筋コンクリート体8を介してフーチング4に伝達し、該フーチングによって圧縮荷重が支持される。
In the pier-footing
また、図5に示すように、橋脚3の頭部に水平力Pが右方向に作用する場合を想定すると、鋼管2は該水平力によって時計回りに回転しようとする。
Further, as shown in FIG. 5, assuming that a horizontal force P acts on the head of the
そのため、鉄筋コンクリート体8には、鋼管2からの支圧力が側面に作用するとともに、左側に位置する異形鉄筋6からの引張力Tが左側底面に、右側に位置する異形鉄筋6からの圧縮力C1とフーチング4の右上面からの圧縮力C2が右側底面に作用するが、鉄筋コンクリート体8は、異形鉄筋6及び充填コンクリート7からなるRC部材としてこれらの力に曲げ抵抗し、かくして橋脚3に作用する水平力Pは、鉄筋コンクリート体8を介してフーチング4に伝達し、該フーチングで支持される。
Therefore, in the reinforced
以上説明したように、本実施形態に係る橋脚とフーチングとの接合構造1及び方法によれば、鋼管2の内面に設けられた突起10と鉄筋コンクリート体8との噛合作用によって、橋脚3上方からの圧縮荷重を鉄筋コンクリート体8を介してフーチング4に伝達させることができるとともに、鋼管接合用鉄筋6と対向する鋼管2の内面9については突起をなくして平滑仕上げとしたので、異形鉄筋6を、必要最小限寸法であるコンクリート被り厚さまで鋼管2の内面に近づけることが可能となり、異形鉄筋6,6の水平方向距離である鉄筋間距離を大きくとることができる。
As described above, according to the joining
そのため、鉄筋コンクリート体8の曲げ耐力が大きくなるとともに、異形鉄筋6,6の鉄筋間距離が拡がった分、フーチング4に埋設される異形鉄筋6の定着長をそれほど長くしなくても、十分な曲げ耐力をもたせることが可能となる。
Therefore, the bending strength of the reinforced
本実施形態では特に言及しなかったが、橋脚3が長い場合、鋼管2の上に該鋼管と同様の鋼管を溶接等で順次継ぎ足していくことが可能であり、その場合、内面を平滑仕上げとした鋼管と内面に突起を設けた鋼管とを別々の鋼管で構成することが可能である。
Although not particularly mentioned in the present embodiment, when the
また、本実施形態では、型枠材12に鋼管2の自重を仮受けする機能を持たせたが、鋼管2を別の公知手段で仮受けし、型枠材12は、型枠の機能だけを持たせるようにしてもかまわない。この場合、コンクリート硬化後に型枠材12を撤去するかどうかは任意である。
Further, in this embodiment, the
また、本実施形態では、異形鉄筋6を突起10と対向させないようにすることにより、異形鉄筋6を最小限の距離まで鋼管2の内面に近づけることが可能な構成としたが、図6に示すように、異形鉄筋6との間で重ね継手を形成する重ね筋61を別途設け、該重ね筋を突起10と対向させるようにしてもかまわない。
Moreover, in this embodiment, it was set as the structure which can make the
この場合、充填コンクリート7による被りが重ね筋61に必要となるため、重ね筋61の水平断面位置を異形鉄筋6よりも鋼管2の中心側となるようにする必要があるが、曲げ抵抗力は、鉄筋間距離が拡がった異形鉄筋6,6で十分に確保することが可能であるとともに、重ね筋61が異形鉄筋6及び突起10との間で重ね継手を形成することにより、鋼管2に作用する引抜き力をフーチング4で支持することが可能となる。
In this case, since the covering with the filling
1 橋脚とフーチングとの接合構造
2 鋼管
3 橋脚
4 フーチング
6 異形鉄筋(鋼管接合用鉄筋)
7 充填コンクリート
8 鉄筋コンクリート体
9 鋼管内面
10 突起
12 型枠材
61 重ね筋
1 Joint structure of pier and
7 Filled
Claims (5)
前記鋼管の下端と前記フーチングの上面との間に所定の隙間が形成されるように前記鋼管を鉛直姿勢にて前記フーチングの上方に配置するとともに、前記フーチングに一端が埋設定着された鋼管接合用鉄筋と前記鋼管内に充填され前記鋼管接合用鉄筋の他端が埋設定着されるコンクリートとで構成された鉄筋コンクリート体を前記鋼管内に形成してなり、前記鋼管の内面であって該鋼管内に充填されたコンクリートと接触する内面のうち、前記鋼管接合用鉄筋と対向する内面を平滑仕上げとし、前記鋼管接合用鉄筋より上方に位置する内面に突起を設けたことを特徴とする橋脚とフーチングとの接合構造。 In the joint structure of pier and footing, which is formed by joining a pier composed of steel pipes to a footing formed of reinforced concrete,
The steel pipe is disposed above the footing in a vertical posture so that a predetermined gap is formed between the lower end of the steel pipe and the upper surface of the footing, and one end of the steel pipe is embedded in the footing. A reinforced concrete body composed of a reinforcing bar and a concrete filled in the steel pipe and the other end of the reinforcing rod for joining the steel pipe is embedded in the steel pipe is formed in the steel pipe, and is an inner surface of the steel pipe and in the steel pipe A bridge pier and a footing characterized in that, among the inner surfaces in contact with the filled concrete, the inner surface facing the steel pipe joining rebar has a smooth finish, and a protrusion is provided on the inner surface located above the steel pipe joining rebar. Bonding structure.
鋼管接合用鉄筋の一端が前記フーチングに埋設定着されるように該フーチングを形成し、前記鋼管の下端と前記フーチングの上面との間に所定の隙間が形成されるようにかつ前記鋼管接合用鉄筋の他端が前記鋼管内に配置されるように該鋼管を鉛直姿勢にて前記フーチングの上方に位置決めし、前記隙間を所定の型枠材で塞ぎ、前記鋼管接合用鉄筋の他端が埋設定着されるように前記鋼管内にコンクリートを充填する各工程からなり、前記鋼管の内面であって該鋼管内に充填されたコンクリートと接触する内面のうち、前記鋼管接合用鉄筋と対向する内面を平滑仕上げとし、前記鋼管接合用鉄筋より上方に位置する内面に突起を設けたことを特徴とする橋脚とフーチングとの接合方法。 In the joining method of the pier and footing that joins the pier composed of steel pipes to the footing formed of reinforced concrete,
The steel pipe joining rebar is formed so that one end of the steel pipe joining rebar is embedded in the footing, and a predetermined gap is formed between the lower end of the steel pipe and the upper surface of the footing. The steel pipe is positioned above the footing in a vertical posture so that the other end of the steel pipe is disposed in the steel pipe, the gap is closed with a predetermined formwork material, and the other end of the steel pipe joining rebar is embedded. The steel pipe is filled with concrete, and the inner surface of the steel pipe that is in contact with the concrete filled in the steel pipe is smoothed on the inner surface facing the steel pipe joining rebar. A method for joining a bridge pier and a footing, characterized in that a finish is provided and a protrusion is provided on an inner surface located above the steel pipe joining rebar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007180994A JP4957418B2 (en) | 2007-07-10 | 2007-07-10 | Structure and method for joining pier and footing |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2007180994A JP4957418B2 (en) | 2007-07-10 | 2007-07-10 | Structure and method for joining pier and footing |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2009019356A true JP2009019356A (en) | 2009-01-29 |
JP4957418B2 JP4957418B2 (en) | 2012-06-20 |
Family
ID=40359232
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2007180994A Active JP4957418B2 (en) | 2007-07-10 | 2007-07-10 | Structure and method for joining pier and footing |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4957418B2 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101892627A (en) * | 2010-07-21 | 2010-11-24 | 河海大学 | Environmentally-friendly steel bridge pier damping structure form |
CN104099860A (en) * | 2014-06-20 | 2014-10-15 | 中铁大桥勘测设计院集团有限公司 | Ice breaking body for bridge towers and bridge piers in seasonal freeze-up river and construction method |
CN104631308A (en) * | 2015-03-16 | 2015-05-20 | 南京工业大学 | Reinforced concrete composite pier with strong impact resistance |
CN105421221A (en) * | 2015-11-03 | 2016-03-23 | 苏交科集团股份有限公司 | Prefabricated segmental assembling concrete bridge pier and connection technique thereof |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104612036A (en) * | 2015-01-22 | 2015-05-13 | 宁波大学 | Unbonded post-tensioning prestress concrete-filled double-wall steel pipe prefabricated assembly piers with additional dampers |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS52142839A (en) * | 1976-05-22 | 1977-11-29 | Tatsunogumi Kk | Construction method of pier body of bridge* etc* |
JPS6290403A (en) * | 1985-10-16 | 1987-04-24 | 清水建設株式会社 | Bridge pier |
JPH0913320A (en) * | 1995-06-30 | 1997-01-14 | Ohbayashi Corp | Construction method of bridge pier column and structure thereof |
JPH09209308A (en) * | 1996-01-31 | 1997-08-12 | Ohbayashi Corp | Bridge pier structure |
JP2000314174A (en) * | 1999-04-30 | 2000-11-14 | Ken Tomomitsu | Concrete support producing method |
JP2003253761A (en) * | 2002-03-01 | 2003-09-10 | Kurimoto Ltd | Fiber-reinforced plastics concrete composite structural member |
-
2007
- 2007-07-10 JP JP2007180994A patent/JP4957418B2/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS52142839A (en) * | 1976-05-22 | 1977-11-29 | Tatsunogumi Kk | Construction method of pier body of bridge* etc* |
JPS6290403A (en) * | 1985-10-16 | 1987-04-24 | 清水建設株式会社 | Bridge pier |
JPH0913320A (en) * | 1995-06-30 | 1997-01-14 | Ohbayashi Corp | Construction method of bridge pier column and structure thereof |
JPH09209308A (en) * | 1996-01-31 | 1997-08-12 | Ohbayashi Corp | Bridge pier structure |
JP2000314174A (en) * | 1999-04-30 | 2000-11-14 | Ken Tomomitsu | Concrete support producing method |
JP2003253761A (en) * | 2002-03-01 | 2003-09-10 | Kurimoto Ltd | Fiber-reinforced plastics concrete composite structural member |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101892627A (en) * | 2010-07-21 | 2010-11-24 | 河海大学 | Environmentally-friendly steel bridge pier damping structure form |
CN104099860A (en) * | 2014-06-20 | 2014-10-15 | 中铁大桥勘测设计院集团有限公司 | Ice breaking body for bridge towers and bridge piers in seasonal freeze-up river and construction method |
CN104631308A (en) * | 2015-03-16 | 2015-05-20 | 南京工业大学 | Reinforced concrete composite pier with strong impact resistance |
CN105421221A (en) * | 2015-11-03 | 2016-03-23 | 苏交科集团股份有限公司 | Prefabricated segmental assembling concrete bridge pier and connection technique thereof |
Also Published As
Publication number | Publication date |
---|---|
JP4957418B2 (en) | 2012-06-20 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104120647A (en) | Segmental assembling concrete frame bridge pier system suitable for rapid construction and construction method | |
KR101184654B1 (en) | Method for constructing united joint of tube filled concrete block | |
KR20110103000A (en) | Precast bridge joint structure with composite hollow concrete filled tube and a construction method for the same | |
JP4957418B2 (en) | Structure and method for joining pier and footing | |
JP2008223225A (en) | Column member, ufc-made precast form and earthquake resisting reinforcement method for column member using the same | |
KR101478131B1 (en) | Construction Method of Precast Pier | |
KR20180072968A (en) | Permanent form for pier and construction method using the same | |
KR101166549B1 (en) | Connection structure of Hollow reinforced concrete column with internal steeltube | |
KR101216126B1 (en) | Arch structure construction method using axial and longitudinal connection rebar | |
KR101892073B1 (en) | Composite Structure Rahmen using Steel Pipe and Constructing Method thereof | |
JP5207108B2 (en) | Structure and method for joining pier and footing | |
JP5152689B2 (en) | Structure and method for joining pier and footing | |
KR101458435B1 (en) | Half precast concrete column manufacturing method using saddle-type ties and dual hoops and constructing method using the same | |
CN112030720A (en) | Prefabricated bent cap and pier stud socket type connecting structure and construction method | |
JP5527932B2 (en) | Design method of pier joint structure | |
KR101004747B1 (en) | Pillar construction method by layer-built and frame construction method adapting the same | |
JP2005200928A (en) | Reinforcing structure of columnar construction | |
JP2006316495A (en) | Foundation structure of bridge pier and its construction method | |
KR101219938B1 (en) | Connection structure of Hollow reinforced concrete column with internal steeltube by using coupler | |
KR20080103260A (en) | Reinforcing bar assembly for separate concrete pours and strut system method utilizing the same | |
KR102017822B1 (en) | Earthquake-registant column and beam constructing method using concrete filled tube and pre-assembled rebar cage | |
KR100578641B1 (en) | Steel-Concrete Hybrid Column, Hybrid Structure System Using the Same, and Construction Method Thereof | |
KR102213216B1 (en) | Construction method for precast column structure and precast column structure | |
JP5104080B2 (en) | Structure and method for joining pier and footing | |
KR101576865B1 (en) | Construction method of slab for bridge without support bar using converse T-type beams |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20100608 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20111228 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20120221 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20120305 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20150330 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 Ref document number: 4957418 Country of ref document: JP Free format text: JAPANESE INTERMEDIATE CODE: R150 |