JP2009002803A - Construction method for building nuclear power plant - Google Patents

Construction method for building nuclear power plant Download PDF

Info

Publication number
JP2009002803A
JP2009002803A JP2007164157A JP2007164157A JP2009002803A JP 2009002803 A JP2009002803 A JP 2009002803A JP 2007164157 A JP2007164157 A JP 2007164157A JP 2007164157 A JP2007164157 A JP 2007164157A JP 2009002803 A JP2009002803 A JP 2009002803A
Authority
JP
Japan
Prior art keywords
construction
nuclear power
equipment
piping
work
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2007164157A
Other languages
Japanese (ja)
Inventor
Hiroshi Mizuhashi
浩 水橋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Original Assignee
Toshiba Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp filed Critical Toshiba Corp
Priority to JP2007164157A priority Critical patent/JP2009002803A/en
Publication of JP2009002803A publication Critical patent/JP2009002803A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a construction method for building a nuclear power generation plant which streamlines measurements in the work for installing a relevant item in a normal position during each work, and also performs an efficient engineering work free from any retracements such as the avoidance of the interference with a temporary construction in advance. <P>SOLUTION: In the construction work on the nuclear power generation plant, equipment and piping are displayed in an actual space on the basis of three-dimensional computer-aided design data to install them on the basis of the positions displayed in the actual space. <P>COPYRIGHT: (C)2009,JPO&INPIT

Description

本発明は原子力発電プラントの建設工事における機器気および配管等の設置に関し、バーチャル建設工法を適用することにより、据付け位置の計測等を必要とすることなく設定できるようにする原子力発電プラントの建設工法に関する。   The present invention relates to installation of equipment air and piping in construction work of a nuclear power plant, and by applying a virtual construction method, a construction method of a nuclear power plant that can be set without requiring measurement of an installation position, etc. About.

原子力発電プラントは、鉄筋コンクリート等により構成される原子炉建屋、タービン建屋等を含む大型建造物であり、この建設工事は大きく分けて下記の3段階の工事ステップにより進められる。   A nuclear power plant is a large building including a reactor building, a turbine building, and the like made of reinforced concrete, and this construction work is roughly divided into the following three stages of construction steps.

第1の工事ステップは、建物工事として行われるコンクリート躯体工事およびこれと同時に行われる埋設工事である。この埋設工事には、コンクリートに埋め込まれる機器の基礎ボルト設定作業、埋設配管の設定作業、埋設電線管の設定作業等が含まれる。   The first construction step is a concrete frame work performed as a building work and a buried work performed simultaneously with this. This burial work includes a work for setting foundation bolts for equipment embedded in concrete, a work for setting buried pipes, a work for setting buried conduits, and the like.

第2の工事ステップは、建築躯体工事と平行して行われる機器等の先行搬入作業である。この先行搬入作業は、建物の各フロアにおいて天上部分の施工が行われる前に行われる工事を含むものである。すなわち、天井が完成した後では、そのエリアに搬入できない機器・配管や、先に搬入したほうが作業上効果的である機器・配管等を先行して搬入するものである。   The second construction step is a prior carry-in work of equipment or the like performed in parallel with the building frame construction. This pre-loading work includes construction performed before construction of the top part is performed on each floor of the building. That is, after the ceiling is completed, equipment / pipe that cannot be carried into the area, or equipment / pipe that is more effective in terms of work are carried in first.

第3の工事ステップは、建築の工事が終了した後に行われる機器・配管等を搬入するステップであり、ここでは各フロアにて先入れした機器・配管およびその後搬入する機器・配管の据付工事、電気計装工事が行われ、本格的な工事が開始される。   The third construction step is a step to carry in equipment / piping etc. that is performed after the construction work is completed. Here, installation work of equipment / piping that has been pre-loaded on each floor and equipment / piping to be carried in afterwards, Electrical instrumentation work will be carried out and full-scale construction will begin.

このような建設工法の従来例について、図8〜図11を参照して説明する。   A conventional example of such a construction method will be described with reference to FIGS.

図8は、第1の工事ステップである埋設工事のうち、機器基礎ボルトの埋設工事を示している。コンクリート躯体工事に際しては、配筋21が施工された後に、メーカ側にて機器基礎ボルト22の設定作業が実施される。この設定作業に際しては、正規位置に据付ける必要があることから、建築側の基準墨23を利用し、設定場所をトランシット等の計測機器を使用して、正規位地に機器基礎ボルト架台24に固定している。   FIG. 8 shows an embedment work for equipment foundation bolts among the burial work that is the first work step. At the time of concrete frame construction, after the reinforcement bar 21 is constructed, setting work of the equipment foundation bolts 22 is performed on the maker side. Since this setting work needs to be installed in a normal position, the construction base standard ink 23 is used and the setting location is set to the equipment base bolt mount 24 in the normal position using a measuring instrument such as transit. It is fixed.

図9および図10は、第2のステップである機器等の先行搬入作業を示している。これらの図に示すように、建築に際しては、まず床25のコンクリート打設を行い、壁26の工事が完了した時点で当該エリア内への機器27および配管28の先行搬入を行う。これは当該エリアの天井施工後では、搬入が困難な機器等および先行して搬入した方が効率的である配管等に対して実施されるからである。先行搬入終了後は、当該エリアの天井工事を行うために必要となる足場29の設置作業が行われる。その際、足場との干渉が生じないような位置への機器・配管等の仮置きを行う必要がある。   FIG. 9 and FIG. 10 show a prior carry-in operation for equipment and the like, which is the second step. As shown in these drawings, when building, concrete is first placed on the floor 25, and when the construction of the wall 26 is completed, the equipment 27 and the piping 28 are carried into the area in advance. This is because after the ceiling construction in the area, it is carried out on equipment that is difficult to carry in and piping that is more efficient when carried in advance. After the preceding carry-in is completed, installation work for the scaffold 29 necessary for ceiling work in the area is performed. At that time, it is necessary to temporarily place equipment, piping, etc. at a position where interference with the scaffold does not occur.

図11は、第3のステップである躯体工事完了後の本格工事を示している。このステップでは、各エリア(部屋)により施工の順序は変わるが、概ね次のような流れで作業が行われる。まず、先行搬入した配管28が空中に吊り上げられ、先行搬入した機器27の据付け、配管28工事、架台30工事、電気品31および計装品工事の順に実施される。その殆どの工事において、据付ける位置は予め設計図面によって決められている位置に設置する必要があり、据付け位置の計測作業を都度実施する必要がある。   FIG. 11 shows the full-scale construction after completion of the housing construction, which is the third step. In this step, although the order of construction varies depending on each area (room), the work is generally performed in the following flow. First, the pipe 28 that has been carried in first is lifted in the air, and the installation of the equipment 27 that has been carried in first, the construction of the pipe 28, the construction of the gantry 30, the electrical equipment 31, and the instrumentation work are carried out in this order. In most of the constructions, the installation position needs to be set at a position determined in advance according to the design drawing, and the installation position needs to be measured each time.

以上述べたように、それぞれの工事ステップにおいては、殆どの作業により設置位置の計測が行われたうえでの据付となり、位置決めによる労力を多く費やしている。   As described above, in each construction step, installation is performed after the installation position is measured by most work, and much labor is required for positioning.

なお、従来技術として、例えばトンネル工事において、立体映像を三次元コンピュータ支援設計(3D−CAD)のデータをバーチャル化し、施工支援する技術が知られている(特許文献1参照)。
特許第3653196号公報
As a conventional technique, for example, in tunnel construction, a technique for virtualizing 3D computer-aided design (3D-CAD) data for stereoscopic images and supporting construction (see Patent Document 1) is known.
Japanese Patent No. 3653196

上述した従来の建設工法においては、埋設品の据付け時に図面寸法通りの位置に設定するための計測、先行搬入品に対し、足場との干渉を回避するための仮置き位置の計測を行う必要があり、また本格工事段階においても図面寸法通りの位置へ設定するための計測作業を行う必要がある。   In the conventional construction method described above, it is necessary to measure the temporary placement position to avoid the interference with the scaffolding for the pre-delivered product, and the measurement for setting the position according to the drawing dimensions when installing the buried product. In addition, it is necessary to perform measurement work to set the position as shown in the drawing dimensions even at the full-scale construction stage.

本発明はこのような事情に鑑みてなされたものであり、各作業時における正規位置への当該品の設定作業における計測の合理化を図るとともに、仮設品との事前干渉回避等のような後戻りのない効率的な工事を行える原子力発電プラントの建設工法を提供することを目的とする。   The present invention has been made in view of such circumstances, and aims to rationalize the measurement in the setting operation of the product to the normal position at each work, and to perform a return such as avoiding prior interference with the temporary product. The purpose is to provide a construction method for nuclear power plants that can perform efficient construction.

前記の目的を達成するため、請求項1に係る発明では、原子力発電プラントの建設工事において、機器および配管を、三次元コンピュータ支援設計データに基づいて現実空間に表示させ、この現実空間に表示された位置に基づいて、機器および配管等の据付けを行うことを特徴とする原子力発電プラントの建設工法を提供する。   In order to achieve the above object, in the invention according to claim 1, in the construction of the nuclear power plant, equipment and piping are displayed in the real space based on the three-dimensional computer-aided design data, and are displayed in the real space. A construction method for a nuclear power plant is provided, in which equipment and piping are installed based on the position.

請求項2に係る発明では、原子力発電プラントの建設工事において、機器および配管の完成状態を、三次元コンピュータ支援設計データに基づいて現実空間に表示させ、この現実空間に表示された位置に基づいて、機器および配管等の据付けを行うことを特徴とする原子力発電プラントの建設工法を提供する。   In the invention according to claim 2, in the construction work of the nuclear power plant, the completed state of the equipment and piping is displayed in the real space based on the three-dimensional computer-aided design data, and based on the position displayed in the real space A construction method for a nuclear power plant characterized by installing equipment and piping is provided.

請求項3に係る発明では、原子力発電プラントの建設工事において、建築躯体との関連で、完成状態を現実空間に表示することで、天井部に設置されるデッキプレートの支持部材と配管等の干渉状態を事前に確認することを可能とし、壁等に埋設されている金物のズレの確認、サポート設計等設計へのフィードバックを行い、現地工事を実施することを特徴とする原子力発電プラントの建設工法を提供する。   In the invention according to claim 3, in the construction work of the nuclear power plant, the completed state is displayed in the real space in relation to the building frame, so that the interference between the support member of the deck plate installed on the ceiling and the piping, etc. Construction method for a nuclear power plant, which allows the state to be confirmed in advance, confirms the displacement of hardware embedded in walls, etc., provides feedback to the design such as support design, and implements on-site construction. I will provide a.

請求項4に係る発明では、三次元コンピュータ支援設計データに時間軸を持たせることで、当該エリア内の施工状況を現実空間に表示させ、実際の工事状況と照し合せることで現場施工の進捗状況を確認することを特徴とする原子力発電プラントの建設工法を提供する。   In the invention according to claim 4, by providing a time axis to the three-dimensional computer-aided design data, the construction status in the area is displayed in the real space, and the actual construction status is checked against the progress of the on-site construction. A construction method for a nuclear power plant characterized by checking the situation is provided.

本発明によれば、計測装置等を使用しなくとも据付位置への設置が可能となる。また、仮設品の設置場所を予め本設品と干渉のない位置に設置することで、後戻りのない工事が実施可能となる。また、建築側にて既に施工されている鉄骨および金物の位置と完成状態とを照し合せることで、事前の干渉確認を可能として設計側へのフィードバックを早期に実施可能とすることができる。さらに、現場工事を行いながら実施するフィールド設計を早期に開始し、タイムリーな工事を可能とすることができる。また、実際の工事状況と計画工程と連動する状態表示して照し合せることで、工事進捗の確認を可能とすることができ、完成状態を表示することで当該場所で工事調整を可能とすることができる。   According to the present invention, installation at an installation position is possible without using a measuring device or the like. In addition, by installing the temporary installation location in advance at a position where there is no interference with the main installation, it is possible to carry out construction without returning. Further, by comparing the position of the steel frame and hardware already constructed on the construction side with the completed state, it is possible to confirm the interference in advance and to implement feedback to the design side at an early stage. In addition, field design can be started at an early stage while performing on-site construction, enabling timely construction. In addition, it is possible to check the progress of construction by displaying and checking the actual construction status and the status linked to the planned process, and it is possible to adjust the construction at the location by displaying the completed status. be able to.

以下、本発明に係る原子力発電プラントの建設工法の実施形態について、図面を参照して説明する。   Hereinafter, embodiments of a construction method for a nuclear power plant according to the present invention will be described with reference to the drawings.

[第1実施形態(図1〜図3)]
図1はバーチャル建設工法における現実空間を示す表示イメージ図であり、図2は配管施工前の状態を示すイメージ図である。図3は配管施工後の状態を示すイメージ図である。
[First Embodiment (FIGS. 1 to 3)]
FIG. 1 is a display image diagram showing a real space in the virtual construction method, and FIG. 2 is an image diagram showing a state before pipe construction. FIG. 3 is an image diagram showing a state after the pipe construction.

図1に示すように、本実施形態では、まず現実空間に完成状態の3D−CADデータを表示させる。具体的には、室内に設置される複数の表示配管、すなわち表示配管(A)1、表示配管(B)2、表示配管(C)3、表示配管(D)4、それに表示ポンプ5、表示モータ6、表示架台7および表示計装ラック8がそれぞれ正規の位置に表示される。   As shown in FIG. 1, in the present embodiment, 3D-CAD data in a completed state is first displayed in the real space. Specifically, a plurality of display pipes installed in the room, that is, display pipe (A) 1, display pipe (B) 2, display pipe (C) 3, display pipe (D) 4, display pump 5, and display The motor 6, the display frame 7, and the display instrumentation rack 8 are displayed at their normal positions.

図2および図3は、配管の施工例を示している。これらの図2および図3に示すように、先行搬入されて室内に仮置きされた配管(A)9を吊上げ、表示配管(A)の位置に合わせることで正規位置に設定することが可能となる。図3では配管(A)9が正規位置に設置された状態を示し、表示配管(A)1は配管9と同じ位置に表示されていることになる。   2 and 3 show examples of piping construction. As shown in FIGS. 2 and 3, the pipe (A) 9 that has been previously carried in and temporarily placed in the room is lifted and can be set to the normal position by matching the position of the display pipe (A). Become. FIG. 3 shows a state where the pipe (A) 9 is installed at the regular position, and the display pipe (A) 1 is displayed at the same position as the pipe 9.

[第2実施形態(図4)]
図4は、本発明のバーチャル建設工法に係る第2実施形態を示している。現実空間には、第1実施形態で示したように、3D−CADの完成状態が表示される。現地での工事を行う場合には工事用の仮設備が必要となり、作業場所近傍への配置が必要となる。しかしながら、本設備との干渉が生じた場合には、その都度仮設備を移動することとなる。仮設備として工事用の電源を供給する仮設分電盤10においては、現実空間に完成状態が表示されることで、本設備との干渉のない位置に予め配置することが可能であり、移動等の後戻り作業が発生することを事前に防止することが可能となる。
[Second Embodiment (FIG. 4)]
FIG. 4 shows a second embodiment according to the virtual construction method of the present invention. In the real space, as shown in the first embodiment, the completion state of 3D-CAD is displayed. In the case of construction work on site, temporary equipment for construction is required, and it is necessary to arrange it near the work place. However, if there is interference with this equipment, the temporary equipment will be moved each time. In the temporary distribution board 10 that supplies construction power as temporary equipment, the completed state is displayed in the real space, so that it can be arranged in advance at a position without interference with the equipment. It is possible to prevent in advance the occurrence of the return work.

[第3実施形態(図5)]
図5は本発明のバーチャル建設工法に係る第3実施形態を示している。本実施形態においては、図5に示すように、先行搬入した機器・配管等のあるエリアでは、建築により天井部にデッキプレート11が施設される。このデッキプレート上には、コンクリート12が打設されるが、その加重を支えるためにデッキプレート11下端には鉄骨13が施工される。
[Third Embodiment (FIG. 5)]
FIG. 5 shows a third embodiment according to the virtual construction method of the present invention. In the present embodiment, as shown in FIG. 5, the deck plate 11 is provided on the ceiling by construction in an area where equipment, piping, and the like that are carried in advance are provided. Concrete 12 is placed on the deck plate, and a steel frame 13 is applied to the lower end of the deck plate 11 to support the load.

このような状態となっている当該エリア内の現実空間に3D−CADを表示することで、工事開始前の段階においても鉄骨13と表示配管(E)14との干渉状態が確認可能となり、鉄骨13の干渉部位の切欠き作業事前に実施することが可能となる。   By displaying 3D-CAD in the real space in the area in such a state, the interference state between the steel frame 13 and the display pipe (E) 14 can be confirmed even before the construction starts, and the steel frame It becomes possible to carry out notching work of 13 interference sites in advance.

[第4実施形態(図6)]
図6は、本発明のバーチャル建設工法に係る第4実施形態を示している。本実施形態において、現地工事を進めながら施工設計を行うものとしては、計装配管および露出電線管が挙げられる。本実施形態では、代表的に、計装配管を例として説明する。現実空間に3D−CADにて完成状態を表示することにようり、前述した仮設備と同様に他設備との干渉を回避した計装配管15のルート設計が可能となる。従来では殆どの設備の工事が完了した時点からルート設計等を行っていたが、本実施形態によれば、工事の初期段階より設計が可能となる。
[Fourth Embodiment (FIG. 6)]
FIG. 6 shows a fourth embodiment according to the virtual construction method of the present invention. In the present embodiment, instrumentation piping and exposed electric pipes are examples of performing construction design while proceeding with on-site construction. In the present embodiment, an instrumentation pipe will be described as an example. By displaying the completed state in 3D-CAD in the real space, it becomes possible to design the route of the instrumentation pipe 15 that avoids interference with other equipment as in the case of the temporary equipment described above. Conventionally, route design and the like have been performed from the point of time when most of the facilities are completed. However, according to the present embodiment, the design can be performed from the initial stage of the work.

[第5実施形態(図7)]
図7は、本発明のバーチャル建設工法に係る第5実施形態を示している。本実施形態においては、3D−CADに工事計画工程の時間軸をもたせ、現時点までに完了している部位を現実空間に表示することで、配管(A)9、配管(C)16、配管(D)17、ポンプ18、モータ19、架台20の据付けは完了し、表示配管(B)2が施工されていないことが確認できるようにしている。本実施形態では工事の進捗を把握することが可能であり、また完成状態を現実空間に表示することで、作業場所での工事調整を効率よく行うことが可能となる。
[Fifth Embodiment (FIG. 7)]
FIG. 7 shows a fifth embodiment according to the virtual construction method of the present invention. In this embodiment, the time axis of the construction planning process is given to the 3D-CAD, and the parts that have been completed so far are displayed in the real space, so that the pipe (A) 9, the pipe (C) 16, the pipe ( D) The installation of 17, the pump 18, the motor 19, and the gantry 20 is completed, and it can be confirmed that the display pipe (B) 2 is not constructed. In this embodiment, it is possible to grasp the progress of the construction, and display the completed state in the real space, so that the construction adjustment at the work place can be performed efficiently.

以上説明したように、本発明のバーチャル建設工法においては、請求項1記載の発明では、完成状態が現実空間に表示されることで据付け位置を計測器等を用いずに競ってすることが可能となることから、据付けに係る作業員工数の削減が可能となる。   As described above, in the virtual construction method according to the present invention, in the invention according to claim 1, it is possible to compete for the installation position without using a measuring instrument or the like by displaying the completed state in the real space. Therefore, it is possible to reduce the number of man-hours required for installation.

また、請求項2〜4記載の発明では、完成状態が表示されることから事前に干渉回避が可能となり、設計への反映が早期に実施可能となることから、後戻りのない工事が実施でき現地作業の効率化が図れる。   Further, in the inventions according to claims 2 to 4, since the completion state is displayed, it is possible to avoid interference in advance and the reflection to the design can be carried out at an early stage. Work efficiency can be improved.

最後に請求項5記載の発明では、当日までの施工完了部位が現実空間に表示することが可能となることから、その場での工事進捗の確認が可能となり、尚且つ完成状態を表示させることで当該場所での作業調整が行えることから効率的な工事管理が可能となる。   Finally, in the invention described in claim 5, since the construction completion site up to the day can be displayed in the real space, it is possible to confirm the progress of the construction on the spot and to display the completed state. Since work adjustments can be made at the location, efficient construction management becomes possible.

本発明の実施形態によるバーチャル建設工法における現実空間への表示イメージ図。The display image figure to the real space in the virtual construction method by embodiment of this invention. 本発明の実施形態による配管施工前のイメージ図。The image figure before the piping construction by embodiment of this invention. 本発明の実施形態による配管施工後のイメージ図。The image figure after the piping construction by embodiment of this invention. 本発明の実施形態による仮設物設置イメージ図。The temporary installation installation image figure by embodiment of this invention. 本発明の実施形態による建築構造物との干渉状態表示イメージ図。The interference state display image figure with the building structure by embodiment of this invention. 本発明の実施形態による計装配管施工ルート設計可能イメージ図。The instrumentation piping construction route design possible image figure by embodiment of this invention. 本発明の実施形態による工事進捗状況確認イメージ図。The construction progress confirmation image figure by embodiment of this invention. 従来の機器基礎ボルト設定イメージ図。The conventional equipment foundation bolt setting image figure. 従来の機器・配管の先行搬入イメージ図。A prior image of conventional equipment and piping. 従来の先入エリアの足場設置状態イメージ図。Fig. 3 is a conventional image of a scaffold installation state in a first-in area. 従来の室内の完成状態イメージ図。The image of a completed state in a conventional room.

符号の説明Explanation of symbols

1‥表示配管(A)、2‥表示配管(B)、3‥表示配管(C)、4‥表示配管(D)、5‥表示ポンプ、6‥表示モー、7‥表示架台、8‥表示計装ラック、9‥配管(A)、10‥仮設分電気盤、11‥デッキプレート、12‥コンクリート、13‥鉄骨、14‥表示配管(E)、15‥計装配管、16‥配管(C)、17‥配管(D)、18‥ポンプ、19‥モータ、20‥架台、21‥配筋、22‥機器基礎ボルト、23‥基準墨、24‥機器基礎ボルト架台、25‥床、26‥壁、27‥機器、28‥配管、29‥足場、30‥架台、31‥電気品。   1. Display pipe (A), 2 Display pipe (B), 3 Display pipe (C), 4 Display pipe (D), 5 Display pump, 6 Display mode, 7 Display stand, 8 Display Instrumentation rack, 9 ... Piping (A), 10 ... Temporary distribution board, 11 ... Deck plate, 12 ... Concrete, 13 ... Steel frame, 14 ... Display piping (E), 15 ... Instrumentation piping, 16 ... Piping (C ), 17 ... Piping (D), 18 ... Pump, 19 ... Motor, 20 ... Base, 21 ... Reinforcement, 22 ... Equipment foundation bolt, 23 ... Standard ink, 24 ... Equipment foundation bolt stand, 25 ... Floor, 26 ... Wall, 27 ... equipment, 28 ... piping, 29 ... scaffolding, 30 ... mount, 31 ... electrical equipment.

Claims (4)

原子力発電プラントの建設工事において、機器および配管を、三次元コンピュータ支援設計データに基づいて現実空間に画像表示させ、この現実空間に表示された位置に基づいて、機器および配管等の据付けを行うことを特徴とする原子力発電プラントの建設工法。 In the construction of a nuclear power plant, equipment and piping are displayed as images in real space based on 3D computer-aided design data, and equipment and piping are installed based on the positions displayed in this real space. Construction method of nuclear power plant characterized by 原子力発電プラントの建設工事において、機器および配管の完成状態を、三次元コンピュータ支援設計データに基づいて現実空間に画像表示させ、この現実空間に表示された位置に基づいて、機器および配管等の据付けを行うことを特徴とする原子力発電プラントの建設工法。 In the construction of a nuclear power plant, the completed state of equipment and piping is displayed as an image in real space based on 3D computer-aided design data, and equipment and piping are installed based on the position displayed in this real space. A construction method for a nuclear power plant characterized by 原子力発電プラントの建設工事において、建築躯体との関連で、完成状態を現実空間に表示することで、天井部に設置されるデッキプレートの支持部材と配管等の干渉状態を事前に確認することを可能とし、壁等に埋設されている金物のズレの確認、サポート設計等設計へのフィードバックを行い、現地工事を実施することを特徴とする原子力発電プラントの建設工法。 In the construction of a nuclear power plant, in relation to the building frame, the completed state is displayed in real space, so that the state of interference between the deck plate support member installed on the ceiling and the piping, etc. must be confirmed in advance. A construction method for a nuclear power plant that is possible to confirm the displacement of hardware embedded in walls, etc., provide feedback to design such as support design, and carry out on-site construction. 三次元コンピュータ支援設計データに時間軸を持たせることで、当該エリア内の施工状況を現実空間に表示させ、実際の工事状況と照し合せることで現場施工の進捗状況を確認することを特徴とする原子力発電プラントの建設工法。 By providing a time axis to the 3D computer-aided design data, the construction status in the area is displayed in the real space, and the progress status of on-site construction is confirmed by comparing it with the actual construction status. Construction method for nuclear power plants.
JP2007164157A 2007-06-21 2007-06-21 Construction method for building nuclear power plant Pending JP2009002803A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2007164157A JP2009002803A (en) 2007-06-21 2007-06-21 Construction method for building nuclear power plant

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2007164157A JP2009002803A (en) 2007-06-21 2007-06-21 Construction method for building nuclear power plant

Publications (1)

Publication Number Publication Date
JP2009002803A true JP2009002803A (en) 2009-01-08

Family

ID=40319349

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2007164157A Pending JP2009002803A (en) 2007-06-21 2007-06-21 Construction method for building nuclear power plant

Country Status (1)

Country Link
JP (1) JP2009002803A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017193888A (en) * 2016-04-21 2017-10-26 株式会社東芝 Carrying-in planning system and carrying-in planning method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02127773A (en) * 1988-11-08 1990-05-16 Nippon Atom Ind Group Co Ltd Plant construction process control support system
JPH11118979A (en) * 1997-08-11 1999-04-30 Toshiba Corp Assembling method of plant
JP2002144266A (en) * 2000-11-06 2002-05-21 Toshiba Corp Working system
JP3653196B2 (en) * 1998-06-30 2005-05-25 飛島建設株式会社 Construction support information system using virtual reality.

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02127773A (en) * 1988-11-08 1990-05-16 Nippon Atom Ind Group Co Ltd Plant construction process control support system
JPH11118979A (en) * 1997-08-11 1999-04-30 Toshiba Corp Assembling method of plant
JP3653196B2 (en) * 1998-06-30 2005-05-25 飛島建設株式会社 Construction support information system using virtual reality.
JP2002144266A (en) * 2000-11-06 2002-05-21 Toshiba Corp Working system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017193888A (en) * 2016-04-21 2017-10-26 株式会社東芝 Carrying-in planning system and carrying-in planning method

Similar Documents

Publication Publication Date Title
CN107990052A (en) A kind of pipeline assembled hanger installation method
CN103526954A (en) Support for overweight precision embedded part and construction method thereof
JP2018526656A (en) Mounting system and method for mapping building components
KR20150029512A (en) The horizontal structural frame and the underground construction methods using it
KR102047997B1 (en) Construction method and slab brackets for underground cable tunnel
JP5183606B2 (en) Unit structure of anchor bolt used for foundation construction of equipment and foundation construction method of equipment using it
JP2009002803A (en) Construction method for building nuclear power plant
CN108194702B (en) Method for installing pipeline in narrow pipe hoistway
JP2002266498A (en) Construction planning device of power plant
CN103276840B (en) Nuclear power plant composite floor slab module and construction method thereof
CN105735228A (en) Construction method and installation accuracy control method of rack systems of high-lift rack climbing type ship lift
JP5749620B2 (en) Seismic isolation method for existing buildings
CN205476655U (en) Satisfy installation of extra -high voltage GIS device context with totally closed removal factory building track
JP2007177541A (en) Structure in-situ installation system
JP2008031684A (en) Module structure and building construction method
JP5901281B2 (en) Underwater hole measuring device and underwater reracing method using the device
CN106320186A (en) Positioning system for pre-embedded anchor bar of arch support and construction method
JP6097066B2 (en) Precast block and non-bearing wall structure
JP5916371B2 (en) Underwater plate bending apparatus and underwater reracing method using the apparatus
KR20040076245A (en) Wall structure with method of R.C steel reinforcing ground assembly(assembly plant) the method of estalishment with pulling up
JP2010037790A (en) Mobile scaffold for construction
CN104596488B (en) For the holder device of building construction measurement and control the vertical method of body of wall
JP2020054158A (en) Wiring shelf installation structure
JP2005097929A (en) Building floor structure of nuclear power plant
CN117823715A (en) Modular pipe laying construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20091104

RD04 Notification of resignation of power of attorney

Free format text: JAPANESE INTERMEDIATE CODE: A7424

Effective date: 20100426

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100513

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20100518

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20101005