JPH02127773A - Plant construction process control support system - Google Patents

Plant construction process control support system

Info

Publication number
JPH02127773A
JPH02127773A JP63280442A JP28044288A JPH02127773A JP H02127773 A JPH02127773 A JP H02127773A JP 63280442 A JP63280442 A JP 63280442A JP 28044288 A JP28044288 A JP 28044288A JP H02127773 A JPH02127773 A JP H02127773A
Authority
JP
Japan
Prior art keywords
construction
work
work schedule
process control
schedule
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP63280442A
Other languages
Japanese (ja)
Inventor
Nobuhide Sato
信秀 佐藤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Toshiba Corp
Nippon Atomic Industry Group Co Ltd
Original Assignee
Toshiba Corp
Nippon Atomic Industry Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Toshiba Corp, Nippon Atomic Industry Group Co Ltd filed Critical Toshiba Corp
Priority to JP63280442A priority Critical patent/JPH02127773A/en
Publication of JPH02127773A publication Critical patent/JPH02127773A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E30/00Energy generation of nuclear origin
    • Y02E30/30Nuclear fission reactors

Abstract

PURPOSE:To easily and exactly set a construction work schedule by providing a process control system, which extracts an object to exist in a construction work block and executes the set and correction of the work schedule in the block, and a CAD (Computer Aided Design) system to execute three-dimensional simulation. CONSTITUTION:A process control work station 2 is provided as the process control system and a CAD system 3 is provided. Then, a data base 5 is provided to be connected through a data base control system 4 to the process control work station 2. The object to exist in the arbitrary construction work block is extracted by using the process control system and the standard work schedule is completed. Next, the three-dimensional simulate display of the construction work is executed along the standard work schedule by using the CAD system and the work schedule is corrected by using the process control system. Then, the real work schedule is completed. Thus, a burden is reduced when respective processes are set. Then, the construction work schedule can be easily and exactly set.

Description

【発明の詳細な説明】 〔発明の目的〕 (産業上の利用分野) この発明は、大規模な構造物であり、かつその建設が長
期に亘るようなプラントにおいて、各建設工事区画の作
業スケジュールを好適に管理するプラント建設工程管理
支援システムに関する。
[Detailed Description of the Invention] [Objective of the Invention] (Industrial Application Field) This invention provides a method for determining the work schedule of each construction work section in a plant that is a large-scale structure and whose construction takes a long time. This invention relates to a plant construction process management support system that appropriately manages plant construction process management.

(従来の技術) 現在、多くの建設工程管理用システムが存在し、これら
はスケジュールの入力、確認および調整を支援している
。このような建設工程管理用システムで得られる情報は
、作業名に対応したスケジュール、例えば線引きのスケ
ジュールであり、造ろうとしている物との対応はその作
業名称を通じて得られる抽象的イメージだけである。
BACKGROUND OF THE INVENTION Many construction process management systems currently exist that support the input, confirmation, and adjustment of schedules. The information obtained with such a construction process management system is a schedule corresponding to the work name, such as a line drawing schedule, and the only correspondence with the object to be built is the abstract image obtained through the work name.

一方、計算機利用技術の発達により、計算機を用いた設
計システムである(:、 A D (Computer
Aided Design)システムが盛んに利用され
ている。
On the other hand, with the development of computer utilization technology, design systems using computers (:, A D (Computer
Aided Design) systems are widely used.

このCADシステムでは、構造物を構成する個々の構成
要素に関する情報、例えば個々の構成要素の名称、位置
や形状等がその設計に必要な範囲内で設定されている。
In this CAD system, information regarding each component constituting a structure, such as the name, position, shape, etc. of each component, is set within the range necessary for its design.

そこで得られる情報は、その構成要素がどのような構造
や形態を有しているかという視覚情報である。
The information obtained is visual information about the structure and form of the component.

(発明が解決しようとする課題) 一般に、プラント等の大規模な構造物では、例えば概略
の大工程をどのようにするか、壁や床を何時迄に作るか
、主要なコンポーネントは何時設置するか、各建設工事
区画における配管等は何時設置するか、というように建
設工程を分割して設定している。例えば、主要なコンポ
ーネントの設置については、そのコンポーネントの搬入
経路が確保されていることを確認し、そのコンポーネン
トがその時点適に確保されていることを確認し、これら
の確認の後に具体的な作業手順を考慮して作業日数を算
出し、その時点での作業スペースを確認し、並行して行
なわれる作業間の干渉を確認する。このような確認作業
は机上で検討する必要があるのだが、これらの作業は実
際かなりの負担となっている。
(Problem to be solved by the invention) In general, in large-scale structures such as plants, for example, how to carry out the general process, by what time should walls and floors be built, and when should major components be installed? The construction process is divided and set, such as when to install piping, etc. in each construction work zone. For example, when installing a major component, it is necessary to confirm that the route for transporting the component is secured, that the component is properly secured at that time, and after these checks, the specific work must be carried out. Calculate the number of work days taking into account the procedure, check the work space at that point, and check for interference between tasks being performed in parallel. This kind of confirmation work needs to be done on a desk, but this work actually becomes a considerable burden.

また、一般にこのような大規模な建設工事では多くの資
源が投入されるので、その資源のロスを避けるために1
!設工程管理用システムには工程再調整機能が備えられ
ている。が、この工程再調整機能を備えていても、実質
的には当初のスケジュールを厳守するのが通常である。
In addition, since large-scale construction works such as this generally require a large amount of resources, in order to avoid resource loss,
! The construction process management system is equipped with a process readjustment function. However, even with this process readjustment function, the original schedule is usually strictly adhered to.

この発明は、上記事情を考慮してなされたものであり、
プラント等の大規模な構造物の建設工程を設定するに際
し各工程設定時の負担を軽減でき、建設作業スケジュー
ルを容易かつ確実に設定できるプラント建設工程管理支
援システムを提供することを目的とする。
This invention was made in consideration of the above circumstances,
The purpose of the present invention is to provide a plant construction process management support system that can reduce the burden of setting each process when setting the construction process of a large-scale structure such as a plant, and can easily and reliably set the construction work schedule.

(発明の構成〕 (課題を解決するための手段) この発明は、各種データベースを入力して任意の建設工
事区画に存在する物を抽出し、その建設工事区画におけ
る作業スケジュールを設定し修正する工程管理システム
と、この工程管理システムに接続され、この工程管理シ
ステムで作成された作業スケジュールを三次元的にシミ
ュレートし表示するCADシステムと、を有することを
特徴するものである。
(Structure of the Invention) (Means for Solving the Problems) This invention is a process of inputting various databases, extracting objects existing in an arbitrary construction work zone, and setting and correcting a work schedule for the construction work zone. This system is characterized by having a management system and a CAD system connected to this process management system and simulating and displaying a work schedule created by this process management system in three dimensions.

(作用) したがって、この発明に係るプラント建設工程管理支援
システムによれば、まず、工程管理システムを用いて任
意の建設工事区画に存在する物を抽−出し、それらの物
を据付け・組立てる標準作業スケジュールを完成させる
。次に、CADシステムを用いて、この標準作業スケジ
ュールに沿った建設作業を三次元的にシミュレートし表
示する。
(Operation) Therefore, according to the plant construction process management support system according to the present invention, first, the process management system is used to extract items existing in a given construction work area, and standard work is performed to install and assemble those items. Complete the schedule. Next, a CAD system is used to three-dimensionally simulate and display the construction work in accordance with this standard work schedule.

この三次元的表示結果に基づいて、工程管理システムを
用い上記作業スケジュールを修正し、実際の作業スケジ
ュールを完成する。このようにして物との対応を三次元
的にとりながら、実際の作業スケジュールを支援する。
Based on this three-dimensional display result, the work schedule is corrected using the process control system to complete the actual work schedule. In this way, the actual work schedule is supported while taking three-dimensional correspondence with objects.

(実施例) 以下、この発明の実施例を図面に基づいて説明する。(Example) Embodiments of the present invention will be described below based on the drawings.

第1図はこの発明に係るプラント建設工程管理支援シス
テムの一実施例を示すブロック図である。
FIG. 1 is a block diagram showing an embodiment of a plant construction process management support system according to the present invention.

プラント建設工程管理支援システム1は、工程管理シス
テムとしての工程管理ワークステーション2と、この工
程管理ワークステーション2に接続されたC A D 
(Computer Aided Design )シ
ステム3と、データベース管理システム4を介して工程
管理ワークステーション2に接続されたデータベース5
と、工程管理ワークステーション2およびCADシステ
ム3に接続された表示装置6および入力装置7とを有し
て構成される。表示装置6は例えばCRT (Cath
ord Ray Tube)表示装置であり、また入力
装置7はマウス等のボインティングデイバイス等である
The plant construction process management support system 1 includes a process management workstation 2 as a process management system, and a C A D connected to this process management workstation 2.
(Computer Aided Design) system 3 and a database 5 connected to the process control workstation 2 via a database management system 4.
, a display device 6 and an input device 7 connected to a process management workstation 2 and a CAD system 3. The display device 6 is, for example, a CRT (Cath
The input device 7 is a pointing device such as a mouse or the like.

CADシステム3にはCADデータベースが内蔵され、
データベース管理システム4はこのCADデータベース
にも接続される。データベース5には工程属性データベ
ース、標準工程データベースおよびシーケンスデータベ
ース等が格納される。
CAD System 3 has a built-in CAD database,
A database management system 4 is also connected to this CAD database. The database 5 stores a process attribute database, a standard process database, a sequence database, and the like.

CADデータベースには、プラント等の大規模な建造物
を建設するための各建設工事区画毎に、その建設工事区
画内に存在する壁や機器等の物に関する情報が記憶され
ている。例えば、その物の名称、位置、形状、数量およ
び物M等の情報である。さらに、物の名称は、例えば構
造に注目して整理することにより機器(ポンプ等)、配
管、ダクト等に整理できる。また、その物が属する系統
別に整理することによりxX系ポンプ、X×配管と整理
できる。さらに、物量は、例えば配管ではXXトンとい
ったけである。
The CAD database stores information regarding objects such as walls and equipment existing in each construction work section for constructing a large-scale building such as a plant. For example, the information includes the name, position, shape, quantity, and object M of the object. Further, the names of objects can be organized into equipment (pumps, etc.), piping, ducts, etc. by focusing on structure, for example. Also, by organizing the items according to the system to which they belong, they can be organized into xX system pumps and Xx piping. Furthermore, the amount of material is only XX tons for piping, for example.

データベース5に格納される工程属性データベースには
、上記建設工事区画毎に、その工事区画内にある物の属
性に関する情報が記憶される。この情報として、例えば
その物の名称、工事開始予定日、工事完了予定日および
工事日数に影響を与える材質等である。また、標準工期
データベースには、各建設工事区画毎にその工事区画に
ある物の名称や歩掛は係数および工事制約条件等が記憶
される。歩掛は係数は物量の平均的な作業量であり、経
験的な値である。例えば配管における歩掛は係数は、−
人1日当りXXトンの工事が可能である、といった値で
ある。
The process attribute database stored in the database 5 stores, for each construction work zone, information regarding the attributes of objects within the construction zone. This information includes, for example, the name of the object, the scheduled start date of construction, the scheduled completion date of construction, and the material that affects the number of construction days. In addition, the standard construction period database stores, for each construction work section, the names of objects in the construction section, rate coefficients, construction constraints, and the like. The coefficient of yield is the average amount of work for the material, and is an empirical value. For example, the coefficient of yield in piping is -
This value means that XX tons of construction work can be done per person per day.

シーケンスデータベースは、後述のように、工程管理ワ
ークステーション2が上記各データベースから各建設工
事区画毎に標準作業スケジュールを作成した段階で、入
力され記憶された情報である。
The sequence database is information that is input and stored at the stage when the process management workstation 2 creates a standard work schedule for each construction work section from the above-mentioned respective databases, as will be described later.

この情報の内容は、例えば建設工事区画に存在するもの
の名称およびその物の標準作業スケジュール等である。
The contents of this information include, for example, the names of the objects existing in the construction work zone and the standard work schedule of the objects.

上記各データベースからの情報は、設計者が入力装置7
を操作し、工程管理ワークステーション2を介しデータ
ベース管理システム4を作動させることによって、この
データベース管理システム4の検索機能により検索され
て表示装置6に表示される。
The information from each of the above databases is input by the designer to the input device 7.
By operating the database management system 4 via the process control workstation 2, the search function of the database management system 4 searches for the information and displays it on the display device 6.

さて、工程管理ワークステーション2は、データベース
管理システム4を介して、上記各データベースから任意
の建設工事区画に存在する物等を抽出し、その建設工事
区画における標準作業スケジュールを設定し、この標準
作業スケジュールを修正して実際の作業スケジュールを
設定する機能を有する。
Now, the process control workstation 2 extracts objects existing in a given construction work zone from each of the above databases via the database management system 4, sets a standard work schedule for that construction work zone, and sets the standard work schedule for the construction work zone. It has the ability to modify the schedule and set the actual work schedule.

つまり、工程管理ワークステーション2は、第3図に示
す表形式の作業スケジュール10を作成するに際し、第
2図のステップ1の如く、各建設工事区画内に存在する
物をCADデータベースからシステム名として抽出し列
記する。さらに、工程管理ワークステーション2は、C
ADデータベースから物量としての材料集計値を、標準
工期データベースから歩掛は係数を、工程属性データベ
ースから工事開始日等を抽出し、表形式の作業スケジュ
ール10の各欄に表示する。
In other words, when creating the tabular work schedule 10 shown in FIG. 3, the process management workstation 2 uses the system name of the objects existing in each construction work zone from the CAD database as in step 1 of FIG. Extract and list. Furthermore, the process control workstation 2
The total material value as physical quantity is extracted from the AD database, the rate and coefficient are extracted from the standard construction period database, and the construction start date, etc. are extracted from the process attribute database and displayed in each column of the work schedule 10 in tabular form.

次に、工程管理ワークステーション2は、入力装置7を
用いた設計者の操作に基づいて、表形式の作業スケジュ
ール10の各システムにつき作業量を設定し、投入人数
を設定して、それぞれ表の所定の欄に表示する。そして
、工程管理ワークステーション2は、材料集計値、歩掛
は係数および投入人数から各システムの所要工期を算出
して、表形式の作業スケジュール10中の所定欄に表示
する。ざらに、工程管理ワークステーション2は、この
所要工期に基づき工事完了日を算出して同様に表示する
。こうして、工程管理ワークステーション2は、第2図
のステップ2の如く、各建設工事区画について標準作業
スケジュールを完成する。
Next, the process control workstation 2 sets the amount of work for each system in the tabular work schedule 10 based on the designer's operation using the input device 7, sets the number of inputs, and Display in the specified column. Then, the process control workstation 2 calculates the required construction period for each system from the material total value, the step rate coefficient, and the number of input workers, and displays it in a predetermined column in the work schedule 10 in tabular form. Roughly speaking, the process management workstation 2 calculates the construction completion date based on this required construction period and similarly displays it. In this way, the process control workstation 2 completes the standard work schedule for each construction work section, as in step 2 of FIG.

工程管理ワークステーション2は、この標準作業スケジ
ュールの完成により、データベース5のシーケンスデー
タベースに、各建設工事区画毎にその建設工事区画の名
称、その工事区画にある物の名称およびその物の作業ス
ケジュール(日時等)を入力する。その後、工程管理ワ
ークステーション2は、このシーケンスデータベースに
基づいて、第3図に示すようなパーチャート形式の工程
表11や工数山積み表12を表示装置6に表示させる。
Upon completion of this standard work schedule, the process control workstation 2 stores, for each construction work zone, the name of the construction work zone, the name of the object in the construction zone, and the work schedule of that object ( (date and time, etc.). Thereafter, the process control workstation 2 causes the display device 6 to display a process chart 11 and a man-hour accumulation table 12 in a parchart format as shown in FIG. 3 based on this sequence database.

ここに示す工数山積み表12は、各月毎に要求される投
入人数を棒グラフで示したものである。
The man-hour accumulation table 12 shown here is a bar graph showing the number of people required for each month.

CADシステム3は、設計者が入力装置7を操作するこ
とによってシーケンスデータベースを検索し、このシー
ケンスデータベースで得られた任意の建設工事区画のシ
ステム名を基にしてCADデータベースを検索し、その
システム名に対応する物の形状データを得て建設工事を
三次元的にシミュレートし、工事の進捗状況を視覚イメ
ージ化する(第2図のステップ3)。したがって、例え
ば、日時を指定した場合には、ある時点における工事の
進捗状況を確認でき、ある期間に行なわれる工事を具体
に確認できる。また、任意の建設工程区画を指定したと
きには、その建設工程区画における異なる各システムの
作業状況を時間軸に沿って視覚的に確認でき、各作業間
の空間的干渉を確認できる。
The CAD system 3 searches the sequence database by the designer operating the input device 7, searches the CAD database based on the system name of an arbitrary construction work zone obtained from this sequence database, and searches the CAD system for the system name. The construction work is simulated three-dimensionally by obtaining the shape data of the object corresponding to the object, and the progress of the construction work is visualized (Step 3 in Figure 2). Therefore, for example, when a date and time is specified, the progress of construction work at a certain point in time can be confirmed, and the construction work to be performed during a certain period can be confirmed concretely. Furthermore, when an arbitrary construction process section is specified, the work status of each different system in that construction process section can be visually confirmed along the time axis, and spatial interference between each work can be confirmed.

工程管理ワークステーション2は、CADシステム3に
よって標準作業スケジュールを視覚的に確認した設計者
の操作によって、第2図のステップ4の如く、表形式の
作業スケジュール10に表示された標準作業スケジュー
ルを修正し、実際の作業スケジュールを完成する。例え
ば、標準作業スケジュールにおける作業順序等を入れ換
えて、xxの工事はYYの工事が完了した後に行なう、
というように表10の個々の要素を入れ換え、実際の作
業スケジュールを作成する。
The process control workstation 2 corrects the standard work schedule displayed in the tabular work schedule 10 as shown in step 4 of FIG. 2 through the operations of the designer who visually confirmed the standard work schedule using the CAD system 3. and complete the actual work schedule. For example, by changing the order of work in the standard work schedule, work on XX will be carried out after work on YY is completed.
By replacing the individual elements in Table 10, an actual work schedule is created.

上記実施例によれば、まず、工程管理ワークステーショ
ン2が標準作業スケジュールを作成し、CADシステム
3がこの標準作業スケジュールを三次元的にシミュレー
トし、視覚イメージ化する。
According to the above embodiment, first, the process control workstation 2 creates a standard work schedule, and the CAD system 3 three-dimensionally simulates and visualizes this standard work schedule.

設計者は、三次元的にシミュレートされた標準作業スケ
ジュールの適否を判定して不適当な箇所を修正し、実際
の作業スケジュールを完成する。したがって、建設作業
スケジュール作成時における負担を軽減でき、作業の見
落しを防止できて、建設作業スケジュールを容易かつ確
実に設定できる。
The designer determines the suitability of the three-dimensionally simulated standard work schedule, corrects inappropriate parts, and completes the actual work schedule. Therefore, the burden of creating a construction work schedule can be reduced, work can be prevented from being overlooked, and the construction work schedule can be easily and reliably set.

〔発明の効果〕〔Effect of the invention〕

以上のように、この発明に係るプラント建設工程管理支
援システムによれば、各種データベースを入力して任意
の建設工事区画に存在する物を抽出し、その建設工事区
画における作業スケジュールを設定し修正する工程管理
システムと、この工程管理システムに接続され、この工
程管理システムで作成された作業スケジュールを三次元
的にシミュレートし表示するCADシステムとを有する
ことから、各建設工事区画に存在する物との対応を三次
元的にとりながら、建設作業スケジュールを視覚的に確
認し設定できるので、建設作業スケジュールを容易かつ
確実に設定できる。
As described above, according to the plant construction process management support system according to the present invention, various databases are input, objects existing in a given construction work zone are extracted, and a work schedule for the construction work zone is set and corrected. Since it has a process management system and a CAD system that is connected to this process management system and three-dimensionally simulates and displays the work schedule created by this process management system, it is possible to Since the construction work schedule can be visually confirmed and set while taking correspondence three-dimensionally, the construction work schedule can be set easily and reliably.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はこの発明に係るプラント建設工程管理支援シス
テムの一実施例を示すブロック図、第2図はこの実施例
の動作を示すフローチャート、第3図はこの実施例にお
いて作成された作業スケジュール等を示す図である 1・・・プラント建設工程管理支援システム、2・・・
工程管理ワークステーション、3・・・CADシステム
、5・・・データベース、10・・・表形式の作業スケ
ジュール。
Fig. 1 is a block diagram showing an embodiment of the plant construction process management support system according to the present invention, Fig. 2 is a flowchart showing the operation of this embodiment, and Fig. 3 is a work schedule etc. created in this embodiment. 1...Plant construction process management support system, 2...
Process control workstation, 3...CAD system, 5...Database, 10...Tabular work schedule.

Claims (1)

【特許請求の範囲】[Claims] 各種データベースを入力して任意の建設工事区画に存在
する物を抽出し、その建設工事区画における作業スケジ
ュールを設定し修正する工程管理システムと、この工程
管理システムに接続され、この工程管理システムで作成
された作業スケジュールを三次元的にシミュレートし表
示するCADシステムと、を有することを特徴とするプ
ラント建設工程管理支援システム。
A process management system that inputs various databases, extracts items existing in a given construction work zone, sets and corrects the work schedule for that construction work zone, and a process management system that is connected to this process management system and created using this process management system. 1. A plant construction process management support system comprising: a CAD system that three-dimensionally simulates and displays a completed work schedule.
JP63280442A 1988-11-08 1988-11-08 Plant construction process control support system Pending JPH02127773A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63280442A JPH02127773A (en) 1988-11-08 1988-11-08 Plant construction process control support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63280442A JPH02127773A (en) 1988-11-08 1988-11-08 Plant construction process control support system

Publications (1)

Publication Number Publication Date
JPH02127773A true JPH02127773A (en) 1990-05-16

Family

ID=17625114

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63280442A Pending JPH02127773A (en) 1988-11-08 1988-11-08 Plant construction process control support system

Country Status (1)

Country Link
JP (1) JPH02127773A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002324154A (en) * 2001-04-25 2002-11-08 Ishikawajima Harima Heavy Ind Co Ltd System and method for managing construction work of structure
JP2003064873A (en) * 2001-08-30 2003-03-05 Sumitomo Forestry Co Ltd Construction automatic analysis system
EP1331580A1 (en) * 2000-10-27 2003-07-30 Mitsubishi Denki Kabushiki Kaisha Facility plan support method, server computer of facility plan support system, and client computer of facility plan support system
JP2009002803A (en) * 2007-06-21 2009-01-08 Toshiba Corp Construction method for building nuclear power plant
JP2009076104A (en) * 2008-12-22 2009-04-09 Jgc Corp Construction work management device
CN102881344A (en) * 2012-09-05 2013-01-16 中国核电工程有限公司 Method for allocating distributed control system signals of nuclear power plant

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1331580A1 (en) * 2000-10-27 2003-07-30 Mitsubishi Denki Kabushiki Kaisha Facility plan support method, server computer of facility plan support system, and client computer of facility plan support system
EP1331580A4 (en) * 2000-10-27 2008-03-26 Mitsubishi Electric Corp Facility plan support method, server computer of facility plan support system, and client computer of facility plan support system
JP2002324154A (en) * 2001-04-25 2002-11-08 Ishikawajima Harima Heavy Ind Co Ltd System and method for managing construction work of structure
JP4698875B2 (en) * 2001-04-25 2011-06-08 株式会社アイ・エイチ・アイ マリンユナイテッド Construction work management system for structures
JP2003064873A (en) * 2001-08-30 2003-03-05 Sumitomo Forestry Co Ltd Construction automatic analysis system
JP2009002803A (en) * 2007-06-21 2009-01-08 Toshiba Corp Construction method for building nuclear power plant
JP2009076104A (en) * 2008-12-22 2009-04-09 Jgc Corp Construction work management device
CN102881344A (en) * 2012-09-05 2013-01-16 中国核电工程有限公司 Method for allocating distributed control system signals of nuclear power plant
CN102881344B (en) * 2012-09-05 2015-06-17 中国核电工程有限公司 Method for allocating distributed control system signals of nuclear power plant

Similar Documents

Publication Publication Date Title
Alizadehsalehi et al. BIM/MR-Lean construction project delivery management system
Wang et al. 4D dynamic management for construction planning and resource utilization
Lian et al. Analysing the effects of Lean manufacturing using a value stream mapping-based simulation generator
US8155928B2 (en) Method for generating data of plant construction simulation and system thereof
US20090204463A1 (en) Method, tool, and system for analyzing a project
US20050216111A1 (en) Planning operation management support system, and planning operation management support program
WO2024045615A1 (en) Automatic labeling method and system for pipeline three-dimensional building information modeling
JPH02127773A (en) Plant construction process control support system
Syan Introduction to concurrent engineering
Sly et al. Simulation data exchange (SDX) implementation and use
CN105093959A (en) Medicine production process three-dimensional simulation apparatus and simulation method
JP2002123786A (en) System and method for planning constructing or building process
JP3391056B2 (en) Production schedule planning device
JP2721231B2 (en) Plant construction process management support system
JPH04184602A (en) System and method for preparation of production schedule
CN110555218A (en) Production model update system, apparatus, method, and computer-readable medium
JPH1040272A (en) Center design support method and system
US20230169706A1 (en) Diagram modification device, diagram modification method, and diagram modification program
JPH04205169A (en) Method and device for production planning
Rohrer AutoMod
Sakai et al. Demonstrative verification study for the next generation production model: Application of the advanced Toyota production system
JPH0935103A (en) Device for managing production planning information
JPH06332909A (en) Plan managing system
JP2005534122A (en) Computer-aided control method of production process
JP6576788B2 (en) Plant construction plan support device